Вы находитесь на странице: 1из 2

Check List for Testing

Equipment needed to be tested:


33 KV Panel
CT
PT
Relay
VCB Breaker

Preliminary Checkup
Test equipment calibration certificate verification
Injection Kit

Multi meter

Megger

Clamp meter

Moving coil Ammeter

CRM

Timer Kit

Test to be carried out in Panel:

Megger / PI

Insulator Visual checkup


Hi-Pot

CRM for BUS Bar

Wiring Through
Functionality Checkup Hooter,
Ammeter checkup

Voltmeter checkup

MFM meter checkup


Earthing Checkup for panel
Panel Interlock

Annunciator, Ind. Lamp

Current Transformer:

Ratio Test
Megger/ PI
Polarity
Resistance
Knee point Test

Potential Transformer

(If Applicable)

Ratio Test
Megger
Resistance
Polarity

/ PI

Breaker:
Hi-pot

Megger / PI

CRM

Timing

Spring charge motor

Coil Resistance

Functional Checks
o Breaker On/ Of
o Spring Charge indication

o Limit Switch operation


o Breaker Aux contact
Operation Checkup
o Manual Close & Trip
o Electrical local / remote close and trip
o Protection Trip
o Anti-pumping circuit
o Interlock circuit

Relay:
Pickup and Drop Voltage for voltage based relay
Secondary injection Test

Functionality Checkup
o Operation of master trip relay

o Breaker tripping contact

-------------