Академический Документы
Профессиональный Документы
Культура Документы
Boiler
This installation consists of two drum water tube MITSUBISHI MAC-**BF type marine boiler with oil
and gas combination burners located in the furnace roof. The unit is composed of a steam drum and
a water drum connected by a bank of inclined generating tubes. Other water side components
include : front screen tubes, side and roof water wall, front and rear water wall tubes, down-comers,
roof and bottom front wall headers, and roof and bottom rear wall headers. Each tube in the furnace
floor, side & roof, front and rear wall are jointed to the adjacent tube by welding. In this welded wall
construction, the tubes forms a gas-tight envelop three side of the furnace. Since the combination
burners are located in the furnace roof, the gas flow from the furnace is evenly distributed across the
front bank and generating banks, then, discharged from the uptake of boiler.
Fig 2-1
3-1
K1D97-N57-10M-M501
2.2
Drum Internals
Steam drum internals consists of surface blow line, internal feed pipe, chemical feed line, baffles and
dry box. Steam generated in the boiler tubes enters the steam drum, where it is forced to pass
through a baffle located at the normal water level before entering the upper part of the steam drum.
Before leaving the boiler through the outlet nozzle, the steam must pass through the dry box located
at the top of the drum. Manholes fitted with hinged manhole covers are provided in the front head of
the steam drum and water drum. The hinges allow the manhole covers to swing into the drum clear of
the manhole.
2.3
Furnace
Water cooled walls are provided by lining the furnace side, floor and roof with a single row of 88.9 mm
tubes, and front and rear with a single row of 76.2 mm tubes. External down comers provide ample
circulation to water drum. The water cooled floor consists of 88.9 mm tubes traversing the furnace
floor from the water drum, then bending to form the furnace side and roof, which terminates in the
steam drum. Furnace front and rear wall tubes arranged from the lower to the upper water wall
headers cover front and rear furnace walls. Upper front and rear water wall headers are connected to
the steam drum. Because water wall tubes are jointed to their adjacent tubes in a welded wall
construction, they form a gas tight envelops lining the furnace.
Where openings are required for burners, access doors and soot blowers, they have been formed by
bending tubes back and to the side to form the opening and then back to their original plane to
continue the welded wall construction. The furnace water wall tubes including reheat furnace are
backed up by insulation buck-stays and a corrugated casing.
2.4
Saddles
Saddles are provided under the water drum and the front & rear water wall headers to support the
weight of the boiler. Rear saddle under the water drum is fixed and the front saddle has slotted bolt
holes, grooves and grease fittings to allow easy movement and lubrication. Grease fittings are
provided on both front and rear saddle of water wall header. The grooved saddles are free to slide to
allow for expansion of the boiler as it is warmed up. The sliding feet should be inspected and cleaned
as frequently as possible and should be greased at least each 600 boiler steaming hours. This
procedure is extremely important and should be followed without failure. There are cases on record
where pressure parts have failed because the sliding saddles and frozen in place, preventing
movement required during normal expansion.
3-2
K1D97-N57-10M-M501
2.5
Economizer
An extended surface type economizer is placed above the boiler tube bank. The economizer is made
up of closely spaced continuous loop elements, which is welded to the terminal headers at both ends.
Each element shall be of 38.1 mm tubes straight carbon steel tubes with spiral steel fin, connected by
U-bends forming integral loop. All elements are supported at the front and rear side by tube plates.
On the outside of the terminal headers, handholes with covers are provided. Insulated steel casings
are provided around the economizer and large removable panels are fitted on the front and rear side
for access and tube removal. Feedwater enters the inlet header at the top and flows through the
elements counter flowing to the gas leaving the boiler, to the lower header, thence to the boiler steam
drum.
2.6
Boiler Accessories
Boiler accessories are listed on this section later with the manufactures name and identifying data.
See instruction books of those accessories for detailed description.
2.6.1
The boiler is equipped with two (2) sets of fuel oil and gas combination burners on the roof wall of the
furnace. The fuel combination burner is of steam assisted pressure jet type, consisting of atomizer
gun, forced draft air register with fuel shut off valve. The fuel is distributed to each burner from a
burner manifold by branch connection pipe. The operation of start or stop of the burners is
automatically operated by the automatic combustion control signal, and remotely operated by the
push button when necessary.
