Вы находитесь на странице: 1из 111

BUILDING CIVIL

STANDARD NOTES &


DETAILS

ADELAIDE CITY
COUNCIL
DETAILS:

BITUMEN PAVING HARDWOOD EDGING


CATCH PIT - INVERT DRAIN
CATCH PIT - KERB AND WATERTABLE
CHECKER PLATE DRAIN (1)
CHECKER PLATE DRAIN (2)
DRIVEWAY CROSSOVER
INVERT DRAIN - 450mm
INVERT DRAIN - 600mm
KERB
KERB AND WATERTABLE
KERB MEDIAN
KERB RAMP
PROPERTY CONNECTION (1)
PROPERTY CONNECTION (2)
TACTILED CROSSOVER

75

HARDWOOD.
75mm WIDE x 25mm THICK
1200 CENTRES

25

8mm BOLT GALVANISED

7mm AGGREGATE ASPHALTIC


CONCRETE

300 MIN.

150

GRASS

100mm TAPER
HARDWOOD.
75mm WIDE x 25mm THICK

PM1 FINE CRUSHED ROCK


(98% MODIFIED COMPACTION)
SUBGRADE (100% STANDARD
COMPACTION)

BITUMEN PAVING HARDWOOD EDGING


1:10

10/08/11

JAS

FRAME DEPTH
PLUS BEDDING

FOR FABRIC
REINFORCEMENT
TYPE SEE TABLE

150

CATCHPIT INVERT TO
EQUAL PIPE INVERT

150

FABRIC REINFORCEMENT
CENTRALLY PLACED

500

DEPTH

REINFORCEMENT

00-1000
1001-3000
1301-1600
1601-1900
>1900

F62
F82
F92
F102
DESIGN

150

800

550

INVERT CATCHPIT
FRAME AND GRATE
1

LUGS

NOTES:
1.

MINIMUM CONCRETE
COMPRESSIVE STRENGTH
(f'c=MPa).

2.

REINFORCEMENT MESH TO BE
PLACED CENTRALLY. COVER
50mm TYPICAL

150

850

150

SECTION 1

TYPICAL CONCRETE PIPE

PLAN
CATCH PIT
INVERT DRAIN
1:20

10/08/11

JAS

CATCHPIT FRAME AND


GRATE (SLOPE TO MATCH
CONCRETE WATERTABLE)

DE
BK SIGN
LE
VE
L

LINTEL

FRAME DEPTH
PLUS BEDDING

75

150

STANDARD KERB
HEIGHT 100, 140 & 200

NOTES:

100mm MIN
CONCRETE BANDAGE

FOR FABRIC
REINFORCEMENT
TYPE SEE TABLE

150

CATCHPIT INVERT TO
EQUAL PIPE INVERT

150 150

FABRIC REINFORCEMENT
CENTRALLY PLACED

500

1.

MINIMUM CONCRETE
COMPRESSIVE STRENGTH
(f'c=MPa).

2.

REINFORCEMENT MESH TO BE
PLACED CENTRALLY. COVER
50mm TYPICAL

150

800

SECTION 1

SECTION 2

550

LUGS

150

850

150

TYPICAL REINFORCED
CONCRETE PIPE

CATCHPIT FRAME
AND GRATE

LINTEL

DEPTH

REINFORCEMENT

00-1000
1001-3000
1301-1600
1601-1900
>1900

F62
F82
F92
F102
DESIGN

PLAN
CATCH PIT

KERB AND WATERTABLE


1:20

10/08/11

JAS

CHECKER PLATE DRAIN.


REFER NOTES 4 AND 5

90

MINIMUM 600mm
MINUS 20mm

VERANDAH POST WITH


INTERNAL STORMWATER PIPE
PLACE ACCESS LID IN
FRONT OF DOWNPIE

STREET PROPERTY
BOUNDARY

VERANDAH

STREET PROPERTY
BOUNDARY

POST
KERB FACE

DRAIN PIPE TYPE TO BE SEALED


AT C.P.D JUNCTION

50mm (APPROX) THICK


SAND/CEMENT BASE

SQUARE ACCESS LID WITH


10mm LIFTING HOLE IN THE
CENTRE

REFER NOTE 3
FINISHED FOOTPATH LEVEL.
REFER NOTE 2

EQUAL TO KERB DEPTH


COVER SUPPORT 16mm PLAIN
ROD WELDED TO C.P.D. FOR FULL
LENGTH OF LID.
REFER NOTE 5

SECTION A-A

CHECKER PLATE DRAIN


NTS

NOTES:
1. CHECKER PLATE DRAIN (C.P.D.) TO BE CONSTRUCTED OF 6mm THICK STEEL PLATE WITH
STEEL CHECKER PLATE TOP ALL FULLY WELDED AND HOT DIPPED GALVANISED.
2. TOP OF C.P.D. AND CHECKER PLATE ACCESS LID TO BE FLUSH WITH FOOTPATH
SURFACE.
3. ANY C.P.D. WIDER THAN 300mm TO BE PROVIDED WITH AN INTERNAL STIFFENER,
PLACED CENTRALLY AND FULLY WELDED.
4. ALL C.P.D.'S TO BE INSTALLED PERPENDICULAR TO THE STREET PROPERTY BOUNDARY.
5. WIDTH DIMENSION TO BE EQUAL TO EXISTING C.P.D. OR SIMILAR X-SECTIONAL AREA OF
EXISTING PIPE, BUT NOT LESS THAN MINIMUM WIDTH.
6. C.P.D. MINIMUM WIDTH 150mm.

10/08/11

JAS

90

CHECKER PLATE DRAIN.


REFER NOTES 4 AND 5

STREET PROPERTY
BOUNDARY

LENGTH EQUAL TO FOOTPATH


WIDTH MINUS 20mm

PROPERTY BOUNDARY

KERB FACE

USE L-SHAPED CHECKER PLATE


DRAIN TO AVOID SERVICE COVERS,
POSTS NAD DRIVEWAYS

1000

REFER NOTE 3

STREET PROPERTY
BOUNDARY

CROSSING PLACE

20mm

50mm (APPROX) THICK


SAND/CEMENT BASE

DRAIN PIPE TYPE SITUATIONS TO


BE SEALED AT THE INTERNAL
PIPE AND C.P.D JUNCTION

CHECKER PLATE DRAIN


MUST STOP AT STREET
PROPERTY LINE

SQUARE ACCESS LID WITH


10mm LIFTING HOLE IN THE
CENTRE

REFER NOTE 3
FINISHED FOOTPATH LEVEL.
REFER NOTE 2

EQUAL TO KERB DEPTH


COVER SUPPORT 16mm PLAIN
ROD WELDED TO C.P.D. FOR FULL
LENGTH OF LID.
REFER NOTE 5

SECTION A-A

CHECKER PLATE DRAIN


NTS

NOTES:
1. CHECKER PLATE DRAIN (C.P.D.) TO BE CONSTRUCTED OF 6mm THICK STEEL PLATE WITH
STEEL CHECKER PLATE TOP ALL FULLY WELDED AND HOT DIPPED GALVANISED.
2. TOP OF C.P.D. AND CHECKER PLATE ACCESS LID TO BE FLUSH WITH FOOTPATH
SURFACE.
3. ANY C.P.D. WIDER THAN 300mm TO BE PROVIDED WITH A 500mm LONG INTERNAL
STIFFENER, FULLY WELDED PLACED CENTRALLY AT KERB AND AT 500mm INTERVALS.
4. ALL C.P.D.'S TO BE INSTALLED PERPENDICULAR TO THE STREET PROPERTY BOUNDARY
AND A MINIMUM OF 1.0m CLEAR OF ANY CROSSING PLACE.
5. WIDTH DIMENSION TO BE EQUAL TO EXISTING C.P.D. OR SIMILAR X-SECTIONAL AREA OF
EXISTING PIPE, BUT NOT LESS THAN MINIMUM WIDTH.
6. C.P.D. MINIMUM WIDTH 150mm.
7. L-SHAPED C.P.D. MUST BE IN THE FOOTPATH WITHIN THE PROPERTY BOUNDARY
ALIGNMENT DRAINING THAT PROPERTY.

10/08/11

JAS

600
150

450

5mm CHAMFER

300

40

40

5mm CHAMFER

REFER NOTE 3
REFER NOTE 1
REFER NOTE 2

DRIVEWAY CROSSOVER
1:10

NOTES:
1.

MINIMUM CONCRETE COMPRESSIVE STRENGTH


(f'c=32MPa).
BRIGHTON LITE OR EQUIVALENT TO BE USED WHEN
FULL LENGTH OF KERBING IS CONSTRUCTED

2.

RF11TM FABRIC REINFORCED MESH, WITH 50mm COVER.

3.

4-Y12 DOWELS, 300 LONG AT CONSTRUCTION JOINTS


WHERE JOINING INTO EXISTING WATERTABLE AND
EVERY 4.0 METERS. CRACK JOINTS AS PER CONCRETE
CODE.

BED: 100mm THICK, 20mm QUARRY RUBBLE TO PM21,


COMPACTED TO 98% MMDD.

10/08/11

JAS

450
225

225

5mm CHAMFER

300

35

5mm CHAMFER

REFER NOTE 3
REFER NOTE 1
REFER NOTE 2

INVERT DRAIN
450mm
1:10

NOTES:
1.

MINIMUM CONCRETE COMPRESSIVE STRENGTH


(f'c=32MPa).
BRIGHTON LITE OR EQUIVALENT TO BE USED WHEN
FULL LENGTH OF KERBING IS CONSTRUCTED

2.

RF11TM FABRIC REINFORCED MESH, WITH 50mm COVER.

3.

4-Y12 DOWELS, 300 LONG AT CONSTRUCTION JOINTS


WHERE JOINING INTO EXISTING WATERTABLE AND
EVERY 4.0 METERS. CRACK JOINTS AS PER CONCRETE
CODE.

BED: 100mm THICK, 20mm QUARRY RUBBLE TO PM21,


COMPACTED TO 98% MMDD.

10/08/11

JAS

600
300

300

5mm CHAMFER

300

40

5mm CHAMFER

REFER NOTE 3
REFER NOTE 1
REFER NOTE 2

INVERT DRAIN
600mm
1:10

NOTES:
1.

MINIMUM CONCRETE COMPRESSIVE STRENGTH


(f'c=32MPa).
BRIGHTON LITE OR EQUIVALENT TO BE USED WHEN
FULL LENGTH OF KERBING IS CONSTRUCTED

2.

RF11TM FABRIC REINFORCED MESH, WITH 50mm COVER.

3.

4-Y12 DOWELS, 300 LONG AT CONSTRUCTION JOINTS


WHERE JOINING INTO EXISTING WATERTABLE AND
EVERY 4.0 METERS. CRACK JOINTS AS PER CONCRETE
CODE.

BED: 100mm THICK, 20mm QUARRY RUBBLE TO PM21,


COMPACTED TO 98% MMDD.

10/08/11

JAS

5mm CHAMFER

150
25mm CHAMFER

FOOTPATH
REFER NOTE 3
CARRIAGEWAY

REFER NOTE 1

100mm
OR
140mm
OR
200mm

50 COVER

300

REFER NOTE 2

KERB
1:10

NOTES:
1.

MINIMUM CONCRETE COMPRESSIVE STRENGTH


(f'c=32MPa).
BRIGHTON LITE OR EQUIVALENT TO BE USED WHEN
FULL LENGTH OF KERBING IS CONSTRUCTED

2.

RF11TM FABRIC REINFORCED MESH, WITH 50mm COVER.

3.

4-Y12 DOWELS, 300 LONG AT CONSTRUCTION JOINTS


WHERE JOINING INTO EXISTING WATERTABLE AND
EVERY 4.0 METERS. CRACK JOINTS AS PER CONCRETE
CODE.

BED: 100mm THICK, 20mm QUARRY RUBBLE TO PM21,


COMPACTED TO 98% MMDD.

10/08/11

JAS

150

5
FALL

KERB HEIGHT
100 OR 140 OR 200

600

5mm
CHAMFER

450
25mm CHAMFER

5mm CHAMFER

300

40

15mm CHAMFER

REFER NOTE 3
REFER NOTE 1
REFER NOTE 2

KERB AND WATERTABLE


1:10

NOTES:
1.

MINIMUM CONCRETE COMPRESSIVE STRENGTH


(f'c=32MPa).
BRIGHTON LITE OR EQUIVALENT TO BE USED WHEN
FULL LENGTH OF KERBING IS CONSTRUCTED

2.

RF11TM FABRIC REINFORCED MESH, WITH 50mm COVER.

3.

4-Y12 DOWELS, 300 LONG AT CONSTRUCTION JOINTS


WHERE JOINING INTO EXISTING WATERTABLE AND
EVERY 4.0 METERS. CRACK JOINTS AS PER CONCRETE
CODE.

BED: 100mm THICK, 20mm QUARRY RUBBLE TO PM21,


COMPACTED TO 98% MMDD.

10/08/11

JAS

50

VARIOUS MEDIAN INFILL

150

50

R25
EXISTING ROAD SURFACE

KERB MEDIAN
1:10

NOTES:
1.

MINIMUM CONCRETE COMPRESSIVE STRENGTH 32MPa


(f'c=MPa).

2.

BRIGHTON LITE OR EQUIVALENT TO BE USED WHEN


FULL LENGTH OF MEDIAN IS CONSTRUCTED.

