SUBRAMANYA EDUCATIONAL SOCIETY(R)

EAST WEST INSTITUTE OF TECHNOLOGY- BANGALORE-91.


DEPARTMENT OF CIVIL ENGINEERING
INTERNAL ASSESSMENT TEST I
SUB:STRUCTURAL ANALYSIS II
SEMESTER:V
DATE: 31-08-2015

SUB CODE: 10CV53


TIME:9.30-10.30 AM

______________________________________________________________________________
ANSWER ANY TWO QUESTIONS
1 a. Derive the slope deflection equation.
(8.5 MARKS)
b. What are the assumptions made in slope deflection equation.
(4 MARKS)
2. Analyse the continuous beam shown in figure 1 by slope deflection method. Draw B.M.D.
(12.5 MARKS)

3. Analyse the frame shown in figure 2 by slope deflection method. Draw B.M.D.
(12.5 MARKS)

SUBRAMANYA EDUCATIONAL SOCIETY(R)

EAST WEST INSTITUTE OF TECHNOLOGY- BANGALORE-91.


DEPARTMENT OF CIVIL ENGINEERING
INTERNAL ASSESSMENT TEST I
SUB:STRUCTURAL ANALYSIS II
SEMESTER:V
DATE: 31-08-2015

SUB CODE: 10CV53


TIME:9.30-10.30 AM

______________________________________________________________________________
ANSWER ANY TWO QUESTIONS
1 a. Derive the slope deflection equation.
(8.5 MARKS)
b. What are the assumptions made in slope deflection equation.
(4 MARKS)
2. Analyse the continuous beam shown in figure 1 by slope deflection method. Draw B.M.D.
(12.5 MARKS)

3. Analyse the frame shown in figure 2 by slope deflection method. Draw B.M.D.
(12.5 MARKS)