Hi,

I'm new to this field and still study PM. So can you tell me how to reduce the p
roject duration by 4 weeks (5 option).
These are my task and duration(weeks),Crash time(weeks) and Predecessor
1. Planning- Duration 2 weeks- Crash time 1 week -Predecessor None
2. Requirement Study - Duration 3 weeks- Crash time 2 weeks -Predecessor 1
3. Feaibility Study - Duration 2 weeks- Crash time 1 week - Predecessor 1
4. Risk Analysis - Duration 4 weeks- Crash time 2 weeks- Predecessor 1
5. Design & Development - Duration 5 weeks- Crash time 2 weeks- Predecessor 2,3
6. Testing- Duration 2 weeks- Crash time 1 week -Predecessor 4
7. Implementation - Duration 3 weeks- Crash time 1 week- Predecessor 4
8. Review of System - Duration 3 weeks- Crash time 2 weeks- Predecessor5,6,7
9. Sign off- Duration 2 weeks- Crash time 1 week- Predecessor 8