Вы находитесь на странице: 1из 543

HARYANA VIDYUT PRASARAN NIGAM LIMITED (INDIA)

ICB No. WB/2008/G-08

TECHNICAL SPECIFICATION

OF

PACKAGE G-08(A)

220 KV GIS SUBSTATION A-4 FARIDABAD

VOLUME – II
Chief Engineer/MM,
Haryana Vidyut Prasaran Nigam Limited
Shakti Bhawan, Sector-6,
Panchkula-134109
Ph: 0172-2583724 / 2583744
Fax:- 0172-2583724 / 2565746
TECHNICAL SPECIFICATIONS
BID DOCUMENT NO. G-8 VOLUME-II
FOR 220 kV GIS SUB-STATION MATERIAL
SECTION –1 GENERAL 1-16
SECTION –2 GENERAL TECHNICAL REQUIREMENTS 1-77
SECTION-2A SPECIFICATION FOR SF-6 GAS INSULATED SWITCHGEAR (220 1-25
KV)
SECTION –3 TECHNICAL SPECIFICATION OF POWER TRANSFORMER
Chapter-1 100 MVA, 220/66 KV Transformer 1-24
SECTION –4 TECHNICAL SPECIFICATION OF SWITCH GEAR
Chapter-1 198 & 60 kV Gapless SA 1-11
Chapter-2 72.5 kV Isolator & L&E 1-16
Chapter-3 72.5 kV SF-6 Breaker 1-23
SECTION –5 TECHNICAL SPECIFICATION FOR PROTECTIVE GEAR
Chapter-1 72.5 kV CT and 245 kV & 72.5 kV NCTs 1-10
Chapter-2 245 & 72.5 kV CVT/PT 1-13
Chapter-3 Control and Relay Panel without automation 1-37
SECTION –6 TECHNICAL SPECIFICATION OF ELECTRICAL AND
MECHANICAL. AUX
Chapter-1 220 kV XLPE Power Cable 1-11
Chapter-2 220V & 48V Battery 1-9
Chapter-3 220 V Battery Charger 1-5
Chapter-4 220 V DCDB 1-6
Chapter-5 415V, LT Switch Board 1-8
Chapter-6 Fire Fighting equipment 1-5
Chapter-7 i) Unarmoured copper control cable 1-3
ii) Armoured copper control cable 4-6
Chapter-8 11 kV XLPE Power Cable 1-3
Chapter-9 200 KVA, 11/0.4 kV Distribution Transformer 1-9
Chapter-10 LT Power Cables 1-4
Chapter-11 MK 1-8
Chapter-12 100 KVA DG Set 1-10
Chapter-13 AAC Tarantulla Conductor 1-14
SECTION –7 SWITCH YARD ERECTION AND INSTALLATION 1-28
SECTION –8 STEEL STRUCTURE 1-4
SECTION –9 CIVIL WORKS 1-40
SECTION-10 TECHNICAL SPECIFICATION OF PLCC EQUIPMENT
Chapter-1 PLC Terminal with protection coupler 1-11
Chapter-2 Line Trap 1-3
Chapter-3 Coupling Device 1-2
Chapter-4 48 V Battery Charger 1-12
Chapter-5 HF Cable 150ohm (Balanced) 1-5
LIST OF DRAWINGS 1-1
LIST OF GUARANTEED CHARACTERSTICS 1-85
Section-1 (General)

1.00 INTRODUCTION:
The scope of this specification covers construction of 220 kV GIS S/Stn. A-4 Faridabad
(up-gradation of 66 kV S/Stn. A-4 Faridabad to 220 KV Level) of PURCHASER on
supply-cum-erection (turnkey) basis as per Annexure-I on single source responsibility
basis.

1.00.1 a) Complete design and engineering of all the system, sub-systems, equipment, material
and services.
b) Providing engineering data, drawings and O&M Manuals for purchasers review, approval
and records
c) Packaging transportation and insurance from the manufacturers works to the site
including port and custom clearance if required.
d) Receipt, storage, insurance, preservation and conservation of equipment at the site.
e) All civil works as required.
f) Fabrication, pre assembly (if any), erection, testing and putting in to satisfactory
operating of all the equipment/material including successful commissioning.
g) Furnishing of spares on CIP basis.
h) Satisfactory conclusion of the contract.

1.00.2 SCOPE:
Detailed scope of work under this package is listed at clause 1.02.0.
In addition to the requirements indicated in this section (Technical Specification), all
requirements as stated in other sections shall also be considered as a part of this
specification as if completely bound herewith.

1.00.3 The bidder shall be responsible for providing all material, equipment and services
specified or otherwise which are required to fulfill the intent of ensuring operatability,
maintainability and the reliability of the complete work.

1.00.4 It is not intent to specify all aspects of design and construction of equipment mentioned
herein. The systems, subsystems and equipment shall confirm in all respects and shall
be capable of performing in continuous commercial operation.

1.00.5 Whenever a material or article is specified or described by the name of a particular


brand, manufacturer or trade mark, the specific item shall be understood as establishing
type, function and quality desired. Products of other manufactures may also be
considered, provided sufficient information is furnished so as to enable the purchaser to
determine that the products are equivalent to those named.

1.00.6 The bidder may also make alternative offers provided such offers are superior in his
opinion, in which case adequate technical information, operational feed back etc., shall
be submitted with the offer to enable the purchaser to asses the superiority and reliability
of the alternative offered. For each alternative offer, its implications on the performance
shall be clearly brought out in the bid for the Owner to make an overall assessment. In
any case, the base offer shall necessarily be in line with specifications. Under no
circumstances the specified equipment etc., shall be brought out as an alternative.

1.00.7 Any deviation or variation from the scope requirement and/or intent of this specification
shall be clearly mentioned under Deviation Schedule of the Bid Proposal Sheets
irrespective of the fact that such deviation/variation may be standard practice or a
possible interpretation of the specification by the bidder. Except for the
deviation/variations which are accepted by the purchaser before the award of the

1
contract, it will be the responsibility of the bidder to fully meet the intent and the
requirements of the specification within the quoted price. No other departure from the
specification except for the declared deviation indicated by the bidder in his proposal
shall be considered. The interpretation of the purchaser in respect of the scope, details
and services to be performed by the bidder shall be binding, unless specifically clarified
other wise by the purchaser in writing before the award of contract.

1.00.8 The drawing enclosed with the specification is preliminary drawings for bidding purpose
only and subject to changes that may be necessary during detailed engineering after
award, keeping the basic parameters as specified.

1.01.0 Project information


1.01.1 The project information relating to the materialogical data, site conditions, site date
including preliminary soil data of the proposed substations are given in Section-B of this
specification.

1.02.0 Scope of work


1.02.1 The Scope of turnkey basis shall comprise, but not limited to the design, engineering,
manufacture, testing and inspection at manufacturers works, packing supply ,
transportation, transit insurance, delivery to site, unloading, storage and equipment
erection including associated civil works, fire detection hydrant systems, structural
works, cabling, lighting , earthing, any other electrical, mechanical auxiliary
equipment/system, supervision of erection, site testing and commissioning of the 220 KV
Substation(s), training of purchasers personal as required.

1.02.2 The weed growth/ tree cutting shall be responsibility of the bidder. Bidder may note that
purchaser shall not pay any compensation for any loss or damage to the properties or
for tree cutting due to bidder’s works.

1.02.3 The equipment and materials to be supplied by the bidder shall enable completion of the
substation(s) in all respects. The equipment and services as detailed in all sections of
the bidding documents and as shown on the Bid drawings shall be within the scope of
supply of the bidder.

The scope of work shall cover in complete conformity with the specifications, the
following specified equipment/items. Any equipment/items though not specifically
mentioned below but which are required to make the substations complete in all
respects for their safe, efficient, reliable and trouble free operation shall not be deemed
to be included and the same shall be supplied and erected by the Bidder, unless they
are specifically excluded elsewhere in this specifications.

• A GELO of the 220 kV SF-6 Gas insulated S/Stn. A-4 Faridabad (up-gradation of 66 kV
S/Stn. A-4 Faridabad to 220 KV Level) with Double Bus Bar arrangement is enclosed
with the specification. The major electrical equipment required with the switchgear are
also shown in the schematic and listed at Annexure-1.The required mandatory
maintenance equipment are listed as per Annexure-II. However, it may be noted that this
list is not exhaustive and in case any additional equipment is required, the same should
be included in the scope of the supply and the offer should be complete and
comprehensive. In addition, all necessary platform, supports, ladder, cat walks etc. for
maintenance works shall also be supplied.
• The scope also includes shifting of existing 10/12.5 MVA, 66/11 KV T/F from bay No. C-
6 to C-1 & up-gradation of existing 66 KV Double Bus and 66 KV Bus-Coupler bay with
twin tarantulla conductor.

2
• Tentative layout of 220kV GIS building is enclosed with this specification. Bidder shall
treat the dimensions and functional details as a minimum i.e. required under the
scope of specifications. They may however be required to optimize the same during
detailed engineering without affecting any of the functional requirements specified.

• 2 No. 220/66 kV, 100 MVA, Power Transformers

• Control relay & protection equipment

• 220kV XLPE Cable with termination arrangements from line to switchgear (GIS) &
transformer to GIS.

• 11 kV XLPE Cables between 11 kV switchgears and LT transformers along with their


termination arrangements.

• 2 No. 11 KV/433 V 200 KVA Transformers along with switchgear. The existing station
T/F shall be spared and returned to HVPNL. Existing batteries, battery charger, ACDB
and DCDB shall also be spared and returned to HVPNL.

• Grounding/earthing.

• Lighting (Indoor & Outdoor)

• 1.1 kV Power and control cables, instrumentation cables

• Lightening protection

• Erection testing and commissioning of all equipment at site.

• Equipment/structure if any spared shall be returned to HVPNL.

• All civil works associated with erection of SF-6 Gas insulated metal clad, switchgear
including their foundation and cable trenches etc. Civil works shall also include
construction of building, drains, sewerage works and septic tanks, requisite water
facilities etc.
• Cable/Gas Insulated Bus duct sealing ends.
• Recommended spare parts, maintenance tools and other equipment necessary for
maintenance purposes for five years of trouble free services.
• Electrical auxiliary equipment.
• Mechanical auxiliary equipment and services like fire protection, air conditioning and
ventilation, EOT cranes etc.
• Training of purchaser’s design and O&M Personnel.

1.03.0 Services and items


The scope also includes but not limited to the following services/items described herein
and elsewhere in specification.
a) System design and engineering
b) Supply of equipment and material
c) Civil Works
d) Structural works
e) Erection works
f) Project management and site supervision
g) Testing and commissioning

3
h) Interface coordination

1.04.0 System Design and Engineering


a) The Bidder shall be responsible for detailed design and engineering of overall system, sub-
systems, elements, system facilities, equipments, auxiliary services, etc. It shall include
proper definition and execution of all interfaces with systems, equipment, material and
services of purchaser for proper and correct design, performance and operation of the
project.
b) Bidder shall provide complete engineering data, drawings, reports, manuals, etc. for
purchaser’s review, approval and records.
c) The scope shall also include the design and engineering as per details elaborated
elsewhere in this specification.
d) The Bidder shall carry out earth resistivity measurements at the substation site(s) (based on
four electrode method)
e) For all structural works, the bidder shall prepare all fabrication drawings. Similarly for civil
works, the detailed construction drawings shall be prepared by the Bidder.

1.05.0 Supply of Equipment and Material


a) The Bidder shall be responsible for design, engineering, manufacture, testing & inspection
at manufacturer’s works, supply transportation, insurance, delivery at site, unloading,
storage, in plant transportation at site, complete erection & supervision, site testing &
inspection, and successful commissioning of all equipment and material listed at ‘Bill of
Quantities’ enclosed as Annexure-1 of this section, detailed elsewhere in specification and
as shown on the Bid drawings. Any item though not specifically mentioned, but is required to
complete the project works in all respects for its safe, reliable, efficient and trouble free
operation shall also be taken to be included, and the same shall be supplied and erected by
the Bidder without extra cost unless it is explicitly excluded elsewhere in the specifications.

b) All consumables, wastages and damages shall be to the account of bidder.

1.06.0 Civil Works


a) The civil works to be executed by the bidder in accordance with specification shall
include design (wherever applicable), engineering, supply of material and construction of
all items given under Bill of Quantities and all other items required for completing the
substations in all respects.
b) The civil works shall include leveling/dressing, site surfacing (gravel filling), construction
of control room building, roads as per PURCHASER drawings and design and
construction of GIS block building including foundation for all equipments, burying of
pipes/cables (if required), drains and road culverts.
c) All civil works shall be carried out as per the specifications covered under Section-9 of
the bid/contract documents and PWD specifications/latest IS Codes.
d) Demolition of some of existing residential/ office structures in the colony at 66 kV S/Stn.
A-4 Faridabad for utilizing space to facilitate upgradation of 66 kV S/Stn.
A-4 Faridabad to 220 kV level as per GELO.

1.07.0 Erection Works


a) The bidder shall construct, erect and install all equipment and material required for
completion of substation(s) covered under the project. He shall be responsible for
provision of all labour, tools and tackles and supervisory staff for safe, reliable, proper
and correct erection of all equipment required for successful completion of the
substation(s).
b) The tools and plant shall include, but not limited to, special hoisting equipment, cranes,
slings, consumables and all other articles and supplies as required.
c) The bidder shall ensure periodic cleaning of work site and removal of all waste material,
packaging material, surplus earth and left-over and their proper disposal.

4
d) The bidder has to employ suitable manpower and supervision personnel. The bidder is
solely and fully responsible for the safety of personnel and materials. Any damages to
the existing facilities shall be made good by the bidder at no extra cost to the purchaser.
The bidder shall coordinate with site personnel for arranging shut down for
interconnection with the existing systems, if required.

1.08.0 Project management and site supervision


a) The bidder shall be responsible for the overall management and supervision of works.
He shall experiences, skilled, knowledgeable and competent personnel for all phase of
the project, so as to provide the purchaser with a high quality system.
b) The bidder’s supervisory personnel shall provide operation and maintenance assistance
during the warranty period.
c) A Project execution schedule called Master Network (MNW) in the form of PERT
chart/network shall be prepared by the bidder for purchaser’s approval. The MNW shall
identify milestones of key event for each work/ component in the areas of engineering,
procurement, manufacturer, dispatch, erection and commissioning. It shall indicate
interfaces and inputs required to be given by Purchaser.

1.09.0 Testing and Commissioning


a) The scope includes testing and commissioning of all equipment, subsystems and
systems of the project and putting them into successful commercial operation. The
scope shall include but not limited to the requirements given elsewhere in the
specification.
b) The bidder shall be responsible to provide all necessary testing and commissioning
personnel, tools and plant, testing equipment, etc. All expenses for carrying out the
routine tests as specified in relevant standard shall be to bidder’s account. However the
expenses w.rt. purchaser/purchaser’s representative for witnessing these tests
which bidder shall take into account shall be as follows:-
i) For Inspections/tests to be carried out for equipment offered from within
purchaser’s country.
All tour expenses shall be borne by purchaser.
ii) For inspections/tests to be carried out for equipment offered from outside
purchaser’s country:-

It is envisaged that inspection/testing of all such equipment shall be witnessed. Each


inspection shall be carried out by a team of 3 to 4 engineers nominated by the
purchaser. Their TO & Fro travel expenditure from purchaser’s country to the place of
inspection/testing shall be borne by the bidder. However all boarding and lodging
charges for these engineers shall be borne by the purchaser.

1.10.0 Interface Coordination


The bidder shall identify all interface issues with purchaser and other agencies, and shall
be responsible for such interfacing, coordination and exchange of all necessary
information.

1.11.0 Terminal Points


a) The approach road up to the GIS substation area shall be provided by the Purchaser. All
internal roads (if any) shall have to be constructed by the bidder.
b) Purchaser shall provide assistance to the bidder for obtaining statuary clearances for
providing temporary connections for construction of power and water. The bidder shall
arrange for necessary meters etc. and shall pay applicable energy and water charges as
per applicable rates to the purchaser/any other statutory body.

1.12.0 Arrangements by the bidder

5
Bidder shall make his own necessary arrangements for the following and for those listed
anywhere else in this specification.
a) Construction power supply at all work areas.
b) Construction water.
c) Construction office and store (open and covered)
d) Construction workshop and material/field testing laboratory
e) Boarding & lodging arrangement for their personnel.
f) Fire protection and security arrangements during construction stage.
g) Any other requirements of the Haryana Governemnt and as per the purchaser’s rules,
regulations and practices.

1.13.0 Mandatory Maintenance Equipment


The Bidder shall include in his scope mandatory maintenance equipment as specified.
The prices of these shall be indicated in respective schedules. These would be
considered in bid evaluation.

A List of mandatory maintenance equipment is given at Annexure-II to section. The


Owner reserves the right to buy any or all of these. The Bidder shall furnish the itemized
and total prices for this equipment in the offer.

In Compliance with the requirements of Bid documents, the prices for mandatory
maintenance equipment must be given separately, and shall be used for bid evaluation
purposes. All mandatory maintenance equipment shall be delivered at site.

1.14.0 Commissioning spares


The bidder shall supply spares, which he expects to consume during installation, testing
and commissioning of system. The quantity of these spares shall be decided based on
his previous experience, such that site works shall not be hampered due to non-
availability of these spares. Bidder shall submit a complete list of such spares along with
the bid, the cost of which shall be deemed to have been included in the lumpsum
proposal price of the package. The unused commissioning spares may be left at the site
for use by the purchaser, if so agreed at a cost to be negotiated.

No mandatory or recommended spares will be used during the commissioning of the


equipment/plant before take over by the purchaser.

1.15.0 Recommended spares


1.15.0.1 In addition to the mandatory maintenance equipment, the bidder shall also provide a list
of recommended spares giving unit prices and total prices for 5 years of normal
operation of equipment in the relevant schedule of the BPS. The Purchaser reserves the
right to buy any or all the recommended spares. The recommended spares parts shall
be delivered at the site(s). The list of recommended spares to be furnished by the bidder
should also contain the following:

a) Population of each item installed along with reference drawing number.


b) Service life expectancy of each item.
c) Offer validity period.

1.15.0.2 Price of recommended spares will not be used for evaluation of bids. The price of these
spares will remain valid for a period of not less than 120 days after the date on which the
validity of main bid expires. The prices of any recommended spares shall be subject to
review by the purchaser and shall be finalized after mutual discussions.

1.16.0 Tools & Tackles

6
The Bidder shall also supply at each substation site one set of all special tool and
tackles, etc. which are required by the purchaser’s maintenance staff to maintain the
works successfully at no extra cost. The list of such tools and tackles shall be enclosed
with the offer.

1.17.0 Training of purchaser’s Personnel

(a) Training at Manufacturer’s works:

The successful Bidder shall arrange for training of 2 persons of the employer at the
manufacturer’s works of GIS for 5 working days in Design, manufacture and testing of
GIS being supplied. To and fro air fare including boarding and lodging charges for the
Employer’s Engineer shall be born by the Employer.

(b) Training at Site:

The Successful Bidder shall arrange for training to 5 persons including operating field
staff of Employer for five days at the site in operation and maintenance of GIS. The
charges of training shall include To and fro air fares, Boarding and lodgings, Training
material etc. of the contractor’s personnel.

1.18.0 SCHEDULE OF QUANTITIES

The detailed description of various items/equipment and civil works are indicated at
Annexure – I to VI & Schedule E1. The bill of quantity of major equipment is also
indicated and wherever the quantities are not indicated the bidder is required to compute
the quantity. Bidder is required to indicate unit rate and total price of the items under a
particular head in bid proposal sheets. Bidder should include all such items in the bid
proposal sheets, which may not be specifically mentioned but are essential for the
execution of the contract.

1.19.0 GENERAL ELECTRICAL LAYOUT (GELO)

The GELO for 220 kV Sub-station A-4, Faridabad (up-gradation of 66 kV S/Stn.


A-4 Faridabad to 220 KV Level) is enclosed as indicated at Annexure-IV.

1.20.0 LOCATIONS OF THE SUBSTATION

The location of the substations is in Faridabad at A-4, Faridabad.

1.21.0 METEOROLOGICAL DATA.

The meteorological data of the substation is indicated at Annexure-III. However, for


design purpose, ambient temperature should be considered as 50° C.

1.22.0 SOIL DATA


The earth resistivity for 220 kV Substation A-4, Faridabad shall be ascertained by the
bidder himself.

1.23.0 DRAWING

1. The bidder shall maintain inter equipment distances, bay length, bay width etc in
accordance with the enclosed general/electrical layouts of the respective substations

7
while doing so the bidder will ensure that the statutory electrical clearances required for
substation are maintained. (Annexure-IV)
2. The drawing enclosed give the basic scheme, layout of substation, substation buildings,
associated service etc. In case of any discrepancy between the drawing and text of
specification the bidder is advised to get these clarified before submission of bid. No
claim what-so-ever on this score shall be entertained after award of contract.
3. The bidder shall adopt PURCHASER design of galvanized steel structure for tower,
beam and equipment supporting structures for 220/66 kV S/Stn(s).

The PLCC equipments will be in the scope of the bidder for all the S/Stn. (Both ends)
including supply, Erection and commissioning.
Notes:
1. The bidder or his authorised representative should visit the site of works and its
surroundings to obtain himself at his responsibility and expenses, all information
regarding general site characteristics, accessibility, infrastructure details and
factual position in respect of scope of work viz-a-viz GELO drg. attached with the
bid document. Any alteration/addition envisage in the document must be got
clarified before submission of the bid.

2. No extra payment shall be made on account of any change in the layout drgs.
required for providing DSLP as per Rezvik method.

3. In addition to switch-yard lighting (as per Section-7) of Vol-II the successful


bidder is required to provide fluorescent tube fitting (2x4 feet) along the periphery
of fencing at a interval of 30 meters.

8
ANNEXURE-I

EQUIPMENT/ MATERIALS TO BE SUPPLIED AND ERECTED FOR 220 KV GIS


SUB-STATION AT A-4, FARIDABAD

MAIN EQUIPMENT

1.0 220 kV GIS

220 kV GIS with 8 (including one spare T/F bay & 2 No. spare line bays) bays and associated
local control panels, control cables all consumables and hardware etc. as per enclosed GELO
Drawing and as per the technical specification.

Sr.No. Description Unit Qty.


