Kick Off Meeting FOTS PARE-PARE

Meeting No: 01
Project: FOTS Pare-Pare
Date & Time: 28 – 29 September 2010 & 09.00 – Selesai
Venue: Ruang Meeting ............... Hotel Jayakarta

COMPANY NAME SIGNATURE

1. Kelana S Dewa 1.
TSEL
2. Sutrisno 2.
3. Janiator 3.

PT. Sufia
1. Soeparno 1.
Technologies
2. Alfian 2.

1. Agus Haryono 1.
PT. Tricomindo CM 2. Dwi Wikutomo 2.
3. Fajar Budi I. 3.
4. M. Ridwan Azir 4.

Detail Implementation Proyek FOTS Pare-Pare:


Kontrak PO HOP102047 OSP PT. Sufia Technologies 20 Agustus 2010 s/d 3 Desember 2010 (15 Minggu)
Kontrak PO HOP102167 PT Tricomindo Cipta Mandiri
Panjang Pekerjaan OSP 131,750 Km
No Subject Action Item Start Finish Status Responsible Party
LOKASI PARE-PARE
1 PARE-PARE CITY
Terminasi OTB (4 pcs) +
OSP Link to
Instalation Cable 2 x 48 Core 18 Okt 10 21 Okt 10 NOK Sufia / Tricomindo
Pare-Pare
New Rack 19 incs (1 pcs)
2 PARE-PARE
Terminasi OTB (2 pcs) +
OSP Link to
Instalation Cable 1 x 48 Core 5 Okt 10 18 Okt 10 NOK Sufia / Tricomindo
Paslak
New Rack 19 incs (1 pcs)
3 BUKHAR
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 26 Okt 10 1 Nov 10 NOK Sufia / Tricomindo
Lapade
New Rack 19 incs (1 pcs)
4 LAPADE
Terminasi OTB (2 pcs) +
OSP Link to
Instalation Cable 1 x 48 Core 1 Nov 10 8 Nov 10 NOK Sufia / Tricomindo
Lapade2
New Rack 19 incs (1 pcs)
5 LAPADE2
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 8 Nov 10 15 Nov 10 NOK Sufia / Tricomindo
Makadae
New Rack 19 incs (1 pcs)
6 MAKADAE
OSP Link to Terminasi OTB (4 pcs) + 5 Okt 10 17 Okt 10 NOK Sufia / Tricomindo
BSC Sidrap Instalation Cable 2 x 48 Core

1/4
New Rack 19 incs (1 pcs)
7 BSC SIDRAP
Terminasi OTB (4 pcs) +
OSP Link to
Instalation Cable 2 x 48 Core 18 Okt 10 19 Okt 10 NOK Sufia / Tricomindo
Sidrap City
New Rack 19 incs (1 pcs)
8 SIDRAP CITY
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 20 Okt 10 28 Okt 10 NOK Sufia / Tricomindo
Kadidi
New Rack 19 incs (1 pcs)
9 KADIDI
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 28 Okt 10 2 Nov 10 NOK Sufia / Tricomindo
Manisa
New Rack 19 incs (1 pcs)
10 MANISA
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 3 Nov 10 8 Nov 10 NOK Sufia / Tricomindo
Rappang
New Rack 19 incs (1 pcs)
11 RAPPANG
Terminasi OTB (4 pcs) +
OSP Link to
Instalation Cable 2 x 48 Core 9 Nov 10 13 Nov 10 NOK Sufia / Tricomindo
Kampis
New Rack 19 incs (1 pcs)
12 KAMPIS
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 14 Nov 10 21 Nov 10 NOK Sufia / Tricomindo
Baranti
New Rack 19 incs (1 pcs)
13 BARANTI
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 5 Okt 10 12 Okt 10 NOK Sufia / Tricomindo
Titoang
New Rack 19 incs (1 pcs)
14 TIROANG
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 13 Okt 10 23 Okt 10 NOK Sufia / Tricomindo
Pinrang Inner
New Rack 19 incs (1 pcs)
15 PINRANG INNER
Terminasi OTB (2 pcs) +
OSP Link to
Instalation Cable 1 x 48 Core 24 Okt 10 27 Okt 10 NOK Sufia / Tricomindo
Pinrang
New Rack 19 incs (1 pcs)
16 PINRANG
Terminasi OTB (4 pcs) +
OSP Link to
Instalation Cable 2 x 48 Core 28 Okt 10 1Nov 10 NOK Sufia / Tricomindo
Manarang
New Rack 19 incs (1 pcs)
17 MANARANG
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 4 Nov 10 18 Nov 10 NOK Sufia / Tricomindo
Pinrang
New Rack 19 incs (1 pcs)
18 SUPPA
Terminasi OTB (4 pcs) +
OSP Link to
Instalation Cable 2 x 48 Core 29 Okt 10 4 Nov 10 NOK Sufia / Tricomindo
Manarang
New Rack 19 incs (1 pcs)
19 PLTD SUPPA
Terminasi OTB (1 pcs) +
OSP Link to Instalation Cable 1 x 24 Core
25 Okt 10 29 Okt 10 NOK Sufia / Tricomindo
Suppa New Rack 19 incs (1 pcs)

