(MOTOR CITY (Both Project) ) 4 Confirmed/ Awarded

3 Final Negotiation
(STATUS OF ENGAGEMENT OF SUB-CONTRACTORS/SUPPLIERS
2 Complete
) comparison
(as at 5th June 2008 ) 1 Obtaining quotation
0 Task Not Started

(Item ) Description Expected Remarks

Submitted
Delivery
date

Status

Invited
on site

Ratio
(Provided
by PM)
1.0 HEAD OFFICE ADMINISTRATION
1.1 Insurance 4 Task Completed 7 7 ###
1.2 Performance Bond & Advance Payment Bond 0

2.0 SITE ADMINISTRATION


2.1 Hoarding, gantry gate 30-Dec-07 4 Task Completed 12 5 42%
2.2 Site Office, site facilities, etc 18-Jan-08 4 Task Completed 16 10 63%
2.3 Project Signboard 30-Dec-07 4 Task Completed 11 5 45%
2.4 Temporary road access 5-Jun-08 Procurement Dept.
2.5 Tower Crane 14-Jun-08 2 8 6 75%
2.6 Mobile Crane - Procurement Dept. 24 9 38%
2.7 Diesel - Procurement Dept. 7 4 57%
2.8 Cleaning works - Waste Disposal - Procurement Dept. 10 4 40%
2.9 Tank - water, diesel, septic - 4 Task Completed 14 7 50%
2.10 Surveyor 16-Jan-08 4 Task Completed 5 5 ###
2.11 Temporary lighting - Procurement Dept.
2.12 Temporary water - Procurement Dept. 8 5 63%
2.13 Temporary telephone - Procurement Dept.
2.14 Security - HR Dept. 5 5 ###
2.15 Genset - Procurement Dept. 9 7 78%
2.16 Testing 4-Jun-08 2 2 7 ###
2.17 Scaffolding Procurement Dept. 5 2 40%
2.18 Safety, First aid - 0 Procurement Dept. 15 9 60%

(A0 ) SITE WORKS/ ENABLING WORKS


(A1 ) Site Clearance & Earthworks 13-Jan-08 4 Task Completed 7 5 71%
(A2 ) Shoring works 25-Jan-08 4 Task Completed 9 5 56%
(A3 ) Dewatering Not applicable
(A4 ) Gunniting 15-Mar-08 2 6 5 83%
(A5 ) Piling works Not applicable
(A6 ) Blockworks
a. Material 3-Mar-08 Procurement Dept. 2 0 0%
b. Sub-contractor 2 0 0%
(A7 ) Waterproofing, pile head treatment 1-Apr-08 3 7 6 86%
(A8 ) Anti-Termite Treatment 15-Apr-08 4 Task Completed 10 6 60%
(A9 ) Sub-Structure RC works
a. Labour 12-Apr-08 2 2 2 ###
b. Rebar 12-Apr-08 0 8 5 63%
c. Concrete 12-Apr-08 1 16 9 56%
d. Formwork 12-Apr-08 1

Prepared by: Eric Ho


Page 1 of 2 Dated: 23.01.08
3.0 SITE WORKS - SUB-STRUCTURE
3.1 Site Clearance & Earthworks 13-Jan-08 4 Task Completed 7 5 71%
3.2 Shoring works 25-Jan-08 4 Task Completed 9 5 56%

Prepared by: Eric Ho


Page 2 of 2 Dated: 23.01.08