Академический Документы
Профессиональный Документы
Культура Документы
CONTENTS
Quantity
Surveying
By : Ajay Kumar Singhal
AKS/TRG-NR/QSG/Rev-0, dated 18-Jan-2009
1)
2)
3)
4)
5)
DEFINITION
OBJECTIVES
WHY QUANTITY SURVEYING IS REQUIRED
SCOPE OF WORK
QUANTITY SURVEYING SERVICES
a)
b)
6)
7)
8)
9)
10)
PRE-TENDER PHASE
POST-TENDER PHASE
METHODS
TAKING OFF QUANTITIES
ABSTRACTING
BILLING
METHODS OF MEASUREMENT OF WORKS IN ACCORDANCE TO IS:1200
a)
b)
c)
d)
EARTHWORK
CONCRETE
FORMWORK
STEEL REINFORCEMENT
DEFINITION
CONSTRUCTION PROJECT
To ascertain the
Commercial
Viability of such
project
if implemented
Preparation of
Initial
Estimated Cost
of Project
SCOPE OF WORK
Project Viability Study / Evaluation Stage
Derivation of the
Final Project
Cost
Comparison of Estimated
vis--vis
Executed Cost
OBJECTIVES
To train personnel involved in Quantity Surveying work to be more
effective and to achieve better standards / results in the preparation
of Bill of Quantities and Estimates.
Certification of
Execution
Cost of
Project
Analysis of reasons
for Variation
Issue of Planning
Drawing
Review
Feedback
Quantity
Surveyor
Owner / Employer
Architects
Check with
Initial Estimate
No Variation
Identify Variation,
if any
Variation
Report
To
Review
Employer /
Engineer
Financers
Engineers / Consultants
Quantity Surveyors
Contractors / Subcontractors
Issue of
GFC Drawing
Feedback
To
Insurers
Solicitors
For Execution
Nodal Agencies
Statutory Authorities
Decision
Quantity Surveying
AKS/TRG-NR/QSG/Rev-0, dated 18-Jan-2009
QUANTITY SURVEYING
SERVICES
To Planner for
Initial Project
Planning
Procurement
Action
Material
Identification
Identification of
Variation in
Quantity and in
Contract Value
Purchase
Department
Client
Billing
Sub-Contractor
Billing
Reconciliation
Identification of
Non-scheduled
Item / Extra Item
Scheduled
Item
Material
Analysis of
Rate
Submission to
Employer / Engineer
Quantity Surveying
services
availed into two phases namely :
are
Pre-Tender Phase
Post-Tender Phase
Quantity
(Client bill versus
Sub-contractor
Bill)
Approval of Rates by
Employer / Engineer
Post-Tender Phase
Pre-Tender Phase
price evaluation.
Value Engineering.
work.
Projection of Timely financial statements.
Schedule of materials.
Contract administration.
METHODS
QUANTITY SURVEYING
Booking of Dimensions
Use of method from
Experience /
Knowledge / Data Bank
by Quantity
Surveyor during
Feasibility study stage
Estimation
Cost-in-use
Studies
Project
Budget
Proposal
Cost
Management
Comparison of
Actual vis--vis
Proposed Cost
Cost
Analysis
The golden rule of booking dimensions is to record length first , the breadth or width
second and height / depth or thickness third and last.
Cost
Planning
Project
Implementation
Actual
Cost
Study
Quantity Surveying
AKS/TRG-NR/QSG/Rev-0, dated 18-Jan-2009
1.
Cubic Items
Example : 0.32 Cum RCC 1:2:4 with 20 mm graded stone aggregate in column below
grounded level.
2.
Square Items
Example : 30.00 Sqm half brick wall in cement mortar 1:4 in super-structures in ground
floor.
3.
4.
5.
Provisional sum
Example : Allow provisional sum of Rs. 2000/= for site clearance .
6.
Lump sum :
Example : Mobilization / Demobilization of Plant and Accessories : Rs.50,00,000/- lump
sum.
7.
Abstracting
The process by means of which the quantities of items of identical character and description are
collected from take off sheets, totaled and deduction made in order to arrive at the net total
quantities of respective items and in trade-wise order is called abstracting.
Decision
Issued Drawings from Owner / Consultant / Architect
Incorporate
in drawings
Discuss in
Clients
local
office
Review
Refer to
Consultant /
Owner /
Architect
Note discrepancies, if any, in various drawings
Discrepancies of
minor nature
Discrepancies of
serious nature
No Discrepancy
Billing
It is a claim for the amount of work done or supply. It consists of :a) Work Order or Agreement Number.
b) Item Number.
d) Unit of Item.
Quantity Surveying
AKS/TRG-NR/QSG/Rev-0, dated 18-Jan-2009
Earthwork
Method of
Measurement of
Works in
Accordance to
IS : 1200
Earthwork
Concrete
Formwork
Reinforcement
Concrete
Formwork
Reinforcement
Earthwork
Concrete
Formwork
Reinforcement
In work which will be covered externally with a damp proof covering or protective
masonry work of brick , stone etc.;
Special works like guniting etc, and
In work which required workmen to operate from the outside.
ACTUAL
EXCAVATION
LINE IN
SLOPE
Where soft soil and hard rock are mixed, the measurement for the total
quantity shall be made. The hard rock excavated shall be stacked and
measured in stack. The quantity of the hard rock excavated shall be arrived
at by applying pre-accepted deductions for voids. From the total quantity of
the mixture, the quantity of hard rock excavated shall be deducted to work
out the quantity of soft soil.
EXCAVATION
PAY LINE
FOUNDATION
Earthwork
Concrete
Formwork
Reinforcement
Dimension shall be measured to nearest 0.01 mtr except for the thickness of slab
which shall be measured to nearest 0.005 mtr.
Unless otherwise stated all concrete work shall be measured in cubic meters.
Unless otherwise stated formwork and reinforcement shall be measured
separately.
Columns shall be measured from top of column base to underside of first slab
and subsequently from top of slab to underside of slab above.
Beam shall be measured from face to face of columns and shall include
haunches, if any, between columns and beams. The depth of beams shall be
measured from bottom of slab to bottom of beam except in case of inverted
beam where it shall be measured from top of slab to top of beam.
No deductions shall be made for the following :
Opening up to 0.1
m2
or as specified;
Earthwork
Concrete
Formwork
Reinforcement
Volume occupied by pipes, conduits, sheathing etc. not exceeding 100 cm2 each in
cross-sectional area or as specified.
Quantity Surveying
AKS/TRG-NR/QSG/Rev-0, dated 18-Jan-2009
Earthwork
Concrete
Formwork
Reinforcement
Quantity
As per
drawing
Rate
Amount
Actual as
per Site
Material
Equipment,
Plant &
Tools
Least of
the two
or as per
Contract
condition
Labour
Others
Piece rate
basis
Supply
basis
Overhead,
Profit &
Contingency
Agency
Commission
Misc. Expenses
Material
Ingradient A
Ingradient B
Ingradient C
Coefficient / Unit
Equipment
Quantity / Unit
+
Cost of
Hire
Charges /
Depreciation
Cost of
Operator
& Helper
Cost of
P.O.L.
+
Cost of
Maintenance
& Spares
+
+
X
Rate / Unit
Duration of Deployment
Cost of
Foundation and
Mobilization &
Demobilization
a)
b)
Labour costs,
c)
d)
Contingencies,
e)
Profit.
f)
Quantity Surveying
AKS/TRG-NR/QSG/Rev-0, dated 18-Jan-2009
Quantity Surveying
AKS/TRG-NR/QSG/Rev-0, dated 18-Jan-2009