AJGS FORECAST

REV00

02ND DECEMBER 2015


ACCOMPLISHMENT
1

Installation of CLT Walls for Bungalow Type B2

2
3

Installation of CLT Walls for Bungalow Type A2


Installation of Steel Plates for Restaurant

Installation of Waterproofing Material for Bungalow Type C2

Arrival of Container No. 10 with Sheathing Materials

CONCERNS/ PROBLEMS ENCOUNTERED


1

AJGS will request for scaffolding & cut-off level for Bungalow Type D

03RD DECEMBER 2015

6:00 AM

7:00 AM

8:00 AM

ACTIVITY

7:00 AM

8:00 AM

9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM

RESTAURANT & KITCHEN


1
Installation of Steel Plates
REQUIREMENT
1

Tower Crane

Safety Floating Pontoon for Installation and Welding

BUNGALOW TYPE B2
1
Installation of CLT Walls
REQUIREMENT
1

Crawler Crane

Aluminum Scaffolding in the Bungalow Platform Area

BUNGALOW TYPE A2
1
Installation of CLT Walls
REQUIREMENT
1

Crawler Crane

Aluminum Scaffolding in the Bungalow Platform Area

BUNGALOW TYPE C2
1
Installation of Waterproofing Material
REQUIREMENT
1

Aluminum Scaffolding in the Bungalow Platform Area

STORAGE AREA TO BUNGALOW AREA


1
2

Unloading of Sheathing Materials - Container No. 10


Transferring of Materials for Bungalows

REQUIREMENT
1
Forklift
2

Telescopic Handler

9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM


2:00 PM

2:00 PM

3:00 PM

4:00 PM

5:00 PM

6:00 PM

3:00 PM

4:00 PM

5:00 PM

6:00 PM

7:00 PM