= 4.125 m
Beam width
= 0.3 m
Step 2
Fixation of d & D
L/d
( Here the condition of our slab is one side simply supported & one side
continuous )
So,
L/d
= (20+26)/2
= 23
Here L = 4.12 m
(Assume modification factor corresponding to Pt =0.25%) = 1.6 for Fe 415
steel
Hence,
d = 4120/(23 x 1.6)
=111.95 mm
(Assume 10 mm dia bars using ) hence Total depth =111.95 + 5 + 15
= 131.95 mm
Take 150 mm overall depth for the slab
So, effective depth d =150-15-5 =130 mm
2
Total weight = 4.775 KN/ m
2
Assume live load Ws =2 KN/ m
2
Hence total weight =6.775 KN/ m
At end span
M(centre) = (Wd L
=(4775x 4.12
)/12 + (Ws L
))/10
)/10
2
2
M(support) ==(4775x 4.12 )/10 + (2000x 4.12 )/9
106 Nmm
10
x1.5
Hence, d =
6451.5
MuD
)
Rub
80.32 131
Determination of reinforcement,
1. At end support
106
106
2. At mid span
106
10
fckb
4.6
Mu
/ ) ] x bd
Ast1 = (0.5 fck/fy)x[ 11
20 x 1000 x
4.6
x
15.225
x 106 / ) ] x 1000 x130
= (0.5 x 20/415)x[ 11
= 340.6
mm2
fckb
4.6
Mu
/ ) ] x bd
Ast2 = (0.5 fck/fy)x[ 11
20 x 1000 x
6
= (0.5 x 20/415)x[ 1- 4.6 x 17.812 x 10 / ) ] x 1000 x130
1
= 402.37 mm
Spacing ,
1. 10 mm dia main bar
d2
Spacing = (1000 x ( 4 ))/340.6
=230 mm
Hence provide 10 mm dia bars @ 200 mm spacing.
1000 x 78.5
So actual area provided =(
)
200
= 392.5
mm2
100 x 392.5
Percentage steel =( 1000 x 130 )
= 0.30 %
2. 10 mm dia distribution bar
d2
Spacing = (1000 x ( 4 ))/402.37
=195 mm
Hence provide 10 mm dia bars @ 190 mm spacing.
So actual area provided =(
= 413.15
1000 x 78.5
)
190
mm2
100 x 413.5
Percentage steel =( 1000 x 130 )
= 0.318 %