UNIVERSITY OF LAGOS

WORKS & PHYSICAL PLANNING DEPARTMENT


INTERNAL MEMORANDUM

FROM: Deputy Director of Works

TO:

Director of Works

(Opera. & Maint.)


Date: 28th September, 2015
RECONSTRUCUTION OF COLLAPSED EXIT CULVERT OF THE B.R.T
TERMINAL IN FRONT OF GUARANTY TRUST BANK
Sir, the exit culvert of the BRT terminal in front of Guaranty Trust Bank has
collapsed, and becoming impassable. There is need to reconstruct the collapsed
culvert.
Below is the estimate of the work.
S/

DESCRIPTION

N
a.)

Demolishing of collapsed

b.)

culvert and cart away


Reinforced in-situ concrete

c.)

1:2:4 19mmAggregate
High Tensile

d.)

Reinforcement bars
Sawn form work to sides
of concrete

QTY

RATE

AMOUNT
295,400.00
1,330,000.00

38m3

35,000.00

850Kg

350.00

297,500.00

450m2

1,200.00

540,000.00

TOTAL 2,462,900.00
Kindly recommend to the Vice-Chancellor, the sum of N 2,462,900.00 for the
execution of the work.
Thank you Sir.

Sulaimon Y.O

UNIVERSITY OF LAGOS

WORKS & PHYSICAL PLANNING DEPARTMENT


INTERNAL MEMORANDUM

FROM: Assist. Coordinator (Building)

THRO: Deputy Director (Opera &

Maint)

TO:

Director of Works

Date: 18th September, 2015


URGENT RECONSTRUCTION OF COLLAPSING ENTRANCE WAY AND
CULVERT OF THE BRT PARK IN FRONT OF GUARANTY TRUST BANK
Sir, there is urgent need to reconstruct the collapsing entrance way and culvert of
the BRT park in front of Guaranty Trust Bank. This is necessary to prevent total
collapse of the culvert and the entrance way.
Below is the estimate of the work.
S/

DESCRIPTION

QTY

N
a.)

Demolishing of collapsed culvert

b.)

and cart away


Reinforced in-situ concrete

c.)

1:2:4 19mmAggregate
High Tensile Reinforcement bars

805

d.)

Sawn form work to sides of

Kg
395

e.)

concrete
225mm Block wall with concrete

m2
68m

AMOUNT
175,500.00

36m
3

infilling in drain

RATE

35,000.00

1,260,000.00

350.00

281,750.00

1,200.00

474,000.00

4,500.00

306,000.00

TOTAL 2,497,250.00
In view of the need to prevent total collapse of the entrance way and culvert the
Director of Works is implored to kindly request for the Vice-Chancellors approval
for the sum of
N2, 497,250.00 for the work.
Thank you Sir.
Sulaimon Y.O

UNIVERSITY OF LAGOS
WORKS & PHYSICAL PLANNING DEPARTMENT

INTERNAL MEMORANDUM

FROM: Deputy Director of Works


TO:
(Opera. & Maint.)
Date: 23rd September, 2015

Director of Works

Sir, we have assessed the situation.


The original building was a 3 bedroom and a study. It also has two-room boys
quarters and a garage. The building was then partitioned for two occupants.
At the time of moving in, the two room boys quarter was in the side of 3A and
shared one room for each occupants. The occupant of 3A in addition is to have
the garage. However, because of the location of the boys quarter, there was a
problem of accessibility as the occupants of 3B need to go through the compound
of the occupant of 3A to assess his own boys quarter.
In order to solve the problem, the then Chairman of Housing instructed that the
garage be converted to two room boys quarters and the former two bedroom
boys quarter should be converted to garage. This way the issue of accessibility
to the boys quarters would have been solved.
And as mentioned in the reply of Dr. Onuoha, the garage was converted to two
rooms boys quarters and was shared by the two occupants, but the former two
room boys quarter was not converted to garage as instructed. Hence, the
occupant of 3A now had to himself, the former two room boys quarters and a
boys quarter in the converted garage (making three boys quarters for the
occupants of 3A).
Flowing from the above, there is need to convert the old boys quarters to garage
as instructed by then Chairman of Housing for the use of occupant of 3A.
Thank you sir.
Engr. O. Oloyede
Deputy Director of Works (O&M)

UNIVERSITY OF LAGOS
WORKS & PHYSICAL PLANNING DEPARTMENT
INTERNAL MEMORANDUM

FROM: Deputy Director of Works


(Opera. & Maint.)

TO: Head, Property Development and


Investment

Date: 23rd September, 2015

CONSTRUCTION OF SHOP ON 33KV EKEDP ELECTRICAL CABLE


NEAR ENI-NJOKU HALL OF RESIDENCE
During our routine inspection, we noticed a shop near Eni-Njoku Hall of Residence
(See attached photographs.). This shop is built on a 33KV EKEDP cable that goes
to the EKEDP/PHCN substation.
On enquiry from the shop operator, Mr. Mike Ogu. He claimed that the shop was
allocated to him by Property Development Investment.
The location of this shop is dangerous for the operator of the shop and students
patronizing the place. There is therefore the need to relocate this shop from the
place to avoid any mishap around the area.
Thank you.

Engr. O. Oloyede
Deputy Director of Works (O&M)

Cc.
Director of Works
Dean of Students Affairs
Coordinator (Power)