Вы находитесь на странице: 1из 38

TRACTION POWER SYSTEM

SIMULATION PRELIMINARY
REPORT
OCTOBER 31, 2013 REV: 4

2012.01.06.TP.PE.11.TPSSStudy Report-04

Traction Power System Simulation Report

Revision: 4

Revision History

Revision

Date

Description

Draft

2/3/2012

Initial Issue for PMC Review

3/30/2012

Revised per PMC review comments dated 3/7/12.

4/10/2012

6/14/2013

Changed report title to Preliminary Report; Misc minor


editorial changes.
Updated study report with revised track alignment data and
substation locations
Baseline condition AW3 load at 5 minute headway;

10/31/13

Add recovery operation with one track at AW4 load at 3


minute headway for four consecutive trains;
Q09 TPS location at 508+50

Change Log and Comments


Section

Description of Change/Question Answered

Name

Date

1.2

Added descriptions on how the 18 substations were


determined.

JGY

3/30/12

3.6

JGY

3/30/12

Misc

Added OCS conductor allowable ampacity for


reference.
Misc. minor editorial changes

JGY

3/30/12

Misc

Misc minor editorial changes

JGY

4/10/12

October 31, 2013


Page 1

Traction Power System Simulation Report

Revision: 4

Table of Contents
1

Executive Summary .......................................................................................................... 5


1.1

Objectives .....................................................................................................................................................5

1.2

Basic requirements .......................................................................................................................................5

1.3

List of substations.........................................................................................................................................6

1.4
Summary of findings ....................................................................................................................................6
1.4.1 Train voltages ...........................................................................................................................................6
1.4.2 Maximum rail potential ...........................................................................................................................7
1.4.3 Ratios of rectifier load RMS current/rating .............................................................................................7
1.5

Conclusions ...................................................................................................................................................7

Introduction ....................................................................................................................... 8
2.1
Main parameters..........................................................................................................................................8
2.1.1 Running rails ............................................................................................................................................8
2.1.2 Substation rectifier units .........................................................................................................................8
2.1.3 Train consists and operational headway .................................................................................................8
2.1.4 Train stops ...............................................................................................................................................9
2.2
Methodology ................................................................................................................................................9
2.2.1 Simulation runs ........................................................................................................................................9
2.2.2 Train dispatching....................................................................................................................................10

Simulation Results ...........................................................................................................11


3.1

Substation power demands (average kW) .................................................................................................11

3.2

Rectifier load current (RMS amps)/ rating ratios .......................................................................................12

3.3

Substation feeder current (RMS amps) ......................................................................................................13

3.4
Train voltage plots......................................................................................................................................16
3.4.1 Normal operations .................................................................................................................................17
3.4.2 Contingency operations .........................................................................................................................18
3.4.3 Recovery operations ..............................................................................................................................19
3.5
Rail potential plot .......................................................................................................................................20
3.5.1 Normal operations .................................................................................................................................21
3.5.2 Contingency operations .........................................................................................................................22
3.5.3 Recovery operations ..............................................................................................................................23
3.6
OCS current plot (RMS amps) .....................................................................................................................24
3.6.1 Normal operations .................................................................................................................................25
3.6.2 Contingency operations .........................................................................................................................26
3.6.3 Recovery operations ..............................................................................................................................27

Appendix A List of Reference Document ....................................................................28


October 31, 2013
Page 2

Traction Power System Simulation Report


5

Revision: 4

Appendix B List of Simulation Data .............................................................................29


5.1

Track Alignment Data ................................................................................................................................29

5.2
Traction Power System Data ......................................................................................................................31
5.2.1 OCS Segments ........................................................................................................................................31
5.2.2 Locations of track cross-bonds ..............................................................................................................31
5.2.3 Conductor Resistances ...........................................................................................................................33
5.2.4 Single Line Diagram................................................................................................................................33
5.2.5 Voltage Levels ........................................................................................................................................35
5.2.6 Rectifier voltage regulation ...................................................................................................................35
5.2.7 Feeder cables and track cross-bonds .....................................................................................................35
5.3
Vehicle Data ...............................................................................................................................................36
5.3.1 Vehicle Weight .......................................................................................................................................36
5.3.2 Power conversion efficiency ..................................................................................................................36
5.3.3 Auxiliary Load.........................................................................................................................................36
5.3.4 Maximum Acceleration Rate, Braking Rate and Jerk Rate .....................................................................36
5.3.5 Maximum Operating Speed ...................................................................................................................37
5.3.6 Vehicle Characteristic Curves.................................................................................................................37

October 31, 2013


Page 3

Traction Power System Simulation Report

Revision: 4

List of Figures

FIGURE 1. TRAIN VOLTAGE PLOT NORMAL OPERATIONS.......................................................................................17


FIGURE 2. TRAIN VOLTAGE PLOT CONTINGENCY OPERATIONS .............................................................................18
FIGURE 3. TRAIN VOLTAGE PLOT RECOVERY OPERATIONS ....................................................................................19
FIGURE 4. RAIL POTENTIAL PLOT NORMAL OPERATIONS.......................................................................................21
FIGURE 5. RAIL POTENTIAL PLOT CONTINGENCY OPERATIONS .............................................................................22
FIGURE 6. RAIL POTENTIAL PLOT RECOVERY OPERATIONS ....................................................................................23
FIGURE 7. OCS CURRENT NORMAL OPERATIONS ...................................................................................................25
FIGURE 8. OCS CURRENT CONTINGENCY OPERATIONS ..........................................................................................26
FIGURE 9. OCS CURRENT RECOVERY OPERATIONS .................................................................................................27
FIGURE 10. OCS SEGMENTS ........................................................................................................................................31
FIGURE 11. SINGLE LINE DIAGRAM FOR THE TRACTION POWER SYSTEM ................................................................34
FIGURE 12. VEHICLE TRACTIVE EFFORT CURVE ..........................................................................................................37

List of Tables

TABLE 1. LIST OF SUBSTATIONS ....................................................................................................................................6