1. 245 kV, 3150A, 40 kA for 1 sec, SF6 gas insulated set 2
transformer feeder bay module each comprising of SF6
gas insulated circuit breaker, current transformer, bus-bar
disconnectors with common grounding switch,
disconnectors with safety grounding switch(es), local
control cubicle, SF6 gas monitoring system for complete
bay, gas insulated terminal connection for connecting
transformer bushing with GIS module through XLPE cable
with termination kit and accessories etc. to complete
Transformer Bay Module with following main equipment
for each bay:-
1. 245 KV Circuit Breaker (Single Phase) - 3
2. 245 KV Isolator (motor operated) - 6
with earth switch(single phase)
3. High speed motor operated - 3
earth switch (single phase)
4. CT (Single Phase) - 3
(300-150/0.577-1-1-1-1A)
2. 245 kV, 3150A, 40 kA for 1 sec, SF6 gas insulated Line set 2
feeder bay module each comprising of SF6 gas insulated
circuit breaker, current transformer, bus-bar disconnectors
with common grounding switch, disconnectors with safety
grounding switch(es), high speed fault making grounding
switch, local control cubicle, SF6 gas monitoring system
for complete bay, gas insulated terminal connection for
connecting Overhead line (Air) with GIS module through
XLPE cable with termination kit and accessories etc. to
complete Feeder Bay Module with following main
equipment for each bay:-
1. 245 KV Circuit Breaker (Single Phase)- 3
2. 245 KV Isolator (motor operated) - 9
with earth switch(single phase)
3. High speed motor operated - 3
earth switch (single phase)
4. CT (Single Phase) - 3
(1200-800-400/1-1-1-1-1A)

9
Sr.No. Description Unit Qty.
3. 245 kV, 40 kA for 1 sec, 3 single phase (isolated), SF6 gas set 2
insulated, metal enclosed 3150A bus bars each enclosed
in bus enclosures running along the length of the
switchgear to interconnect each of circuit breaker bay
module. Each bus bar set shall be complete with voltage
transformer, disconnectors, bus bar grounding switch, SF6
gas monitoring system for the complete bus etc with
following main equipment for each bay:-
1. High speed motor operated - 3
earth switch (single phase)
2. Inductive Bus PTs (Single Phase) - 3

4. 245 kV, 3150A, 40 kA for 1 sec, SF6 gas insulated Bus set 1
Coupler Bay Module comprising of SF6 gas insulated
circuit breaker, current transformer, disconnectors
switches, disconnector with safety grounding switch(es).
Local control cubicle, SF-6 gas monitoring system for the
complete bay etc with following main equipment for each
bay:-
1. 245 KV Circuit Breaker (Single Phase) - 3
2. 245 KV Isolator (motor operated) - 6
with earth switch(single phase)
3. CT (Single Phase) - 3
(1200-800-400/1-1-1-1-1A)

10
ANNEXURE-II
METEOROLOGICAL DATA

Equipment to be supplied against this specification shall be suitable for satisfactory continuous
operation under the following tropical conditions:

i) Location In the state of Haryana

ii) Max. Ambient air temp. (deg. C) 50

iii) Min ambient air temp. (deg. C) -2.5

iv) Daily average air temp. (deg. C) 35

v) Average no. of Thunder storm 45


days per Annum

vi) Maximum Relative Humidity (%) 100

vii) Minimum Relative Humidity (%) 26

viii) Average annual rain fall (mm) 900

ix) Max. wind pressure (kg/sq m) 195

x) Max. altitude above mean sea 1000


level (meters)
xi) Isoceraunic level (days/year) 45

xii) Seismic level 0.3 g


(horizontal acceleration)

xiii) Average no. of rainy days 120


per Annum

NOTE: Moderately hot and humid tropical climate conductive to rust and fungus growth. The
climate conditions are also prone to wide variations in ambient condition. Smoke is also
present in the atmosphere. Heavy lightening also occurs during June to October.

11
ANNEXURE-III

Sr. NAME OF SUB STATION SINGLE LINE LAYOUT DRG.


No. DIAGRAM NO. NO.

1. 220 kV GIS S/Stn.A-4, Faridabad HGD-1/3158 HGD-1/3158

12
MODEL TECHNICAL SPECIFICATION
SEC-2 GTR
(GENERAL TECHNICAL REQUIREMENT)
SECTION-2 GTR (GENERAL TECHNICAL REQUIREMENTS)

CLAUSE NO. PARTICULARS PAGE NO.

1.0 Foreword 1
2.0 General Requirement 1
3.0 Standards 2
4.0 Services to be performed by the 2
Equipment being furnished
5.0 Engineering Data and Drawings 11
6.0 Material/Workmanship 14
7.0 Design Improvements/Coordination 18
8.0 Quality Assurance Programme 19
9.0 Type Testing, Inspection & 20
Inspection Certificate
10.0 Tests 23
11.0 Packaging & Protection 23
12.0 Finishing of Metal Surfaces 24
13.0 Handling, Storing & Installation 26
14.0 Tools and Tackles 28
15.0 Auxiliary Supply 28
16.0 Support Structure 29
17.0 Clamps and Connectors including 30
Terminal Connectors
18.0 Control Cabinets, Junction Boxes, Terminal 32
Boxes & Marshalling Boxes for Outdoor Equipment
19.0 Auxiliary Switches 33
20.0 Terminal Blocks and Wiring 34
21.0 Lamps and Sockets 35
CLAUSE NO. PARTICULARS PAGE NO.

22.0 Bushings, Hollow Column Insulators, 36


Support Insulators
23.0 Motors 37
24.0 Technical Requirement of Equipments 39
Annexure-A Corona and Radio Interference Voltage 47
(RIV) Test
Annexure-B List of Specifications 50
SEC-GTR (GENERAL TECHNICAL REQUIREMENTS)

1.0 FOREWORD
1.1 The provisions under this section are intended to supplement general
requirements for the materials, equipments and services covered
under other sections of Bid documents and is not exclusive.
However in case of conflict between the requirements specified in this
section and requirements specified under other sections, the
requirements specified under respective sections shall prevail.
2.0 GENERAL REQUIREMENT
2.1 The bidders shall submit the technical requirements, data and
information as per the technical data sheets provided in the Volume II
of bid documents.
2.2 The bidders shall furnish catalogues, engineering data, technical
information, design documents, drawings etc.
2.3 It is recognised that the bidders may have standardised on the use
of certain components, materials, processes or procedures different
from those specified herein. Alternate proposals offering similar
equipment based on the manufacturer’s standard practice will also be
considered provided such proposals meet the specified designs,
standard and performance requirements and are acceptable to the
HVPNL.
2.4 Except for lighting fixtures, wherever a material or article is specified
or defined by the name of a particular brand, Manufacturer or Vendor,
the specific name mentioned shall be understood as establishing type,
function and quality and not as limiting competition. For lighting
fixtures , makes shall be as defined in Section- Lighting System.
2.5 Equipment furnished shall be complete in every respect with all
mountings, fittings, fixtures and standard accessories normally
provided with such equipment and/or needed for erection, completion
and safe operation of the equipment as required by applicable codes
though they may not have been specifically detailed in the Technical
Specifications unless included in the list of exclusions. Materials and
components not specifically stated in the specification but which are

Page - 1
necessary for commissioning and satisfactory operation of the
switchyard/substation unless specifically excluded shall be deemed to
be included in the scope of the specification and shall be supplied
without any extra cost. All similar standard components/parts of
similar standard equipment provided, shall be inter-changeable with
one another.
3.0 STANDARDS
3.1 The works covered by the specification shall be designed, engineered,
manufactured, built, tested and commissioned in accordance with the
Acts, Rules, Laws and Regulations of India.
3.2 The equipment to be furnished under this specification shall conform
to latest issue with all amendments (as on the date of bid opening) of
standard specified under Annexure -B of this section, unless
specifically mentioned in the specification.
3.3 The Bidder shall note that standards mentioned in the specification
are not mutually exclusive or complete in themselves, but intended to
compliment each other.
3.4 The Bidder shall also note that list of standards presented in this
specification is not complete. Whenever necessary the list of
standards shall be considered in conjunction with specific IS/IEC.
3.5 When the specific requirements stipulated in the specifications exceed
or differ than those required by the applicable standards, the
stipulation of the specification shall take precedence.
3.6 Other internationally accepted standards which ensure equivalent or
better performance than that specified in the standards specified
under Annexure B / individual sections for various equipments shall
also, be accepted, however the salient points of difference shall be
clearly brought out in additional information schedule of Vol III along
with English language version of such standard. The equipment
conforming to standards other than specified under Annexure-B /
individual sections for various equipments shall be subject to
HVPNL’s approval.
3.7 The bidder shall clearly indicate in his bid the specific standards in
accordance with which the works will be carried out.
4.0 SERVICES TO BE PERFORMED BY THE EQUIPMENT BEING
FURNISHED
4.1 The lighting impulse voltage shall be 1050kVp.
4.2 All equipments shall also perform satisfactorily under various other
electrical, electromechanical and meteorological conditions of the site
of installation.
Page 2
4.3 All equipment shall be able to withstand all external and internal
mechanical, thermal and electromechanical forces due to various
factors like wind load, temperature variation, ice & snow, (wherever
applicable) short circuit etc for the equipment.
4.4 The bidder shall design terminal connectors of the equipment taking
into account various forces that are required to withstand.
4.5 The equipment shall also comply to the following:
a) All outdoor EHV equipments except marshalling kiosks shall be
suitable for hot line washing.
b) To facilitate erection of equipment, all items to be assembled at
site shall be “match marked”.
c) All piping, if any between equipment control cabinet/ operating
mechanism to marshalling box of the equipment, shall bear
proper identification to facilitate the connection at site.
4.6 Operating times of circuit breakers, protective relays and PLCC
equipment have been specified in respective sections.
4.7 EHV equipments and system shall be designed to meet the following
major technical parameters as brought out hereunder.
4.7.1 System Parameter

S.NO Description of 220 kV 66 kV 11 kV


parameters System System System

1. System operating 220kV 66kV 11kV


voltage

3. Rated frequency 50Hz 50Hz 50Hz

4. No. of phase 3 3 3

Page - 3
S.NO Description of 220 kV 66 kV 11 kV
parameters System System System
5. Rated Insulation
levels
i) Full wave impulse 1050kVp 325kVp 75kVp
withstand
voltage(1.2/50
micro sec.)

ii) Switching impulse - - -


withstandvoltage
(250/2500micro
sec.) dry and wet

Iii) One minute power 460kV 140kV 28kV


frequency dry and
wet withstand
voltage (rms)

6. Corona extinction 156kV - -


voltage

7. Max. radio 1000 500 -


interference micro- micro-
voltage for volt volt
frequency
between 0.5 MHz
and 2 MHz
156kV rms for
220kV system &
92 kV rms for
132kV system

8. Minimum 25 mm/kV 25 mm/kV 25 mm/kV


creepage distance (6125 (1813 (300
mm) mm) mm)

Page - 4
9.Min. clearances
S.NO Description of 220 kV 66 kV 11 kV
parameters System System System
i) Phase to phase (for 2100 mm 800 mm
Rod -
conductor
configuration)
and
(for
conductor
conductor
configuration)
ii) Phase to earth 2100 mm 800mm
iii) Sectional 5000 mm 3000 mm
clearances
10. Rated short circuit 40 kA 31.5 kA 25 kA
current for 1 sec.
duration

11. System neutral Effectively Effectively Effectively


earthing earthed earthed earthed

4.7.2 Major Technical Parameters

The major technical parameters of the equipments are given


below. For other parameters and features respective technical
sections should be referred.
(A) 100MVA 220/66KV Power Transformer
Maximum Continuous Capacity(MVA) ONAN ONAF OFAF
50 75 100
Rated Voltage HV LV
220KV 66KV
Percentage Impedance 12.5% at 100MVA Base
Vector Group YYO
Page 5
Insulation level HV LV Neutral
Lightning Impulse withstand voltage 950KV 325KV 170KV
Power Frequency withstand voltage 395KV 140KV 70KV

Page 6
(A) For 245 kV & 72.5 kV Circuit Breaker and Isolator
Rated voltage kV (rms) 245 72.5

Rated frequency (Hz) 50 50

No. of Poles 3 3

Design ambinet 50 50
temperature (°C)
Rated insulation levels :
1) Full wave impulse withstand voltage (1.2/50 micro sec.)

- between line ± 1050 kVp ±325 kVp


terminals and ground

- between terminals ± 1050 kVp ±325 kVp


with circuit breaker open

- between terminals ± 1200 kVp ±375 kVp


with isolator open

2) One minute power frequency dry and wet withstand voltage


- between line 460 kV (rms) 140 kV (rms)
terminals and ground

Page - 7
- between terminals 460 kV (rms) 140 kV (rms)
with circuit breaker open
- between terminals 530 kV (rms) 160kV (rms)
with Isolator open
Max. radio interference 1000 500
voltage (microvolts) for (at 156 kV (at 92 kV
frequency between 0.5 MHz rms) rms)
and 2 MHz in all positions of
the equipments.

Minimum creepage distance :-


Phase to ground (mm) 6125 1813
Between CB Terminals (mm) 6125 1813
System neutral earthing Effectively Effectively
earthed earthed
Seismic acceleration - 0.3g horizontal -
Rating of Auxiliary - 10 A at 220 V DC -
Contacts
Breaking capacity of 2 A DC with circuit time
Auxiliary Contacts constant of not less than 20 ms.
Phase to phase spacing (mm) 4000 (min.) 2000

Auxiliary Switch shall also Comply with other clauses of this chapter.

(B) FOR 245 kV & 72.5 kV CT/CVT/SA

Rated voltage kV (rms) 245 72.5


Rated frequency (Hz) 50 50
No. of poles 1 1

Page - 8
Design ambient temperature (°C) 50 50
Rated insulation levels :

1) Full wave impulse withstand voltage (1.2/50 micro sec.)


- between line terminals ± 1050 kVp ±325 kVp
and ground for CT and CVT
- for arrester housing ± 1050 kV peak ±325 kVp

2) One minute power frequency dry and wet withstand voltage


- between line terminals 460 kV rms 140 kV rms
and ground for CT and CVT

- for arrester housing

460 kV rms 140kV rms


Max. radio interference
1000 for CT/CVT 500
voltage (microvolts) for
500 for SA
frequency between 0.5 MHz
(at 156 kV (at 92 kV
and 2 MHz in all positions
rms) rms)
of the equipment.
Minimum creepage distance :-
Phase to ground (mm)
6125 1813
System neutral earthing
- Effectively earthed -
Seismic acceleration
- 0.3g horizontal -
Partial discharge for :-
- Surge arrester at
1.05 COV - Not exceeding 50 pc. -
- for CT/CVT
- Not exceeding 10 pc. –

(C) For 72.5 kV ISOLATOR


Rated Voltage kV (rms) 72.5

Rated frequency (Hz) 50

No. of Poles 3

Design ambinet 50
temperature (°C)
Rated insulation levels :
Page 9
P
1) Full wave impulse withstand voltage (1.2/50 micro sec.)
- between line ± 325 kVp
terminals and ground
- between terminals ± 375 kVp
with Isolator open
2) One minute power frequency dry and wet withstand
voltage
- between line 140 kV (rms)
terminals and ground
- between terminals 160 kV (rms)
with Isolator open
Minimum creepage distance :-
Phase to ground (mm) 1813
Seismic acceleration 0.3g horizontal.

Rating of Auxiliary Contacts 10 A at 220 V DC


Breaking capacity of 2 A DC with circuit
Auxiliary Contacts time constant of
not less than 20 ms.
Phase to phase spacing (mm) 2000
Auxiliary Switch shall also Comply with other clauses of this chapter.
(D) Technical Parameters of Bushings/Hollow Column
insulators/support insulators :
For For For

220 kV 66 kV 11 kV
System System System
(a) Rated Voltage (kV) 245 72.5 12

Page-10
(b) Impulse withstand ±1050 ±325 ±170
voltage(Dry& Wet) (kVp)
(c) Switching surge - - -
Withstandvoltage
(dry and wet) (kVp)
(d) Power frequency 460 140 70
withstand voltage
(dry and wet) (kV rms)

(e) Total creepage 6125 1813 900


distance (mm)
(f) Pollution Class-III Heavy (as per IEC 71) and as specified in
Section-2 for all class of equipment.
(g) Insulator shall also meet requirement of and IEC-815 for 220 kV
system, as applicable having alternate long & short
sheds.
5.0 ENGINEERING DATA AND DRAWINGS
5.1 The engineering data shall be furnished by the Bidder in
accordance with the Schedule for each set of equipment as specified
in the Bid Document.
5.2 The list of drawings/documents which are to be submitted to the
HVPNL as detailed below/in individual sections.
The Bidder shall necessarily submit all the drawings/ documents
unless anything is waived.
The Bidder shall submit 4 (four) sets of drawings/ design
documents /data/ test reports as may be required for the approval of
the HVPNL.
5.3 Drawings
5.3.1 All drawings submitted by the Bidder including those submitted at
the time of bid shall be in sufficient detail to indicate the type, size,
arrangement, material description, Bill of Materials, weight of each
component, break-up for packing and shipment, dimensions, internal &
the external connections, fixing arrangement required and any other
information specifically requested in the specifications.
5.3.2 Each drawing submitted by the Bidder shall be clearly marked with
the name of the HVPNL, the unit designation, the specifications
title, the specification number and the name of the Project. If
standard catalogue pages are submitted, the applicable items shall be
indicated therein. All titles, noting, markings and writings on the
drawing shall be in English. All the dimensions should be in metric
units.
Page-11
5.3.3 Further work by the Bidder shall be in strict accordance with these
drawings and no deviation shall be permitted without the written
approval of the HVPNL, if so required.
5.4 The review of these data by the HVPNL will cover only general
conformance of the data to the specifications and documents,
interfaces with the equipment provided under the specifications,
external connections and of the dimensions which might affect
substation layout. This review by the HVPNL may not indicate a
thorough review of all dimensions, quantities and details of the
equipment, materials, any devices or items indicated or the accuracy
of the information submitted. This review and/or approval by the
HVPNL shall not be considered by the Bidder, as limiting any of
his responsibilities and liabilities for mistakes and deviations from the
requirements, specified under these specifications and documents.
5.5 All manufacturing and fabrication work in connection with the
equipment prior to the approval of the drawings shall be at the
Bidder’s risk. The Bidder may make any changes in the
design which are necessary to make the equipment conform to the
provisions and intent of the Contract and such changes will again be
subject to approval by the HVPNL. Approval of Bidder’s
drawing or work by the HVPNL shall not relieve the Bidder of
any of his responsibilities and liabilities under the Contract.
5.6 All engineering data submitted by the Bidder after final process
including review and approval by the HVPNL shall form part of the
Contract Document and the entire works performed under these
specifications shall be performed in strict conformity, unless
otherwise expressly requested by the HVPNL in Writing.
5.7 Approval Procedure
The successful bidder shall submit 4 sets of drawings as detailed in
relevant specifications complete in all respects for approval to HVPNL as
per schedule given in bar-chart. The following schedule shall be
followed generally for approval and for providing final
documentation.

i) Approval/comments/ within 4 weeks of receipt of


by HVPNL on initial drawings by HVPNL.
submission
ii) Resubmission Within 3 (three) weeks
(where ever from date of comments
required) including both ways postal
time).
iii) Approval or comments Within 3 weeks of receipt
of resubmission.
iv) Furnishing of final sets of Before commissioning of S/Stn.
drawings (10 copies for each item
per sub-station)
Page-12
v) Furnishing of instruction & Before commissioning of S/Stn.
operation manual (10
copies for each item per
sub-station)

vi) Furnishing of CD-ROM of final Before commissioning of S/Stn.


Drawings (2 Nos. for each item
Per sub-station)

vii) Furnishing of CD-ROM of Instruction Before commissioning of S/Stn.


Manual & operation (2 Nos. for each item per
Sub-station)

(viii) Furnishing of CD-ROM of Automation Before commissioning of S/Stn.


Software(2 Nos. for each sub-station)

(ix) Furnishing of CD-ROM of Application


software for numerical relays (2 Before commissioning of S/Stn.
Nos. for each sub-station)

Page-13
NOTE :

(1) The Bidder may please note that all resubmissions must
incorporate all comments given in the earlier submission by the
HVPNL or adequate justification for not incorporating the
same must be submitted failing which the submission of
documents is likely to be returned.
(2) The drawings which are required to be referred frequently during
execution should be submitted on cloth lined paper. The list of
such drawings shall be intimated to the Bidder at the time
of approval of drawings.
(3) All major drawings should be submitted in Auto Cad.

(4) The instruction Manuals shall contain full details of drawings of


all equipment being supplied under this contract, their exploded
diagrams with complete instructions for storage, handling,
erection, commissioning, testing, operation, trouble shooting,
servicing and overhauling procedures.
(5) If after the commissioning and initial operation of the substation,
the instruction manuals require any modifications/
additions/changes, the same shall be incorporated and the
updated final instruction manuals shall be submitted by the
Bidder to the HVPNL.
(6) The Bidder shall furnish to the HVPNL catalogues of spare
parts.
5.8 List of drawings other than equipment drawings (detailed in relevant
specifications) to be submitted for approval shall be as under:-
1) Earthmat design and layout
2) Switchyard structural layout and section (for reference and record of
HVPNL).
3) DSLP Calculation and drawings (for reference and record of HVPNL).
4) Earth Resistivity measurement report (for reference & record of HVPNL).
5) Wiring diagram & cable schedule of each bay.
6) Trench Layout drawing.
6.0 MATERIAL/ WORKMANSHIP
6.1 General Requirement
6.1.1 Where the specification does not contain references to workmanship,
equipment, materials and components of the covered equipment, it is
essential that the same must be new, of highest grade of the best
quality of their kind, conforming to best engineering practice and
suitable for the purpose for which they are intended.
Page-14
6.1.2 Incase where the equipment, materials or components are indicated in
the specification as “similar” to any special standard, the HVPNL
shall decide upon the question of similarity. When required by the
specification or when required by the HVPNL the Bidder shall
submit, for approval, all the information concerning the materials or
components to be used in manufacture. Machinery, equipment,
materials and components supplied, installed or used without such
approval shall run the risk of subsequent rejection, it being
understood that the cost as well as the time delay associated with the
rejection shall be borne by the Bidder.

6.1.3 The design of the Works shall be such that installation, future
expansions, replacements and general maintenance may be
undertaken with a minimum of time and expenses. Each component
shall be designed to be consistent with its duty and suitable factors of
safety, subject to mutual agreements. All joints and fastenings shall
be devised, constructed and documented so that the component parts
shall be accurately positioned and restrained to fulfill their required
function. In general, screw threads shall be standard metric threads.
The use of other thread forms will only be permitted when prior
approval has been obtained from the HVPNL.
6.1.4 Whenever possible, all similar part of the Works shall be made to
gauge and shall also be made interchangeable with similar parts. All
spare parts shall also be interchangeable and shall be made of the
same materials and workmanship as the corresponding parts of the
Equipment supplied under the Specification. Where feasible, common
component units shall be employed in different pieces of equipment in
order to minimize spare parts stocking requirements. All equipment of
the same type and rating shall be physically and electrically
interchangeable.
6.1.5 All materials and equipment shall be installed in strict accordance with
the manufacturer’s recommendation(s). Only first-class work in
accordance with the best modern practices will be accepted.
Installation shall be considered as being the erection of equipment at
its permanent location. This, unless otherwise specified, shall include
unpacking, cleaning and lifting into position, grouting, levelling,

Page-15
aligning, coupling of or bolting down to previously installed equipment
bases/foundations, performing the alignment check and final
adjustment prior to initial operation, testing and commissioning in
accordance with the manufacturer’s tolerances, instructions and the
Specification. All factory assembled rotating machinery shall be
checked for alignment and adjustments made as necessary to re-
establish the manufacturer’s limits suitable guards shall be provided for
the protection of personnel on all exposed rotating and / or moving
machine parts and shall be designed for easy installation and
removal for maintenance purposes. The spare equipment(s) shall be
installed at designated locations and tested for healthiness.
6.1.6 The Bidder shall apply oil and grease of the proper specification to
suit the machinery, as is necessary for the installation of the
equipment. Lubricants used for installation purposes shall be drained
out and the system flushed through where necessary for applying the
lubricant required for operation. The Bidder shall apply all
operational lubricants to the equipment installed by him.
6.1.7 All oil, grease and other used in the Works/ Equipment
shall be purchased in India unless the Bidder has any special
requirement for the specific application of a type of oil or grease not
available in India.
6.1.8 A cast iron or welded steel base plate shall be provided for all rotating
equipment which are to be installed on a concrete base unless
otherwise agreed to by the HVPNL. Each base plate shall support
the unit and its drive assembly, shall be of design with pads for
anchoring the units, shall have a raised up all around and shall have
threaded in air connections, if so required.
6.1.9 Corona and radio interference voltage test for equipments shall be in
line with the procedure given at
Annexure-A.
6.2 Provisions For Exposure to Hot and Humid climate
Outdoor equipment supplied under the specification shall be suitable for
service and storage under tropical conditions of high temperature, high
humidity, heavy rainfall and environment favourable to the growth
of fungi and mildew. The indoor equipments located in
nonairconditioned areas shall also be of same type.