10/08/11

JAS

1200 NOMINAL

A
LENGTH OF RAMP:
900mm MIN. TO 1520mm MAX
1200mm FOR 100mm HIGH KERB
1500mm FOR 140mm HIGH KERB

45

45

600mm TACTILE

300mm CLEARANCE

KERB FACE

BRIGHTON LITE OR EQUIVALENT TO BE


USED (NO REINFORCEMENT) MINIMUM
CONCRETE COMPRESSIVE STRENGTH
f'c=32MPa.
BROOM SURFACE FINISH

FOOTPATH
CROSSFALL
150

SHARP TRANSITION WITH


NO LIP AT WATERTABLE

SHARP TRANSITION
AT MEET POINT
WITH FOOTPATH

RAMP GRADIENT
1:8 MAX
100mm THICK, 20mm QUARRY
RUBBLE TO PM21, COMPACTED
TO 98% MMDD.

TACTILE TYPE B INDICATOR.


COLOUR: GREY
REFER TO AS 1428.4-1992.
DO NOT USE METAL TACTILES

SECTION A-A
SHARP TRANSITION
BETWEEN RAMPS
AND SLOPING SIDES

KERB RAMP
NTS

NOTES:
1. KERB RAMP SHOULD BE LAID IN THE DIRECTION
OF TRAVEL ACROSS THE ROAD ALIGNED WITH THE
KERB RAMP ON THE FAR SIDE.
2. IT IS DESIRABLE THAT THE KERB RAMP AND
SLOOPING SIDES BE KEPT FREE OF PENETRATIONS
(ie. SERVICE COVERS), IF UNAVOIDABLE, THE
COVERS MUST BE SLIP RESISTANT.

10/08/11

JAS

STREET PROPERTY
BOUNDARY

REFER DETAIL A
REINFORCED CONCRETE PIPE,
MINIMUM SIZE 150 DIAMETER.
(uPVC AND OTHER MATERIALS
NOT PERMITTED)

200 MIN COVER FOR THE


FULL LENGTH OF RCP

250 SQ.

PIPE
100 MINIMUM CONCRETE
BANDAGE
100 MINIMUM FALL

OUTLET PIPE INVERT MUST BE


EQUAL TO SUMP INVERT LEVEL

PIPE TO BE CONNECTED INTO TOP


HALF OF THE STORMWATER PIIPE
AND FLUSH WITH INTERNAL WALL

MAIN STORMWATER
PIPE

INSTALL JUNCTION CHAMBER IF


THE DIAMETER OF THE PROPOSED
CONNECTION PIPE IS EQUAL TO
OR GREATER THAN HALF THE
DIAMETER OF THE
CORPORATIONS STORMWATER
PIPE

300x300x6mm THICK CHECKER


PLATE COVER WITH 10mm
LIFTING HOLE IN THE CENTRE

FINISHED FOOTPATH LEVEL

COVER SUPPORT 16mm PLAIN


ROD, 35mm LONG WELDED TO
ANGLE AT CORNERS OF FRAME

FRAME 25x25x3mm MILD


STEEL ANGLE
SUMP WALL (INSITU
CONCRETE OR BRICK)

75 MIN.

MINIMUM 25mm FIXINGS LUGS OR


DYNABOLT IN EACH CORNER

DETAIL A

PROPERTY CONNECTION
NTS

10/08/11

JAS

STREET PROPERTY
BOUNDARY

REFER DETAIL A
200 MIN COVER FOR THE
FULL LENGTH OF RCP

REINFORCED CONCRETE PIPE,


MINIMUM SIZE 150 DIAMETER.
(uPVC AND OTHER MATERIALS
NOT PERMITTED)

250 SQ.

PIPE

100 MINIMUM CONCRETE


BANDAGE

100 MINIMUM FALL

OUTLET PIPE INVERT MUST BE


EQUAL TO SUMP INVERT LEVEL

CATCHPIT

POSSIBLE EXISTING WET SUMP


TYPE CATCHPIT

300x300x6mm THICK CHECKER


PLATE COVER (HOT DIPPED
GALVANISED) WITH 10mm
LIFTING HOLE IN THE CENTRE)

FINISHED FOOTPATH LEVEL

COVER SUPPORT 16mm PLAIN


ROD, 35mm LONG WELDED TO
ANGLE AT CORNERS OF FRAME

FRAME 25x25x3mm MILD


STEEL ANGLE
SUMP WALL (INSITU
CONCRETE OR BRICK)

75 MIN.

MINIMUM 25mm FIXINGS LUGS OR


DYNABOLT IN EACH CORNER

DETAIL A

PROPERTY CONNECTION
NTS

10/08/11

JAS

0.9m (TYP)

THROAT WIDTH
PREFERRED 3m
MAXIMUM 6m
(SUBJECT TO APPROVAL)

YELLOW LINE (ONLY WHERE


NO KERB EXISTS)

300mm WIDE STOP LINE

BUILDING

PROPERTY
LINE

1.2m MIN.

BITUMEN FINISH
GRADE 1:48 TO 1:24

1m

GRADE 1:10 MAX.


REFER NOTE

1m RADIUS AND TAPER


CONCRETE MARGIN (300-150)
600mm TACTILES

10m NO STANDING ZONE

30

CONCRETE KERB AND


GUTTER

300mm CONCRETE
MARGIN

TACTILED CROSSOVER
NTS

NOTE:
VEHICLE ACCESS MUST BE CHECKED IN
ACCORDANCE WITH AUSTRALIAN STANDARDS
2890.1-1993 OR APPROPRIATE TO ENSURE THAT A
VEHICLE WILL NOT SCRAPE THEIR UNDERSIDE
WHEN NEGOTIATING THE CROSSOVER

10/08/11

JAS

BOLLARDS AND
RAILINGS
DETAILS:

BICYCLE PARKING RAIL-FRAME


BOLLARD DETAIL
COLLAPSABLE BOLLARD DETAIL
CONCRETE / TIMBER SLEEPER RETAINING WALL DETAIL
FENCE AND FOOTING DETAIL
TYPICAL HANDRAIL

CL

800

CL

R1
0

GALVANISED 50 CHS 5.0


CAST 250mm INTO
FOOTINGS

PROVIDE 30mm
ASPHALT OVER
FOOTING

FINISHED
SURFACE
FLANGED
END

MASS CONCRETE
FOOTINGS
GRADE N20

BICYCLE PARKING RAIL-FRAME


NTS

10/08/11

JAS

6mm CAP PLATE HOT DIP


GALVANISED WELDED TO PIPE
OR
CONCRETE INFILL TO PIPE
WITH MOUND TO TOP SURFACE

1200

152 CHS 6.3 HOT DIP


GALVANISED

MOUND CONCRETE

150

1000

FINISHED SURFACE

450-500

BOLLARD DETAIL
(BL ON PLAN)
1:20

10/08/11

JAS

6mm CAP PLATE


HOT DIP GALVANISED
WELDED TO CHANNEL.

1000

114 CHS (HOT DIP


GALVANISED) PAINT
TO SUIT.

140 x 10 PL. x 200 LONG


WELDED TO CHANNEL

HEAVY DUTY HINGE BOLTED


TO BASE PL AND CHANNEL.
300 Sq. x 10 PL. BOLTED TO BASE PL.
4/M12 4.6/S H.D. BOLTS
THREADED AT TOP FOR
40mm.

200

650

30 x 10 PL. x 40 LONG WITH


10mm HOLE WELDED TO
BASE PL.

MASS CONCRETE
FOOTING CONCRETE
GRADE N25
450

COLLAPSABLE BOLLARD DETAIL


NTS

140 x 10 PL. x 200 WELDED TO


CHANNEL WITH 40 x 15mm SLOT.

300 Sq. x 10
BASE PL.

30 x 10 PL x 40 LONG WITH 10mm


HOLE WELDED TO BASE PL.

SECTION A-A

10/08/11

JAS

STEEL UPRIGHT
CONCRETE PIER FOOTING

SLEEPER

NEW CONCRETE/TIMBER SLEEPER


RETAINING WALL

MAX. HEIGHT RETAINED


=1.800m

300mm WIDE SELECTED


GRANULAR BACKFILL
MATERIAL (7mm)

150 UC 23 STEEL UPRIGHT


AT 240mm CTS.

CORNER DETAIL
NTS

SLEEPERS 200 x 100 x 2400mm LONG


(TIMBER GRADE F1; CONCRETE
GRADE N25) ON EDGE

A
NEW HOTMIX PAVEMENT SURFACE

SLEEPER

FOR FOOTING SIZE/ REINF'T


REFER PLAN.
STEEL UPRIGHTS
2-150 PFC

ALTERNATIVE CORNER DETAIL


NTS

SLEEPER

MASS CONCRETE 600x


2500mm DEEP BORED
CONCRETE PIER FOOTING
f'c=20MPa
G=20 kN/m

STEEL UPRIGHT

AGRICULTURAL DRAIN

125 MIN.
COVER

LOCAL SHAPING OF SLEEPER


MAY BE REQUIRED TO SUIT
THE STEEL UPRIGHT

200

CONCRETE PIER FOOTING

SECTION A-A
NTS

CONCRETE/ TIMBER SLEEPER


RETAINING WALL DETAIL
NTS

10/08/11

JAS

POSTS @ 2100
MAX CTRS

2100 MAX.

NEW GOOD-NEIGHBOUR COLORBOND


FENCE (REFER ARCHITECT'S
DRAWINGS FOR DETAILS)

MIN. 100 COVER

100

850 BELOW
GROUND LEVEL

MIN.
300

FENCE AND FOOTING DETAIL


1:20

10/08/11

JAS

TRAFFICABLE
SURFACE TO TOP
OF HANDRAIL

EXTENDED HANDRAIL
300 MIN. PARALLEL TO
SURFACE BELOW

KERB RAIL

TURN HANDRAIL
THROUGH A TOTAL
OF 180 OR RETURN
FULLY TO END POST
OR WALL FACE.

175 TO TOP OF KERB


RAIL
WARNING TACTILE
INDICATORS TO
AS 1428.4

TRANSITION

LANDING

300 10

RAMP

LANDING

RAMP

600 TO 800

LANDING 1200 MIN.

TYPICAL HANDRAIL ELEVATION


NTS

NOTES:
1. THE 300mm EXTENSION IS NOT REQUIRED WHERE THE
HANDRAIL IS CONTINUOUS, E.G. ON THE INSIDE OF AN
INTERMEDIATE LANDING.
2. HANDRAIL, STAUNCHION & KICKRAIL TO STRICTLY
COMPLY WITH AS 1428.1.
3. ALL HANDRAIL, KICKRAIL, STAUNCHIONS & BRACKETS TO
BE HOT DIP GALVANISED AFTER FABRICATION. ALL SITE
WELDS TO HAVE THE WELD SLAG REMOVED & FINISH WITH 2
COATS OF COLD GALVANISED TREATMENT.
4. STANCHIONS AND HANDRAIL NOT SHOWN FOR CLARITY.

900

300
R16 ROD
SUPPORT

42.3 CHS 4.0 HANDRAIL

6 CAP PL.

6 CAP PL.,
SEAL WELD

42.3 CHS 4.0


KICK RAIL

48.3 CHS 4.0 STAUNCHIONS,


SPACING TO SUIT RAMP
PROFILE (1.5m MAX CTS).

175

WALKWAY

300 MIN.

900

CONTINUE KERB AND HANDRAILS


ACROSS/AROUND LANDING WHERE
POSSIBLE.

190 x 8 BASE PL.,


6mm CFW TO STAUNCHION
10mm NON-SHRINK GROUT,
4M12 DOME HEAD CHEMSET
ANCHORS.

TYPICAL HANDRAIL DETAIL


1:20

NOTE:
1. THE 300mm EXTENSION IS NOT REQUIRED WHERE THE
HANDRAIL IS CONTINUOUS, E.G. ON THE INSIDE OF AN
INTERMEDIATE LANDING.
2. HANDRAIL, STAUNCHION, KICKRAIL TO STRICTLY
COMPLY WITH AS 1428.1.
3. ALL HANDRAIL, KICKRAIL, STAUNCHIONS & BRACKETS TO
BE HOT DIP GALVANISED AFTER FABRICATION. ALL SITE
WELDS TO HAVE THE WELD SLAG REMOVED & FINISH WITH
2 COATS OF COLD GALVANISED TREATMENT.

10/08/11

JAS

ENVIRONMENTAL
DETAILS:

DIVERSION DRAIN
GRATED INLET PIT SEDIMENT TRAP
KERB FILTER FABRIC
LEVEL SPREADER
PROTECTION OF EXISTING STORMWATER INLETS
SEDIMENT FENCE
SIDE ENTRY PIT SEDIMENT TRAP
STRAW BALE & GEOTEXTILE SEDIMENT FILTER
TEMPORARY CONSTRUCTION EXIT
TYPICAL SEDIMENT BASIN
WORM SEDIMENT TRAP

0.3m
MIN.

NATURAL SURFACE

2.5

2.5

1.0m
MIN.

2.5

300
MIN.

COMPACTED EARTH BANK


TOP WIDTH 0.5m MIN.

DIVERSION DRAIN
NTS

10/08/11

JAS

50-75mm GRAVEL, 200mm MIN DEPTH

SILT LADEN RUNOFF

SILT LADEN RUNOFF

GEOTEXTILE FILTER FABRIC


HEAVY GAUGE WIRE MESH
12mm PITCH
ALTERNATIVELY, DROP INLET MAY
BE SURROUNDED BY HALE BALE
BARRIERS OR A SILT FENCE
REFER RELEVANT DETAILS

FILTERED WATER

GRATED INLET PIT SEDIMENT TRAP


NTS

10/08/11

JAS

MIN.

