Академический Документы
Профессиональный Документы
Культура Документы
PROJECT (Proyecto):
SITE
ACTIVITY
SECTOR
ITEM
DURATION
[days]
START
[data]
END
[data]
LAPSED
[days]
QUANTITY
[-]
UNIT
[si]
WORK
[% done]
[status]
AMMONIA
STOOP
7/11/2015
8/19/2015
40
Task
A 3-4
LEVELING & COMPACTION
1
1
7/11/2015
8/15/2015
7/11/2015
8/15/2015
LAYING PE FILM
1
1
7/12/2015
8/16/2015
7/12/2015
8/16/2015
FORM PLYWOOD 3T
1
1
7/12/2015
8/16/2015
7/12/2015
8/16/2015
1
1
7/13/2015
8/17/2015
7/13/2015
8/17/2015
1
1
7/14/2015
8/18/2015
7/14/2015
8/18/2015
EXPANSION JOINT/CAULKING
1
1
7/15/2015
8/19/2015
7/15/2015
8/19/2015
m2
1
m2
1
m2
1
m2
1
m2
1
m2
1
MASONRY WORKS
6 C-C1, 7 C-C1, 8 C-C1
SCAFFOLDING
6/25/2015
8/7/2015
7/17/2015
7/31/2015
7/6/2015
7/18/2015
8/1/2015
7/7/2015
7/17/2015
7/31/2015
7/6/2015
7/24/2015
8/7/2015
7/28/2015
6/25/2015
7/5/2015
7/5/2015
HOLLOW BRICK WALL T150 mm (M
7
6/26/2015
7/7/2015
7/7/2015
3 A-B, 3 B-C, A 3-4, A 4-5, A 5-6, A 6-7, A 7-8, A 8-9, A 9-10, 10 A-B, 10 B-C
CERAMIC BRICK WALL T250 mm
14
7/3/2015
4
7/29/2015
7/5/2015
6/25/2015
7/4/2015
7/5/2015
7/2/2015
7/6/2015
7/16/2015
1
1
7
7
44
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Task
--1
m2
22
Plan
Forecast
Actual
Plan
Forecast
Actual
B 3-4, 4 A-B
SCAFFOLDING
WATERPROOFING WORKS
1-3 / A-D
--1
m2
10
7/16/2015
8/1/2015
7/28/2015
23
Plan
Forecast
Actual
7/16/2015
8/24/2015
40
Task
7/16/2015
7/15/2015
7/20/2015
7/18/2015
7/16/2015
7/19/2015
7/21/2015
8/19/2015
SHEET-APPLIED MEMBRANE
4
4
7/16/2015
7/16/2015
7/20/2015
7/17/2015
7/17/2015
7/19/2015
7/18/2015
8/16/2015
RIGID INSULATION
4
4
7/19/2015
8/17/2015
7/22/2015
8/20/2015
1
1
7/22/2015
8/20/2015
7/22/2015
8/20/2015
7/23/2015
7/25/2015
m2
Plan
Forecast
Actual
Plan
Forecast
Actual
m2
1
--1
m2
1
m2
1
m2
1
m2
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
LAST WEEK
29-6
30-6
1-7
2-7
3-7
4-7
5-7
CURRENT WEEK
6-7
7-7
8-7
9-7
10-7
11-7
###
16-7
17-7
18-7
8/21/2015
8/23/2015
1
PROTECTED CONCRETE
1
1
7/26/2015
8/23/2015
7/26/2015
8/23/2015
EXPANSION JOINT
1
1
7/27/2015
8/24/2015
7/27/2015
8/24/2015
CONTROL JOINT
1
1
7/27/2015
8/24/2015
7/27/2015
8/24/2015
m2
1
ml
1
ml
1
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
3-10 / A-C
CEMENT MORTAR BEVEL
1
1
7/28/2015
7/16/2015
7/21/2015
7/29/2015
7/17/2015
7/19/2015
7/30/2015
7/28/2015
7/23/2015
7/31/2015
7/29/2015
7/28/2015
8/7/2015
8/7/2015
