INSPECTIONMANUAL
Section17
Page6of6
Date:May17,1996
Subject: VOLUMEDETERMINATION
ApprovedBy:
17.1 DEFINITIONS
1. TOTALOBSERVEDVOLUME(TOV)
TOVisthetotalofallpetroleumliquids,sedimentandwater,andfreewateratthe
observedtemperature.
2. SEDIMENTANDWATER(S&W)
S&Wisthenonhydrocarbonsolidmaterialandwaterinsuspensioninapetroleum
liquid.
3. FREEWATER(FW)
FWisthevolumeofwaterthatisnotinsuspensioninthepetroleumliquid.Typically
foundatthelowerlayer
4. GROSSOBSERVEDVOLUME(GOV)
GOV=TOVFW
GOVisthetotalvolumeofallpetroleumliquidsandsedimentandwater,excludingfree
wateratobservedtemperature.
5. GROSSSTANDARDVOLUME(GSV)
GSV=GOVxVCF
GSVisthetotalvolumeofallpetroleumliquidsandsedimentandwater,excludingfreewater,
correctedbytheappropriatevolumecorrectionfactor.
6.
VOLUMECORRECTIONFACTOR(VCF)
TheVCFisafactorusedforconvertingvolumesatanobservedtemperatureandgravity
ordensitytoastandardtemperatureof60For15C.
7. TOTALCALCULATEDVOLUME(TCV)
TCV=GSV+FW
TCVisthetotalcorrectedvolumeofallpetroleumliquidsandsedimentandwater,correctedto
astandardtemperatureplusallfreewatermeasuredatobservedtemperature.
8. NETSTANDARDVOLUME(NSV)
NSV=GSVS&W
NSVisthetotalcorrectedvolumeofallpetroleumliquids,excludingsedimentandwater
andfreewater.
9. ONBOARDQUANTITY(OBQ)
OBQisthematerialremaininginvesseltanks,voidspaces,and/orpipelinespriortoloading,
includingoil,water,slops,sludgeandsediments.
CAMINCARGOCONTROL,INC
INSPECTIONMANUAL
Section17
Page6of6
Date:May17,1996
Subject: VOLUMEDETERMINATION
ApprovedBy:
10. REMAININGONBOARD(ROB)
ROBisthematerialremaininginvesseltanks,voidspaces,and/orpipelinesafterdischarge,
includingoil,water,slops,sludgeandsediments.
17.2 READINGTHECALIBRATIONCHARTS
1.
Foreachoperation,theInspectormustobtainfromthecalibrationchartsthefollowing:
1. For each shore tank measured (opening and closing): the TOV for the Physical
Gauges, the free water volume for the Free Water Gauge and the Roof
Correctionvolume.
2. For each vessel compartment measured: the TOV for the Physical Gauge (trim
corrected if applicable) and the free water volume for the Free Water
Gauge/CorrectedFreeWaterGauge.
22. INNAGECHART
1.Whenthephysical/correctedgaugeobtainedisanullageandthechartiscalibrated
asaninnagechart,theInspectormustconvertthemeasurementtoaninnageby
deductingtheoutagegaugefromthePhysicalReferenceHeight.
2. TheTOVcorrespondingtotheinnagegaugedfractionmustbeaddedtowholeTOV.
3. Typically,thecalibrationcharthasaseparateareaorchartforFreeWater.Ifnot,
thentheFreeWaterTOVmustbeobtainedfromthesamechartandfractions
mayhavetobecalculatedbyinterpolation.
3. ULLAGECHART
1. Whenthephysical/correctedgaugeobtainedisaninnageandthechartiscalibrated
asanullagechart,themeasurementmustbeconvertedtoanoutagebydeducting
theinnagegaugeformthePhysicalReferenceHeight.
2. The TOV corresponding to the ullage gauged fraction must be subtracted from
wholeTOV.
3. Typically,thecalibrationcharthasaseparateareaorchartforFreeWater.Ifnot,
thentheFreeWaterTOVmustbeobtainedfromthesamechartandfractions
mayhavetobecalculatedbyinterpolation.
