Академический Документы
Профессиональный Документы
Культура Документы
No. 93-1970
BROX INDUSTRIES, INC.,
Plaintiff, Appellee,
v.
H.J. STABILE & SONS, INC. ET AL.,
Defendants, Appellants.
____________________
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEW HAMPSHIRE
[Hon. Martin F. Loughlin, Senior U.S. District Judge]
__________________________
____________________
Before
Torruella, Circuit Judge,
_____________
Bownes, Senior Circuit Judge,
____________________
and Selya, Circuit Judge.
_____________
____________________
James E. Owers,
_______________
with whom
on brief
BOWNES,
BOWNES,
case
requires us
claim under a
evidentiary
therefore
payment bond.
hearing, held
granted
the timeliness of
The district
that
judgment
This diversity
the notice
for
BACKGROUND
BACKGROUND
court, after
an
was timely
and
plaintiff-appellee
a notice of
We affirm.
Brox
__________
We set forth a summary of the pertinent facts found
by the district court.
Stabile &
Son, Inc.
contract with
Wal-Mart
the
real
subcontracted
Wal-Mart
Insurance Company.
party
in
interest.
Reliance,
Stabile
project.
Atom
In
of course,
subsequently
to do work on the
Brox to do
By mid-
its contract
with Atom.
Stabile instructed
Brox that
it should cease
On December
13
operations on
-22
winter,
they agreed
spring to
Brox
that
complete the
work.
anticipated
Stabile
doing so.
that
Brox would
return the
Stabile
fully expected
work-site in the
On December
substantial
work
23, 1991
remained
date
that
for
Brox notified
the
following
spring,
work, and
Brox
this work in
December 1991.
In February and March 1992, in response to concerns
of
Wal-Mart
about
conducted tests
employee
the
quality
of its work.
filled
in
of
Also
several
Brox's
paving,
Brox
in March
1992, a
Brox
potholes at
the
worksite
in
Atom, however,
Stabile.
Nonetheless, Brox
the paving work in the spring under its contract with Atom.
On
May
14, 1992
wanted two
store, to
Atom
informed
Stabile that
which were
be paved by
June 1.
-3-
of New
contiguous to
On
it
the
June 4 Stabile
Although
are
Stabile
the
specifics
recognized that
unclear,
Atom would
shortly
be unable
to Atom.
thereafter
to meet
its
it sought to engage a
and Brox entered into two contracts for the completion of the
paving at the project,
work.
On June 30
with Atom.
for off-site
its contract
the
United States
District Court
for the
District of
New
Under the
as Brox, must
claim to:
the Principal,
the Surety, or the Owner, "within ninety (90) days after such
claimant did or
work or labor, or
claim is
made."
No claim is
notice as
Brox's March
18, 1992
bond's requirements.
on two alternative
of Stabile
notice was
and Reliance
untimely under
is
the
-44
arguendo
________
that its
notice was
bond.
untimely, Reliance
According to
Alternatively, Brox
Brox, no prejudice
maintained that
its
must show
recovery under
could be shown.
notice was
timely
work
According to the
[was] completed
in December,
to be
1991."
Brox Industries, Inc. v. H.J. Stabile & Son, Inc., No. 92______________________
__________________________
426-L,
slip op.
at
6 (D.N.H.
August 18,
1993).
At
the
evidentiary
agreement
[about
[Brox's]
work
completed
notice
under
hearing the
a winter
under
its
that "[i]f
was
subcontract
. .
made then
with
Atom
. an
clearly
was
not
Because the
and
winter hiatus
notice was
Id. at 7.
___
In response
the project
found that
the contract as of
court eventually
substantial work to do on
period,
hiatus]
the bond."
tests
court stated
to Brox's
site in February
pothole
repairs,
the
done at
i.e., quality
____
ninety-day
notice
the district court found that both the tests and the
-55
the
at 5.
completion of
the project."
Id.
___
Accordingly,
under New
above work
v. School, 94 A.2d
______
that the
for the
the notice
on
(1)
it never
of the forum
64,
78
timeliness
attaches.
(1938).
of Brox's
The
notice
arguments
hinge upon
two New
as to
the
Hampshire
v. Cray,
____
194 A.2d
763
precluded from
-66
recovering due to
Cray
____
late notice
of claim.
The principal
in
of New Hampshire.
RSA 447:17 in
statute.
effect at that
Under
time, in
materials furnished
"shall within
ninety days
furnish
principal on a
prior to the
down the
spring
completion of the
1959 the
another construction
claim with the proper
principal.
lubricants to the
winter.
surety
company.
