SPURLINES OF JHPL PROJECT (PHASE 1A)

DAILY PROGRESS REPORT (SPURLINE WORKS)


CLIENT

: GAIL (INDIA) LIMITED

REPORT NO

169

CONSULTANT

: MECON LIMITED

REPORT DATE

24-May-16

COMPLETION DT.

: Mech. 09.07.2017, Pre-Comm & EGP -Drying & Comm - 09.10.2017 , FOA DT.10.07.2015 (For Spread-A)

PROGRESS DATE :

23-May-16

Sr.

Activity Description

UOM

Activity Start Date

Activity Completion Date

Scope of Work

SPREAD - A, KPTL (24'' x 83.69 KM)


Previous

Today's

Cummulative

Pre Construction Survey

Mtr

83686

83686.000

0.000

83686.000

ROU Route Survey

Mtr

11.02.2016

83686

17050.000

0.000

17050.000

ROU Handing Over

Mtr

01.04.2016

83686

9400.000

0.000

9400.000

Hindrance Free ROU Handover

Mtr

83686

0.000

0.000

0.000

ROU Clearing & Grading

Mtr

01.04.2016

83686

9400.000

0.000

9400.000

X-70 Gr Pipe

Mtr

27.09.2015

67686

46263.103

314.045

46577.148

Line Pipe Received


X-80 Gr Pipe

Mtr

05.02.2016

16000

14645.443

0.000

14645.443

83686

6232.073

0.000

6232.073

38

38

6000

395

16

411

72000

4989.022

215.855

5204.877
0

Stringing

Mtr

05.04.2016

Fabrication of Bends

Nos

15.04.2016

Nos
9

Mainline Welding

11

Completed

At Ch: 80

09.04.2016
Mtr

10

Remarks

Nos

695

Mtr

11686

Nos

6695

395

16

411

Free Tie/Tie-in Welding

Total Welding

09.04.2016
Mtr

83686

4989.022

215.855

5204.877

12

RT Taken

27.04.2016

6695

348

16

364

13

RT Interpretation

28.04.2016

6695

335

18

353

6695

239

14

253

NDT Total Accepted

Nos

AT Ch: 77 and 80

14
Repair %
15

Joint Coating

Nos

08.05.2016

7070

235

242

AT Ch: 77 and 80

16

Trenching

Mtr

17.05.2016

81736

78

85

163

From Ch: 80.400 towards dobhi

17

Lowering & Holiday Testing

Mtr

83686

18

HDPE Duct Laying

Mtr

83686

19

OFC Blowing

Mtr

83686

Mtr

Nos

Nos

38

Mtr

Nos

20

Mt

1950

Nos

20

21
22

23

Cased Crossings

Asphalted Roads/Cart Track


Canal/Nala/Drain Crossing

HDD Crossing

24

Pipeline Crossing

Nos

25

Backfilling

Mtr

83686

26

Cleaning & Gauging

Mtr

83686

27

Hydrotesting

Mtr

83686

28

Marker Installation

Direction Marker

Nos

275

Pipeline Warning Signs

Nos

160

Kilo Meter Posts

Nos

84

Aerial Marker

Nos

17

Navigable Waterway Marker

Nos

ROU Boundary Marker

Nos

765

29

Clean up & Restoration

Mtr

83686

CLIENT
CONSULTANT
COMPLETION DT.
FOA DT.

S.No

CATEGORY-1

1
2
3
4
5
6
7
8
9
10
11
12

13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
CATEGORY-2

1
2
3
4
5
6
7
8
9

SPURLINES OF JHPL PROJEC

DAILY PROGRESS REPORT (MC

AIL (INDIA) LIMITED

MECON LIMITED

Mech. 09.07.2017, Pre-Comm & EGP -Drying & Comm - 09.10.2017

07.2015 (For Spread-A)

EQUIPMENT Details (operator included)

ader

cavator/Back Hoe-Ex-280/300 & above of Equivalent

cavator/Back Hoe-Ex-200 & above of Equivalent

e Layer/Side boom -70T & above Capacity

e Layer/Side boom -60T & above Capacity

e Layer/Side boom -40T & above Capacity

e Bending Machine 24"Dia

zer With ripper-D7/D6 or Equivalent

G Welding Machines

mi Automatic Welding Machine

zer With ripper-D8 or Equivalent

dra (8-10MT)

to Welding Unit (3 welding machine per crew alongwith two internal clamp)

e Bevelling (Facing)Machine (appropriate size for Automatic Welding)

rizantal Auger Boring Machine with Rock Breaking tool

e Clamp (Pneumatic/Hydraulic)-Internal

e Mounted Cranes(75 MT & above)

