REPUBLIC OF INDONESIA

LIST OF PLANNED PRIORITY


EXTERNAL LOANS
(DRPPLN)
2016

Ministry of National Development Planning/


National Development Planning Agency
- 2016 -

Foreword
In the process of preparing development projects to be funded by external
loans, the Ministry of National Development Planning arranges the List of Planned
Priority External Loans or Daftar Rencana Prioritas Pinjaman Luar Negeri (DRPPLN),
containing the list of projects that have met most of the readiness criteria. The DRPPLN
of 2016 published through the Decree of the Minister of National Development
Planning/Head
of
National
Development
Planning
Agency
Number
KEP.25/M.PPN/HK/03/2016. The DRPPLN 2016 consists of 25 projects: 24 projects of
ministries/agencies and 1 project of the local government. The total amount of the
external loans that needed to finance the projects in DRPPLN 2016 is estimated USD $
4.0 billion.
The DRPPLN 2016 will be used as a reference for planning and budgeting of
new external loan projects which will be executed in 2016-2017. With the issuance of the
DRPPLN 2016, the ministries/agencies /local authorities, as executing agencies, are
expected to enhance the readiness of their proposed projects listed in the DRPPLN 2016
and to ensure the activities can be done in a timely manner. In addition, the DRPPLN
2016 is also expected to be used by development partners as a reference in taking followup measures regarding their cooperation plan with the Government of Indonesia.
Ministry for National Development Planning/
Head of the National Development Planning Agency,

Sofyan A. Djalil

List of Contents
Foreword ...................................................................................................................... i
List of Contents ......................................................................................................... iii
Chapter 1 ......................................................................................................................v
1.
2.

Introduction ......................................................................................................... v
Recapitulation and List of Projects in the DRPPLN 2016 ............................. vi

Chapter 2 .................................................................................................................... ix
Kementerian Pekerjaan Umum dan Perumahan Rakyat/ Ministry of Public
Works and Housing .................................................................................................. 1
Direktorat Jenderal Bina Marga/ Directorate General of Highways ....................3
1. Engineering Service for National Roads Development Project .....................5
2. Development of Cileunyi - Sumedang - Dawuan Toll Road Phase II...........7
3. Toll Road Development of Manado - Bitung ...................................................9
Direktorat Jenderal Cipta Karya/ Directorate General of Human
Settlements ................................................................................................................11
4. Community Based Water and Sanitation Program (PAMSIMAS) ..............13
5. Engineering Service for Sanitation Improvement Project ............................17
6. Engineering Service for Water Supply Development Project ......................19
7. IKK Water Supply Program and Small Water Treatment Plant for Water
Scarcity Area.......................................................................................................21
8. Small Scale Water Treatment Plants for Emergency Relief ..........................23
9. National Slum Upgrading ................................................................................25
Direktorat Jenderal Sumber Daya Air/ Directorate General of Water
Resources ...................................................................................................................29
10. Engineering Service for Bulk Water and Water Supply Development
Project ..................................................................................................................31
11. Engineering Service for Coastal and River Development Project ...............33
12. Flood Management in Selected River Basins .................................................35
13. Engineering Service for Dam Multipurpose Development Project .............38
14. Engineering Service for Irrigation and Lowland Development Project .....40
15. Integrated Participatory Development and Management of Irrigation
Project - Phase I ..................................................................................................42
16. The Urgent Rehabilitation of Strategic Irrigation for Western Region of
Indonesia .............................................................................................................45
17. Komering Irrigation Project Stage III ..............................................................47
18. Rentang Irrigation Modernization Project ......................................................50

Kementerian Perhubungan/ Ministry of Transportation ................................... 53


19. Procurement of Track Material and Turn Out -Phase II ...............................55
iii

Kementerian Riset, Teknologi, dan Perguruan Tinggi/ Ministry of Research,


Technology, and Higher Education ......................................................................57
20. Development of Four Higher Education Institutions................................... 59
21. University of Gadjah Mada Achieving World Class University with SocioEntrepreneurial Spirit ....................................................................................... 63
22. The Plan of Hasanuddin University Hospital Development ...................... 66

Kementerian Agama/ Ministry of Religious Affairs ..........................................69


23. The Transformation of IAINs Into Modern Islamic Universities (TIMEs) 71
24. The Development and Improvement of Three Islamic Higher Educational
Institutions ......................................................................................................... 74

Pemerintah Daerah Provinsi Aceh/ Local Government of Aceh Province .....77


25. Reengineering and Improving the Hospitals and Referral System in
Selected Aceh Districts ..................................................................................... 79

iv

Chapter 1
1. Introduction
In order to support the achievement of national development priorities as stated in
Medium-Term National Development Plan or Rencana Pembangunan Jangka Menengah
Nasional (RPJMN) of 2015-2019, the Government of Indonesia explores the utilization
of all potential sources of financing, including external loans. The utilization of the
external loans is regulated under the Government Regulation Number 10/2011 on the
Procedure for Procurement of External Loans and Grants.
As mandated in the Government Regulation Number 10/2011, The Ministry of
National Development Planning/National Development Planning Agency
(Bappenas) coordinates the planning process of projects funded by external loans.
During the process, several external loan planning documents are issued, among
others the List of Medium-Term Planned External Loans or Daftar Rencana Pinjaman
Luar Negeri Jangka Menengah (DRPLN-JM)/ Blue Book and the List of Planned Priority
External Loans or Daftar Rencana Prioritas Pinjaman Luar Negeri (DRPPLN)/ Green
Book. The DRPLN-JM/ Blue Book is a document that contains the planned programs
and projects which are appropriate to be funded by external loans for the mediumterm period, while the DRPPLN/ Green Book is a document that contains the list of
external loans projects which already have a funding source indication and ready to
be negotiated within the yearly effective period.
The formulation of DRPPLN is based on the Decree of Minister for National
Development Planning/Head of National Development Planning Agency Number 4
year 2011 on the Procedures of Planning, Proposing, Assessing, Monitoring and
Evaluating of Projects Financed by External Loans and Grants. Projects that listed in
DRPPLN should have met most of the required readiness criteria through the
assessment of readiness documents submitted by the executing agencies. The
readiness assessment is conducted in order to minimize the barriers that may occur
during the implementation, and to increase the effectiveness and the efficiency of
external loans utilization.
Through the Ministerial Decree Number KEP.25/M.PPN/HK/03/2016, The Ministry of
National Development Planning/National Development Planning Agency (Bappenas)
has issued the DRPPLN 2016. As the DRPLN-JM/ Blue Book of 2015-2019 was
prepared using the program based approach, therefore, the DRPPLN of 2016 also be
presented in program-based approach. It means that the DRPPLN of 2016 may contain
initial proposed projects in the DRPLN-JM or part of program/ project of the DRPLNJM of 2015-2019. As the program based approach applied, the projects which are listed
in the DRPLN-JM of 2015-2019 can be adjusted in terms of locations, scope of projects,
and project cost, as long as the adjustment remains in the corridors of the target
achievement of external loan programs listed in the DRPLN-JM 2015-2019.

The DRPPLN 2016 is presented in two chapters. Chapter 1 consists of the


recapitulation of the projects by the executing agencies, by the indicative sources of
financing, and by the sector allocation. While Chapter 2 consists of the summary of
each project information, such as location, scope, outputs and outcomes as well as
stakeholders involved in project implementation (project digest).

2. Recapitulation and List of Projects in the DRPPLN 2016


The DRPPLN 2016 consists of 25 proposed projects, with the total loan amount of USD
4.0 billion, and the counterpart funding of USD 1.2 billion. The recapitulation of
proposed projects in the DRPPLN 2016 on the basis of executing agencies is shown in
Table 1, while the proportion of infrastructure and non-infrastructure sector allocation
is presented in Table 2.
Table 1. The DRPPLN 2016 by Executing Agencies

No

Executing Agency

Number of
Projects

Ministries/Agencies

Amount (USD million)


Loans

Counterpart
Funds

24

3,889.4

1,183.0

Ministry of Public Works

18

3,196.4

1,064.9

Ministry of Transportation

175.1

30.9

Ministry of Research,
Technology, and Higher
Education

279.7

36.9

Ministry of Religious
Affairs

238.2

50.3

106.8

10.7

Local Government of
Aceh Province

106.8

10.7

Total

25

3,996.2

1,193.7

Local Governments
5

vi

The external loan projects, as stated in the DRPPLN 2016, mostly will be used to
financed infrastructure sector, such as construction of dam and irrigation (USD 1.56
million, 39%), slum alleviation program (USD 0.8 million, 19%), water supply and
sanitation (USD 0.4 million, 10%), development of highway and national road (USD
0.3 million, 9%), the provision of railway facilities (USD 0.2 million, 4%), and the
provision of bulk water and flood management (USD 0.1 million, 3%). While for noninfrastructure sector, external financing of the DRPPLN 2016 is utilized to support
higher education development (USD 0.5 million, 13%), and health sector (USD 0.1
million, 3%).
Table 2. Recapitulation of the DRPPLN 2016 by Sector
No

