Obra: Projeto residencial padro CAIXA 42m

ITEM REF
CDIGO
DESCRIO
1
SERVIOS PRELIMINARES
1.1
PREPARO DO TERRENO
SETOP
PRE-LIM-005 LIMPEZA DO TERRENO, CAPINA E QUEIMA
1.2
SONDAGEM
SONDAGEM A PERCUSSO D = 2 1/2" COM MEDIDA DE SPT (FATURAMENTO MNIMO
SETOP
SON-SPT-010 = 30 M)
MOBILIZAO E DESMOBILIZAO POR EQUIPAMENTO DE SONDAGEM A
SETOP
SON-SPT-005 PERCUSSO D = 2 1/2"
1.3
LOCAO DA OBRA
SETOP
LOC-OBR-005 LOCAO DA OBRA (GABARITO)
2
ADMINISTRAO LOCAL
2.1
MO DE OBRA LOCAL
SETOP
ADM-EST-005 ESTAGIRIO DE ENGENHARIA (COM LEIS SOCIAIS)
SETOP
ADM-TEC-005 TCNICO DE EDIFICAES
SETOP
ADM-VIG-005 VIGIA OU SEGURANA (1X)
2.2
EQUIPAMENTOS
SETOP
EQU-BET-010
BETONEIRA SEM CARREGADOR B-320 COM MOTOR ELETRICO MONOFSICO
SETOP
EQU-FUR-005 FURADEIRA DE IMPACTO 1/2"
SERRA CIRCULAR COM MOTOR ELTRICO MONOFSICO, INCLUSIVE MESA, DISCO
E COIFA
COMPOSIO 1
2.3
EQUIPAMENTOS DE PROTEO INDIVIDUAL
COMPOSIO 2
Consumo de EPI - obra
2.4
FERRAMENTAS
COMPOSIO 3
Consumo de ferramentas - obra
2.5
MVEIS E UTENSLIOS
COMPOSIO 4
Despesa mensal com mveis e utenslios
2.6
DESPESAS GERAIS
COMPOSIO 5
Despesas gerais - mensal
3
CANTEIRO DE OBRAS
3.1
REAS DE VIVNCIA
BARRACO INSTALAO SANITRIA TIPO I, A = 14,52 M2 (OBRA DE PEQUENO
SETOP
IIO-BAR-025 PORTE, EFETIVO AT 30 HOMENS) - PADRO DEOP

SETOP

IIO-BAR-015

BARRACO DEPSITO E FERRAMENTARIA TIPO I, A = 14,52 m2 (OBRA DE


PEQUENO PORTE, EFETIVO AT 30 HOMENS) - PADRO DEOP
ESCRITRIO DA FISCALIZAO TIPO I, A = 18,15 M2 (OBRA DE PEQUENO A MDIO
PORTE, EFETIVO AT 60 HOMENS, DE CURTA A MDIA DURAO) - PADRO DEOP

SETOP
IIO-ESC-005
3.2
INSTALAES PROVISRIAS
SETOP
IIO-LIG-010 LIGAO PROVISRIA DE LUZ E FORA-PADRO PROVISRIO 30KVA
SETOP
IIO-LIG-015 LIGAO PROVISRIA DE GUA E ESGOTO
SETOP
IIO-TAP-005 TAPUME EM CHAPA COMPENSADO DE 12 MM E PONTALETES H = 2,20 M
SETOP
INC-EXT-010 EXTINTOR DE INCNDIO GUA PRESSURIZADA 2-A, CAPACIDADE 10L
SETOP
INC-EXT-015 EXTINTOR DE INCNDIO TIPO P QUMICO 20-B:C, CAPACIDADE 6 KG
SETOP
INC-EXT-025 BASE DECORATIVA PARA EXTINTORES
SETOP
INC-EXT-025 BASE DECORATIVA PARA EXTINTORES
3.3
MONTAGEM DE ANDAIMES
SETOP
AND-FAC-005 FORNECIMENTO DE ANDAIME METLICO PARA FACHADA
MONTAGEM E DESMONTAGEM DE ANDAIME METLICO PARA FACHADA, INCLUSIVE
SETOP
AND-FAC-010 ASSOALHO, RODAP E GUARDA-CORPO
CONSTRUO/MONTAGEM E DESMONTAGEM DE ANDAIME PARA REVESTIMENTO
SETOP
AND-FOR-005 INTERNO DE FORROS
4
MOVIMENTO DE TERRA
4.1
SERVIO DE TERRAPLENAGEM

SETOP
TER-API-005 APILOAMENTO DO FUNDO DE VALAS COM SOQUETE
SETOP
TER-ESC-035 ESCAVAO MANUAL DE VALAS H <= 1,50 M
SETOP
TER-REA-005 REATERRO COMPACTADO DE VALA MANUAL
4.2
TRANSPORTES
TRANSPORTE DE MATERIAL DE QUALQUER NATUREZA EM CAMINHO DMT > 5 KM
SETOP
TRA-CAM-020 (DENTRO DO PERMETRO URBANO)
SETOP
IIO-LIG-015 CARGA DE MATERIAL DE QUALQUER NATUREZA SOBRE CAMINHO - MANUAL
Retirada de entulho de obra em cacamba de aco com 5m3 de capacidade, inclusive
SCO-RIO
TC 05.15.0100 carregamento do container, transporte e descarga e tarifa de disposicao final.