Note; Oil / Gas combination burners are provided by Hamworhy Combustion, hence
instruction details to check their instruction manuals.
2.6.2
The control system is capable of controlling each boiler separately or all boilers together. The control
system is also capable of burning fuel oil only, fuel oil / gas together or fuel gas only at normal
operating condition. The boiler is arranged for all equal load sharing and each is capable of operating
in a single boiler mode. The restart of one boiler and transfer to gas firing does not affect the
continued operation of the other running boiler. The system control total fuel quantity and combustion
air quantity according to steam demand, and to maintain steam pressure constantly at main steam
outlet. The total fuel quantity for each boiler is the sum of fuel oil flow and gas flow to each boiler. The
calibration of these signals is such that they are of equivalent calorific value. Combustion air for
burner is supplied by forced draft fan. And combustion air quantity is controlled in accordance with
total fuel quantity by the forced draft fan inlet vanes.
Note; Automatic combustion control system is provided by Hamworhy Combustion, hence
instruction details to check their instruction manuals.
3-3
K1D97-N57-10M-M501
2.6.3
The boiler water level control system shall be two (2) element type sensing steam flow and drum level.
The feed water flow is controlled automatically by the regulating valve in accordance with variation of
water level to maintain the water level constant. And steam flow is used as feed forward signal. The
water flow can be also adjusted manually and independently. In case of control air supply failure, the
regulating valve is locked.
Note; Feed water control system is provided by Hamworhy Combustion, hence instruction
details to check their instruction manuals.
2.6.4
The BMS is a system operated by manual local / remote control of FO and GAS fired burners or by
automatic operation linked with ACC.
Should any abnormality occur the BMS system will, after indicating an alarm, trip the fuel supply to
the boiler which is in an abnormal condition.
Note; Burner management system is provided by Hamworhy Combustion, hence instruction
details to check their instruction manuals.
2.6.5
Soot Blower
The boiler is equipped with soot blower system of steam nozzle tube type to clean the external
surface of tubes. The tunmber of soot blowers are as follows:
Position
No.
Type
Two (2)
Stationary rotary
Economizer
Six (6)
Stationary rotary
Soot blower of stationary rotary is driven by electric motor. All soot blowers are automatically and
sequentially operated from the soot blower operating panel at control room.
Note; Soot blower control system is provided by Hamworhy Combustion, hence instruction
details to check their instruction manuals.
2.7
(1)
Manufacturer
Hamworthy Combustion Engineering Limited,
Safety Valve
(3)
Soot Blower
(4)
(5)
(6)
(7)
3-4
K1D97-N57-10M-M501
2.8
Design Data
PRESSURES (bar)
Design 18
Operating (Main Steam Outlet) 16
Hydrostatic Test (Maximum) 27
Safety Valve Settings:
Steam Drum 18
Economizer 22.5
TEMPERATURE (degree C)
Steam Saturated
Feed Water 135
EVAPORATION (kg/h)
Maximum Capacity 80,000
FURNACE VOLUME (m3)
Furnace84.7
HEATING SURFACE (m2)
Boiler 955
Economizer 1542
WEIGHT (kg)
Total Cold Water to Fill Unit Completely 41,800
Cold Water to Fill Boiler to Normal Level 30,400
Cold Water to Fill Economizer 2,200
Boiler, Dry, Complete with Burners and Soot Blower 85,600
Economizer, Dry Complete with fittings 24,400
Boiler Water, Steaming Condition 26,100
Economizer Water, Operating Condition 2,200
Total One Boiler, Steaming Condition 111,700
Total One Economizer, Operating Condition 26,600
3-5
K1D97-N57-10M-M501
2.9
Tube Data
Location (Material)
Quantity / BLR
Diameter
Thickness
mm
mm
928
50.8
2.9 or 3.2
45
88.9
5.5
33
76.2
4.0
33
76.2
4.0
45
88.9
5.5
16
76.2
4.5
16
76.2
4.5
32
88.9
5.5
3-6
K1D97-N57-10M-M501
LOAD
10
25
50
75
100
EVAPORATION
kg/h
8,000
20,000
40,000
60,000
80,000
DRUM PRESSURE
bar
16.0
16.0
16.0
16.0
16.0
deg.C
135
135
135
135
135
deg.C
204.3
204.3
204.3
204.3
204.3
4
87.8
89.9
90.6
90.4
90.0
HHV
MJ/kg
53.85
53.85
53.85
53.85
53.85
LHV
MJ/kg
48.76
48.76
48.76
48.76
48.76
kg/h
416
1,015
2,015
3,028
4,056
25
16
7.5
O2 RATE
4.3
2.8
1.7
1.5
1.5
kg/h
8,930
20,050
37,430
55,770
74,570
kg/h
9,350
21,070
39,450
58,800
78,630
m3/h
11,250
26,610
52,310
77,980
107,180
deg.C
25
25
25
25
25
deg.C
138
144
155
169
184
CALORIFIC VALUE
FUEL CONSUMPTION
Note)
- Flue gas flow of volume base is actual condition volume flow at boiler outlet, not standard condition
volume flow.