Number of
Projects

Sector

Amount(USD million)
Loans

Counterpart Funds

Infrastructure

19

3,371.5

1,095.8

Non-Infrastructure

624.7

97.9

25

3,996.2

1,193.7

Total

Table 3. Recapitulation of the DRPPLN 2016 by Source of Financing


No

Source of Financing

Multilateral Agencies

Loan Amount
(USD million)
2,434.3

ADB

856.9

World Bank

733.0

IDB

744.4

IFAD

100.0

Bilateral Partners

1,561.9

China (Exim Bank)

472.6

Hungary

36.4

Spain

14.8

Korea (EDCF)

228.0

Japan (JICA)

671.7

10

Germany (KfW)

138.4
Total

3,996.2

vii

Some figures/ diagrams of the DRPPLN/ Green Book 2016 as follows:

Diagram A. Proportion of Loan Amount by Type of Executing Agency

Local Governments
2,7%

Ministries/
Agencies
97,3%

Diagram B. Proportion of Loan Amount by Sector

Non Infrastructure
15,6%

Infrastructure
84,4%

viii

Table 4. List of DRPPLN 2016


(in US$ 000)
No

Project Title

Program Title

Loan

Counterpart
Fund

Lender

Ministry of Public Works


Directorate General of Highways

Engineering
Service for
National Roads
Development
Project

Development of
Cileunyi
Sumedang
Dawuan Toll
Road Phase II

Toll Road
Development of
Manado Bitung

Development
and
Improvement
of National
Roads
Program

Toll Road
Development
Program

45,000

ADB

219,399

24,378

China
(Exim
Bank)

78,100

8,678

China
(Exim
Bank)

300,000

769,440

World
Bank

25,200

ADB

26,380

ADB

36,443

10,000

Directorate General of Human Settlement

Community Based
Water and
Sanitation
Program
(PAMSIMAS)

Engineering
Service for
Sanitation
Improvement
Project

Engineering
Service for Water
Supply
Development
Project

IKK Water Supply


Program and
Small Water
Treatment Plant
for Water Scarcity
Area

Drinking
Water
Development
Program

Development
of Waste
Water
Management
Program

Development
of Waste
Water
Management
Program

ix

Hungary

(in US$ 000)


No

Project Title

Program Title

Small Scale Water


Treatment Plants
for Emergency
Relief
National Slum
Upgrading

Slum
Alleviation
Program

Loan

Counterpart
Fund

Lender

14,848

153

Spain

329,760

6,000

IDB

433,000

7,000

World
Bank

2,000

Directorate General of Water Resources

10

11

12

13

14

Engineering
Service for Bulk
Water and Water
Supply
Development
Project
Engineering
Service for Coastal
and River
Development
Project
Flood
Management in
Selected River
Basins
Engineering
Service for Dam
Multipurpose
Development
Project
Engineering
Service for
Irrigation and
Lowland
Development
Project

Provision and
Management
of Bulk Water
Supply
Program

9,620

ADB

ADB
0

Mitigation of
Water
Hazards
Program

Korea
(EDCF)

10,500

108,700

48,668

1,930

Dam
Development
Program

ADB

ADB
0
Korea
(EDCF)

21,679

Development
and
Management
of Irrigation
Program

38,100

ADB

(in US$ 000)


No

Project Title

15

Integrated
Participatory
Development and
Management of
Irrigation Project Phase I

Program Title

Loan

Counterpart
Fund

600,000

Lender

ADB
70,000

100,000

IFAD

16

The Urgent
Rehabilitation of
Strategic
Irrigation for
Western Region of
Indonesia

195,778

27,150

Korea
(EDCF)

17

Komering
Irrigation Project
Stage III

120,000

31,061

Japan
(JICA)

Rentang Irrigation
Modernization
Projet (RIMP)

480,000

62,361

Japan
(JICA)

175,056

30,892

China
(Exim
Bank)

18

Ministry of Transportation

19

Procurement of
Track Material
and Turn Out
Phase II

Railway
Development
Program

Ministry of Research, Technology, and Higher Education

20

Development of
Four Higher
Education
Institutions
Project

Improving
Access, Quality,
Relevance, and
Competitiveness
of Higher
Education

176,486

27,360

IDB

21

University of
Gadjah Mada
Achieving World
Class University
with SocioEntrepreneurial
Spirit

Improving
Access, Quality,
Relevance, and
Competitiveness
of Higher
Education

71,649

7,041

Japan
(JICA)

xi

(in US$ 000)


No

22

Project Title

Program Title

The Plan of
Hasanuddin
University
Hospital
Development

Loan

Counterpart
Fund

Lender

31,566

2,586

Germany
(KfW)

118,201

20,255

IDB

120,000

30,000

IDB

106,800

10,700

Germany
(KfW)

3,996,195

1,193,723

Ministry of Religious Affair

23

24

The
Transformation of
IAINs Into
Modern Islamic
Universities
(TIMEs)
The Development
and Improvement
of Three Islamic
Higher
Educational
Institutions

Improving
Access, Quality,
Relevance, and
Competitiveness
of Islamic Higher
Education

Local Government of Aceh Province

25

Reengineering
and Improving
the Hospitals and
Referral Systems
in Selected Aceh
Districts

Health
Services
Referral
Program

TOTAL

xii

Chapter 2
PROJECT DIGEST

xiii

Kementerian Pekerjaan Umum dan


Perumahan Rakyat/
Ministry of Public Works and Housing

Direktorat Jenderal Bina Marga/


Directorate General of Highways

GB-16-01-2
1.

Project Title

: Engineering Service for National Roads Development


Project

2.

Program Title

: Development and Improvement of National Roads


Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Highways, Ministry of Public


Works and Housing

5.

Duration

: 36 Months

6.

Location

: Nationwide

7.

Objectives
To accelerate the road construction projects of Sumatera, Java, Kalimantan, Bali and
Papua.

8.

Scope of Project
Conduct feasibility studies (FS), environmental impact assessments (EIA), land
acquisition and resettlement plan (LARAP), and detailed engineering design (DED)
for preparing the national road constructions, including flyover/ underpass on
national roads in big cities and railway crossings, ring roads (bypass) and other
strategic road constructions in Sumatera, Java, Kalimantan, Sulawesi, Bali and
Papua Island along 1,000 km.

9.

Activities
Activities

Consulting services

Implementation
Location

Project Implementation Unit


Directorate
General
of
Highways, Ministry of Public
Works and Housing

Nationwide

GB-16-01-2

10. Funding Source


Funding (US $ 000)

Implementing Agency

Loan

Grant

Local

Total

Directorate
General
of
Highways,
Ministry
of
Public Works and Housing

45,000

45,000

Total

45,000

45,000

Source

ADB

11. Disbursement Plan


Disbursement Plan (US $ 000)
1

2nd

st

11,250

Total

3rd
16,875

16,875

45,000

12. Funding Allocation


Activities
a. Preparing FS
documents
b. Preparing EIA and
LARAP documents
c. Preparing DED
documents
Total

Category (US $ 000)


Services

Constructions Goods

11,250
5,625
28,125
45,000

13. Program Reference


BB-ID: BB-1519-R0-03

Trainings Other

GB-16-02-1
1.

Project Title

: Development of Cileunyi - Sumedang - Dawuan Toll


Road Phase II

2.

Program Title

: Toll Roads Development Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Highways, Ministry of Public


Works and Housing

5.

Duration

: 36 months

6.

Location

: West Java Province

7.

Objectives
a. Strengthen the road network in the West Java area to enhance mobility as full
access controlled expressway in order to allow enough capacity for the expected
increase in traffic volume;
b. Improve accessibility and capacity of road networks connecting Bandung and
Cirebon and the proposed new airport and seaport;
c. Promote national and regional development in the corridor-impacted areas and
cities along the road in the eastern part of West Java;
d. Increase productivity of the area and improve access to regional and
international market; and
e. As an alternative of existing national road Cileunyi Sumedang - Dawuan
which the condition of the traffic is dense and prone to disaster.

8.

Scope of Project
a. Civil works of toll road construction for 10.1 km;
b. Consulting services for detailed engineering design and construction
supervision;
c. Land acquisition.

9.

Activities
Activities
a. Civil works
(Rancakalong
Sumedang Section)

Implementation
Locations

Project Implementation Units

West Java Province

Directorate General of
Highways, Ministry of Public
Works and Housing

b. Consulting services
c. Land acquisition

GB-16-02-1
10. Funding Source
Funding (US $ 000)

Implementing Agency

Loan

Directorate General of
Highways, Ministry of
Public Works and Housing
Total

Grant

Local

Total

219,399

24,378

243,777

219,399

24,378

243,777

Source
China
(Exim
Bank)

11. Disbursement Plan


Disbursement Plan (US $ 000)
1

2nd

st

38,246

3rd

61,483

Total

4th

77,509

66,539

243,777

12. Funding Allocation


Activities

Category (US $ 000)


Services Constructions

a. Civil works
b. Consulting services

Goods

Other

228,631
2,180

c. Land acquisition

11,826
1,140

d. Miscellaneous
expenses
Total

Trainings

2,180

228,631

13. Program Reference


BB-ID: BB-1519-R0-01

11,826

1,140

GB-16-03-1
1.