Page-16
6.2.1 Space Heaters

6.2.1.1 The heaters shall be suitable for continuous operation at 240 V as


supply voltage. On-off switch and fuse shall be provided.
6.2.1.2 One or more adequately rated thermostatically connected heaters
shall be supplied to prevent condensation in any compartment. The
heaters shall be installed in the compartment and electrical
connections shall be made sufficiently away from below the heaters to
minimize deterioration of supply wire insulation. The heaters shall be
suitable to maintain the compartment temperature to prevent
condensation.
6.2.1.3 Suitable anti condensation heaters with the provision of thermostat
shall be provided.
6.2.2 FUNGI STATIC VARNISH
Besides the space heaters, special moisture and fungus resistant
varnish shall be applied on parts which may be subjected or
predisposed to the formation of fungi due to the presence or deposit of
nutrient substances. The varnish shall not be applied to any
surface of part where the treatment will interfere with the operation or
performance of the equipment. Such surfaces or parts shall be
protected against the application of the varnish.
6.2.3 Ventilation opening
Wherever ventilation is provided, the compartments shall have
ventilation openings with fine wire mesh of brass to prevent the entry of
insects and to reduce to a minimum the entry of dirt and dust.
Outdoor compartment openings shall be provided with shutter type
blinds and suitable provision shall be made so as to avoid any
communication of air / dust with any part in the enclosures of the
Control Cabinets, Junction boxes and Marshalling Boxes, panels etc.
Page-17
6.2.4 Degree of Protection
The enclosures of the Control Cabinets, Junction boxes and
Marshalling Boxes, panels etc. to be installed shall provide degree of
protection as detailed here under:
a) Installed out door: IP- 55
b) Installed indoor in air conditioned area: IP-31 c)
Installed in covered area: IP-52
d) Installed indoor in non air conditioned area where possibility of
entry of water is limited: IP-41.
e) For LT Switchgear (AC & DC distribution Boards) : IP-52
The degree of protection shall be in accordance with IS:13947 (Part-I)
/ IEC-947 (Part-I) / IS 12063 / IEC 529. Type test report for degree
of protection test, on each type of the box shall be submitted for
approval.
6.3 RATING PLATES, NAME PLATES AND LABELS
6.3.1 Each main and auxiliary item of substation is to have permanently
attached to it in a conspicuous position a rating plate of non-corrosive
material upon which is to be engraved HVPNL PO No., manufacturer’s
name, year of manufacture, equipment name, type or serial number
together with details of the loading conditions under which the item of
substation in question has been designed to operate, and such diagram
plates as may be required by the HVPNL. The rating plate of each
equipment shall be according to IEC requirement.
6.3.2 All such nameplates, instruction plates, rating plates of transformers,
reactors, CB, CT, CVT, SA, Isolators, C & R panels and PLCC
equipments shall be bilingual with Hindi inscription first followed by
English. Alternatively two separate plates one with Hindi and the
other with English inscriptions may be provided.
6.4 FIRST FILL OF CONSUMABLES, OIL AND LUBRICANTS
All the first fill of consumables such as oils, lubricants, filling
compounds, touch up paints, soldering/brazing material for all copper
piping of circuit breakers and essential chemicals etc. which will be
required to put the equipment covered under the scope of the
specifications, into successful Operation, shall be furnished by the
Bidder unless specifically excluded under the exclusions in these
specifications and documents.
7.0 DESIGN IMPROVEMENTS / COORDINATION
7.1 The bidder shall note that the equipment offered by him in the bid
only shall be accepted for supply. However, the HVPNL or the
Bidder may propose changes in the specification of the equipment or
quality thereof and if the HVPNL & Bidder agree upon any
such changes, the specification shall be modified accordingly.
Page-18
7.2 If any such agreed upon change is such that it affects the price and
schedule of completion, the parties shall agree in writing as to the
extent of any change in the price and/or schedule of completion
before the Bidder proceeds with the change. Following such
agreement, the provision thereof, shall be deemed to have been
amended accordingly.
7.3 The Bidder shall be responsible for the selection and design of
appropriate equipments to provide the best co-ordinated performance
of the entire system. The basic design requirements are detailed out
in this Specification. The design of various components, subassemblies
and assemblies shall be so done that it facilitates easy field assembly andmaintenance.
7.4 The Bidder has to coordinate designs and terminations with the
agencies (if any) who are Consultants/Bidder for the HVPNL.
The names of agencies shall be intimated to the successful bidders.
7.5 The Bidder will be called upon to attend design co-ordination
meetings with the Engineer, other Bidder’s and the Consultants of
the HVPNL (if any) during the period of Contract. The Bidder
shall attend such meetings at his own cost at Panchkula or at mutually
agreed venue as and when required and fully cooperate with such
persons and agencies involved during those discussions.
8.0 QUALITY ASSURANCE PROGRAMME
8.1 To ensure that the equipment and services under the scope of this
Contract whether manufactured or performed within the Bidder’s Works
or at his Sub-Bidder’s premises or at the HVPNL’s site or at any other
place of Work are in accordance with the specifications, the Bidder shall
adopt suitable quality assurance programme to control such activities at
all points necessary. Such programme shall be broadly outlined by the
Bidder and finalised after discussions before the award of contract.
The detailed programme shall be submitted by the Bidder after the
award of contract and finally accepted by HVPNL after discussion.
However, in case detailed valid programme approved by HVPNL for the
equipment already exist, same would be followed till its validity. A
quality assurance programme of the Bidder shall generally cover the
following:
(a) His organisation structure for the management and
implementation of the proposed quality assurance programme :
(b) Documentation control system;
(c) Qualification data for bidder’s key personnel;
(d) The procedure for purchases of materials, parts components and
selection of sub-Bidder’s services including vendor analysis,
source inspection, incoming raw material inspection, verification
of material purchases etc.
(e) System for shop manufacturing and site erection controls
including process controls and fabrication and assembly control;
Page-19
(f) Control of non-conforming items and system for corrective
actions;
(g) Inspection and test procedure both for manufacture and field
activities.

(h) Control of calibration and testing of measuring instruments and


field activities;
(i) System for indication and appraisal of inspection status;
(j) System for quality audits;
(k) System for authorising release of manufactured product to the
Purcahser.
(l) System for maintenance of records;
(m) System for handling storage and delivery; and
(n) A quality plan detailing out the specific quality control measures
and procedures adopted for controlling the quality characteristics
relevant to each item of equipment furnished and/or services
rendered.
The HVPNL or his duly authorised representative reserves the right to
carry out quality audit and quality surveillance of the system and
procedure of the Bidder/his vendor’s quality management and control
activities.
8.2 Quality Assurance Documents
The Bidder would be required to submit all the Quality Assurance
Documents as stipulated in the Quality Plan at the time of HVPNL’s
inspection of equipment/material

9.0 TYPE TESTING, INSPECTION, TESTING & INSPECTION


CERTIFICATE
9.1 All equipment being supplied shall conform to type tests including
additional type tests as per technical specification and shall be subject
to routine tests in accordance with requirements stipulated under
respective sections. HVPNL reserves the right to witness any or all
the type tests. The Bidder shall intimate the HVPNL the
detailed program about the tests atleast three (3) weeks in advance in
case of domestic supplies & six (6) weeks in advance in case of
foreign supplies.
9.2 The reports for all type tests and additional type tests as per technical
specification shall be furnished by the Bidder alongwith equipment
/ material drawings. The type tests conducted earlier should have
either been conducted in accredited laboratory (accredited based on
ISO / IEC Guide 25 / 17025 or EN 45001 by the national accredition
body of the country where laboratory is located ) or witnessed by the
representative(s) of HVPNL or Utility. The test reports
submitted shall be of the tests conducted within last 7 (Seven) years
Page-20
prior to the date of bid opening. In case the test reports are of the
test conducted earlier than 7 (Seven) years prior to the date of bid
opening, the Bidder shall repeat these test(s) at no extra cost to the
HVPNL.
In the event of any discrepancy in the test reports i.e. any test report
not acceptable due to any design / manufacturing changes (including
substitution of components) or due to non-compliance with the
requirement stipulated in the Technical Specification or any/all
additional type tests not carried out, same shall be carried out without
any additional cost implication to the HVPNL.
9.3 The HVPNL intends to repeat the type tests and additional type
tests on transformers for which test charges shall be payable as per
provision of contract. The price of conducting type tests and additional
type tests shall be included in Bid price and break up of these shall be
given in the relevant schedule of Bid Proposal Sheets. These Type test
charges would be considered in bid evaluation. In case Bidder does not
indicate charges for any of the type tests or does not mention the name
of any test in the price schedules, it will be presumed that the
particular test has been offered free of charge. Further, in case any
Bidder indicates that he shall not carry out a particular test, his offer
shall be considered incomplete and shall be liable to be rejected.
For outdoor receptacles, trefoil clamps, diesel engine, alternator,
motors, cable glands and junction boxes, type testing and type test
reports as per relevant standard shall be submitted for HVPNL’s
approval.
9.4 The HVPNL, his duly authorized representative and/or outside
inspection agency acting on behalf of the HVPNL shall have at all
reasonable times free access to the Bidder’s/sub-vendors
premises or Works and shall have the power at all reasonable times to
inspect and examine the materials and workmanship of the Works
during its manufacture or erection if part of the Works is being
manufactured or assembled at other premises or works, the
Bidder shall obtain for the Engineer and for his duly authorized
representative permission to inspect as if the works were
manufactured or assembled on the Bidder’s own premises or
works. Inspection may be made at any stage of manufacture,
despatch or at site at the option of the HVPNL and the equipment
if found unsatisfactory due to bad workmanship or quality, material is
liable to be rejected.
Page - 21
9.5 The Bidder shall give the HVPNL /Inspector thirty (30) days
written notice of any material being ready for joint testing including
Bidder and HVPNL. Such tests shall be to the Bidder’s
account except for the expenses of the Inspector. The HVPNL
/inspector, unless witnessing of the tests is virtually waived, will
attend such tests within thirty (30) days of the date of which the
equipment is notified as being ready for test/inspection.
9.6 The HVPNL or Inspector shall, within fifteen (15) days from the
date of inspection as defined herein give notice in writing to the
Bidder, of any objection to any drawings and all or any equipment
and workmanship which in his opinion is not in accordance with the
Contract. The Bidder shall give due consideration to such
objections and shall either make the modifications that may be
necessary to meet the said objections or shall confirm in writing to
the HVPNL /Inspector giving reasons therein, that no modifications
are necessary to comply with the Contract.
9.7 When the factory tests have been completed at the Bidder’s or
Sub-Bidder’s works, the HVPNL/inspector shall issue a
certificate to this effect within fifteen (15) days after completion of
tests but if the tests are not witnessed by the HVPNL /Inspector,
the certificate shall be issued within fifteen (15) days of receipt of the
Bidder’s Test certificate by the HVPNL/Inspector. The completion of
these tests or the issue of the certificate shall not bind the HVPNL to
accept the equipment should, it, on further tests after erection, be
found not to comply with the Contract. The equipment shall be
dispatched to site only after approval of test reports and issuance of
Despatch Instruction by the HVPNL .
9.8 In all cases where the Contract provides for tests whether at the
premises or at the works of the Bidder or of any Sub-Bidder,
the Bidder except where otherwise specified shall provide free of
charge such items as labour, materials, electricity, fuel, water, stores,
apparatus and instruments as may be reasonably demanded by the
HVPNL /Inspector or his authorized representative to carry out
effectively such tests of the equipment in accordance with the
Contract and shall give facilities to the HVPNL /Inspector or to his
authorized representative to accomplish testing.

Page - 22
9.9 The inspection by HVPNL and issue of Inspection Certificate thereon
shall in no way limit the liabilities and responsibilities of the Bidder in
respect of the agreed quality assurance programme forming a part of the
Contract.
9.10 The HVPNL will have the right of having at his own expenses any other
test(s) of reasonable nature carried out at Bidder’s premises or at site
or in any other place in addition of aforesaid type and routine tests, to
satisfy that the material comply with the specification.
9.11 The HVPNL reserves the right for getting any field tests not specified in
respective sections of the technical specification conducted on the
completely assembled equipment at site. The testing equipments for these
tests shall be provided by the HVPNL.
10. TESTS
10.1 Pre-commissioning Tests
On completion of erection of the equipment and before charging, each
item of the equipment shall be thoroughly cleaned and then inspected
jointly by the HVPNL and the Bidder for correctness and
completeness of installation and acceptability for charging, leading to
initial pre-commissioning tests at Site. The list of pre-commissioning tests to
be performed and shall be included in the Bidder’s quality assurance
programme.
10.2 Commissioning Tests
10.2.1 The testing equipments required for testing and commissioning shall be
arranged by the Bidder.
10.2.2 The specific tests requirement on equipment shall be included in quality
assurance program.
10.2.3 The Bidder shall be responsible for obtaining statutory clearances
from the concerned authorities for commissioning the equipment and the
switchyard. However necessary fee shall be reimbursed by HVPNL
on production of requisite documents.
11.0 PACKAGING & PROTECTION
11.1 All the equipments shall be suitably protected, coated, covered or boxed
and crated to prevent damage or deterioration during transit, handling
and storage at Site till the time of erection. On request of the HVPNL,
the Bidder shall also submit packing details/associated drawing for
any equipment/material under his scope of supply, to facilitate the
HVPNL to repack any equipment/material at a later date, in case the
need arises. While packing all the materials, the limitation from the point
of view of availability of Railway wagon sizes in India should be taken
into account. The Bidder shall be responsible for any loss or damage
Page - 23
during transportation, handling and storage due to improper packing. Any
demurrage, wharfage and other such charges claimed by the
transporters, railways etc. shall be to the account of the Bidder.
HVPNL takes no responsibility of the availability of the wagons.
11.2 All coated surfaces shall be protected against abrasion, impact,
discolouration and any other damages. All exposed threaded portions
shall be suitably protected with either a metallic or a non-metallic
protecting device. All ends of all valves and pipings and conduit
equipment connections shall be properly sealed with suitable devices to
protect them from damage.
12.0 FINISHING OF METAL SURFACES
12.1 All metal surfaces shall be subjected to treatment for anti-corrosion
protection. All ferrous surfaces for external use unless otherwise
stated elsewhere in the specification or specifically agreed, shall be
hot-dip galvanized after fabrication. High tensile steel nuts & bolts and
spring washers shall be electro galvanized to service condition 4. All
steel conductors including those used for earthing/grounding (above
ground level) shall also be galvanized according to IS: 2629.

12.2 HOT DIP GALVANISING


12.2.1 The minimum weight of the zinc coating shall be 610 gm/sq. m and
minimum thickness of coating shall be 85 microns for all items thicker
than 6mm. For items lower than 6mm thickness requirement of
coating thickness shall be as per relevant Standard/Specification. For
surface which
shall be embedded in concrete, the zinc coating shall be 610 gm/sq. m
minimum.
12.2.2 The galvanized surfaces shall consist of a continuous and uniform
thick coating of zinc, firmly adhering to the surface of steel. The
finished surface shall be clean and smooth and shall be free from
defects like discoloured patches, bare spots, unevenness of coating,
spelter which is loosely attached to the steel globules, spiky deposits,
blistered surface, flaking or peeling off, etc. The presence of any of
these defects noticed on visual or microscopic inspection shall render
the material liable to rejection.
12.2.3 After galvanizing. no drilling or welding shall be performed on the
galvanized parts of the equipment excepting that nuts may be
threaded after galvanizing. Sodium dichromate treatment shall be
provided to avoid formation of white rust after hot dip galvanization.
12.2.4 The galvanized steel shall be subjected to six one minute dips in
copper sulphate solution as per IS-2633.

Page - 24
12.2.5 Sharp edges with radii less than 2.5 mm shall be able to withstand
four immersions of the Standard Preece test. All other coatings shall
withstand six immersions. The following galvanizing tests should
essentially be performed as per relevant Indian Standards.
- Coating thickness
- Uniformity of zinc
- Adhesion test
- Mass of zinc coating
12.2.6 Galvanized material must be transported properly to ensure that
galvanized surfaces are not damaged during transit. Application of
zinc rich paint at site shall not be allowed.
12.3 PAINTING
12.3.1 All sheet steel work shall be degreased, pickled, phosphated in
accordance with the IS-6005 “Code of practice for phosphating iron
and sheet”. All surfaces, which will not be easily accessible after shop
assembly, shall beforehand be treated and protected for the life of the
equipment. The surfaces, which are to be finished painted after
installation or require corrosion protection until installation, shall be
shop painted with at least two coats of primer. Oil, grease, dirt and
swaf shall be thoroughly removed by emulsion cleaning. Rust and
scale shall be removed by pickling with dilute acid followed by
washing with running water, rinsing with slightly alkaline hot water
and drying.
12.3.2 After phosphating, thorough rinsing shall be carried out with clean
water followed by final rinsing with dilute dichromate solution and
oven drying. The phosphate coating shall be sealed with application of
two coats of ready mixed, stoving type zinc chromate primer. The first
coat may be “flash dried” while the second coat shall be stoved.
12.3.3 After application of the primer, two coats of finishing synthetic enamel
paint shall be applied, each coat followed by stoving. The second
finishing coat shall be applied after inspection of first coat of painting.
12.3.4 The exterior colour of the paint shall be as per shade no: 631 (for
outdoor) & 631 (for indoor) of IS-5 and inside shall be glossy white for
all equipment, marshalling boxes, junction boxes, control cabinets,
panels etc. unless specifically mentioned under respective sections of
the equipments. Each coat of primer and finishing paint shall be of
slightly different shade to enable inspection of the painting. A small
quantity of finishing paint shall be supplied for minor touching up
required at site after installation of the equipments.

Page - 25
12.3.5 In case the Bidder proposes to follow his own standard surface finish
and protection procedures or any other established painting
procedures, like electrostatic painting etc., the procedure shall be
submitted alongwith the Bids for HVPNL’s review & approval.
12.3.6 The colour scheme as given below shall be followed for Fire Protection
and Air Conditioning systems
S.No. PIPE LINE Base colour Band
colour
Fire Protection System
1 Hydrant and Emulsifier system FIRE RED -
pipeline
2 Emulsifier system detection line FIRE RED Sea Green
- water
3 Emulsifier system detection line FIRE RED Sky Blue
-Air
4 Pylon support pipes FIRE RED
Air Conditioning System
5 Refrigerant gas pipeline - at Canary Yellow -
compressor suction
6 Refrigerant gas pipeline - at Canary Yellow Red
compressor discharge
7 Refrigerant liquid pipeline Dark -
Admiralty
Green
8 Chilled water pipeline Sea Green -
9 Condenser water pipeline Sea Green Dark Blue

The direction of flow shall be marked by → (arrow) in black colour.

Base Colour Direction of flow Band Colour

13.0 HANDLING, STORING AND INSTALLATION


13.1 In accordance with the specific installation instructions as shown on
manufacturer’s drawings or as directed by the HVPNL or his
representative, the Bidder shall unload, store, erect, install, wire, test
and place into commercial use all the equipment included in the
contract. Equipment shall be installed in a neat, workmanlike manner so
that it is level, plumb, square and properly aligned and oriented.
Commercial use of switchyard equipment means completion of all site
tests specified and energisation at rated voltage.

Page - 26
13.2 Bidder may engage manufacturer’s Engineers to supervise the
unloading, transportation to site, storing, testing and commissioning of
the various equipment being procured by them separately.
Bidder shall unload, transport, store, erect, test and commission the
equipment as per instructions of the manufacturer’s supervisory
Engineer(s) and shall extend full cooperation to them.
13.3 In case of any doubt/misunderstanding as to the correct interpretation
of manufacturer’s drawings or instructions, necessary clarifications
shall be obtained from the HVPNL. Bidder shall be held
responsible for any damage to the equipment consequent to not
following manufacturer’s drawings/instructions correctly.
13.4 Where assemblies are supplied in more than one section, Bidder
shall make all necessary mechanical and electrical connections
between sections including the connection between buses. Bidder
shall also do necessary adjustments/alignments necessary for proper
operation of circuit breakers, isolators and their operating
mechanisms. All components shall be protected against damage
during unloading, transportation, storage, installation, testing and
commissioning. Any equipment damaged due to negligence or
carelessness or otherwise shall be replaced by the Bidder at his
own expense.
13.5 Bidder shall be responsible for examining all the shipment and
notify the HVPNL immediately of any damage, shortage,
discrepancy etc. for the purpose of HVPNL’s information only. The
Bidder shall submit to the HVPNL every week a report detailing
all the receipts during the weeks. However, the Bidder shall be
solely responsible for any shortages or damages in transit, handling
and/or in storage and erection of the equipment at Site. Any
demurrage, wharfage and other such charges claimed by the
transporters, railways etc. shall be to the account of the Bidder.
13.6 The Bidder shall be fully responsible for the equipment/material
until the same is handed over to the HVPNL in an operating
condition after commissioning. Bidder shall be responsible for the
maintenance of the equipment/material while in storage as well as
after erection until taken over by HVPNL, as well as protection of
the same against theft, element of nature, corrosion, damages etc.
13.7 Where material / equipment is unloaded by HVPNL before the
Bidder arrives at site or even when he is at site, HVPNL by
right can hand over the same to Bidder and there upon it will be
the responsibility of Bidder to store the material in an orderly and
proper manner.

Page - 27
13.8 The Bidder shall be responsible for making suitable indoor storage
facilities, to store all equipment which require indoor storage.
13.9 The words ‘erection’ and ‘installation’ used in the specification are
synonymous.
13.10 Exposed live parts shall be placed high enough above ground to meet
the requirements of electrical and other statutory safety codes.
13.11 The design and workmanship shall be in accordance with the best
engineering practices to ensure satisfactory performance throughout
the service life. If at any stage during the execution of the Contract, it
is observed that the erected equipment(s) do not meet the above
minimum clearances as given in clause 4.7.1 the Bidder shall
immediately proceed to correct the discrepancy at his risks and cost.

13.12 Equipment Bases

A cast iron or welded steel base plate shall be provided for all rotating
equipment which is to be installed on a concrete base unless
otherwise agreed to by the HVPNL. Each base plate shall support the
unit and its drive assembly, shall be of a neat design with pads for
anchoring the units, shall have a raised lip all around, and shall have
threaded drain connections.

14.0 TOOLS AND TACKLES

The Bidder shall supply with the equipment one complete set of all
special tools and tackles for the erection, assembly, dis-assembly and
maintenance of the equipment. However, these tools and tackles shall
be separately, packed and brought on to Site.
15.0 AUXILIARY SUPPLY
15.1 The sub-station auxiliary supply is normally met through a system
indicated under section “Electrical & Mechanical Auxiliaries” having the
following parameters. The auxiliary power for station supply, including
the equipment drive, cooling system of any equipment, air-
conditioning, lighting etc shall be designed for the specified
Parameters as under. The DC supply for the instrumentation and
PLCC system shall also conform the parameters as indicated in the
following.

Page - 28
Normal Variation Frequency Phase Neutral
Voltage in Voltage in HZ /Wire
connection

415V +/- 10% 50 +/- 5% 3/ Solidly


4 Wire Earthed.
240V +/- 10% 50 +/- 5% 1/ Solidly
2 Wire Earthed.
220V 190V to240V DC - Isolated
2 wire
System
48V _ DC _ 2 wire
system
(+) earthed

Combined variation of voltage and frequency shall be limited to +/- 10%.