- Maximum flue gas temperature at boiler outlet is about 450 degree-C.
- In case that ambient air temperature is 28 degree-C, boiler expected performance data is the same with
above figure.
1.0800 Vol %
96.7299 Vol %
0.9890 Vol %
0.0000 Vol %
0.0000 Vol %
0.2701 Vol %
0.9380 Vol %
3-7
K1D97-N57-10M-M501
LOAD
10
25
50
75
100
EVAPORATION
kg/h
8,000
20,000
40,000
60,000
80,000
DRUM PRESSURE
bar
16.0
16.0
16.0
16.0
16.0
deg.C
135
135
135
135
135
deg.C
204.3
204.3
204.3
204.3
88.1
90.5
91.4
91.4
91.0
HHV
MJ/kg
46.01
46.01
46.01
46.01
46.01
LHV
MJ/kg
43.12
43.12
43.12
43.12
43.12
kg/h
469
1,141
2,258
3,388
4,536
49
31
18
16
15
O2 RATE
6.9
5.0
3.2
2.8
2.7
kg/h
10,370
22,170
39,420
58,140
77,370
kg/h
10,840
23,320
41,680
61,530
81,910
m3/h
12,690
28,870
54,700
80,310
107,390
deg.C
25
25
25
25
25
deg.C
139
145
154
167
181
204.3
CALORIFIC VALUE
FUEL CONSUMPTION
Note)
- Flue gas flow of volume base is actual condition volume flow at boiler outlet, not standard condition
volume flow.
- Maximum flue gas temperature at boiler outlet is about 450 degree-C.
- In case that ambient air temperature is 28 degree-C, boiler expected performance data is the same with
above figure.
FUEL OIL : MGO (ISO 8217 DMA grade)
3-8
K1D97-N57-10M-M501
LOAD
10
25
50
75
100
EVAPORATION
kg/h
8,000
20,000
40,000
60,000
80,000
DRUM PRESSURE
bar
16.0
16.0
16.0
16.0
16.0
deg.C
135
135
135
135
135
deg.C
204.3
204.3
204.3
204.3
88.1
90.5
91.4
91.4
91.0
MJ/kg
40.7
40.7
40.7
40.7
40.7
kg/h
497
1,209
2,392
3,590
4,806
49
31
18
16
15
O2 RATE
6.9
5.0
3.2
2.8
2.7
kg/h
10,290
21,990
39,090
57,670
76,730
kg/h
10,790
23,200
41,490
61,260
81,540
m3/h
12,740
29,060
55,290
81,200
108,590
deg.C
25
25
25
25
25
deg.C
139
145
154
167
181
LHV
FUEL CONSUMPTION
204.3
Note)
- Flue gas flow of volume base is actual condition volume flow at boiler outlet, not standard condition
volume flow.
- Maximum flue gas temperature is about 450 degree-C.
- In case that ambient air temperature is 28 degree-C, boiler expected performance data is the same with
above figure.
