Вы находитесь на странице: 1из 13

GTO/GTD : Friday Weekly Result-Week 14/2016

Group Operation Technology Development


Midstream Technology Development
Item
Project
1

heat loss
FUR 1,2,3


(Rockwool Castable)

Ceramic Fiber Module


Discharge Castable
(Density 128 kg/m3, service temp =
1400c)




Monitor Demand charge

Slab Slitting Project

Application and Downstream Technology Development


Item
Project

Support Downstream & Application


committee

GOTTWALD Crane Management

Slitting Machine

Result-Week 14/2016

lopment
opment
Objective

40%

2%

40%

On Peak

On Peak

SSI can buy stock slabs which have width


more than 1550 mm. with capability to do
width-slitting.

Technology Development
Objective


D&A

GOTTWALD Crene


support

Milestone
1.Heat loss
2. [Furnace and recuperator
efficiency]
1. .2
Trial heat loss

2. PR/PO Order
3.

3.


May'16
1.
Trial

4.
PR/PO

Order

2.

5.

3.

3.
May'16
4.

Trial


1.



5.
2.

3. PR/PO Order Ceramic Fibre / Module

4.
Jun-August'16
5.
1. Monitoring Demand Charge
2. Cosview Monitor
3. Forecast Demand Charge Monitor
1.

2. Match
Costview Level 2

3.

Proved formula
4.




Slab



Model

Product
by Area (FM RM) Combine (FM+RM)
5.
New high Demand
Charge
6. Program Implement
7. /

1. 4/April/16

This week result

1. PR/PO Process Rock wool castable

1. 7/April/16

1..Udomvit , Partcode
2. 4/April/16

QCC GOT (Knowledge Sharing)

Presentation

Mobile Slitting Machine Project


1. Slitting Machine 12 ..59

2. Manpower and safety equipment



12 ..59
3. Sling and hook

- Forklift 32

- Slab 46

18 ..59
4. Rework tool Debread ..59 Slab

- 11 .. 59
- Gouging 11 .. 59
Scarfing touch

5. LPG cylinder

6. Practice for operation and Safety Work instruction Scarfing


This week result

Modular Building
1. JFE SYS
SS
H Beam
1.
BHB
Checkerd plate
1. WCE

Initiative cost reduction GOT

1. Pesent
1. SCD PUR
2. SCD W/H
3. slab 40
SSI

Next step

1.
PR/PO Process
2. May'16
1. May'16

1.
PR/PO Process
2.
Thermal image

1.
PR/PO Process

Online monitoring Cosview Pulpit FM


Operator Demand charge online Monitor
Demand Charge
Demand charge

Next step

Modular Building
1. ,
Pre-cast
2.
Office
LINE
H Beam
1. mock up WCE
Checkerd plate
1.

2. print

1.
WCE

1. De-Berad Scarfing torch

W1
W2
W3
W4

Date
7-Jan-16
14-Jan-16
18-Jan-16
18-Jan-16

Time
11:00 a.m.
14:45 p.m.
11:45 a.m.
11:45 a.m.

Demand Charge (KW)


8,223
33,622
41,356
41,356

Cost (Baht)
609,662
2,492,698
3,066,169
3,066,169

W1
W2
W3
W4

Date
1-Feb-16
1-Feb-16
18-Feb-16
18-Feb-16

Time
12:45 p.m.
12:45 p.m.
11:45 a.m.
11:45 a.m.

Demand Charge (KW)


32,914
32,914
44,000
44,000

Cost (Baht)
2,440,244
2,440,244
3,262,160
3,262,160

Date
W1 1-Mar-16
W2 10-Mar-16
W3 10-Mar-16
W4 10-Mar-16

Time
10:45 a.m.
10:00 a.m.
10:00 a.m.
10:00 a.m.

Demand Charge (KW)


40,400
44,000
44,000
44,000

Cost (Baht)
2,995,256
3,262,160
3,262,160
3,262,160

7,735
573,471


160
140
120
100

Frequency

80
60
40
20
0


15 (KW)

2559

15 (KW)

Frequency

Вам также может понравиться