150

USE SPACER BETWEEN KERB


& FILTER TO MAINTAIN
EFFECTIVE OPENING

100
MIN.

GEOFABRIC & GRAVEL


EXTENDS 250mm MIN. PAST
THE END OF THE WIRE MESH
TO ENSURE SEAL WITH KERB.

ROLL OF WIRE MESH &


GEOFABRIC FILLED
WITH 25-50 GRAVEL

KERB FILTER FABRIC

THIS PRACTICE ONLY TO BE USED WHERE SPECIFIED


IN AN APPROVED SWMP.

10/08/11

JAS

EARTH BANK

E
L GRAD
CHANNE
N
IO
S
R
m
6
DIVE
OR LAST
< 1.0% F

DE,
0% GRA
SILL AT NGTH 4m
E
MIN. L

DIVERSION OR
PERIMETER BANK
ABLE
VER ST
FLOW O
SHEET ISPOSAL AREA
D

PERSPECTIVE VIEW
2.0m MIN
0.15m
MIN

SILL
EROSION CONTROL MATTING

SECTION

LEVEL SPREADER
NTS

10/08/11

JAS

STAKES

EXISTING GRATE

GEOTEXTILE
FILTER FABRIC

PROTECTION OF
EXISTING STORMWATER INLETS
NTS

10/08/11

JAS

DISTURBED AREA

UNDISTURBED AREA

FASTEN WIRE MESH TO STAKES


WITH HEAVY DUTY WIRE STAPLES
FIX GEOFABRIC TO WIRE MESH.
JOINTS TO HAVE MIN 300mm OVERLAP
AND EITHER SEWN OR ATTACHED TO
STAKES

FLOW DIRECTION

PROVIDE STAKES AT 2.0m MAX SPACING


DRIVEN 500mm-700mm INTO GROUND.
STAKES TO BE 100mm DIA TIMBER POSTS
OR 1.5kg/m STEEL POSTS

GEOFABRIC & WIRE MESH


BURIED 200mm INTO GROUND,
ROCKY GROUND, SET INTO
CONCRETE PLINTH

SILT FENCE INSTALLATION METHOD


NTS

STEEL STAKES
OR SIMILAR

3000

WIRE OR STEEL MESH


DISTURBED AREA
OF FL
OW

STAKES DRIVEN
600 INTO GROUND

600
MAX

TION

200

DIRE
C

MAX

DETAIL OF OVERLAP

UNDISTURBED
AREA

GEOTEXTILE FILTER
FABRIC

SEDIMENT FENCE

DRAINAGE AREA 0.6HA MAX. SLOPE GRADIENT 1:2 MAX.


SLOPE LENGTH 60M MAX.

10/08/11

JAS

HEAVY GAUGE WIRE MESH


12mm PITCH

PROVIDE 80 x 50 BATTEN SPACED


50mm FROM KERB FACE AND 70mm
FROM WATERTABLE
GEOTEXTILE FILTER FABRIC, FIXED
TO REAR SIDE OF BATTEN

FINISHED SURFACE

50-75mm GRAVEL
SILT LADEN RUNOFF
FINISHED SURFACE

CONCRETE GUTTER

FILTERED WATER

SIDE ENTRY PIT SEDIMENT TRAP


NTS

10/08/11

JAS

DISTURBED AREA

UNDISTURBED AREA
PROVIDE 2 STAKES PER BALE,
DRIVEN 600mm INTO GROUND.
HAY BALES PLACED LENGTH
WISE, END TO END.

FLOW DIRECTION

EMBED BALE 100mm INTO GROUND

100

GROUND LEVEL

HAY BALE BARRIER


NTS

GEOTEXTILE FILTER FABRIC

ANGLE FIRST STAKE


TOWARDS PREVIOUSLY
LAID STAW BALE
DRIVE IN THREE
STAKES PER BALE

STAPLE GEOTEXTILE FILTER


ON TOP EDGE OF BALE.
DISTURBED AREA
OF FL
OW
200

TION

100

DIRE
C

FACE BALE TWINE AWAY


FROM DIRECT SUNLIGHT
UNDISTURBED
AREA

STAKES DRIVEN 600


INTO GROUND
DRAINAGE AREA 0.5HA. SLOPE GRADIENT 1:2 MAX.
SLOPE LENGTH 50m MAX.

STRAW BALE & GEOTEXTILE SEDIMENT FILTER


NTS

10/08/11

JAS

15.0m LE

NGTH

ENTRY TO
SITE

IDTH

W
3.0m
)
.
N
I
(M

BERM

MIN OF 5 STEEL OR TIMBER


"CATTLE GRID" SHAKER AT 3.0m CTS.

50-75mm BALLAST

300mm

0.2m
MIN

3.0m
(MIN.)

EXIT TO
PUBLIC R
OAD

GEOFABRIC BIDMIN A12


TO UNDERLINE BALLAST.

TEMPORARY CONSTRUCTION EXIT


NTS

10/08/11

JAS

RISER PIPE OPEN AT TOP


STORAGE VOLUME

300

TWL

MAX SLOPE 2:1

600

MAX SIDE
SLOPE 2:1

CREST OF
OVERFLOW OUTLET

1000

750

SETTLING VOLUME
IN
FL
OW

PRIMARY

100

OUTLET

UPVC PIPE 250

2 x 35mm HOLES

200
200

2 x 30mm HOLES

STEEL REINFORCED
CONCRETE BASE 400
x 400 x 400.

100

2 x 25mm HOLES
WIRE MESH

OUTLET PROTECTION
PROVIDE 2m x 2m x 0.17m
RIP-RAP. STONE GRADING
d50=0.110m.

25 TO 50mm OPENING
GEOTEXTILE FILTER - BIDIM A24
OR EQUIVALENT
PERFORATED PIPE
PROVIDE 20 x 10mm HOLES

TYPICAL CROSS SECTION OF SEDIMENT BASIN

250

NOTE:
OUTLET PIPE IS ONLY USED FOR THE ARRANGEMENT AT
THE PROPOSED RESIDUALS LAGOON AREA.

CONSTRUCT DENSELY
GRASSED OVERFLOW
SPILLWAY. MAX. SLOPE 6.5%.
CREST 300 ABOVE TOP OF
WATER LEVEL

1000

FLOW

SEDIMENT STROAGE ZONE

LENGTH
WIDTH

INFLOW

EARTH
EMBANKMENT

LENGTH/WIDTH
RATIO 3:1 MIN.

PLAN VIEW OF TYPICAL SEDIMENT BASIN


NTS

10/08/11

JAS

WIRE MESH
FILTER FABRIC

SEMI-PORTABLE VERSION
(SEALED BOTH ENDS)

GRAVEL (50-75mm)

WORM SEDIMENT TRAP


NTS

10/08/11

JAS

KERBING
DETAILS:

100mm KERB / 100mm KERB & GUTTER


150mm KERB / 150mm KERB & GUTTER
200mm KERB / 200mm KERB & GUTTER
300mm CONCRETE INVERT DRAIN
450mm CONCRETE INVERT DRAIN
600mm CONCRETE INVERT DRAIN
BLOCK PAVE INVERT DRAIN DETAIL
CONCEALED EDGE STRIP
CROSSOVER
EDGE STRIP
EXTENDED HEIGH KERB / EXTENDED HEIGHT KERB & GUTTER
KERB RAMP (1)
KERB RAMP (2)
KERB RAMP (3)
MEDIAN KERB
MOUNTABLE KERB & GUTTER
NEW KERB ON EXISTING PAVEMENT DETAIL
PRECAST CONCRETE WHEEL STOP
RAMPED THRESHOLD
ROLLOVER KERB & GUTTER

100

50

R15

100

FSL

FINISHED PAVEMENT

150

CLEAN BACKFILL
BEHIND KERB U.N.O.

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)

300

SUBGRADE (100% STANDARD


COMPACTION)

100mm KERB
(100K ON PLAN)
1:10

100

50

300
R15

FSL

5mm LIP ON PAVEMENT


20

40

CLEAN BACKFILL
BEHIND KERB U.N.O.

150

100

FINISHED PAVEMENT

300

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)

SUBGRADE (100% STANDARD


COMPACTION)

100mm KERB AND GUTTER


(100K&G ON PLAN)
1:10

10/08/11

JAS

100

50
R15

150

FSL

FINISHED PAVEMENT
150

CLEAN BACKFILL
BEHIND KERB U.N.O.

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)
300

150mm KERB

SUBGRADE (100% STANDARD


COMPACTION)

(150K ON PLAN)
1:10

100

50

300
R15

150

FSL

FINISHED PAVEMENT

40

CLEAN BACKFILL
BEHIND KERB U.N.O.
150

5mm LIP ON PAVEMENT

300

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)

SUBGRADE (100% STANDARD


COMPACTION)

150mm KERB AND GUTTER


(150K&G ON PLAN)
1:10

10/08/11

JAS

100

50
R15

200

FSL

CLEAN BACKFILL
BEHIND KERB U.N.O.

200

FINISHED PAVEMENT

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)
SUBGRADE (100% STANDARD
COMPACTION)

300

200mm KERB
(200K ON PLAN)
1:10

100

300
R15

FSL

R15

5mm LIP ON PAVEMENT

FINISHED PAVEMENT

40

200

25

200

CLEAN BACKFILL
BEHIND KERB U.N.O.

50

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)
300

SUBGRADE (100% STANDARD


COMPACTION)

200mm KERB AND GUTTER


(200K&G ON PLAN)
1:10

10/08/11

JAS

R75

5mm LIP ON ASPHALTIC


CONCRETE PAVEMENT
(TYP.)

25

300

50

125

20mm CHAMFER
(TYP.)

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)

SL72 MESH

SUBGRADE (100% STANDARD


COMPACTION)

300mm CONCRETE INVERT DRAIN


(300ID ON PLAN)
1:10

10/08/11

JAS

20mm CHAMFER
(TYP.)

150

R75

35

450

5mm LIP ON ASPHALTIC


CONCRETE PAVEMENT
(TYP.)

50

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)

SL72 MESH

SUBGRADE (100% STANDARD


COMPACTION)

450mm CONCRETE INVERT DRAIN


(450ID ON PLAN)
1:10

10/08/11

JAS

20mm CHAMFER
(TYP.)

150

R75

40

600

5mm LIP ON ASPHALTIC


CONCRETE PAVEMENT
(TYP.)

50

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)

SL72 MESH

SUBGRADE (100% STANDARD


COMPACTION)

600mm CONCRETE INVERT DRAIN


(600ID ON PLAN)
1:10

10/08/11

JAS

POLYMER MODIFIED ADHESIVE


MORTAR TO SUPERINTENDENT'S
APPROVAL

1:20

10

1:8
150

100

20

25mm BEDDING SAND

20

WIDTH OF INVERT DRAIN

20mm F.C.R. (PM.1/20QM)


BASECOURSE (98%
MODIFIED COMPACTION)

GRADE N20 CONCRETE SL82


MESH CENTRAL WIDTH OF
CONCRETE BASE SHALL NOT
EXCEED WIDTH OF INVERT
DRAIN

SUBGRADE (100% STANDARD


COMPACTION)

BLOCK PAVE INVERT DRAIN DETAIL


(VEHICULAR)
1:10

10/08/11

JAS

EQUAL

SELECTED PAVING
UNITS

100

CONCRETE EDGE STRIP

25mm BEDDING SAND

100
EQUAL
CAST EDGE AGAINST
PAVING UNITS

CONCEALED EDGE STRIP


(NON-VEHICULAR)
1:10

10/08/11

JAS

STANDARD KERBING BEYOND

125

20mm CHAMFER
(TYP.)
FINISHED SURFACE
150

R25
80

80

600

R40

270

FINISHED SURFACE

290

250

600

CROSSOVER
1:10

10/08/11

JAS

125

N25 CONCRETE. TOOLED JOINTS AT


2.0m CTRS. 2xN16, 200 LAP
CONTINUOUS.

LANDSCAPING
200

PAVEMENT

100mm MIN. Q.R. PM(2/20QR)


SUBBASE COURSE
(98% MODIFIED COMPACTION)
SUBGRADE (100% STANDARD
COMPACTION)

EDGE STRIP
(ES ON PLAN)
1:10

10/08/11

JAS

110

25
TWO PART POLYURETHANE SEALANT
SEAL-N-FLEX TRAFFICABLE OR
APPROVED EQUIVALENT

300mm MIN.
750mm MAX.

150 LAP

SL.72 MESH

150

FINISHED SURFACE

HEIGHT VARIES

N12 CONTINUOUS

N12 BARS AT 300 CTS.

C.J

530

COMPRESSIBLE
FILLER NOMINAL 12mm
WIDE
1.N12 BAR

200 PIERS AT 1200mm CTS.


AND AT EACH SIDE OF JOINT

200

EXTENDED HEIGHT KERB & GUTTER


(EHK&G ON PLAN)
1:10

150

SL82 MESH

C.J (OPTIONAL)

2N12 BARS
530

FINISHED SURFACE

25

HEIGHT VARIES
300mm MIN.
750mm MAX.

100

200 PIERS AT 1200mm CTS.


AND AT EACH SIDE OF JOINT

200

EXTENDED HEIGHT KERB


(EHK ON PLAN)
1:10

10/08/11

JAS

A
2000 MIN.

1500 MIN.

BUILDING LINE

LANDING 1500 MIN. FROM


TOP OF RAMP TO ANY
OBSTRUCTION

UPPER
LANDING

1520 MAX.

KERB RAMP
1 IN 8 MAX.