16.0 SUPPORT STRUCTURE
16.1 HVPNL has standardized the design of support structure and other
control dimensions as given in standard structural (design) drawings
enclosed with Section-Project. The Bidder shall strictly adhere to
these dimensions. The Bidder is required to supply standard
structures of various equipment. Bidder may also refer relevant
Clauses of Section (Structure) in this regard. All brackets, angels, stool
or other members necessary for attaching the operating mechanism
to the supporting structure shall be engineered and supplied by the
Bidder. The Support structures for all equipments shall be supplied by the
Bidder.
16.2 The support structures should be hot dip galvanised with minimum
610 gram/sq.m net of zinc.
16.3 In case of any deviation in this regard the bid is liable to be
considered technically non responsive and shall be liable to be
rejected.
16.4 Support structure shall meet the following mandatory requirements :
16.4.1 The minimum vertical distance from the bottom of the lowest
porcelain part of the bushing, porcelain enclosures or supporting

Page - 29
insulators to the bottom of the equipment base, where it rests on the
foundation pad shall be 2.55 metres.
17.0 CLAMPS AND CONNECTORS INCLUDING TERMINAL
CONNECTORS
17.1 All power clamps and connectors shall conform to IS:5561 & NEMA
CC1 and shall be made of materials listed below :
a) For connecting Aluminum alloy casting,
ACSR conductors conforming to designation A6
of IS:617 and all test shall
conform to IS:617
b) For connecting Bimetallic connectors made
equipment ter- from aluminum alloy casting,
minals made of conforming to designation A6
copper with of IS 617 with 2mm thick
ACSR conductors bimetallic liner and all test
shall conform to IS:617
c) For connecting G.I Galvanised mild steel shield
wire
d) i) Bolts, nuts & i) Electrogalvanised for sizes
Plain, washers below M12, for others hot
dip galvanised.
ii) Spring washers ii) Electro-galvanised mild
for items steel suitable for atleast
‘a’ to ‘c’ service condition-3 as per
IS:1573
17.2 Each equipment shall be supplied with the necessary terminals and
connectors, as required by the ultimate design for the particular
installation. The conductor terminations of equipment shall be either
expansion, sliding or rigid type suitable for single/twin Tarantulla
Conductor. The requirement regarding external corona and RIV as
specified for any equipment shall include its terminal fittings and the
equipment shall be factory tested with the connectors in position. If
corona rings are required to meet these requirements they shall be
considered as part of that equipment and included in the scope of work.
17.3 Where copper to aluminum connections are required, bi-metallic
clamps shall be used, which shall be properly designed to ensure that
any deterioration of the connection is kept to a minimum and
Page - 30
restricted to parts which are not current carrying or subjected to
stress. The design details of the joint shall be furnished to the
HVPNL by the Bidder.
17.4 Low voltage connectors, grounding connectors and accessories for
grounding all equipment as specified in each particular case, are also
included in the scope of Work.
17.5 No current carrying part of any clamp shall be less than 10 mm thick.
All ferrous parts shall be hot dip galvanized. Copper alloy liner of
minimum 2 mm thickness shall be cast integral with aluminum body
for Bi-metallic clamps.
17.6 All casting shall be free from blow holes, surface blisters, cracks and
cavities. All sharp edges and corners shall be blurred and rounded off.
17.7 Flexible connectors, braids or laminated straps made for the terminal
clamps for bus posts shall be suitable for both expansion or through
(fixed/sliding) type connection of 4" IPS AL. tube as required. In both
the cases the clamp height (top of the mounting pad to centre line of
the tube) should be same.
17.8 Clamp shall be designed to carry the same current as the conductor
and the temperature rise shall be equal or less than that of the
conductor at the specified ambient temperature. The rated current for
which the clamp/connector is designed with respect to the specified
reference ambient temperature, shall also be indelibly marked on each
component of the clamp/connector, except on the hardware.
17.9 All current carrying parts shall be designed and manufactured to have
minimum contact resistance.
17.10 Clamps and connectors shall be designed to be corona controlled.
Corona extinction voltage for 220 kV class clamps shall not
be less than 156 kV and R.I.V. level shall
not be more than 1000 micro volts at the test voltage specified in
respective sections.
17.11 Tests
17.11.1 Clamps and connectors should be type tested as per IS:5561 and shall
also be subjected to routine tests as per IS:5561. Following type test
reports on three samples of similar type shall be submitted for
approval as per clause 9.2 above except for sl. no.(ii) & (iii) for which
type test once conducted shall be applicable (i.e. the requirement of
test conducted within last five years shall not be applicable).
i) Temperature rise test (maximum temperature rise allowed is
35°C over 50°C ambient)
ii) Short time current test
Page - 31
iii) Corona (dry) and RIV (dry) test (for 220 KV voltage level clamps)
iv) Resistance test and tensile test
18.0 CONTROL CABINETS, JUNCTION BOXES, TERMINAL BOXES &
MARSHALLING BOXES FOR OUTDOOR EQUIPMENT
18.1 All types of boxes, cabinets etc. shall generally conform to & be
tested in accordance with IS-5039/IS-8623, IEC-439, as applicable,
and the clauses given below:
18.2 Control cabinets, junction boxes, Marshalling boxes & terminal boxes
shall be made of sheet steel or aluminum enclosure and shall be dust,
water and vermin proof. Sheet steel used shall be at least 2.0 mm
thick cold rolled or 2.5 mm hot rolled. The box shall be properly
braced to prevent wobbling. There shall be sufficient reinforcement to
provide level surfaces, resistance to vibrations and rigidity during
transportation and installation. In case of aluminum enclosed box the
thickness of aluminum shall be such that it provides adequate rigidity
and long life as comparable with sheet steel of specified thickness.
18.3 Cabinet/boxes shall be free standing floor mounting type, wall
mounting type or pedestal mounting type as per requirements. A
canopy and sealing arrangements for operating rods shall be provided
in marshalling boxes / Control cabinets to prevent ingress of rain
water.
18.4 Cabinet/boxes shall be provided with double hinged doors with
padlocking arrangements. The distance between two hinges shall be
adequate to ensure uniform sealing pressure against atmosphere. The
quality of the gasket shall be such that it does not get
damaged/cracked during the operation of the equipment.
18.5 All doors, removable covers and plates shall be gasketed all around
with suitably profiled EPDM gaskets. The gasket shall be tested in
accordance with approved quality plan. The quality of gasket shall be
such that it does not get damaged/cracked during the ten years of
operation of the equipment or its major overhaul whichever is earlier.
All gasketed surfaces shall be smooth straight and reinforced if
necessary to minimize distortion and to make a tight seal. Ventilating
Louvers, if provided, shall have screen and filters. The screen shall be
fine wire mesh made of brass.
18.6 All boxes/cabinets shall be designed for the entry of cables from
bottom by means of weather proof and dust-proof connections.
Boxes and cabinets shall be designed with generous clearances to
avoid interference between the wiring entering from below and any
terminal blocks or accessories mounted within the box or cabinet.
Page - 32
Suitable cable gland plate projecting at least 150 mm above the base
of the marshalling kiosk/box shall be provided for this purpose along
with the proper blanking plates. Necessary number of cable glands
shall be supplied and fitted on this gland plate. The gland shall project
at least 25mm above gland plate to prevent entry of moisture in cable
crutch. Gland plate shall have provision for some future glands to be
provided later, if required. The Nickel plated glands shall be dust
proof, screw on & double compression type and made of brass. The
gland shall have provision for securing armour of the cable separately
and shall be provided with earthing tag. The glands shall conform to
BS:6121.
18.7 A 240V, single phase, 50 Hz, 15 amp AC plug and socket shall be
provided in the cabinet with ON-OFF switch for connection of hand
lamps. Plug and socket shall be of industrial grade.
18.8 For illumination of a 20 Watts fluorescent tube or 15 watts CFL shall be
provided. The switching of the fittings shall be controlled by the door
switch.
18.9 All control switches shall be of rotary switch type and Toggle/piano
switches shall not be accepted.
18.10 Positive earthing of the cabinet shall be ensured by providing two
separate earthing pads. The earth wire shall be terminated on to the
earthing pad and secured by the use of self etching washer. Earthing
of hinged door shall be done by using a separate earth wire.
18.11 The bay marshalling kiosks shall be provided with danger plate and a
diagram showing the numbering/connection/feruling by pasting the
same on the inside of the door.
18.12 a) The following routine tests alongwith the routine tests as per
IS:5039 shall also be conducted:
i) Check for wiring
ii) Visual and dimension check
b) The enclosure of bay marshalling kiosk, junction box, terminal
box shall conform to IP-55 as per IS:13947 including application
of, 2.5 KV rms for 1 (one) minute, insulation resistance and
functional test after IP-55 test.
19.0 Auxiliary Switches (Applicable for isolators and circuit
breakers)
The following type test reports on auxiliary switches shall be
submitted for approval:
(a) Electrical endurance test - A minimum of 2000 operation for 2A
D. C. with a time constant greater than or equal to 20
Page - 33
millisecond with a subsequent examination of mV drop/visual
defects/temperature rise test.
(b) Mechanical endurance test. A minimum of 1,00,000 operations
with a subsequent checking of contact pressure test/visual
examination.
(c) Heat run test on contacts.
(d) IR/HV test etc.
20.0 TERMINAL BLOCKS AND WIRING
20.1 Control and instrument leads from the switchboards or from other
equipment will be brought to terminal boxes or control cabinets in
conduits. All interphase and external connections to equipment or to
control cubicles will be made through terminal blocks.
20.2 Terminal blocks shall be 650 V grade and have continuous rating to
carry the maximum expected current on the terminals. These shall be
of moulded piece, complete with insulated barriers, stud type
terminals, washers, nuts and lock nuts. Screw clamp, overall insulated,
insertion type, rail mounted terminals can be used in place of stud
type terminals. But preferably the terminal blocks shall be non-
disconnecting stud type equivalent to Elmex type CATM4, Phoenix
cage clamp type of Wago or equivalent.
20.3 Terminal blocks for current transformer and voltage transformer
secondary leads shall be provided with test links and isolating
facilities. The current transformer secondary leads shall also be
provided with short circuiting and earthing facilities.
20.4 The terminal shall be such that maximum contact area is achieved
when a cable is terminated. The terminal shall have a locking
characteristic to prevent cable from escaping from the terminal clamp
unless it is done intentionally.
20.5 The conducting part in contact with cable shall preferably be tinned or
silver plated however Nickel plated copper or zinc plated steel shall
also be acceptable.
20.6 The terminal blocks shall be of extensible design.
20.7 The terminal blocks shall have locking arrangement to prevent its
escape from the mounting rails.
20.8 The terminal blocks shall be fully enclosed with removable covers of
transparent, non-deteriorating type plastic material. Insulating barriers
shall be provided between the terminal blocks. These barriers shall not
hinder the operator from carrying out the wiring without removing the
barriers.

Page - 34
20.9 Unless otherwise specified terminal blocks shall be suitable for
connecting the following conductors on each side.
a) All circuits except Minimum of two of 2.5 sq mm
CT circuits copper flexible.
b) All CT circuits Minimum of 4 nos. of 2.5 sq mm
copper flexible.
20.10 The arrangements shall be in such a manner so that it is possible to
safely connect or disconnect terminals on live circuits and replace fuse
links when the cabinet is live.
20.11 Atleast 20 % spare terminals shall be provided on each
panel/cubicle/box and these spare terminals shall be uniformly
distributed on all terminals rows.
20.12 There shall be a minimum clearance of 250 mm between the
First/bottom row of terminal block and the associated cable gland
plate. Also the clearance between two rows of terminal blocks shall be
a minimum of 150 mm.
20.13 The Bidder shall furnish all wire, conduits and terminals for the
necessary inter phase electrical connections (where applicable) as well
as between phases and common terminal boxes or control cabinets.

20.14 All input and output terminals of each control cubicle shall be tested
for surge withstand capability in accordance with the relevant IEC
Publications, in both longitudinal and transverse modes. The
Bidder shall also provide all necessary filtering, surge protection,
interface relays and any other measures necessary to achieve an
impulse withstand level at the cable interfaces of the equipment
21.0 LAMPS AND SOCKETS
21.1 Lamps
All incandescent lamps shall use a socket base as per IS-1258, except in
the case of signal lamps.
21.2 Sockets
All sockets (convenience outlets) shall be suitable to accept both 5
Amp & 15 Amp pin round Standard Indian plugs. They shall be
switched sockets with shutters.
21.3 Hand Lamp:

Page - 35
A 240 Volts, single Phase, 50 Hz AC plug point shall be provided in
the interior of each cubicle with ON-OFF Switch for connection of hand
lamps.
21.4 Switches and Fuses:
21.4.1 Each panel shall be provided with necessary arrangements for
receiving, distributing, isolating and fusing of DC and AC supplies for
various control, signalling, lighting and space heater circuits. The
incoming and sub-circuits shall be separately provided with switchfuse
units. Selection of the main and Sub-circuit fuse ratings shall be such as
to ensure selective clearance of sub-circuit faults. Potential circuits for
relaying and metering shall be protected by HRC fuses.
21.4.2 All fuses shall be of HRC cartridge type conforming to IS:9228
mounted on plug-in type fuse bases. Miniature circuit breakers with
thermal protection and alarm contacts will also be accepted. All
accessible live connection to fuse bases shall be adequately shrouded.
Fuses shall have operation indicators for indicating blown fuse
condition. Fuse carrier base shall have imprints of the fuse rating and
voltage.
22.0 Bushings, Hollow Column Insulators, Support Insulators:
22.1 Bushings shall be manufactured and tested in accordance with IS:
2099 & IEC: 137 while hollow column insulators shall be manufactured
and tested in accordance with IEC 233/IS 5621. The support
insulators shall be manufactured and tested as per IS 2544/IEC 168
and IEC 273. The insulators shall also conform to IEC 815 as
applicable.
The bidder may also offer composite silicon insulator, conforming to
IEC-1109.
22.2 Support insulators, bushings and hollow column insulators shall be
manufactured from high quality porcelain. Porcelain used shall be
homogeneous, free from laminations, cavities and other flaws or
imperfections that might affect the mechanical or dielectric quality and
shall be thoroughly vitrified tough and impervious to moisture.
22.3 Glazing of the porcelain shall be uniform brown in colour, free from
blisters, burrs and similar other defects.
22.4 Support insulators/bushings/hollow column insulators shall be
designed to have ample insulation, mechanical strength and rigidity
for the conditions under which they will be used.
22.5 When operating at normal rated voltage there shall be no electric
discharge between the conductors and bushing which would cause
corrsion or injury to conductors, insulators or supports by the

Page - 36
formation of substances produced by chemical action. No radio
interference shall be caused by the insulators/bushings when
operating at the normal rated voltage.
22.6 Bushing porcelain shall be robust and capable of withstanding the
internal pressures likely to occur in service. The design and location
of clamps and the shape and the strength of the porcelain flange
securing the bushing to the tank shall be such that there is no risk of
fracture. All portions of the assembled porcelain enclosures and
supports other than gaskets, which may in any way be exposed to the
atmosphere shall be composed of completely non hygroscopic material
such as metal or glazed porcelain.
22.7 All iron parts shall be hot dip galvanised and all joints shall be air
tight. Surface of joints shall be trued up porcelain parts by grinding
and metal parts by machining. Insulator/bushing design shall be such
as to ensure a uniform compressive pressure on the joints.
22.8 Tests
In bushing, hollow column insulators and support insulataors shall
conform to type tests and shall be subjected to routine tests in
accordance with IS: 2099 & IS: 2544 & IS : 5621. The type test
reports shall be submitted for approval.
23.0 MOTORS
Motors shall be “Squirrel Cage” three phase induction motors of
sufficient size capable of satisfactory operation for the application and
duty as required for the driven equipment and shall be subjected to
routine tests as per applicable standards. The motors shall be of
approved make.
23.1 Enclosures
a) Motors to be installed outdoor without enclosure shall have hose
proof enclosure equivalent to IP 55 as per IS: 4691. For motors
to be installed indoor i.e. inside a box, the motor enclosure, shall
be dust proof equivalent to IP 44 as per IS: 4691.
b) Two independent earthing points shall be provided on opposite
sides of the motor for bolted connection of earthing conductor.
c) Motors shall have drain plugs so located that they will drain
water resulting from condensation or other causes from all
pockets in the motor casing.
d) Motors weighing more than 25 Kg. shall be provided with
eyebolts, lugs or other means to facilitate lifting.
23.2 Operational Features

Page - 37
a) Continuous motor rating (name plate rating) shall be at least ten
(10) percent above the maximum load demand of the driven
equipment at design duty point and the motor shall not be over
loaded at any operating point of driven equipment that will rise in
service.
b) Motor shall be capable at giving rated output without reduction
in the expected life span when operated continuously in the
system having the particulars as given in Clause 15.0 of this
Section.
23.3 Starting Requirements:
a) All induction motors shall be suitable for full voltage direct-on-
line starting. These shall be capable of starting and accelerating to
the rated speed alongwith the driven equipment without
exceeding the acceptable winding temperature even when the
supply voltage drops down to 80% of the rated voltage.
b) Motors shall be capable of withstanding the electrodynamic
stresses and heating imposed if it is started at a voltage of 110%
of the rated value.
c) The locked rotor current shall not exceed six (6) times the rated
full load current for all motors, subject to tolerance as given in
IS: 325.
d) Motors when started with the driven equipment imposing full
starting torque under the supply voltage conditions specified
under Clause 15.0 shall be capable of withstanding atleast two
successive starts from cold condition at room temperature and
one start from hot condition without injurious heating of winding.
The motors shall also be suitable for three equally spread starts
per hour under the above referred supply condition.
e) The locked rotor withstand time under hot condition at 110% of
rated voltage shall be more than starting time with the driven
equipment of minimum permissible voltage by at least two
seconds or 15% of the accelerating time whichever is greater. In
case it is not possible to meet the above requirement, the Bidder
shall offer centrifugal type speed switch mounted on the motor
shaft which shall remain closed for speed lower than 20% and
open for speeds above 20% of the rated speed. The speed
switch shall be capable of withstanding 120% of the rated speed
in either direction of rotation.
23.4 Running Requirements:
a) The maximum permissible temperature rise over the ambient
temperature of 50 degree C shall be within the limits specified in
Page - 38
IS:325 (for 3 - phase induction motors) after adjustment due to
increased ambient temperature specified.
b) The double amplitude of motor vibration shall be within the limits
specified in IS: 4729. Vibration shall also be within the limits
specified by the relevant standard for the driven equipment
when measured at the motor bearings.
c) All the induction motors shall be capable of running at 80% of
rated voltage for a period of 5 minutes with rated load
commencing from hot condition.
23.5 TESTING AND COMMISSIONING
An indicative list of tests is given below. Bidder shall perform any
additional test based on specialties of the items as per the field
Q.P./Instructions of the equipment Bidder or HVPNL without any extra
cost to the HVPNL. The Bidder shall arrange all instruments
required for conducting these tests along with calibration
certificates and shall furnish the list of instruments to the HVPNL for
approval.
(a) Insulation resistance.
(b) Phase sequence and proper direction of rotation.
(c) Any motor operating incorrectly shall be checked to determine
the cause and the conditions corrected.
24.0 TECHNICAL REQUIREMENT OF EQUIPMENTS
24.1 Circuit Breakers
a. The manufacturer(s) whose SF6 Circuit Breaker are offered should
have designed, manufactured tested as per IEC/IS or equivalent
standard supplied the same for the specified system voltage and which
are in satisfactory operation for at least 2 (two) years as on the date of
bid opening.
Or
b. The manufacturer(s) whose SF6 Circuit Breaker are offered who have
recently established production line in India for the specified system
voltage or above class, based on technological support of a parent
company or collaborator for the respective equipment(s) can also be
considered provided the parent company (Principal) or collaborator
meets qualifying requirements stipulated under clause no 24.1.a given
above.
And
Furnishes (jointly with parent company or collaborator) a legally
enforceable undertaking to guarantee quality, timely supply,
Page - 39
performance and warranty obligations as specified for the
equipment(s)
And
Furnishes a confirmation letter from the parent company or
collaborator along with the bid stating that parent company or
collaborator shall furnish performance guarantee for an amount of
10% of the cost of such equipment(s). This performance guarantee
shall be in addition to contract performance guarantee to be submitted
by the Bidder
24.2 Isolators
The manufacturer whose isolators are offered, should have designed,
manufactured, tested as per IEC/IS or equivalent standard and
supplied the isolator for the specified system voltage and fault level
and should be in satisfactory operation for at least 2 (two) years as on
the date of bid opening.
24.3 Instrument Transformers
The manufacturer whose instrument transformers are offered, should
have designed, manufactured & tested as per IS/IEC or equivalent
standard and supplied the same for the specified system voltage for
NCT, CT & CVT, PT and fault level in case of NCT, CT. These equipment
should be in
satisfactory operation for at least 2 (two) years as on the date of bid
opening.
24.4 Surge Arresters
The manufacturer whose Surge Arresters are offered should have
designed, manufactured and tested as per IEC/IS or equivalent
standard and supplied the Surge Arrester for the specified energy
capability with rated system voltage and which are in satisfactory
operation for at least 2 (two) years as on the date of bid opening.
24.5 1.1 kV Grade Power & Control Cables
24.5.1 Applicable for PVC Control Cable
The manufacturers, whose PVC control cables are offered, should
have designed, manufactured, tested and supplied in a single contract at
least 100 Kms of 1.1 kV grade PVC insulated control cables as on the
date of bid opening . Further the manufacturer should also have
designed, manufactured, tested and supplied at least 1 km of 16C x
2.5 Sq.mm or higher size as on the date of bid opening.
24.5.2 Applicable for PVC Power Cable
The manufacturer, whose PVC Power Cables are offered, should have
designed, manufactured, tested and supplied in a single contract
Page - 40
atleast 100 Kms of 1.1 kV or higher grade PVC insulated power cables as
on the date of bid opening . Further the manufacturer should also have
designed, manufactured, tested and supplied at least 1 km of 1C x 150
Sq. mm or higher size as on the date of bid opening.
24.5.3 Applicable for XLPE Power Cables
The Manufacturer, whose XLPE Power cables are offered, should have
designed, manufactured, tested and supplied in a single contract
atleast 25 Kms of 1.1 kV or higher grade XLPE insulated power cables as
on the date of bid opening . Further the manufacturer should also have
designed, manufactured, tested and supplied at least 1 km of 1C x 630
Sq. mm or higher size as on the date of bid opening.
24.6 LT Switchgear
24.6.1 The Manufacturer whose LT Switchgear are offered, should be a
manufacturer of LT Switchboards of the type and rating being offered. He
should have designed, manufactured, tested and supplied at least 50
nos. draw out circuit breaker panels, out of which at least 5 nos.
should have been with relay and protection schemes with current
transformer. He should have also manufactured at least 50 nos. motor
control center panels of the type and rating being offered which
should be in successful operation as on date of bid opening.
24.6.2 The Switchgear items (such as circuit breakers, fuse switch units,
contactors etc.), may be of his own make or shall be procured from
reputed manufacturers and of proven design. At least one hundred
circuit breakers of the make and type being offered shall be operating
satisfactory as on date of bid opening.
24.7 Battery and Battery Charger
24.7.1 Requirements for Battery Manufacturers
The manufacturer whose Batteries are offered should have designed,
manufactured and supplied DC Batteries of the type specified and
being offered, having a capacity of at least 600 AH and these shall be
operating satisfactorily for two years in power sector and/or industrial
installations as on date of bid opening.
24.7.2 Requirements for Battery Charger Manufacturers
The manufacturer, whose Battery Chargers are offered, should have
designed, manufactured and supplied Battery Chargers generally of
the type offered, with static automatic voltage regulators and having a
continuous output of atleast ten (10) KW and these should be in
successful as on the date of bid opening.
24.8 LT Transformers

Page - 41
The manufacturer, whose transformers are offered should have
designed, manufactured, type tested including short circuit test as per
IEC/IS or equivalent standards and supplied transformers of at least
33 kV class of 800 kVA or higher. The transformer should have been
in successful operation for at least 2 years as on the date of bid
opening.
24.9 Fire Fighting System
The bidder or his sub-vendor should have designed, supplied, tested,
erected and commissioned at least one number fire protection system
of the each type described in (i), (ii) and (iii) below in installations
such as power plants, substations, refineries, fertilizer plants or other
industrial or commercial installations. Such systems must have been
designed to the recommendations of Tariff Advisory Committee of
India or any other international accredited authority like (FOC, London
or NFPA, USA etc.) executed during last ten (10) years and should
have been in successful operation for at least 2 years as on the date
of bid opening.
(i) Automatic hydrant type fire protection system
(ii) Automatic high velocity or automatic medium velocity water
spray type fire protection system
(iii) Smoke detection system.
In case bidder himself do not meet the requirement of design, he can
engage a consultant(s) who must have designed i) Automatic hydrant
type fire protection system, ii) Automatic high velocity or automatic
medium velocity water spray type fire protection system and iii)
Smoke detection system, which must be in successful operation for at
least two years as on the date of bid opening.
24.10 Control and Relay Panels

24.10.1 The C&R Panels from a manufacturer who has designed,


manufactured, tested, installed and commissioned C&R panels which
are in satisfactory operation on 220KV system for at least 2 (two)
years on the date of bid opening can be offered.
The Bidder shall arrange C&R panels along with main relays from the
same manufacturer. However, one of the distance protection schemes
on each 220 kV feeder C&R panel and busbar protection on bus coupler
cum bus bar protection panel can be of other make also.
The manufacturer own make relays includes the relays manufactured by
their Principals /Associates.