7/28/2015
7/15/2015
7/22/2015
8/1/2015
7/16/2015
7/19/2015
8/6/2015
7/30/2015
7/27/2015
8/7/2015
8/4/2015
7/28/2015
8/7/2015
8/7/2015
SHEET-APPLIED MEMBRANE
8
3
RIGID INSULATION
8
7
6
6
8/8/2015
8/8/2015
8/13/2015
8/13/2015
PROTECTED CONCRETE
1
1
8/14/2015
8/14/2015
8/14/2015
8/14/2015
EXPANSION JOINT
1
1
8/15/2015
8/15/2015
8/15/2015
8/15/2015
CONTROL JOINT
1
1
8/15/2015
8/15/2015
8/15/2015
8/15/2015
m2
2
--1
m2
5
m2
1
m2
1
m2
1
m2
1
ml
1
ml
1
FINISHING WORKS
3-4 / B-C
SCAFFOLDING
CEMENT PLASTER
GYPSUM PARTITION
CEMENT PLASTER
GYPSUM PARTITION
21
4
PAINTING WORKS
3-4 / B-C
EMULSION PAINT (EXPOSED
4
4
7/3/2015
8/10/2015
7/3/2015
7/3/2015
7/18/2015
7/4/2015
7/4/2015
7/19/2015
7/18/2015
7/18/2015
7/20/2015
7/3/2015
7/2/2015
7/18/2015
7/7/2015
7/3/2015
7/27/2015
7/20/2015
7/17/2015
7/21/2015
7/18/2015
7/18/2015
7/18/2015
7/18/2015
7/29/2015
7/24/2015
7/21/2015
7/29/2015
7/22/2015
7/19/2015
7/17/2015
7/18/2015
7/20/2015
7/30/2015
7/28/2015
8/10/2015
8/1/2015
7/28/2015
6/19/2015
9/6/2015
6/19/2015
6/19/2015
6/22/2015
6/22/2015
39
Task
m2
1
m2
9
m2
2
m2
1
m2
5
m2
7
80
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Task
m2
1
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
4
4
7/26/2015
7/26/2015
7/29/2015
7/29/2015
3
3
7/30/2015
7/30/2015
8/1/2015
8/1/2015
2
2
8/2/2015
8/2/2015
8/3/2015
8/3/2015
2
2
8/2/2015
8/2/2015
8/3/2015
8/3/2015
3
3
8/4/2015
8/4/2015
8/6/2015
8/6/2015
m2
1
m2
1
m2
1
m2
1
m2
1
7
7
6/23/2015
6/23/2015
6/29/2015
6/29/2015
3
3
8/11/2015
8/11/2015
8/13/2015
8/13/2015
14
14
8/14/2015
8/14/2015
8/27/2015
8/27/2015
2
2
8/29/2015
8/29/2015
8/30/2015
8/30/2015
m2
1
m2
1
m2
1
ENAMEL PAINT
m2
1
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
1-3 / A-D
EMULSION PAINT (GYPSUM)
ENAMEL PAINT
2
2
6/30/2015
6/30/2015
6/30/2015
9/5/2015
9/5/2015
7/6/2015
6/29/2015
7/3/2015
9/6/2015
9/6/2015
m2
4
m2
1
7
7
8/2/2015
8/2/2015
7/13/2015
8/8/2015
8/8/2015
7/24/2015
8/9/2015
8/9/2015
7/3/2015
8/10/2015
8/10/2015
7/5/2015
8/10/2015
8/10/2015
7/7/2015
8/15/2015
8/15/2015
8/9/2015
8/9/2015
7/4/2015
8/12/2015
8/12/2015
7/6/2015
8/14/2015
8/14/2015
7/10/2015
8/15/2015
8/15/2015
Plan
Forecast
Actual
Plan
Forecast
Actual
m2
Plan
Forecast
Actual
m2
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
11
3-4 / A-B
EMULSION PAINT (EXPOSED
1
1
3
3
5
5
ENAMEL PAINT
1
1
2
m2
2
m2
4
m2
1
UREA
STOOP
A 3-4
LEVELING & COMPACTION