1200 MIN.

45

WARNING UNIT AS
SPECIFIED IN AS1428.4

45

KERB FACE

LOWER
LANDING

1000 MIN.

PLAN
INCLUDED ANGLE BETWEEN
RAMP SURFACE AND
LOWER SURFACE 166 MIN.

SHARP TRANSITION AT
CHANGE OF GRADE TOP
AND BOTTOM OF RAMP

190 MAX.

FOOTPATH

TOP
LANDING
1500 MIN.

ROADWAY
1 IN 8
KERB RAMP
1520 MAX.

LOWER
LANDING
1200 MIN.

SECTION A-A
KERB

SLOPING
SIDE

RAMP

SECTION B-B
KERB RAMP DETAIL
1:50

NOTE:
THE RAMP AND SLOPING SIDES SHOULD
BE SLIP RESISTANT AND OF A COLOUR
THAT CONTRASTS WITH THE ADJOINING
SURFACES.

10/08/11

JAS

A
1200

WARNING UNIT AS
SPECIFIED IN AS1428.4

JOINT

JOINT

PLAN OF KERB RAMP


150

1050

25mm FALL

75

1:20

FINISHED SURFACE

25

RAMP

100

125

FINISHED SURFACE

SECTION A-A
1:10

10/08/11

JAS

WARNING UNIT AS
SPECIFIED IN AS1428.9

DIRECTION AND LOCATION


OF FOOTPATH

RAMP DOWN

1500

45

LANDING:
SLOPE SHALL NOT EXCEED
1 IN 50 IN ANY DIRECTION
1200
(MIN.)

UTTER
AND G
KERB

PLAN
1:50

VARIES
(GRADIENT 1:10 MAX.)
FINISHED SURFACE

SECTION A-A
1:10

KERB RAMP CROSSING


SECTION
SCALE 1:10

NOTES:
1. RAMPS GIVING ACCESS TO ROADWAYS HAVING
KERB AND FOOTPATHS EACH SIDE SHALL BE
PROVIDED IN PAIRS, ONE IN EACH FOOTWAY AND
DIRECTLY OPPOSITE EACH OTHER.
2. THE RAMP AND SLOPING SIDES SHALL BE SLIP
RESISTANT. (ie. CONCRETE TEXTURED SURFACE)
TO AS 3661.
3. TACTILE DIRECTIONAL INDICATORS (WARNING
UNITS) SHALL BE AS SPECIFIED IN AS 1428.4

10/08/11

JAS

255
25

110

R40

R40

R20

190

225

140

FINISHED PAVEMENT

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)

300

SUBGRADE (100% STANDARD


COMPACTION)

MEDIAN KERB
(MK ON PLAN)
1:10

10/08/11

JAS

530

20mm CHAMFER (TYP.)

230
65

300

165

5mm LIP ON ASPHALTIC


CONCRETE PAVEMENT

R20

FSL

125

CLEAN BACKFILL
BEHIND KERB U.N.O.

100

200

FINISHED PAVEMENT

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)
300

SL.72 MESH

SUBGRADE (100% STANDARD


COMPACTION)

MOUNTABLE KERB & GUTTER


(MK&G ON PLAN)
1:10

10/08/11

JAS

SAWCUT
SAWCUT
WIDTH

Q.R.
EXISTING BITUMEN
SURFACE PROFILE

KERBING

REMOVE HOT MIX


LAYER

F.C.R.

EXISTING PAVEMENT

WIDTH OF SAWCUT
DEPENDENT ON
COMPACTION PLANT

EXISTING BITUMEN SURFACE

EXIST PAVEMENT
DEPTH

5mm LIP ON PAVEMENT

NEW ISLAND

RETAIN EXISTING PAVEMENT

300 MIN.

100mm MINIMUM THICKNESS

NEW KERB ON
EXISTING PAVEMENT DETAIL

FCR (PM1) (98% MODIFIED


COMPACTION) EXTEND 300mm
BEHIND BACK OF KERB.
SUBGRADE (100% STANDARD
COMPACTION)

NTS

10/08/11

JAS

165
30
15

30
75

15

EPOXY GROUT

30

110

SEAL DOWEL HOLE WITH EPOXY


MORTAR TWO HOLES PER UNIT

FINISHED SURFACE

2 R12 DOWELS 400 LONG


300mm INTO PAVING (250
FROM EACH END)
EACH UNIT 1770 LONG

PRECAST CONCRETE WHEEL STOP


1:5

10/08/11

JAS

DOOR
RAMP GRADIENT
1:8 MAX

35

20 MAX

280 MAX

RAMPED THRESHOLD
1:10

NOTE:
THE EDGES OF THE THRESHOLD RAMP
SHALL BE TAPERED OR SPLAYED AT A
MINIMUM OF 45 WHERE THE RAMP DOES
NOT ABUT A WALL.

10/08/11

JAS

5mm LIP ON PAVEMENT


70

160

300
25

FSL

25

CLEAN BACKFILL
BEHIND KERB U.N.O.

125

75

FINISHED PAVEMENT

100mm MIN. COMPACTED Q.R.


(PM.2/20QG) SUBBASE
(95% MODIFIED COMPACTION)
300

SUBGRADE (100% STANDARD


COMPACTION)

ROLLOVER KERB & GUTTER


(RK&G ON PLAN)
1:10

10/08/11

JAS

NOTES & LEGENDS


NOTES:

GENERAL COMPACTION NOTES


GENERAL NOTES
PAVEMENT NOTES
REFERENCE DOCUMENTATION
SIGNAGE AND LINEMARKING NOTES
SITE CONTAMINATION - CONTRACTORS RESPONSIBILITIES
STORMWATER NOTES
SUBGRADE PREPARATION FOR PAVEMENT
SURFACE AND SUBSURFACE DRAINAGE AND SEDIMENT CONTROL

LEGENDS:

EXISTING SERVICES LEGEND


LEGEND (1)
LEGEND (2)
SURVEY LEGEND (1)
SURVEY LEGEND (2)

GENERAL COMPACTION NOTES

1. ALL AREAS TO BE FILLED SHALL BE COMPLETELY CLEARED OF ALL DELETERIOUS MATERIAL,


INCLUDING THE FOLLOWING : TREES, ROOTS AND ALL OTHER DECAYED VEGETATION.
2. PRIOR TO THE COMMENCEMENT OF ANY CIVIL OR STRUCTURAL CONSTRUCTION, THE ENTIRE SITE
AREA IS TO BE COMPACTED AND TESTED IN ACCORDANCE WITH AS1289.5.1.1 TO PRODUCE THE
FOLLOWING:
- 98% STANDARD COMPACTION AT THE SURFACE AND AT 300mm BELOW SURFACE LEVEL, WHEN
PAVEMENTS AND STRUCTURES ARE TO BE CONSTRUCTED, ELSEWHERE 95%.
- TESTING SHALL BE CARRIED OUT A RATE OF 1 TEST PER 150 Sq/m AT EACH 200mm LAYER OF FILL (MIN 5
TESTS PER LAYER).
TESTING SHALL BE EVENLY SPACED OVER THE ENTIRE SITE, AND AT RANDOM LOCATIONS.
TEST RESULTS SHALL BE FORWARDED TO THE SUPERINTENDENT FOR APPROVAL PRIOR TO
COMMENCEMENT OF WORKS.
3. ALL NEW FILL SHALL BE COMPACTED TO PRODUCE 98% OF THE STANDARD COMPACTION TO AS
1289.5.1.1 (U.N.O.) WHEN BENEATH PAVING AND STRUCTURES, ELSEWHERE 95%.
FILL MATERIAL TO BE APPROVED BY THE SUPERINTENDENT. THE LOOSE THICKNESS OF EACH LAYER
BEFORE COMPACTION SHOULD NOT EXCEED 200mm WITHOUT THE APPROVAL OF THE
SUPERINTENDENT.
PROVIDE COMPACTION TESTS FOR NEW FILL AS PER NOTE 2.
4. ALL EXISTING FILL WITHIN THE CONSTRUCTION AREA SHALL BE COMPLETELY REMOVED. MATERIAL
SHALL BE REPLACED AND COMPACTED IN LAYERS NOT EXCEEDING 200mm WHEN MEASURED LOOSE.
EACH LAYER SHALL BE COMPACTED TO ACHIEVE A DENSITY OF NOT LESS THAN 98% STANDARD
COMPACTION WHEN BENEATH PAVING AND STRUCTURES, ELSEWHERE 95%

10/08/11

JAS

GENERAL NOTES

1. THESE DRAWINGS ARE NOT CADASTRAL PLANS AND MUST NOT BE USED IN DETERMINING PRECISE
DETAILS WITH RESPECT TO BOUNDARIES.
2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.
3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE.
4. ALL LEVELS ARE EXPRESSED IN METRES.
5. ALL CO-ORDINATES ARE A.M.G. BASED, UNLESS NOTED OTHERWISE.
6. LEVEL DATUM IS A.H.D.

SUPPLIED SETOUT INFORMATION


7. SET OUT OF CARPARKS AND ASSOCIATED FEATURES SHALL BE SUPPLIED TO THE CONTRACTOR IN AN
ELECTRONIC 2D FORMAT (AutoCAD 2007) WHICH CONTAINS CONTROL POINTS AND T.B.M. NO TABULATED
SET OUT INFORMATION IN HARD COPY WILL BE ISSUED. CAD FILES WILL BE ISSUED IN MILLIMETRES.
CONTRACTOR TO ALLOW FOR FILE CONVERSION AS REQUIRED. ORIGINAL FULL SIZE AURECON
DRAWING MAY BE SCALED SUBJECT TO CORRECT BAR SCALE VERIFICATION.
8. REFER TO DIMENSIONED ARCHITECTURAL BUILDING DETAILS FOR ALL SET OUT DIMENSIONS OF
BUILDINGS, KERBING, PAVING, ETC.
9. THESE DRAWINGS SHALL BE READ IN CONJUNCTION WITH THE RELEVANT SPECIFICATIONS.
10. REFER TO STRUCTURAL ENGINEERS DRAWINGS FOR DETAILS OF CONCRETE FLOOR AND BEAMS
BEFORE SETTING OUT.
11. REFER TO HYDRAULICS DRAWINGS FOR ALL UNDERGROUND PIPEWORK AND DETAILS.
12. SPOIL TO BE STOCKPILED AS DIRECTED BY THE SUPERINTENDENT AND EXCESS NOT USED IS TO BE
REMOVED FROM SITE BY CONTRACTOR.
13. THESE DRAWINGS ARE A SCHEMATIC REPRESENTATION OF SERVICES INFORMATION CONTAINED IN
DRAWINGS ISSUED BY THE RELEVANT AUTHORITIES.
THE INFORMATION CONTAINED IN THESE DRAWINGS IS INDICATIVE ONLY, AND REFERENCE SHOULD BE
MADE TO THE RELEVANT AUTHORITIES DOCUMENTATION TO CONFIRM ACCURACY AND COMPLETENESS.
WHERE INFORMATION IS AVAILABLE, THE SUB-SURFACE SERVICES INSTALLED BY CONTRACTORS OTHER
THAN THE AUTHORITIES HAVE BEEN SHOWN, BUT ADDITIONAL UNDOCUMENTED SERVICES MAY BE
PRESENT. SHOULD THE CONTRACTOR BELIEVE THAT SUB-SURFACE SERVICES ARE AT RISK OF DAMAGE
DURING CONSTRUCTION, THE CONTRACTOR SHOULD NOTIFY THE RELEVANT AUTHORITIES AND
ESTABLISH THE EXACT LOCATION OF THE SERVICES.
14. THE FINISHED SURFACE SHALL BE EVENLY GRADED BETWEEN DESIGN SURFACE LEVELS.
15. DEMOLISH AND REMOVE ALL EXISTING INSTALLATIONS WHICH ARE TO BE AFFECTED BY NEW WORKS.
EXTENT OF DEMOLITION TO BE CONFIRMED ON SITE WITH THE SUPERINTENDENT PRIOR TO
COMMENCEMENT OF WORKS.
16. CONTRACTOR TO ADJUST LIDS OF EXISTING SERVICE PITS TO MATCH FINISHED SURFACE LEVEL.
PROVIDE HEAVY DUTY COVER IF IN PAVED AREA TO THE REQUIREMENTS OF THE RELEVANT AUTHORITY,
IF APPLICABLE. RELOCATE SERVICE AS REQUIRED.
17. WORKMANSHIP AND MATERIALS ARE TO BE IN ACCORDANCE WITH THE RELEVANT CURRENT S.A.A.
CODES INCLUDING ALL AMENDMENTS, AND THE LOCAL STATUTORY AUTHORITIES, EXCEPT WHERE
VARIED BY THE CONTRACT DOCUMENTS.
18. ANY DISCREPANCY BETWEEN DRAWINGS SHALL BE REPORTED TO THE SUPERINTENDENT BEFORE
WORK PROCEEDS.

