Вы находитесь на странице: 1из 3
Oe sernenyras 183MW Isimba Hydre Power Plant & ad Isimba-Bujagali Interconnection Project 2 as Ena Sete Date: 18" November, 2015 (Our Ret: GWENISMHPP/CONTEIPLIO709 Energy nftatech PVFLTC, For the attention of: Dra Chakravory, Project Manager, Isimba Project Subject: Submission of Integrated EPC Project Implementation shedule RS, Dear Sir, Reference is made to your letter retOS45-PM-GC-CW-168 dated Sep.21,2015 and (0045-PM-SC-CW-174 daled Oct. 19,2015, we hereby reply tothe comments as follows 1. The schedule should be developed with more milestones, activities and sub-actvites. No activity shouldbe longer than 30 days, ‘CWE reply: The same willbe elaborated in the monthly schedule. 2. The engineering section should be linked with activites inthe schedule. Further, this section should be delaled, covering all components of project. Civil, HM and EM

Вам также может понравиться