TABLE 2. LIST OF SIMULATION RUNS AND RECTIFIER CAPACITIES (MW) ...................................................................9
TABLE 3. SUBSTATION POWER DEMANDS IN KW (0 MINUTE OFFSET) .....................................................................11
TABLE 4. SUBSTATION RECTIFIER RMS LOAD CURRENT /RATING RATIO..................................................................12
TABLE 5. POSITIVE FEEDER LOAD CURRENTS (RMS AMPS) .......................................................................................13
TABLE 6. NEGATIVE FEEDER LOAD CURRENTS (RMS AMPS) .....................................................................................15
TABLE 7. LIST OF STATION LOCATIONS ......................................................................................................................29
TABLE 8. LIST OF TRAFFIC SIGNAL AND PEDESTRIAN CROSSING LOCATIONS ...........................................................29
TABLE 9. LOCATION OF TRACK CROSS-BONDS RELATIVE TO SUBSTATIONS .............................................................32
TABLE 10. CONDUCTOR RESISTANCES FOR 1 MESSENGER // 1 CONTACT WIRE ......................................................33
TABLE 11. SYSTEM VOLTAGE LEVELS ..........................................................................................................................35
TABLE 12. DC VOLTAGE REGULATION FOR RECTIFIER ...............................................................................................35
TABLE 13. VEHICLE ASSIGNED WEIGHTS ....................................................................................................................36

October 31, 2013


Page 4

Traction Power System Simulation Report

Revision: 4

Executive Summary

This revision of the report details the findings from the simulation study of the Purple Line
traction power system between Bethesda and New Carrollton.
The study takes into account the latest development in Design Criteria, Design Build Technical
Requirements, track alignment, substation locations and the light rail vehicle data.

1.1 Objectives
The simulation analysis is based on the MTA Red / Purple Line Design Criteria (Reference 2)
and the Design Build Technical Requirements (Reference 10). The objective of this study is to
confirm that the proposed traction power system configuration can meet the requirements of the
Design Criteria and the Design Build Technical Requirements.

1.2 Basic requirements


The basic requirements of the criteria are summarized as follows:
The system should be able to support 2-car train operation at AW3 load at 5 minute headway.

Under normal operation, at least 90% of all train voltage observations during simulation shall
be above the minimum vehicle voltage for full performance, i.e., 650V.
Rectifier load should be within its 100% rating for normal operation.
The maximum rail potential should be equal to or less than 50V.

Under contingency operation (substation outage for single-rectifier substations; or rectifier


unit outage for two-rectifier substations), train voltages should be at or above 525V.
Rectifier load should be within its 150% rating for 2 hours for contingency operation.
The maximum rail potential should be equal to or less than 75V.

Recovery Service of four sequential maximum length trains operating at maximum allowable
speeds with AW4 loads at normal LRV performance levels at three minute headways at any
location on the Mainline with simultaneous service of maximum length Trains at five minute
headways on the other track (Reference 10). The performance requirements are the same as in
contingency operation listed above.

October 31, 2013


Page 5

Traction Power System Simulation Report

Revision: 4

1.3 List of substations


In the previous study as detailed in the report revision 2, it was determined that 18 substations
were needed in order to meet the design criteria.
According to the latest site surveys and drawings, the locations of substations are listed in the
following table. The number of rectifier units for the substations are also listed in the same table.
Table 1. List of substations
Name
Rectifiers
Q01
2x2MW
Q02
1x2MW
Q03
1x2MW
Q04
1x2MW
Q05
1x2MW
Q06
1x2MW
Q07
1x2MW
Q08
1x2MW
Q09
1x2MW
Q10
1x2MW
Q11
1x2MW
Q12
1x2MW
Q13
1x2MW
Q14
1x2MW
Q15
1x2MW
Q16
1x2MW
Q17
1x2MW
Q18
2x2MW
Note: SOL=Start of Line at 100+00

Location
chainage
120+29
168+00
222+66
267+59
321+00
371+00
424+15
462+00
508+50
552+50
598+50
657+25
712+00
757+50
807+00
850+50
903+00
952+00

Location
(miles from
SOL)
0.38
1.29
2.32
3.17
4.19
5.13
6.14
6.86
7.74
8.57
9.44
10.55
11.59
12.45
13.39
14.21
15.21
16.14

Distance to
next sub
(miles)
0.90
1.04
0.85
1.01
0.95
1.01
0.72
0.88
0.83
0.87
1.11
1.04
0.86
0.94
0.82
0.99
0.93
0.21

A schematic diagram for the proposed traction power system is shown in Figure 11 in Appendix
B.

1.4 Summary of findings


1.4.1

Train voltages

The system meets the requirements for train voltages

Under normal operation condition, the occurrence of train voltages below 650V is 0.28%
of all train voltage observations during simulation, i.e., 99.72% of all observed train
voltages are above 650V. The minimum train voltage identified is 622V (see Fig. 1).
Under all contingency operation conditions, all train voltages are above 525V. The
minimum train voltage identified is 568V (see Fig. 2).
Under recovery operation conditions, all train voltages are above 525V. The minimum
train voltage identified is 603V (see Fig. 3).

October 31, 2013


Page 6

Traction Power System Simulation Report


1.4.2

Revision: 4

Maximum rail potential

The system meets the requirements for rail potential limit

Rail potential is less than 50V under normal operation. The maximum rail potential
identified is 39V (see Fig. 4).

Rail potential is less than 75V under all contingency operation conditions. The maximum
rail potential identified is 61V (see Fig. 5).

Rail potential is less than 75V under all recovery operation conditions. The maximum rail
potential identified is 42V (see Fig. 6).

1.4.3

Ratios of rectifier load RMS current/rating

The system meets the requirements for rectifier load/rating ratios

All rectifier loads are within 100% continuous rating under normal operation. The
maximum ratio identified is 54% (see Table 4).

All rectifier loads are within 150% 2-hour rating under all contingency operation
conditions. The maximum ratio identified is 73% (see Table 4).

All rectifier loads are within 150% 2-hour rating under all recovery operation conditions.
The maximum ratio identified is 73% (see Table 4).

1.5 Conclusions
The system configuration presented in this report conforms to the design criteria and the design
build technical requirements.

October 31, 2013


Page 7

Traction Power System Simulation Report

Revision: 4

Introduction

2.1 Main parameters


The main parameters for the simulation models are listed as follows.

