ELEMENT NO.

1 - WORK BELOW LOWEST FLOOR FINISH

12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

Excavate oversite average 200mm deep commencing


from formation level, get out, part return, fill in and
ram, deposit and spread in making up levels where
directed within the site and remainder load and cart
away to Contractor's own dump

M2

110

3.00

330.00

M3

15.00

120.00

Excavation
A

Excavate commencing from formation level, get


out, part return, fill in and ram, deposit and
spread in making up levels where directed within
the site and remainder load and cart away to
Contractor's own dump :B

Pit for pad footing not exceeding 1.50m deep

=
RM16.00
Lean concrete grade 15 as described
spread and
levelled :-

50mm thick under pad footing

M2

11.50

92.00

Ditto under ground slab

M2

110

11.50

1,265.00

M3

310.00

1,240.00

Vibrated reinforced
described in :-

concrete

Grade

30

as

RM16.00
RM16.00

Pad footing

Column stump

M3

310.00

310.00

150mm Thick ground slab

M2

110

46.50

5,115.00

Mild steel & High tensile reinforcement bar to B.S.


4449 as described in :H

Pad footing

Kg

400

3.20

1,280.00

Column stump

Kg

300

3.20

960.00

Layer of B.R.C. Ref. No A8 and embedded in apron

m2

69

16.00

1,104.00

Sawn formwork as described to:L

Sides of pad footing

M2

24

38.00

912.00

Sides of column stump

M2

15

38.00

570.00

150mm thick to sides of concrete slab

50

4.75

237.50

To Collection

13,535.50

C10/E1/1

ELEMENT NO. 1 - WORK BELOW LOWEST FLOOR FINISH

12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

Damp Proof Membrane


A

Single layer of 0.25mm thick (heavy-duty) polythene


sheet laid under floor bed on top of blinding screed
(measured separately) well lapped of joints and seal
with approved pressure-adhesive tapes (measured nett no allowance for laps)

M2

110

3.00

330.00

Prepare and apply an approved waterproofing


compound as described to wet area in floor slab and
wall, all strictly in accordance with the manufacturer's
instructions

M2

30.00

0.00

M2

110

5.00

550.00

Anti-Termite
C

An approved anti-termite treatment to be executed


strictly in accordance with the manufacturer's
instructions complete with five (5) years warranty

To Collection

880.00

C10/E1/2

ELEMENT NO. 1 - WORK BELOW LOWEST FLOOR FINISH

12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

ELEMENT NO. 1 - WORK BELOW LOWEST

Collection
=
Page C10/E1/1

RM16.00

13,535.50

Page C10/E1/2

880.00

To Summary

14,415.50

C10/E1/3

ELEMENT NO.2 : APRON, PERIMETER DRAIN & RAMP


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)

12-Nov-15

Item

Description

Unit

Quantity

Excavate oversite average 200mm deep commencing


from formation level, get out, part return, fill in and
ram, deposit and spread in making up levels where
directed within the site and remainder load and cart
away to Contractor's own dump

M2

50

3.00

150.00

M3

15.00

120.00

Rate

(RM) Amount

(RM)

Excavate commencing from formation level, get


out, part return, fill in and ram, deposit and
spread in making up levels where directed within
the site and remainder load and cart away to
Contractor's own dump :B

Trench for perimeter drain not exceeding 1.50m deep.


Lean concrete grade 15 as described spread and
levelled :-

50mm thick blinding screed and levelled under apron

M2

50

11.50

575.00

Ditto under ramp

M2

11.50

0.00

Hardcore consisting of hard, dry broken bricks or


stones, spread and levelled, well consolidated,
watered and blinded with sand.
E

150mm thick hardore under apron

M2

50

11.25

562.50

Ditto under ramp

M2

11.25

0.00

Vibrated reinforced
described in :

concrete

Grade

30

as

100mm Thick apron

M2

50

31.00

1,550.00

175mm Thick ramp

M2

54.25

0.00

Kg

125

3.20

400.00

10mm Diameter high tensile rod reinforcement as


starter bar
Steel fabric reinforcement as described well lapped
at joints including notching around all obstructions
(measured nett - no allowance for laps) :-

Layer of B.R.C. Ref. No A8 and embedded in apron.