Page - 42
24.11 PLCC
24.11.1 The manufacturer whose PLCC panels are offered should
have designed, manufactured, tested, supplied and
commissioned PLCC panels for the specified voltage level and
the same should be in successful operation for atleast 2
(two) years as on the date of bid opening.
24.11.2 The manufacturer whose line traps are offered should have
designed, manufactured tested, supplied and commissioned
similar linetraps for the specified voltage and fault level and
should be successful operation for atleast 2 (two) years as on
the date of bid opening.
24.11.3 PLCC Panels/line traps manufactured by the the manufacturer
meeting the requirements at Clause No. 24.11.1 & 24.11.2
except that the PLCC Panels/line traps manufactured, tested and
supplied by them is not in operation for the stipulated period can
also be offered provided the manufacturer furnishes an
undertaking jointly executed by him and his collaborator, who in
turn fully meets the requirement specified at 24.11.1 / 24.11.2
above as per the format enclosed in the bid document for
successful performance of the equipment offered.

25 . Operating and maintenance instructions:


These instructions shall give sufficient details to enable the HVPNL to maintain,
dismantle, reassemble and adjust all parts of the equipment and shall contain the
following information.
• table of content

• list of illustration

• introduction
the instruction shall contain:
-General technical characteristics
- a brief general description of the equipment and
- a definition of the technical terms used in subsequent pharagraphs of the instruction book

Detail description: This shall contain a complete and accurate description of the equipment, its
assembly and dismantling, as well as components and accessories. An accurate list stating
clearance, tolerances, temperatures, fits, etc. is required.
Page-43
Operating principles: A brief summary of the technical operating basis of the equipment,
including diagrams, circuit diagrams and similar ones.
Operating instructions: The instructions shall be accurate and easy to understand and shall
contain the sequence of individual manipulations required for operation of the equipment, table
lists and graphic presentation, should be used as far as possible for making the description
understood more readily. The operating and maintenance instructions shall be written and
prepared in English by the Bidder. All labels, instructions on equipment shall be written in English
by the Bidder. The following information for secondary equipment (distance relays, bus bar and
breaker failure relay, differential relay, pilot wire differential relay, over current relays etc…) shall
be given in CD-ROM’s in English
1. Operating manuals

2. Maintenance and setting instructions

3. Electrical circuits

4. Soft ware required for local and remote setting, testing, tele metering and getting
information from the relays.
Bidder shall give 5 sets of CD-ROM for secondary and primary equipment.

Testing and adjustment: The entire testing and adjustment procedure for equipment after
overhauls and during operation shall be dealt with Maintenance instructions are to be divided in
to three parts.
1. Preventive maintenance indicating the inspection required at regular intervals, the
inspection procedure, the routine cleaning and lubricating operations, the regular safety check
and similar steps.

2. Repair and adjustment, describing the inspections fitting and dismantling of parts, fault
tracing as well as repair and adjustment procedure.

3. Spare parts list, containing all the necessary data for ordering spare part.

26. MONTHLY PROGRESS REPORTS


For the control of the works by the HVPNL, the Bidder shall prepared detailed monthly
progress reports in following form:

These reports show the progress of material orders and procurement, material shipments,
construction and assembly works included in the contract. It will also include but not limited to
commencement dates, percentage of completion (with regards to the affected payments vs. Total
contract amount excluding escalation and to the physical realisation of works) and expected
completion dates.

Progress reports shall show manufacture of goods and construction operations for each
item of work the time work under the contract started to the anticipated completion date, there by
indicating the periods during which was previously underway as well as estimated future periods
of manufacture and construction operations.

Page-44
Monthly progress reports which are prepared at the end of each calendar month by the
Bidder shall be submitted to the HVPNL in three (3) copies and two (2) of them shall be given to
the HVPNL after approval of the regional department not later than seven (7) days after the close
of the reporting period.

The HVPNL has the right to withhold an amount not exceeding 1000 US$ or equivalent Rs which
are calculated by using selling exchange rates of the Central Bank of India per month from the
earnings of the Bidder if proper monthly progress report are not submitted to the HVPNL in due
course

MONTHLY PROGRESS REPORT

1 st page
Bidder
Sub-Bidder
Contract No
Bidder’s Site Engineering(s) name,
telephone and fax number
1. Civil Engineer(s)

2. Electrical Engineer (s)

3. Supervisor(s)

4. Site test engineer(s)

5. Commissioning engineer(s)
HVPNL’s Control Engineer(s) name,

Telephone and fax number


1. Civil Engineer:

2. Electrical Engineer
Second and the following page
Project Report No:
Month from.......to.....
CHAPTER-I General

CHAPTER-II

a) List of letters submitted by Consortium

b) List of letters send by the HVPNL

c) Photocopies of minutes of meeting

d) list of project submitted and stage


Page-45
(indicate revision)

CHAPTER-III Work activity

Delivery of goods (shipped, arrived to port,


At customs, arrived to side in good condition not)

* Supplied by Bidder
a) Local
b) Foreign

Civil Works
Erection
Site test
Overall function test

CHAPTER-IV Problem and difficulties confronted with indicating agreements and


disagreements

CHAPTER V Work program expected to be done next month

CHAPTER VI Monetary realization of the project and monthly monetary projection up to


completion.

Page - 46
ANNEXURE-A
CORONA AND RADIO INTERFERENCE VOLTAGE (RIV) TEST

1. General
Unless otherwise stipulated, all equipment together with its
associated connectors, where
applicable, shall be tested for external corona both by observing the
voltage level for the extinction of visible corona under falling power
frequency voltage and by measurement of radio interference voltage
(RIV).
2. Test Levels:
The test voltage levels for measurement of external RIV and for
corona extinction voltage are listed under the relevant clauses of the
specification.
3. Test Methods for RIV:
3.1 RIV tests shall be made according to measuring circuit as per
International Special-Committee on Radio Interference (CISPR)
Publication 16-1(1993) Part -1. The measuring circuit shall preferably be
tuned to frequency with 10% of 0.5 Mhz but other frequencies in the
range of 0.5 MHz to 2 MHz may be used, the measuring frequency being
recorded. The results shall be in microvolts.
3.2 Alternatively, RIV tests shall be in accordance with NEMA standard
Publication No. 107-1964, except otherwise noted herein.
3.3 In measurement of, RIV, temporary additional external corona
shielding may be provided. In measurements of RIV only standard
fittings of identical type supplied with the equipment and a simulation
of the connections as used in the actual installation will be permitted
in the vicinity within 3.5 meters of terminals.
3.4 Ambient noise shall be measured before and after each series of tests
to ensure that there is no variation in ambient noise level. If variation
is present, the lowest ambient noise level will form basis for the
measurements. RIV levels shall be measured at increasing and
decreasing voltages of 85%, 100%, 115% and 130% of the specified
RIV test voltage for all equipment unless otherwise specified. The
specified RIV test voltage for 220 kV is listed in the detailed
specification together with maximum permissible RIV level in
micro volts.

Page - 47
3.5 The metering instruments shall be as per CISPR recommendation or
equivalent device so long as it has been used by other testing
authorities.
3.6 The RIV measurement may be made with a noise meter. A calibration
procedure of the frequency to which noise meter shall be tuned shall
establish the ratio of voltage at the high voltage terminal to voltage
read by noisel meter.
4. Test Methods for Visible Corona
The purpose of this test is to determine the corona extinction voltage
of apparatus, connectors etc. The test shall be carried out in the same
manner as RIV test described above with the exception that RIV
measurements are not required during test and a search technique
shall be used near the onset and extinction voltage, when the test
voltage is raised and lowered to determine their precise values. The
test voltage shall be raised to 130% of RIV test voltage and
maintained there for five minutes. In case corona inception does not
take place at 130 %, test shall be stopped, otherwise test shall be
continued and the voltage will then be decreased slowly until all
visible corona disappears. The procedure shall be repeated at least 4
times with corona inception and extinction voltage recorded each
time. The corona extinction voltage for purposes of determining
compliance with the specification shall be the lowest of the four
values at which visible corona (negative or positive polarity)
disappears. Photographs with laboratory in complete darkness shall
be taken under test conditions, at all voltage steps i.e. 85%, 100%,
115% and 130%. Additional photographs shall be taken at corona
inception and extinction voltages. At least two views shall be
photographed in each case using Panchromatic film with an ASA
daylight rating of 400 with an exposure of two minutes at a lens
aperture of f/5.6 or equivalent. The photographic process shall be
such that prints are available for inspection and comparison with
conditions as determined from direct observation. Photographs shall
be taken from above and below the level of connector so as to show
corona on bushing, insulators and all parts of energised connectors.
The photographs shall be framed such that test object essentially, fills
the frame with no cut-off.
4.1 The test shall be recorded on each photograph. Additional photograph
shall be taken from each camera position with lights on to show the
relative position of test object to facilitate precise corona location from
the photographic evidence.
4.2 In addition to photographs of the test object preferably four
photographs shall be taken of the complete test assembly showing
Page - 48
relative positions of all the test equipment and test objects. These four
photographs shall be taken from four points equally spaced around
the test arrangement to show its features from all sides. Drawings of
the laboratory and test set up locations shall be provided to indicate
camera positions and angles. The precise location of camera shall be
approved by HVPNL’s inspector, after determining the best camera
locations by trial energisation of test object at a voltage which results
in corona.
4.3 The test to determine the visible corona extinction voltage need not
be carried out simultaneously with test to determine RIV levels.
4.4 However, both test shall be carried out with the same test set up and
as little time duration between tests as possible. No modification on
treatment of the sample between tests will be allowed. Simultaneous
RIV and visible corona extinction voltage testing may be permitted at
the discretion of HVPNL’s inspector if, in his opinion, it will not
prejudice other test.
5. Test Records:
In addition to the information previously mentioned and the
requirements specified as per CISPR or NEMA 107-1964 the following
data shall be included in test report:
a) Background noise before and after test.
b) Detailed procedure of application of test voltage.
c) Measurements of RIV levels expressed in micro volts at each
level.
d) Results and observations with regard to location and type of
interference sources detected at each step.
e) Test voltage shall be recorded when measured RIV passes
through 100 microvolts in each direction.
f) Onset and extinction of visual corona for each of the four tests
required shall be recorded.

Page - 49
ANNEXURE - B
LIST OF SPECIFICATIONS
GENERAL STANDARDS AND CODES
Wherever Indian Standards have been mentioned, equivalent IEC or any other
Internationally recognized standard will also be applicable.
India Electricity Rules
Indian Electricity Act
Indian Electricity (Supply) Act
Indian Factories Act
IS-5, - Colors for Ready Mixed Paints and Enamels.
IS-335, - New Insulating Oils.
IS-617, - Aluminium and Aluminium Alloy Ingots and
Castings for General Engineering Purposes
IS-1448 (P1 to P 145) - Methods of Test for Petroleum and its
Products.
IS-2071 (P1 to P3) - Methods of High Voltage Testing.
IS-12063 - Classification of degrees of protection
provided by enclosures of electrical
equipment.
IS-2165
P1:1997 - Insulation Coordination.
P2:1983
IS-3043 - Code of Practice for Earthing
IS-6103 - Method of Test for Specific Resistance
(Resistivity) of Electrical Insulating Liquids
IS-6104 - Method of Test for Interfacial Tension of Oil
against Water by the Ring Method
IS-6262 - Method of test for Power factor & Dielectric
Constant of Electrical Insulating Liquids.
IS-6792 - Method for determination of electric strength
of insulating oils.
IS-5578 - Guide for marking of insulated conductors.
IS-11353 - Guide for uniform system of marking &
identification of conductors & apparatus
terminals.
IS-8263 - Methods for Radio Interference Test on High
voltage Insulators.

Page - 50
IS-9224 (Part 1,2&4) - Low Voltage Fuses
IEC-60060 (Part 1 to P4) - High Voltage Test Techniques
IEC 60068 - Environmental Test
IEC-60117 - Graphical Symbols
IEC-60156, - Method for the Determination of the Electrical
Strength of Insulation Oils.
IEC-60270, - Partial Discharge Measurements.
IEC-60376 - Specification and Acceptance of New Sulphur
Hexafloride
IEC-60437 - Radio Interference Test on High Voltage
Insulators.
IEC-60507 - Artificial Pollution Tests on High Voltage
Insulators to be used on AC Systems.
IEC-60694 - Common Specification for High Voltage
Switchgear & Controlgear Standards.
IEC-60815 - Guide for the Selection of Insulators in respect
of Polluted Conditions.
IEC-60865 (P1 & P2) - Short Circuit Current - Calculation of effects.
ANSI-C.1/NFPA.70 - National Electrical Code
ANSI-C37.90A - Guide for Surge Withstand Capability (SWC)
Tests
ANSI-C63.21, - Specification for Electromagnetic Noise and Field
C63.3 - Strength Instrumentation 10 KHz to 1
GHZ
C36.4ANSI-C68.1 - Techniquest for Dielectric Tests
ANSI-C76.1/EEE21 - Standard General Requirements and Test
Procedure for Outdoor Apparatus Bushings.
ANSI-SI-4 - Specification for Sound Level Metres
ANSI-Y32-2/C337.2 - Drawing Symbols
ANSI-Z55.11 - Gray Finishes for Industrial Apparatus and
Equipment No. 61 Light Gray
NEMA-107T - Methods of Measurements of RIV of High
Voltage Apparatus
NEMA-ICS-II - General Standards for Industrial Control and
Systems Part ICSI-109

Page - 51
CISPR-1 - Specification for CISPR Radio Interference
Measuring Apparatus for the frequency
range 0.15 MHz to 30 MHz
CSA-Z299.1-1978h - Quality Assurance Program Requirements
CSA-Z299.2-1979h - Quality Control Program Requirements
CSA-Z299.3-1979h - Quality Verification Program Requirements
CSA-Z299.4-1979h - Inspection Program Requirements
TRANSFORMERS
IS:10028 (Part 2 & 3) - Code of practice for selection, installation &
maintenance of Transformers (P1:1993),
(P2:1991), (P3:1991)
IS-2026 (P1 to P4) - Power Transformers
IS-3347 (part 1 to Part 8) - Dimensions for Porcelain transformer Bushings
for use in lightly polluted atmospheres.
IS-3639 - Fittings and Accessories for Power
Transformers
IS-6600 - Guide for Loading of OIl immersed
Transformers.
IEC-60076 (Part 1 to Part 5) - Power Transformers
IEC-60214 - On-Load Tap-Changers.
IEC- 60354 - Loading Guide for Oil - Immersed power trans
formers
IEC-60076-10 - Determination of Transformer Sound Levels
General requirements for Distribution, Power
ANSI-C571280 - and Regulating Transformers
Test Code for Distribution, Power and
ANSI-C571290 - Regulation Transformers
Guide for Loading Oil-Immersed Power
ANSI-C5792 - Transformers upto and including 100 MVA
with 55 deg C or 65 deg C Winding Rise

Page - 52
ANSI-CG,1EEE-4 - Standard Techniques for High Voltage Testing
CIRCUIT BREAKERS
IEC-62271-100 - High Voltage Alternating Current Circuit
Breakers
IEC-60427 - Synthetic Testing of High Voltage alternating
current circuit Breakers.
IEC-61264 - Pressurized Hollow Column Insulators

CURRENT TRANSFORMERS, VOLTAGE TRANSFORMERS AND COUPLING


CAPACITOR VOLTAGE TRANSFORMERS
IS-2705- (P1 to P4) - Current Transformers.
IS:3156- (P1 to P4) - Voltage Transformers.
IS-4379 - Identification of the Contents of Industrial Gas
Cylinders
IEC-60044-1 - Current transformers.
IEC-60044-2 - Voltage Transformers.
IEC-60358 - Coupling capacitors and capacitor dividers.
IEC-60044-4 - Instrument Transformes : Measurement of
Partial Discharges
IEC-60481 - Coupling Devices for power Line Carrier
Systems.
ANSI-C5713 - Requirements for Instrument transformers
ANSIC92.2 - Power Line Coupling voltage Transformers
ANSI-C93.1 - Requirements for Power Line Carrier Coupling
Capacitors
BUSHING
IS-2099 - Bushings for Alternating Voltages above
1000V
IEC-60137 - Insulated Bushings for Alternating Voltages
above 1000V
SURGE ARRESTERS
IS-3070 (PART2) - Lightning arresters for alternating current
systems : Metal oxide lightning arrestors
without gaps.
IEC-60099-4 - Metal oxide surge arrestors without gaps

Page - 53
IEC-60099-5 - Selection and application recommendation
ANSI-C62.1 - IEE Standards for S A for AC Power Circuits
NEMA-LA 1 - Surge Arresters
CUBICLES AND PANELS & OTHER RELATED EQUIPMENTS
IS-722, IS-1248, IS-3231, 3231 (P-3) - Electrical relays for power system protection
IS:5039 - Distributed pillars for Voltages not Exceeding
1000 Volts.
IEC-60068.2.2 - Basic environmental testing procedures Part
2: Test B: Dry heat
IEC-60529 - Degree of Protection provided by enclosures.
IEC-60947-4-1 - Low voltage switchgear and control gear.
IEC-61095 - Electromechanical Contactors for household
and similar purposes.
IEC-60439 (P1 & 2) - Low Voltage Swtichgear and control gear
assemblies
ANSI-C37.20 - Switchgear Assemblies, including metal
enclosed bus.
ANSI-C37.50 - Test Procedures for Low Voltage Alternating
Current Power Circuit Breakers
ANSI-C39 - Electric Measuring instrument
ANSI-C83 - Components for Electric Equipment
IS: 8623: (Part I to 3) - Specification for Switchgear & Control
Assemblies.
NEMA-AB - Moulded Case Circuit and Systems
NEMA-CS - Industrial Controls and Systems
NEMA-PB-1 - Panel Boards
NEMA-SG-5 - Low voltage Power Circuit breakers
NEMA-SG-3 - Power Switchgear Assemblies
NEMA-SG-6 - Power switching Equipment
NEMA-5E-3 - Motor Control Centers
1248 (P1 to P9) - Direct acting indicating analogue electrical
measuring instruments & their accessories.
Disconnecting switches

Page - 54
IEC-60129 - Alternating Current Disconnectors (Isolators)
and Earthing switches
IEC-1129 - Alternating Current Earthing Switches Induced
Current switching
IEC-60265 (Part 1 & Part 2) - High Voltage switches
ANSI-C37.32 - Schedule of preferred Ratings, Manufacturing
Specifications and Application Guide for high
voltage Air Switches, Bus supports and switch
accessories
ANSI-C37.34 - Test Code for high voltage air switches
NEMA-SG6 - Power switching equipment
PLCC and line traps
IS-8792 - Line traps for AC power system.
IS-8793 - Methods of tests for line traps.
IS-8997 - Coupling devices for PLC systems.
IS-8998 - Methods of test for coupling devices for PLC
systems.
IEC-60353 - Line traps for A.C. power systems.
IEC-60481 - Coupling Devices for power line carrier
systems.
IEC-60495 - Single sideboard power line carrier terminals
IEC-60683 - Planning of (single Side-Band) power line
carrier systems.
CIGRE - Teleprotection report by Committee 34 & 35.
CIGRE - Guide on power line carrier 1979.
CCIR - International Radio Consultative Committee
CCITT - International Telegraph & Telephone
Consultative Committee
EIA - Electric Industries Association
Protection and control equipment
IEC-60051 : (P1 to P9) - Recommendations for Direct Acting indicating
analogue electrical measuring instruments and
their accessories.
IEC-60255 (Part 1 to part 23) - Electrical relays.
IEC-60297

Page - 55
(P1 to P4) - Dimensions of mechanical structures of the
482.6mm (19 inches) series.
IEC-60359 - Expression of the performance of electrical &
electronic measuring equipment.
IEC-60387 - Symbols for Alternating-Current Electricity
meters.
IEC-60447 - Man machine interface (MMI) - Actuating
principles.
IEC-60521 - Class 0.5, 1 and 2 alternating current watt
hour metres
IEC-60547 - Modular plug-in Unit and standard 19-inch
rack mounting unit based on NIM Standard
(for electronic nuclear instruments)
ANSI-81 - Screw threads
ANSI-B18 - Bolts and Nuts
ANSI-C37.1 - Relays, Station Controls etc.
ANSI-C37.2 - Manual and automatic station control,
supervisory and associated telemetering
equipment
ANSI-C37.2 - Relays and relay systems associated with
electric power apparatus
ANSI-C39.1 - Requirements for electrical analog indicating
instruments
MOTORS
IS-325 - Three phase induction motors.
IS-4691 - Degree of protection provided by enclosure
for rotating electrical machinery.
IEC-60034 (P1 to P19:) - Rotating electrical machines
IEC-Document 2 - Three phase induction motors
(Central Office) NEMA-MGI Motors and Generators
Electronic equipment and components
MIL-21B, MIL-833 & MIL-2750
IEC-60068 (P1 to P5) Environmental testing
IEC-60326 (P1 to P2) : Printed boards
Material and workmanship standards

Page - 56
IS-1363 (P1 to P3) - Hexagon headbolts, screws and nuts of
product grade C.
IS-1364 (P1 to P5) - Hexagon head bolts, screws and nuts of
products grades A and B.
IS-3138 - Hexagonal Bolts and Nuts (M42 to M150)
ISO-898 - Fasteners: Bolts, screws and studs
ASTM - Specification and tests for materials
Clamps & connectors
IS-5561 - Electric power connectors.
NEMA-CC1 - Electric Power connectors for sub station
NEMA-CC 3 - Connectors for Use between aluminium or
aluminum- Copper Overhead Conductors
Bus hardware and insulators
IS: 2121 - Fittings for Aluminum and steel cored Al
conductors for overhead power lines.
IS-731 - Porcelain insulators for overhead power lines
with a nominal voltage greater than 1000 V.
IS-2486 (P1 to P4) - Insulator fittings for overhead power lines
with a nominal voltage greater than 1000 V.
IEC-60120 - Dimensions of Ball and Socket Couplings of
string insulator units.
IEC-60137 - Insulated bushings for alternating voltages
above 1000 V.
IEC-60168 - Tests on indoor and outdoor post insulators of
ceramic material or glass for Systems with
Nominal Voltages Greater than 1000 V.
IEC-60233 - Tests on Hollow Insulators for use in electrical
equipment.
IEC-60273 - Characteristices of indoor and outdoor post
insulators for systems with nominal voltages
greater than 1000V.
IEC-60305 - Insulators for overhead lines with nominal
voltage above 1000V-ceramic or glass
insulator units for a.c. systems Characteristics
of String Insulator Units of the cap and
pintype.

