What: ONGOING XU CAMPUS INFRASTRUCRE DEVELOPMENTS


When: June 2010

The information below provided by the Xavier University (XU) - Physical Plant Office
(PPO)to the Central Student Government (CSG) for information disclosure purposes
to the XU Studentry is the Ongoing Campus Infrastructure Developments for the
School Year 2010-11. Also, information about scope and status of the project as of
June 2010 are provided.

PROJECT NAME SCOPE OF WORKS STATUS


* SC basement & roofdeck, Engg Roofdeck, Med
1 Waterproofing for final approval
canopy and roofdeck, gym basement
2 Campus Ministry Office Renovations renovation of faculty room for final approval
*installation of electric fan to classrooms for
3 Classroom Electric Fan for Teachers for request to purchasing unit
teachers
*bidding and procurement of RFID based turnstile
5 Turnstile Project ongoing works
system
6 Chemistry laboratory *renovation of Chemistry Laboratory ongoing works
*gutter and roofing repair
7 Chapel repair *pews repair ongoing works
*building repainting
*fire sprinkler and alarm system
8 CIT Bldg. fire sprinkler project *construction of ramp ongoing works
*renovation of ground floor CR for handicapped
9 SBM retrofitting building retrofitting ongoing works
10 SOE Project renovation of Deans Office completed
11 Gym Stairs renovation of Gym stairs (front and rear) ongoing works
XU Main Campus Structured Cabling System
12 Structured cabling system ongoing works
Project (Phase I, II,III)
13 Math Department renovation of faculty room planning stage
*construction of new canteen
*construction of SEP business center
14 New Canteen development planning stage
*construction of Bookcenter
*construction of DSA/OSA office
*SBM admin & faculty office renovation
15 SBM renovations planning stage
*Graduate School classrooms & AVRs
16 Engineering Admin Office Office renovation planning stage
*expand dental area to accommodate additional
17 Clinic dental area extension planning stage
dental chair
18 Marine Center at Jasaan new marine center planning stage

19 Museo renovations renovate building to accommodate artist plans planning stage


* ONGOING XU CAMPUS INFRASTRUCRE DEVELOPMENTS information provided by XU-PPO as of June 2010.