M2

50

16.00

800.00

Ditto, in ramp

M2

18.00

0.00

To Collection

4,157.50

C10/E2/4

ELEMENT NO.2 : APRON, PERIMETER DRAIN & RAMP


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Description

Unit

Quantity

Rate

12-Nov-15

(RM) Amount

(RM)

Sawn formwork as described to:


A

To edges of apron slab exceeding 200mm but not


=
RM16.00
RM16.00
exceeding 300mm high

50

3.80

190.00

To edges of ramp slab, ditto

3.80

0.00

M2

4.00

0.00

50

65.00

3,250.00

40.00

280.00

No

120.00

120.00

M2

50

4.00

200.00

Damp Proof Membrane


C

Single layer of 0.25mm thick (heavy-duty) polythene


sheet laid under floor bed on top of blinding screed
(measured separately) well lapped of joints and seal
with approved pressure-adhesive tapes (measured nett no allowance for laps)
Perimeter Drain

225mm (internal) Wide half-round precast concrete as


described surface water drain channel including
hoisting, jointing and pointing in cement and sand
(1:3) and laid to falls including all necessary
excavation, 100mm concrete (Grade 15 - 40mm
aggregate) as described base and half brickwall sides
with and including all necessary cement and sand
(1:3) plastering to wall complete, all as per drawing.

Precast Concrete Cover


E

600mm x 250mm wide precast concrete cover slab


Mild Steel Grating

Heavy duty mild steel grating overall size 800mm x


600mm consisting of 75mm x 50mm x 6mm thick
angle framing all around with 50mm x 6mm thick
mild steel flat bar in fill at 40mm centres all welded to
12mm x 50mm mild steel framing including priming
and hoisting to position

Anti-Termite
G

An approved anti-termite treatment to be executed


strictly in accordance with the manufacturer's
instructions complete with five (5) years warranty

To Collection

4,040.00

C10/E2/5

ELEMENT NO.2 : APRON, PERIMETER DRAIN & RAMP


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Description

Unit

Quantity

Rate

12-Nov-15

(RM) Amount

(RM)

ELEMENT NO.2 : APRON AND PERIMETER


DRAIN
Collection
=
Page C10/E2/1

RM16.00

4,157.50

Page C10/E2/2

4,040.00

To Summary

8,197.50

C10/E2/6

ELEMENT NO.3 : FRAME


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description
Vibrated reinforced
described in :-

concrete

Grade

30

Rate

(RM)

Amount
(RM)

Unit

Quantity

M3

310.00

1,550.00

Kg

225

3.20

720.00

Kg

938

3.20

3,001.60

M2

56

38.00

2,128.00

as

Column
Mild steel reinforcement bar to BS 4449 as
described :In column
=

RM16.00

10mm diameter as stirrups.


High tensile reinforcement bar to B.S. 4449 as
described in :-

Column
Sawn formwork as described to:

Sides of column

To Summary

7,399.60

C10/E3/1

ELEMENT NO.4 : UPPER FLOOR


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Description
Vibrated reinforced
described in :-

concrete

Grade

30

12-Nov-15

(RM) Amount

(RM)

46.50

372.00

M2

38.00

304.00

Kg

132

3.20

422.40

11

65.00

715.00

100.00

100.00

Unit

Quantity

M2

Rate

as

150mm thick ditto


Sawn formwork as described to:

To soffit of suspended floor slab including strutting.


High tensile reinforcement bar to B.S. 4449 as
described in :-

10mm Diameter in suspended floor slab.


..
Waterproofing

=
RM16.00
Prepare and apply an approved
waterproofing
compound as described to wet area in upper floor slab
and wall, all strictly in accordance with the
manufacturer's instructions.

M2

Allow for performing ponding test if required by the


S.O. over areas of waterproofed to ensure
watertightness and effectiveness of waterproofing
system used including providing water, pumps,
temporary walling, etc. and making good all defects
and leave the whole in perfect working order .

Item

To Summary
==

1,913.40

RM16.00
RM16.00
RM16.00

C10/E4/2

ELEMENT NO. 5 : ROOF


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

12-Nov-15

Description

Unit

Quantity

Metal decking roof covering of approved brand as


selected by the S.O. with and including all accessories
on a layer of double sided sisalation sheet on chicken
wire mesh (both measured separately) and laid on
purlins to Engineer's detail

M2

183

60.00

An approved ridge/hip capping tiles to match roofing


tiles bedded in jointed in coloured cement and sand
(1:3) mortar as described including cutting and
splayed ends, mitres and intersection

15.00

Ditto, 3-way apex tile

No

25.00

Ditto, end cap

No

20.00

M2

183

35.00

6,405.00

Rate
(RM)

Amount
(RM)

Roof Covering
10,980.00

Roof Trusses
E

'Ajiya' light weight roof trusses or approved equivalent


as selected by S.O. including strut, rods, purlins, bolt,
nut with washer, gusset plate, painting and all
accessories and fittings.
Roof Insulation Work

