Академический Документы
Профессиональный Документы
Культура Документы
Unit
S.Y.
Quanity
26,000
S.Y.
2,400
L.S.
Forde Construction
Company Inc.
Durwood Greene
Construction Co.
Unit Price
1.19
Total
30,940.00
Unit Price
1.45
Total
37,700.00
Unit Price
1.40
Total
36,400.00
Unit Price
1.39
Total
36,140.00
Unit Price
1.50
Total
39,000.00
2.75
6,600.00
3.60
8,640.00
3.75
9,000.00
2.39
5,736.00
3.00
7,200.00
5,000.00
5,000.00
1,500.00
1,500.00
2,000.00
2,000.00
5,000.00
5,000.00
3,000.00
3,000.00
2,600.00
2,600.00
2,500.00
2,500.00
4,000.00
4,000.00
5,000.00
5,000.00
5,000.00
5,000.00
4.00
960.00
2.00
480.00
2.35
564.00
2.00
480.00
2.50
600.00
L.S.
L.F.
240
TOTAL BID
46,100.00
50,820.00
51,964.00
52,356.00
54,800.00
BID TABULATION
2009 Asphalt Milling Project
Double Oak
Construction.Inc.
Item
Description
1
2" Asphalt Surface Milling & Transportation
of Milled Materials to Storage Site Complete
Unit
S.Y.
Quanity
26,000
Unit Price
1.75
Total
45,500.00
Unit Price
1.57
Total
40,820.00
2.75
6,600.00
3.15
7,560.00
S.Y.
2,400
L.S.
3,500.00
3,500.00
5,500.00
5,500.00
L.S.
1,500.00
1,500.00
9,009.53
9,009.53
L.F.
240
3.00
720.00
2.29
549.60
TOTAL BID
57,820.00
63,439.13
Unit Price
Total
Unit Price
Total
Unit Price
Total