Project Title

: Toll Road Development of Manado - Bitung

2.

Program Title

: Toll Roads Development Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Highways, Ministry of Public


Works and Housing

5.

Duration

: 36 months

6.

Location

: North Sulawesi Province

7.

Objectives

8.

a.

Improve accessibility and capacity of road networks to facilitate traffic


movement in the integrated economic development area (KAPET) of Manado Bitung and Bitung Special Economic Zone (SEZ) as well as to support Bitung
International Hub Port;

b.

Increase productivity by reducing of distributional cost and by opening access


to regional and international market;

c.

Improve economic growth by developing road to support regional


development;

d.

Reduce travel time and travel cost along the corridor;

e.

Provide an alternative road to improve safety and comfort for users.

Scope of Project
Civil works of toll road construction for 7 km.

9.

Activities
Activities
Civil works

Implementation Locations
North Sulawesi Province

(Section 1, Segment 2)

Project Implementation
Units
Directorate General of
Highways, Ministry of
Public Works and
Housing

GB-16-03-1
10. Funding Source
Implementing Agency
Directorate General of
Highways, Ministry of
Public Works and
Housing
Total

Funding (US $ 000)


Loan

Grant

Local

Total

78,100

8,678

86,778

78,100

8,678

86,778

Source

China
(Exim Bank)

11. Disbursement Plan


Disbursement Plan (US $ 000)
1

st

2nd

8,670

3rd
31,240

Total

4th

31,240

15,610

86,778

12. Funding Allocation


Activities

Category (US $ 000)


Services

Constructions

Civil works

86,778

Total

86,778

13. Program Reference


BB-ID: BB-1519-R0-01

10

Goods

Trainings

Other

Direktorat Jenderal Cipta Karya/


Directorate General of Human Settlements

11

GB-16-04-1
1.

Project Title

: Community Based Water and Sanitation Program


(PAMSIMAS)

2.

Program Title

: Drinking Water Development Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency :

5.

Duration

: 48 months

6.

Location

: Nationwide

7.

Objectives

a. Directorate General of Human Settlements, Ministry


of Public Works and Housing;
b. Directorate General of Regional Development,
Ministry of Home Affairs;
c. Directorate General of Village Government
Development, Ministry of Home Affairs;
d. Directorate General of Community and Village
Empowernment, Ministry of Villages,
Disadvantages Regions and Transmigration;
e. Directorate General of Desease Control and
Environmental Health, Ministry of Health.

To increase the number of under-served and low income rural and peri-urban
populations accessing sustained water supply and sanitation services through
mainstreaming programmatic and scaling-up of a community-based approach on
a national scale in the context of universal access to water and sanitation by 2019.
8.

Scope of Project
a.

Community empowerment and local institutional development;

b.

Improving sanitation and hygiene practices;

c.

Water supply and public sanitation infrastructure;

d.

District and village incentive grants;

e.

Implementation support and project management.

13

GB-16-04-1

9.

Activities
Activities

Implementation
Location

Project Implementation Unit


1. Directorate General of Regional
Development, Ministry of Home
Affairs;

a.

2. Directorate General of Village

Community
empowerment and
local institutional
development

Government Development,
Ministry of Home Affairs
3. Directorate General of Community
and Village Empowernment,
Ministry of Villages, Disadvantages
Regions and Transmigration

b. Improving
sanitation and
hygiene practices

Nationwide

Directorate General of Disease


Control and Environmental Health,
Ministry of Health

c. Water supply and


public sanitation
infrastructure
Directorate General of Human
Settlements, Ministry of Public Works
and Housing

d. District and village


incentive grants
e. Implementation
support and project
management

14

GB-16-04-1

10. Funding Source


Implementing Agency
a. Directorate General
of Human
Settlements, Ministry
of Public Works and
Housing

Funding (US $ 000)


Loan

Grant

182,930

b. Directorate General
of Regional
Development,
Ministry of Home
Affairs

35,020

c. Directorate General
of Village
Government
Development,
Ministry of Home
Affairs

14,610

d. Directorate General
of Community and
Village
Empowernment,
Ministry of Villages,
Disadvantages
Regions and
Transmigration

35,020

e. Directorate General
of Disease Control
and Environmental
Health, Ministry of
Health

29,430

300,000

Total

Local*

Total

769,440

1,069,440

769,440

1,069,440

*) Including parallel financing from local government and community

15

Source

World
Bank

GB-16-04-1

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd

3rd

131,760

325,110

Total

4th

357,340

255,240

1,069,440

12. Funding Allocation


Activities

Category (US $ 000)


Services

Constructions Goods

a. Community
empowerment and
local institutional
development
b. Improving
sanitation and
hygiene practices

Trainings

158,070

73,390

c. Water supply and


public sanitation
infrastructure

437,500

d. District and village


incentive grants
e. Implementation
support and project
management
Total

Other

302,930

97,550
170,940

437,500

13. Program Reference


BB-ID: BB-1519-R0-04

16

158,070

302,930

GB-16-05-2
1.

Project Title

: Engineering Service for Sanitation Improvement


Project

2.

Program Title

: Development of Waste Water Management Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Human Settlements, Ministry of


Public Works and Housing

5.

Duration

: 36 Months

6.

Location

: Cirebon City, Kendari City, Tangerang City, Bekasi City


and Bekasi Regency

7.

Objectives
To accelerate the project preparation for sanitation improvement in selected region;
To improve the quality of project implementation.

8.

9.

Scope of Project
a.

Preparation of feasibility studies (FS), detailed engineering design (DED), and


environmental impact assessment (EIA) document;

b.

Preparation of land acquisition and resettlement plan (LARAP) in Cirebon City,


Kendari City, Tangerang City, Bekasi City and Bekasi Regency;

c.

Supervision activities.

Activities
Activities

Consulting services

1.
2.
3.
4.
5.

Implementation
Location

Project Implementation Unit

Cirebon City
Kendari City
Tangerang City
Bekasi City
Bekasi Regency

Directorate General of Human


Settlements, Ministry of Public
Works and Housing

10. Funding Source


Implementing Agency

Funding (US $ 000)


Loan

Grant

Local

Total

Directorate General of Human


Settlements, Ministry of
Public Works and Housing

25,200

25,200

Total

25,200

25,200

17

Source

ADB

GB-16-05-2

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd
2,520

Total

3rd
2,520

20,160

25,200

12. Funding Allocation


Activities
Consulting services
Total

Category (US $ 000)


Services

Constructions

25,200
25,200

13. Program Reference


BB-ID: BB-1519-R0-05

18

Goods

Trainings

Other

GB-16-06-2
1.

Project Title

: Engineering Service for Water Supply Development


Project

2.

Program Title

: Drinking Water Development Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Human Settlements, Ministry of


Public Works and Housing

5.

Duration

: 36 Months

6.

Location

: Riau Province, Bengkulu Province, Banten Province,


West Java Province, and DKI Jakarta Province

7.

Objectives
To accelerate the project preparation for water supply development in selected
region. To improve the quality of project implementation;

8.

9.

Scope of Project
a.

Preparation of feasibility studies (FS), environmental impact assessment (EIA),


and detailed engineering design (DED) document;

b.

Preparation of land acquisition and resettlement plan (LARAP);

c.

Supervision during project implementation.

Activities
Activities

Implementation Location

Project
Implementation
Unit

Consulting services

1. Riau Province (Dumai City,


Rokan Hilir Regency, Bengkalis
Regency)
2. Bengkulu Province (Bengkulu
Tengah Regency, Bengkulu City,
Seluma Regency)
3. Banten Province and DKI Jakarta
Province
4. West Java Province (Sumedang
Regency, Majalengka Regency,
Indramayu Regency, Cirebon
Regency, and Cirebon City)

Directorate
General of
Human
Settlements,
Ministry of
Public Works and
Housing

19

GB-16-06-2

10. Funding Source


Funding (US $ 000)

Implementing Agency

Loan

Directorate General of
Human Settlements ,
Ministry of Public Works
and Housing
Total

Grant

Local

Total

26,380

26,380

26,380

26,380

Source

ADB

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd
7,275

Total

3rd
14,100

5,000

26,380

12. Funding Allocation


Activities
Consulting services
Total

Category (US $ 000)


Services

Constructions

26,380
26,380

13. Program Reference


BB-ID: BB-1519-R0-04

20

Goods

Trainings

Other

GB-16-07-1
1.

Project Title

: IKK Water Supply Program and Small Water


Treatment Plant for Water Scarcity Area

2.

Program Title

: Drinking Water Development Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Human Settlements, Ministry of


Public Works and Housing

5.

Duration

: 24 months

6.

Location

: Nationwide

7.

Objectives
To increase access to clean water for communities in water scarcity areas.

8.

9.

Scope of Project
a.

Construction of water supply systems for communities in water scarcity areas:

b.

Construction of water treatment plant;

c.

Construction of raw water transmission pipelines;

d.

Construction of distribution pipelines.

Activities
Activities
a.

Construction of water
treatment plant

b.

Construction of raw water


transmission pipeline

c.