Data base

Feb-13
PREO
TOTAL
2,227.17

UN

QUANT

UNIT

200.00

2.21

442.00

20.00

49.44

988.80

vb

1.00

618.00

618.00

41.87

4.26

178.37
79,156.07

ms
ms
ms

4.00
6.00
12.00

2,370.44
2,370.44
1,679.16

ms
ms

2.00
0.50

127.03
72.10

254.06
36.05

ms

3.00

672.08

2,016.24

R$

1.00

866.78

866.78

R$

6.00

1,994.77

11,968.62

ms

6.00

1,500.00

9,000.00

ms

6.00

1,860.00

11,160.00
12,495.80

un

1.00

5,736.14

5,736.14

UND

1.00

3,972.67

3,972.67

UND

1.00

UND
UND
m
UND
UND
UND
UND

1.00
1.00
10.50
1.00
1.00
2.00
2.00

m/ms

780.78

3,97

3,099.70

130.13

4,88

635.03

145.00

5.677,42
1,009.83
430.70
93.99
119.85
128.07
27,91
27,91

4.94

9,481.76
14,222.64
20,149.92

5.677,42
1,009.83
430.70
986.90
119.85
128.07
#VALUE!
#VALUE!

716.30
3,435.94

m
m
m

25.81
7.49
6.22

8.47
25.78
25.04

218.61
193.09
155.75

m x km
m

10.68
1.78

1.06
14.73

11.32
26.22

45.00

62.91

2,830.95

VALOR TOTAL DA OBRA R$

97,314.97

COMPOSIO 1: SERRA CIRCULAR COM MOTOR ELTRICO MONOFSICO,


INCLUSIVE MESA, DISCO E COIFA (MS)
Quant
Preo Unittotal c/ bdi
EQU-SER-010 Serra circular com mesa
und
1.00
136.48
136.48
FER-DIS-015 Disco p/ serra circular
und
1.00
154.50
154.50
EPI-COI-005 Coifa p/ serra circular
und
1.00
381.10
381.10
TOTAL DO SERVIO
672.08
COMPOSIO 4: MVEIS E UTENSLIOS (MS)

Revista
Construo
Mercado

Imvel
Mobilirio
Equipamentos de
informtica

und
und
und

Quant
Preo Unittotal c/ bdi
1.00 1,000.00 1,000.00
1.00
200.00
200.00
1.00

300.00

300.00

TOTAL DO SERVIO

1,500.00

COMPOSIO 5: DESPESAS GERAIS (MS)

Revista
Construo
Mercado

Limpeza e higiene
Material de escritrio
Energia eltrica
gua e esgoto
Telefone

und
und
und
und
und

Quant
Preo Unittotal c/ bdi
1.00
250.00
250.00
1.00
300.00
300.00
1.00
270.00
270.00
1.00
150.00
150.00
1.00
890.00
890.00
TOTAL DO SERVIO 1,860.00

COMPOSIO 2: Consumo de Equipamentos de Proteo Individual para a obra


Bota
Bota Capa de
Cinto de
Luvas
M. O.
QUANT. borracha couro
chuva Capacete Farda segurana borracha
Pedreiro
2
2
2
2
1
4
Carpinteiro
1
1
1
1
1
1
Armador
1
1
1
1
Pintor
1
1
1
1
Ajudante
2
1
2
1
2
2
2
Total
7
1
7
2
7
7
2
6
Preos unit.
32.58 24.67
13.39
9.96
30.9
41.38
2.54
Preo total
0.00
32.58 172.69
26.78
69.72 216.30
82.76
15.24
TOTAL: R$
866.78
1 Preos SETOP/MG

Luvas
raspa
2
2
2
6
8.99
53.94

culos
2
1
1
1
2
7
12.36
86.52

COMPOSIO 3: Ferramentas de uso em obra


M. O.
QUANT. Alicate Brocha
Pedreiro
2
2
1
Carpinteiro
1
1
Armador
1
1
Pintor
1
2
Ajudante
2
1
1
Total
7
5
4
Preos unit.
29.59
9.81
Preo total
147.95 39.24
TOTAL: R$
1,994.77

Caixa

Carrinho
2
1
1
1
1
2
5
3
34.12
224.09
170.60
672.27

Chave
fenda

Disco de Desempecorte
nadeira Esquadro Martelo
3
2
4
2
2
1
1
1
1
1
1
1
1
4
4
5
4
4
4.51
72.39
12.93
25.26
19.08
18.04
289.56
64.65
101.04
76.32

1 Preos SETOP/MG

Protetor
Mscara auricular
6
2
3
1
3
1
3
1
6
2
21
7
2.16
9.27
45.36
64.89

Nvel

P
2
1

3
5.9
17.70

2
3
17.77
53.31

Rgua Talhadeira Trena


3
1
2
1
1
1
1
1
1
1
4
4
5
31.93
7.23 37.49
127.72
28.92 187.45