Page - 57
IEC-60372 (1984) - Locking devices for ball and socket couplings
of string insulator units : dimensions and
tests.
IEC-60383 (P1 and P2) - Insulators for overhead lines with a nominal
voltage above 1000 V.
IEC-60433 - Characteristics of string insulator units of the
long rod type.
IEC-60471 - Dimensions of Clevis and tongue couplings of
string insulator units.
ANSI-C29 - Wet process porcelain insulators
ANSI-C29.1 - Test methods for electrical power insulators For
ANSI-C92.2 - insulators, wet-process porcelain and
toughened glass suspension type
ANSI-C29.8 - For wet-process porcelain insulators
apparatus, post-type
ANSI-G.8 - Iron and steel hardware
CISPR-7B - Recommendations of the CISPR, tolerances of
form and of Position, Part 1
ASTM A-153 - Zinc Coating (Hot-Dip) on iron and steel
hardware
Strain and rigid bus-conductor
IS-2678 - Dimensions & tolerances for Wrought
Aluminum and Aluminum Alloys drawn round
tube.
IS-5082 - Wrought Aluminum and Aluminum Alloy Bars.
Rods, Tubes and Sections for Electrical
purposes.
ASTM-B 230-82 - Aluminum 1350 H19 Wire for electrical
purposes
ASTM-B 231-81 - Concentric - lay - stranded, aluminum 1350
conductors
ASTM-B 221 - Aluminum - Alloy extruded bar, road, wire,
shape
ASTM-B 236-83 - Aluminum bars for electrical purpose (Bus-
bars)

Page - 58
ASTM-B 317-83 - Aluminum-Alloy extruded bar, rod, pipe and
structural shapes for electrical purposes
(Bus Conductors)
Batteries and batteries charger
Battery
IS:1651 - Stationary Cells and Batteries, Lead-Acid Type
(with Tubular Positive Plates)
IS:1652 - Stationary Cells and Batteries, Lead-Acid Type
(with Plante Positive Plates)
IS:1146 - Rubber and Plastic Containers for Lead-Acid
Storage Batteries
IS:6071 - Synthetic Separators for Lead-Acid Batteries
IS:266 - Specification for Sulphuric Acid
IS:1069 - Specification for Water for Storage Batteries
IS:3116 - Specification for Sealing Compound for Lead-
Acid Batteries
IS:1248 - Indicating Instruments
Battery Charger
IS:3895 - Mono-crystalline Semiconductor Rectifier Cells
and Stacks
IS:4540 - Mono-crystalline Semiconductor Rectifier
Assemblies and Equipment.
IS:6619 - Safety Code for Semiconductor Rectifier
Equipment
IS:2026 - Power Transformers
IS:2959 - AC Contactors for Voltages not Exceeding
1000 Volts
IS:1248 - Indicating Instruments
IS:2208 - HRC Fuses
IS:13947 (Part-3) - Air break switches, air break disconnectors &
fuse combination units for voltage not
exceeding 1000V AC or 1200V DC
IS:2147 - Degree of protection provided by enclosures
for low voltage switchgear and controlgear.
IS:6005 - Code of practice for phosphating of Iron and
Steel

Page - 59
IS:3231 - Electrical relays for power system protection
IS:3842 - Electrical relay for AC Systems
IS:5 - Colours for ready mix paint
IEEE-484 - Recommended Design for installation design
and installation of large lead storage batteries
for generating stations and substations.
IEEE-485 - Sizing large lead storage batteries for
generating stations and substations
Wires and cables
ASTMD-2863 - Measuring the minimum oxygen concentration
to support candle like combustion of plastics
(oxygen index)
IS-694 - PVC insulated cables for working voltages
upto and including 1100 Volts.
IS-1255 - Code of practice for installation and
maintenance of power cables, upto and
including 33 kV rating
IS-1554 (P1 and P2) - PVC insulated (heavy duty) electric cables
(part 1) for working voltage upto and
including 1100 V.
- Part (2) for working voltage from 3.3 kV upto
and including 11kV.
IS:1753 - Aluminium conductor for insulated cables
IS:2982 - Copper Conductor in insulated cables.
IS-3961 (P1 to P5) - Recommended current ratings for cables.
IS-3975 - Mild steel wires, formed wires and tapes for
armouring of cables.
IS-5831 - PVC insulating and sheath of electric cables.
IS-6380 - Elastometric insulating and sheath of electric
cables.
IS-7098 - Cross linked polyethylene insulated PVC
sheathed cables for working voltage upto and
including 1100 volts.
IS-7098 - Cross-linked polyethyle insulated PVC
sheathed cables for working voltage from
3.3kV upto and including 33 kV.

Page - 60
IS-8130 - Conductors for insulated electrical cables and
flexible cords.
IS-1753 - Aluminum Conductors for insulated cables.
IS-10418 - Specification for drums for electric cables.
IEC-60096 (part 0 to p4) - Radio Frequency cables.
IEC-60183 - Guide to the Selection of High Voltage Cables.
IEC-60189 (P1 to P7) - Low frequency cables and wires with PVC
insulation and PVC sheath.
IEC-60227 (P1 to P7) - Polyvinyl Chloride insulated cables of rated
voltages up to and including 450/750V.
IEC-60228 - Conductors of insulated cables
IEC-60230 - Impulse tests on cables and their accessories.
IEC-60287 (P1 to P3) - Calculation of the continuous current rating of
cables (100% load factor).
IEC-60304 - Standard colours for insulation for low-
frequency cables and wires.
IEC-60331 - Fire resisting characteristics of Electric cables.
IEC-60332 (P1 to P3) - Tests on electric cables under fire conditions.
IEC-60502 - Extruded solid dielectric insulated power
cables for rated voltages from 1 kV upto to 30 kV
IEC-754 (P1 and P2) - Tests on gases evolved during combustion of
electric cables.
AIR conditioning and ventilation
IS-659 - Safety code for air conditioning
IS-660 - Safety code for Mechanical Refrigeration
ARI:520 - Standard for Positive Displacement
RefrigerationCompressor and Condensing
Units
IS:4503 - Shell and tube type heat exchanger
ASHRAE-24 - Method of testing for rating of liquid coolers
ANSI-B-31.5 - Refrigeration Piping
IS:2062 - Steel for general structural purposes
IS:655 - Specification for Metal Air Dust
IS:277 - Specification for Galvanised Steel Sheets

Page - 61
IS-737 - Specification for Wrought Aluminium and
Aluminium Sheet & Strip
IS-1079 - Hot rolled cast steel sheet & strip
IS-3588 - Specification for Electrical Axial Flow Fans
IS-2312 - Propeller Type AC VentilationFans
BS-848 - Methods of Performance Test for Fans
BS-6540 Part-I - Air Filters used in Air Conditioning and General
Ventilation
BS-3928 - Sodium Flame Test for Air Filters (Other than
for Air Supply to I.C. Engines and
Compressors)
US-PED-2098 - Method of cold DOP & hot DOP test
MIL-STD-282 - DOP smoke penetration method
ASHRAE-52 - Air cleaning device used in general ventilation
for removing particle matter
IS:3069 - Glossary of Terms, Symbols and Units Relating
to Thermal Insulation Materials.
IS:4671 - Expanded Polystyrene for Thermal Insulation
Purposes
IS:8183 - Bonded Mineral Wool
IS:3346 - Evaluation of Thermal Conductivity properties
by means of guarded hot plate method
ASTM-C-591-69 - Standard specification for rigid preformed
cellular urethane thermal insulation
IS:4894 - Centrifugal Fans
BS:848 - Method of Performance Test for Centrifugal
Fans
IS:325 - Induction motors, three-phase
IS:4722 - Rotating electrical machines
IS:1231 - Three phase foot mounted Induction motors,
dimensions of
IS:2233 - Designations of types of construction and
mounting arrangements of rotating electrical
machines
IS:2254 - Vertical shaft motors for pumps, dimensions
of

Page - 62
IS:7816 - Guide for testing insulation resistance of
rotating machines
IS:4029 - Guide for testing three phase induction motors
IS:4729 - Rotating electrical machines, vibration of,
Measurement and evaluation of
IS:4691 - Degree of protection provided by enclosures
for rotating electrical machinery
IS:7572 - Guide for testing single-phase a.c. motors
IS:2148 - Flame proof enclosure for electrical apparatus
BS:4999 - Noise levels
(Part-51)
Galvanizing
IS-209 - Zinc Ingot
IS-2629 - Recommended Practice for Hot-Dip
galvanizing on iron and steel.
IS-2633 - Methods for testing uniformity of coating of
zinc coated articles.
ASTM-A-123 - Specification for zinc (Hot Galvanizing)
Coatings, on products Fabricated from rolled,
pressed and forged steel shapes, plates,
bars and strips.
ASTM-A-121-77 - Zinc-coated (Galvanized) steel barbed wire
Painting
IS-6005 - Code of practice for phosphating of iron and
steel.
ANSI-Z551 - Gray finishes for industrial apparatus and
equipment
SSPEC - Steel structure painting council
Fire protection system
Fire protection manual issued by tariff advisory committee (TAC) of India
HORIZONTAL CENTRIFUGAL PUMPS
IS:1520 - Horizontal centrifugal pumps for clear, cold
and fresh water
IS:9137 - Code for acceptance test for centrifugal &
axial pumps

Page - 63
IS:5120 - Technical requirement - Rotodynamic special
purpose pumps
API-610 - Centrifugal pumps for general services
- Hydraulic Institutes Standards
BS:599 - Methods of testing pumps
PTC-8.2 - Power Test Codes - Centrifugal pumps
DIESEL ENGINES
IS:10000 - Methods of tests for internal combustion
engines
IS:10002 - Specification for performance requirements for
constant speed compression ignition
engines for general purposes (above 20 kW)
BS:5514 - The performance of reciprocating compression
ignition (Diesel) engines, utilising liquid fuel
only, for general purposes
ISO:3046 - Reciprocating internal combustion engines
performance
IS:554 - Dimensions for pipe threads where pressure
tight joints are required on threads
ASME Power Test Code - Internal combustion engine PTC-17
- Codes of Diesel Engine Manufacturer’s
Association, USA
PIPING VALVES & SPECIALITIES
IS:636 - Non percolating flexible fire fighting delivery
hose
IS:638 - Sheet rubber jointing and rubber inserting
jointing
IS:778 - Gun metal gate, globe and check valves for
general purpose
IS:780 - Sluice valves for water works purposes (50 to
300 mm)
IS:901 - Couplings, double male and double female
instantaneous pattern for fire fighting
IS:902 - Suction hose couplings for fire fighting
purposes

Page - 64
IS:903 - Fire hose delivery couplings branch pipe
nozzles and nozzle spanner
IS:1538 - Cast iron fittings for pressure pipes for water,
gas and sewage
IS:1903 - Ball valve (horizontal plunger type) including
floats for water supply purposes
IS:2062 - SP for weldable structural steel
IS:2379 - Colour Code for the identification of pipelines
IS:2643 - Dimensions of pipe threads for fastening
purposes
IS:2685 - Code of Practice for selection, installation and
maintenance of sluice valves
IS:2906 - Sluice valves for water-works purposes (350
to 1200 mm size)
IS:3582 - Basket strainers for fire fighting purposes
(cylindrical type)
IS:3589 - Electrically welded steel pipes for water, gas
and sewage (150 to 2000 mm nominal
diameter)
IS:4038 - Foot valves for water works purposes
IS:4927 - Unlined flax canvas hose for fire fighting
IS:5290 - Landing valves (internal hydrant)
IS:5312 - Swing check type reflex (non-return) valves
(Part-I)
IS:5306 - Code of practice for fire extinguishing
installations and equipment on premises
Part-I - Hydrant systems, hose reels and foam inlets
Part-II - Sprinkler systems
BS:5150 - Specification for cast iron gate valves
MOTORS & ANNUNCIATION PANELS
IS:325 - Three phase induction motors
IS:900 - Code of practice for installation and
maintenance of induction motors
IS:996 - Single phase small AC and universal electric
motors

Page - 65
IS:1231 - Dimensions of three phase foot mounted
induction motors
IS:2148 - Flame proof enclosure of electrical apparatus
IS:2223 - Dimensions of flange mounted AC induction
motors
IS:2253 - Designations for types of construction and
mounting arrangements of rotating electrical
machines
IS:2254 - Dimensions of vertical shaft motors for pumps
IS:3202 - Code of practice for climate proofing of
electrical equipment
IS:4029 - Guide for testing three phase induction motors
IS:4691 - Degree of protection provided by enclosure
for rotating electrical machinery
IS:4722 - Rotating electrical machines
IS:4729 - Measurement and evaluation of vibration of
rotating electrical machines
IS:5572 - Classification of hazardous areas for electrical
(Part-I) installations (Areas having gases and
vapours)
IS:6362 - Designation of methods of cooling for rotating
electrical machines
IS:6381 - Construction and testing of electrical
apparatus with type of protection ‘e’
IS:7816 - Guide for testing insulation for rotating
machine
IS:4064 - Air break switches
IEC DOCUMENT 2 - Three Phase Induction Motor
(Control Office) 432
VDE 0530 Part I/66 - Three Phase Induction Motor
IS:9224 - HRC Fuses
(Part-II)
IS:6875 - Push Button and Control Switches
IS:694 - PVC Insulated cables
IS:1248 - Indicating instruments

Page - 66
IS:375 - Auxiliary wiring & busbar markings
IS:2147 - Degree of protection
IS:5 - Colour Relay and timers
IS:2959 - Contactors
PG Test Procedures
NFPA-13 - Standard for the installation of sprinkler
system
NFPA-15 - Standard for water spray fixed system for the
fire protection
NFPA-12A - Standard for Halong 1301 Fire Extinguishing
System
NFPA-72E - Standard on Antomatic Fire Detectors
Fire Protection Manual by TAC (Latest Edition)
NFPA-12 - Standard on Carbon dioxide extinguisher
systems
IS:3034 - Fire of industrial building:
Electrical generating and distributing stations code of practice
IS:2878 - CO2 (Carbon dioxide) Type Extinguisher
IS:2171 - DC (Dry Chemical Powder) type
IS:940 - Pressurised Water Type
D.G. SET
IS:10002 - Specification for performance requirements for
constant speed compression ignition
(diesel engine) for general purposes
IS:10000 - Method of tests for internal combustion
engines
IS:4722 - Rotating electrical machines-specification
IS:12063 - Degree of protection provided by enclosures
IS:12065 - Permissible limit of noise levels for rotating
electrical machines.
- Indian Explosive Act 1932
Steel structures
IS-228 (1992) - Method of Chemical Analysis of pig iron, cast
iron and plain carbon and low alloy steels.

Page - 67
Code of practice for use of structural steel in
overhead transmission line towers.
Code of practice for use of steel tubes in
general building construction
IS-802 (P1 to 3:) -
Dimensions for hot rolled steel beam, column
channel and angle sections.
IS-806 -
Covered electrodes for manual arc welding of
IS-808 - carbon of carbon manganese steel.
Code of Practice for use of metal arc welding
for general construction in Mild steel
IS-814 -
Code of practice for training and testing of
metal arc welders. Part 1 : Manual Metal arc
IS-816 -
welding.
Code of practice for design loads (other than
IS-817 -
earthquake) for buildings and structures.
Steel tubes for structural purposes.
IS-875 (P1 to P4) - Recommended practice for radiographic
examination of fusion welded butt joints in
steel plates.
IS-1161 -
Hexagonal head bolts, screws & nuts of
IS-1182 -
products grade C.
Hexagon headbolts, screws and nuts of
product grades A and B.
IS-1363 (P1 to P3) -
Technical supply condition for threaded steel
fasteners.
IS-1364 -
Methods for bend test.
IS-1367 (P1 to P18) - Method for tensile testing of steel products.
Criteria for earthquake resistant design of
IS-1599 - structures.
IS-1608 - Line Pipe.
IS-1893 - Steel for general structural purposes.
Code of practice for Radiographic testing. Single
IS-1978 - coil rectagular section spring washers for
IS-2062 - bolts, nuts and screws.
IS-2595 - Code of practice for ultrasonic pulse echo
testing by contact and immersion methods.
IS-3063 -

IS-3664 - Page - 68
Safety code for erection of structural steel
work.
Recommendations for metal arc welding of
IS-7205 - carbon and carbon manganese steels.
Inch series square and Hexagonal bolts and
screws
IS-9595 -
Square and hexagonal nuts
ANSI-B18.2.1 - Round head bolts
Specification for General Requirements for
ANSI-B18.2.2 - rolled steel plates, shapes, sheet piling and
bars of structural use
ANSI-G8.14 -
Specifications of structural steel
ASTM-A6 -
Specification for malleable iron castings
Practice for safeguarding against embilement
ASTM-A36 - of Hot Galvanized structural steel products
ASTM-A47 - and procedure for detaching embrilement
Specification for high strength low alloy
ASTM-A143 -
structural steel
Specification for low and intermediate tensile
strength carbon steel plates of structural
ASTM-A242 -
quality
Specification for Galvanized steel transmission
ASTM-A283 -
tower bolts and nuts
Specification for High strength low alloy
ASTM-A394 - structural manganese vanadium steel.
Specification for High strength low alloy
colombium- Vanadium steel of structural
ASTM-441 -
quality
Code for welding in building construction
ASTM-A572 -
welding inspection
Structural welding code
AWS D1-0 - American institute of steel construction
Manufactured graphite electrodes
AWS D1-1 -
AISC - Mild steel tubes, tubulars and other wrought
NEMA-CG1 - steel fittings
Piping and pressure vessels
IS-1239 (Part 1 and 2) - Page - 69
IS-3589 - Seamless Electrically welded steel pipes for
water, gas and sewage.
IS-6392 - Steel pipe flanges
ASME - Boiler and pressure vessel code
ASTM-A120 - Specification for pipe steel, black and hot
dipped, zinc-coated (Galvanized) welded and
seamless steel pipe for ordinary use
ASTM-A53 - Specification for pipe, steel, black, and hot-
dipped, zinc coated welded and seamless
ASTM-A106 - Seamless carbon steel pipe for high
temperature service
ASTM-A284 - Low and intermediate tensile strength carbon-
silicon steel plates for machine parts and
general construction.
ASTM-A234 - Pipe fittings of wrought carbon steel and alloy
steel for moderate and elevated temperatures
ASTM-S181 - Specification for forgings, carbon steel for
general purpose piping
ASTM-A105 - Forgings, carbon steel for piping components
ASTM-A307 - Carbon steel externally threated standard
fasteners
ASTM-A193 - Alloy steel and stainless steel bolting materials
for high temperature service
ASTM-A345 - Flat rolled electrical steel for magnetic
applications
ASTM-A197 - Cupola malleable iron
ANSI-B2.1 - Pipe threads (Except dry seal)
ANSI-B16.1 - Cast iron pipe flangesand glanged fitting.
Class 25, 125, 250 and 800
ANSI-B16.1 - Malleable iron threaded fittings, class 150 and
300
ANSI-B16.5 - Pipe flanges and flanged fittings, steel nickel
alloy and other special alloys
ANSI-B16.9 - Factory-made wrought steel butt welding
fittings
ANSI-B16.11 - Forged steel fittings, socket-welding and
threaded

Page - 70
ANSI-B16.14 - Ferrous pipe plug, bushings and locknuts with
piple threads
ANSI-B16.25 - Butt welding ends
ANSI-B18.1.1 - Fire hose couplings screw thread.
ANSI-B18.2.1 - Inch series square and hexagonal bolts and
screws
ANSI-B18.2.2 - Square and hexagonal nuts
NSI-B18.21.1 - Lock washers
ANSI-B18.21.2 - Plain washers
ANSI-B31.1 - Power piping
ANSI-B36.10 - Welded and seamless wrought steel pipe
ANSI-B36.9 - Stainless steel pipe
Other civil works standards
IS-269 - 43 grade ordinary port-land cement.
IS2721 - Galvanized steel chain link fence fabric
IS-278 - Galvanized steel barbed wire for fencing.
IS-383 - Coarse and fine aggregates from natural
sources for concrete.
IS-432 (P1 and P2) - Mild steel and medium tensile steel bars and
hard-dawn steel wire for concrete
reinforcement.
IS-456 - Code of practice for plain and reinforced
concrete.
IS-516 - Method of test for strength of concrete.
IS-800 - Code of practice for general construction in
steel.
IS-806 - Steel tubes for structural purposes.
IS-1172 - Basic requirements for water supply, drainage
and sanitation.
IS-1199 - Methods of sampling and analysis of concrete.
IS-1566 - Hard-dawn steel wire fabric for concrete
reinforcement.
IS-1742 - Code of Practice for Building drainage.
IS-1785 - Plain hard-drawn steel wire for pre stressed
concrete.

Page - 71
IS-1786 - High strength deformed Steel Bars and wires
for concrete reinforcement.
IS-1811 - Methods of sampling Foundry sands.
IS-1893 - Criteria for earthquake resistant design of
structures.
IS-2062 - Steel for general structural purposes.
IS-2064 - Selection, installation and maintenance of
sanitary appliances-code of practices.
IS-2065 - Code of practice for water supply in buildings.
IS-2090 - High tension steel bars used in prestressed
concrete.
IS-2140 - Standard Galvanized steel wire for fencing.
IS-2470 (P1 & P2) - Code of practice for installation of septic
tanks.
IS-2514 - Concrete vibrating tables.
IS-2645 - Integral cement waterproofing compounds.
IS-3025 (Part 1 to
Part 48) - Methods of sampling and test (Physical and
chemical) for water and waste water.
IS-4091 - Code of practice for design and construction
of foundations for transmission line towers
and poles.
IS-4111
(Part 1 to P5) - Code of practice for ancillary structures in
sewerage system.
IS-4990 - Plywood for concrete shuttering work.
IS-5600 - Sewage and drainage pumps.
National buiding code of India 1970
USBR E12 - Earth Manual by United States Department of
the interior Bureau of Reclamation
ASTM-A392-81 - Zinc/Coated steel chain link fence fabric
ASTM-D1557-80 - test for moisture-density relation of soils using
10-lb (4.5 kg) rame land 18-in. (457 mm)
Drop.
ASTM-D1586 - Penetration Test and Split-Barrel

Page - 72
(1967) - Sampling of Soils
ASTM-D2049-69 - Test Method for Relative Density of
Cohesionless Soils
ASTM-D2435 - Test method for Unconsolidated, (1982)
- Undrained Strengths of Cohesive Soils in
Triaxial Compression.
BS-5075 - Specification for accelerating Part I
Admixtures, Retarding Admixtures and Water
Reducing Admixtures.
CPWD - Latest CPWD specifications
ACSR MOOSE/AAC TARANTULLA
CONDUCTOR
Methods for Determination of BS:443-1969
IS:6745 Mass of zinc coating on zinc
coated Iron and Steel Articles
IS:8263 Methods for Radio Interference IEC:437-
1973 Test on High Voltage Insulators
NEMA:107-1964
CISPR
IS:209 Zinc Ingot BS:3436-1961
IS:398 Aluminum Conductors for IEC:209-1966
Part – V Overhead Transmission Purposes
IS: 5484 EC grade Aluminium rod produced by continuous casting rod
and rolling.
Reels and Drums forBS:1559-1949
IS:1778 Bare Conductors
Method for Tensile Testing ISO/R89-
IS:1521 1959 of steel wire
Recommended practice for
IS:2629 Hot dip Galvanising on Iron
and Steel.
Method for Testing Uniformity
IS:2633
of coating of zinc Coated Articles.
Hot dip galvanised coatings
IS:4826 on round steel wires ASTMA-472-729
IS:1841 EC grade Aluminium rod produced by rolling.
GALVANISED STEEL EARTHWIRE

Page - 73
IS:1521 Method for Tensile Testing ISO/R:89-1959
of Steel Wire
IS:1778 Reels and Drums for Bare Conductors
IS:2629 Recommended practice forHot Dip Galvanising
on Ironand Steel.
IS:2633 Methods for testing Uniformityof Coating of
Zinc Coated
Articles.
IS:4826 Hot dip Galvanised Coatings ASTM:A 475-
72a on Round Steel Wires BS:443-1969
IS:6745 Method for Determination BS:443-1969of mass
of Zinc Coating on Zinc coated Iron and Steel
Articles.
IS:209 Zinc ingot BS:3463-1961
IS:398 (Pt. I to Aluminum Conductors for BS:215 (Part-II)
P5:1992) overhead transmission purposes.
Lighting Fixtures and Accessories
(i) IS:1913 General and safety requirements for electric
lighting fittings.
(ii) IS:3528 Water proof electric lighting fittings.
(iii) IS:4012 Dust proof electric lighting fittings.
(iv) IS:4013 Dust tight proof electric lighting fittings.
(v) IS:10322 Industrial lighting fittings with metal
reflectors.
(vi) IS:10322 Industrial lighting fittings with plastic
reflectors.
(vii) IS:2206 Well glass lighting fittings for use under
ground in mines (non-flameproof type).
(viii) IS:10322 Specification for flood light.
(ix) IS:10322 Specification for decorative lighting outfits.
(x) IS:10322 Lumanaries for street lighting
(xi) IS:2418 Tubular flourescent lamps
(xii) IS:9900 High pressure mercury vapour lamps.
(xiii) IS:1258 Specification for Bayonet lamp flourescent
lamp.