Layer of approved sisalation (non-tear) double-sided


aluminium foil sisalation fixed to top of steel purlins
with 150mm (minimum) lapped at joints, including
layer of chicken wire mesh all laid strictly in
accordance
with
manufacturer's
instructions
(measured nett - no allowance for laps)

M2

183

8.00

1,464.00

50mm Rockwool insulation (60kg/m3) as described to


laid on rafter well lapped at joints (measured nett - no
allowance for laps)

M2

183

12.00

2,196.00

83

18.00

1,494.00

83

7.00

581.00

Wrot pressure treated timber Grade 'B' as


specified :
H

200mm x 25mm thick fascia board


Prepare and apply one under coat and two
finishing coats of gloss enamel paint as described
on the followings woodworks :

To surface of fascia board exceeding 200mm and not


exceeding 300mm high

RM16.00
RM16.00
To=Collection
=

RM16.00
RM16.00

C10/E5/3

23,120.00

ELEMENT NO. 5 : ROOF


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Description

Unit

Quantity

=
RM16.00
RM16.00
No. 22 gauge galvanised iron sheeting as described:-

12-Nov-15

Rate
(RM)

Amount
(RM)

Flashing; 570mm girth, three times bend, one end


chased into concrete work or brickwall and other end
dressed over roofing including metal paint on all
exposed surfaces

23

38.00

874.00

Valley gutter 900mm girth, 5 times bend, bolt and


fixed under roof tiles

25.00

Flat Roof
Vibrated reinforced
described in :-

concrete

Grade

30

as

100mm thick roof slab

M2

25.00

0.00

450mm high 100 thick R.C wall for roof slab

150.00

0.00

Sawn formwork as described to:


E

RM16.00
To soffit of suspended roof slab=including
strutting.

M2

30.00

0.00

To side of flat roof

3.00

0.00

Kg

2.60

0.00

M2

35.00

0.00

High tensile reinforcement bar to B.S. 4449 as


described in :G

10mm Diameter in suspended floor slab.


..
Waterproofing

=
RM16.00
=
RM16.00
Prepare and apply an approved
waterproofing
compound as described to wet area in upper floor slab
and wall, all strictly in accordance with the
manufacturer's instructions.

To Collection

874.00

C10/E5/4

ELEMENT NO. 5 : ROOF


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Description

Unit

Quantity

12-Nov-15

Rate
(RM)

Amount
(RM)

ELEMENT NO.5 : ROOF


Collection
=
Page C10/E5/1

RM16.00

=
Page C10/E5/2

RM16.00
RM16.00

23,120.00

To Summary

874.00

23,994.00

C10/E5/5

ELEMENT NO.6 : STAIRCASE


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM) Amount

(RM)

Staircase
Vibrated reinforced
described in :-

concrete

Grade

30

as

In Staircase

M3

200.00

400.00

125mm Thick suspended landing slab.

M2

25.00

25.00

RM16.00
High tensile reinforcement =
bar to B.S.
4449 as
described in :-

In staircase
C

12mm Diameter bar

Kg

125

2.60

325.00

10mm Diameter bar

Kg

37

2.60

96.20

Landing slab
E

12mm Diameter bar

Kg

53

2.60

137.80

10mm Diameter bar

Kg

22

2.60

57.20

Sawn formwork as described to:


G

Sloping soffit of staircase

M2

30.00

180.00

Soffit of landing slab

M2

30.00

30.00

Sides of raking open string of staircase 300mm


(extreme) width including cutting to profiles of tread
and riser.

9.00

36.00

Undercut riser exceeding 100mm but not exceeding


200mm high.

15

6.00

90.00

Edge of landing slab ditto

6.00

6.00

To Collection

1,383.20

C10/E6/6

ELEMENT NO.6 : STAIRCASE


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM) Amount

(RM)

Staircase Finishes
Cement and sand (1:6) with and approved
plasticiser as specified.
A

19mm Thick, to sloping soffit of staircase.

M2

12.00

72.00

19mm Thick to soffit of landing slab.

M2

12.00

12.00

19mm Thick to sides of raking open string of staircase


300mm (extreme) wide.

3.60

14.40

19mm Thick to edge of landing slab exceeding


200mm but not exceeding 300mm high.

3.60

3.60

Cement and sand (1:3) backing screed as specified


:E

To receive tiles at riser, 250mm high.

15

12.00

180.00

To receive tiles at tread, 164mm width.

13

2.00

26.00

To receive tiles at landing slab.

M2

3.00

9.00

To receive nosing tiles.

15

14.00

210.00

100mm x 100mm homogeneous tiles or approved


equivalent as described bedded and jointed in
cement and sand (1:3) mortar as described and
pointed in matching coloured cemnet and laid on
screeded bed (measured separately) to required
pattern.
J

To landing slab.