2.1.1

The vehicles are based on 95 feet length per car. Maximum operation speed is 55 mph
(Ref.1 as listed in Appendix A);
Traction power is supplied by DC rectifiers at 750V nominal voltage (Ref.2);
The OCS has 6 segments, using Fixed Termination Single Contact Wire (FTSCW) and
Auto-Tension Simple Catenary (ATSC) as shown in Reference 7.
o In OCS Segments 1,2,3,4,6, OCS) has either one messenger wire of 500kcm
hard drawn copper or one parallel feeder cable of 500kcm hard drawn copper,
plus one contact wire of 350kcm hard drawn copper (Ref.7); The operating
temperature of the OCS is at 75oC, with the contact wire 30% worn as the worst
case (Ref.2).
o In OCS Segment 5 of the OCS, 2x1000 kcmil copper feeders will be used per
track for electro-magnetic interference mitigation (Ref.7), plus one contact wire of
350kcm of hard drawn copper. The feeders will be connected to the contact wire
through risers.
Running rails

Running rails are of 115 RE rails. The working temperature of the rails is at 60oC, with 10%
worn as the worst case (Ref.2).
Both rails are used for traction return current on each track. The running rails on the two tracks
are assumed to be cross-bonded at approximately 2000 intervals.
2.1.2

Substation rectifier units

Each substation is assumed to have 1x2000kW rectifier unit, which is the standardized size for
MTA LRT rectifiers (Ref.2). The two end-of-line substations are equipped with 2x2000kW
rectifier units each.
The dc no-load voltage is at 795V and the nominal load voltage at 750V, giving an inherent
voltage regulation of 6%. With a minimum short circuit capacity of 100MVA for the ac supply,
2.2% extra regulation is added to the overall regulation.
2.1.3

Train consists and operational headway

Trains consists are based on 2-car trains (Reference 3 as listed in Appendix A).
In normal operation, the minimum headway is 5-minutes for weekday peak period operations,
with train weight at AW3 (Reference 10).
Recovery Service of four sequential maximum length Trains operating at maximum allowable
speeds with AW4 loads at normal LRV performance levels at three minute headways at any
October 31, 2013
Page 8

Traction Power System Simulation Report

Revision: 4

location on the Mainline with simultaneous service of maximum length Trains at five minute
headways on the other track. (Reference 10).
2.1.4

Train stops

Train stops and dwell times are according to Scenario 2 as contained in the reference 8
(Simulation study report Rev4).
In addition to regular passenger stops, all traffic signal stops and pedestrian crossing stops are
also included in the simulation model.
In practical operation, a train may not necessarily stop at every traffic signal, depending on the
status of the signal and timing. There is a degree of randomness on where each train might stop
when it encounters a traffic signal. By including all traffic signal stops, the model captures the
worst case loads for the traction power system.

2.2 Methodology
Simulations have been carried out to assess the traction power system performance under both
normal operation, contingency operation and recovery operation conditions.
2.2.1

Simulation runs

Simulation runs and the number of rectifiers in service in each run are listed in the following
table.
Table 2. List of simulation runs and rectifier capacities (MW)
Substation
Name

Normal

Outage-1

Outage-2

Outage-3

Outage-4

Outage-5

Outage-6

Q01

Q02

Q03

Q04

Q05

Q06

Q07

Q08

Q09

Q10

Q11

Q12

Q13

Q14

Q15

Q16

Q17

Q18

Note- Highlighted cells indicate substations in contingency operation. For recovery operation,
substations are in normal configuration.

October 31, 2013


Page 9

Traction Power System Simulation Report

Revision: 4

Contingency conditions are defined as follows:

For Q01 and Q18 substations, 1 rectifier unit is out of service while the other rectifier
remains in service. DC bus and feeders also remain in service.
For all other substations, the rectifier, dc positive bus and positive feeders are all
taken out of service. The section break bypass switches are closed at the affected
substations so that electrical continuity of the OCS conductors is maintained on each
track while the two tracks are not electrically connected in parallel.

All contingency conditions are covered by 6 simulation runs listed in the above table, labeled
Outage-1 through Outage-6. Each contingency run covers 3 substations that are in
contingency conditions. The substations with contingency conditions in each contingency
run are separated by five substations that are in normal operation. In this way, the effect of
one contingency on another in the same run is minimized. The number of simulation runs is
minimized while the accuracy of the simulation results is not compromised.
Recovery operations are covered by 2 simulation runs:

EB trains with AW3 weight and 5 minute headway; WB trains with AW4 weight and 3
minute headway
EB trains with AW4 weight and 3 minute headway; WB trains with AW3 weight and 5
minute headway

By assigning a regular headway of three minutes at AW4 weight, these two runs cover all
recovery operation conditions that will have four sequential trains operating at three minute
headway at all location throughout the line.
2.2.2

Train dispatching

Under each condition, train dispatching from the two ends of the track are simulated with
different time offsets, so that trains on the two tracks may meet at different locations and the
worst cases of power demands can be captured. The simulation results in this report reflect the
following offsets:

WB train is dispatched at the same time as EB train (0 minute offset)

WB train is dispatched 0.5 minute later than EB train (0.5 minute offset)

WB train is dispatched 1 minutes later than EB train (1 minute offset)

WB train is dispatched 1.5 minutes later than EB train (1.5 minute offset)

WB train is dispatched 2 minutes later than EB train (2 minute offset)

WB train is dispatched 2.5 minutes later than EB train (2.5 minute offset)

October 31, 2013


Page 10

Traction Power System Simulation Report

Revision: 4

Simulation Results

3.1 Substation power demands (average kW)


The average power demands in kW for both normal operation and contingency operation are
listed in the following table (peak hour service, 0 minute offset).
Table 3. Substation power demands in kW (0 minute offset)
Substation
Name

Normal

Outage-1

Outage-2

Outage-3

Outage-4

Outage-5

Outage-6

Q01

642

566

929

698

659

569

566

Q02

656

695

823

696

707

697

Q03

599

612

780

871

674

624

Q04

737

753

777

959

1023

807

Q05

871

935

900

920

1104

1203

Q06

910

1199

999

943

966

1224

Q07

893

1282

994

926

962

1207

Q08

976

1337

1329

1057

1011

1068

Q09

1,024

1116

1353

1379

1100

1065

Q10

998

1045

1081

1373

1286

1080

Q11

936

1053

986

1030

1262

1266

Q12

904

1259

1010

953

1006

1274

Q13

888

1195

964

937

1014

1232

Q14

934

1200

1223

1008

979

1020

Q15

923

981

1216

1242

991

945

Q16

847

862

919

1183

1096

862

Q17

833

836

849

900

1087

892

Q18

738

739

743

759

814

1173

652

Total

15,311

15,187

15,020

15,052

15,014

15,085

15,186

Maximum

1,024

1,337

1,353

1,373

1,379

1,286

1,266

Note - Highlighted cells indicate substations in contingency operation

Power demands for other headway offsets are similar as those listed above. They are not listed
in this report for brevity.