20 SOREANG
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 12 Okt 10 25 Okt 10 NOK Sufia / Tricomindo
PLTD Suppa
New Rack 19 incs (1 pcs)

2/4
21 PASLAK
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 5 Okt 10 12 Okt 10 NOK Sufia / Tricomindo
Soreang
New Rack 19 incs (1 pcs)
22 RESIDEN
Terminasi OTB (1 pcs) +
OSP Link to
Instalation Cable 1 x 24 Core 10 Nov 10 18 Nov 10 NOK Sufia / Tricomindo
Paslak
New Rack 19 incs (1 pcs)
23 ANDI
Terminasi OTB (2 pcs) +
OSP Link to
Instalation Cable 1 x 48 Core 1 Nov 10 10 Nov 10 NOK Sufia / Tricomindo
Residen
New Rack 19 incs (1 pcs)
24 GRAPARI PARE-PARE
Terminasi OTB (2 pcs) +
OSP Link to
Instalation Cable 1 x 48 Core 26 Okt 10 1 Nov 10 NOK Sufia / Tricomindo
Andi
New Rack 19 incs (1 pcs)
25 BOJO
OSP Link to Terminasi OTB (1 pcs) +
Grapari Pare- Instalation Cable 1 x 24 Core 15 Okt 10 26 Okt 10 NOK Sufia / Tricomindo
Pare New Rack 19 incs (1 pcs)
26 KUPA
Terminasi OTB (2 pcs) +
OSP Link to
Instalation Cable 1 x 48 Core 5 Okt 10 15 Okt 10 NOK Sufia / Tricomindo
Bojo
New Rack 19 incs (1 pcs)
27 PARE-PARE CITY 2
OSP Link to Terminasi OTB (1 pcs) +
Pare-Pare City Instalation Cable 1 x 24 Core 21Okt 10 25 Okt 10 NOK Sufia / Tricomindo
and Bojo New Rack 19 incs (1 pcs)

Note:
1. Handle HHpit 19mm, HHsp 22mm, HHpsp 22mm, HH1 22
2. Belmouth u/ HHsp, HHpsp, HH1 4bh
3. Label HHsp nama kota+ring (PRE01...) HHpsp (PRE01/1....), label dlm HH menggunakan mika acrylic
4. Rambu jangan mencantumkan project Telkomsel
5. Sper HDPE di belmouth diberi sper panjang 20cm
6. Clem di HBPS berjarak 1m
7. U/ crosing jalan dan rel KA menggunakan pipa PVC-sub-duct 3 way- HDPE
8. Riser pipe 6m u/ HBPS
9. Pelindung Steel wire/ labrang menggunakan HDPE kuning 32/28 p=3m
10. Span wartel labrang D-12, span wartel hinging D-16
11. HBPS 1 mengunakan pole 9 m dan HBPS 2 mengunakan pole 11 m
12. RVC dng panjang lebih panjang 6 m posisi sambungan panjang dibagi 2
13. Perijinan jalan Nasional, Propinsi, Kabupaten Pinrang status menunggu proses pembuatan bank garansi dan
surat pernyataan Telkomsel
14. Perijinan jalan Kabupaten Sidrap dan Kota Pare-Pare status proses penghitungan bank garansi oleh dinas
PU
15. Pekerjaan dimulai dari site ke jalan raya untuk menghindari community issue
16. Membawa surat ijin asli yang berasal dari TPI
17. Menggunakan ID Karyawan
18. Mencantumkan No Handphone setiap PIC
19. Jika ada perubahan nama dan lokasi kerja, segera diinformasikan ke TPI untuk dibuatkan surat ijin baru atau
memo.
20. Vendor atau kontraktor tidak diperkenankan meninggalkan utang-piutang, janji-janji terhadap warga sekitar.

21. Spesifikasi sesuai kesepakatan DRM sbb :

No Item Spesifikasi
1 Kabel Fiber Optic CCSI SM G.652.D with polyaramid yarn
2 OTB Network Cable 24 Core dan 48 Core

3/4
3 Joint Closure 3M
4 Loss Splicing 0.1 dB
5 HDPE tanam langsung Unilon, OD = 40mm, T = 4mm
6 Besi Tulangan KS 10 SNI
7 Ball Marker 3M with ID
8 ODC Network Cable

22. Contact Person

NO INSTANSI NAMA NOMOR HP KETERANGAN


1 PT. TELKOMSEL Kelana Saha Dewa 0811 977 795 Project Manager
Sutrisno 0811917659 PIC FO Pare-Pare Inner City
Janiator 08124800077 NOS Regional Sulawesi Papua
Chandra 0811400079 NO Kendari

2 PT. SUFIA Alvian 08122-0091517 Site Manager


Ebe Casba 0813-4500-2407 Koordinator Supervisor

3 PT. Tricomindo Cipta Mandiri Fajar Budi Ismanto 08122260555 Project Manager
Dwi Wikutomo 08123070274 Team Leader
Agus Haryono 081355298422 Enginnering OSP & ISP

Manpower
 Team Rojok = 450 orang
 Team Tarik Kabel = 75 orang (5 Team)
 Team Sipil Hand Hole & Jembatan = 32 orang
 Team Jointer = 15 orang (5 Team)