Вы находитесь на странице: 1из 1

Submittal

Transmittal

Project:

FAEL KHAIR PROGRAM

Date

Contract No

BD1-0033, PACKAGE-14

Shelter ID

TRANSMITTAL to DDC: Md. Rafiqul Islam, RE

From
: MBPL

Submittal No. MBPL/Pk14


By: Engr. Md. Mahmudul Hasan, CM

Quantity

Reference

Title/Description/Manufacturer

01

HSE Reprort

Submitted for review and approval

All sites of package-14

Resubmission

Spec. Section, Title &


Paragraph/Drawing/Detail Reference

Substitution involved - Substitution request attached

Resubmitted for review and approval

If substitution involved, submission includes point-by-point

Complies with contract requirements

comparative data or preliminary details

Will be available to meet construction schedule

Items included in submission will be ordered

Engineer's review time included in construction schedule

immediately upon receipt of approval

______________________________________________________________________________________________________________
I hereby state that I have personally reviewed this submission and found that it complies with the project specifications.
MBPL Safety Officer's Name__Md. Rafique_________________________ Signature __________________________________
(electronic signatures NOT acceptable)

TRANSMITTAL

To PMC: Construction Manager


From DDC: RE
Other

Attn:
By:

Date Rec'd by PMC/DDC:


Date Trnsmt'd by A/E:

Approved

Provide file copy with corrections identified

Approved as noted

Sepia copies only returned

Not subject to review


No action required

Point-by-point comparative data required

Revise / Resubmit

to complete approval process

Rejected / Resubmit
Approved as noted / Resubmit
Other remarks on above submission:

Submission Incomplete / Resubmit


One copy retained by sender