October 31, 2013


Page 11

Traction Power System Simulation Report

Revision: 4

3.2 Rectifier load current (RMS amps)/ rating ratios


The ratios of rectifier load current (RMS amps in peak hour service) over the rated current are
listed in the following table.
Table 4. Substation rectifier RMS load current /rating ratio
Substation

Power Rating
(kW)

Current Rating
(A)

Normal (all
offsets)

Outages (all
offsets)

Recovery (all
offsets)

Q01

4,000

5,333

18%

32%

21%

Q02

2,000

2,667

33%

42%

40%

Q03

2,000

2,667

31%

45%

38%

Q04

2,000

2,667

40%

54%

45%

Q05

2,000

2,667

45%

63%

59%

Q06

2,000

2,667

47%

63%

64%

Q07

2,000

2,667

44%

65%

61%

Q08

2,000

2,667

49%

68%

70%

Q09

2,000

2,667

54%

72%

73%

Q10

2,000

2,667

53%

73%

72%

Q11

2,000

2,667

48%

65%

63%

Q12

2,000

2,667

45%

65%

61%

Q13

2,000

2,667

45%

63%

59%

Q14

2,000

2,667

48%

64%

61%

Q15

2,000

2,667

47%

64%

61%

Q16

2,000

2,667

45%

63%

57%

Q17

2,000

2,667

47%

59%

55%

Q18

4,000

5,333

19%

34%

24%

54%

73%

73%

Maximum

The above table indicates that the rectifiers have sufficient capacities to support the normal
operation, all the contingency operation conditions and the recovery operations. The system
meets the requirements of the design criteria in terms of rectifier ratings.

October 31, 2013


Page 12

Traction Power System Simulation Report

Revision: 4

3.3 Substation feeder current (RMS amps)


Feeder name designations in the simulation model are according to the single line diagram
shown in Figure 11 in Appendix B. A typical substation feeder numbering is shown in the
diagram below.

For each simulation, an RMS load current for each feeder in each substation is derived from the
simulation results. These include both positive feeders and negative feeders. The maximum
values from all the simulation runs are summarized for each feeder, which represent the worst
case load for the feeder.
The following table lists positive feeder load currents.
Table 5. Positive Feeder Load Currents (RMS Amps)
Substation

Feeder Name

Maximum
Normal Op

Q01

EB1-Feeder

397

Maximum
Contingency
Op
478

Q01

EB2-Feeder

369

464

475

Q01

WB1-Feeder

185

274

250

Q01

WB2-Feeder

196

299

265

Q02

EB1-Feeder

263

306

331

Q02

EB2-Feeder

296

349

375

Q02

WB1-Feeder

391

440

499

Q02

WB2-Feeder

390

448

499

Q03

EB1-Feeder

287

361

360

Maximum
Recovery Op
514

October 31, 2013


Page 13

Traction Power System Simulation Report

Revision: 4

Table 5. Positive Feeder Load Currents (RMS Amps)


Feeder Name

Maximum
Normal Op

Q03

EB2-Feeder

287

Maximum
Contingency
Op
375

Q03

WB1-Feeder

279

339

380

Q03

WB2-Feeder

272

351

369

Q04

EB1-Feeder

391

468

472

Q04

EB2-Feeder

400

498

492

Q04

WB1-Feeder

252

318

346

Q04

WB2-Feeder

271

351

372

Q05

EB1-Feeder

357

448

533

Q05

EB2-Feeder

341

454

525

Q05

WB1-Feeder

417

509

620

Q05

WB2-Feeder

403

518

612

Q06

EB1-Feeder

319

428

515

Q06

EB2-Feeder

322

417

518

Q06

WB1-Feeder

435

550

656

Q06

WB2-Feeder

435

536

659

Q07

EB1-Feeder

354

466

555

Q07

EB2-Feeder

348

473

551

Q07

WB1-Feeder

334

457

545

Q07

WB2-Feeder

340

476

552

Q08

EB1-Feeder

396

521

560

Q08

EB2-Feeder

395

518

561

Q08

WB1-Feeder

418

540

690

Q08

WB2-Feeder

431

550

703

Q09

EB1-Feeder

390

499

584

Q09

EB2-Feeder

376

493

560

Q09

WB1-Feeder

487

601

777

Q09

WB2-Feeder

483

609

754

Q10

EB1-Feeder

413

535

565

Q10

EB2-Feeder

427

523

578

Q10
Q10
Q11

WB1-Feeder
WB2-Feeder
EB1-Feeder

474
467
395

601
567
506

710
695
586

Q11

EB2-Feeder

382

499

565

Q11

WB1-Feeder

390

503

577

Q11

WB2-Feeder

383

495

566

Q12

EB1-Feeder

305

440

483

Q12

EB2-Feeder

314

444

491

Q12

WB1-Feeder

375

516

598

Q12

WB2-Feeder

369

501

587

Q13

EB1-Feeder

370

482

545

Q13

EB2-Feeder

358

462

525

Q13

WB1-Feeder

356

476

550

Q13

WB2-Feeder

362

463

556

Q14

EB1-Feeder

436

524

550

Substation

Maximum
Recovery Op
358

October 31, 2013


Page 14

Traction Power System Simulation Report

Revision: 4

Table 5. Positive Feeder Load Currents (RMS Amps)