M2

40.00

120.00

To undercut riser, 250mm high.

15

8.00

120.00

To tread, 164mm width.

13

7.00

91.00

Nosing tile 75mm wide x 200mm x 8mm thick.

15

6.00

90.00

Prepare and apply one undercoat and two coat


emulsion paint as specified.
N

On plastered sloping soffit of staircase

M2

7.00

42.00

On plastered soffit of landing slab.

M2

7.00

7.00

On plastered sides of raking open string of staircase


300mm (extreme) wide.

7.00

28.00

On plastered to edge of landing slab exceeding


100mm but not exceeding 200mm high

2.00

2.00

To Collection

1,027.00

C10/E6/7

ELEMENT NO.6 : STAIRCASE


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM) Amount

(RM)

Stainless Steel Handrail


A

Supply and fix 1000mm high stainless


handrailing, consist of balustrading, top
intermediate rail, bottom rail and complete
accessories and finishes, all accordance to
instruction and Architect's drawings.

steel
rail,
with
S.O's

285.00

1,425.00

Supply and fix 1000mm high stainless steel


handrailing with glass, consist of balustrading, top
rail, intermediate rail, bottom rail and complete with
accessories and finishes, all accordance to S.O's
instruction and Architect's drawings.

380.00

1,900.00

To Collection

3,325.00

C10/E6/8

ELEMENT NO.6 : STAIRCASE


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Collection
=
Page C10/E6/1

Unit

Quantity

Rate

(RM) Amount

(RM)

RM16.00

1,383.20

Page C10/E6/2

1,027.00

Page C10/E6/3

3,325.00

To Summary
=

5,735.20

RM16.00
RM16.00

C10/E6/9

ELEMENT NO.7 : EXTERNAL WALL & INTERNAL WALL


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Description

Rate

12-Nov-15

Unit

Quantity

(RM)

Amount

(RM)

No.

9,600

1.80

17,280.00

42

2.50

105.00

133

38.00

5,054.00

BRICKWALL
Brickwork in Special Interlocking Clay Brick all
as per architect's drawings and the manufacturer's
detail
A

115mm Thick brickwall, reinforced with and


including brick reinforcement at every fourth course.

SUNDRIES
Bituminous sheet damp proof course as specified
(measured nett - no allowance made for laps)
B

115mm wide to half brickwall


RC Coping

100mm x 75mm Thick cast in-situ concrete or precast,


grade 25 as described concrete coping including
reinforcement and formwork setting in position,
jointed and pointed in cement mortar (1:3) all as per
detail drawing.

To Summary
=

22,439.00

RM16.00

C10/E7/1

ELEMENT NO.8 : WINDOW AND EXTERNAL DOORS


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM) Amount

(RM)

30.00

180.00

No

380.00

380.00

Double leaf solid decorative timber door overall size


1100mm x 2400mm high with external waterproof as
per architect's drawing

No

1,350.00

1,350.00

Single leaf solid decorative timber door overall size


900mm x 2400mm high with external waterproof as
per architect's drawing

No

1,200.00

2,400.00

No

2,000.00

0.00

No

4,000.00

0.00

EXTERNAL DOOR
Lintol
A

125mm wide x 200mm high cast in-situ concrete or


precast, grade 25 as described lintol including
reinforcement and formwork setting in position, jointed
and pointed in cement mortar (1:3) all as per detail
drawing.
Supply and fix the following timber door complete
with metal frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :-

Single leaves timber flush door overall size 900 mm x


2400 mm high with external waterproof as per
architect's drawing

Supply and fix the following solid timber door


complete with metal frames, painting, ironmongery
and other accessories for the proper installation of
the works all as per architect's drawings and the
manufacturer's detail :C

Supply and fix the following powder coated


aluminium sliding door complete with aluminium
frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :-

A set of aluminium sliding door overall size 1500mm x


2400mm high with 6mm thick clear glass panel (SD1)

A set of aluminium sliding door overall size 3000mm x


2400mm high with 6mm thick clear glass panel (SD2)

To Collection

4,310.00

C10/E8/1

ELEMENT NO.8 : WINDOW AND EXTERNAL DOORS


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

125mm wide x 200mm high cast in-situ concrete or


precast, grade 25 as described lintol including
reinforcement and formwork setting in position, jointed
and pointed in cement mortar (1:3) all as per detail
drawing.