Page - 74
(xiv) IS:3323 Bi-pin lamp holder tubular flourescent lamps.
(xv) IS:1534 Ballasts for use in flourescent lighting fittings.
(Part-I)
(xvi) IS:1569 Capacitors for use in flourescent lighting fittings.
(xvii)IS:2215 Starters for flourescent lamps.
(xviii)IS:3324 Holders for starters for tubular flourescent lamps
(xix) IS:418 GLS lamps
(xx) IS:3553 Water tight electric fittings
(xxi) IS:2713 Tubular steel poles
(xxii)IS:280 MS wire for general engg. purposes
Conduits, Accessories and Junction Boxes
(1) IS:9537 Rigid steel conduits for electrical wiring
(2) IS:3480 Flexible steel conduits for electrical wiring
(3) IS:2667 Fittings for rigid steel conduits for electrical wiring
(4) IS:3837 Accessories for rigid steel conduits for electrical wiring
(5) IS:4649 Adaptors for flexible steel conduits.
(6) IS:5133 Steel and Cast Iron Boxes
(7) IS:2629 Hot dip galvanising of Iron & Steel.
Lighting Panels
(1) IS:13947 LV Switchgear and Control gear(Part 1 to 5)

(2) IS:8828 Circuit breakers for over current protection for house
hold and similar installations.
(3) IS:5 Ready mix paints
(4) IS:2551 Danger notice plates
(5) IS:2705 Current transformers
(6) IS:9224 HRC Cartridge fuse links for voltage above 650V(Part-2)

(7)IS:5082 Wrought aluminium and Al. alloys, bars, rods, tubes


and sections for electrical purposes.
(8)IS:8623 Factory built Assemblies of Switchgear and Control
Gear for voltages upto and including 1000V AC and
1200V DC.
(9)IS:1248 Direct Acting electrical indicating instruments
Page - 75
Electrical Installation
(1) IS:1293 3 pin plug
(2) IS:371 Two to three ceiling roses
(3) IS:3854 Switches for domestic and similar purposes
(4) IS:5216 Guide for safety procedures and practices in electrical
work.
(5) IS:732 Code of practice for electrical wiring installation
(system voltage not exceeding 650 Volts.)
(6) IS:3043 Code of practice for earthing.
(7) IS:3646 Code of practice of interior illumination part II & III.
(8) IS:1944 Code of practice for lighting of public through fares.
(9) IS:5571 Guide for selection of electrical equipment for
hazardous areas.
(10) IS:800 Code of practice for use of structural steel in general
building construction.
(11) IS:2633 Methods of Testing uniformity of coating on zinc
coated articles.
(12) IS:6005 Code of practice for phosphating iron and steel.
(13) INDIAN ELECTRICITY ACT
(14) INDIAN ELECTRICITY RULES
LT SWITCHGEAR
IS:8623 (Part-I) Specification for low voltage switchgear and control
gear assemblies
IS:13947 (Part-I) Specification for low voltage switchgear and control
gear, Part 1 General Rules
IS:13947 (part-2) Specification for low voltage switchgear and control
gear, Part 2 circuit breakers.
IS:13947 (part-3) Specification for low voltage switchgear and control
gear.
Part 3 Switches, Disconnectors, Switch-disconnectors
and fuse combination units
IS:13947 (part-4) Specification for low voltage switchgear and control
gear.
Part 4 Contactors and motors starters.

Page - 76
IS:13947 (part-5) Specification for low voltage switchgear and control
gear.
Part 5 Control-circuit devices and switching elements
IS:13947 (part-6) Specification for low voltage switchgear and control
gear.
Part 6 Multiple function switching devices.
IS:13947 (part-7) Specification for low voltage switchgear and control
gear.
Part 7 Ancillary equipments
IS:12063 Degree of protection provided by enclosures
IS:2705 Current Transformers
IS:3156 Voltage Transformers
IS:3231 Electrical relays for power system protection
IS:1248 Electrical indicating instruments
IS:722 AC Electricity meters
IS:5578 Guide for Marking of insulated conductors
of apparatus terminals
IS:13703 (part 1) Low voltage fuses for voltage not exceeding 1000V
AC or 1500V DC Part 1 General Requirements
IS:13703 (part 2) Low voltage fuses for voltage not exceeding 1000V
AC or 1500V DC Part 2 Fuses for use of authorized
persons
IS:6005 Code of practice of phosphating iron and steel
IS:5082 Wrought Aluminum and Aluminum alloys for electrical
purposes
IS:2633 Hot dip galvanizing

Page - 77
TECHNICAL SPECIFICATION
FOR SF6 GAS INSULATED SWITCHGEAR RATED 245 KV

1 General

1.1 Scope of supply

This specification applies to the design, fabrication, inspection, testing, delivery and installation of a
single phase, 245 kV, 50 Hertz, indoor gas insulated switchgear (GIS) as specified in the GELO.

The assembled equipment shall be capable of withstanding electrical, mechanical and thermal
ratings of the specified system. All joints and connections shall be able to withstand the forces of
expansion, vibration, contraction and specified seismic requirements without deformation,
malfunction and leakage.

The Vendor shall carefully check this specification and submit an itemized list of all exceptions,
deviations or comments for clarification with the proposal.

1.2 Information about power supply


1.2.1 AC supplies
AC power for heaters and other auxiliary loads will be provided on the base of 230 V, 50 Hz., 3-
phase circuits. The normal maximum and minimum voltages that will occur in the supply are
as specified. All equipment supplied shall be capable of running continuously or switching the
AC within the range of the normal maximum and minimum voltages specified.

1.2.2 DC supplies
DC supplies will be provided for all control, interlocking, alarm, indication and power supply
circuits. The normal maximum and minimum voltage levels that will occur on the supply are
specified. At least one single fused outlet from the substation DC distribution board will be
provided for each local control cabinet.

1.3 Information about the building provided


The building and all civil works will be supplied. Special attention will be given to an optimized
design with small space requirements and therefore the bidders input is essential. An overhead
crane will be supplied for installation and maintenance work. The bidder shall specify the lifting
capacity necessary for lifting of the heaviest piece during installation or maintenance.

2. Standards and codes

All electrical switchgear, the components of the control system, the protection scheme shall be
conform to the relevant IEC standards and publications of the latest issue.

The following standards are applicable in the relevant parts to the individual components of the gas
insulated switchgear:

IEC 62271-203 High-voltage metal enclosed switchgear for rated voltage of 72.5 kV
and above
IEC 62271-100 High-voltage alternating-current circuit breakers
IEC 62271-102 Alternating current disconnector and earthing switches
IEC 60694 Common clauses for high-voltage switchgear and control gear standards
IEC 60044 Current and voltage transformers
IEC 60060 High voltage test techniques
1
IEC 60071 Insulation coordination
IEC 60099 Surge arresters
IEC 60137 Bushings for alternating voltage above 1000V
IEC 60255 Electrical Relays
IEC 60265 High voltage switches
IEC 60270 Partial discharge measurement
IEC 60376 Specification and acceptance of new sulfur hexa-fluoride
IEC 60480 Guide to checking of sulphur hexafluoride (SF6)
IEC 60529 Degrees of protection
IEC 60815 Pollution levels
IEC 60859 Cable connections for GIS
IEC 61000 Electromagnetical compatibility (EMC)
IEC 61634 Use and handling of SF6
IEC 61639 Direct connections Transformer - GIS
IEC 60364/60479/60621/IEEE std. 80 Standards for station grounding.
CENELEC/SVDB Pressure vessel codes

3. Electrical ratings
The GIS equipment shall provide one enclosure per phase for all gas compartments. Three
phase enclosure or mixed design shall not be acceptable. The apparatus shall have the
following basic electrical and design characteristics:

i) Phase design Single Phase


ii) Rated system voltage kV 220
Maximum Rated system voltage kV 245
iii) Rated withstand voltages, phase to ground
a Rated lightning impulse withstand voltage (peak) kV 1050
b Rated switching impulse voltage (peak) kV 850
c Power frequency 1 minute (r.m.s.) KV 460
iv) Rated frequency Hz 50
v) Rated current A 3150
vi) Rated short-time current (r.m.s) (1s) KA 40
vii) Rated momentary current (peak) KA 100
viii) Rated short circuit breaking current kA 40
ix) Partial discharge level, complete bay 1.5 x U/√3 pC < 10
x) SF6 gas pressure at 68 ºF / 20 ºC , for reference, shall kPa
be submitted by the manufacturer.
xi) Material
a Enclosures Aluminum
b Conductors Aluminum

2
4. Equipment specification

4.1 Requirements of the gas insulated switchgear

It is understood that each manufacturer has his own particular GIS design concept and it is not
the purpose of this specification to impose unreasonable restrictions. However, in the interest of
safety, reliability and maintainability, the switchgear offered shall meet the following minimum
requirements stipulated herein.

4.1.1 General
The GIS switchgear shall be made of tubular Aluminum enclosures and filled with SF6 gas for
insulation. Enclosures shall be of single phase encapsulation for both the busbars and the
feeder section bays.

The switchgear shall be modular in design. Future extensions shall be easily accomplished by
adding extra feeders without dismantling any major parts of the equipment. As much as
possible parts shall be of standard manufacture with similar parts and assemblies being
interchangeable. The bidder is encouraged to offer an optimized physical layout regarding
minimized space requirements and maintainability.

Shipping sections which are tested in the factory shall be joint in the field by using bolted and
sealed flange connections only. Field welding of enclosures is not acceptable. The size of the
pre-assembled shipping sections shall be as big as practical for transportation. Complete
station assembly in the factory for testing purpose and disassembly for shipping is not
preferred.

The flanged connections shall have gas seals between the flange surfaces. For outdoor
application, suitable means shall be used to protect the gas seal from the external environment.
Connections including bolts and nuts shall be adequately protected from corrosion and easy
accessible with the proper tools.

4.1.2 Sectionalization
The switchgear must be sectionalized, with gas tight barriers between sections or
compartments. The sections shall be designed

i) to minimize operational shut down when the gas pressure is reduced due to leakage
or for maintenance purposes.

ii) to minimize the quantity of gas that has to be evacuated and recharged before and
after maintaining any item of equipment.

Each breaker bay shall consist as minimum of the following gas tight individual monitored
zones:
i) Circuit breaker
ii) Bus section
iii) Feeder section
iv) Potential trafo

Sectionalisation shall ensure that Circuit breaker enclosure will not include any other
equipment in its gas compartment. Continuous bus lengths with out gas segregation shall not be
acceptable.

In case of double bus-bar or one and half configurations, equipment redundancy shall be
maintained by way of selective mechanical arrangement of the gas compartments.

Each section shall be provided with necessary valves to allow evacuation and refill of gas
without evacuation of any other section. To reduce the probability of leaks, connections with
pipes between gas compartments are not acceptable.
3
The gas system proposed shall be submitted with the proposal. External fixtures shall be of
non-corrosive material and be capped where required.

For the purpose of gas monitoring and maintenance, the GIS is provided with a gas density
switch in each gas compartment.

4.1.3 Conductor Type and contacts


Conductors shall be made of extruded aluminum suitable for the specified voltage and current
ratings. The electrical connections between the various gas sections shall be made by means
of multiple contact connectors (plug-in type) so that electrical connection is automatically
achieved when bolting one section to an other. Field welding of the conductor is not acceptable.
The surface of the connector fingers and conductor tubes on such connections shall be silver
plated.

4.1.4 Support insulators and section barriers


Support insulators shall be used to maintain the conductors and enclosure in proper relation.
Barrier insulators which are employed to isolate gas compartments and non-barrier insulators
which allow the gas pressure to equalize.

The insulators shall be manufactured from high quality epoxy resin, free of all voids and be
designed to reduce the electrical stress on the insulators to a minimum.

Insulator cones shall be embedded in full return current carrying metal fixing rings in order to
avoid mechanical stresses to the cast resin part and to impart full conductivity across the flange
connection.

The mechanical strength must be sufficient to ensure the conductor’s space requirements and
clearances when short circuit faults occur. In addition, the gas barrier insulators sealing to the
conductors and the enclosure wall shall be designed to withstand the maximum pressure
differential that could occur across the barrier, i.e. maximum operating pressure at one side and
vacuum on the other side.

Tests shall be carried out during the manufacturing of the switchgear to ensure that all
insulators are free of partial discharge at a voltage which is at least 10% higher than the rated
voltage.

4.1.5 Gas system


The GIS shall be furnished with sufficient sulfur hexa-fluoride (SF6 ) gas to pressurize the
complete system in a sequential approach, one zone or compartment at a time to the rated
nominal density. An additional quantity of gas equal to 10% of the system requirements shall be
furnished.

Maximum water content of SF6 -gas in GIS, within guarantee period:


CB ≤ 50 PPM (weight)
Others ≤ 75 PPM (weight)

During commissioning the dew point of SF6 gas shall be measured and documented.

The Gas loss of the switchgear shall be in no case higher than 0.5% per year. Clear
instructions shall be provided by the vendor about handling, recycling and treatment of new and
used SF6 gas. Components may be filled with N2 for transportation and refilled with SF6 on site.

4.1.5.1 Gas seals

All gas seals shall be designed to ensure that leakage rates are kept to an absolute minimum
under all normal pressure, temperature, electrical load and fault conditions. All gas seals
located in the flanges of the equipment enclosures shall be of the O-ring type. The material and
method of sealing used shall be stated in the tender.
4
4.1.5.2 SF6 gas density and pressure

The rated pressure of the SF6 insulating gas in the GIS equipment shall be as low as possible
while still meeting the requirements for electrical insulation and space limitations to reduce the
effects of leaks and to ensure that there is no chance of the gas liquefying at the lowest
ambient temperature. The initial gas pressure or density at the time of charging the equipment
shall provide a 10% margin above the minimum allowable operating pressure for the plant to be
safely operated for a reasonably long period before recharging is necessary.

4.1.5.3 SF6 gas quality

The GIS shall be designed for use with SF6. All SF6 gas supplied as part of the contract shall
comply with the requirements of IEC 60376 at a minimum. Certificate of poison inspection shall be
appended to wholesale gas.

4.1.5.4 Gas monitoring devices

Temperature-compensated gas density monitoring devices shall be provided for each gas
compartment. Any pipe-work connection between the various gas compartments and a
centralised measuring device shall be strictly avoided. The devices shall provide continuous
and automatic monitoring of the density of the gas. The monitoring device shall have two alarm
settings. These shall be set so that:

a) advanced warning can be given that the gas density is approaching an unacceptably low
level

b) after an urgent alarm, measures can be taken to immediately isolate the particular
compartment electrically by tripping circuit breakers and opening disconnect switches.

4.1.5.5 SF6 Gas treatment


Under normal operating conditions it shall not be necessary to treat the insulating SF6 gas
between major overhauls. Self sealing vacuum couplings shall be provided on all gas
compartments to facilitate filling and recharging. In all gas compartments permanent efficient
filters and drying agent shall be at least effective for the duration of time between major
overhauls.

4.1.5.6 Supply of SF6 gas

The contract shall include the supply of all SF6 gas necessary for filling and putting in
commercial operation the complete switchgear installation.

4.1.5.7 Gas filling - evacuation plant

All apparatus necessary for filling and evacuating the SF6 gas into and from the switchgear
equipment shall be supplied by the Bidder to enable any maintenance work to be carried
out.

The apparatus for filling or evacuating all gases to be used shall be provided with all necessary
hoses, couplings, flexible tubes and valves for coupling with the switchgear equipment. Details of
the proposed gas handling apparatus shall be provided.

4.1.6 Pressure relief


Automatic external pressure relief devices shall be incorporated in the basic design as a
precaution against bursting of enclosure. Internal pressure relief devices shall be not
acceptable.

The bursting pressure of the relief device shall be effectively coordinated with the rated gas
5
pressure and the pressure rise due to arcing to avoid any mal-operation in normal operating
conditions. Deflection devices shall be installed to ensure that personnel will not be
endangered. Pressure relief shall be by means of a metallic bursting disc system with a preset
opening pressure. For better gas tightness, bursting discs made of graphite or non-metallic
material shall be avoided.

4.1.7 Switchgear enclosures


The metal enclosures for the GIS equipment modules shall be made from Aluminum alloy and
tubular in construction. The vendor shall state the material used for his particular design. All
flanges shall be directly bolted together with good metallic contact to make enclosures
equipotential. Insulators or insulating material between flanges shall be avoided in order to get the
best electrical connection between the different enclosure modules. Flange connections via
external cross-bonding are not allowed.

Enclosures shall withstand normal and transient pressure in operation. They shall be designed
and manufactured according to the related standards to guarantee safety and reliability of
material, construction, welding technology and testing.

The material and thickness of enclosure shall be such as to withstand an internal flashover without
burn through for a period of 500 ms till the back-up relay protection clears the fault. The material
shall be such that it has no effect of environment as well as from the by-products of SF6
breakdown under arcing condition.

The gas-filled enclosures shall comply to the pressure vessel code applied in the country of
manufacturer.

4.1.8 Expansion joints and flexible connection


Expansion and installation alignment shall be considered in the design of the bus and
enclosure. The continuity of service during thermal expansion / contraction and vibrations shall be
ensured. If required, expansion joints shall be provided with compensators for the enclosure and
sliding plug-in contacts for the conductors. The number and position of expansion joints or flexible
connections are to be determined by the manufacturer to ensure that the complete installation
will not be subject to expansion stresses which could lead to distortion or failure of any piece of
the SF6 equipment, support structures or foundations.

Also, expansion joints, flexible connections and adjustable mountings shall be provided to
compensate for reasonable manufacturing and construction tolerances in the associated
equipment to which the GIS may be connected. This is to ensure that unreasonably excessive
accuracy is not required when installing such equipment and constructing the associated
foundations or support structures, e.g. transformers or the interconnection of isolated sections of
switchgear by means of long GIS busbar or duct installations. Flexible joints may also be
provided to allow more efficient maintenance and future extensions of the GIS.

4.1.9 Finish of surface and cleaning


The finish of interior surfaces of the GIS enclosures shall facilitate cleaning and inspection. Any
paints or other coatings that may be used shall not deteriorate when exposed to the SF6 gas
and arc products, etc., that may be present in the enclosures. They shall not contain any
substances which could contaminate the enclosed SF6 gas or affect its insulating properties
over a period of time.

The equipment shall be manufactured and assembled at the manufacturer©s works under
conditions of the utmost cleanliness. Before factory tests and packing for shipment, interior
surfaces, insulators, barriers etc., must be thoroughly cleaned.

6
4.1.10 Supporting structures
All supporting structures necessary for the support of the GIS equipment including associated
parts as anchor bolts, beams etc. shall be supplied. Access has to be considered in the design
of the structures to all equipment of the GIS. It has to be possible to surround the GIS with the
gas cart.

The specified stresses for outdoor equipment like wind, earthquake, snow, ice and thermal
expansion due to current and sun radiation have to be considered. Proper surface treatment for all
parts especially in outdoor situation have to be considered. All steel members have to be hot-
dipped galvanized according to DIN

4.1.11 Future extension


Where a double busbar system is specified it shall be possible to extend the switchgear by
adding future feeders with at least one of the busbar systems and the existing feeders
remaining in service continuously. The Vendor is required to demonstrate clearly in his
submitted documents the suitability of the switchgear design in this respect.

In case of extension, the interface shall incorporate facilities for installation and testing of
extension to limit the part of the existing GIS to be re-tested and to allow for connection to the
existing GIS without further dielectric testing.

4.1.12 Repair
Where double busbar is specified, in case of any internal fault in the busbar or busbar
disconector, circuit breaker, repair works must be possible with at least one bus bar in service.
Any failure shall be immediately signaled by the systems inherent self-supervision with clear
description of the nature and the location of this failure. Generally any failure shall have impact
only on the direct related devices and the rest of the substation shall remain in normal
operation.

4.1.13 Removal of components


The GIS shall be designed so that any component of the GIS can be easily removed. As
minimum flexibility in the layout arrangement it shall be possible to remove the circuit breaker with
both busbar remaining in service and it shall be possible to remove the disconnector of the
busbars, with one busbar remaining in service

4.1.14 Earthing of the switchgear


The Bidder shall supply the connection between the GIS and the station earthing system. The
station earthing itself will be provided. Nevertheless the Bidder shall propose the earthing net
under the GIS. The earthing system shall be based on a multi-point design ensuring the
protection in case of indirect contact (Touch or step voltages, in case of system fault) and
transient phenomena in case of lightning or switching operations.

Earthing conductors shall allow fault with short circuit current. Conductors with copper bars are
preferred over copper wires. Separate ground strips to short circuit flanges and earthing
switches are not allowed. Grounding switches shall be connected to ground through the
enclosure. Individual ground leads for the ground switches are not allowed. The inductive
voltage against ground in each part of the enclosure shall be not more than 65 V.

4.1.15 Auxiliary contacts


Each equipment shall be furnished with adequate number of electrically independent contacts at
user©s disposal. They shall be wired to terminals located in the local control cabinet of the circuit
breaker bay. Installation of auxiliary relays (contact multiplication) may be used to meet the overall
7
control and protection requirements.

4.1.16 Special tools


Any special tools needed for installation, operation and inspection shall be included in the
quotation. For gas handling purpose following tools shall be quoted as a minimum:

i) Dew point meter


ii) Leakage detector
iii) Precision pressure gauge

4.1.17 Spare parts


As an option the bidder is requested to supply a list of recommended spare parts for at least five
years operation.

Requirements of the high voltage components

4.1.18 Circuit Breaker

4.1.18.1 General

The GIS circuit breakers shall comply with the following general requirements for circuit
breakers and the latest revisions of the relevant IEC specifications.

Circuit-breakers shall be the SF6 gas insulated type of single phase design with the specified
ratings. The breaker shall be Self-Blast / Puffer type principle and consist of one interrupting
arcing chambers.

Each circuit-breaker including the drive mechanism shall be completely factory assembled,
adjusted and tested. The breaker shall include a suitable operating mechanism to assure
proper opening and closing, and shall permit checking adjustments and opening characteristics.
Each mechanism shall include dual trip coils in redundant design. The mechanism shall be
capable of reclosing within the range specified in the applicable standards. The breakers are to
be re-strike-free.

The breaker layout arrangement shall be either horizontal or vertical to provide higher mechanical
stability and ease in maintenance. The operating principle of the breaker shall ensure minimized
dynamic floor loading. Low reaction forces on foundations especially dynamically, are favorable
and considered in the evaluation.

4.1.18.2 Required Technical Data

Maximum operating Voltage kV 245


Rated withstand voltage across open contacts
- Lightning kV 1050 + 245
- Switching kV 850 + 245
- Power frequency kV 530
Rated short-circuit breaking current (r.m.s.), 1s: kA 40
Rated making current (peak): kA 100
Rated break time ms < 40
Rated opening time ms ≤ 20
Rated closing time ms ≤ 55
Close-open time ms ≤ 30
Rated cable and line charging breaking current A 500
Number of breaks per pole: Nos. 1
SF6 gas pressure at 68 °F/20 °C: (Actual values shall be submitted by manufacturer)
Filling pressure kPa
Alarm pressure kPa
8
Blocking pressure kPa

Operating mechanism :

Number per single phase circuit breaker 1


Rated operating sequence O-0.3s-CO-3 min-CO /

Time for recharging CO cycle


Type Spring / Hydraulic-spring
Number of trip coils 2
Number of closing coils 1/2
Rated control voltage (DC) V 220
Number of operations permissible without
maintenance
At no load Nos. 2000
At rated current Nos. 2000
At 40 / 50 kA Nos. 20

4.1.18.2.1 Breaking capacity

The total breaking time from energizing of the trip coil at rated control voltage to final arc
extinction shall be as short as possible.

The circuit breaker shall be capable of breaking all currents from zero up to the specified
maximum fault current in accordance with the relevant IEC publications. Official test reports
shall be submitted with the tender as evidence that the offered circuit breaker meets the
specific rating.

4.1.18.3 Auto-reclosing

If auto-reclosing is required, the circuit-breakers shall be capable of tripping and reclosing


according to the specified duty cycle.

4.1.18.4 Closing devices

All electrically operated closing devices and any mechanism charging motors or devices shall be
suitable for operation at any voltage between 110% and 85% of the nominal control voltage
measured at the device terminals.