Feeder Name

Maximum
Normal Op

Q14

EB2-Feeder

440

Maximum
Contingency
Op
535

Q14

WB1-Feeder

402

484

575

Q14

WB2-Feeder

379

474

550

Q15

EB1-Feeder

439

549

632

Q15

EB2-Feeder

430

541

621

Q15

WB1-Feeder

320

414

498

Q15

WB2-Feeder

352

465

543

Q16

EB1-Feeder

434

545

597

Q16

EB2-Feeder

431

520

598

Q16

WB1-Feeder

319

424

462

Q16

WB2-Feeder

305

390

427

Q17

EB1-Feeder

378

459

549

Q17

EB2-Feeder

358

424

524

Q17

WB1-Feeder

413

494

549

Q17

WB2-Feeder

422

488

565

Q18

EB1-Feeder

295

439

423

Q18

EB2-Feeder

264

393

379

Q18

WB1-Feeder

309

456

417

Q18

WB2-Feeder

278

409

376

487

609

777

Substation

Maximum

Maximum
Recovery Op
558

Of all the positive feeders, the maximum is 487A under normal operation, 609A for contingency
operation and 777A for recovery operation.
The following table lists negative feeder load currents.
Table 6. Negative Feeder Load Currents (RMS Amps)
Feeder Name

Maximum Normal Op

Q01

EB1-Return

551

Maximum
Contingency
Op
739

Q01

WB1-Return

419

620

482

Q02

EB1-Return

422

541

499

Q02

WB1-Return

530

643

687

Q03

EB1-Return

441

618

533

Q03

WB1-Return

426

604

549

Q04

EB1-Return

660

842

707

Q04

WB1-Return

431

629

526

Q05

EB1-Return

626

855

825

Q05

WB1-Return

610

842

836

Q06

EB1-Return

594

813

814

Q06

WB1-Return

673

888

941

Q07

EB1-Return

598

877

849

Q07

WB1-Return

590

856

841

Substation

Maximum
Recovery Op
671

October 31, 2013


Page 15

Traction Power System Simulation Report

Revision: 4

Table 6. Negative Feeder Load Currents (RMS Amps)


Feeder Name

Maximum Normal Op

Q08

EB1-Return

697

Maximum
Contingency
Op
939

Q08

WB1-Return

666

912

Q09

EB1-Return

714

963

943

Q09

WB1-Return

737

983

1,067

Q10

EB1-Return

710

965

917

Q10

WB1-Return

756

1,010

1,055

Q11

EB1-Return

650

876

885

Q11

WB1-Return

659

887

904

Q12

EB1-Return

598

859

806

Q12

WB1-Return

613

877

855

Q13

EB1-Return

634

871

825

Q13

WB1-Return

627

864

828

Q14

EB1-Return

664

856

852

Q14

WB1-Return

674

878

905

Q15

EB1-Return

677

898

924

Q15

WB1-Return

611

833

825

Q16

EB1-Return

686

912

897

Q16
Q17

WB1-Return
EB1-Return

553

781

694

660

812

805

Q17

WB1-Return

626

793

805

Q18

EB1-Return

528

826

682

Q18

WB1-Return

501

800

630

756

1,010

1,067

Substation

Maximum

Maximum
Recovery Op
917
1,011

Note - The above list includes all simulated headway offsets

Of all the negative feeders, the maximum is 756A under normal operation, 1010A for
contingency operation and 1067A for recovery operation.

3.4 Train voltage plots


The following figures show the instantaneous train voltages (between pantograph and return
rails) across the system for the duration of simulation.
These figures indicate that:

There are instants when train voltages are below 650V under normal operations but the
frequency of such occurrence is below the specified limit of 10% of all observed train
voltage, per the Design Criteria.
All train voltages are above 525V under all contingency operation conditions.
All train voltages are above 525V under all recovery operations.

The system meets the requirements of the design criteria in terms of train voltages.

October 31, 2013


Page 16

Traction Power System Simulation Report


3.4.1

Revision: 4

Normal operations

Figure 1. Train voltage plot normal operations

October 31, 2013


Page 17

Traction Power System Simulation Report


3.4.2

Revision: 4

Contingency operations

Figure 2. Train voltage plot contingency operations

October 31, 2013


Page 18

Traction Power System Simulation Report


3.4.3

Revision: 4

Recovery operations

Figure 3. Train voltage plot recovery operations

October 31, 2013


Page 19

Traction Power System Simulation Report

Revision: 4

3.5 Rail potential plot


The following figures show the instantaneous rail potential (with respect to remote ground)
across the system for the duration of simulation.
These figures indicate that:

Rail potential is within 50V across the system under normal operations.
Rail potential is within 75V across the system under all contingency operation conditions.
Rail potential is within 75V across the system under all recovery operation conditions.

The system meets the requirements of the design criteria in terms of rail potential.

October 31, 2013


Page 20

Traction Power System Simulation Report


3.5.1

Revision: 4

Normal operations

Figure 4. Rail potential plot normal operations

October 31, 2013


Page 21

Traction Power System Simulation Report


3.5.2

Revision: 4

Contingency operations

Figure 5. Rail potential plot contingency operations

October 31, 2013


Page 22

Traction Power System Simulation Report


3.5.3

Revision: 4

Recovery operations

Figure 6. Rail potential plot recovery operations

October 31, 2013


Page 23

Traction Power System Simulation Report

Revision: 4

3.6 OCS current plot (RMS amps)


The following figures show the RMS currents in the OCS along the tracks across the system.
The RMS value for each location on each track is computed from the instantaneous currents
through the OCS conductors in the duration of simulation.
These figures indicate that:

The maximum OCS RMS current in the system is 735A under normal operation.
The maximum OCS RMS current in the system is 1033A under all contingency operation
conditions.
The maximum OCS RMS current in the system is 1183A under all recovery operation
conditions

According to Reference 5, allowable ampacity for 500kcm messenger is 810A and for 350kcm
contact wire 650A, making a total ampacity of 1460A (continuous current rating) for the OCS
(based on 75oC conductor temperature, 25oC ambient temperature, wind velocity of 2
feet/second, under sun light).
If the contact wire is 30% worn, its cross-sectional area is reduced to 245kcm and its ampacity
is reduced to 520A. The total OCS ampacity is reduced to 1330A. This is sufficient to support
normal operations, contingency operations and recovery operations. (Ampacity for 245kcm is
not given in reference 5, as it is not a standard size. Using the ampacity of 530A for a 250kcm
contact wire, the ampacity of 245kcm contact is calculated to be 524A. It is rounded down to
520A.)