Construction of distribution
pipeline

Implementation
Locations

Nationwide

Project Implementation
Units
Directorate General of
Human Settlements,
Ministry of Public
Works and Housing

10. Funding Source


Implementing Agency
Directorate General of
Human Settlements, Ministry
of Public Works and Housing
Total

Funding (US $ 000)


Loan

Grant

36,443
36,443

21

Local

Total

10,000

46,443

10,000

46,443

Source

Hungary

GB-16-07-1
11. Disbursement Plan
Disbursement Plan (US $ 000)
1

Total*

2nd

st

10,360

26,083

36,443

*) Not including local funding of USD 10.0 million

12. Funding Allocation


Activities

Category (US $ 000)


Services

Constructions

a. Construction of
water treatment
plant
b. Construction of
raw water
transmission
pipeline

46,443

c. Construction of
distribution
pipeline
Total

46,443

13. Program Reference


BB-ID: BB-1519-R0-04

22

Goods

Trainings

Other

GB-16-08-1
1.

Project Title

: Small Scale Water Treatment Plants for Emergency


Relief

2.

Program Title

: Drinking Water Development Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Human Settlements, Ministry of


Public Works and Housing

5.

Duration

: 24 months

6.

Location

: Medan, Bekasi, Surabaya, and Makassar City

7.

Objectives
a. To provide small scale water treatment plants that can be effectively used in
case of emergency;
b. To overcome the difficulties to get save drinking water in emergency situations.

8.

Scope of Project
a. Infrastructure, including land acquisition and storage construction, access road
to small scale water treatment plant storage location/ location open storage
(LOS), electricity, communication, and fencing storage;
b. Procurement and installment of mobile water treatment plant for emergency
relief;
c. Emergency Module Units (EMUs) training program, consists of:
i. EMUs Management and Training through knowledge and capacity
building programs in management, planning, and coordination to provide
training for new staff;
ii. EMUs Operation and Maintenance for Technicians through capacity
building for technical staff to Emergency Module Units operational,
maintenance and sustainability.

9.

Activities
Activities
a.
b.

Infrastructure works
Procurement and
installment of mobile
water treatment plant

Implementation
Locations
Medan (North
Sumatera)
Bekasi (West Java)
Surabaya (East Java)
Makassar (South
Sulawesi)

23

Project Implementation
Unit
Directorate General of
Human Settlements,
Ministry of Public
Works and Housing

GB-16-08-1
10. Funding Source
Implementing Agency
Directorate General of
Human Settlements,
Ministry of Public Works
and Housing
Total

Funding (US $ 000)


Loan

Grant

Local

Total

14,848

153

15,001

14,848

153

15,001

Source

Spain

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

Total*

2nd
12,478

2,370

14,848

*) Not including local funding of USD 0.15 million

12. Funding Allocation


Activities

Category (US $ 000)*


Services

Constructions

a. Infrastructure works
b. Procurement and
instalment of mobile
water treatment
plant
Total

Goods

5,817

133

8,898

133

5,817

*) Not including local funding of USD 0.15 million

13. Program Reference


BB-ID: BB-1519-R0-04

24

8,898

Trainings Other

GB-16-09-1
1.

Project Title

: National Slum Upgrading

2.

Program Title

: Slum Alleviation Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency :

a. Directorate General of Human Settlements,


Ministry of Public Works and Housing
b. Ministry of National Development Planning/
National Development Planning Agency

5.

Duration

: 60 months

6.

Location

: Nationwide

7.

Objectives
a. To improve community access to appropriate infrastructure and services in
order to alleviate slums, based on the 8 slum indicators, such as building
standards, access roads, availability of clean water supply, drainage
connectivity, sewerage management, waste management, fire safety, public
space;
b. To promote collaboration with stakeholders through empowerment of local
governments;
c. To improve community welfare by promoting sustainable livelihoods.

8.

Scope of Project
a. Slum alleviation activities (50 cities, 1,412 villages), in community level and
local government;
b. Slum prevention activities (153 cities, 4,732 villages) through collaboration at
community level and local government;
c. Sustainable livelihood to support slum alleviation and prevention.

25

GB-16-09-1
9.

Activities
Activities

Implementation
Locations

Project Implementation
Units
Ministry of National
Development Planning/
National Development
Planning Agency

a. Institutional and Policy


Development
b. Integrated Planning Support
and Capacity Building for
Local Government and
Communities
c. Urban Infrastructure and
Services Investment Support
d. Block Investments for Slum
Alleviation and Prevention

Nationwide

e. Building Community
Institutions and Local
Government

Directorate General of
Human Settlements,
Ministry of Public Works
and Housing

f. Knowledge Generation and


Review
g. Support to Project
Management Unit
h. Technical Assistance and
Implementation Support

Directorate General of
Human Settlements,
Ministry of Public Works
and Housing

i. Contingency for Disaster


Response

26

GB-16-09-1
10. Funding Source
Implementing Agency
a. Directorate General
of Human
Settlements, Ministry
of Public Works and
Housing
b. Ministry of National
Development
Planning/ National
Development
Planning Agency
Total
*) Not

Funding (US $ 000)


Loan

Source

Grant

Local

Total*

329,760

6,000

335,760

IDB

431,000

7,000

440,000

World
Bank

2,000

762,760

13,000

775,760

including the parallel financing from Central Government & Local Government, which

amounts US$ 1,31 billion.

11. Disbursement Plan


Disbursement Plan (US $ 000)
Source
IDB
World
Bank
Total
*) Not

st

2nd

3rd

5,650 107,240 108,400

4th

5th

Total*

6th

64,600

49,870

92,200 113,600 103,200

71,800

52,000

440,000

12,850 199,440 222,000 167,800 121,670

52,000

775,760

7,200

335,760

including the parallel financing from Central Government & Local Government, which

amounts US$ 1,31 billion.

27

GB-16-09-1
12. Funding Allocation
Activities

Category (US $ 000)*


Services

Constructions

a. Institutional and
Policy Development
b. Integrated Planning
Support and Capacity
Building for Local
Government and
Communities

2,000
89,000

c. Urban Infrastructure
and Services
Investment Support

310,000

d. Block Investments for


Slum Alleviation and
Prevention

233,540

e. Building Community
Institutions and Local
Government

78,730

f. Knowledge
Generation and
Review

4,610

g. Support to Project
Management Unit

35,080

h. Technical Assistance
and Implementation
Support

39,000

i.

Contingency for
Disaster Response

j.

Contingency
Total

Goods Trainings Other

0
12,700
241,810

543,540

6,610 12,700

including the parallel financing from Central Government & Local Government, which
amounts US$ 28,9 million for IDB Project
*)

13. Program Reference


BB-ID: BB-1519-R0-07

28

Direktorat Jenderal Sumber Daya Air/


Directorate General of Water Resources

29

GB-16-10-2
1.

Project Title

: Engineering Service for Bulk Water and Water Supply


Development Project

2.

Program Title

: Provision and Management of Bulk Water Supply


Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Water Resources, Ministry of


Public Works and Housing

5.

Duration

: 36 months

6.

Location

: Java Island, Nusa Tenggara Islands, Maluku Island,


Bangka Belitung Islands, and archipelago region in
Southern and Northern Sulawesi

7.

Objectives

8.

a.

To accelerate the project preparation for bulk water and water supply
development.

b.

To identify and evaluate the water demand and water use in Java, Nusa
Tenggara, and archipelago region;

c.

To identify existing condition of water supply;

d.

To identify the potential of surface water and underground water;

Scope of Project
a.

Conduct research, analysis, mapping area, and rehabilitation system of water


supply;

b.

Prepare basic design of water supply system, budget analysis, estimated


construction cost, and financial analysis;

c.

Identification and preparation of conservation area, and analyze the maximum


supporting capacity of raw and underground water;

d.

Strengthen the capabilities of human resources of bulk water and water supplys
stakeholders.

31

GB-16-10-2

9.

Activities
Activities

Implementation Location

Project Implementation
Unit

Consulting services

Java Island, Nusa Tenggara


Islands, Maluku Island, Bangka
Belitung
Islands,
and
archipelago region in Southern
and Northern Sulawesi

Directorate General of
Water Resources,
Ministry of Public
Works and Housing

10. Funding Source


Funding (US $ 000)

Implementing Agency

Loan

Grant

Local

Directorate General of Water


Resources, Ministry of
Public Works and Housing

2,000

2,000

Total

2,000

2,000

Source

Total

ADB

11. Disbursement Plan


Disbursement Plan (US $ 000)
1

2nd

st

500

Total

3rd
850

650

2,000

12. Funding Allocation


Activities
Consulting services
Total

Category (US $ 000)


Services

Constructions Goods

2,000
2,000

13. Program Reference


BB-ID: BB-1519-R0-09

32

Trainings

Other

GB-16-11-2
1.

Project Title

: Engineering Service for Coastal and River


Development Project

2.

Program Title

: Mitigation of Water Hazard Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Water Resources, Ministry of


Public Works and Housing

5.

Duration

: 36 months

6.

Location

: Nationwide

7.

Objectives

8.

9.

a.

To accelerate the project preparation of coastal and river development;

b.

To identify the constrains during river and coastal development and


rehabilitation planning;

c.

