0 оценок0% нашли этот документ полезным (0 голосов)
4K просмотров14 страниц
This letter serves as a notice to AHJV regarding the lack of appropriate personel to perform the on-going activities at this critical juncture of the HRT project.
This letter serves as a notice to AHJV regarding the lack of appropriate personel to perform the on-going activities at this critical juncture of the HRT project.
This letter serves as a notice to AHJV regarding the lack of appropriate personel to perform the on-going activities at this critical juncture of the HRT project.
HART ewsaonpen208
July 45, 2015
Enrico Fontana, PhD, Project Manager and Managing Director
‘Ansaldo Honolulu Joint Venture
Pacifie Guardian Center
737 Bishop St Suite 2860
Honolulu, Hi 96813
Dear Mr. Fontana:
Subject: Honolulu Rall Transit Project
Contract No. CT-HRT-1200106
Core Systems Design Bulld 0/M
Notice for Lack af On Site Personnel
‘This letter serves as a notice to ALLV regarding the lack of approoriate personnel (SP Section 4-8) to
perform the on-going activities at tis critical juncture of the HRTproject. HART wants to reiterate
‘that the absence of a number of Key Personnel at this time fs unacceptable and inappropriate for a
project ofthis magnitude. HART is concermed thatthe continued vacancies of Key Personnel and
‘other important positions are affecting the HRT's progress. Without immediate action to have these
‘personnel available in Honolulu, many on-going and future issues will not be addressed in a timely
‘manner, which wil further affect the Project's progress.
1. Communication Lead Engineer
‘Mr, Alfonso Buono is identified as the Communication Lead Engineer, but he has officially been
reassigned toa diferent location to work on other assignments. Mr. Vincent Sibbet was proposed
{8s an interim substitution for Mr. Buono, but he has recently let AHJV to join another firm. This is @
‘major concern for HART due tothe late design progress and the recent challenges related to on-time:
completion of the On-Board Communications Systems (OBS) design and the transfer of the
Integrated Communication Control System (|CCS) work to T&T. In addition, there are a number of
outstanding design issues that need to be resolved as soon as possible. AHIV must provide a
competent senior communications engineer to lead the Commurications subsystem work here in
Honolulu This is @ Key Personnel position specified in SP Section SP-4.8,
2. Traction Electrification Lead Engineer
Mr. Mario Petrone has served as the ead Traction Electrification Engineer. He has left the Project
‘and is now residing fulltime in italy. Mr. Alessandro Acquaviva ls supporting the TES work, but he
‘does not have the requisite implementation experience to lead the traction electriftcation work as
the Project transitions from design into assembly, testing, instalation and commissioning. itis
imperative that AFUV fils this position with an experienced Lead Engineer to deal with many
challenges ahead. HART is especially concerned regarding the need to bring traction power on ine
(27 1 COUNTY OF HOMDLLL, As at 700, £89
Prone 057688359 ex (605/E85310 mo ores‘Enrico Fontana, PhD, Project Manager and Managing Director
Powe 2
July 45, 2015,
‘o-support vehicle delivery in the near term and all requited coordination with HECO to energize the
system. This isa Key Personnel postion specified in SP Section SP-4.8,
3. Interface Manager
HART hes been informed thatthe current Interface Manager will not be avalable to support the
Construction phase. Interface isan on-going and critical activity throughout all phases ofthe Project.
\ithout continued interface management by AHIV, HART is concerned about the rsks of interface
Confcts and discrepancies which will eventually affect Project's completion. HART expects that
AHUV will provide an Interface Manager during the Construction phase. This isa Key Personnel
position specified in SP Section SP-4.8,
4. Pmlect Control Manager
CCurrenty the Project Controls Manager (PCM) isnot on istand. Without the Project Controls Manager
‘onsite in Honolulu, HART is concerned regarding AHJV's abt to work with HART to address all the
‘on going issues withthe revision ofthe Baseline Project Schedule (BPS). This is especially critical
given the PCM also serves as the Lead Scheduler. This is @ Key Personnel position specified in SP
Section $P-4.8.