FUEL OIL : Crude Oil (LHV : 40.7 MJ/kg)
Methane : 0.177 mol %
Ethane : 0.017 mol %
HC Liquids : Balance
3-9
K1D97-N57-10M-M501
96.0
MGO
Efficiency [%]
94.0
Natural Gas
Crude Oil
92.0
90.0
88.0
86.0
84.0
0
10
20
30
40
50
60
70
80
90
100
80
90
100
80
90
100
1
6,000
MGO
Natural Gas
Crude Oil
5,000
4,000
3,000
2,000
1,000
0
0
10
20
30
40
50
60
70
6.0
MGO
O2 Rate [%]
5.0
Natural Gas
Crude Oil
4.0
3.0
2.0
1.0
0.0
0
10
20
30
40
50
60
70
3-10
K1D97-N57-10M-M501
pH at 25 deg.C
Feed Water
Boiler Water
8.5 9.7
10.5 11.5
mg/L
Not detected
Dissolved Oxygen
mg/L
0.5 or less
Oil
mg/L
ppm
10 30
Silica (SiO2)
mg/L
50 or less
mg/L
150 or less
Dissolved Solid
mg/L
Note 1 : Feed water in this table means the mixture of condensate and distilled water to supply into the boiler.
Note 2 : Estimate the pH value from alkalinity tends to give pH readings varying with silica, Ca, Mg, and other
salt contents of boiler water and hence is not necessarily deemed appropriate : resort to this method
only as a means to obtain a rough guide (alkalinity serves merely as an marine means in determining
the pH level). Also, be sure to control pH to the target value while, on the other hand, keeping
alkalinity at the minimum necessary level. Limiting the P alkalinity to within a certain range would
make it possible to inhibit the alkali corrosion even if boiler water concentration should take place on
the heating surface, etc.
3-16
K1D97-N57-10M-M501
3.7.7
(1)
(2)
: Hydrazine hydrate
Dosage
A. Initial dosage
Pressure[P] (MPa)
P1
1<P2
2<P3
Na3PO412H2O (g/ton)
120
120
40
NaOH (g/ton)
90
30
21
30
30
10
11.4
11.0
10.8
Chemicals
Resulting
PO4 (ppm)
values
pH
(-)
<Note>
(1) Above dosage is determined as the water hardness of zero.
(2) In the initial phase of operation, reaction with iron content of boiler steel produces
iron phosphate film on the steel surfaces causing phosphoric acid to remain below
the specified limit.
B. Supplementary dosage (per one boiler)
Adjustment of chemical concentration should be done to satisfy the limitations based on
the analysis after initial dosing. Following table gives the amount to be done.
Chemicals
Dosage for
Value
adjustment (g/ton)
Na3PO412H2O
About 40
<Note>
(1) The injection quantities indicated are calculated assuming distilled water to be used
as boiler feed water.
(2) The values given are mere theoretical targets and hence require to be controlled as
appropriate for actual boiler load and feed water quality so that the desired boilerwater quality can be ensured in each particular application.
(3) Example for Boiler Treatment Chemicals
Marker
Chemicals
PO4 enchanting agent
ADJUNCT B
pH enchanting agent
GC
3-17
K1D97-N57-10M-M501
200
375
57.5
240
72.5
375
200
3.7.8
3-18
K1D97-N57-10M-M501
3.7.9
3-19
K1D97-N57-10M-M501
3.7.10
1.5
0.5
0
0
60
120
180
3-20
K1D97-N57-10M-M501
4.
Outline of Maintenance
4. Outline of Maintenance
4.1
: Hydrazine hydrate
4.2
4.3
Hydrostatic Test
There are two kind of hydrostatic test, one for checking water-tightness of pressure parts and
the other for checking strength of the same. Test pressure should be determined to suit the
case.
4-1
K1D97-N57-10M-M501
4.
Outline of Maintenance
4.5
Water Washing
Hot water washing is intended to remove sludge sticking to the gas side of the boiler that
cannot be blown off by soot blowing. There are two ways for hot water washing, one by use of
soot blowers and the other by use of a temporary hand nozzle. Both ways have their own
merits, either way may be adopted as the case may be. Hot water washing is generally
required 68 hours. Hot water air heater shall be washed by use of water hose.
Recommended hot water temperature is about 80 degree C and pure water of 50 ton shall be
required.