To improve the planning process of river and coastal development and


rehabilitation;

d.

To strengthen the capability of river and coastal human resources;

e.

To compose river and coastal development and rehabilitation


document/standard from project preparation to operation maintenance.

Scope of Project
a.

Analyze river and coastal master plan and feasibility studies;

b.

Prepare complete detailed designs, land acquisitions, resettlement plans,


environmental impact assessments (EIAs), constructions, operation and
maintenance documents for river and coastal development and rehabilitation;

c.

Prepare procurement scheme that will be done during river and coastal
development and rehabilitation projects;

d.

Implement technical and financial analysis for every river and coastal
development and rehabilitation projects;

e.

Strengthen the capabilities of human resources of river and coastals


stakeholders.

Activities
Activities
Consulting services

Implementation Location

Project Implementation Unit


Directorate General of Water
Resources, Ministry of Public
Works and Housing

Nationwide

33

GB-16-11-2

10. Funding Source


Implementing Agency

Funding (US $ 000)


Grant

Local

Directorate General of
9,620
Water Resources,
Ministry of Public Works
10,500
and Housing

9,620

ADB

10,500

Korea
(EDCF)

20,120

Total

20,120

Total

Source

Loan

11. Disbursement Plan


Disbursement Plan (US $ 000)
1

2nd

st

6,124

Total

3rd
11,110

2,886

20,120

12. Funding Allocation


Activities
Consulting services
Total

Category (US $ 000)


Services

Constructions Goods

20,120
20,120

13. Program Reference


BB-ID: BB-1519-R0-11

34

Trainings

Other

GB-16-12-1
1.

Project Title

: Flood Management in Selected River Basins

2.

Program Title

: Mitigation of Water Hazards Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency

: a. Directorate General of Water Resources, Ministry


of Public Works and Housing
b. Directorate General of Agriculture Infrastructure
and Facilities, Ministry of Agriculture
c. Directorate General of Regional Development,
Ministry of Home Affairs
d. Ministry of National Development Planning/
National Development Planning Agency

5.

Duration

: 72 months

6.

Location

: Maluku and Banten Province

7.

Objectives
To better manage and mitigate flood risks in selected rivers and reducing its negative
impacts to economic and social sector, though implementation of process-oriented
integrated flood risk management.

8.

Scope of Project
a. Strengthening watershed conservation activities;
b. Providing public information on flood risks for flood plan management;
c. Improving conveyance of the river for reduction of flood peak;
d. Strengthening communitys preparedness for emergency flood management;
and
e. Improving the capacity of the government in the flood subsector.

35

GB-16-12-1
9.

Activities
Activities
a. Construction
Works
b. Consulting
Services

Implementation
Locations

Project Implementation Unit

Maluku and
Banten
Province

a. Directorate General of Water


Resources, Ministry of Public Works
and Housing
b. Directorate General of Agriculture
Infrastructure and Facilities, Ministry
of Agriculture
c. Directorate General of Regional
Development, Ministry of Home
Affairs
d. Ministry of National Development
Planning/ National Development
Planning Agency

10. Funding Source


Implementing Agency

Funding (US $ 000)


Loan

Grant

Local

Total

a. Directorate General of Water


Resources, Ministry of
Public Works and Housing

87,286

39,080

126,366

b. Directorate General of
Agriculture Infrastructure
and Facilities, Ministry of
Agriculture

11,240

5,032

16,272

c. Directorate General of
Regional Development,
Ministry of Home Affairs

9,011

4,035

13,046

d. Ministry of National
Development Planning/
National Development
Planning Agency

1,163

521

1,684

48,668

157,368

Total

Source

ADB

108,700

36

GB-16-12-1
11. Disbursement Plan
Disbursement Plan (US $ 000)
1

st

13,544

nd

27,613

3rd

4th

31,566

36,286

5th

Total

6th

28,854

19,505

157,368

12. Funding Allocation


Activities

Category (US $ 000)


Services Constructions Goods Trainings Other

a. Construction works
b. Consulting services

85,652
12,302

c. Vehicle and
equipment

1,956

d. Workshop, training,
and socialization

6,050

e. Land acquisition

17,163

f. Contingencies

11,430

g. Others

22,815

Total

12,302

85,652

13. Program Reference


BB-ID: BB-1519-R0-11

37

1,956

6,050

51,408

GB-16-13-2
1.

Project Title

: Engineering Service for Dam Multipurpose


Development Project

2.

Program Title

: Dam Development Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Water Resources, Ministry of


Public Works and Housing

5.

Duration

: 36 months

6.

Location

: Nationwide

7.

Objectives

8.

9.

a.

To accelerate the project preparation for dam development including


recommendations for design approval from the Commission of Dams Safety
and Certificate of Design Approval for dam constructions;

b.

To prepare technical details of dam construction;

c.

To do preparation plans of goods and services procurement.

Scope of Project
a.

Conducting the analysis in term of operation, maintenance, facility construction


and procurement plans;

b.

Conducting the analysis in term of detailed design, land acquisition,


resettlement plan and environmental impact assessment;

c.

Review of dam design;

d.

Certification of design;

e.

Procurement document preparation.

Activities
Activities

Consulting services

Implementation
Location

Project Implementation Unit


Directorate General of Water
Resources, Ministry of Public Works
and Housing

Nationwide

38

GB-16-13-2
10. Funding Source
Funding (US $ 000)

Implementing Agency
Directorate General of Water
Resources, Ministry of Public
Works and Housing
Total

Local

Source

Loan

Grant

Total

1,930

1,930

ADB

21,679

21,679

Korea
(EDCF)

23,609

23,609

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd
7,662

Total

3th
8,360

7,588

23,609

12. Funding Allocation


Activities
Consulting services
Total

Category (US $ 000)


Services

Constructions Goods

23,609
23,609

13. Program Reference


BB-ID: BB-1519-R0-10

39

Trainings

Other

GB-16-14-2
1.

Project Title

: Engineering Service for Irrigation and Lowland


Development Project

2.

Program Title

: Development and Management of Irrigation Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Water Resources, Ministry of


Public Works and Housing

5.

Duration

: 48 months

6.

Location

: Nationwide

7.

Objectives

8.

a.

To accelerate the project preparation of irrigation and lowland development;

b.

To identify the constraints during irrigation and lowland development and


rehabilitation planning;

c.

To improve the planning process of irrigation and lowland development and


rehabilitation;

d.

To assess the benefit of the project in order to increase agricultural production


and farmers income;

e.

To strengthen the capability of irrigation and lowland human resources;

f.

To create irrigation and lowland development and rehabilitation document


standard from project preparation to operation maintenance.

Scope of Project
a.

Analyze irrigation and lowland master plan and feasibility studies (FS);

b.

Prepare complete detailed designs, land acquisitions, resettlement plans,


environmental impact assessments (EIAs), constructions, operation and
maintenance documents for irrigation and lowland development and
rehabilitation;

c.

Prepare procurement scheme that will be done during irrigation and lowland
development and rehabilitation projects;

d.

Implement technical and financial analysis for every irrigation and lowland
development and rehabilitation projects;

e.

Strengthen the capabilities of human resources of irrigation and lowlands


stakeholders.

40

GB-16-14-2

9.

Activities
Activities

Implementation Location Project Implementation Unit

Consulting services

Directorate General of
Water Resources, Ministry
of Public Works and
Housing

Nationwide

10. Funding Source


Implementing Agency
Directorate General of Water
Resources, Ministry of Public
Works and Housing
Total

Funding (US $ 000)


Loan

Grant

Local

Total

38,100

38,100

38,100

38,100

Source

ADB

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd

6,350

3rd

12,700

Total

4th

12,700

6,350

38,100

12. Funding Allocation


Activities
Consulting services
Total

Category (US $ 000)


Services

Constructions

38,100
38,100

13. Program Reference


BB-ID: BB-1519-R0-08

41

Goods

Trainings

Other

GB-16-15-0
1. Project Title

: Integrated Participatory Development and


Management of Irrigation Project - Phase I

2. Program Title

: Development and Management of Irrigation Program

3. Executing Agency

: Ministry of Public Works and Housing

4. Implementing Agency :

a. Directorate General of Water Resource, Ministry of


Public Works and Housing
b. The Agency for Agricultural Extension and Human
Resources Development, Ministry of Agriculture
c. Ministry of Home Affairs
d. Ministry of National Development Planning/
National Development Planning Agency
e. Local Government

5. Duration

: 60 months

6. Location

: Nationwide

7.

Objectives
Increase rice production, to accelerate poverty alleviation in agriculture on western
and eastern region of Indonesia through the establishment of sustainable irrigated
agriculture development in the participative manner emphasizing the
empowerment of the beneficiary farmers and water user's association (WUAs).

8.

Scope of Project
a.

Supporting the integrated development of irrigation facilities through


participatory sustainable integrated development (SID), construction phase,
and operation & maintenance (O&M) activities;

b.

Participatory rehabilitation of rehabilitation system;

c.

Forming and empowerment of water user's association (WUAs);

d.

Empowerment of O&M officers;

e.

Implementation of irrigation asset management;

f.

Improvement of tertiary and on-farm level;

g.