M2

Rate

(RM) Amount

(RM)

24

30.00

720.00

17

380.00

6,460.00

WINDOWS
Lintol
A

Supply, deliver and install the following in powder


coated aluminium frame window glass panel or
approved equivalent with 5mm thick light grey
tinted glass including all frames, transomes,
mullions,
fittings,
locks,
fasteners,
stays,
ironmongery and other accessories for the proper
installation of the works all as per architect's
drawings and manufacturer's detail:B

Casement window of various sizes and panels complete


with light grey tinted glass

To Collection

7,180.00

C10/E8/2

ELEMENT NO.8 : WINDOW AND EXTERNAL DOORS


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM) Amount

(RM)

ELEMENT NO.8 : WINDOW AND EXTERNAL


DOORS
Collection
=
Page C10/E8/1

RM16.00

Page C10/E8/2

7,180.00

To Summary
=

4,310.00

11,490.00

RM16.00
RM16.00

C10/E8/3

ELEMENT NO.9 : INTERNAL DOORS


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

12-Nov-15

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

125mm wide x 200mm high cast in-situ concrete or


precast, grade 25 as described lintol including
reinforcement and formwork setting in position, jointed
and pointed in cement mortar (1:3) all as per detail
drawing.

14

30.00

420.00

No

345.00

1,380.00

No

315.00

630.00

No

1,500.00

0.00

Lintol
A

Supply and fix the following timber door complete


with metal frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :B

Single leaves timber flush door overall size 900 mm x


2400 mm high as per architect's drawing
Single leaves waterproofed timber flush door overall
size 750 mm x 2400 mm high as per architect's drawing

Supply and fix the following powder coated


aluminium folded door complete with aluminium
frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :D

A set of aluminium folded door overall size 750mm x


2100mm high with 6mm thick clear glass panel (FD1)

To Summary
=

2,430.00

RM16.00
RM16.00
C10/E9/1

ELEMENT NO.10 : INTERNAL WALL FINISHES


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

M2

80

23.00

1,840.00

M2

49

19.00

931.00

M2

80

7.00

560.00

M2

49

70.00

3,430.00

Cement and sand (1:6) with and approved


plasticiser as described
A

19mm thick Plainface to walls, column and the like.


Cement and sand (1:3) as described screed to
receive tiles

19mm Thick to receive ceramic wall tiles


=
RM16.00
Prepare and apply one coat alkali
resisting
primer
sealer and two coats of approved emulsion paint

Plastered walls, column and the like


200mm x 200mm glazed ceramic wall tiles or
approved equivalent ; bedded in cement and sand
(1: 3) screed (measured separately) ; jointing in neat
matching coloured cement ; in approved colour,
thickness and pattern

To wall and column

To Summary
=

6,761.00

RM16.00
C10/E10/1

ELEMENT NO.11 : INTERNAL FLOOR FINISHES


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

M2

86

19.00

1,634.00

M2

86

60.00

5,160.00

M2

75.00

Cement and sand (1:3) backing screed as


specified:
A

To received tiles
=
RM16.00
200mm x 200mm non-slip ceramic tiles or
approved equivalent as described bedded and
jointed in cement and sand (1:3) mortar as
described and pointed in matching coloured
cement and laid on screeded bed (measured
separately) to required pattern

To floor
------------------------------Timber strip floor finish or approved equivalent as
described lay and jointed with approved material
all as per architect's drawings and the
manufacturer's detail :-

To Floor

To Summary
=

6,794.00

RM16.00
RM16.00

C10/E11/1

ELEMENT NO.12 INTERNAL CEILING FINISHES


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

M2

28.00

0.00

M2

110

45.00

4,950.00

M2

7.00

0.00

M2

110

7.00

770.00

CEILING FINISHES
Cement and sand (1:6) with and approved
plasticiser as specified :
A

19mm thick to plainface soffit of concrete slab and


beam.
Suspended Gypsum Board

C
D

1200mm x 600mm Suspended gypsum board with


= fixed RM16.00
RM16.00
cornice or approved equivalent and
to
ceiling joist
=
RM16.00
RM16.00
and spacer including all accessories
as per
Architect's
Drawing and manufacturer's detail.

Prepare and apply one coat approved alkali


resisting primer sealer and two coats emulsion paint
as specified.
To soffit of plastered concrete slab and beam.
To soffit of gypsum board ceiling.
=

RM16.00
RM16.00

To Summary

5,720.00

C10/E12/1

ELEMENT NO. 13 : EXTERNAL FINISHES


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

WALL FINISHES
Prepare and apply one coat alkali resisting primer
sealer and two coats of approved weathersheild
paint
A

Plastered walls, column and the like.

M2

80

8.00

640.00

Ditto, to copings and the like.

