Академический Документы
Профессиональный Документы
Культура Документы
REPORT NO
169
CONSULTANT
: MECON LIMITED
REPORT DATE
24-May-16
COMPLETION DT.
: Mech. 09.07.2017, Pre-Comm & EGP -Drying & Comm - 09.10.2017 , FOA DT.10.07.2015 (For Spread-A)
PROGRESS DATE :
23-May-16
Sr.
Activity Description
UOM
Scope of Work
Today's
Cummulative
Mtr
83686
83686.000
0.000
83686.000
Mtr
11.02.2016
83686
17050.000
0.000
17050.000
Mtr
01.04.2016
83686
9400.000
0.000
9400.000
Mtr
83686
0.000
0.000
0.000
Mtr
01.04.2016
83686
9400.000
0.000
9400.000
X-70 Gr Pipe
Mtr
27.09.2015
67686
46263.103
314.045
46577.148
Mtr
05.02.2016
16000
14645.443
0.000
14645.443
83686
6232.073
0.000
6232.073
38
38
6000
395
16
411
72000
4989.022
215.855
5204.877
0
Stringing
Mtr
05.04.2016
Fabrication of Bends
Nos
15.04.2016
Nos
9
Mainline Welding
11
Completed
At Ch: 80
09.04.2016
Mtr
10
Remarks
Nos
695
Mtr
11686
Nos
6695
395
16
411
Total Welding
09.04.2016
Mtr
83686
4989.022
215.855
5204.877
12
RT Taken
27.04.2016
6695
348
16
364
13
RT Interpretation
28.04.2016
6695
335
18
353
6695
239
14
253
Nos
AT Ch: 77 and 80
14
Repair %
15
Joint Coating
Nos
08.05.2016
7070
235
242
AT Ch: 77 and 80
16
Trenching
Mtr
17.05.2016
81736
78
85
163
17
Mtr
83686
18
Mtr
83686
19
OFC Blowing
Mtr
83686
Mtr
Nos
Nos
38
Mtr
Nos
20
Mt
1950
Nos
20
21
22
23
Cased Crossings
HDD Crossing
24
Pipeline Crossing
Nos
25
Backfilling
Mtr
83686
26
Mtr
83686
27
Hydrotesting
Mtr
83686
28
Marker Installation
Direction Marker
Nos
275
Nos
160
Nos
84
Aerial Marker
Nos
17
Nos
Nos
765
29
Mtr
83686
CLIENT
CONSULTANT
COMPLETION DT.
FOA DT.
S.No
CATEGORY-1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
CATEGORY-2
1
2
3
4
5
6
7
8
9
MECON LIMITED
ader
G Welding Machines
dra (8-10MT)
to Welding Unit (3 welding machine per crew alongwith two internal clamp)
e Clamp (Pneumatic/Hydraulic)-Internal
mma Source
st Cleaning Machine
ck Breaker Attachment
zing Pump
watering Pump
ad WT Tester
e Locator
e Clamp-External(24")
REPORT DATE
PROGRESS DATE :
As progressive MCEDS
Contract Requirment End of
9th month
Available on Site
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
12
NOS
12
13
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
NOS
As Reqd
NOS
10
169
24-May-16
23-May-16
Remarks
SPURLINES OF JHP
SL NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
DESCRIPTION
Resident Construction Manager/ Section Incharge
Planning Engineer
QA/QC Engineer
Safety Officer
Qualified Surveyor
Welding/NDT Engineer/AUT Interpreter
Discipline Engineers (Civil/Mech/Instrn.)
Foreman/Supervisor
Civil Surveyor/Liaison team consisting of 2 (two) members
Document Controller/Account Officer (For Line Pipe)
Store Keeper / Store Incharge
Welder ( Manual/Semi-Auto/Automatic)
Fitter
Grinder
Machine Operator
Blast Cleaning Crew consisting of 5 (five) persons
Electrician / Machine Mechanic
Rigger
Drivers
Pipe Bending Crew
Rock Breaker Crew (As required)
Thrust./Hor.Auger Boring Crew
X-ray/Gamma ray Crew
Hydrotesting Crew
Field Joint Coating Crew
Holiday Testing Crew
HDD Crew
OFC Jointing Crew
Civil Survey Crew (with equipment)
Station Civil Works (Carpenter/Bar-Bender/Mason/Fitter etc.)
Unskilled Workers
Station Mechanical, Pre-Fabrication / Erection Crew
REPORT DATE
PROGRESS DATE :
6(1/4/1)
20
2/2
1/1
1/1
1/1
1/1
10
12
12
12
As Req
As Req
30
25
As Req
As Req
4/2
As Req
As Req
35
20
169
24-May-16
23-May-16
SPURLINES O
H
CLIENT
CONSULTANT
: MECON LIMITED
COMPLETION DT.
FOA DT.
Description
Medical Treatment
Environmental Cases
Near Misses
HSE Statistics
REPORT NO
REPORT DATE
PROGRESS DATE :
Previous
Today
9200
1190
23
A)
169
24-May-16
23-May-16
Cumulative
10390
27
0
0
0
0
0
SPURLINES OF JHP
CONSULTANT
: MECON LIMITED
COMPLETION DT.