10/08/11

JAS

PAVEMENT NOTES

1. EXISTING PAVERS THAT ARE INDICATED TO BE RELAID ARE TO BE NEATLY STOCKPILED ON SITE TO
AVOID DAMAGE DURING CONSTRUCTION.
2. AREAS OF RELAID PAVERS SHALL HAVE BASE MATERIAL CUT TO NEW LEVEL WITHIN EXISTING BASE
MATERIAL AND NEW 25mm SAND LAYER.
3. PAVER LOC OR SIMILAR PRODUCT SHALL BE USED ON ALL RELAID PAVERS.
4. PAVERS RELAID SHALL BE CLEANED PRIOR TO RE-INSTALLATION. DAMAGED PAVERS ARE TO BE
REPLACED.
5. IN AREAS WHERE ASPHALT PAVEMENT EXISTS AND NEW PAVEMENT IS BEING LAID THE CONTRACTOR
SHALL REMOVE THE EXISTING TOP COAT AND PAVEMENT DOWN 100mm FROM SURFACE LEVEL.
6. RE-ASPHALTED AREAS SHALL HAVE EXISTING BASE MATERIAL EXCAVTED (GENERALLY 100mm)
REPLACED WITH A DTEI SPEC PM1/20QG AND COMPACTED (98% MODIFIED) TO NEW DESIGN LEVEL AND
HOTMIX PLACED TO MATCH NEW LEVELS.
7. ALL PAVERS UPON COMPLETION OF INSTALLATION SHALL BE TREATED WITH A STAIN RESISTANT
COATING/SEALANT TO ASSIST WITH CLEANING OF PAVERS. CONTRACTOR TO SUBMIT TREATMENT AND
WORK METHOD TO SUPERINTENDENT FOR APPROVAL.

10/08/11

JAS

REFERENCE DOCUMENTATION
1. REFER TO THE GEOTECHNICAL ENGINEERS RECOMMENDATIONS FOR ALL SITE AND SOIL EXCAVATION
EXTENTS.
2. THE CIVIL SPECIFICATION SHALL BE READ IN CONJUCTION WITH THE GEOTECHNICAL REPORT FOR
SOIL EXCAVATION AND WITH THE DRAWINGS PROVIDED.
3. STRUCTURAL DRAWINGS FOR ALL BUILDING STRUCTURAL DETAILS.
4. LANDSCAPE ARCHITECTURAL DRAWINGS FOR ALL TREE LOCATIONS, TREE PROTECTION AND
LANDSCAPE DETAILS.
5. ARCHITECTURAL DRAWINGS FOR FINAL COORDINATION OF PROJECT DETAILS AND ALL BUILDING
DETAILS.
6. REFER TO THE ENVIRONMENTAL ENGINEERS REPORT FOR ALL SITE SOIL CONTAMINATION REPORTS
AND REQUIREMENTS.

10/08/11

JAS

SIGNAGE & LINEMARKING NOTES


1. TRAFFIC CONTROL DETAILS IN ACCORDANCE WITH AUSTRALIAN STANDARD AS1742 MANUAL OF
TRAFFIC CONTROL DEVICES AS MODIFIED BY THE "CODE OF TECHNICAL REQUIREMENTS FOR THE LEGAL
USE OF TRAFFIC CONTROL DEVICES (TSA)" AND "INTERIM GUIDELINES FOR PAVEMENT MARKING MANUAL
IN SOUTH AUSTRALIA (TSA)".
2. FINAL LOCATION OF SIGNS TO BE DETERMINED ON SITE.
3. SIGNS TO BE INSTALLED IN ACCORDANCE WITH AS 1742-APPENDIX C.
4. ALL LINE DIMENSIONS QUOTED ARE TO THE CENTRE OF LINEMARKING OR TO THE FACE OF KERB.
5. ALL LINEMARKING 100mm WIDE UNLESS NOTED OTHERWISE.

PAVEMENT MARKING TABLE


LINE TYPE

COLOUR

DESCRIPTION

STOP LINE

WHITE

450mm WIDE.
(RECESS 300 BACK FROM
FACE OF KERB)

HOLDING LINE

WHITE

450mm WIDE,
600mm LINE 600 GAP.
(RECESS 300 BACK FROM
FACE OF KERB)

NO STANDING
LINE

YELLOW

100 WIDE
CONTINUOUS

TURNING
LINE

WHITE

100mm WIDE
600mm LINE 600mm GAP

SEPARATION
LINE A

WHITE

100mm WIDE
3.0m LINE 9.0m GAP

SEPARATION
LINE B

WHITE

100mm WIDE
6.0m LINE 6.0m GAP

UNBROKEN
SEPARATION
LINE

WHITE

100mm WIDE
CONTINUOUS

BROKEN
LANE
LINE

WHITE

100mm WIDE
3.0m LINE 9.0m GAP

CONTINUITY
LINE

WHITE

100mm WIDE
1.0m LINE 3.0m GAP

CHEVRON/
DIAGONAL
MARKING

WHITE

L=100mm
B=600mm
W=200mm
S=3000mm
A=45

CARPARKING
LINE

WHITE

100mm WIDE
CONTINUOUS
(NOTE: REFER TO ARCHITECT'S
DRAWINGS FOR CARPARK
SETOUT & DIMENSIONS)

CROSSWALK
LINE

WHITE

150mm WIDE
600 LINE, 300 GAP

EDGE
LINE

WHITE

100mm WIDE
23.0m LINE, 1.0m GAP

REFER DIAGRAM

SIGNAGE LEGEND
No.
A
B
C
D
E
El
Er
F
G
H
I
J
K
L
M
N
O

CODE & SIZE


R1-2A
R2-4A
R2-7A
R1-1A
R5-35
R5-35l
R5-35r
D4-2-2
RS-10
R5-23
R5-20
R5-16
R5-13
R3-1

TYPE
GIVE WAY
NO ENTRY
ONE WAY TRAFFIC
STOP
NO STOPPING -BOTH WAYS
NO STOPPING -LEFT
NO STOPPING -RIGHT
HAZARD DIRECTIONAL SIGN
DISABLED PARKING BAY
LOADING ZONE
BUS ZONE
PRAM PARKING BAY
1/2 HOUR PARKING
MANAGERS PARKING
NIGHT STAFF PARKING
5 MINUTE PARKING
WOMBAT CROSSING

10/08/11

JAS

SITE CONTAMINATION CONTRACTORS RESPONSIBILITIES


1. CREATE AND ADHERE TO A SITE SPECIFIC CEMP (CONSTRUCTION ENVIRONMENTAL MANAGEMENT
PLAN). THIS DOCUMENT SHALL CONTAIN THE NATURE AND IMPLICATIONS OF THE CONTAMINATION.
2. APPOINT A CEMP ADMINISTRATOR TO IMPLEMENT AND MANAGE THE CEMP. PREPARE AN
ORGANISATIONAL CHART (TO BE ADDED INTO THE CEMP) OUTLINING RESPONSIBILITIES FOR THE
ONGOING MANAGEMENT OF THE SITE DURING CONSTRUCTION WORKS. IMPLEMENT A FORMAL PROCESS
OF APPROVAL AND DOCUMENTATION UNDER THE CEMP.
3. IMPLEMENT A SYSTEM OF ONGOING MONITORING AND REVIEW OF THE EFFECTIVENESS OF THE CEMP,
INCLUDING INTERNAL OR EXTERNAL AUDITS.
4. PREPARE AND IMPLEMENT A CONSTRUCTION OH&S PLAN COGNISANT OF THE SITE CONTAMINATION.
IMPLEMENT A REVIEW PROCESS FOR ASSOCIATED DOCUMENTS. IMPLEMENT A RECORD KEEPING
SYSTEM FOR ASSOCIATED DOCUMENTS, INCLUDING NON-CONFORMANCES.
5. ENSURE EVERY RELEVANT PARTY IS AWARE OF THE CONTENT AND REQUIREMENTS OF THE CEMP.
CONDUCT FORMAL DOCUMENTED INDUCTIONS FOR RELEVANT PEOPLE; MAKE COPIES OF THE CEMP
AND OTHER DOCUMENTATION AVAILABLE TO ALL RELEVANT PEOPLE.
6. REQUIRE THE FOLLOWING OF ANYONE WHO MAY DISTURB THE CONTAMINATED SOIL (E.G.
CONTRACTOR'S STAFF, SUBCONTRACTORS, GEOTECHNICAL CONSULTANTS): INDUCTION; PROVISION OF
WRITTEN PLAN OF HOW EXPOSURE TO CONTAMINATED SOIL WILL BE MANAGED; CEMP ADMINISTRATOR
APPROVAL OF PLAN; CEMP ADMINISTRATOR SIGNOFF ON COMPLETED WORKS; REPORTING OF
INCIDENTS AND IMPLEMENTATION OF CORRECTIVE ACTION AND DOCUMENTATION.
7. TEMPORARY VEHICLE WASHDOWN REQUIRED AT SITE EXIT TO PREVENT TRACKING OF
CONTAMINATED SOIL OFF SITE.
8. RESTRICT VEHICLE ACCESS TO THE SITE TO ESSENTIAL VEHICLES ONLY.
9. CONTROLLED DEMOLITION OF CONCRETE ON-GROUND SLABS TO AVOID BREAKING THE CONCRETE UP
INTO SMALL PIECES AND MIXING THEM WITH THE SITE SOILS.
10. DEMOLISHED CONCRETE TO BE WASHED FREE OF SOIL PRIOR TO DISPOSAL, IN ORDER TO BE
CONSIDERED NON-CONTAMINATED.
11. AVOID STOCKPILING CONTAMINATED SOILS. WHERE STOCKPILING IS UNAVOIDABLE, KEEP
STOCKPILES DAMP AND COVER WITH WATERPROOF TARPAULINS TO PREVENT DUST GENERATION.
12. ANY EXCAVATION WORK WILL REQUIRE WORKERS TO WEAR "APPROPRIATE" PPE, PLUS CONSTANT
DAMPING-DOWN TO PREVENT DUST GENERATION.
13. IF EXCAVATED SOILS ARE SUITABLE FOR RE-USE AS FILL AND ARE GOING TO BE USED AS SUCH,
ENSURE PROMPT MOISTURE CONDITIONING AND PLACEMENT TO AVOID DUST GENERATION.
14. EXCAVATED SITE SOILS THAT NEED TO BE DISPOSED OF OFF SITE WILL REQUIRE TRANSPORT BY
OPERATORS LICENSED TO TRANSPORT CONTAMINATED SOILS, UNDER THE APPROPRIATE TRANSPORT
CERTIFICATES. (IMPLICIT IN THIS IS THAT WASTE SOIL WILL HAVE TO BE CHARACTERISED (BY SAMPLING,
LABORATORY ANALYSIS AND INTERPRETATION) FOR DISPOSAL, AND, IF EXCEEDING THE WASTE FILL
CRITERIA, WILL HAVE TO BE DISPOSED OF TO A SUITABLY LICENSED FACILITY.
15. CONSTRUCT A CUT-OFF BUND WITH CLEAN MATERIAL TO PREVENT RUNOFF OF SITE STORMWATER
OFF-SITE. (PRESUMABLY ALTERNATIVE SITE STORMWATER MANAGEMENT ACHIEVING THIS AIM WOULD
BE ACCEPTABLE.)
16. MONITOR THE INTEGRITY OF SITE SURFACES.
17. AVOID DEWATERING OF EXCAVATIONS. WATER COLLECTED FROM ANY DEWATERING TO BE TESTED
TO DETERMINE APPROPRIATE DISPOSAL METHOD.
18. AVOID OFF-SITE DISPOSAL OF ANY WATER FROM THE SITE. WATER COLLECTING ON THE SITE FROM
ANY SOURCE TO BE TESTED TO DETERMINE APPROPRIATE DISPOSAL METHOD.
19. MANAGE DUST GENERALLY.
20. MANAGE EROSION OF EXPOSED SURFACES GENERALLY.
21. MANAGE NUISANCE ODOUR ISSUES.
22. ENSURE THAT CROSS-CONTAMINATION OF CLEAN IMPORTED MATERIALS BY THE IN SITU
CONTAMINATED SOIL DOES NOT OCCUR.
23. MAINTAIN THE SITE IN GOOD ORDER GENERALLY.
24. MANAGE COMPLAINTS FROM MEMBERS OF THE PUBLIC AND OTHERS.

10/08/11

JAS

STORMWATER NOTES

1. INLET PIPES SET 20mm ABOVE PIT INVERT LEVEL UNLESS NOTED OTHERWISE.
2. OUTLET PIPE I.L. ARE SET AT PIT I.L. UNLESS NOTED OTHERWISE.
3. TOP R.L. FOR SIDE ENTRY PITS IS WATER TABLE LEVEL.
4. TRENCH GRATES TO BE STAINLESS STEEL HEELPROOF AND SLIP-PROOF TYPE BY ACO OR APPROVED
EQUIVALENT.
5. ALL STORMWATER PIPES SHALL BE uPVC PIPES SHALL BE SEWER CLASS DWV UNLESS NOTED
OTHERWISE.
6. ALL STORMWATER PITS GREATER THAN 600x600 SHALL BE PROVIDED WITH A SPLIT LID TO ENSURE
MAXIMUM LID "LIFT" IS 600x600.
7. ALL STORMWATER PITS ON PLAN DRAWINGS TO HAVE HEELPROOF GRATE OR PAVER INFILL LID
WHERE LOCATED ON PAVEMENT OR FOOT TRAFFIC AREA.
8. ALL STORMWATER PITS TO HAVE ACCESS STEP IRONS INSTALLED IN ACCORDANCE WITH AS1657 AND
AS4198 WHERE DEPTH IS GREATER THAN 1200mm.
9. AG DRAINS TO BE INSTALLED BEHIND ALL RETAINING WALLS AND LOCATIONS SHOWN ON DRAWINGS.
10. ALL AG DRAINS TO 100, WRAPPED IN 200 MICRON GEOTEXTILE (BIDIM A24 OR SIMILAR) AND MINIMUM
300mm THICKNESS OF 20mm DRAINAGE SCREENINGS U.N.O.
11. ALL DOWNPIPE RISERS TO BE AS SHOWN ON ARCHITECTURAL DRAWINGS. CONNECT TO 150
UNDERGROUND CONNECTION UNLESS NOTED OTHERWISE.