53

3.00

159.00

M2

24

19.00

456.00

M2

18

80.00

1,440.00

M2

60.00

360.00

1,000.00

FLOOR FINISHES
Cement and sand (1:3) finished with steel trowel as
described :C

To received tiles
300mm x 300mm homogeneous tiles or approved
equivalent as described bedded and jointed in
cement and sand (1:3) mortar as described and
pointed in matching coloured cement and laid on
screeded bed (measured separately) to required
pattern

To floor
200mm x 200mm non-slip ceramic tiles or approved
equivalent as described bedded and jointed in
cement and sand (1:3) mortar as described and
pointed in matching coloured cement and laid on
screeded bed (measured separately) to required
pattern

To floor

Cement and sand (1:3) as described paving


trowelled hard and smooth to
F

25mm thick cement render to apron and floor

M2

50

20.00

50mm thick concrete in print texture

M2

30.00

50mm thick grove line for ramp texture

M2

30.00

CEILING FINISHES
Cement and sand (1:6) with and approved
plasticiser as specified :
J

19mm thick to plainface soffit of concrete slab


=
RM16.00
RM16.00
Asbestos Free Ceiling

M2

15.00

90.00

1200mm x 600mm asbestos free ceiling sheets or


approved equivalent and fixed to ceiling joist and
spacer including all accessories as per Architect's
Drawing and manufacturer's detail.

M2

108

40.00

4,320.00

M2

8.00

48.00

Prepare and apply one coat approved alkali


resisting primer sealer and two coats weathershield
paint as specified.
=
RM16.00
RM16.00

RM16.00

To soffit of concrete slab

To soffit of asbestos ceiling.

M2

108

8.00

864.00

To concrete in print texture

M2

12.00

To Summary
=

9,377.00

RM16.00
RM16.00
C10/E13/1

ELEMENT NO. 14 : BUILDER'S WORK IN CONNECTION


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Rate

12-Nov-15

Description

Unit

Quantity

(RM)

Amount

(RM)

Construct L-shape concrete top, overall size 900mm x


600mm wide x 800mm high concrete (1:2:4-20mm
Aggregate) including formwork, layer of mesh fabric
reinforcement well lapped at joint including support
beam and casting 1 no. sink (measured separately) and
finish with 200mm x 200mm ceramic tiles, 10mm PVC
tile trim edging strip, corner edging piece all as per
detail drawing

No

650.00

0.00

Construct L-shape concrete top, overall size 4200mm x


600mm wide x 800mm high concrete (1:2:4-20mm
Aggregate) including formwork, layer of mesh fabric
reinforcement well lapped at joint including support
beam and finish with 200mm x 200mm ceramic tiles,
10mm PVC tile trim edging strip, corner edging piece
all as per detail drawing

No

3,000.00

3,000.00

Construct concrete top overall size 850mm x 350mm


wide x 250mm high concrete (1:2:4-20mm Aggregate)
ditto, casting 1 no wash hand basin (measured
separately) ditto

No

650.00

1,300.00

1,200.00

1,200.00

Concrete Top
A

Mild Steel Plinth


D

RM16.00

Mild steel plinth for water tank (measured separately)


including waterproofed plywood and anti corrosion
painting and all related works as per Engineer's
drawing

Item

To Summary

5,500.00

C10/E14/2

ELEMENT NO.15 : SANITARY FITTING


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

No.

600.00

1,200.00

No.

420.00

840.00

No.

50.00

100.00

No.

35.00

70.00

No.

25.00

50.00

No.

10

15.00

150.00

No.

30.00

120.00

Supply and fix the following sanitary fittings and


accessories, including jointing and connecting to
services and soil and waste pipes and making good
all work disturbed
Pedestal water closet
A

Approved equivalent Low level Pedestal water closet


comprising of water closet tank and water cisten 'P' or
'S' trap and white plastic hinged seat cover and jointed
up and plugging and screwing water closet tank to tile
concrete floor including working or making good floor
and wall tiling around.

Wash hand basin


B

Approved equivalent jointless cultured marble


countertop wash hand basin bowl complete with
bright chrome plated pillar tap, 32mm dia. Plastic
bottle trap and fixed counter with an approved bracket
to all around.
Toilet Roll

Approved equivalent vitreous china semi recessed


toilet roll holder, plugged and screwed to tiled
brickwall including working or making good wall
tiling around.
Soap Holder

Approved equivalent vitreous china soap holder.


Hand Spray Bidet

=
RM16.00
Approved equivalent hand spray controlled complete
with 1200mm flexible hose with hook handle
including jointing to galvanised mild steel tubing

Water Tab
F

Approved equivalent water tab complete with all


jointing
Floor Trap

150mm x 150mm stainless steel cover to floor trap


with 100mm diameter openable stainless steel grating
including connecting to pipes and setting in concrete
floor and making good tiling works.

RM16.00

To Collection

2,530.00

C10/E15/3

ELEMENT NO.15 : SANITARY FITTING


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

No.