October 31, 2013


Page 24

Traction Power System Simulation Report


3.6.1

Revision: 4

Normal operations

Figure 7. OCS current normal operations

October 31, 2013


Page 25

Traction Power System Simulation Report


3.6.2

Revision: 4

Contingency operations

Figure 8. OCS current contingency operations

October 31, 2013


Page 26

Traction Power System Simulation Report


3.6.3

Revision: 4

Recovery operations

Figure 9. OCS current Recovery operations

October 31, 2013


Page 27

Traction Power System Simulation Report

Revision: 4

Appendix A List of Reference Document

The following documents are used as reference.


1. MTA Purple/Red Line Design Criteria Manual; Chapter 04 Light Rail Vehicles, July,
2013.
2. MTA Purple/Red Line Design Criteria Manual; Chapter 16 - Traction Power
Substations, July, 2013.
3. MTA Purple/Red Line Design Criteria Manual; Chapter 3 Operational characteristics
and requirements, July, 2013.
4. 2013.08.01.PE.Preliminary Engineering Drawings-Vol1-00 (Preliminary Engineering
Submission; August 1, 2013)
5. South Wire Copper Product Catalogue Bare Copper Wire and Cable.
6. GEC Red Line Team Meeting Minutes Car Interfaces (to Traction Power Design);
Dated December 7, 2011. With characteristic curves contained in a separate Excel file.
7. Purple Line OCS - Draft preliminary engineering master overlap plan sheets 1-6; not
dated
Purple Line OCS - Draft preliminary engineering auto-tensioned simple catenary;
dated September 28, 2012.
Purple Line OCS - Draft preliminary engineering conductor particulars fixed
termination catenary; dated September 28, 2012.
8. MTA Purple Line: Draft Computer Simulation Analyses - Running Times/Vehicle Braking,
Rev.4; Dated September 17, 2013; DCN 2011.12.22.SU.PE.11.Computer Simulation
Analyses-04.
9. MTA Purple/Red Line Design Criteria Manual; Chapter 15 Signaling, July, 2013.
10. Draft Request for Proposals, Volume II Book 2, Technical Provisions Part 1 Design
Build Requirements : Section 11 - Systems General Requirements, September, 2013.

October 31, 2013


Page 28

Traction Power System Simulation Report

Revision: 4

Appendix B List of Simulation Data

5.1 Track Alignment Data


The LRT route has two tracks, labeled Eastbound (EB) and Westbound (WB) (Reference 4).
Details of track alignment, speed limits and train stop scenarios are listed in a separate
document for the train performance simulation (Reference 8).
Station locations are listed in the following table.
Table 7. List of station locations
Station
Code
BEM
CCL
LYT
WOS
SST
SSL
DAD
MAP
LOB
PIB
TLT
RIR
WEC
CAC
EAC
COP
MSQ
RIP
BEA
ANR
NEC

Station Name
Bethesda
Chevy Chase Lake
Lyttonsville
Woodside/16th St
Silver Spring TC
Silver Spring Lib
Dale Drive
Manchester Place
Long Branch
Piney Branch Road
Takoma_Langley TC
Riggs Rd
Adelphi/West Campus
Campus Center
East Campus
College Park Metro
M Square
Riverdale Park
Beacon Heights
Annapolis/Glenridge
New Carrollton

median
location
chainage
102+32
174+41
247+63
302+63
328+75
350+83
380+67
409+85
431+77
453+41
492+96
523+14
596+62
625+87
655+75
703+80
742+98
789+28
838+68
906+13
955+70

median
location ft
from SOL
232
7,441
14,763
20,263
22,875
25,083
28,067
30,985
33,177
35,341
39,296
42,314
49,662
52,587
55,575
60,380
64,298
68,928
73,868
80,613
85,570

median
location
miles from
SOL
0.044
1.409
2.796
3.838
4.332
4.751
5.316
5.868
6.284
6.693
7.442
8.014
9.406
9.960
10.526
11.436
12.178
13.055
13.990
15.268
16.206

Traffic signal and pedestrian crossing locations are listed in the following table.
Table 8. List of traffic signal and pedestrian crossing locations
Station
Code
C01
C02
C03
C04
C05
C06
C07
C08
C09
C10
C11
C12
C13

Station Name
Bonifant St/Dixon
Bonifant St/Georgia
Wayne Ave/Fenton
Wayne Ave/Cedar
Wayne Ave/Dale
Wayne Ave/Mansfield
Wayne Ave/Sligo Crk
Wayne Ave/Mnchester
Wayne Ave/Ply Tnl
Arliss St/Garland
Arliss St /Piney Br
Piney Br Rd/Garland
Piney Br Rd/Barron

location
chainage
337+95
341+45
352+45
362+20
377+45
389+70
397+95
400+45
405+95
426+45
433+45
440+45
444+95

location ft
from SOL
23,795
24,145
25,245
26,220
27,745
28,970
29,795
30,045
30,595
32,645
33,345
34,045
34,495

location
miles from
SOL
4.507
4.573
4.781
4.966
5.255
5.487
5.643
5.690
5.795
6.183
6.315
6.448
6.533

October 31, 2013


Page 29

Traction Power System Simulation Report

Revision: 4

Table 8. List of traffic signal and pedestrian crossing locations


Station
Code
C14
C15
C16
C17
C18
C19
C20
C21
C22
C23
C24
C25
C26
C27
C28
C29
C30
C31
C32
C34
C35
C36
C37
C38
C40
C41
C42
C43
C44
C45
C46
C47
C49
C50
C51
C52
C53
C54
C55
C56
C57
C58