Improvement of conservatory catchment area through public consultation and


dissemination.

42

GB-16-15-0
9.

Activities
Activities

Implementation
Location

a. Civil works

a. Directorate General of Water


Resource, Ministry of Public
Works and Housing

b. Procurement of
equipment
c. Consulting services
d. Training and
workshop
e. Rehabilitation of
irrigation scheme
(district level)

Project Implementation Unit

Nationwide

b. The Agency for Agricultural


Extension and Human
Resources Development,
Ministry of Agriculture
c. Ministry of Home Affairs
d. Ministry of National
Development Planning/
National Development
Planning Agency

f. Rehabilitation of
irrigation scheme
(province level)

e. Local Government

10. Funding Source


Implementing Agency
a. Ministry of Public
Works and Housing

Funding (US $ 000)


Loan

Grant

600,000

56,560

d. National Development
Planning Agency
e. Local Government
Total

Total

23,348

623,348

Source

ADB

b. Ministry of Home
Affairs
c. Ministry of
Agriculture

Local

18,224

18,224

28,428

84,988

1,500

1,500

43,440
700,000

43

43,440
1,500

70,000

771,500

IFAD

GB-16-15-0
11. Disbursement Plan
Disbursement Plan (US $ 000)
1

st

33,635

Total

2nd

3rd

4th

5th

117,308

226,180

244,255

150,122

771,500

12. Funding Allocation


Activities

Category (US $ 000)


Services

Constructions Goods

a. Civil works

2,754

60,449

d. Training and
capacity building

28,171

e. Survey and
investigation

14,337

f. Survey,
investigation, and
design

16,059

g. Irrigation asset
management

130,339

h. Contingencies
Total

Other

447,791

b. Equipment,
vehicles, and
furniture
c. Consulting
services

Trainings

71,600
90,845

447,791

13. Program Reference


BB-ID: BB-1519-R0-08

44

2,754

28,171

201,939

GB-16-16-0
1.

Project Title

: The Urgent Rehabilitation of Strategic Irrigation for


Western Region of Indonesia

2.

Program Title

: Development and Management of Irrigation Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Water Resources, Ministry of


Public Works and Housing

5.

Duration

: 48 months

6.

Location

: Lampung and Banten Province

7.

Objectives
To increase agricultural production, create employment opportunities and improve
socio-economic conditions of the rural population in the Project area through the
provision of assured irrigation & drainage facilities, improved flood control, farm
road system, and village water supply.

8.

Scope of Project
a. Rehabilitation and modernization of irrigation facilities;
b. Development and improvement of irrigation and drainage systems;
c. Operation and maintenance capacity building.

9.

Activities
Activities
a. Construction works
b. Consulting services

Implementation
Locations
Lampung and
Banten Province

c. Land acquisition

Project Implementation
Units
Directorate General of
Water Resources, Ministry
of Public Works and
Housing

10. Funding Source


Implementing Agency

Funding (US $ 000)


Loan

Grant

Local

Total

Directorate General of
Water Resources, Ministry
of Public Works and
Housing

195,778

27,150

222,928

Total

195,778

27,150

222,928

45

Source

Korea
(EDCF)

GB-16-16-0
11. Disbursement Plan
Disbursement Plan (US $ 000)
1

st

27,837

2nd

3rd

43,724

4th

27,837

61,765

Total

5th
61,765

222,928

12. Funding Allocation


Activities

Category (US $ 000)


Services

Constructions

a. Construction
Works
b. Consulting Services

Trainings

Other

143,180
11,834

c. Land Acquisition

8,167

d. Others
Total

Goods

59,764
11,834

143,180

13. Program Reference


BB-ID: BB-1519-R0-08

46

67,913

GB-16-17-1
1.

Project Title

: Komering Irrigation Project Stage III

2.

Program Title

: Development and Management of Irrigation Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Water Resources, Ministry of


Public Works and Housing

5.

Duration

: 96 months

6.

Location

: South Sumatera Province

7.

Objectives
a. To increase and stabilize crop yields and productions in the existing irrigation
area;
b. To introduce diversified cropping pattern, including the rainy season paddy
and dry season paddy as the main crop and palawija (secondary crops);
c. To increase agricultural production by developing new irrigated agricultural
lands with favorable physical conditions for agricultural development; and
d. To strengthen the existing institutions for agricultural support services for an
effective operation of the project.

8.

Scope of Project
a. Civil Works :
- Construction of Lempuing Secondary Canal (6.7 Km) and sub-secondary
canals (67.6 Km);
- Construction of Tertiary System: 8,500 ha;
- Increase of flow capacity and improvement works of existing irrigation
facilities :
i. Improvement of Perjaya Headworks; 1 L.S
ii. Heightening of Komering Main Canal; 13.2 Km
iii. Heightening and improvement of Belitang Secondary Canal (88.0 to
88.15) ; 36.2 Km
iv. Construction of Belitang New Canal for development of 8,500 ha (88.15
to 25) ; 18.5 Km.

47

GB-16-17-1
b. Consulting Services :
- Review and design of Lempuing Irrigation Scheme including preparation of
bidding documents;
- Design for increase of flow capacity and improvement works of existing
irrigation facilities of the Komering Irrigation Project necessary for conveying
water to Lempuing scheme;
- Construction supervision and management works;
- Strengthening of irrigation management;
- Project benefit monitoring and evaluation (PBME).
9.

Activities
Activities

Implementation
Locations

a. Construction works
b. Consulting services
c. Land acquisition

South Sumatera
Province

Project Implementation Units


Directorate General of Water
Resources, Ministry of
Public Works and Housing

10. Funding Source


Implementing Agency

Funding (US $ 000)


Loan

Grant

Local

Total

Directorate General of
Water Resources, Ministry
of Public Works and
Housing

120,000

31,061

151,061

Total

120,000

31,061

151,061

Source

JICA

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st
7,644

2nd
10,916

3rd

4th

21,476

48

34,878

5th
43,229

Total
151,061

GB-16-17-1
12. Funding Allocation
Activities

Category (US $ 000)


Services Constructions Goods Trainings

a. Construction works
b. Consulting services

80,668
10,860

c. Land acquisition

15,289

d. Others
Total

Other

44,244
10,860

80,668

13. Program Reference


BB-ID: BB-1519-R0-08

49

15,289

44,244

GB-16-18-1
1.

Project Title

: Rentang Irrigation Modernization Project

2.

Program Title

: Development and Management of Irrigation Program

3.

Executing Agency

: Ministry of Public Works and Housing

4.

Implementing Agency : Directorate General of Water Resources, Ministry of Public


Works and Housing

5.

Duration

: 76 months

6.

Location

: West Java Province

7.

Objectives

8.

9.

a.

To increase rice production up to target of more than 10 million ton in 2025 by


increasing the cropping intensity of rice from 126 % in present condition to 200 %
of target year 2025 for all irrigation area of 87,840 ha with modernization of the
existing irrigation and drainage system including improvement of water
management;

b.

To improve the productivity of paddy and agricultural crop by the improvement


of water use efficiency to be supplied by the Jatigede Dam through an improvement
of water distribution and water utilization;

c.

To develop the sustainable irrigation systems through the modernization of


irrigation and drainage infrastructure with strengthening/ improvement of
operation & maintenance (O&M) institutions as well as empowerment of water
users association (WUAs) and introduction of asset management;

d.

To increase the income level of the farmers through the additional agricultural
production realized by the implementation of the project.

Scope of Project
a.

Civil works (upgrading works of existing facilities) and construction of new


facilities;

b.

Modernization support program.

Activities
Activities
a.
b.
c.
d.

Civil works
Procurement
Consulting services
Modernization
support program

Implementation
Locations

West Java
Province

50

Project Implementation Units

Directorate General of Water


Resources, Ministry of Public
Works and Housing

GB-16-18-1
10. Funding Source
Funding (US $ 000)

Implementing Agency

Loan

Grant

Local

Total

Directorate General of
Water Resources, Ministry
of Public Works and
Housing

480,000

62,361

542,361

Total

480,000

62,361

542,361

Source

JICA

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd

46,803

93,375

3rd
166,776

4th
147,159

5th

6th

85,188

3,060

Total
542,361

12. Funding Allocation


Activities

Category (US $ 000)


Services Constructions Goods Trainings

a. Civil works
b. Procurement
c. Consulting services

1,807
32,968

d. Modernization
support program

102,518

e. Miscellaneous
expenses
Total

Other

317,995

87,073
32,968

317,995

13. Program Reference


BB-ID: BB-1519-R0-08

51

1,807

102,518

87,073

Kementerian Perhubungan/
Ministry of Transportation

53

GB-16-19-1
1.

Project Title

: Procurement of Track Material and Turn Out -Phase


II

2.

Program Title

: Railway Development Program

3.

Executing Agency

: Ministry of Transportation

4.

Implementing Agency : Directorate General of Railways, Ministry of


Transportation

5.

Duration

: 36 months

6.

Location

: DKI Jakarta Province

7.

Objectives

8.

9.

a.

To recondition the existing railway lines into the real capacity, which is
designed to maintain train speed;

b.

To upgrade the service line for both passenger and freight train operations;

c.

