5 Questions on Project Quality Management
1. Process Analysis is a function of:
A. Performance Analysis
B. Quality Metrics
C. Process Improvement Plan By Mughees Sarwar Awan at 9:50 am, 5/8/09
Answer A. The option B is incorrect because a Quality Audit is to identify inefficiencies, non-compliance in
project activities. It does not necessarily identify the root cause.
Answer D. Run Chart shows the past pattern of variation. Trend Analysis involves forecasting the future
trend based on past performance.
Answer D. Note that Pareto diagram is not the best tool for root-cause analysis. It mainly helps the project
management team to quantify and categories the defects/issues according to sources (e.g. engineering defects,
acoustic defects, setup problems, etc)
5. A planning phase for an engineering component generated 80 engineering drawings. The QA team
randomly selected 8 drawings for inspection. This exercise can BEST be described as example of:
A. Inspection
B. Statistical Sampling
C. Flowcharting
D. Control Charting Answer B. Inspection” is what the team is doing on individual drawings;
however, the entire exercise of random selection and inspecting a work product is known as
“Statistical Sampling” .