Method Statement for Electrical Works

(Conduit Works (Embedded or Surface


Type))

TOTAL 9 PAGES
(Including Cover)

Purpose
PROJECTNAME

: Khabat Thermal Power PlantUnits 1&2

DOCUMENTNO.

:KP-00+++-CY712-BKM7103

TITLE

:Method Statement for Electrical Works (Conduit


Works (Embedded or Surface Type))

OWNER

For Information

Rev.
No.

DATE

First Issue
DESCRIPTION

Lokman Ektiren

For Approval
For Construction

:Ministry of Electricity (MOE) of


Kurdistan Regional Government

24.10.2015

For Review

As-Built

Ersin Gkda

Cuma Aydn

PREPARED
CHECKED
REVIEWED APPROVED
GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

Owner

Ministry of Electricity (MOE)


Of Kurdistan Regional Government
Contractor

POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor

GAMA POWER SYSTEMS


ENGINEERING & CONTRACTING, INC.

TABLE OF CONTENTS

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
2 of 10

PURPOSE

SCOPE OF WORK

RESPONSIBILITIES

DEFINITIONS / ABBREVIATIONS

PERSONNEL

MATERIALS

EQUIPMENT

EXECUTION

TECHNICAL INFORMATIONS

10

TIME LINE OF ACTIVITIES

11

PROGRESS MEASUREMENT

12

QUALITY REQUIREMENTS

13

HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS

14

RISK ASSESSMENTS

15

REFERENCES

1PURPOSE

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
3 of 10

This document is to clarify the general overview of the execution plan and method for the
cable conduit works ,which are embedded or surface types, set in KHABAT THERMAL
POWER PLANT Unit 1 & 2 Project located near Erbil City, KRG/Iraq.

The purpose of this Method Statement is to state the minimum key activities which shall be
carried out properly to execute the project objectives and requirements during Contract
period up to Issue Final Acceptance Certificate(FAC) by Employer for the project.

2SCOPE OF WORK

This method statement describeshow to create a complete secure conduit work and and
ensure the system sustainability during the power plant operation in light of the project
related drawings and standards.
Respectively, works will be in accordance to the related Specifications, Codes and
Standards, HSE Procedures and Approved Drawings.

3RESPONSIBILITIES

GAMA is responsible to ensure the healthiness of conduits and auxiliary materials during
construction and guarantee to keep the installed conduits in good condition as per the
project technical specification and general implementation rules and ensure the Quality
Assurance.

In order to provide performance of every sort of activities and operations (affecting the
quality of the product) pursuant to the defined documents, all deviations, errors or negative
issues shall be reported.

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
4 of 10

4DEFINITIONS / ABBREVIATIONS
PPE :Personal Protective Equipment
QCP : Quality Control Procedure
QA/QC : Quality Assurance/Quality Control
GAMA: GAMA G Sistemleri Mhendislik ve Taahht A..and GAMA Ltd.
FAC: Final Acceptance Certificate
QMS: Quality Management System
ITP:Inspection and Test Plan
HSE: Health, Safety and Environment

5PERSONNEL
Following personnel have been assigned for the performing of the field work by BUKEM
TELEKOM Ltd.

Site Electrical Engineer

Electrical Supervisor

QA/QC Engineer

HSE Engineer

Foreman

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
5 of 10

6MATERIALS
Equipments, tools, consumables and others shall be supplied by the contractor during the
construction.

7EQUIPMENTS

Spring (for bending)

Bending machine

Conduit Cutter

Vacuum Cleaner

Plier

Drilling Machine

8EXECUTION
Storage of the materials, transporting materials to the place where the work activity will
appear, precautions for work safety, preparations before commencing installation and
complete implementation with fulfilling the project specification and regulations shall be
considered as one part during the execution of work.

8.1 Receipt and Storage of Materials


Materials supplied by the contractor shall be kept in designated storage area which is
compatible with the material handling and storage procedures. All necessary precautions
against the outer caused damages shall be taken into consideration and applied with its all
aspects to protect fully.

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
6 of 10

8.2 Arrangement for Cable Conduit


All necessary equipments, hand tools and qualified team shall be ready prior to
commencement of installation.The responsible engineer for the particular work shall bring
the related drawings with him to avoid any incompatibility which could be faced while
activities on site. A brief safety tool box meeting shall be handled prior to commencement
of work.