To reduce accident risks.

Scope of Project
a.

Procurement of 1,500 km track materials of the International Union of Railways


(UIC) 54 type;

b.

Procurement of 500 units of turnout.

Activities
Implementation
Locations

Activities
Procurement of track
material and turn out

Project Implementation Units


Directorate General of
Railways, Ministry of
Transportation

DKI Jakarta
Province

10. Funding Source


Implementing Agency

Funding (US $ 000)


Loan

Grant

Local

Total

Directorate General of
Railways, Ministry of
Transportation

175,056

30,892

205,948

Total

175,056

30,892

205,948

55

Source

China
(Exim Bank)

GB-16-19-1
11. Disbursement Plan
Disbursement Plan (US $ 000)
1

2nd

st

41,190

Total

3rd
82,379

82,379

205,948

12. Funding Allocation


Activities

Category (US $ 000)


Services Constructions

Goods

Procurement of track
material and turn out

205,948

Total

205,948

13. Program Reference


BB-ID: BB-1519-R0-14

56

Trainings

Other

Kementerian Riset, Teknologi, dan


Perguruan Tinggi/
Ministry of Research, Technology, and
Higher Education

57

GB-16-20-1
1.

Project Title

: Development of Four Higher Education Institutions

2.

Program Title

: Improving
Access,
Quality,
Relevance,
Competitiveness of Higher Education Program

3.

Executing Agency

: Ministry of Research, Technology and Higher Education

4.

Implementing Agency : Jember University, State University of Malang,


Mulawarman University, Sultan Ageng Tirtayasa
University

5.

Duration

: 48 months

6.

Location

: East Java Province, East Kalimantan Province, and Banten


Province

7.

Objectives

and

Improved the access, quality, relevance, and competitiveness of Higher Education


in Indonesia through the establishment of Center of Excellence for Biotechnology,
Educational Innovation, Tropical Studies, and Food Security.
8.

Scope of Project
a. Jember University
i. Construction buildings;
ii. Equipment, furniture, and fixture;
iii. Soft program;
iv. Project management;
v. Start up workshop;
vi. Midterm review and familiarization.
b. State University of Malang
i. Learning center buildings/twin buildings;
ii. Equipment, furniture, and fixture;
iii. Soft program;
iv. Project management;
v. Start up workshop;
vi. Midterm review and familiarization.

59

GB-16-20-1
c. Mulawarman University
i. Construction buildings;
ii. Equipment, furniture, and fixture
iii. Soft program;
iv. Project management;
v. Start up workshop;
vi. Midterm review and familiarization;
d. Sultan Ageng Tirtayasa University
i. Construction buildings;
ii. Equipment, furniture, and fixture;
iii. Soft program;
iv. Project management;
v. Start up workshop;
vi. Midterm review and familiarization.
9.

Activities
Implementation
Location

Activities

Project
Implementation Unit

Jember University
State University of
Malang
East Java Province,
East Kalimantan
Mulawarman
Province, and Banten
University
Province.
Sultan Ageng
Tirtayasa
University

a. Civil works
b. Equipment procurement
c. Soft Program
d. Start up workshop
e. Midterm Review and
Familiarization
f. Project Management

60

GB-16-20-1

10. Funding Source


Funding (US $ 000)
Implementing
Agency

Local
Loan

Grant

Central
Government

University
Revenue (PNBP)

Total

a. Jember University

44,078

1,996

1,166

47,240

b. State University of
Malang

38,400

9,338

471

48,209

c. Mulawarman
University

44,631

4,844

1,931

51,406

d. Sultan Ageng
Tirtayasa
University

49,377

3,800

3,814

56,991

Total

Source

176,486

19,978

IDB

7,382 203,846

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st
0,050

2nd

3rd

28,940

73,490

4th
60,930

*) Not including allocation for contingencies of USD 14.02 million

61

Total*
163,410

GB-16-20-1
12. Funding Allocation
Activities

Category (US $ 000)


Services

Constructions

a. Civil works

Goods

Trainings

120,351

b. Equipment procurement

45,287

c. Soft program

14,441

d. Start up workshop

80

e. Midterm review and


familiarization
f. Project management

80
9,583

g. Contingency
Total

Other

14,024
9,583

13. Program Reference


BB-ID: BB-1519-R0-17

62

120,351

45,287

14,521

14,104

GB-16-21-1
1.

Project Title

: University of Gadjah Mada Achieving World Class


University with Socio-Entrepreneurial Spirit

2.

Program Title

: Improving
Access,
Quality,
Relevance,
Competitiveness of Higher Education Program

3.

Executing Agency

: Ministry of Research, Technology and Higher Education

4.

Implementing Agency : University of Gadjah Mada

5.

Duration

: 60 months

6.

Location

: D.I. Yogyakarta Province

7.

Objectives

and

a.

Supporting the vision of the University of Gadjah Mada as a pioneer of excellent


and innovative world class national university with the new tag line as a socioentrepreneur university;

b.

Increasing the achievement of accreditation for study programs;

c.

Increasing the capability development of students, study programs, and


research activities;

d.

Constructing the building and its peripheral devices that will be a place to work,
a place to learn, a place to socialize, a vehicle for scientific and identify
development;

e.

The procurement of quality equipment for teaching, research and service


activities;

f.

Developing community services that encourage community self-reliance;

g.

Supporting the effectiveness and efficiency of resource utilization by promoting


the welfare of the academicians;

h.

Improving the ability of teaching staff to do research so increases the number of


scientific publications, and ultimately improves the ratio of professors and nonprofessors;

i.

Preparing qualified graduates who have spirit of entrepreneurship.

63

GB-16-21-1

8.

Scope of Project
i.

Construction of new buildings, for:


a. Smart and green learning center;
b. Information technology learning center and laboratory;
c. Engineering Research Innovation Center (ERIC);
d. Law learning center;
e. Pre-clinic and biomedic learning center and laboratory;
f. Advance pharmaceutical science learning center and laboratory;
g. Animal science learning center and laboratory;
h. Integrated farming learning center and laboratory;
i. Agrotropica learning center and laboratory; and
j. Learning center and teaching factory.

ii.

Equipment procurement, for:


a. Smart and green learning center;
b. ERIC building;
c. Pre-clinic and biomedic learning center and laboratory;
d. Advance pharmaceutical science learning center and laboratory;
e. Animal science learning center and laboratory; and
f. Agrotropica learning center and laboratory.

iii. Human resources development and curriculum design;


iv. Consultant services (detailed engineering design, management and supervision,
equipment); and
v. Project management.
9.

Activities
Implementation
Location

Activities
a. Civil works
b. Equipment procurement
c. Human resources development
and curriculum design
d. Consulting services
e. Project management

D.I. Yogyakarta
Province

64

Project
Implementation Unit
University of
Gadjah Mada

GB-16-21-1

10. Funding Source


Funding (US $ 000)

Implementing Agency

Loan

Grant

Local

Total

Source

University of Gadjah Mada

71,649

7,041

78,690

Total

71,649

7,041

78,690

Japan
(JICA)

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd

3rd

4th

5th

4,354

18,837

22,426

27,259

5,814

Total
78,690

12. Funding Allocation


Activities

Category (US $ 000)


Services

Constructions

a. Civil works

Goods Trainings

57,038

b. Equipment
procurement

14,615

c. Human resources
development and
curriculum design
d. Consulting services
e. Project management
Total

1,455

5,227
355
5,582

57,038

13. Program Reference


BB-ID: BB-1519-R0-17

65

14,615

1,455

Other

GB-16-22-0
1.

Project Title

: The Plan of Hasanuddin University Hospital


Development

2.

Program Title

: Improving
Access,
Quality,
Relevance,
Competitiveness of Higher Education Program

3.

Executing Agency

: Ministry of Research, Technology and Higher Education

4.

Implementing Agency : Ministry of Research, Technology and Higher Education

5.

Duration

: 48 months

6.

Location

: Makassar City

7.

Objectives

and

To improve the medical education quality in Hasanuddin University through medical


science and technology development by integrating education research and health
care service with international standards.
8.

Scope of Project
a. Procurement of equipment, covers:
i. Mandatory equipment for B Class Hospital accreditation;
ii. Five centers of excellence;
iii. Radiology and clinical pharmacy;
iv. Simulation center; and
v. Research laboratory.
b. Human resources development;
c. Development of telemedicine and management information system; and
d. Management and consulting services.

9.

Activities
Implementation
Location

Activities
a. Procurement of equipment;
b. Human resources development;
c. System development;
d. Management and consulting
services.

Hasanuddin
University, South
Sulawesi

66

Project
Implementation Unit
Ministry of Research,
Technology and
Higher Education

GB-16-22-0

10. Funding Source


Funding (US $ 000)

Implementing Agency

Loan

Ministry of Research,
Technology and Higher
Education
Total

Grant

Source

Local

Total

31,566

2,586

34,152

31,566

2,586

34,152

Germany
(KfW)

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd
25,866

Total

3rd
7,634

652

34,152

12. Funding Allocation


Activities

Category (US $ 000)


Services Constructions Goods Trainings Other

a. Procurement of
equipment

26,044

b. Human resources
development
c. System development
d. Management and
consulting services

1,545
4,019
918

e. Contingency
Total

1,626
4,937

26,044

13. Program Reference


BB-ID: BB-1519-R0-17

67

1,545

1,626

Kementerian Agama/
Ministry of Religious Affairs

69

GB-16-23-1
1.