DD Rig with all Equipment & Accessories (Cap.150T and above)

Ray M/C -Internal Crawler

Ray M/C -External

mma Source

ter Lifting Pump(400m3/hr,& above)

ing Pump (400 to 1000 m3/hr)

ssurization Pump -Motorized

UT with two Operators

uction/Resistance Heating Equipment or LPG Multi torch


Compressor -(300CFM)
Compressor -(450/600/800CFM)
Compressor-(1000-1500 CFM)

G Sets 62.5 KVA to 200 KVA (inclusive of generators)

st Cleaning Machine

e Trailers (FB/SemiLow Bed)

no Drill Crawler Mounted for rock blasting

nd Drill (Pneumatic) for Rock Blasting

ck Breaker Attachment

zing Pump

vel Cutting Machine -Manual


Machine

watering Pump

ilday Detector Unit

ad WT Tester

e Locator

e Clamp-External(24")

ble Cranes (As Required)

e Trailer for Coated Line Pipe

OJECT (PHASE 1A)


(MCEDS STATUS)
REPORT NO

REPORT DATE

PROGRESS DATE :

SPREAD - A, KPTL (24'' x 83.69 KM)


UOM

As progressive MCEDS
Contract Requirment End of
9th month

Available on Site

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

12

NOS

12

13

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

NOS

As Reqd

NOS

10

169
24-May-16
23-May-16

Remarks

SPURLINES OF JHP

DAILY PROGRESS REPORT (M


CLIENT
CONSULTANT
COMPLETION DT.
FOA DT.

SL NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17

18
19
20
21
22
23
24
25
26
27
28
29
30
31
32

SPURLINES OF JHPL PROJECT (PHASE 1

DAILY PROGRESS REPORT (MAN POWER DEPLOYMENT


: GAIL (INDIA) LIMITED
: MECON LIMITED
: Mech. 09.07.2017, Pre-Comm & EGP -Drying & Comm - 09.10.2017
10.07.2015 (For Spread-A)

DESCRIPTION
Resident Construction Manager/ Section Incharge
Planning Engineer
QA/QC Engineer
Safety Officer
Qualified Surveyor
Welding/NDT Engineer/AUT Interpreter
Discipline Engineers (Civil/Mech/Instrn.)
Foreman/Supervisor
Civil Surveyor/Liaison team consisting of 2 (two) members
Document Controller/Account Officer (For Line Pipe)
Store Keeper / Store Incharge
Welder ( Manual/Semi-Auto/Automatic)
Fitter
Grinder
Machine Operator
Blast Cleaning Crew consisting of 5 (five) persons
Electrician / Machine Mechanic

Rigger
Drivers
Pipe Bending Crew
Rock Breaker Crew (As required)
Thrust./Hor.Auger Boring Crew
X-ray/Gamma ray Crew
Hydrotesting Crew
Field Joint Coating Crew
Holiday Testing Crew
HDD Crew
OFC Jointing Crew
Civil Survey Crew (with equipment)
Station Civil Works (Carpenter/Bar-Bender/Mason/Fitter etc.)
Unskilled Workers
Station Mechanical, Pre-Fabrication / Erection Crew

F JHPL PROJECT (PHASE 1A)

ORT (MAN POWER DEPLOYMENT)


REPORT NO

REPORT DATE

PROGRESS DATE :

SPREAD - A, KPTL (24'' x 83.69 KM)


Total Requirements as per
Total Available at Site
contract
1/1

6(1/4/1)

20

2/2

1/1

1/1

1/1

1/1

10

12

12

12

As Req

As Req

30

25

As Req

As Req

4/2

As Req

As Req

35

20

169
24-May-16
23-May-16

24'' x 83.69 KM)


Remarks

SPURLINES O

H
CLIENT

: GAIL (INDIA) LIMITED

CONSULTANT

: MECON LIMITED

COMPLETION DT.