4. ROOFCORRECTION
1. Roofcorrectionvolumemustbedeterminedbyfollowingtheinstructionsonthe
CAMINCARGOCONTROL,INC
INSPECTIONMANUAL
Section17
Page6of6
Date:May17,1996
Subject: VOLUMEDETERMINATION
ApprovedBy:
calibrationchart.UsuallytheroofweighthasbeendeductedfromtheTOVata
setAPIGravity.Insuchcase,theInspectormust:
i.
ObtaintheApiGravityfortheproductinthetank.(seeSection17.3.1.1Shore
TankAPIGravity);
ii. ObtainfromtheshoretankcalibrationchartthesetAPIGravityonwhichthe
roofdeductionwasbasedonandthe+or correctionperobservedAPI
degree;
iii. DeductthesetAPIGravityfromtheAPIGravityfortheproductinthetank;
iv. MultiplythedifferencebythecorrectionperobservedAPIdegree;
v. ThevolumeobtainmustbeaddedorsubtractedfromtheTOVintheshoretank
accordingtocalibrationchartinstructions.
17.3 VOLUMECORRECTIONFACTOR(VCF)
1. APIGRAVITY
Accordingtoeachindividualoperation,theInspectormustobtaintheAPIGravityas
follows:
1. ShoreTankAPIGravity
1. Iftheoperationisaninventory,orifthetankisdeliveringproducttoanother
source,theAPImaybesubmittedbytheterminalortestedintheCamin
CargoControllab.ThetestedAPIispreferred.
2. Ifthetankisreceivingproductfromanothersource,theAPIfortheopeningof
theshoretankmaybesubmittedbytheterminalortestedinCaminCargo
Controllab.UnlesstheInspectorisotherwiseinstructed,thesubmittedis
usedforcalculations.The APIfortheclosingoftheshoretankmustbe
tested or calculated. Unless the Inspector is otherwise instructed, the
calculatedisusedandtheformulaisasfollow:
[(TOVcTOVo)xAPId]+[TOVoxAPIo]
ClosingAPIGravity
=
TOVc
where:
TOVc
TOVo
APIo
APId
=
=
=
=
ClosingTOV
OpeningTOV
OpeningAPIGravityfrom
APIfromdeliveringsource
2. VesselAPIGravity
1. Iftheoperationisaload,theInspectormustproceedasfollows:
CAMINCARGOCONTROL,INC
INSPECTIONMANUAL
Section17
Page6of6
Date:May17,1996
Subject: VOLUMEDETERMINATION
ApprovedBy:
1. Ifonlyoneshoretankperproductloadedisbeingused,theAPImustbethe
sameastheshoretank(refertoShoreTankAPIGravityabove)
2. Ifmorethanoneshoretankperproductloadedisbeingused,thentheAPI
maybetestedattheCaminCargoControllab(whichispreferrediftime
allows)ortheAPImaybevolumetricallycalculatedasfollows:
(TotalGOV1xAPI1)+(TotalGOV2xAPI2)+(...)
TotalVesselGOVReceived
Where:
TotalGOV1
API1
=
TotalGOV2
API2 =
(...)
= TotalDeliveredGOVfromshoretankno1
APIusedforcalculatingthetotalGSVinshoretankno.
1
= TotalDeliveredGOVfromshoretankno2
APIusedforcalculatingthetotalGSVinshoretankno.
2
Asmanyshoretanksasthevesselwasloadedfrom
2. Iftheoperationisadischargeorapartialdischargeandunlessotherwiseinstructed,
theInspectorshouldusedtheAPIrecordedattheloadport.
