Note: All the walls and partitions of the Nuclear Medicine laboratory should be made up of 9” thick brick or 6” thick concrete.
Fume Hood to be installed; if required
Fig: A TYPICAL LAY OUT FOR NUCLEAR MEDICINE FACILITY HAVING BOTH GAMMA CAMERA AND PET-CT
INSTALLATIONS.
Note: All the walls of the PET-CT Facility should be made up of thick brick or thick concrete but the walls of PET-CT room should
be concrete only, the thickness of which depends upon the area and workload.
Fume Hood should be installed if required.
FIG: A TYPICAL LAY-OUT FOR A 2-BEDDED ISOLATION WARD FOR HOSPITALISATION OF PATIENTS TREATED
WITH LARGE DOSE OF I-131
Note: All the walls should be made up of concrete and the thickness of which depends upon the area of the room, position of the
bed with walls and the occupancies of all the sides. The ducting line for the fume hood has to be shown in the plan.
FROM ISOLATION WARD I FROM ISOLATION WARD II
VALVE - I VALVE - II
DELAY TANK - 1 DELAY TANK - 2 FIG: DUAL DELAY TANK SYSTEM FOR
COLLECTION AND SAFE DISPOSAL
OF RADIOACTIVE WASTE FROM
ISOLATION WARD
MAIN SEWERAGE
CHAMBER SEWERAGE LINE
Note: The capacity of the delay tank for a single patient is 3000 litres each.