10/08/11

JAS

SUBGRADE PREPARATION FOR PAVEMENT

1. THE EXISTING GROUND SURFACE IS TO BE STRIPPED TO REMOVE ANY LOOSE SURFICIAL SOIL OR
TOPSOIL AND/OR ASSOCIATED ORGANIC MATTER. ALL TOPSOIL AND UNCONTROLLED FILL IS TO BE
STRIPPED AND THE UPPER 200mm OF EXPOSED SUB-GRADE COMPACTED TO ACHIEVE 98% STANDARD
COMPACTION. ANY EXPOSED SOIL IS TO BE PROOF ROLLED, IN THE PRESENCE OF THE
SUPERINTENDENT AND ENGINEER, WITH A NON-VIBRATING 20t SMOOTH DRUM ROLLER ( OR APPROVED
OTHER) TO IDENTIFY ANY SOFT OR WEAK AREAS.
2. DURING PROOF ROLLING, ALL SOFT, WET, WEAK OR ORGANIC MATERIALS ARE TO BE REMOVED AND
REPLACED WITH SELECTED COMPACTED FILL.
3. ALL EXCAVATED AREAS BEFORE BACKFILL ARE TO BE SURVEYED BY LICENSED SURVEYOR TO
QUALIFY SELECTED FILL QUANTITY. CONTRACTOR TO ALLOW THIS SURVEYING IN THEIR CONTACT.
4. THE SELECTED FILL IS TO BE A WELL GRADED GRANULAR FILL SIMILAR IN COMPOSITION TO A QUARRY
WASTE PRODUCT. THE SELECTED FILL IS TO BE PROPERLY MOISTURE CONDITIONED PRIOR TO
PLACEMENT AND COMPACTION.
5. THE FILL IS TO BE PLACED AND COMPACTED IN LAYERS NOT EXCEEDING 200mm COMPACTED
THICKNESS, TO A DENSITY NOT LESS THAT 98% OF STANDARD COMPACTION FOR GRAVELY FILL.
6. FIELD AND LABORATORY DENSITY TESTING ARE REQUIRED AFTER PROOF ROLLING OF STRIPPED
GROUND, AFTER BACK FILLING ANY AREAS OF UNSUITABLE FOUNDATION SOIL AND DURING THE
PLACEMENT OF ANY SELECTED FILL AND PAVEMENT LAYERS. TESTING AGENT TO BE NATA APPROVED
AND TESTS TO BE CONDUCTED IN ACCORDANCE WITH GUIDELINES.
7. PROOF ROLL PAVEMENT SUBGRADES PRIOR TO PAVEMENT INSTALLATION. CONTRACTOR TO HAVE A
GEOTECHNICAL ENGINEER TEST THE WHOLE PAVEMENT SUB-SURFACE ONCE SUBGRADE LEVELS ARE
REACHED FOR CBR VALUE. DESIGN CBR IS 3.0%. CONTRACTOR TO INFORM SUPERINTENDANT OF CBR
VALUE ON SITE PRIOR TO NEW PAVEMENT CONSTRUCTION.

10/08/11

JAS

SURFACE AND SUBSURFACE DRAINAGE AND


SEDIMENT CONTROL

1. IT'S ESSENTIAL THAT PROPER SITE DRAINAGE AND WATERPROOFING IS IMPLEMENTED AND
MAINTAINED DURING AND AFTER CONSTRUCTION.
2. AT ALL STAGES OF CONSTRUCTION (INCLUDING DEMOLITION WORKS), CONTRACTOR SHALL TAKE
MEASURES TO ENSURE ALL STAGNANT WATER FROM THE CONSTRUCTION SITE (BUILDING AND
CARPARK AREAS) IS REMOVED FROM THE SITE (TO THE SATISFACTION OF THE SUPERINTENDENT)
BEFORE AFFECTING THE EXISTING EXPOSED SOIL. THE CONTRACTOR SHALL ALLOW FOR THIS IN THEIR
TENDER.
3. SURFACE RUNOFF SHOULD BE PREVENTED FROM ENTERING CONSTRUCTION AREAS, PARTICULARLY
EXCAVATIONS AND FOOTING LOCATIONS, BY GRADING THE GROUND SURFACE AWAY FROM SUCH
AREAS, OR USING SURFACE INTERCEPTOR DRAINS. RUNOFF THAT IS GENERATED WITHIN THE
CONSTRUCTION AREAS MUST BE DIRECTED TO COLLECTOR DRAINS THROUGH THE PROVISION OF
SUITABLE GROUND SURFACE FALLS AND THEN CARRIED AWAY FROM THE WORKS IN SEALED
STORMWATER PIPES TO AN APPROPRIATE DISPOSAL OUTLET.
4. THE USE OF SUBSURFACE CUT-OFF DRAINS OR DRAINAGE BLANKETS WILL HELP PREVENT POSSIBLE
SUBSURFACE SEEPAGE FROM EXCAVATION FACES.
5. SHOULD WATER BE ALLOWED TO SOAK INTO EXISTING SOIL, THE CONTRACTOR IS TO EXCAVATE AND
REMOVE THE WATER-AFFECTED SOIL UNTIL SOIL WITH EXISTING, EQUILIBRIUM MOISTURE CONTENT IS
FOUND. THE EXCAVATED AREA IS THEN TO BE BACKFILLED WITH SELECTED FILL AND COMPACTED IN
ACCORDANCE WITH THE CIVIL SPECIFICATION.
6. FOR MORE DETAILS ON SITE RUN OFF CONTROL REFER TO GEOTECHNICAL INVESTIGATION REPORT
AND CIVIL SPECIFICATION.
7. SEDIMENT CONTROL DEVICES SHOULD BE INSTALLED AS A STANDARD POLLUTION CONTROL
FOLLOWING RECCOMENDATIONS BY THE E.P.A. IT IS RECOMMENDED THAT THESE METHODS ARE
ADOPTED ON SITE.
8. THE CONTRACTOR IS TO INSTALL APPROPRIATE SEDIMENT TRAPS AT ALL ENTRIES (AT SEP AND GIP)
TO THE UNDERGROUND STORMWATER DRAINS AND IN SWALES. INSTALL SEDIMENT FENCE AT SITE
PERIMETER WHERE SITE RUNOFF COULD CROSS. THE CONTRACTOR TO MAINTAIN THESE TRAPS
REGULARLY.
9. A "TEMPORARY CONSTRUCTION EXIT" SHALL BE INSTALLED AT A LOCATION AGREED WITH THE
SUPERINTENDENT ON SITE.

10/08/11

JAS

LEGEND

(EXISTING SERVICES LINETYPES)

EUG

EUG

EXISTING TELSTRA SERVICES


EXISTING ETSA SERVICES
EXISTING OVERHEAD ETSA SERVICES
COMMON SERVICES TRENCH

SSD

SSD

SWD

SWD

EXISTING FIRE MAIN


SUB SURFACE DRAIN
EXISTING GAS MAIN
EXISTING SEWER MAIN
EXISTING STORMWATER PIPE
EXISTING WATER MAIN

10/08/11

JAS

LEGEND
100K

600ID

NEW KERB:
100K = 100mm HIGH KERB
100K&G = 100mm HIGH KERB AND GUTTER
150K = 150mm HIGH KERB
150K&G = 150mm HIGH KERB AND GUTTER
200K = 200mm HIGH KERB
200K&G = 200mm HIGH KERB AND GUTTER
ES = EDGE STRIP
EHK = EXTENDED HEIGHT KERB
EHK&G = EXTENDED HEIGHT KERB AND GUTTER
TK = TRANSITION KERB
KB = KERB BREAK
RK&G = ROLLOVER KERB AND GUTTER
MK = MEDIAN KERB
MK&G = MOUNTABLE KERB AND GUTTER
INVERT DRAIN
JOINTING:
IJ = ISOLATION JOINT
TJ = TOOL JOINT
CJ = CONSTRUCTION JOINT
SCJ = SAW CUT JOINT
DCJ = DOWELLED CONSTRUCTION JOINT

RW

RETAINING WALL
NEW STORMWATER PIPE
AG DRAIN
EXISTING STORMWATER TO REMAIN
EXISTING STORMWATER TO BE REMOVED
SWALE
GRATED INLET PIT (GIP)
JUNCTION PIT (JP)
SIDE ENTRY PIT (SEP)

I.O.
DP
F/W

INSPECTION OPENING
DOWN PIPE
FLOOR WASTE
TRENCH GRATE
CHEQUER PLATE DRAIN

100.000

FFL 9.990

DESIGN LEVEL:
T.K. = TOP OF KERB
W.T. = BOTTOM OF KERB
I.L. = INVERT LEVEL
TOW = TOP OF WALL
BOW = BOTTOM OF WALL
BEW = BULK EARTHWORKS
FINISHED FLOOR LEVEL
SIGN

BL

BOLLARD
FENCE

TREE TO REMAIN

TREE TO BE REMOVED

BATTER SLOPE

HEADWALL

BRICK/BLOCK PAVING (NON VEHICULAR). REFER DRAWING ??? FOR DETAIL


BRICK/BLOCK PAVING (VEHICULAR). REFER DRAWING ??? FOR DETAIL
CONCRETE PAVEMENT (LIGHT DUTY). REFER DRAWING ??? FOR DETAIL
CONCRETE PAVEMENT (MEDIUM DUTY). REFER DRAWING ??? FOR DETAIL
CONCRETE PAVEMENT (HEAVY DUTY). REFER DRAWING ??? FOR DETAIL
HOTMIX PAVEMENT (LIGHT DUTY). REFER DRAWING ??? FOR DETAIL
HOTMIX PAVEMENT (MEDIUM DUTY). REFER DRAWING ??? FOR DETAIL
HOTMIX PAVEMENT (HEAVY DUTY). REFER DRAWING ??? FOR DETAIL
RUBBLE PAVEMENT. REFER DRAWING ??? FOR DETAIL
SPRAY SEAL PAVEMENT. REFER DRAWING ??? FOR DETAIL

10/08/11

JAS

5T

41

EXISTING SPOT LEVEL AT BACK OF KERB

41
.3

MOUNTABLE KERB & GUTTER

.35

150 HIGH KERB & GUTTER


150 HIGH KERB

100K&G
100 HIGH KERB & GUTTER
100K
ES

100 HIGH KERB

41

K&G

EXISTING SPOT LEVEL

41.3

EXISTING CONTOUR

40.600

DESIGN SPOT LEVEL

I.L. 9.990

INVERT LEVEL

40.600

DESIGN CONTOUR
INDICATES DIRECTION OF SURFACE FALL (SWALE)

EDGE STRIP

SEP

ID
INVERT DRAIN

SEP

EXISTING KERB AND GUTTER

GIP

EXISTING KERB AND GUTTER TO BE REMOVED


RW

EXISTING SPOT LEVEL AT TOP OF KERB


EXISTING SPOT LEVEL AT WATERTABLE

41

MOUNTABLE KERB

.35

MK

MK&G

.35

BK

LEGEND

RETAINING WALL

JP

DP

SIDE ENTRY PIT


EXISTING SIDE ENTRY PIT
GRATED INLET PIT
JUNCTION PIT
DOWNPIPE

TREE
TRENCH GRATE
EXISTING TREE TO BE RETAINED
PLATE DRAIN
EXISTING TREE TO BE REMOVED

375

FENCELINE

FFL 9.990

STORMWATER PIPE
FINISHED FLOOR LEVEL

10/08/11

JAS

SURVEY LEGEND
S.E.P.
WATER METER
STOBIE
LITTER BIN
TELSTRA PIT (SMALL)
TRAFFIC LIGHT
SIGN POST
INSPECTION OPENING
BOLLARD
MAIL BOX
SEWER I.P.
H

HYDRANT
INSPECTION COVER

GRATE
SUMP
GAS METER
SURVEY MARK
TELSTRA PIT (MEDIUM)
MANHOLE
INSPECTION POINT
TELSTRA PIT
STREET LIGHT
ELECTRIC CABLE COVER
S.E.P. (DOUBLE)
SIGNAL BOX
MANHOLE (STORMWATER)
FENCE

LEVEL INFORMATION
WATER TABLE
TOP OF KERB
EDGE OF CONCRETE
UPRIGHT KERB

NAT. SURF (BITUMEN)


X-OVER
EDGE OF PAVERS
INVERT

10/08/11

JAS

SURVEY LEGEND
128.53 WT

WATERTABLE LEVEL

CATHODIC PROT.MARKER

SIGN - HOARDING

MARKER POST

CABLE MARKER

TAP

IRRIG CONT.VALVE-SPRINKLER

TRAFFIC LIGHT

STOBIE POLE

SEWER MH - VENT

LIGHTPOLE

SEWER IP - IO

ETSA CONNECTION

EWS WATER METER - FP/SV

ETSA METER BOX

TELECOM PIT - PILLAR

STORM WATER MANHOLE

10/08/11

JAS

PAVEMENT
DETAILS:

ASHALTIC OVERLAY
BRICK / BLOCK PAVING
CONCRETE PAVEMENT
CONCRETE STEP DETAIL
HOTMIX PAVEMENT
RUBBLE PAVEMENT
SPRAY SEAL PAVEMENT
TIMBER EDGING
TOOLED JOINT
TURF / LANDSCAPING
TYPICAL ROAD CROSS SECTION

FINISHED SURFACE

PLANE EXISTING ASPHALT TO


ENABLE NEW OVERLAY TO FINISH
FLUSH WITH EXISTING FEATURES.

