PROYECTO
UBICACIN
: SHANCAYAN/JAMANCA JIRCA/INDEPENDENCIA/HUARAZ/ANCASH
CENTRO ABASTECIMIENTO
: HUARAZ
FECHA
: ABRIL 2016
1- DATOS GENERALES
A-POR PESO
MATERIALES
UNIDAD
CANTIDAD
PESO.UNIT.
PESO.TOTAL
CEMENTO
BL.
11,780.73
42.50
500,680.90
UND
43,582.92
10.00
435,829.20
KG
41,361.71
1.00
41,361.71
CLAVOS Y GRAPAS
KG
470.15
1.00
470.15
P2
15,435.16
4.00
61,740.66
MADERA EUCALIPTO
UND
70.50
50.00
3,525.00
GAL
745.07
4.50
3,352.83
YESO
BL
297.6900
28.00
8,335.32
OTROS
KG
2,000.00
1.00
PESO TOTAL
B-POR VOLUMEN
EN AGREGADOS
DESCRIPC.
UNIDAD
AFECTOS IGV
SIN IGV
ARENA FINA
M3
3.9557
ARENA GRUESA
M3
1,052.2893
HORMIGN
M3
313.1637
PIEDRA CHANCADA
M3
1,052.2893
M3
177.1000
MATERIAL AFIRMADO
M3
1,440.5510
OTROS MATERIALES
M3
VOLUMEN TOTAL
CAPACIDAD DEL VOLQUETE (M3)
2,000.00
1,057,295.76
15.0000
4,054.35
15.00
270.29
REDONDEO
270.00
2- FLETE TERRESTRE
UNIDAD DE TRANSPORTE HUARAZ-OBRA
UNIDAD QUE DA COMPROBANTE
S/.
S/.
FLETE POR KG
0.02
DESCRIPCION
AFECTO IGV
SIN IGV
TOTAL
23,789.15
23,789.15
23,789.15
3- FLETE RURAL
MATERIALES
AGREGADOS
Cantidad
0.00
Peon S/.
Unidades de
Capacidad de
Nmero de
Flete no
Carga
Carga
Viajes
Afecto a IGV
1,057,296
1.00
42.50
24,877.55
0.00
4,054.35
1.00
0.0283
143,263.22
0.00
0.00
0.00
AFECTO IGV
23,789.15
0.00
23,789.15
TOTAL DE FLETE
23,789.15