: Mech. 09.07.2017, Pre-Comm & EGP -Drying & Comm 09.10.2017

FOA DT.

10.07.2015 (For Spread-A)


Sr. No

Description

Safe Man Hours

Tool Box Meeting

First Aid Cases

Lost Time Cases

Medical Treatment

Environmental Cases

Near Misses

SPURLINES OF JHPL PROJECT (PHASE 1A)

HSE Statistics
REPORT NO

REPORT DATE

PROGRESS DATE :

Previous

Today

9200

1190

23

A)

169
24-May-16
23-May-16

Cumulative
10390
27
0
0
0
0
0

SPURLINES OF JHP

DAILY PROGRESS REPORT (Ne


CLIENT

: GAIL (INDIA) LIMITED

CONSULTANT

: MECON LIMITED

COMPLETION DT.

: Mech. 09.07.2017, Pre-Comm & EGP -Drying & Comm - 09.10.2017

FOA DT.

10.07.2015 (For Spread-A)

Site Office Key Person


Sr. No

Description

Resident Construction Manager/ Section


Incharge

Planning

QA/QC Engineer

HR/Admin ( Liasoning )

Store Incharge

Site Activities Responsibility Details


Sr. No

Activities

Line Pipe Receiving

ROU Route Survey

ROU Cleaning /Grading

Stringing

Bending

Mainline Welding

Free Tie-in / Tie-in

NDT

Joint Coating

10

Trenching

11

Lowering

12

Duct Laying

13

Backfilling

14

OFC Blowing

15

Cased Crosssing

16

HDD Work

17

Hydrotesting

18

Marker Installation

19

Restoration

Remarks:

SPURLINES OF JHPL PROJECT (PHASE 1A)


DAILY PROGRESS REPORT (Next Day Plan with Contact Numbers)

& EGP -Drying & Comm - 09.10.2017

Location

Name

Gaya Office

Mr.Vinod Singh Tomar

Gaya Office

Pavan Mishra/Mintu Choudhury

Gaya Office

Joydev Dalai/Vinay Sharma

Gaya Office

Raghunath Sekhawat

Gaya Office

M. Haque

Location

Responsible Person

Pipeyard at Bhindus

M. Haque

At Ch: 64 towards Dobhi

Dinesh Kumar Singh

At Ch: 69 owards Dobhi

D.K Singh/Tarun Kumar

At Ch: 77 towards Dobhi

Deepak Tomar

At Bhindas Yard

Rama Shankar Roy

At Ch:80 towards Patna Top

Rohit Choubey

At Ch: 77 towards Dobhi

Saumey Shrivastav

At Ch: 78 towards Dobhi

Mukesh Kumar

At Ch: 80 towards Dobhi

Tarun Kumar

1A)

umbers)
REPORT NO

169

REPORT DATE

24-May-16

PROGRESS DATE :

23-May-16

Contact No.

Remarks

7260898910
7260898905/7260898904
7260898902/7260898908
7260898901
7260898907

Contact No.
7260898907
7260898924
7260898917/7260898918
7260898922
7260898919
7260898916

7260898921
7260898926
7260898918

Remarks

SPURLINE
Client

: M/s. GAIL (India) Ltd.

PMC

: M/s. MECON Ltd.

Contactor

: M/s. Kalpataru Power Transmission Ltd.

FOA No

: GAIL/NOIDA/C&P/PROJ/JHPL/LAYING/015-002/13 Dated 10.07.2015

HINDRANCE REC
Sr.No

Date of Hindrance

11.07.2015 to 27.12.2015

28.12.2015

29.12.2015 to 11.02.2016

12.02.2016

12.02.2016 to 23.03.2016

01.04.2016

02.04.2016

03.04.2016

04.04.2016

10

05.04.2016

11

06.04.2016

12

07.04.2016

13

08.04.2016

14

09.04.2016

15

10.04.2016

16

11.04.2016

17

12.04.2016

18

13.04.2016

19

14.04.2016

20

15.04.2016

21

16.04.2016

22

17.04.2016

23

18.04.2016

24

19.04.2016

25

20.04.2016

26

21.04.2016

27

22.04.2016

28

23.04.2016

29

24.04.2016

30

25.04.2016

31

26.04.2016

32

27.04.2016

33

28.04.2016

34

29.04.2016

34

29.04.2016

35

30.04.2016

36

01.05.2016

37

02.05.2016

38

03.05.2016

39

04.05.2016

40

05.05.2016

40

05.05.2016

41

06.05.2016

42

07.05.2016

43

08.05.2016

44

09.05.2016

45

11.05.2016

46

12.05.2016

47

13.05.2016

48

14.05.2017

49

15.05.2017

50

16.05.2017

51

17.05.2017

52

18.05.2017

53

19.05.2017

54

20.05.2017

55

21.05.2017

56

22.05.2017

57

23.05.2017

SPURLINES OF JAGDISHPUR-PHULPUR-HA
(India) Ltd.

