Estimation of Running Track ( Hostel )

S. No. Item
102 Jungle clearance including uprooting of rank
vegetation, grass, brush wood, saplings and tree
not exceeding 30cm girth and removing not
exceeding 50meters outside the periphery of
the area cleared.
Site clearing
1201 Rammed moorum flooring

Nos. L

D/H

Qty

Unit

Rate

Amount

190

63

11970 m2

7.4

88578

190

63

11970 m2

7.4

88578

506

0.3

455.4 m3

247.9

112893.66

506

2.5

1265 m2

586

741290

2560 Providing and laying 60 mm thick factory made


cement concrete interlocking paver block of
M-30 grade made by block making machine with
strong vibratory compaction and of approved
size and shape laid in required colour and pattern
over and including 50 mm thick compacted bed
of course sand filling the joints with sand etc.

Total =
20 % above tender rate =
1 % for labour welfare =
3.5 % for contingencies=
Gross Total =

201471.66
40294.33
2014.72
7051.51
250832.22
Say 11.73 lacs