70.00

140.00

No.

35.00

70.00

No.

450.00

450.00

Supply and fix the following sanitary fittings and


= and connecting
RM16.00 to
accessories, including jointing
services and soil and waste pipes and making good
all work disturbed (Cont'd)
Mirror
A

600mm x 450mm x 6mm Thick mirror with and


including 6mm Thick water proofed plywood backing
fix to 37.70 mm x 19mm aluminium frame edging all
around and plugged and screwed mirror with
chromium plated dome headed screws to tile wall.
Shower

Approved equivalent shower rose with arm and wall


flange and fixing to wall and making good all
connection.
Sink

An approved
double bowl
chrome plated
trap and fixed
around.

equivalent jointless aluminium sink


double drainer complete with bright
pillar tap, 32mm diameter plastic bottle
counter with an approved bracket to all

Testing
D

RM16.00
On completion of the Sanitary= Installation,
test and
commision all fittings for water tightness and make
good all defects, re-test and leave whole in perfect
working order to the satisfaction of the S.O. and
Authorities

Item

To Collection

500.00

1,160.00

C10/E15/4

ELEMENT NO.15 : SANITARY FITTING


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

ELEMENT NO.16 : SANITARY FITTINGS

Collection
Page C10/E16/1

2,530.00

Page C10/E16/2

1,160.00

To Summary

3,690.00

C10/E15/5

ELEMENT NO. 16 : BUILT-IN FURNITURE


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

12-Nov-15

Description

Unit

Quantity

Rate

(RM)

Amount

(RM)

To supply and install low cabinet overall size 4500mm


x 600mm x 780mm high, all as per Architectural's
drawing.

No

1,200.00

0.00

Ditto, overall size 7850mm x 600mm x 780mm high,


all as per Architectural's drawing.

No

2,500.00

0.00

Low Cabinet

Wardrobe
C

To supply and install wardrobe overall size 1800mm x


600mm x 2100mm high, all as per Architectural's
drawing.

No

900.00

0.00

Ditto, overall size 2400mm x 600mm x 2100mm high,


all as per Architectural's drawing.

No

1,200.00

0.00

Ditto, overall size 2700mm x 600mm x 2100mm high,


all as per Architectural's drawing.

No

1,400.00

0.00

No

600.00

0.00

SHOE'S RACK
F

To supply and install shoe's rack overall size 2200mm x


450mm x 2100mm high, all as per Architectural's
drawing.

To Summary
=

0.00

RM16.00

C10/E16/6

ELEMENT NO.17 : INTERNAL SANITARY SERVICES


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Qty.

Rate (RM)

Amount (RM)

a) 150mm dia. UPVC soil underground sewer line

22

25.00

550.00

a) 100mm dia. UPVC soil underground and stack

34

20.00

680.00

b) 75mm dia. UPVC waste underground and vent

15

18.00

270.00

c) 50mm dia. UPVC Pipe

10

15.00

150.00

All Provisional Quantites


A

UPVC Waste, Soil and Vent Pipe to BS4515, BS5255


& BS4660 including all joints, bends, tees, branches,
expansion joints, fittings, approved type bats holders,
etc as shown in the drawings:-

UPVC floor gully trap, 110 x 20 extension grating


collar, 82 x 50 concentric reducer to be connected to
50mm dia. UPVC 'P' trap, 100mm square frame
including setting on and surrounding with concrete
(Grade 30) as described.

Nos.

150.00

600.00

Gully Trap at Ground Floor of deep sealed coated cast


iron type with outlet dimeter to suit c/w all necessary
extension piece and cast iron hinged grating gully to be
bendded and surrounded with plain concrete (Grade
30), 100mm dia. waste pipe with gasket of tar.

Nos.

200.00

200.00

600mm x 600mm x 900mm (average) deep house


manhole constructed of 115mm thick clay bricks
jointed and pointed in cement and sand (1:3) mortar as
described with and including excavations, formworks,
grade 25 concrete bedding, layer of BRC A8, 50mm
grade 15 concrete blinding and all necessary
rendering, plastering etc. all as per details.

No

500.00

3,000.00

To Summary

5,450.00

C10/E17/7

ELEMENT NO.18 : INTERNAL COLD WATER SERVICES


12-Nov-15

CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)


Item

Description

Unit

Qty.

Rate (RM)

Amount (RM)

Nos.

400.00

800.00

15mm dia. ABS PN15 Pipe (internal distribution)

Meter

13

35.00

455.00

ii) 20mm dia. ABS PN15 Pipe (internal distribution)

Meter

22

40.00

880.00

iii) 25mm dia. ABS PN15 Pipe (internal distribution)

Meter

18

55.00

990.00

iv) 25mm dia. Gate Valve

Nos.