5. Field Supervisors (Site Engineers)
Under Section 2.1.3.7 of AHJV Proposal ~ BAFO Il which Is a part of the Contract documents, AH
‘dentitid three (3) Site Engineers responsible for Communications, Automated Train Control
(ATCYSCADA and Traction Electification (TE). These personnel are presented in AKIV'S
Organization Chart Rev. 05~00, dated April 2015, as Filed Supervisors for each subsystem. The
[ATC/SCADA and TE Field Supervisors are expected to be on-site in Honolulu by July 2%, 2015. In
‘addition. the Organization Chart shows that another key position. the Logistics Manager. isto be on-
site by June 4", 2015 when materials are delivered. Without having these personnel during the
Construction phase, which has already started, HART Is especially concerned regarding AHLV's ably
to supervise and inspect equipment delivery and instalation, and ultimately project completion.
HART wants to point out that selecting competent personnel for these positions is very citical and
will take time since they have a major role in ensuring on time and quality delivery of equipment and
installation work. AHIV has provided notice to HART that the fist TPSS has arrived at the Port of
Honolulu and should be delivered tothe ROC in the coming days. HART is greatly concerned that the
TE Field Supervisor isnot yet available onsite to support this activity.
6 Other Positions
6.4 Construction Manager
‘Based upon HART's on-going observation of construction activities being performed by the AHLV's
Construction team, HART Is concerned regarding the progress being made inthis area. HART hasEnrioo Fontana, PhD, Project Manage: and Menaging Director
Page 3
July 15, 2015,
‘observed and taken notice of AHJV Construction team's inability to deliver in eccordance with plan
‘and commitment. The Construction Management team, under the Constructien Manager leadership,
's responsible to manage the installation of all AHJV's equipment and construction work, oversee the:
‘Safety and Security aspect, coordinate schedule, monitor environmental compliance and interface
with Fixed Faclities Contractors on turn-over and acceptance of Fixed Faciltes. These activities
require detalled planning, precise execution and serious commitment from the CM leadership.
HART requests that AHLV takes a more proactive approach working on construction issues. AKJV
should have frequent communications withthe Fixed Facilities Contractors. AHJV's needs and
requirements must be clearly identified and maintained. For AHUV's own work, Items such as
building permits and drawings must be prepared in advance and ready for corstruction activites to
‘avoid delaying and wasting resources. These improvements can effectively be implemented by an
experienced Construction Management team. Therefore, HART asks that AHLV considers bringing on
board a Construction Management team with requisite experience and serious commitment to deal
With the above deficiencies and upcoming challenges.
62 General System Lead Enginger
Mr. Giovanni Russo has served as the lead General System Engineer. HART understands that he Is
leaving the Project. Mr. Russo has been leading the system performance sinulation and operation
analyses, developed and updated test plans, and worked on system integration activites. He was
‘proposed as a key person during the testing and commissioning phase. Given his current role on
the Project, tis critical that AHUV provides a replacement as soon as possible. This person must
have the required qualifications and experience related to the General System area that was led by
Mr. Giovanni Russo.
ae a cee een neon ga eee
ae
y eg)
sac
cc: Jeffrey Siehien (HART)
Huy Huynh (C800)HART ewronaoeres
‘August 18, 2015
Enrico Fontana, PhD, Project Manager and Managing Director
‘Ansaldo Honolulu Joint Venture
PacificGuacdian Center
737 Bishop St Suite 2860
Honolu, Hi 96813
Dear Mr Fontana:
Subject: Honolulu Rail Transit Project
Contract No, CT-HRT-1200108
Core Systems Design Build 0/M
Replacement of Communications Lead Engineer
Reference: AMVPM-18107
HART tas reviewed the referenced AHUV letter and Mr. Mark Maxted's resume, HART also
Conducted an interview with Mr. Maxted. This letter isto Inform AHLV that HART accepts AHIV's
‘proposal to substitute Mr. Alfonso Buono with Mr. Mark Manted as AHIV's Communications Lead
Enginoor.
HART looks forward to having Mr. Masted's participation and making contributon to the Honolulu
Rall Transit Project.
