AL FAROOK RESIDENTIAL SENIOR SECONDARY SCHOOL

FIRST MID TERM EXAMINATION 2010-2011

MATHEMATICS QUESTION PAPER SOLVED

CLASS XII
3. .(as this is a graph question you have to draw a graph and shade the appropriate region using the
information given below)

X+Y<24

ITEM A ITEM B REQUIREMENT


TIME 1 0.5 16
COST 300 160

MAXIMISE

Z=300X+160Y

Subject to constraints

X+0.5Y≤16

X 0 16
Y 32 0

X+Y≤24

X 0 24
Y 24 0

At A(9,15)

Z=300*9+15*160=5100

At B (16,0)

Z=4800

At C (0,0)
Z=0

At D (0,24)

Z=3840

There fore, inorder to make maximum profit 9 of item A and 15 of item B should be produced.

4.(as this is a graph question you have to draw a graph and shade the appropriate region using the
information given below)

Z=2X+Y

X+3Y=6

X 0 6
Y 2 0

X-3Y=3

X 0 3
Y -1 0

3X+4Y≤24

X 0 8
Y 6 0

-3X+2Y=6

X 0 -2
Y 3 0

5X+Y=5
X 0 1
Y 5 0