Вы находитесь на странице: 1из 4

EL-MAHD

PIPING CLEANING & PRESSURE TEST REPORT


Package No.: EL-DAN-TP-01

Location: FA00 (HUMDIFIER PUMPS)

Report No.:HYD-01

Project: SUEZ STEEL

Client: DANILEI

Company: SUEZ STEEL CO.

Test Description: HYDROTEST

Test Procedure:- QC-WI-8.2.4.13

Test Date.: 25-09-2014

Test Description:
DRAWING #

Rev

DP03KF-FE21-P7000-TD122

06

TANK #

Rev
00

EQUIPMENT
From

To

Remarks:
Blowing and Cleaning Report
EL-MAHD

Signature: NA

Date:NA

DANIELI

Signature:NA

Date: NA
Test Conditions

Design Temperature: 135 C

Design Pressure: 18.7 BARG

Test Medium: WATER

Test Pressure Min.: 28 BARG

Required Test Duration: 1 HOURS

Water Quality Acceptable

Yes

Operating Pressure: 15.3 BARG

NO

Test Release
ELMAHD

Signature:

Date:-25-09-2013

DANIELI

Signature:

Date:-25-09-2013
Test Equipment

Gauge No.01 Range: 0 TO 100 BARG

Calibration Date:- 16/7/2015

Serial Number: 9135449

Gauge No.02 Range: 0 TO 100 BARG

Calibration Date:- 16/7/2015

Serial Number: 9135442

Test Results
Test Date: 25-09-2013

Actual Gauge Pressure:

29

BARG

Test Acceptance
ELMAHD

Signature:

Date: 25/9/2014

DANIELI

Signature:

Date: 25/9/2014
tank Restoration Complete ( after final alighment)

Re-Instatement Completed

Yes

NO

NA

ELMAHD

Signature:

Date:

DANIELI

Signature:

Date:

TENOVA (HYL)
PIPING CLEANING & PRESSURE
TEST REPORT

Doc. No: FRM-001


Rev: 00
Date: 30/02/2013
Page: 1 of 1

Package No.: NA

Location: FE41-CO2 Area

Report No.: HYL-SSC-002

Project: DP03KF

Client: DANILEI

Company: SUEZ STEEL CO.

Test Description: SERVICE TEST

Test Procedure:

Test Date.: 30-03-2013

Test Description:
P & ID Number

Rev

ISO Number

Rev

EQUIPMENT
From

To

DP03KF-FE41-P7000-TD528

LS-400-MO1-FE41.3729

DP03KF-FE41-P7000-TD528

LS-400-MO1-FE41.3730

DP03KF-FE41-P7000-TD528 & TD526

LS-550-MO1-FE41.3731

DP03KF-FE41-P7000-TD526

LS-400-MO1-FE41.3732

DP03KF-FE41-P7000-TD526

LS-400-MO1-FE41.3733

DP03KF-FE41-P7000-TD526

LS-400-MO1-FE41.3734

DP03KF-FE41-P7000-TD526

LS-400-MO1-FE41.3735

DP03KF-FE41-P7000-TD526 &TD523

LS-500-MO1-FE41.3736

DP03KF-FE41-P7000-TD523

LS-400-MO1-FE41.3737

DP03KF-FE41-P7000-TD523 &TD524

RS-500-MO1-FE41.4750

DP03KF-FE41-P7000-TD524

RS-550-MO1-FE41.4751

DP03KF-FE41-P7000-TD524

RS-350-MO1-FE41.4752

DP03KF-FE41-P7000-TD524

RS-350-MO1-FE41.4753

DP03KF-FE41-P7000-TD524

RS-350-MO1-FE41.4754

DP03KF-FE41-P7000-TD524

RS-350-MO1-FE41.4755

DP03KF-FE41-P7000-TD524

RS-350-MO1-FE41.4756

DP03KF-FE41-P7000-TD524

RS-350-MO1-FE41.4757

DP03KF-FE41-P7000-TD524

RS-550-MO1-FE41.4758

DP03KF-FE41-P7000-TD524

RS-400-MO1-FE41.4759

DP03KF-FE41-P7000-TD524

RS-400-MO1-FE41.4760

DP03KF-FE41-P7000-TD524

RS-400-MO2-FE41.4761

DP03KF-FE41-P7000-TD524

RS-400-MO2-FE41.4762

Remarks:

Service test is performed at operating conditions after the completing the modification and PWHT for above mentioned lines.
There were no leak found in the system under test.
Blowing and Cleaning Report

HYL

Signature:

Date:24-03-2013

DANIELI

Signature:

Date:
Test Conditions

Pipe Class: MO1/MO2

Design Temperature: 90 0C

Design Pressure: 15 BARG

Test Medium:NITROGEN/DEMIN WATER


Required Test Duration: 1.5 HOURS

Operating Pressure: 10 BARG

Test Pressure Min.: 10 BARG (At Operating Pressure)


Water Quality Acceptable

Yes

NO

Test Release
HYL

Signature:

Date: 24-03-2013

DANIELI

Signature:

Date:
Test Equipment

Gauge No.01 Range: NA

Calibration Date: NA

Date: NA

Gauge No.02 Range: NA

Calibration Date: NA

Date: NA

Test Results
Test Date: 30-03-2013

Actual Gauge Pressure: 9.98 BARG (At Operating Pressure)


Test Acceptance

HYL

Signature:

Date: 30-03-2013

DANIELI

Signature:

Date:

Piping Restoration Complete


Re-Instatement Completed

Yes

NO

NA

HYL

Signature:

Date:

DANIELI