Вы находитесь на странице: 1из 4

INSTITUTION OF SURVEYORS MALAYSIA

BUILDING COST INFORMATION CENTRE

ELEMENTAL COST ANALYSIS - FORM 1

JOB TITLE : CLIENT :


LOCATION : TENDER DATE :
INFORMATION ON TOTAL PROJECT

Project and Contract information


Project Details and Site Conditions : Contract :

Market Conditions:
Contract Particulars : Competitive Tender List
Cost fluctuation :
Type of Contract : Yes RM Int(JV)/L
No
Basis of Tender : Open/Selected
Bills Of Quantities Competition Government

Bills of Appr. Quant. Negotiated Private

Sched. of Rates/ Serial Provisional Sums RM


Spec. & Drawings Prime Cost Sums RM
Preliminaries RM
Contract Period Stip. By Client: Contigencies RM
Contract Sum RM
Contract Period Offered by Builders: weeks

Number Of Tenders Issue :

Number of Tenders Received :


ANALYSIS OF SINGLE BUILDING
Design / Shape Information
Accommodation and Design Features:

Areas: Functional Unit: m2 Design/Shape:

Lower Ground Floor m2 External Wall Area Percentage of Gross Floor Area:
=
Ground Floor m2 Gross Floor Area
Upper Floor m2 a) Below Ground Floor %
GROSS FLOOR AREA 0 m2 = #DIV/0! Construction

b) Single Storey %
Usable Area m2 Construction
Circulation Area m2
Ancillary Area m2 Storey Height c) 2-Storey %
Internal Division m2 Construction
GROSS FLOOR AREA 0 m2 Av, Below Ground Floor m
d) 3-storey %
Floor spaces not enclosed m2 At Ground Floor m Construction
Roof Area m2
(Structural and Plant Rooms) Above Ground Floor m e) 4-storey %
Construction

Brief Cost Information


Contract Sum :RM Functional Unit Cost excluding
Provisional Sum :RM external works: (RM/m2) #DIV/0!
Prime Cost Sum :RM
Preliminaries :RM being ### % of remainder
Contigencies :RM being % Contract Sum

Contract Sum Less Contingencies RM


THE INSTITUTION OF SURVEYORS MALAYSIA
BUILDING COST INFORMATION CENTRE

ELEMENTAL COST ANALYSIS - FORM 2 0


0

SUMMARY OF ELEMENT COSTS

GROSS FLOOR AREA : - m2 TENDER DATE :


Preliminaries Shown Separately
Total Cost Cost per Element Element Element Reinforced Rein-
Element
of Element m2 GFA unit Unit Rate Ratio/ Concrete forcement
RM RM Quantity RM m2 GFA m3 KG
1 Substructure
1.A. Piling m
1.B. Work Below Lowest Floor Finish m²
Group Element Total : -
2. Superstructure
2.A. Frame m²
2.B. Upper floor m²
2.C. Roof m²
2.D. Stairs
2.E. External Walls m²
2.F. Windows and External doors m²
2.G. Internal Walls & Partitions m²
2.H. Internal Doors m²
Group Element Total : -
3. Finishes
3.A. Internal Wall Finishes m²
3.B. Internal Floor Finishes m²
3.C. Internal Ceiling Finishes m²
3.E. External finishes
Group Element Total : -
4. Fittings and Furnishings P.C. Sum Allowed
5. Services
5.A. Sanitary Installation nos
5.B. Plumbing Installation
5.C. Refuse Disposal
5.D. Air-Conditioning & Ventilation Tm3
System
5.E. Electrical And Telephone
Installation
5.F. Fire Fighting Installation
5.G. Lift & Conveyor Installation
5.H. Communication Installation
5.J. Special Installation
5.K. Builder's Profit and Attendance on
Services
5.L. Builder's Work in Connection with
Services
Group Element Total : -
Sub-total excluding External Works,
Preliminaries and Contingencies -
6. External works
6.A. Site work
6.B. Drainage
6.C. External services
6.D. Ancillary buildings
6.E. Recreational facilities
Group Element Total : -
Preliminaries
TOTAL (less Contigencies) -
0

30-Dec-99

Formwork

M2

Tender Sum
INSTITUTION OF SURVEYORS, MALAYSIA
BUILDING COST INFORMATION CENTRE

ELEMENTAL COST ANALYSIS - FORM 3 0


0
BRIEF SPECIFICATION
GROSS FLOOR AREA : 0 TENDER DATE : 30-Dec-99
ELEMENT SPECIFICATION

1 Substructure
1A Piling Not applicable
1B Work Below Lowest Floor Finish Reinforced Vibrated Quality Control Concrete pad footing, column stump,ground
beam, ground floor slab

2 Superstructure
2.A. Frame Reinforced Concrete column, beam, upstand beam and curved beam.
2.B. Upper floor Reinforced Concrete suspended floor slab
2.C. Roof Reinforced Concrete suspended roof slab and Alang-alang traditional roof
2.D. Stairs Reinforced Concrete staircase with cement and sand screed to receive stone finish,
timber and mild steel handrails and balusters.
2.E. External Walls Half clay brickwork
2.G. Windows and External doors Timber fixed glass panel window, timber flush door and fire-rated door
2.I. Internal Walls & Partitions Half clay brickwork
2.J. Internal Doors Stainless steel butt hinges, close door, mortise lock, dead lock, mild steel flush bolt,
mild steel pull handle and toilet indicator

3 Finishes
3.A. Internal wall Finishes Plaster and paint, ceramic tiles, stone and pebble wash
3.B. Internal floor Finishes Cement and sand paving, stone, slate, marble, kempas tible, and carpet.
3.C. Internal ceiling Finishes Cement and sand plaster and paint
3.D. Painting & Decoration One undercoat and two coat of 'JOTASHIELD' arcylic paint or other equivalent
3.E. External finishes emulsion
Plaster andpaint to ceramic
paint, plasteredtiles,
wall,stone
column
andand hollow
pebble brickwork.
wash

4 Fittings and Furnishings Built in furniture, loose furnitures and fittings, decorative ceiling, interior designer's
floor and wall finishes, decorative and arch lighting, artifacts

5 Services
5A Sanitary Installation Pedestal water closet, siphon-jet pedestal water closet, wall hung was basin, urinal,
toilet roll holder, self-rimming under counter top wash basin, handspray controlled
bidet, single bowl sink, stainless steel hand dispenser, frameless mirror, hook and
stopper, floor trap, handicap water closet, handicap grab bar.
5B Plumbing Installation Cold water piping installation, piping sanitary and fibre glass water storage tank
5C Refuse Disposal Not applicable
5D Air conditioning Installation As specified by M&E Engineer
5E Electrical And Telephone Installation As specified by M&E Engineer
5F Fire Fighting Installation As specified by M&E Engineer
5G Lift and Conveyor Installation
5H Communication Installation
5J Special Installation Swimming pool and pool bar
5K Builder's Profit and Attendance on In connection with mechanical and electrical services
5L Services
Builder's Work in Connection with In connection with mechanical and electrical services
Services
6 Externanal Works
Site clearance and temporary works,roadworks and carpark,rubble stone wall,
6.A. Site work rubble feature wall, pony-tail railing and planter box
6.B. Drainage Surface water drainage
6.C. External services Water reticulation
Guard house, refuse chamber, hose reel water tank and pump room, gen set and
6.D. Ancillary buildings switch room
6.E. Recreational facilities

Вам также может понравиться