4.6
Acid cleaning
Acid cleaning is intended to remove scales on the water side of the boiler. Inhibited hydrochloric
acid solution is generally used for this purpose. But it is important to consult with the
professional expert as to the details of cleaning job so as to take most suitable measures to the
actual case and to prevent damage that may result otherwise.
4.7
Refractory
As a refractory, castable type is applied. This refractory is often used for repairing work. When
the castable refractory is to be used on the pressure parts, it should be given necessary
clearances for thermal expansion. After repairing refractory work, never fail to dry it out by
firing.
4-2
K1D97-N57-10M-M501
4.
4.8
Outline of Maintenance
4.9
Economizer
By-pass operation using Auxiliary Feed Water line can be applied when economizer tubes are
damaged. Faulty tubes shall be repair as earlier as possible.
Note; Economizer by-pass operation is not applied to this project as project requirement.
Burner
The burner tip is to be cleaned periodically and examined for disorder. The swirler is to be
maintained as clean as possible, and also the burner throat area is to be always kept in good
working order.
4-3
K1D97-N57-10M-M501
4.
4.12.2
Outline of Maintenance
Soot blower
The soot blower steam line drain discharge, smoothness of rotary motion, and adequacy of
lubrication are to be monitored. In the process of boiler open-up inspection, the element nozzle
is to be examined for disorder and also the element for bend.
The soot blower steam line drain discharge should be carried out
before operation of soot blower.
To make sure no steam leakage from soot blower mounted inlet valve
into blowing element.
4.11.3
By taking the control unit indicator reading, the control performance of each system is to be
monitored. The air supply line drain is to be blown out every one week. The moving parts of
every equipment are to be kept always clean or grease-up periodically for rust prevents
purpose as necessary
.
Note; Burner management system is provided by Hamworhy Combustion, hence
instruction details to check their instruction manuals.
4.11.4
4-4
K1D97-N57-10M-M501
4.
Outline of Maintenance
IMPORTANT
The followings are to be checked periodically to operate boiler safely.
Item
Check Method
Check Interval
1 / Day
1 / 2 Weeks
Combustion condition
and Flame Detector
Burner
Level
Point
Fuel shut off valve for Check operation of each fuel shut off valves such
safety system
1 / Day
Air Slide Operation of Close or open the air slide manually at boiler side.
Water
1 / Day
as fuel oil shut off valve, fuel gas shut off valve
1 / 2 Week
1 / 3 Month
1 / 6 Month
Water
Fuel gas line
expansion joint
Sliding
surface
boiler and economizer make sure no harmful rust or scratch. Put make
feet and valve stem
1 / 2 Year
1 / week
up grease periodically.
Casing / Insulation for Check the condition of casings and to make sure
boiler,
and duct
1 / week
for
1 / week
4-5
K1D97-N57-10M-M501
4.
Outline of Maintenance
Set Point
Location
-240 mm
Local
Local
Local
Over current
Starter
Flame Out
Local
4 bar
Local
Remarks
After 7 sec., off signal
Emergency fuel oil shut off valve is shut down by the condition as follows.
Particular
Fuel Oil Pressure Low-Low
Fuel Oil Temp. Low-Low
Atom. Steam Press. Low-Low
Fuel Oil Pump Stop
Boiler Trip
Set Point
Location
1 bar
Local
n/a
n/a
3 bar
Local
No voltage
Starter
Local
Remarks
Emergench fuel gas cut valve is shut down by the condition as follows.
Particular
Set Point
Location
n/a
Local
n/a
Local
Local
Boiler Trip
Local
Remarks
Set Point
Location
Local
Local
5 deg.C
Local
Local
Local
Local
Remarks
4-6
K1D97-N57-10M-M501
6. General Maintenance
5)
Place test clamps (gags) on all safety valves. Safety valves should never be opened by
hydrostatic pressure.
6)
The pressure gage used should be checked, before applying the maximum test pressure.
7)
When filling the boiler open the vents on the boiler drum to bleed off all air, close the valve
when water runs out.
