In conceptualization

Defining initial goal, technical specifications, scope of work, identification of resources, singing
stake holders

Activities Predecessor Duration cost


1. Conceptualization - 2 days

2. Organizing Team 1
Members
3. Planning
3.1 Identify individual 2
tasks
3.2 Analyzing team 3.1
members required
3.3 Analyzing 2
requirements of
building
3.4 Analyzing 3
machinery needed
3.5 Analyzing 3
equipment needed
3.6 Analyzing raw 3.4
material needed

4. Managing building
Consulting Real
Estate

Sight visit
Project manager
meeting
Selecting and booking
the building for
factory and oulet
Down payment
(security and advance
rent payment)
5. purchasing machinery
Conducting market
survey (analyzing
vendors)
Asking for quotations
Analyzing quotations
Managers’ meeting
with selected vendor
(bargaining and
agreement on prices)
Placing purchase
order
Receiving machinery
+ payment
Installing machinery
6. Purchasing
equipment
Conducting market
survey (analyzing
vendors)
Asking for
quotations
Analyzing
quotations
Managers’
meeting with
selected vendor
(bargaining and
agreement on prices)
Placing
purchase order
Receiving
equipment +
payment
Renovating
outlet
Organizing and
installing equipment.
7. recruiting employees
Contacting
Negotiations
Hiring and contract
writing

8. purchasing raw
material
Need analysis of type
and quantity required
Market survey
Quotations from
vendors
analysing quotations
managers’ meeting
with selected vendor
(bargaining and
agreement on prices)
Placing order
Receiving and
payment

9. marketing
Placing ad on flex
Board
Ads on 5 cable
network

10. test run


11. handing over the
project to the
contractor