Station Name
Piney Br Rd/Univ
Univ/Seek
Univ/Carroll
Univ/Merrimac
Univ/Lebanon
Univ/Langley Plaza
Univ/Tak-Lan TC
Univ/New Hampshire
Univ/TakLan Crossrd
Univ/14th Ave
Univ/15th Ave
Univ/Riggs Road
Univ/Guilford Road
Univ/23rd Ave
Univ/24th Ave (N)
Univ/West Park
Univ/Adelphi
Pres Dr/Campus
Pres Dr/Valley
STOP SIGN Ped 1
STOP SIGN Ped 2
STOP SIGN Ped 3
Campus/Regents
Rossboro/Baltimore
Paint Pkwy/Rossboro
Paint Pkwy/PaintTrl
Paint Pkwy/MFRI
Paint Pkwy/Metro
River Road/Rivertch
River Road/Haig
River/Kenilworth
Kenilwth/Rittenhse
Riverdale/Mustang
Riverdale/64th Ave
Riverdale/On Ramp
Riverdale/Off Ramp
Riverdale/66th Ave
Riverdale/67th Ave
Vets Pkwy/Glenridge
Vets Pkwy/Annapolis
Vets Pkwy/Ellin
Ellin/Hanson Oaks

location
chainage
449+95
459+45
470+95
477+70
484+45
486+95
489+95
494+95
499+70
504+95
516+45
524+95
535+20
548+20
555+20
563+20
593+70
601+95
615+20
626+95
630+20
635+20
640+45
653+20
664+20
673+45
680+45
692+95
732+95
744+45
759+95
772+45
811+95
820+45
825+45
830+20
831+95
836+45
886+70
903+20
921+95
934+95

location ft
from SOL
34,995
35,945
37,095
37,770
38,445
38,695
38,995
39,495
39,970
40,495
41,645
42,495
43,520
44,820
45,520
46,320
49,370
50,195
51,520
52,695
53,020
53,520
54,045
55,320
56,420
57,345
58,045
59,295
63,295
64,445
65,995
67,245
71,195
72,045
72,545
73,020
73,195
73,645
78,670
80,320
82,195
83,495

location
miles from
SOL
6.628
6.808
7.026
7.153
7.281
7.329
7.385
7.480
7.570
7.670
7.887
8.048
8.242
8.489
8.621
8.773
9.350
9.507
9.758
9.980
10.042
10.136
10.236
10.477
10.686
10.861
10.993
11.230
11.988
12.205
12.499
12.736
13.484
13.645
13.740
13.830
13.863
13.948
14.900
15.212
15.567
15.813

October 31, 2013


Page 30

Traction Power System Simulation Report

Revision: 4

5.2 Traction Power System Data


5.2.1

OCS Segments

OCS segments are shown in the following figure.

Figure 10. OCS segments

5.2.2

Locations of track cross-bonds

At this stage, the precise locations of track cross-bonds have not been determined. A nominal
spacing of 2000 between cross-bonds is assumed, per Design Criteria Chapter 15 - Signaling
(Reference 9). The following table lists the locations of the cross-bonds relative to substations
based on this assumption. Also listed in the table are the distances between adjacent crossbonds or between cross-bonds and their nearest substations.

October 31, 2013


Page 31

Traction Power System Simulation Report

Revision: 4

Table 9. Location of track cross-bonds relative to substations


Distance to
previous
location (ft)

TPS/Bond
Locations

Chainage

Distance to
previous
location (ft)

Z-Bond_12

523+17

1,467

Z-Bond_13

537+83

1,467

2,385

Q10

552+50

1,467

2,386

Z-Bond_14

575+50

2,300

1,822

Q11

598+50

2,300

1,822

Z-Bond_15

618+08

1,958

TPS/Bond
Locations

Chainage

SOL-Bond_00

100+00

Q01

120+29

2,029

Z-Bond_01

144+14

Q02

168+00

Z-Bond_02

186+22

Z-Bond_03

204+44

Q03

222+66

1,822

Z-Bond_16

637+66

1,958

Z-Bond_04

245+12

2,246

Q12

657+25

1,959

Q04

267+59

2,247

Z-Bond_17

675+50

1,825

Z-Bond_05

285+39

1,780

Z-Bond_18

693+75

1,825

Z-Bond_06

303+19

1,780

Q13

712+00

1,825

Q05

321+00

1,781

Z-Bond_19

734+75

2,275

Z-Bond_07

337+66

1,666

Q14

757+50

2,275

Z-Bond_08

354+32

1,666

Z-Bond_20

782+25

2,475

Q06

371+00

1,668

Q15

807+00

2,475

Z-Bond_09

388+71

1,771

Z-Bond_21

828+75

2,175

Z-Bond_09A

406+42

1,771

Q16

850+50

2,175

Q07

424+15

1,773

Z-Bond_22

868+00

1,750

Z-Bond_10

443+07

1,892

Z-Bond_23

885+50

1,750

Q08

462+00

1,893

Q17

903+00

1,750

Z-Bond_11

485+50

2,350

Z-Bond_24

927+50

2,450

Q09

508+50

2,300

Q18

952+00

2,450

EOL-Bond_25

963+14

1,114

As shown in the above table, a total of 26 cross bonds are assumed, including one at each end
of the line: SOL (start of line) and EOL (end of line).
It is further assumed that the distance between two adjacent cross-bonds, or between one
cross-bond and its nearest substation return connection, should not exceed 2500. Based on
this assumption and the distance between adjacent substations, the number of cross-bonds is
determined.

Where there is only one cross-bond between two adjacent substations, the cross-bond is
located at the mid-point within the feeding section.

Where there are two cross-bonds between two adjacent substations, the cross-bonds
are located at and points with the feeding section.

October 31, 2013


Page 32

Traction Power System Simulation Report


5.2.3

Revision: 4

Conductor Resistances

Conductor resistances are listed in the following tables.