8)
Before lowering the pressure, take up the slack on the nuts of the handhole and manhole
fittings, were new gaskets have been fitted. The nuts should be pulled just snug with the
wrenches supplied for the purpose. Do not use a pipe or other extension on the wrench handle.
9)
When inspection is completed, open the vent valves and lower the pressure slowly by cracking
a drain valve. Use one of the bottom blow valve. Before starting to drain the boiler, be sure to
open the vent valves.
10)
6.9
Remove the safety valve gags, replace the lifting levers and easing gear.
Boiling Out
If the presence of oil is found on the waterside of the boiler, it must be removed by boiling out. This is
necessary after assembly of a new boiler, after completion of repairs requiring extensive replacement
of tubes, or if oil has entered the feed water from some other source. Boiling out is also a quick and
efficient method of removing various types of scale. The chemicals to be used and the strength of
solution required, depends on the character of the scale. Consult the boiler water chemist. Boiling out
to remove oil requires the use of a fairly strong caustic solution. One such solution is about 2 kg of
caustic soda and about 4 kg of hydrated trisodium phosphate, for each 1,000 kg of cold water
required to fill the boiler. This chemical solution is sufficient to remove ordinarily compounded
lubricating oils or the usual protective oil coating applied to tubes before shipment. Straight mineral
lubricating oils used for high temperature engines require stronger solutions. If such oil is present in
the boiler use about 2 kg trisodium phosphate and about 5.5~6.5 kg caustic soda per 1,000 kg of
water. In addition it is advisable to add detergent (wetting agent) amounting to about 0.5 % of the
boiler water. There are other chemical solutions which can be used. There are many satisfactory
compounds for boiling out, they are sold under various trade names by reputable firms. When such
compounds are used, follow the manufactures instructions.
6.9.1
Steaming Method
Boiling out may be accomplished by injecting steam through temporary lines into the bottom blow.
Temporary drip lines are connected to the boiler air vent and starting valve. The drip lines should be
open drains to portable tanks or drums, which are used for inspection and measuring tanks.
1)
A chemical injector is used to inject the chemical solutions into the boiler, water wall as required.
The chemicals are dissolved in water and injected into the boiler, water wall, in proportion to the
weight of cold water required to fully fill each part. The water weights of each part are listed
under "2.11 Design Data".
6-9
K1D97-N57-10M-M501
6. General Maintenance
2)
After injecting the dissolved chemicals, slowly start admitting steam, allowing the condensate to
fill the unit, until water overflows from the vents of the boiler.
3)
Then throttle the vents and steam injection valves to maintain a pressure of about 0.4 MPa on
the unit, and to allow some overflow from vent. Regulate the vent valve so that the overflow is
roughly in proportion to the weight of water of each part of the unit.
4)
The progress of boiling out can be determined by examination of samples from the drip lines.
Check the alkalinity of the samples, and inject additional chemical solution as needed, to
maintain a satisfactory strength of the solution. Continue boiling out until no trace of oil can be
found in the samples taken from the drip lines.
6.9.2
Firing Method
If steam and electric power are available and the auxiliaries are ready for service a boiler can be
boiled out using a light fire. When the firing method can be used, it is much simpler and does not
require temporary piping. The same chemical solution is used as described in the preceding method.
The quantity of solution to use should be figured for the weight of cold water required to fill the boiler
to normal steaming level. (See "2.11 Design Data".)
1)
2)
After filling some water, about half amount of chemicals shall be admitted into the water drum.
Manhole shall be closed and the boiler shall be filled the water again. Solid chemicals should
be dissolved with water before admitted.
3)
When the boiler water has been filled in the steam drum to some degree, rest chemicals shall
be admitted into it through manhole.
4)
When necessary amount of chemicals has been admitted into the drum, manhole shall be
closed and the boiler shall be filled up to the normal water level.
5)
Using one burner, burner shall be fired at 0.3 MPa of oil pressure for about 5 minutes at rest
about 10 minutes interval. After repeated 2 hours, then burner shall be fired again for 10
minutes at rest 5 minutes interval. It is to avoid for burning of refractory and rapid thermal
expansion. The boiler shall be fired at a rate to start steaming in about 2 hours. MGO shall be
used with air atomizing. Valve operation during pressure raising, refer to 5.2 Starting a Boiler
from Dead Ship Conditions.