1
1
7/16/2015
8/20/2015
7/16/2015
8/20/2015
LAYING PE FILM
1
1
7/17/2015
8/21/2015
7/17/2015
8/21/2015
FORM PLYWOOD 3T
1
1
7/17/2015
8/21/2015
7/17/2015
8/21/2015
1
1
7/18/2015
8/22/2015
7/18/2015
8/22/2015
m2
1
m2
1
m2
1
m2
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
1
STRUCTURAL CONCRETE (ST
1
1
7/19/2015
8/23/2015
7/19/2015
8/23/2015
EXPANSION JOINT/CAULKING
1
1
7/20/2015
8/24/2015
7/20/2015
8/24/2015
m2
1
m2
1
MASONRY WORKS
7 C-D, 8 C-D, 9 C-D, 10 C-D, 11 C-D
SCAFFOLDING
7/16/2015
8/17/2015
1
1
7/25/2015
8/8/2015
7/25/2015
8/8/2015
9
9
7/26/2015
8/9/2015
8/3/2015
8/17/2015
SCAFFOLDING
7/18/2015
7/18/2015
7/16/2015
HOLLOW BRICK WALL ELEVATI
7
7/19/2015
7/19/2015
7/17/2015
12 A-B, 12 B-C, A 11-12, A 10-11, A 9-10, A 8-9, A 7-8, A 6-7, A 5-6, A 4-5
CERAMIC BRICK WALL ELEVAT
14
7/19/2015
10
7/29/2015
7/18/2015
4 A-B, 4 B-C, C 4-5, C 5-6, C 6-7, C 7-8, C 8-9, C 9-10, C 10-11, C 11-12
CERAMIC BRICK WALL ELEVAT
14
8/2/2015
8
7/29/2015
7/16/2015
7/18/2015
7/17/2015
7/16/2015
7/25/2015
7/18/2015
7/28/2015
33
Task
---
B 4-5, 5 B-C
m2
1
8/1/2015
8/7/2015
7/28/2015
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
--1
m2
12
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
m2
Plan
Forecast
Actual
m2
11
8/15/2015
8/5/2015
7/28/2015
13
Plan
Forecast
Actual
8/8/2015
9/15/2015
39
Task
1
1
8/8/2015
8/16/2015
8/8/2015
8/16/2015
2
2
8/9/2015
8/17/2015
8/10/2015
8/18/2015
SHEET-APPLIED MEMBRANE
4
4
8/10/2015
8/18/2015
8/13/2015
8/21/2015
RIGID INSULATION
4
4
8/11/2015
8/19/2015
8/14/2015
8/22/2015
1
1
8/14/2015
8/22/2015
8/14/2015
8/22/2015
3
3
8/16/2015
8/23/2015
8/18/2015
8/25/2015
PROTECTED CONCRETE
1
1
8/19/2015
8/26/2015
8/19/2015
8/26/2015
EXPANSION JOINT
1
1
8/20/2015
8/27/2015
8/20/2015
8/27/2015
CONTROL JOINT
1
1
8/20/2015
8/27/2015
8/20/2015
8/27/2015
m2
1
--1
m2
1
m2
1
m2
1
m2
1
m2
1
ml
1
ml
1
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
4-12 / A-C
CEMENT MORTAR BEVEL
1
1
8/21/2015
8/28/2015
8/21/2015
8/28/2015
4
4
8/22/2015
8/29/2015
8/25/2015
9/1/2015
m2
1
--1
Plan
Forecast
Actual
Plan
Forecast
Actual
SHEET-APPLIED MEMBRANE
8
8
8/23/2015
8/30/2015
8/30/2015
9/6/2015
RIGID INSULATION
8
8
8/24/2015
8/31/2015
8/31/2015
9/7/2015
1
1
8/31/2015
9/7/2015
8/31/2015
9/7/2015
6
6
9/1/2015
9/8/2015
9/6/2015
9/13/2015
PROTECTED CONCRETE
1
1
9/7/2015
9/14/2015
9/7/2015
9/14/2015
EXPANSION JOINT