From May
In late 1958,
completed
In May
the project
shut
In
through
the
by the
time of
argued that
continuing one
its
agreement with
such that
the
under the
in November
1958.
principal was
notice requirement
-77
the facts of
seasonal hiatus.
After
Court stated:
We cannot accept Cray's contention that
it ceased to furnish materials not in
November 1958, after
which date
no
materials were in fact furnished, but the
following spring when LaClair failed to
resume operations.
Id. at
___
766.
position
untimely.
Defendants
as Cray
was,
argue that
and
that
Brox
is in
its notice
is
the
same
therefore
Defendants' position is
the New
contractor on a highway
with
materials,
case in
State,
Cray, the
____
and
was
in
contractor
required
January
1961
for
and pipe.
was under
by statute
not delivered.
opinion in New
___
plaintiff
In
Delivery of
On April
the
by
order
substantially undercut
to
various
As was the
contract with
obtain
be "as required."
the
bond.1
Id. at 714.
___
____________________
1. On April 29, 1961 the notice requirement contained in RSA
447:17, see supra p. 7, was amended to require such a filing
___ _____
"within ninety days after the completion and acceptance of
the project."
-88
contractor was
in financial
on
the
construction through
December 1961
April.
project,
and
a new construction
the materials
the
surety
completed
construction company.
company was
hired by
In
the
filed a
a different
original contractor.
Id.
___
The pipe
was timely
notice statute.
two
factors.
under
the pre-amendment
Id. at 715.
___
version of
1961
the
based on
divisible
October, 27,
as to
deliveries."
And
second, "[o]n
culvert it
Id.
___
Id.
___
elapsed since
ceased to
notice of
furnish
contract to make
Moreover,
in American
________
Fidelity
Co.
v.
Cray, supra,
the
______________
____
_____
plaintiff in this case had a single
contract for a series of deliveries of
specified materials.
Id.
___
Unlike
the situation
(citation omitted).
notice
filed within
ninety
The court
days of
concluded
the
that "[a]
last delivery
on
and permitted
Id.
___
plaintiff's filing
was
premature,
that it
the
that
premature
Id. at 716.
___
is similarly situated
to the
was therefore
timely.
Culvert, Brox
_______
Brox
gave notice
passed
since
Nevertheless,
We
agree.
of its
its
claim, more
last
paving
out
factors,
we
on
days had
the
project.
eventually
carrying
At the time
than ninety
work
Atom.
completed
Stabile's
the paving
contract
believe, place
this
work
with
case
necessary
Wal-Mart.
for
These
squarely under
the
The
district
court
also
found,
consistent
with
New
___
in effect,
Supreme Court in
by the New
at the
time notice is
as the one at
given under
notice is
not
the
last
work was
original contract.
viewed as
has
performed
by
In effect,
in the future --
claimant
under
the
to perform
the
be
which it
not begin
Thus, as
has noted,
is clear, as in
in
____________________
Son, Inc., slip op. at 7.
_________
i.e.,
____
a second
-1111
requirement, as
see
In
identical
and
to a
contractual
the New
Hampshire
fact, the
identical statutory
notice requirement at
provision
subrogation
issue here
is
why
involves
opposed
no reason
Id. at 714.
___
we can
to the latter.
196
A.2d at
715
(citing
cases).
Aside
above,
the parties
New Hampshire
have focussed
cases discussed
their attention
on cases
construing
Act,
the ninety-day
40 U.S.C.
270b(a).
precedent under
these cases.
notice requirement in
the Miller
New Hampshire
law, we need
not delve
into
the
performances,
question
we have
of
uncovered
ninety-day
only a
gaps
handful of
between
cases.
-1212
ninety
orders,
______
days between
deliveries under
payment for
the earlier
deliveries.
J.).
the
273
F.2d
(2d
Cir.
1959)
a series of purchase
___________________
plaintiff never
made
any
Of
course, in
deliveries after
the
____
ninety-day plus hiatus.
performed
purchase
under a
orders,
On
contract,
a
as
greater
opposed
than
where work
to
ninety-day
is
series
of
interval
in
of immediate
notice.
See
___
Id. at
___
882;
(2d Cir.
and the New Hampshire Supreme Court reached the same result.
The three Miller Act
in
first
case,
The
273
F.2d
873
(2d
Cir.
1959),
not
its
requirement.
timeliness
And the
under
the
ninety-day
notice
649 F.2d 29
(1st Cir. 1981) and A.B. Cooley v. Barten & Wood, Inc., 249
____________
____________________
F.2d 912 (1st
-1313
the
instant
case, do
not
involve gaps
in
the claimant's
any substantive
-1414