Академический Документы
Профессиональный Документы
Культура Документы
IMPROVEMENT
WE DECIDED TO LOOK AT THE
REASONS FOR REJECTIONS IN 77 UNITS
100%
DEFECTS 2014-2015
7.00%
6.00%
5.00%
6.29%
6.09%
5.63%
5.43%
5.07%
4.51%
4.72%
4.55%
3.00%
REJEC
TION 2.45%
RATE
2.00%
4.69%
0.00%
4.46%
41913.0 41974.0
42036.0 42095.0 42156.0 42217.0
41883.0 41944.0 42005.0 42064.0 42125.0 42186.0
4.7%
REJECTI
77
ON
RATE
1639
UNITS
INSPECT
ED
100%
99%
95%
89%
80%
50
60%
40
QUANTITY
30
CUMMULATIVE
REJECTION
4.70%
1.00%
70
60
3.68%
4.00%
Goo
d
80
UNITS
REJECTE
D
C UMM%
40%
20
20%
10
0
Rib71
gap
Wrong Mtl
Deep3 CS K
DEFEC TS
S cratches
1
0%
83%
100%
100%
REJECTIONS
LE SECTIONS
97% BY
92%
100%
50
40
QUANTITY
30
20
10
0
64
LE-02
0
4
LE-03
LE-04
LE-05
ASSEMBLY SECTION
90%
80%
70%
60% CUMM%
50%
40%
30%
20%
10%
0%
LE-01
REASON FOR
IMPROVEMENT
THE TEAM THEN REVIEWED THE
REJECTION DATA BY THE OPERATOR
MANUFACTURING THE ASSEMBLY TO
UNDERSTAND IF THE REJECTIONS ARE
CAUSED BY ANY PARTICULAR
OPERATOR. REJECTIONS BY OPERATOR
100%
43%
22%
17
FRI
16
16
15
MON
THU
WED
ASSEMBLY SEC TION
13
TUE
100%
90%
80%
70%
60%
50%
C umm%
40%
30%
20%
10%
0%
25
79%
20
55%
15
QUANTITY
10
29%
5
0
22
20
TOM
JIM
19
16
JOHN
ED
DEFEC TS
100%
90%
80%
70%
60%
50%
C UMM%
40%
30%
20%
10%
0%
FINDINGS
OVER LAST ONE YEAR, 83% OF THE
RIB GAP ISSUES WERE FOUND IN THE
LE-02 SECTION
THEME
REDUCE THE RIB GAP ISSUE IN LE-02
SECTION
CURRENT SITUATION
THE TEAM REVIEWED THE REJECTION
DATA OF 64 LE-02 ASSEMBLIES
97%
NUMBER
OF REJECTIONS
BY RIB#
90% 94%
100%
99% 100%
70
60
80%
50
40
Quantity
30
47%
RIB#
1
60%
C umm%
40%
20
10
64
57
RIB 1
RIB 6
RIB
62
RIB
45
RIBS
RIB 4
RIB 3
20%
0%
RIB#
6
S/B:
S/B: 16.240
16.240
+0/-.005
+0/-.005
MAX:
MAX: 16.240
16.240
MIN:
MIN: 16.210
16.210
RANGE
RANGE OF
OF OOT:
OOT: ..
0030
0030
S/B:
S/B: 10.082
10.082
+0/-.005
+0/-.005
MAX:
MAX: 10.090
10.090
MIN:
MIN: 10.060
10.060
RANGE
RANGE OF
OF OOT:
OOT: ..
0030
0030
Rib#5
Rib#4
Rib#3
Rib#2
Skin
Rib
height
Rib#1
CURRENT SITUATION
TO BETTER UNDERSTAND THE REASONS FOR REJECTION, THE TEAM REVIEWED THE ASSEMBLY
PROCESS OF LE-02 SECTION.