Sincerely,
ee
Justin Garrod
Project Manager
cc: Jeffrey Siehien (HART)
Huy Huynh (cS0C)
——_—_
(avo coun oF HONOLULU ne ace Sat $70, 109A Set, Ho, Han 685
Prom 8087686150 fa (087S65130" wen todasHART | ane
‘September 15, 2015,
Enrico Fontana, PhO, Project Manager and Managing Director
‘Asaldo Honolulu Joint Venture
Pacific Guardian Center
737 Bishop St Suite 2860
Honolulu, HI96813
Dear Mr. Fontana:
Subject: Honolulu Rail Transit Project
Contract No. CT-HRT-1200108
Core Systems Design Build 0/M
Notice for Lack of OnSite Personne!
Reference: CMS-A00.00285
Inthe referenced letter, HART gave natice to ANUV regarding the lack of having appropriate
personnel availabe to perform on-going crical activities related to the HRT project. Inthe letter,
HART emphasized that continued absence of many Key Personnel and many critical positions is
‘Uracceptable, Ithas been almost two months since HART provided notice to AHJV on this matter.
Teday there is very litle progress made. HART has to reiterate that without immediate action to
heve these personnel available in Honolulu as soon as possible, the Project's progress will be
further impacted and any corrective actions, as a result, wil become more dfcut.
Te following isa list of Key Personnel and ertcal project postions that were identified in the
referenced letter:
Communication Lead Engineer
‘Traction Electrification Lead Engineer
Interface Manager for Construction
Project Control Manager
Field Superisors (Site Engineers - three (3) positions)
General System Lead Engineer
‘As the HRT Core Systems work isin the construction and installation phase, HART wants to reiterate our
‘concer regarding the lack of te above personnel. Please provide your immediate action plan that
Clearly identifies when each ofthe above personnel wil be availabe to work in Honolulu and how AHJV
plans to cover the work during the interim for each position
one: (607085159 fo eD6TEESSI0 wen nraaenstogEnrico Foxtana, PhD, Project Manager and Managing Director
Page 2
‘September 45, 2015
Sincerely,
sain Garrod
Project Manager
oc: Jeffrey Sichien (HART)
Huy Huynh (6300)HART ‘ows 00 00816
HONOLUW AUTHORITY er RAPIO TRANSPORTATION,
October 27, 2015
Enrico Fontana, Ph.., Project Manager and Managing Director
‘Ansaldo Honolulu Joint Venture
Pacific Guardian Center
737 Bishop St Suite 2860
Honolulu, Hawaii 96813
Dear Mr. Fontana
Subject: Honolulu Ral Transit Project
Contract No. CT-HRT-1200106
Core Systems Design Build 0/M
Request for Approval of Key Personnel-Traction Electrification Lead Engineer
Reference: AHIV.PM-15158
In response to AFL's request for approval of key personnel substitution, HART hereby provides
conditional approval of AHJV's proposal to substitute Mr. Maria Petrone with Mr. Alessandro
‘Acquaviva forthe Traction Electiication (TE) Lead Engineer postion. This approval isto be
reviewed after si months (April 2016). HART's approval is based upon the following:
‘+ Mr. Acquaviva has been a key technical member supporting Mr. Petrone withthe design of
the TE system. HART has observed Mr. Acquaviva performance with respect tothe TE
system since he joined the project in January 2014, Mr, fequavva’s design experience and
knowledge ofthe HRT TE system are beneficial tothe remaining phases of the HRT project.
‘+ -AXUV's proposal to nave Mr. Bruno Lorusso, an experienced TE Senior Commissioning
Engineer, to be onsite in Honolulu to support Mr. Acquavisa,
‘As part of this approval, HART requests that AHIV identity key traction power engineers from Ansaldo
STS' headquarters and your TES subcontractor who will be able to provide direct technical support to
Mr. Acquaviva for any design and testing assistance. Please prosde this information to HART within
‘2 weeks from the date of ths leter.
si
=
Tel Sichien
oth Garrod
$5 Project Manager
ci Jeffrey Siehien, HART
Huy Huynh, CSOC
en
(ory AND COUNTY OF HONOLUL Fc, Ste 170, 1099 Aaa Seer, Ho 96813
Panes aRTEARIE fue fANSETO we tonaeshn,HART _.
The Effect of Employee Engagement On Organizational Performance Via The Mediating Role of Job Satisfaction - The Case of IT Employees in Jordanian Banking Sector