6)
Boiler pressure shall be raised slowly to reach about 1.4 MPa after 4 hours of oil burning.
7)
Boiler pressure shall be maintained at 1.4 MPa during the soda-boiling period.
8)
When oil content of boiler water can not be measured, soda-boiling shall be continued for 8
hours. When oil content of boiler water can be measured, after holding the boiler for 3 hours at
soda-boiling pressure of 1.4 MPa, sample of boiler water shall be taken at every 1 hour to be
checked of its alkaline strength and oil content. If the oil content of the sample water has
become to show no more increase at each measurement, that is, when no further operation of
soda-boiling is thought necessary, soda-boiling can be terminated even before 8 hours have
passed.
6-10
K1D97-N57-10M-M501
6. General Maintenance
9)
If the water level gauge is fouled with oil in soda-boiling operation, it shall be cleaned by
blowing steam by closing water-side root valve and opening drain valve of the gauge.
6.9.3
1)
2)
Open up the boiler and wash down with a high pressure water hose, playing the hose into all
tubes.
3)
Carefully inspect the boiler, and if any trace of oil remains, repeat the boiling out process.
Prepare an apparatus to supply adequate quantity of hot water and a hose and nozzle for
spouting hot water.
2)
Remove the casing access doors and dusting panels to facilitate the work.
3)
Provide a means for immediate and constant draining of the waters and the removal of the
sludge, resulting from washing down.
4)
Water under 1.8 MPa and at a temperature of about. 6590degC should be sprayed on to the
6-11
K1D97-N57-10M-M501
6. General Maintenance
tubes, using an armored hose. Work from the top of the boiler down. In cases where slag
removal is extremely difficult, secure from washing, and allow the water to soak into the slag for
a period of 30 minutes to one hour. Then continue washing down the tubes.
5)
Attention should be paid not to let washing water penetrate behind the bricks. It will be effective
to lay a sheet of canvas on the furnace floor. If small quantity of water is absorbed by bricks and
heat insulating materials, the bad effect will be removed by slowly drying soon after the finish or
washing.
6)
7)
As soon as possible after washing is completed, light up the boiler, using one burner at a time.
The drying out operation should be done very slowly and should be continued until the boiler is
thoroughly dried out. The drying should be made at least for 12 hours.
Introduction
Safe and efficient methods of cleaning boilers by acid washing have been developed to remove scale.
This work should be done by contractors having experienced and competent personnel with proper
equipment. The following information is herewith presented for the general information of the operator.
This discussion will be limited to the cleaning of the boiler circuits. The following should be supplied:
1)
An acid filling tank of sufficient capacity to hold the prescribed amount of acid and inhibitor.
2)
One centrifugal acid filling and circulating pump with bronze impeller designed to deliver a
minimum of from 0.20.4 m3/min at 35 mTH or of such capacity as to fill the unit in not more
than 2 hours.
3)
Suitable temporary piping and fittings to connect both the pump and tank to the boiler.
4)
Cleaning chemicals.
A typical cleaning solution would contain 2834 % hydrochloric (muriatic) acid, an inhibitor and
water. The amount of acid used would be roughly 1020 % by volume of water necessary to fill
the component to be cleaned. See "Design Data. Selection of the concentration of acid used (1
6 % by weight for any one unit) depends upon the type and amount of scale or rust and other
impurities to be removed. Special attention must be given to ensure that the acid solution is not
enriched by ferric or cupric ion, which can be caused from the removed scale or deposits
containing a large portion of ferric or cupric oxide. This will impair the effect of the inhibitor. In
such a condition, keep the acid solution below the maximum allowable concentration of ferric or
cupric ion, by adding or renewing the reducing agent.
6-12
K1D97-N57-10M-M501
6. General Maintenance
6.11.2
1)
Procedure
If more than a trace of oil is found in the boiler, it must first be boiled out with an alkaline
solution. A boiling out period of from 610 hours in adequate, when followed by acid cleaning.
2)
Remove all tools, rags and other foreign material from the waterside of the boiler. Secure all
handhole plates, the manhole plates and valves, that will make the boiler watertight and
isolated from all boiler accessories except the water gauges.