25mm HOTMIX
AC10 OVERLAY
300

EXISTING
ASPHALT

EXISTING BASE

EXISTING FEATURE WHICH


REMAIN. (KERB AND GUTTER IS
SHOWN FOR ILLUSTRATION)

NEW BASECOURSE
(THIN BASE SHOWN
FOR ILLUSTRATION)

ASPHALTIC OVERLAY
NTS

NOTE:
EXCAVATE EXISTING PAVEMENT, COMPACT
SURFACE AND KEY IN NEATLY

10/08/11

JAS

CONCEALED CONCRETE EDGE


STRIP. EMBEDDED MIN. 100mm
INTO FIRM GROUND (INSTALLED
AT ENGINEERS DISCRETION)

SELECTED PAVING
UNITS

ED
N
IG

25mm BEDDING SAND

SUBGRADE (100%
STANDARD COMPACTION)

125

E
D
E
B
O
T
T

20mm Q.R. (PM.2/20QG)


BASECOURSE
(95% MODIFIED COMPACTION)

YE

BRICK/BLOCK PAVING
(NON-VEHICULAR)
1:10

D
E
N

20mm F.C.R. (PM.1/20QM)


BASECOURSE
(98% MODIFIED COMPACTION)
20mm Q.R. (PM.2/20QG)
SUBBASE
(95% MODIFIED COMPACTION)
SUBGRADE (100%
STANDARD COMPACTION)

E
B
O

T
T
E

IG
S
DE

175

25mm BEDDING SAND

150

SELECTED PAVING
UNITS (80mm THK)

BRICK/BLOCK PAVING
(VEHICULAR)
1:10

10/08/11

JAS

CONCRETE SL52 MESH


CENTRAL GRADE N25

SUBGRADE (100%
STANDARD COMPACTION)

T
T
E

E
B
O

S
E
D

75
100

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)

E
N
IG

CONCRETE PAVEMENT
LIGHT DUTY
1:10

CONCRETE SL72 MESH


CENTRAL GRADE N25

E
D
E

B
O
T

SUBGRADE (100%
STANDARD COMPACTION)

100
125

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)

E
N
G
I

T
E
Y CONCRETE PAVEMENT

CONCRETE SL82 MESH


CENTRAL GRADE N32

O
T
T

YE

SUBGRADE (100%
STANDARD COMPACTION)

IG
S
E

D
E
B

150

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)

D
E
N

150

MEDIUM DUTY
1:10

CONCRETE PAVEMENT

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)
SUBGRADE (100%
STANDARD COMPACTION)

O
T
T

YE

D
E
N

D
E
B

IG
S
E

150

CONCRETE 2 LAYERS
SL82 MESH 50mm
COVER GRADE N40

200

HEAVY DUTY (TYPE 1)


1:10

CONCRETE PAVEMENT
HEAVY DUTY (TYPE 2)
1:10

10/08/11

JAS

600
FINISHED SURFACE
25
5mm WIDE x 3mm DEEP GROOVES AT
10mm CTS. IN 75mm GROUPING

300

LAP GTH
LEN

160

AT SS
RO
TH CKNE
I
TH

SL72 MESH, 30mm COVER

COMPACTED
SUBGRADE

200

FINISHED SURFACE

400

LAP GTH
LEN

CONCRETE STEP DETAIL


1:10

10/08/11

JAS

HOT MIX AC.10

E
B
O

T
T
YE

25

LIGHT DUTY
1:10

20mm F.C.R. (PM.1/20QM)


BASECOURSE
(98% MODIFIED COMPACTION)

SUBGRADE (100%
STANDARD COMPACTION)

75

HOTMIX PAVEMENT

HOT MIX AC.10

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)

75

ED
N
IG
S
DE

100

SUBGRADE (100%
STANDARD COMPACTION)

T
YE

100

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)

25

E
N
SIG
E
D
E
OB

20mm F.C.R. (PM.1/20QM)


BASECOURSE
(98% MODIFIED COMPACTION)

HOTMIX PAVEMENT
MEDIUM DUTY
1:10

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)
SUBGRADE (100%
STANDARD COMPACTION)

E
N
G
SI
E
ED
B
O

T
T
YE

230

20mm F.C.R. (PM.1/20QM)


BASECOURSE
(98% MODIFIED COMPACTION)

150

35

HOT MIX AC.14

HOTMIX PAVEMENT
HEAVY DUTY
1:10

10/08/11

JAS

SUBGRADE (100%
STANDARD COMPACTION)

T
T
E

E
B
O

IG
S
DE

150

D
E
N

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)

RUBBLE PAVEMENT
1:10

10/08/11

JAS

20mm Q.R. (PM.2/20QG)


SUBBASE
(95% MODIFIED COMPACTION)
SUBGRADE (100%
STANDARD COMPACTION)

D
E
OB

D
E
N

IG
S
E

100

2 COAT 14/7
SPRAY SEAL

T
T
YE SPRAY SEAL PAVEMENT
1:10

10/08/11

JAS

FINISHED SURFACE

200 x 35 PERMAPINE
50 x 50 x 300 PERMAPINE
STAKE

GALVANISED
FASTENER

TIMBER EDGING
(TE ON PLAN)
NTS

10/08/11

JAS

CUT EVERY SECOND WIRE IN


FABRIC ALONG LINE OF JOINT

10 x 20 DEEP GROOVE
TROWELLED IMMEDIATELY

TOOLED JOINT DETAIL


(TJ ON PLAN)
1:20

10/08/11

JAS

150

MIN. 150 THICK CLEAN


TOPSOIL/LOAM MIX. SEEK
DIRECTION FROM SMA

SUBGRADE (95%
COMPACTION)

TURF/LANDSCAPING
1:10

10/08/11

JAS

20.00m
3.50m

3.50m

3.50m

3%

3%

2.5%

=5H

N.S.

0.000

1V

3.50m

X
x

100K

2.5%

X
100K

5H
1V=

TYPICAL CROSS SECTION


ROAD ONE
NTS

10/08/11

JAS

STORMWATER
DETAILS:

BANDAGE JOINT
CHEQUER PLATE DRAIN DETAIL
DOWNPIPE CONNECTION
DOWNPIPE ENTRY TO REINFORCED CONCRETE PIPE
ENTRY TO RCP AT T-JUNCTION
GRATED TRENCH DRAIN DETAIL
HEADWALL DETAIL
INSPECTION OPENING
IRRIGATION DUCT FINISH
JUNCTION BOX WITH OPENING
JUNCTION PIT / GRATED INLET PIT DETAIL
ROCK FACE DETAILS - SCOUR PROTECTION
ROCK FILLED MATTRESS DETAIL
SADDLE PIT
SIDE ENTRY PIT 900 x 600
SIDE ENTRY PIT 1800 x 600 (1)
SIDE ENTRY PIT 1800 x 600 (2)
SIDE ENTRY PIT 1800 x 900
SIDE ENTRY PIT ON TRUNK DRAIN
STORMWATER SOAKAGE WELL
SUBSOIL DRAIN DETAIL
TRENCH GRATE SUMP
TRENCH INSTALLATION
TYPICAL RIP RAP DETAIL
TYPICAL SWALE CROSS SECTION
TYPICAL TRENCH DETAIL

200

150

PIPE

150

PIPE SHALL STOP AT


THE EXTERNAL FACE OF
BIG PIPE.

2N12 'U' BARS.


25MPa CONCRETE

2N12 'U' BARS.


300 COG.

75

75

SECTION A-A

BANDAGE JOINT
NTS

10/08/11

JAS

WELD COVER TO SIDES

6mm FLOOR PLATE


COVER.
300
100
DEEP

FINISHED SURFACE

6mm MILD STEEL HOT DIP


GALVANISED PLATE DRAIN

50mm BEDDING SAND

CHEQUER PLATE DRAIN DETAIL


1:10

10/08/11

JAS

100

15

300 x 300 x 6mm


CHECKER PLATE COVER

15

100

25

OPENING TO SUIT
DOWNPIPE

450

250

25

PLAN

NOTE:
DOWNPIPE OMITTED FOR CLARITY.

DOWNPIPE

EXPANSION JOINT

ALTERNATIVE POSITIONS
FOR DOWNPIPE
6mm MILD STEEL
CHECKER PLATE COVER

25

25

15

MIN. 300 COVER

DEPTH VARIES - MIN. 420

PAVEMENT LEVEL

100

RCP OUTLET-GRADE TO
MAIN STORMWATER DRAIN

15

100

250

100

450

SECTION A-A
DOWNPIPE CONNECTION DETAIL
1:10

10/08/11

JAS

100

30

FINISHED PAVEMENT LEVEL

150 DOWN PIPE


ENTRY
ROCLA SADDLE SLOPE
JUNCTION TO SUIT

RCP

150 TAKE OFF


CORE 180mm OPENING TO
RCP PIPE AS CLOSE AS
POSSIBLE TO OBVERT

SECTION

FIX SADDLE TO RCP PIPE IN


ACCORDANCE WITH
MANUFACTURERS DETAILS
30
150 DOWN PIPE

150 DOWN
PIPE ENTRY

150 TAKE OFF

PLAN
DOWNPIPE ENTRY TO
REINFORCED CONCRETE PIPE
NTS

10/08/11

JAS

CL
CENTRE LINE

ROCLA SADDLE SLOPE


JUNCTION TO SUIT
IPE

P
VC

UP

RCP

150 (OR 100) TAKE OFF


CORE 180mm OPENING TO
RCP PIPE

150 (OR 100)


TAKE OFF

FIX & SEAL TIGHT SADDLE TO


RCP PIPE IN ACCORDANCE
WITH MANUFACTURERS DETAILS

PLAN

SECTION

ENTRY TO RCP
AT T-JUNCTION
NTS

10/08/11

JAS

ACO HEELGUARD COMPOSITE


COVER TO DRAIN
FINISHED SURFACE
ACO DRAIN K100S PRESLOPED
SYSTEM IN LINE SUMP AT END
OF TRENCH
100mm THK. CONCRETE
ALL AROUND ACO DRAIN
(N25 GRADE CONCRETE)
SUBGRADE (100% STANDARD
COMPACTION)
NOTE:
ACO DRAIN SHALL BE ASSEMBLED AND LAID TO
MANUFACTURER'S SPECIFICATIONS.

GRATED TRENCH DRAIN DETAIL


NTS

10/08/11

JAS

60
2 x PIPE

200

PLAN

DISSIPATOR (DELETE
DISSIPATOR TO INLET
HEADWALL)

E
PIP
NOTE:
DISSIPATOR NOT SHOWN.

ELEVATION

OR 150 MIN.
4

300

DISSIPATOR (DELETE
DISSIPATOR TO INLET
HEADWALL)

150

OR 300 MIN.
3

600

2 x SL.82 MESH

200

SL82 MESH
CENTRAL

GRADE N40
CONCRETE (TYP.)

SECTION A-A
HEADWALL DETAIL
NTS

NOTE:
FLOODGATE INSTALLATION INFRONT OF HEADWALL
TO MANUFACTURERS SPECIFICATION.

10/08/11

JAS

LIFTING SOCKET WITH BYLON


PLUG COVER

445

GATIC CAST IRON IP COVER AND


CONCRETE SURROUND OR
APPROVED EQUIVALENT

368
237

FINISHED SURFACE

150 UPVC RISER WITH


REMOVABLE SEALING CAP

CAST IRON COVER TO BE MARKED


'SEWER' WITH 3mm HIGH LETTERS

SECTION A-A

PLAN

SURFACE INSPECTION OPENING DETAIL


NTS

75x50 HARDWOOD SUPPORTS TO


EXTEND 300mm PAST EACH SIDE
OF TRENCH.
CAST IRON COVER TO BE MARKED
"STORMWATER" WITH 10mm HIGH
LETTERING.

370

COVER LEVEL

PROVIDE 2 OFF 6mm LOCKDOWN


S/S ALLENHEAD SCREWS.
GROUND LEVEL
REINFORCED PRECAST CONCRETE.
100mm OR 150mm PVC
RISER WITH SCREWED CAP.

LIFTING LUG WITH NYLON PLUG.


445

PLAN

CLEAR OPENING :
150 FOR 100 RISER
230 FOR 150 RISER

SECTION A-A

SURROUNDING GROUND OMITTED FOR CLARITY.

INSPECTION OPENING
(I.O. ON PLAN)
NTS

10/08/11

JAS

RISER TO BE CAPPED AT FINISHED


SURFACE LEVEL TO ENABLE FUTURE
LOCATION BY OTHERS (APPLIES TO
BOTH END OF DUCT)
MARK KERB WITH YELLOW PAINT
FINISHED SURFAC

200

500

BASECOURSE
SUBBASE

100 UPVC IRRIGATION DUCT


NOTE:
SAND BACKFILL TO IRRIGATION DUCT
AND COMPACT TO 100% STD. MDD.

IRRIGATION DUCT FINISH


NTS

NOTE:
REFER TO ELECTRICAL DRAWINGS FOR LOCATIONS

10/08/11

JAS

150

900

150

GATIC TYPE 'E' COVER AND FRAME


400 x 600

PLAN
GATIC TYPE 'E' COVER AND FRAME
400 x 600

BRICKWORK OR MAKEUP UNITS TO SUIT


TWO LAYERS OF A.R.C. No.
SL62 MESH (50mm COVER)

750

PRECAST UNITS

C.J.
150

C.J.