45.00

225.00

20mm dia. water meter for Banglo unit.

Lot

50.00

50.00

20mm dia. lockable valve for water meter.

No.

50.00

50.00

20mm dia. Gate Valve for water meter

No.

50.00

50.00

25mm dia. Stainless Steel 304 (Sch 40) stand pipe for
water meter c/w all necessary fittings.

Meter

150.00

450.00

25mm dia. ABS PN15 Underground Pipe tapping from


external recticulation mains water meter and from water
meter to water tank at celing roof c/w all necessary
fittings.

Meter

20

45.00

900.00

25mm dia. 90 deg. Elbow

Nos.

12

50.00

600.00

25mm dia. Tee

Nos.

80.00

240.00

All Provisional Quantites


A

SIRIM approved type (MS 1225:1991) HDPE Water


Storage tank c/w inlet/outlet opening, level indicator,
float valve, manhole, air vent, drain/overflow piping c/w
elevated structure support and all necessary accessories:
i) 900 Litres (200 gals)

ABS (Acrylonitrile Butadiene Styrene) PN15 to MS 1419:


Part 1: 1997, MS 1058: Part 2: 2002, AS3518: Part 1:
1988 c/w fittings, bends, supports, brackets, tees, valves
and all necessary accessories from water tank distribute
to toilet:
i)

To Summary

5,690.00

C10/E18/8

ELEMENT NO.19 : EXTERNAL WORKS


CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

Description

12-Nov-15

Unit

Qty.

Rate (RM)

Amount (RM)

Trim, level and grade horizontal or sloping surface of


ground to receive turfing (measured separately) and
remove all surplus excavated materials off site to
Contractor's own dumping area

M2

4.00

0.00

Spot turfing including 50mm Thick bed of black earth as


specified, on flat ground.

M2

5.00

0.00

380.00

0.00

0.00

0.00

All Provisional Quantities


Turfing
A

Fencing and Gates


Special Interlocking Clay Brick all as per architect's
drawings and the manufacturer's detail
C

1500mm High overall fencing including all necessary


column, excavation, formwork and disposal of surplus
excavated material complete.
Mild Steel Gates

Decorative fencing to main entrance as specified in


Architect Drawings.

Item

To Summary

0.00

C10/E19/9

SUMMARY
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS)
Item

12-Nov-15

Description

Amount

(RM)

SUMMARY
ELEMENT NO. 1 - WORK BELOW LOWEST FLOOR FINISH

Page C10/E1/3

14,415.50

ELEMENT NO. 2 - APRON AND PERIMETER DRAIN

Page C10/E2/3

8,197.50

ELEMENT NO. 3 - FRAME

Page C10/E3/1

7,399.60

ELEMENT NO. 4 - UPPER FLOOR

Page C10/E4/1

1,913.40

ELEMENT NO. 5 - ROOF

Page C10/E5/3

23,994.00

ELEMENT NO. 6 - STAIRCASE

Page C10/E6/4

5,735.20

ELEMENT NO. 7 - EXTERNAL WALL & INTERNAL WALL

Page C10/E7/1

22,439.00

ELEMENT NO. 8 - WINDOW AND EXTERNAL DOOR

Page C10/E8/3

11,490.00

ELEMENT NO. 9 - INTERNAL DOOR

Page C10/E9/1

2,430.00

ELEMENT NO. 10 - INTERNAL WALL FINISHES

Page C10/E10/1

6,761.00

ELEMENT NO. 11 - INTERNAL FLOOR FINISHES

Page C10/E11/1

6,794.00

ELEMENT NO. 12 - INTERNAL CEILING FINISHES

Page C10/E12/1

5,720.00

ELEMENT NO. 13 - EXTERNAL FINISHES


=
RM16.00

Page C10/E13/3

9,377.00

ELEMENT NO. 14 - BUILDER'S WORK IN CONNECTION

Page C10/E14/1

5,500.00

ELEMENT NO. 15 - SANITARY FITTINGS

Page C10/E15/3

3,690.00

ELEMENT NO. 16 - BUILT-IN FURNITURE

Page C10/E16/1

ELEMENT NO. 17 - INTERNAL SANITARY SERVICES

Page C10/E17/1

5,450.00

ELEMENT NO. 18 - INTERNAL COLD WATER SERVICES

Page C10/E18/1

5,690.00

ELEMENT NO. 19 - EXTERNAL WORKS

Page C10/E19/1

ELEMENT NO. 20 - ELECTRICAL WORKS (ALLOWANCE)

Total to Summary Of Building Works

C10/Summ

8,500.00

155,496.20