ON Ltd.

ataru Power Transmission Ltd.

IDA/C&P/PROJ/JHPL/LAYING/015-002/13 Dated 10.07.2015

HINDRANCE RECORD
Description

ROU not available due to non- issuance of Sec 6(1) notification


Sec 6(1) notification published for approx 10 km form Ch: 83.6 to 73.6
Sec 6(1) notification published for approx 10 km form Ch: 83.6 to 73.6
but revenue team not available for panchnama
Revenue team available at site and panchnama started
Panchnama in progress
Grading work started from CH: 83.6 , and progress hampered due to
non-payment of the compensation by GAIL
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0

Grading Progress hampred due to non-payment of the compensation by


GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampred due to non-payment of the compensation by
GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading work was stopped by farmers ue to non-payment of the
compensation by GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress is hampred due to non-payment of the compensation
by GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading Progress hampered by farmers due to non-payment of the
compensation by GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0

Grading work stopped by Farmers


Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Grading work stopped by Farmers
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Stringing work stopped by Farmers
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Work stopped by land users due to non-payment of the compensation
by GAIL
Survey Team idle due to non issuance of sec 6(1) notification for ch: 73.6
to Ch: 0
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 due to non payment
of compensation by GAIL after 11 AM
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL

Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL

Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 79 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 79 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 after 2.00 PM due to non
payment of compensation by GAIL

Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 80 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL

Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL

Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL

PURLINES OF JAGDISHPUR-PHULPUR-HALDIA PIPELINE PROJECT PHASE 1 SPREAD A

CE RECORD
Duration of Hindrance
Affected Activities

Location
From

Survey and subsequent activities

11.07.2015

Survey and subsequent activities

Survey and subsequent activities

Grading and subsequent activities


Grading and subsequent activities

Grading

Grading

Ch: 83.5

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 83.2

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 83.1

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 83

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

6:00 AM

6:00 AM

6:00 AM

Grading

Ch: 82.9

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 82.8

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 82.5

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 82.2

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 82

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

Grading

Ch: 81.7

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Grading

Ch: 81.6

1:00 PM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Grading

Ch: 81.6

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Grading

Ch: 81.3

6.00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

6:00 AM

6:00 AM

6:00 AM

6:00 AM

6:00 AM

Grading

Ch: 80

6.00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Grading

Ch: 79

6.00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Stringing

Ch: 81

6.00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Mainline Welding

Ch: 82

6.00 AM

Survey and subsequent activities

Ch: 73.6 to Ch: 0.00

6:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

11:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Mainline Welding

Ch: 82

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 69

6:00 AM

Mainline Welding

Ch: 79

3:00 PM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 69

6:00 AM

Mainline Welding

Ch: 79

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 69

6:00 AM

Stringing

Ch: 78.5

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 69

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 69

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 69

6:00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

2.00 PM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Trenching

Ch: 80

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Trenching

Ch: 79.350

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Trenching

Ch: 79.350

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Trenching

Ch: 79.350

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Trenching

Ch: 79.350

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Trenching

Ch: 79.350

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

Grading and subsequent activities

Ch: 76.712 to 76.412


and Ch: 70

6:00 AM

Stringing

Ch: 77

6.00 AM

REPORT NO

169

REPORT DATE

24-May-16

PROGRESS DATE :

23-May-16

Duration of Hindrance
Remarks
To
27.12.2015

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
12.00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM

12.00 PM
6:00 PM
11.00 AM
6:00 PM
2.00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6.00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM

6:00 PM

6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM

6:00 PM
6:00 PM
6:00 PM

12:30 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM

6:00 PM

6:00 PM

6:00 PM
6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM
6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM

6:00 PM