1
1
9/8/2015
9/15/2015
9/8/2015
9/15/2015
CONTROL JOINT
1
1
9/8/2015
9/15/2015
9/8/2015
9/15/2015
m2
1
m2
1
m2
1
m2
1
m2
1
ml
1
ml
1
FINISHING WORKS
3-4 / B-C
7/26/2015
9/8/2015
SCAFFOLDING
1
1
7/26/2015
7/26/2015
7/26/2015
7/26/2015
CEMENT PLASTER
4
4
7/27/2015
7/27/2015
7/30/2015
7/30/2015
GYPSUM PARTITION
3
3
8/11/2015
8/11/2015
8/13/2015
8/13/2015
45
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Task
--1
m2
1
m2
1
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
3-10 / A-C
SCAFFOLDING
2
2
8/14/2015
8/14/2015
8/15/2015
8/15/2015
CEMENT PLASTER
3
3
8/16/2015
8/16/2015
8/18/2015
8/18/2015
21
21
8/19/2015
8/19/2015
9/8/2015
9/8/2015
--1
m2
1
GYPSUM PARTITION
m2
1
PAINTING WORKS
3-4 / B-C
7/4/2015
9/28/2015
7/10/2015
7/6/2015
7/7/2015
8/19/2015
8/19/2015
4
4
7/7/2015
7/7/2015
7/4/2015
8/16/2015
8/16/2015
3
3
8/16/2015
8/16/2015
8/18/2015
8/18/2015
2
2
8/20/2015
8/20/2015
8/21/2015
8/21/2015
2
2
8/20/2015
8/20/2015
8/21/2015
8/21/2015
3
3
8/22/2015
8/22/2015
8/24/2015
8/24/2015
87
Task
m2
4
m2
1
m2
1
m2
1
m2
1
m2
1
7/11/2015
7/11/2015
7/17/2015
7/10/2015
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
m2
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
3
3
7/7/2015
9/10/2015
9/10/2015
7/14/2015
9/12/2015
9/12/2015
14
14
9/13/2015
9/13/2015
9/26/2015
9/26/2015
2
2
9/27/2015
9/27/2015
9/28/2015
9/28/2015
8
m2
1
m2
1
ENAMEL PAINT
m2
1
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
1-3 / A-D
EMULSION PAINT (GYPSUM)
7
7
7/19/2015
8/3/2015
7/25/2015
8/9/2015
ENAMEL PAINT
2
2
9/19/2015
9/19/2015
9/20/2015
9/20/2015
m2
1
m2
1
7
7
8/20/2015
8/20/2015
8/26/2015
8/26/2015
Plan
Forecast
Actual
Plan
Forecast
Actual
m2
Plan
Forecast
Actual
m2
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
Plan
Forecast
Actual
1
3-4 / A-B
EMULSION PAINT (EXPOSED
ENAMEL PAINT
1
1
8/27/2015
8/27/2015
7/18/2015
8/28/2015
8/28/2015
8/27/2015
8/26/2015
7/19/2015
8/30/2015
8/27/2015
8/28/2015
8/28/2015
7/20/2015
9/2/2015
9/2/2015
9/1/2015
8/27/2015
7/23/2015
9/2/2015
9/2/2015
2
m2
1
m2
4
m2
1
###
23-7
24-7
25-7
###
27-7
28-7
29-7
30-7
31-7
1-8
2-8
3-8
4-8
5-8
6-8
7-8
8-8
9-8
10-8
11-8
12-8
13-8
14-8
15-8
###
17-8
18-8
19-8
20-8
21-8
22-8
###
24-8
25-8
26-8
27-8
28-8
29-8
###
31-8
1-9
2-9
3-9
4-9
5-9
6-9
7-9
8-9
9-9
10-9
11-9
12-9
###
14-9
15-9
16-9
17-9
18-9
19-9
###
21-9
22-9
23-9
24-9
25-9
26-9
###
28-9
29-9
30-9