2
VCFTABLE
BasedonAveragedTemperaturesandtheAPIGravity,theInspectorshouldobtainthe
corresponding VCF for each shore tank and vessel compartment (opening and
closing)fromtheappropriateASTMTableasfollows:
Product
TabletobeUsed
CrudeOil
6A
CleanOils
6B
ResidualOils/VGO
6BExceptAsphalt
Asphalt
7
Chemicals
6C
17.4 SHORETANKVOLUMECALCULATIONS
1. CALCULATION
Open
GSVo
= (TOVoFWo+orRoofo)*VCFo
CAMINCARGOCONTROL,INC
INSPECTIONMANUAL
Section17
Page6of6
Date:May17,1996
Subject: VOLUMEDETERMINATION
ApprovedBy:
Close
GSVc
Delivered/ReceivedGSV
= (TOVcFWc+orRoofc)*VCFc
=(GSVoGSVc+orLineSlack+orDeltoTrcks)
1. Ifthelineconditionwasverifiedandaslackconditionisobserved,thisdifference
shouldbeappliedasfollows:
i. Iftheshoretankisdeliveringproducttoanothersource,thelineslackvolume
shouldbesubtractedfromtheDeliveredGSV.
ii. Iftheshoretankisreceivingproductfromanothersource,thelineslackvolume
shouldbeaddedtotheReceivedGSV.
2. Iftheshoretankisactivetotherack,thevolumedeliveredtotrucksiscalculatedas
follows:
Thesumofallmeterticketvolumesobtainedupontheopeningoftheshoretank
MINUS()thesumofallmeterticketvolumesobtainedatthecloseoftheshore
tank.
3. ThevolumedeliveredtotrucksshouldbemultipliedbytheclosingVCFoftheshore
tankbeenactivetotherack.
4. Thevolumedeliveredtotrucksshouldbe:
i. addedtothereceivingshoretankGSV,iftheoperationisadischarge.
ii. subtractedtothedeliveringshoretankGSV,iftheoperationisaloading.
2.
TheGSViscalculatedoneShoreTankatatime.Whenthereismorethanoneshoretank
perproduct,allGSV'softhesameproductmustbeaddedtoobtaintheTotalGSV.
3. Forcleanoilsandresidualoils:GSV=NSV
4. ToobtaintheTotalNSVforcrudeoiltheInspectormust:
1. ObtaintheSedimentandWaterPercentage(S&W%)fromtheOperationsManager
orDispatcheronduty.
2. CalculatetheS&Wvolumeby:
*WithAutomaticSampler
TotalS&W= (TotalTCV*S&W%)
TotalNSV=
(TotalTCVTotalS&W)
*
WithoutAutomaticSampler
(TotalGSV*S&W%)
(TotalGSVTotalS&W)
IfanautomaticsamplerwasusedthentheFreeWaterdifferencefromtheopeningto
theclosingmustbeaddedtotheGSVinordertoobtaintheTCV.
17.5 VESSELVOLUMECALCULATIONS
1. CALCULATION
CAMINCARGOCONTROL,INC
INSPECTIONMANUAL
Section17
Page6of6
Date:May17,1996
Subject: VOLUMEDETERMINATION
ApprovedBy:
EachCompartment
GSV
(TOVFW)*VCF
TheGSViscalculatedonecompartmentatatime.AllGSVmustbeaddedtoobtainthe
TotalGSVforeachproduct.
i.
Whenthevesselisloading,
TotalGSVReceived
= TotalGSVAfterLoadingOBQPriorLoading
TotalTCVReceived
= TotalGSVAfterLoading+FWOBQPrior
Loading
ii. Whenthevesselisloadingontop,
TotalGSVReceived
= TotalGSVAfterLoadingTotalGSVBefore
Loading
TotalTCVReceived
= TotalGSVAfterLoading+FWTotalGSV
BeforeLoading+FW
iii. Whenthevesselisdischarging,
TotalGSVDelivered
= TotalGSVBeforeDischargeROBAfter
Discharge
TotalTCVDelivered
= TotalGSVBeforeDischarge+FWROB
AfterDischarge
iv. Whenthevesselispartiallydischarging,
TotalGSVDelivered
= TotalGSVBeforeDischargeTotalGSVAfter
Discharge
TotalTCVDelivered
= TotalGSVBeforeDischarge+FWTotalGSV
AfterDischarge+FW