(2)
DRILL
HOLES C/T
MOUNTING
STRAPS
AND RIBS
USING DJ
(1)
LOAD SKIN
AND RIBS ON
TO AF
(3)
DEBURR,
CSK AND
ATTACH THE
RIBS TO THE
SKIN USING
HI-LOKS
(4)
LOCATE
PLENUMS
AND
TRANSFER
DRILL HOLES
TO THE SKIN
(5)
DEBURR,
CSK AND
ATTACH THE
PLENUMS TO
SKIN USING
RIVETS
(6)
FINAL FINISH
AND
INSPECTION
RIB HIEGHT MEASUREMENTS ON RIB #1 AND RIB# 6 WERE TAKEN AT EACH STEP OF THE BUILD
PROCESS FOR TWO CONSECUTIVE UNITS
LE02
S.NO 227
RIB # 1
RIB# 6
LE02 INBD
LE02 OUTBD
LE02
S.NO 228
RIB# 1
RIB# 6
LE02 INBD
LE02 OUTBD
NOMINAL
+0/-.005
16.24
10.082
NOMINAL
+0/-.005
16.24
10.082
16.236
10.080
Delta
(5)
Delta
(1)
from
(3)
Delta Installatio Delta
from Constrai nomina Installatio
from
n of
From
nominal nt in AF
l
n of Hiloks nominal Plenum Nominal
-0.004
16.24
0
16.226
-0.014
16.226
-0.014
-0.002
10.088 0.006
10.067
-0.015
10.069
-0.013
Detail
part
16.239
10.081
Delta
(5)
Delta
(1)
from
(3)
Delta Installatio Delta
from Constrai nomina Installatio
from
n of
From
nominal nt in AF
l
n of Hiloks nominal Plenum Nominal
-0.001
16.237 -0.003
16.216
-0.024
16.217
-0.023
-0.001
10.081 -0.001
10.067
-0.015
10.068
-0.014
Detail
part
MAJOR DEVIATION IN THE RIB HEIGHT IS OBSERVED AFTER THE INSTALLATION OF HILOKS WHICH
ARE USED TO SECURE THE RIB TO THE SKIN.
ANALYSIS
THE TEAM STUDIED THE PROCESS AND BRAINSTORMED POTENTIAL CAUSES FOR RIB CHORDAL
HEIGHT OOT CONDITION.
MAN
MATERI
AL
Different
Mechanics
Working on
Assembly
Design
Lack of
Training
Different shop
practices used
by different
individuals
Tool over
constraint
s the part
Tool
Maintenan
ce Cycle
Tool Design
Tool under
constraint
s the part
MACHINE
METHO
High fastenerD
count at
Inadequate
Skin to Rib
Contact
Fixturing
crown
Excess Drill
Pressure
Applied on
Holes
Type
of
Drill
Point
Fastener
Type and
Hole Size
Tool Improperly
locates Ribs
And Skin
Light
Weight Rib
Design
Tolerance
stack up
Ribs
OOT
Detail Parts
OOT
Plenu
m OOT
Skin
OOT
Fastener
Torque
Sequence
Assembly
Process
Pressure
used
during Drilling
or Fastener
install
Validation of Skin
Contour, And
Tolerance
Validation of
Detail parts
Temperature
Variation
Method Of
Measuring Rib
Deformation
MEASUREMEN
TS
Rib
Chord
Height
OOT
MOTHER
NATURE
ANALYSIS..CONTD
THE TEAM PROPOSED AND CONDUCTED TESTS TO VERIFY PROBABLE ROOT CAUSES.
UPPER
LOWER
MEASUREMENTS WERE TAKEN AT BOTH INBOARD AND OUTBOARD LOCATION OF THE RIB AS
SHOWN FOR ALL THE TESTS
WE ENSURED THAT ALL THE TESTS WERE CONDUCTED BY THE SAME OPERATOR AND THAT ALL
THE MEASUREMENTS WERE TAKEN BY THE SAME INSPECTOR
ANALYSIS..CONTD
TEST 1
TEST WAS CONDUCTED TO MEASURE THE DEFELECTION DURING THE DRILLING AND FASTENER
INSTALLATION PROCESS FOR TWO DIFFERENT ASSEMBLIES. THE MEASUREMENTS WERE TAKEN AT
EACH PROCESS STEP OF DRILLING AND INSTALLING TWO FASTENERS. THE MEASUREMENTS WERE
RECORDED AT EACH STEP.