Project Title

: The Transformation of IAINs Into Modern Islamic


Universities (TIMEs)

2.

Program Title

: Improving Access, Quality, Relevance, and


Competitiveness of Islamic Higher Education Program

3.

Executing Agency

: Ministry of Religious Affairs

4.

Implementing Agency : State Islamic Institute of Antasari, State Islamic Institute


of Imam Bonjol, and State Islamic Institute of Sultan
Maulana Hasanuddin

5.

Duration

: 48 Months

6.

Location

: South Kalimantan Province, West Sumatera Province,


and Banten Province

7.

Objectives
a. To transform the three State Islamic Institute (IAINs) into State Islamic
Universities (UINs) by improving the quality and competitiveness of the three
IAINs both at regional and national levels;
b. To refine existing management into good university leadership and
management;
c. To provide a wider access of education for people to the higher education;
d. To construct new buildings for existings and new faculties as well as academic
supporting units, including laboratories, libraries, training and study centers,
and offices, as well as other supporting facilities and infrastructures.

8.

Scope of Project
a. State Islamic Institute of Antasari
i. Construction buildings;
ii. Equipment, furniture, and fixture;
iii. Staff development;
iv. Consultancy;
v. Start up workshop;
vi. Midterm review and familiarization;
b. State Islamic Institute of Imam Bonjol
i. Construction buildings;
ii. Equipment, furniture, and fixture;
iii. Staff development;
iv. Consultancy;
v. Start up workshop;
vi. Midterm review and familiarization;

71

GB-16-23-1
c. State Islamic Institute of Sultan Maulana Hasanuddin
i. Construction buildings;
ii. Equipment, furniture, and fixture;
iii. Staff development;
iv. Consultancy;
v. Start up workshop;
vi. Midterm review and familiarization;
9.

Activities
Activities

Implementation Project Implementation


Location
Unit
State Islamic Institute
South
of Antasari
Kalimantan
Province, West State Islamic Institute
Sumatera
of Imam Bonjol
Province, and State Islamic Institute
Banten
of Sultan Maulana
Province
Hasanuddin

a.
b.
c.
d.
e.

Civil works
Equipment procurement
Staff development
Start up workshop
Midterm review and
familiarization
f. Project management
10. Funding Source
Implementing Agency

Funding (US $ 000)


Loan

Grant

Local

Total

a. State Islamic Institute of


Antasari

39,909

10,099

50,008

b. State Islamic Institute of


Imam Bonjol

38,292

4,171

42,463

c. State Islamic Institute of


Sultan Maulana
Hasanuddin

40,000

5,985

45,985

118,201

20,255

138,456

Total

Source

IDB

72

GB-16-23-1

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd
5,780

3rd

4,372

4th

52,487

Total*

63,229

125,868

*) Not including allocation for contingencies of US$ 12.59 million

12. Funding Allocation


Activities

Category (USD)
Services

Constructions

a. Civil works

Goods

Trainings

b. Equipment
procurement

20,695

c. Staff development

11,807

d. Startup workshop

45

e. Midterm review and


familiarization
f. Project management

60
5,804

g. Contingency
Total

Other

87,458

12,587
5,804

87,458

13. Program Reference


BB-ID: BB-1519-R0-18

73

20,695

11,852

12,647

GB-16-24-1
1.

Project Title

: The Development and Improvement of Three Islamic


Higher Educational Institutions

2.

Program Title

: Improving
Access,
Quality,
Relevance,
and
Competitiveness of Islamic Higher Education Program

3.

Executing Agency

: Ministry of Religious Affairs

4.

Implementing Agency : State Islamic Institute of Sulthan Thaha Saifuddin, State


Islamic Institute of Raden Intan Lampung, and Islamic
State University of Sunan Ampel Surabaya

5.

Duration

: 48 Months

6.

Location

: Jambi Province, Lampung Province, and East Java


Province

7.

Objectives

8.

a.

To deliver better education which is relevant to job demand and promote


Islamic moderateness;

b.

To improve qualification and competence of teaching and non-teaching staffs;

c.

To build resource sharing of pedagogic insights, research findings, and good


academic practices;

d.

To provide advanced and sufficient infrastructure and facilities for education.

Scope of Project
a. State Islamic Institute of Sulthan Thaha Saifuddin
i. Construction buildings;
ii. Equipment, furniture, and fixture;
iii. Staff development;
iv. Consultancy;
v. Start up workshop;
vi. Midterm review and familiarization.
b. State Islamic Institute of Raden Intan Lampung
i. Construction buildings;
ii. Equipment, furniture, and fixture
iii. Staff development;
iv. Consultancy;
v. Start up workshop;
vi. Midterm review and familiarization.

74

GB-16-24-1
c. Islamic State University of Sunan Ampel Surabaya
i. Construction buildings;
ii. Equipment, furniture, and fixture;
iii. Staff development;
iv. Consultancy;
v. Start up workshop;
vi. Midterm review and familiarization.
9.

Activities
Implementation
Location

Activities
a. Civil works
b. Equipment procurement
c. Staff development
d. Start up workshop
e. Midterm review and
familiarization
f. Project management

Jambi Province,
Lampung
Province, East
Java Province

Project
Implementation Unit
IAIN Sultan
Thaha Saifuddin
IAIN Raden Intan
Lampung
UIN Sunan
Ampel Surabaya

10. Funding Source


Implementing Agency

Funding (US $ 000)


Loan

Grant

Local

Total

IAIN Sultan Thaha


Saifuddin

40,000

10,000

50,000

IAIN Raden Intan


Lampung

40,000

10,000

50,000

UIN Sunan Ampel


Surabaya

40,000

10,000

50,000

120,000

30,000

150,000

Total

Source

IDB

75

GB-16-24-1

11. Disbursement Plan


Disbursement Plan (US $ 000)
1st

2nd

6,820

3rd

5,760

Total*

4th

57,352

66,433

136,365

*) Not including allocation for contingencies of US$ 13.64 million

12. Funding Allocation


Activities

Category (US $ 000)


Services

Constructions

a. Civil works

Goods

Trainings

b. Equipment
procurement

23,960

c. Staff development

9,466

d. Start-up workshop

45

e. Midterm review and


familiarization
f. Project management

60
6,189

g. Contingency

13,636

h. Miscellaneous
expenses
Total

Other

96,586

58
6,189

96,586

13. Program Reference


BB-ID: BB-1519-R0-18

76

23,960

9,511 13,754

Pemerintah Daerah Provinsi Aceh/


Local Government of Aceh Province

77

GB-16-25-0
1.

Project Title

: Reengineering and Improving the Hospitals and


Referral System in Selected Aceh Districts

2.

Program Title

: Health Services Referral Program

3.

Executing Agency

: Local Government of Aceh Province

4.

Implementing Agency : Local Government of Aceh Province

5.

Duration

: 60 months

6.

Location

: Aceh Province

7.

Objectives

8.

a.

To improve the quality of services through regionalized referral system in the


Aceh Province;

b.

To improve the quality of human resources through functional training


(medical and nursing) as well as managerial training;

c.

To reduce disparities / inequalities in health status between the district/ city;

d.

To provide Basic Essential Obstetric Newborn Care (BEONC/PONED) services


as the flagship program to improve maternal care and neonatal emergency
services;

e.

To reduce morbidity and mortality, especially in high-risk groups (pregnant


women, newborns, and toddlers);

f.

To implement the center of excellence of cancer diagnosis and medication at the


dr. Zainal Abidin Regional Public Hospital.

Scope of Project
a.

Civil works;

b.

Procurement of equipment;

c.

Training and scholarship;

d.

Consultant services;

e.

System development;

f.

Monitoring and evaluation.

79

GB-16-25-0
9.

Activities
Implementation
Location

Activities
a.
b.
c.
d.
e.
f.

Civil works;
Procurement of equipment;
Training and scholarship;
Consultant services;
System development;
Monitoring and evaluation.

Project Implementation
Unit

Local Government of
Aceh Province

Aceh Province

10. Funding Source


Funding (US $ 000)

Implementing
Agency

Loan

Grant

Local

Total

Local Government
of Aceh Province

106,800

10,680

117,480

Total

106,800

10,680

117,480

Source
Germany
(KfW)

11. Disbursement Plan


Disbursement Plan (US $ 000)
1

st

11,214

2nd
33,642

3rd

4th

40,050

27,127

80

5th
5,447

Total
117,480

GB-16-25-0
12. Funding Allocation
Activities

Category (US $ 000)


Services Constructions

a. Civil works

Goods

Trainings

Other

66,000

b. Procurement
equipment

28,000

c. Consulting
services

4,497

d. System
development

5,000

e. Land
acquisition

6,366

f. Project
management

4,117

g. Others

3,500

Total

9,497

66,000

13. Program Reference


BB-ID: BB-1519-R0-23

81

34,366

7,617