3)
Extension should be connected to the highest vents in the boiler, to ensure safe removal of
hydrogen gas, generated during the acid cleaning. Allow no welding during the acid cleaning
process.
4)
Temporary piping should be connected from the filling tank to the filling pump suction, and from
the filling pump discharge to the lower water wall header drains. Piping should also be
connected from the most convenient steam drum connection to the filling tank.
5)
Start filling the boiler with water 6590degC. While the feed water is being injected into boiler
through the regular feed system, start pumping the acid and inhibitor into the boiler through the
water wall header drains. If all the acid has not been pumped into the boiler by the time the
water shows in the gauge glass, secure feeding the boiler, until all the acid has been injected
into the boiler.
6)
When all of the acid has been injected into the boiler continue to fill with water until the level in
the steam drum is high enough to cover all tubes to be cleaned. The tubes must be covered to
permit thermal circulation.
7)
If it is desired to acid clean the entire drum completely fill the unit, adding acid in the same
proportions as before.
8)
Run the circulating pumps 35 minutes each hour. If it is found that a wide temperature spread
exists between various parts of the boiler or if the scale deposit is excessive, use a half hour
cycle.
9)
Check test samples of the cleaning solution with a standard sodium hydroxide solution and
methyl orange indicator. The value of this depends upon being able to get a true representative
sample. The acid concentration should be tested at the end of each circulation period. When
the concentration has leveled off, and remains constant over two successive tests the
dissolution can be considered complete.
10)
Empty the boiler through the skin valve using compressed air.
11)
Average acid contact time should be from 68 hours. If the scale has not been removed during
this period, the probable cause is:
6.11.3
1)
a)
b)
Misidentified scale and wrong solution used, high in silicates, sulfates or oil.
General Precautions
Before injecting the acid solution into the boiler it is good practice to check the effectiveness of
the inhibitor. A weak inhibitor will permit excessive corrosion of the boiler metal.
6-13
K1D97-N57-10M-M501
6. General Maintenance
2)
A quick check of inhibitor consists of diluting the concentrated acid to approximately 5 %, then
drop in a piece of cold rolled steel in the solution and heat to 65degC. Well mixed inhibited acid
produces very few hydrogen bubbles which should be small and difficult to see. For comparison
run a test with uninhibited acid.
3)
Check the metal temperatures particularly the steam drum before injecting acid, before and
during each pumping operation. This can be done by using thermocouples located at critical
points or by contact pyrometer. It should be noted that THE TEMPERATURE IS A MOST
CRITICAL FACTOR in the procedure. Too low a temperature, under 50degC will result in poor
dissolution of most deposits. Too high a temperature, more than 80degC for most inhibitors, will
increase the corrosion rate appreciably, if not to a damaging degree. Stay within the
temperature limits prescribed by the manufacturer of the inhibitor. If there is any doubt, stay
under a temperature of 65 degC.
4)
After draining out the acid, wash down the boiler with fresh water, using the same washing
process as described after boiling out.
5)
The boiler should be boiled out with an alkaline solution (See Boiling Out). This is to both clean
the boiler of suspended particles and to return all surfaces to an alkaline base.
6)
After boiling out, wash the boiler with a strong steam of hot fresh water with a hose.
7)
After acid cleaning DO NOT ENTER OR WORK in the boiler until it has been filled at least once
with water, and preferably after the boiling out process.
6.12.1
nternals should be inspected whenever boilers are secured. Internal fittings should be removed from
the drum as necessary. Internal fittings should be carefully marked and identified as to position in the
drum to insure proper reinstallation. When above inspection indicates need for it, proceed with a
thorough wire brushing of all tubes and drums. The boiler should then be blown out thoroughly with
air, followed by washing out with water. Dry the boiler out and explore random tubes in all parts of the
boiler with a power wire brush. If dirty, repeat the cleaning process specified above.
6-14
K1D97
N57-10M-M501
K1D97
N57-10M-M501
K1D97
N57-10M-M501
K1D97
N57-10M-M501
K1D97
N57-10M-M501
K1D97
N57-10M-M501
K1D97
N57-10M-M501
K1D97
N57-10M-M501