8.3 Material Inspection and Clearences


Conduits and other project materials on site shall be re-inspected visually against
damages and keep in safe and good condition. Prior to giving start conduit works or to
other activities all necessary work clearances shall be completed with other disciplines in
coordination.
8.4 Precautions
Any activities such as conduiting and other related works shall not be executed without
valid work permit taken from responsible officer of main contractor. The activities around
and near the electrical equipments shall be categorized as crucial danger level to avoid
accidentially contact with live conductors etc.. Lighting necessaries shall be applied during
night work shift. All electrical and related works shall be carried out by competent and
qualified electricians.
8.5 Installation
8.5.1

Requirements prior to conduit work

Prior to start cable conduit work, the following site checkings should be followed properly.
All safety obligations shall be checked whether it is completed or not. The working shall be
checked prior to installation start whether it is suitable for insllation or not. If all aspects of
the work is completed thenthe conduit work could start.
8.5.2

Cable conduit work

Conduits, where they are placed on the surface, shall be exposed and all conduits shall
be routed to the suitable location till the power source or the tray for ease of installation of

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
7 of 10

cables. Conduit supports shall be fixed at particular intervals as per 50 cm with suitable
metal clamps for proper installation. Where bending is required the premanufactured
bends shall be installed for turns on vertical and horizontal directions. From cable tray to
the conduits and conduits to the equipment ,the extending of the cables shall be done via
flexible conduits with suitable glands.
Conduits, where they are placed in the concrete or wall structure, the conduit installation
method shall be embedded type. Conduits embedded in the concrete or wall structure
shall be installed as perdrawings and necessary controls for conduits shall be done before
concrete pouring. The conduits and boxes shall be fixed properly attaching on the steel
structure or wall structure with steel tie to prevent damages and keep it in the position
required during concrete pouring and for later fixture installation. Where ceiling type
lighting fixtures are available, conduits should be installed at least 10 cm away from the
fixturesin order not to damage the conduit while installation of the fixtures. Boxes shall be
installed where branching is available. Conduits on walls shall be installed after
completion of the wall chipping. All placement of metal boxes of power socket, lighting
switch and other services shall be completed according to the related drawings
considering also project technical requirements. If necessary the metal boxes shall be
mounted with the help of gypsum on wall.

9TECHNICAL INFORMATION

conc wall 200mm


conduit pipe
PVC Conduit Box
mortar filling
plastering finishing

1) Concrete wall
(1) 20mm depth chipping in conc wall

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
8 of 10

(2) 20mm conduit pipe, PVC conduit Box use


(3) 20mm mortar filling (same level of concrete surface) (4)
20mm plastering finishing

2) CMU wall

(1) Chipping
(2) Gypsum or Mortar filling
(3) 20 mm conduit pipe, PVC conduit Box (the surface should be same level with
gypsum plastering level) use
(4) Mortar filling to fill remaining area (same level of CMU surface) (5)
20 mm plastering,

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
9 of 10

10TIME LINE OF ACTIVITIES


N/A

11PROGRESS MEASUREMENT
Progress will be followed by BUKEM TELEKOM Site Representatives by daily.

12QUALITY REQUIREMENTS
Subcontractor shall strictly comply with the BUKEM TELEKOM Project QA/QC Plan.
Subcontractor is committed to establish, document, implement, and maintain the project
quality management system (QMS) and continually improve its effectiveness in accordance
with international standards.
Inspection and Test Plan (ITP) for Electrical Works(Cable Pulling,Termination,Jointing and
Conduit) (Doc. No: KP-00+++-CQ712-G0012) shall be followed during the execution of
works. Works and reporting shall be carried out by the Subcontractor in accordance to the
ITP and required documents mentioned on the ITP shall be submitted to BUKEM TELEKOM
for his review.

13HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS


All works shall be in compliance with the local laws and regulations, GAMA HSE Plan,
HSE Procedurs, requirements and instructions.

In addition all employees and GAMA subcontractor employees on site will have through
GAMA Project Safety Induction for site safety, health and environmental prior to work
activities. Other training courses will be attended as required by GAMA or POSCO as
required.

KHABAT TPP UNITS 1&2

Method Statement
for Electrical Works (Conduit Works(Embedded or
SurfaceType))

Doc. No KP-00+++-CY712-BKM7103
Rev. No.
0
Page
10 of 10

Each work scope or task will have a completed and approved Job Safety Analysis and
Risk Assessment (JSARA) identifying the potential hazards and control measures that will
be implemented to protect people and environment. The JSARA will be used by Supervisor
as the basis of conducting his daily site briefings for the workers.

In addition to the above, all employees conducting the works defined in this Method
Statement will wear basic PPE which is highly visible vest, hardhat, safety shoe, safety
googles. For additional safety requirements for a particular or specific task please refer to
the JSARA prepared for that task.

14RISK ASSESSMENTS
Risk Assesment can be found in Attachment 1.