Академический Документы
Профессиональный Документы
Культура Документы
SCHOOL OF ENGINEERING
Civil & Environmental Engineering This paper MUST be handed
in at the end of the
examination Yes No
✔
CAMPUS: Townsville
STUDENT NAME:
(block letters)
STUDENT NUMBER:
INSTRUCTIONS TO STUDENTS:
Answer all questions.
Marks for each question and its parts are shown in parentheses.
Maximum marks = 60
Copyright Reserved
Question 1: True/False or multiple choice (10 marks)
True False
(ii) Which one of the following is typically associated with bottom-up budgeting?
A: competition for funds is often intense
B: resource requirements are frequently overstated
C: aggregate budgets are quite accurate
D: tasks need not be identified in detail
E: commitment by the functional managers is low
(iii) Each time a production output doubles, the worker hours per unit decrease to a fixed percentage of their
previous value. That percentage is called the mass production factor.
True False
(iv) The statistical measure that can be used to test estimation errors for potential bias is called MAD.
True False
(v) A(n) ___ is a clearly identifiable point in a project or set of activities that commonly denotes a reporting
requirement of completion of a large or important set of activities.
A: event
B: milestone
C: critical event
D: gate
E: checkpoint
(vi) The critical path in a network is the path that
A: is the longest path
B: is the shortest path
C: has the largest number of nodes
D: has the largest number of activities
E: has the greatest technical risk
(vii) The expected time that an activity would take is calculated by the formula TE=(a+4m+b)/6 where a equals
_____, m equals_____, and b equals _____.
A: pessimistic time estimate, most likely time estimate, actual time
B: contingency time estimate, actual time, most likely time estimate
C: optimistic time estimate, most likely time estimate, pessimistic time estimate
D: actual time, pessimistic time estimate, optimistic time estimate
E: most likely time estimate, contingency time estimate, optimistic time estimate
(viii)The critical path contains activities that
A: have the highest costs
B: can't be delayed without slipping the project end date
C: have the highest risk
D: are the most important to the project's success
E: use more resources than other activities
(ix) Activity __________ is defined as the cost per day of crashing a project activity.
A: slope
B: expediting cost
C: premium
D: acceleration cost
E: rush premium
(x) Which of the following should be used as a guideline in crashing a project?
A: crash only activities on the critical path, starting with the least expensive
B: crash any activity, starting with the least expensive
C: crash any activity, starting with the longest
D: crash only activities on the critical path, starting with the longest
(a) State some guidelines for choosing an organisational form for a project. (2)
(b) Define four basic types of project organisation. (3)
(c) Identify key advantages and disadvantages of each type. (3)
(a) Identify various resources that may need to be considered when scheduling projects. (1)
(b) What is resource loading? How does it differ from resource levelling? (2)
(c) What is an activity slope and what does it indicate? (1)
(d) Name four priority rules. How would you determine the best priority rule? (2)
(e) Name three efficiency criteria that might be considered when choosing a multi-project scheduling
system. (1)
(f) What are two methods for addressing the constrained resources allocation problem? (1)
(g) When might a firm choose to crash a project? What factors must be considered in making this
decision? (2)
(a) Five activities of a project to develop a new type of telecommunications satellite were monitored at week 6
as shown in Table 1.
(b) Calculate the critical ratios for the following activities (Table 2) in the World Trade building project. Which
activities are on target and which need to be investigated? (3)
The architectural planning section of a large engineering firm has determined the following lists of activities (Table 3)
necessary to receive approval from the relevant authorities.
As soon as the above activities are completed, the actual project can start.
The project manager has developed the cost estimates and three time estimates - optimistic (a), pessimistic (b) and
most likely (m) - for completion of each activity which are given in Table 4 below:
QUESTION 6 (6 marks)
(a) What are the key management topics in project management? Why is human resource management
important?
(2)
(b) As a project manager, how would you ensure commitment from your team on a project in a remote area in
Northern Territory? (4)
Question 2
(a)
(i) Use the FUNCTIONAL form if the emphasis is on technical performance.
(ii) Cost and schedule are not critical.
(iii) This is also appropriate if the project lies within one functional area and
coordination is not needed.
(iv) This form is also best if large capital investments are required.
(i) Use the PROJECT form if the firm is organized on this basis
(ii) Also appropriate if the firm already has a significant number of projects.
(i) Choose the MATRIX form if the project requires part-time technical skills
from a number of organization’s functional areas.
(b)
(c)
Question 3
(a) skilled and unskilled labour; special skills or services; machine or facility hours;
materials, cash; computing time etc.
(b) Resource loading shows the amounts of various resources required by a specific
schedule during specific time periods. Resource leveling aims to minimize the
period-by-period variations in resource usage (indicated by resource loading
projections) by shifting tasks within their slack allowances, thereby smoothing the
resource loading.
(c) The activity slope identifies the trade-off between the project schedule and the
level of resources in dollars per period of time expedited.
Given the computer facilities available today, it is possible for a PM to try a variety
of priority rules and select one that gives good results on the measure of
importance for each situation. Minimum slack first is generally best.
(f) Heuristics (rule of thumb) and Optimisation models (LP, Branch and bound,
Integer Programming, etc.)
(g) When the activities become delayed and threaten to delay the project
completion; the client changes the project requirements; better allocation of
resources (other than time) can be obtained; competition requires earlier
completion; new projects require this project’s resources, etc.
The factors of importance are the costs and benefits of crashing activities for
earlier completion compared to the costs and benefits of delay (overheads,
penalties, etc.)
Question 4
(a)
D
A, 5
2
C
2
B
3 E
4
Question 5
SOLUTION
(a)
A
D H
C
F
B
I
E
G
(b)
Activity a m b Predecessor Normal cost Crash cost Expected tome Var. Crash days $/crash day
A 3 6 9 - 600 1,500 6 1 3 300
B 2 4 6 - 500 800 4 0.444444 2 150
C 1 2 3 A, B 300 600 2 0.111111 1 300
D 6 7 14 C 800 1,000 8 1.777778 2 100
E 2 4 6 C 400 800 4 0.444444 2 200
F 6 8 16 D 1,000 2,000 9 2.777778 3 333
G 1 2 3 E, F 200 300 2 0.111111 1 100
H 3 6 9 D 600 1,350 6 1 3 250
I 6 10 14 H, G 1,100 1,500 10 1.777778 4 100
(c)
Activity ES EC LS LC Critical Slack
A 0 6 0 6 √ 0
B 0 4 2 6 2
X 6 6 6 6 √
C 6 8 6 8 √
D 8 16 8 16 √
E 8 12 21 25 13
F 16 25 16 25 √
G 25 27 25 27 √
H 16 22 21 27 5
I 27 37 27 37 √
(e)
Variance of critical path = 7.55564; SD = 2.748753
Prob. that the project will be completed in 35 days or less is given by z = (35-37)/2.748753 = -0.7276 which
corresponds to a probability of 23.3%.
Prob. that the project will not be completed in 40 days is given by z = (40-37)/2.748753 = 1.0914 which corresponds
to a probability of (1-0.8621) = 13.8 %.
(f)
Days to Crash costs Total costs
complete
37 0 5500
36* 100 5600
35** 200 5700
Note: Check the critical path after each day of crashing and crash the activity on the critical path which costs the
least for crashing.