Table 10. Conductor resistances for 1 messenger // 1 contact wire
R values no wear at given temp

Ohms/mi

Ohms/kft

temp
C for
given
value

messenger
500kcm HD
copper

0.11616

0.02200

20

contact 350kcm
HD copper

0.16099

0.03049

20

OCS=Messenger
// contact wire

0.06747

0.01278

Conductor Type

running rail 115


# steel (1 rail,
AREMA avg R)

0.05390

0.01021

running rail 115


# steel (2 rails//,
AREMA avg R)

0.02695

0.00510

20

Ref
Source

Service
Wire Co.
catalog

calc from
AREMA
chem
comp

Temp coeff

Working temp C

Working temp, no
wear

Working temp, with wear

Working
temp C

Reference
Source

Temp
diff C

Ohms/mi

% wear
(Xsection
area
loss)

0.00377

75

MTA DC

55

0.1402

0%

0.00377

75

MTA DC

55

0.1944

30%

75

MTA DC

60

MTA DC

Temp
coeff
1/C

0.003611

Reference
Source

Reference
Source

0.14000

MTA DC

0.0815

40

0.0617

Ohms/mi

0.27767
0.09307

10%

0.03084

MTA DC

0.06854

0.03427

For segment 5, where 2x1000 kcmil copper cables are used to run in parallel with the contact wire, the resultant OCS resistance is
0.03113 Ohms/mile, in comparison with 0.09307 Ohms/mile for other segments where only 1x500 kcmil messenger or cable is used
in parallel with the contact wire.
5.2.4

Single Line Diagram

Single line diagram for the system is shown in the following figure, including both positive and negative circuits.

October 31, 2013


Page 33

Traction Power System Simulation Report

Revision: 4

Figure 11. Single line diagram for the traction power system

October 31, 2013


Page 34

Traction Power System Simulation Report


5.2.5

Revision: 3

Voltage Levels

The traction power system voltage levels are listed in the following table (Reference 1).
Table 11. System voltage levels

5.2.6

Maximum sustained supply voltage

900 VDC

Nominal supply voltage

750 VDC

Minimum voltage for full performance

650 VDC

Minimum sustained supply voltage

525 VDC

Regeneration cut-off

900 VDC

Rectifier voltage regulation

The inherent regulation of the rectifier equipment is at 6%. When the ac supply impedance is
added (with minimum short circuit capacity at 100MVA for the ac supply), the total regulation is
at 8.2%. Calculations are detailed in the following table.
Table 12. DC voltage regulation for rectifier
Nominal voltage
No-load voltage
Voltage drop
% regulation
Rectifier rating
Rectifier full load current
Rectifier transformer rating
Supply voltage (no-load, line-line)
Supply voltage (no-load, phase)
Minimum supply short circuit capacity at TPSS
Supply short circuit current (phase)
Rectifier full load current at supply voltage (phase)
AC supply voltage regulation
Total dc voltage regulation
DC voltage drop total
DC voltage at full load current
Equivalent DC resistance of converter & supply

5.2.7

750
795
45
6%
2000
2667
2200
13200
7621
100
4374
96
2.2%
8.2%
60.25
734.75
0.0226

Vnom
Vdo
Vdc
Based on Vnom
kW
Amp
kVA
Vac (line-line)
Vac (line-neutral)
MVA
Amp, ac RMS
Amp, ac RMS
Based on Vnom
Vdc
Vdc
Ohms

Feeder cables and track cross-bonds

Substation feeder cables are assumed to be of 2x1000 kcm copper for each feeder circuit, with
300 length from dc bus to the OCS connection. The lump resistance for each feeder circuit is
1.65 milli-Ohms.
Each negative feeder circuit is assumed to be of 4x1000kcm copper. With 300 from the dc
negative bus to the track connection, the lump resistance for each circuit is 0.825 milli-Ohms.
For substation Q07, the length of the feeder cables is assumed to be 640, due to the distance
between the substation location and the sectionalization gaps. The resultant feeder resistances
are 3.52 milli-Ohms for each positive feeder circuit and 1.76 milli-Ohms for each negative feeder
circuit.

October 31, 2013


Page 35

Traction Power System Simulation Report

Revision: 3

For track cross-bonds at each location, 2x1000 kcmil copper cables are assumed, with a
maximum length of 100. The resultant circuit resistance is 0.55 milli-Ohms.

5.3 Vehicle Data


5.3.1

Vehicle Weight

The vehicle used for simulation is based on the 95 feet car. The vehicle and passenger weights
are listed in the following table (Reference 1).
Table 13. Vehicle Assigned Weights
Assigned
Weight

for 1-car

for 2-cars

Weight
Class

Load details

lb

kg

lb

kg

(Ready to
run)

AW0

Maximum empty
operating weight lb

105,500

47,897

211,000

95,794

(Seated
load)

AW1

AW0 weight plus seated


load of 72 passengers
and one operator

116,742

53,001

233,484

106,002

AW2

AW1 load plus 106


standees at 2.7 ft2 of
suitable standing space
per standee

133,066

60,412

266,132

120,824

141,228

64,118

282,456

128,235

149,390

67,823

298,780

135,646

(Design
load)

(Crush load)

AW3

(Structural
design)

AW4

AW1 load plus 159


standees at 1.8 ft2 of
suitable standing space
per standee
AW1 load plus 212
standees at 1.35 ft2 of
suitable standing space
per standee

Note - From Reference 1.

It is assumed that the vehicles rotational weight is 10% of AW0 weight.


AW3 weight is used in simulation for normal operation and contingency operation; AW4 weight
is used for recovery operation.
5.3.2

Power conversion efficiency

Power conversion efficiency is at 0.85 for both auxiliary power converter and propulsion unit
(Ref.6).
5.3.3

Auxiliary Load

The onboard auxiliary load is assumed to be 80kW per car on the pantograph side (Ref.1).
5.3.4

Maximum Acceleration Rate, Braking Rate and Jerk Rate

The maximum acceleration rate is 3.0 mph/s. The maximum Braking rate is 3.0 mph/s. The jerk
rate limit is 1.5 mph/s/s.
October 31, 2013
Page 36

Traction Power System Simulation Report


5.3.5

Revision: 3

Maximum Operating Speed

The maximum operating speed is 55 mph [89 km/hr].


5.3.6

Vehicle Characteristic Curves

The following figures show the vehicle characteristic curves that accompany Reference 1.

Figure 12. Vehicle tractive effort curve

In the traction power system load flow study, regenerative braking power is utilized only for
onboard auxiliary loads. This produces the worst case power demand and energy consumption.
The maximum line draw per vehicle is 1650 amperes, including both propulsion and auxiliary
loads.

October 31, 2013


Page 37

Вам также может понравиться