TEST1 : UNIT 1
DRILLING AND INSTALLATION OF FASTENER
TEST 1: UNIT 2
DRILLING AND INSTALLATION OF FASTENER
16.245
16.245
16.240
16.240
16.235
16.235
MEASUREMENT
16.230
MEASUREMENT
16.230
Crown
16.225
16.225 Crown
Beyond Crown
16.220
1
4
STEP
Outboar
d
Beyond Crown
16.220
1
4
STEP
8
9
Outboard
Inboard
ANALYSIS..CONTD
TEST 2
TEST 2 WAS CONDUCTED ON AN ASSEMBLY TO INSTALL CLEARANCE FIT FASTENERS AT THE CROWN
AREA TO VALIDATE THE EFFECT OF FASTENER FIT IN THE HOLES.
TEST 2
INSTALLATION OF CLEARANCE FASTENERS
16.245
16.240
Tolerance Zone
Outboa
rd
MEASUREMENT
16.235
Crown
Beyond Crown
16.230
1
STEP
ANALYSIS..CONTD
TEST 3
TEST 3 WAS CONDUCTED ON AN ASSEMBLY TO RE-SEQUENCE THE DRILLING AND INSTALLATION OF
FASTENERS TO START FROM CROWN AND MOVE TOWARDS THE LEG AND ALTERNATING FROM UPPER
TO LOWER LEGS
TEST 3
RESEQUENCED INSTALLTION OF FASTENER
16.245
16.240
Outboa
rd
MEASUREMENTS
16.235
Crown
Beyond Crown
16.230
1
STEP
ANALYSIS..CONTD
TEST 4
IN TEST 4, FINITE ELEMENT ANALYSIS WAS CONDUCTED TO DEMONSTRATE LOCATION OF STRESS
CONCENTRATIONS IN THE PRESENT RIB DESIGN USING A SIMPLE LOADING CONDITION. THE TEST WAS
CONDUSCTED TO VALIDATE THE LIGHT WEIGHT DESIGN OF THE RIB
D 0.030
Max Principal
Stress = 2710 psi
Min Principal
Stress 3560 psi
THE TEAM WAS NOW READY TO DEVELOP THE CORRECTIVE ACTIONS FOR THE ROOT CAUSES WHICH
WERE ESTABLISHED BY TEST 1, 2, 3 AND 4
COUNTERMEASURES
COUNTERMEASURE
MATRIX
PROBL
EM
ROOT
CAUSES
COUNTERMEA
USRE
A
DRILLING SEQUENCE
C
RE-DESIGN FOR
CLEARANCE FIT OF
FASTENERS
D
LIGHT WEIGHT RIB
DESIGN
LEGENDS
RE-SEQUENCE THE
DRILLING AND
INSTALLATION OF
FASTENERS
DESIGNED TRANSITION
FIT OF FASTENERS
EFF
.
FEA
S.
Y/N
?
15
20
REQUEST CUSTOMER
TO UPDATE THE HOLE
TOLERANCE
20
REQUEST CUSTOMER
FOR STRENGTHENING
THE RIB LEGS
25
PRACTICAL
METHODS
PRACTICAL
METHODS
LOW
HIGH
COUNTERMEASURES
CONTD
BARRIERS AND
AIDS
BARRIERS
AIDS
CUSTOMERS WILLINGNESS
REDUCED REJECTION
COST
INCREASED CUSTOMER
SATISFACTION
TIME
ENGINEERING MANPOWER
REDUCED REWORK
IMPROVED FLOW
MEET SCHEDULE
RESULTS
TO BE
DETERMINED
STANDARDIZATION
TO BE
DETERMINED