FOA DT.
Description
Planning
QA/QC Engineer
HR/Admin ( Liasoning )
Store Incharge
Activities
Stringing
Bending
Mainline Welding
NDT
Joint Coating
10
Trenching
11
Lowering
12
Duct Laying
13
Backfilling
14
OFC Blowing
15
Cased Crosssing
16
HDD Work
17
Hydrotesting
18
Marker Installation
19
Restoration
Remarks:
Location
Name
Gaya Office
Gaya Office
Gaya Office
Gaya Office
Raghunath Sekhawat
Gaya Office
M. Haque
Location
Responsible Person
Pipeyard at Bhindus
M. Haque
Deepak Tomar
At Bhindas Yard
Rohit Choubey
Saumey Shrivastav
Mukesh Kumar
Tarun Kumar
1A)
umbers)
REPORT NO
169
REPORT DATE
24-May-16
PROGRESS DATE :
23-May-16
Contact No.
Remarks
7260898910
7260898905/7260898904
7260898902/7260898908
7260898901
7260898907
Contact No.
7260898907
7260898924
7260898917/7260898918
7260898922
7260898919
7260898916
7260898921
7260898926
7260898918
Remarks
SPURLINE
Client
PMC
Contactor
FOA No
HINDRANCE REC
Sr.No
Date of Hindrance
11.07.2015 to 27.12.2015
28.12.2015
29.12.2015 to 11.02.2016
12.02.2016
12.02.2016 to 23.03.2016
01.04.2016
02.04.2016
03.04.2016
04.04.2016
10
05.04.2016
11
06.04.2016
12
07.04.2016
13
08.04.2016
14
09.04.2016
15
10.04.2016
16
11.04.2016
17
12.04.2016
18
13.04.2016
19
14.04.2016
20
15.04.2016
21
16.04.2016
22
17.04.2016
23
18.04.2016
24
19.04.2016
25
20.04.2016
26
21.04.2016
27
22.04.2016
28
23.04.2016
29
24.04.2016
30
25.04.2016
31
26.04.2016
32
27.04.2016
33
28.04.2016
34
29.04.2016
34
29.04.2016
35
30.04.2016
36
01.05.2016
37
02.05.2016
38
03.05.2016
39
04.05.2016
40
05.05.2016
40
05.05.2016
41
06.05.2016
42
07.05.2016
43
08.05.2016
44
09.05.2016
45
11.05.2016
46
12.05.2016
47
13.05.2016
48
14.05.2017
49
15.05.2017
50
16.05.2017
51
17.05.2017
52
18.05.2017
53
19.05.2017
54
20.05.2017
55
21.05.2017
56
22.05.2017
57
23.05.2017
SPURLINES OF JAGDISHPUR-PHULPUR-HA
(India) Ltd.
ON Ltd.
HINDRANCE RECORD
Description
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 82 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 whole day due to
non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 79 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Mainline welding was stopped by villagers at Ch: 79 whole day due to non
payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villageres at Ch: 78.5 whole day due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 after 2.00 PM due to non
payment of compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 80 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Trenching work could not be started at Ch: 79.350 due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
Grading was stopped by Villagers at Ch: 76.712 to 76.412 and Ch: 69 whole
day due to non payment of compensation by GAIL
Stringing was stopped by villagers at Ch: 77 whole day due to non payment of
compensation by GAIL
CE RECORD
Duration of Hindrance
Affected Activities
Location
From
11.07.2015
Grading
Grading
Ch: 83.5
Grading
Ch: 83.2
Grading
Ch: 83.1
Grading
Ch: 83
6:00 AM
6:00 AM
6:00 AM
6:00 AM
Grading
Ch: 82.9
Grading
Ch: 82.8
Grading
Ch: 82.5
Grading
Ch: 82.2
Grading
Ch: 82
Grading
Ch: 81.7
6:00 AM
Grading
Ch: 81.6
1:00 PM
6:00 AM
Grading
Ch: 81.6
6:00 AM
6:00 AM
Grading
Ch: 81.3
6.00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
Grading
Ch: 80
6.00 AM
6:00 AM
Grading
Ch: 79
6.00 AM
6:00 AM
Stringing
Ch: 81
6.00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
Mainline Welding
Ch: 82
6.00 AM
6:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
11:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 82
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 79
3:00 PM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Mainline Welding
Ch: 79
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
Stringing
Ch: 78.5
6:00 AM
6:00 AM
6:00 AM
6:00 AM
6:00 AM
Stringing
Ch: 77
2.00 PM
6:00 AM
Stringing
Ch: 77
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
Trenching
Ch: 80
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
Trenching
Ch: 79.350
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
Trenching
Ch: 79.350
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
Trenching
Ch: 79.350
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
Trenching
Ch: 79.350
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
Trenching
Ch: 79.350
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
6:00 AM
Stringing
Ch: 77
6.00 AM
REPORT NO
169
REPORT DATE
24-May-16
PROGRESS DATE :
23-May-16
Duration of Hindrance
Remarks
To
27.12.2015
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
12.00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
12.00 PM
6:00 PM
11.00 AM
6:00 PM
2.00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6.00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
12:30 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM
6:00 PM