SL62 MESH (50mm


COVER)

150

900

150

SECTION A-A
JUNCTION BOX WITH OPENING
1:20

10/08/11

JAS

GATIC COVER TO SUIT OR


APPROVED EQUIVALENT

REBATE TO SUIT

FINISHED SURFACE

DEPTH VARIES

SL72 MESH CENTRAL

MIN. 250 LAP

CJ

100

CJ

100

WIDTH
VARIES

REFER PLAN FOR SIZE


& ALIGNMENT OF
INLET/ PIPE OUTLET.

100

JUNCTION PIT (<0.8m)


GRATED INLET PIT DETAIL (<0.8m)
1:20

GATIC COVER TO SUIT OR


APPROVED EQUIVALENT

REBATE TO SUIT

FINISHED SURFACE

DEPTH VARIES

REFER TABLE

MAX PIT DEPTH

MESH

1200
1500
1800
2500

SL 72
SL 82
SL 92
SL 102

NOTES:
PROVIDE STEP IRONS IN
ACCORDANCE WITH AS1657 FOR PITS.

MIN. 400 LAP


CJ

150

CJ

150

WIDTH
VARIES

150

REFER PLAN FOR SIZE


& ALIGNMENT OF
INLET/ PIPE OUTLET.

JUNCTION PIT (>0.8m)


GRATED INLET PIT DETAIL (>0.8m)
1:20

10/08/11

JAS

DRAIN FINISHING LEVEL

500 MIN.

VARIES
1
ROCK TO BE 150 MIN. &
300 MAX.
EXCAVATION PROFILE
DRAIN INVERT

500 MIN.

BIDIM A34 GEOTEXTILE UNDER


ROCK OR APPROVED SIMILAR
COARSE QUARRY WASTE
COMPACTED AROUND ROCK

500 MIN.

ROCK FACE DETAILS


SCOUR PROTECTION
NTS

10/08/11

JAS

ROCK FILLED RENO MATTRESS


6.0m x 2.0m x 170mm
200

FINISHED SURFACE

BIDIM A24 GEOTEXTILE OR


APPROVED EQUIVALENT

ROCK FILLED MATTRESS DETAIL


NTS

10/08/11

JAS

N12 BARS

PLAN
GATIC COVER & FRAME TO SUIT
OR EQUIVALENT APPROVED
HEAVY DUTY IN CARPARK & ROADWAY
LIGHT DUTY IN FOOTPATH & LANDSCAPED AREAS.
FINISHED SURFACE

SL72 MESH CENTRAL

100
N12 BAR

200

N25 CONCRETE

250 x 250 SAWCUT HOLE


100

300 x 300

100

PIPE AS SPECIFIED

SECTION A-A

STORMWATER PIT
(SADDLE PIT)
NTS

10/08/11

JAS

A
150

900

150

600

REFER PLAN FOR SIZE


AND ALIGNMENT OF
INLET/OUTLET PIPE

KERB AND GUTTER

PLAN
HEAVY DUTY CAST IRON
COVER AND FRAME

REBATE TO SUIT

FINISHED SURFACE
FINISHED SURFACE

250 LAP

SL72 MESH
CENTRAL (TYP.)

CJ

150

CJ

600

150

SECTION A-A
SIDE ENTRY PIT DETAIL
900 x 600
1:20

10/08/11

JAS

150

900

300

80 FALL

1200

40 FALL

300

600

FLOW DIRECTION
80 FALL

40 FALL

100

600

REBATE TO
SUIT.

900

600

PLAN
GATIC COVER OR
APPROVED EQUIVALENT.

REBATE TO SUIT
FINISHED SURFACE

DEPTH VARIES

FINISHED SURFACE

2. COVERS TO BE BOLT DOWN TYPE BOLTS TO


BE STAINLESS STEEL WITH HEADS FOR 1/4"
ALLEN KEY AND 5/16" WHITWORTH THREADS.

CJ

CJ
150

NOTES:
1. COVER AND FRAME TO BE STANDARD
MANUFACTURE OF GATIC AUSTRALIA OR
SIMILAR APPROVED. REINFORCEMENTS TO BE
SL62 MESH UNLESS NOTED OTHERWISE.

250
LAP

SL.72 MESH
CENTRAL (TYP.)

150

600

150

SECTION A-A
SIDE ENTRY PIT DETAIL
1800 x 600
1:20

1. 1 BAY SIDE ENTRY PIT = 900 x 600.


2 BAY SIDE ENTRY PIT = 1800 x 600.
2. CONCRETE UNDULATIONS ARE ONLY NEEDED
WHEN ROAD FALL EXCEEDS 3%.
10/08/11

JAS

150

100

600

REBATE TO
SUIT.

40 FALL

300

45

80 FALL

80 FALL

FLOW DIRECTION

CO
UN NC
DU RE
LA TE
TIO
NS

600

300

A
40 FALL

B
1200

900

900

600

KERB
INVERT

140

50

INVERT

450

225

225

225

225

225

225

SECTION A-A
GATIC COVER OR
APPROVED EQUIVALENT.

REBATE TO SUIT
FINISHED SURFACE

DEPTH VARIES

FINISHED SURFACE

SL.72 MESH
CENTRAL
(TYP.)
250
LAP
NOTE:
COVER AND FRAME TO BE STANDARD
MANUFACTURE OF GATIC AUSTRALIA OR
SIMILAR APPROVED. REINFORCEMENTS TO BE
SL62 MESH UNLESS NOTED OTHERWISE.

CJ

CJ
150

100

TOP

200

PLAN

150

600

150

SECTION B-B
SIDE ENTRY PIT DETAIL
1800 x 600
1:20

1. 1 BAY SIDE ENTRY PIT = 900 x 600.


2 BAY SIDE ENTRY PIT = 1800 x 600.
2. CONCRETE UNDULATIONS ARE ONLY NEEDED
WHEN ROAD FALL EXCEEDS 3%.

10/08/11

JAS

C
150

1800

150

GUTTER WIDTH AS PER DESIGN.


(REFER DETAIL)

**

FOR W=600, X-FALL=80mm


FOR W=680, X-FALL=90mm

A
B

A
B

TOP OF KERB (BACK)

1200

X-FALL
40mm

300

300

*
*
X-FALL
APRON

*
*
X-FALL
APRON

FLOW DIRECTION

W=600 OR 680

X-FALL
40mm

INVERT OF KERB

G=300 OR 380

TOP OF KERB (FRONT)

600

1800

PLAN
NOTE:
COVER AND FRAME TO BE STANDARD MANUFACTURE OF
GATIC AUSTRALIA OR SIMILAR APPROVAL. REINFORCEMENOT
TO SCALE TO BE RF.62 FABRIC, UNLESS NOTED OTHERWISE.
(CAST IN LINTEL TO FRONT EDGE OF COVER)

CENTRAL SUPPORT BRACKET.


(FOR 1800 WIDE ONLY)

DEPTH VARIES

SL72 MESH
CENTRAL.
300 RCP U.N.O.
INLET / OULET PIPE.

C.J.

150

C.J.

SECTION A-A
TOP OF KERB

TH=

FOR H=100, TH=150mm


FOR H=150, TH=200mm

100 OR 150

150

INVERT OF KERB
BASE OF KERB

SECTION B-B
PAVING
INDICATIVE ONLY

DEPTH VARIES

1800

TH=

100 OR 150

150

SL72 MESH CENTRAL.


INLET / OULET PIPE.
C.J.
GRADE N25 CONCRETE BENCHING IN PIT TO
A HEIGHT OF 1/3 DIAMETER OF RC PIPE
(BENCHING TO BE HAND TROWELLED TO SUIT
PIPE ARRANGEMENT)

C.J.
150

300/380

(G=300)
(G=380)

150

600

150

SECTION C-C
900mm/1800mm SIDE ENTRY
PIT DETAIL (TYPE A)
1:20

10/08/11

JAS

210
50

CONSTRUCTION
JOINT
SL62 MESH
CENTRAL

BREAK & FORM


450 SQ. HOLE

MORTAR

1950 TRUNK DRAIN

SECTION B FOR SIDE ENTRY PIT


ON TRUNK DRAIN
NTS

10/08/11

JAS

CONCRETE COVER WITH LIFTING HOLE

PAVEMENT/GROUND LEVEL

1 PIPE LENGTH (2440mm)

DEPTH VARIES

SOCKETED CONCRETE
DRAINAGE PIPE

INLET PIPE- REFER CONTRACT


DRAWINGS FOR ALIGNMENT,
SIZE AND REDUCED LEVEL
VARIES - 1050
MIN.

PERVIOUS SOIL
(EG. SAND STRATUM)

40-65mm AGGREGATE

STORMWATER SOAKAGE WELL


NTS

10/08/11

JAS

DAMP PROOF MEMBRANE


ALONG SIDE MASONRY WALL
TOPSOIL OR PAVING

GRANULAR FREE DRAINING


MATERIAL (SAND OR SIMILAR)

FILTER GEOTEXTILE
GEOFABRICS BIDIM A24 OR
APPROVED EQUIVALENT
10-14mm SCREENINGS
300 MIN.

LAP GEOTEXTILE

100mm SLOTTED CORRUGATED


POLYETHYLENE SUBSOIL DRAIN
LAID ON MIN. 1% GRADE

FINISHED FLOOR LEVEL

300 MIN.

NOTE:
CROWN OF DRAIN TO BE BELOW
UNDERSIDE OF SLAB. (WRAP DRAIN
WITH BIDIM A24 GEOTEXTILE FABRIC)
OR AT SCREENINGS/N.S. INTERFACE

SUBSOIL DRAIN DETAIL


NTS

10/08/11

JAS

150 EVERLEVEL OR APPROVED


EQUIVALENT TRANSVERSE BAR
MEDIUM DUTY TRENCH GRATING
(GALVANISED)

DEPTHVARIES

FINISHED SURFACE

C.J.
100

C.J.

100

150

100

SL72 MESH
CENTRAL (TYP.)

TRENCH GRATE SUMP


MEDIUM DUTY
1:10

10/08/11

JAS

E
A

ALTERNATIVE SIDE SLOPE TO


SUIT NATURAL STABILITY

300 MIN.

0.7 D

OVERLAY ZONE

SIDE ZONE

HAUNCH ZONE

100 MIN

FOUNDATION BEDDING ZONE

TRENCH INSTALLATION
NTS

NOMINAL EXTERNAL
DIAMETER
D ( mm )

MINIMUM
WIDTH
A (mm )

HAUNCH
DEPTH
B (mm)
(0.3 x D mm)

MAXIMUM ALLOWABLE
WIDTH
E (mm)
TRENCH INSTALLATION

300
375
450
525
600
750
900

300

110

1.1

300

135

1.2

300

160

1.3

300

180

1.5

300

205

1.6

450

255

1.8

450

310

1.9

TYPICAL CONCRETE PIPE BEDDING


SUPPORT BACKFILL
10/08/11

JAS

VARIES
1

300 THICK LAYER OF ROCK


ROCK TO BE 150 MIN &
300 MAX.
EXCAVATION PROFILE

500 MIN.

BIDIM A34 GEOTEXTILE UNDER


ROCK OR APPROVED SIMILAR
100mm THICK LAYER
OF 65 BALLAST
(PM3)

500 MIN.

TYPICAL RIP RAP DETAIL


NTS

ROCK TO BE 150 MIN. & 300 MAX.

DRAIN INVERT

BIDIM A34 GEOTEXTILE UNDER


ROCK OR APPROVED SIMILAR

COARSE QUARRY WASTE


COMPACTED AROUND ROCK

RIP RAP DETAIL


NTS

10/08/11

JAS

BOUNDARY

TURN DOWN MIN. 300mm


FOR ANCHORAGE

CENTRELINE

5000

EXTEND TENSAR MAT MIN.


350mm INTO PAVEMENT.
LOCATE AT THE
SUBBASE/BASE INTERFACE

TENSAR MAT SCOUR


PROTECTION. COVER
WITH 100mm OF TOP SOIL

SLOPE VARIES FOR


DEPTH OF SWALE
REFER PLANS
900

TWO LAYERS OF 100mm


RIVER PEBBLES TO INVERT
OF SWALE (FULL LENGTH)

TYPICAL SWALE CROSS SECTION DETAIL


NTS

10/08/11

JAS

FINISHED SURFACE

TRENCH WIDTH

BACKFILL

300

OVERLAY ZONE *
COMPACTED ORDINARY FILL

100 110 VARIES

REINFORCED CONCRETE PIPE *

MAXIMUM DEPTH IN METRES

NATURAL GROUND SURFACE

HAUNCH ZONE *
COMPACTED SELECT FILL
BED ZONE *
COMPACTED SELECT FILL

ROCK/SOIL
FOUNDATION *

300 MIN.

CL

TYPICAL TRENCH DETAIL - RIGID PIPE


NTS

* :- REFER TO SPECIFICATION FOR INSTALLATION DETAILS.

FINISHED SURFACE
TRENCH WALL
TRENCH FILL (COMPACTED
SELECT FILL)
B

EMBEDMENT ZONE (BEDDING


SAND COMPACTED TO 95%
MODIFIED COMPACTION)

ZONE OF INFLUENCE
FOR SIDE SUPPORT

2.5 D

D
>75 <150
>150 <300
>300 <450
>450 <900

2.5 D

MINIMUM VALUES
B

75

100

100

100

150

150

100

200

150

150

300

150

TYPICAL TRENCH DETAIL - FLEXIBLE PIPE


NTS

NOTES:
REFER TO CIVIL SPECIFICATION FOR FURTHER
REQUIREMENTS

10/08/11

JAS

Вам также может понравиться