The breaker shall close correctly when an electrical closing pulse of 50 ms duration is applied to the
closing coil.

4.1.18.5 Tripping devices

All electrical tripping devices shall be suitable for operation at any voltage between 110% and
85% of the nominal voltage, measured at the device terminals. The tripping devices of a circuit
breaker, when the circuit breaker is not carrying current, shall be capable of operating
satisfactory down to 70% of the nominal control voltage, measured at the device terminals.

An emergency hand tripping (mechanical) device shall be provided in the operating mechanism.

4.1.18.6 Operating mechanism


One operating mechanism shall be supplied for each single phase circuit-breaker. Electric
motor for the driving mechanism shall be DC operated to allow operation in case of AC failure
and thus of highest reliability. In case of failure of Aux. supply the mechanism shall have
sufficient energy stored to perform O-CO cycle.

In order to reduce maintenance work and outage time pneumatic operating mechanisms will not be
accepted.

9
Circuit breaker shall be operated by spring charge mechanism or electro hydraulic mechamism
or a combination of these shall be complete with all control equipment. The only external
requirement for operation shall be electrical supply. Hydraulic pipe working on site or common
system for substation shall not be acceptable.

Low stored operating energy shall be detected by some suitable method and dependent on the
position of the spring shall initiate one or more of the following operations:

1. start pump motor


2. block auto-reclosing if stored operating energy is insufficient to complete a break-
make-break operation
3. block closing if stored operating energy is insufficient to complete a make-break
operation
4. block tripping if stored operating energy is insufficient to complete a break operation

Charging of the operating mechanism shall be possible in the event of failure of the motor drive.
This be possible by connecting an external mobile pump with an electrically operated motor. The
mechanism shall be in a dust and vermin proof box for indoor installation or in a
weatherproof box for outdoor installation.

Each breaker shall have sufficient auxiliary switches all wired to terminals located in the local
control cubicle.

4.1.18.7 Anti pumping

All circuit-breaker mechanisms shall be provided with means to prevent pumping while the
closing circuit remains energized, should the circuit breaker either fail to latch, or be tripped
during closing due to the operation of the protective relays.

4.1.18.8 Position indicating devices

Position indicators shall be provided to clearly indicate whether a circuit-breaker is open or


closed. Each circuit-breaker shall be provided with an operation counter per mechanism to
record the number of tripping operations performed. The counter may be located at the local
control cabinet.

4.1.19 Disconnect switch

4.1.19.1 General

The GIS disconnect switches shall comply with the following general and the latest revision of the
relevant IEC standards.

Disconnect switches shall be three pole, group operated, no-load break, with one motor
operated mechanism per three-pole. They shall also have facilities for emergency manual
operation and the necessary operating handles or hand cranks shall be supplied.
Disconnect switches shall be interlocked to prevent the earthing switch from closing on a
energized bus section.
All main contacts shall either be silver plated or shall have silver inserts. Each disconnect switch
shall open or close only due to motor-driven or manual operation. The switch contact shall not
move due to gravity or other means, even if a part fails. Once initiated, the motor mechanism
shall complete an open or close operation without requiring the initiating contact to be held
closed.

4.1.19.2 Technical Data Requirement::

10
Rated Voltage kV 245
Rated withstand voltage across open contacts:
- Lightning kV 1050 + 245
- Switching kV 850 + 245
- Power frequency kV 530
Rated current A 3150
Rated short-circuit withstand current (r.m.s.), 1s kA 40
Capacitive current breaking capacity A 0.25
Bus Transfer current switching A, 1600,
V 20
Type of operating mechanism Motor
Number of drives per 3 phase 1
Control voltage (DC) V 220
Number of CO permissible without maintenance No. 2000

Electric motor for the driving mechanism shall be DC operated. Mechanisms shall be arranged
either mechanically or electrically so that all three phases of any particular disconnect switch
operate simultaneously. All mechanisms shall be suitable for electrical motor operation to
achieve a fully automatic operation in an unmanned substation.

For emergency situations manual operation shall be possible. Handles or hand cranks shall be
provided. Manual operation shall be prevented if the interlocking conditions have not been
satisfied. The auxiliary energy shall be electrically uncoupled from the motor when the switch is
operated manually.

The mechanisms shall be arranged for locking in the open and in the closed position. Facilities
shall be available to allow the switch to be padlocked in any position.

11
4.1.19.3 Position indicating and view ports

View ports shall be provided for each pole of the switch to permit visual inspection of each
switch contact position of each pole. External mechanically connected position indicators shall
also be provided showing either open or close position.

4.1.20 Maintenance earthing switch

4.1.20.1 General
The GIS earthing switches shall comply with the following general requirements and the latest
revision of the relevant IEC standards.

Maintenance grounding switches shall be three pole, group operated, no-load break, with one
motor operated mechanism per three-pole. They shall also have facilities for emergency
manual operation and the necessary operating handles or hand cranks shall be supplied.
Maintenance earthing switches shall be electrically interlocked to prevent the earthing switch
from closing on a energized bus section.

All main contacts shall either be silver plated or shall have silver inserts. Each earthing switch
shall open or close only due to motor-driven or manual operation. The switch contact shall not
move due to gravity or other means, even if a part fails. Once initiated, the motor mechanism
shall complete an open or close operation without requiring the initiating contact to be held
closed.

4.1.20.2 Technical Data Requirement:

Rated Voltage KV 245


Rated withstand voltage across open contacts:
- Lightning kV 1050 + 245
- Switching kV 850 + 245
- Power frequency kV 530
Rated current A 3150
Rated short-circuit withstand current (r.m.s.), 1s: kA 40
Type of operating mechanism Motor
Number of drives per 3 phase Nos. 1
Control voltage (DC) V 220
Number of CO permissible without maintenance Nos. 2000

4.1.20.3 Operating mechanism

Electric motor for the driving mechanism shall be DC operated. Mechanisms shall be arranged
either mechanically or electrically so that all three phases of any particular earthing switch
operate simultaneously.

All mechanisms shall be suitable for electrical motor operation to achieve a fully automatic
operation in an unmanned substation. For emergency situations manual operation shall be

12
possible. Handles or hand cranks shall be provided. Manual operation shall be prevented if the
interlocking system does not allow the operation of the switch.

The auxiliary energy shall be electrically uncoupled from the motor when the switch is operated
manually.

The mechanisms shall be arranged for locking in the open and in the closed position. Facilities
shall be available to allow the switch to be padlocked in any position.

4.1.20.4 Position indicating devices and view ports

View ports shall be provided for each pole of the switch to permit visual inspection of each
switch contact position of each pole. External mechanically connected position indicators shall
also be provided showing either open or close position.

4.1.21 Disconnector / earthing switch

4.1.21.1 General

Bidder is encouraged to offer combination of disconnector and earthing switch having common
drive system. The arrangement would ensure best mechanical interlocking between
disconnector and an earthing switch, compact design, reduced hardware and thus an overall
improved performance.

Other technical and functional requirements shall remain same as those mentioned for
disconnector and maintenance earthing switch at serial no. 6.1.19 and 6.1.20 respectively.

4.1.22 Fast acting earthing switch

4.1.22.1 General

Fast acting earthing switches can be located at the busbar and at all external HV connections of
feeders (like HV cable or overhead line or transformer connections). The switching capability shall
be 160 A inductive at 15 kV and 10A capacitive at 15 kV. Furthermore it shall withstand the full
making capability.

The fast acting earthing switches shall comply with the following general requirements of fast
acting earthing switches and the latest revision of the relevant IEC specifications.

Fast acting earthing switches shall be single pole or three pole operated, with one motor
operated mechanism per single pole position. They shall also have facilities for emergency
manual operation and the necessary operating handles or hand cranks shall be supplied.
Fast acting earthing switches shall be electrically interlocked to prevent the fast acting earthing
switch from closing on a energized bus section.

All main contacts, male and female, shall either be silver plated or shall have silver inserts.
Each fast acting earthing switch shall open or close only due to motor-driven or manual
operation. The switch contact shall not move due to gravity or other means, even if a part fails.
Once initiated, the motor mechanism shall complete an open or close operation without
requiring the initiating contact to be held closed.

13
4.1.22.2 Technical Data Requirement:

Rated Voltage kV 245


Rated withstand voltage across open contacts:
- Lightning kV 1050 + 245
- Switching kV 850 + 245
- Power frequency kV 530
Rated current A 3150
Rated short-circuit withstand current 1s, (r.m.s.): kA 40
Inductive current switching capability A 160
kV, 15
Capacitive current switching capability A , 10
kV 15
Type of Mechanism Motor
No. of drives per three phase Nos. 3
Closing time ms 50
Control voltage V 220
Number of permissible CO without maintenance Nos. 2000
Number of short-circuit making 40 / 50 kA Nos. 2

4.1.22.3 Operating mechanism

Each phase of the earthing switch shall be equipped with a separate and single phase
operating mechanism. Electric motor for the driving mechanism shall be DC operated.
Mechanisms shall be arranged either mechanically or electrically that all three phases of any
particular fast acting earthing switch operate simultaneously.

All mechanisms shall be equipped with a motor suitable for operation from the auxiliary supply,
and a set of springs for energy storage and closing. Motors shall be suitable for operation at
any voltage between 85% and 110% of the rated auxiliary voltage.

For emergency situations manual operation shall be possible. Handles or hand cranks shall be
provided, together with all necessary operation rods and rod guides.

The auxiliary energy shall be electrically uncoupled from the motor when the switch is operated
manually. The mechanisms shall be arranged for locking in the open and in the closed position.

4.1.22.4 Auxiliary switches

Each fast acting earthing switch shall be furnished with 8 (4 NO and 4 NC) electrically
independent contacts at user©s disposal. The auxiliary switches shall indicate the position of the
switch contacts, and shall be independent of the motor operation.

4.1.22.5 Position Indicating devices and view ports

View ports shall be provided for each fast acting earthing switch to ensure visual inspection of
each switch contact position. Inspection of the main contacts shall be possible using an optical
device which shall also provide lighting of the contact zone to be verified. External mechanically
connected position indicators shall also be provided.

14
4.1.23 Current transformers

4.1.23.1 General

The current transformers shall be supplied in accordance with the following


general requirements and the latest revisions of the relevant IEC or ANSI specifications.
All current transformer cores shall be located outside the enclosure separated from the
primary core. Each current transformer shall be arranged so that the enclosure current
does not affect the accuracy or the ratio of the device or the conductor current being
measured.

They shall be ring type multi ratio with fully distributed secondary windings with relay
accuracy per IEC 185 (1987), incl. IEC 44-6 (1992) or ANSI / IEEE C57.13-1978.

Current transformer secondary cores shall be terminated to shorting terminal blocks.


It shall be possible to test each current transformer without the removal of gas through
the insulated grounding switches. The Principal Parameters shall be as per Annexure-A

4.1.23.2 Position of the Current Transformers and Cores, Ratios and Characteristics

The number and position of the current transformers relative to the circuit-
breakers, disconnecting switches and ground switches shall be as detailed in the
attached single line diagram.

The rating, ratio, accuracy class etc. for the individual current transformer secondary cores
shall be as specified in Annexure-B(i) & B(ii). Where multi-ratio current transformers are
required, the various ratios shall be obtained by changing the effective number of turns on the
secondary winding.

4.1.24 Voltage transformers

4.1.24.1 General

The voltage transformers shall be supplied in accordance with the following


general requirements and the latest revisions of the relevant IEC and ANSI standards.

Each voltage transformer shall be an electromagnetic, dry type SF6 -enclosed single phase
unit with the specified ratings. The Principal Parameters shall be as per Annexure-C

The voltage transformers are to be connected as shown in the attached single line diagram.
Voltage transformers shall be attached to the gas-insulated system in such a manner that
they can be readily disconnected from the system if required for dielectric testing. The metal
housing of the voltage transformer shall be connected to the metal enclosure of the GIS with
a flanged, bolted and gasketed joint so that the transformer housing is thoroughly
grounded to the GIS enclosure. Adequate measures shall be provided to prevent any
unacceptable impact on the secondary control and protection circuits which might result
from very fast transients (VFT) or ferro-resonance.

4.1.24.2 Ratios and Characteristics


15
The rating, ratio, accuracy class, connection, etc. for the voltage
transformers shall be as specified in Annexure-D(i).

4.1.24.3 Secondary terminals, Grounding and Fuses

The beginning and end of each secondary winding and all secondary
taps shall be wired to suitable terminals accommodated in the local
control cabinet for the feeder bay. Fuses shall be also located in the local
control cabinet.

Secondary terminals shall have permanent markings for identification of


polarity, in accordance with IEC. Provisions shall be made for
grounding of the secondary windings inside the local control cabinet.

4.1.24.4 Test conditions for tests at site

Power frequency tests for the completed GIS at site shall be possible
without removing the voltage transformers. The power frequency test
voltage for at site tests shal be 80% of the factory test voltage, for 1
min., and at 100 Hz.

4.1.25 Gas insulated bus duct

The components of the GIS shall be connected by a single phase bus


ducts. The enclosure shall be connected by use of bolted and gasketed
joints. The bus conductor shall be connected with plug in contacts with
silver plated contact surface. The bus system shall be capable of
withstand the mechanical and thermal stresses due to short circuit
currents, as well as thermal expansion and contraction created by
temperature cycling.

4.1.26 SF6/Air bushings

4.1.26.1 General

Outdoor SF6 to air bushings, for the connection between the GIS
and overhead lines or conventional air insulated equipment shall be
furnished where specified.
Bushings shall comply with the relevant IEC standards.
The bushings can be with composite insulators (Silicone rubber) or
with porcelain insulators with all surfaces free from imperfections. The
internal insulation of the bushings can be a resin impregnated paper
winding (RIP body) or compressed SF6-gas. The internal and
external electrical field of the bushings can be controlled by a capacitive
grading body /grading shields.
16
The RIP body must consists of resin impregnated paper insulation
with concentric aluminium layers. The space between the RIP body
and the insulator must be filled with insulating foam compound or
compressed SF6-gas.
Bushings with porcelain insulators must designed to cause
negligible damages in case of porcelain rupture, having either a low
pressure volume or a small SF6-gas volume next to the porcelain.

4.1.26.2 Insulation levels and creepage distances:


The insulation levels are applicable to normal sea level atmospheric conditions.
The creepage
distance over the external surface of outdoor bushings shall not be less than 25
mm/kV.

4.1.26.3 Mechanical forces on bushing terminals:


Outdoor bushings must be capable of withstanding a cantilever force
applied to the terminal of at least 2500 N.

4.1.26.4 Interface definition

The flange and conductor connection between bushing and GIS


component shall be the standard of the GIS supplier.

4.2 Local Control and Operation Circuit


Note: The technical requirements in this specification apply to a
conventional LCC only. A specification for numerical control would
be added.

4.2.1 General

One local control cabinet (LCC) shall be supplied for the local control
and operation of each circuit breaker bay. Each LCC shall contain
the local control, interlocking, operation and indication devices for the
associated GIS feeder bay.

The LCCs shall be free-standing / integrated with the GIS switchgear. A


general arrangement drawing showing the installation position shall be
submitted with the quotation.

The LCCs shall be installed indoors but care must be taken with the
design to ensure that all LCCs are drip and splash proof. The LCCs
shall also be dust and vermin proof. For outdoor installations the LCCs
shall be weather proof.

The control and operation circuits shall be well shielded and with
safety measures to protect operator from touching energized parts.
Power frequency withstand of control circuits shall be 2 kV for 1 minute.
17
4.2.2 Required features for conventional local control cabinets

The LCCs shall be provided with the following features:

a) A mimic diagram showing the single line diagram. Position indicators,


on/off switches for
the HV devices and local / off / remote switches shall be installed on or
adjacent to the
various symbols of the mimic diagram. The following devices shall be
supplied as a
minimum:
- Circuit breaker control switch with two indicating lights.
- Circuit breaker "local-remote" selector switch.
- Disconnect switch control switch with two indicating lights.
- Grounding switch control switch with two indicating lights.
- Mimic bus including symbols according to. the single line diagram.
- Annunciator panel.

b) Any interposing relays and control switches associated with the


circuit breakers,
disconnect switches, grounding switches etc.

c) The alarm and indication devices specified.

d) Fuses and links. These shall be installed in the interior of the LCCs.

e) Terminal blocks for the terminating and marshaling of auxiliary supply


circuits, control,
interlocking, indication and alarm circuits from the GIS and for
cable connections to the remote control room or the owners
control system.

f) Each LCC shall be furnished with a guarded resistance heater


to prevent the internal
equipment from humidity deposit. The heater shall be rated 230
VAC and fed through a two pole fused disconnect switch.

g) A fluorescent lamp and a duplex convenience outlet rated


230 VAC, 15 amps with ground fault interrupter shall be installed in
each LCC.

4.2.3 Wiring Requirements

Each circuit breaker shall have control suitable for operation on 220 V
DC with two electrically independent trip circuits.

The control voltage for the close circuit and the primary and
backup trip circuits shall be supplied through separate miniature
circuit-breakers (MCB).
18
Each disconnect switch shall have control suitable for operation on
220 V DC. The control
voltage for open and close circuits shall be supplied through a separate
MCB.
Alarm contacts shall be provided for monitoring all vital systems of each
circuit breaker and gas
system.

The alarm contacts for the circuit breakers shall be wired to terminals in the LCCs.
All current transformer tap leads shall be terminated on shorting type
terminal blocks in the local control cabinets and shall be accessible at all
times.
All potential transformer leads shall be terminated and fused in the LCCs.

All other devices shall be wired to heavy duty terminal blocks


provided in the local control
cabinet. The terminal blocks shall have no less than 20% spare terminals
per cabinet.
Wiring shall use copper conductors, 1.5 mm2 minimum. For CTs and
PTs the wire size shall
be 4 mm2.

4.2.4 DC Supplies and Circuits

DC supplies as specified will be provided by the owner for all


control, interlocking, alarm, indication and power supply circuits. The
normal maximum and minimum voltage levels that will occur on the
supply are specified.

At least one single fused outlet from the substation DC distribution


board will be provided for each local control cabinet.

The design of all circuits must be such that separately fused or


subfused circuits are always kept electrically separate.

4.2.5 A.C. Supplies and Circuits

A.C. power for heaters and other auxiliary loads will be provided by the
owner by two 220 V, 50 Hz., 3-phase circuits.
The normal maximum and minimum voltages that will occur in the
supply are as specified. All equipment supplied shall be capable of
running continuously or switching the a.c. current within the range of the
normal maximum and minimum voltages specified.

4.2.6 Cable connections within the GIS and their LCC's

All cable connections between the various GIS modules and the
LCCs shall be made by prefabricated multi-core cables with multi-
point plug-in connections on both ends. PTs and CTs shall be hard
19
wired.

All cables shall be shielded and adequate for their application (indoor
/ outdoor). The cables shall be fire retardant and PVC-free.

5.0 TYPE TESTS

The GIS equipment offered should be type tested. Test reports of all the following
tests as per provision in relevant IEC should not be more than seven years old
reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or
witnessed by HVPN or another electric power utility and be submitted by the
successful bidder to HVPNL for approval as per schedule given in Bar Chart:-

1. Tests to verify the insulation level of the equipment and dielectric tests on
auxiliary circuits.
2. Tests to prove the radio interference voltage (RIV) level (if applicable)
3. Tests to prove the temperature rise of any part of the equipment and
measurement of the resistance of the main circuit
4. Tests to prove the ability of the main and earthing circuits to carry the rated peak
and rated short-time withstand current
5. Tests to verify the making and breaking capacity of the included switching
devices
6. Tests to prove the satisfactory operation of the included switching devices
7. Tests to prove the strength of enclosures
8. verification of the degree of protection of the enclosure
9. Gas tightness tests
10. Electromagnetic compatibility tests (EMC)
11. Additional tests on auxiliary and control circuits
12. Tests on partitions
13. Tests to prove the satisfactory operation at limit temperatures
14. Tests to prove performance under thermal cycling and gas tightness tests on
insulators
15. Corrosion test on earthing connections (if applicable)
16. Tests to assess the effects of arcing due to an internal fault

5.1 ROUTINE TESTS:


As per quality assurance program (QAP).

20
5.2 ACCEPTANCE TESTS:

All the acceptance tests as stipulated in the relevant IEC listed below shall be
carried out by the Supplier in presence of HVPNL representative, unless
dispensed with in writing by the HVPNL.
1. Dielectric test on main circuit
2. Tests on auxiliary and control circuits
3. Measurement of the resistance of the main circuit
4. Tightness tests
5. Design and visual checks
6. Pressure tests of enclosures
7. Mechanical operation tests
8. Tests on auxiliary circuits, equipment and interlocks in the control mechanism
9. Pressure test on partitions.

21
6 Switchgear installation

7 Requirements for inspection and maintenance

The operational integrity of the fully enclosed SF6 insulated switchgear is


not subject to external influences, such as pollution, moisture, dust,
etc. As a consequence of this, the shall be practically maintenance-
free.
During inspection, it shall be not necessary to open the GIS
enclosures, thus avoiding interruption of operation.

The number of operations before maintenance is required shall be not less than:

i) for circuit breakers:


2000 mechanical operations
20 interruptions at max. rated fault current.

ii) for disconnect switch and


maintenance earthing switches:
2000 mechanical operations

iii) fast acting earthing switch:


2000 mechanical operations
2 operations at making current capability

8. Tools

The Vendor shall include in his proposal the recommended tools


required for installation, commissioning, operation and maintenance.
The following tools shall be supplied as a minimum:

Tools for gas handling 1 set


Leakage detector 1 piece
SF6 filling and evacuating device 1 set

22
ANNEXURE-A

PRINCIPAL PARAMETERA OF CTs:-


Sr. Item 245 kV
No.

1. Type of CT/installation Single phase, SF6 insulated


2.
3. Suitable for system frequency 50 Hz
4. Highest system voltage (kV rms) 245
5. Current ratio A/A
a. Transformer CT 300-150/0.577-1-1-1-1A
b. Line / Bus Coupler CT 1200-800-400/1-1-1-1-1A
6. Method of earthing Solidly earthed
7. Rated continuous Thermal current 125 % for all taps
8. Ratio taps The tapings shall be only on
secondary winding.
9. Acceptable limit of temperature rise aboveAs per IS:2705 or equivalent IEC
the specified ambient temperature for
continuous operation at rated current.
10. Acceptance partial discharge level at 1.1 As per IS:11322-1985 or equivalent
times the rated voltage IEC
11. 1.2/50 microsecond lightning impulse withstand voltage (kVp)
a. CT 1050

12. 1 minute dry & wet power frequency withstand voltage primary (kV rms)
a. CT 460
13. Power frequency over voltage withstand 3
requirement for secondary winding (kV
rms) (for 1 minute)
14. Rated short time withstand current (kA 40
rms) for 1 second. 23
15. Rated dynamic withstand current (kAp) 100
ANNEXURE B(i)

COREWISE DETAILS OF 245kV Transformer CTs

(300-150/0.577-1-1-1-1A)

NUMBER OF CORES - 5

Core Application Current Output Accuracy Formula for minimum Maximum I.S.F./
No. Ratio (A) burden class knee-point voltage Exciting A.L.F
(VA) as per At CT Secondary Current
IEC 185 resistance at 750C at (mA)
300A tap (Volt)
1 2 3 4 5 6 7 8
1 DIFFERENTIAL 300-150/0.577 - PS 40 (RCT+2) 30ATVk/4 -
PROTECTION
2 REF PROTECTION 300-150/1 - PS 14 (RCT+2) 30ATVk/2 -
3 OVER CURRENT 300-150/1 25 5P - - 10
PROTECTION
4 BUSBAR PROTECTION 300-150/1 - PS 40 (RCT+4) 30ATVk/2 -
(FOR LOW IMPEDANCE
SCHEME)

5 METERING 300-150/1 25 1.0 - - <5

NOTE : 4th core for bus bar protection has been kept in view of general design
being followed in HVPNL. In case this CT is used on a sub station having high
impedance bus bar protection scheme or no bus bar protection scheme then this core
shall be short-circuited at site.

24
ANNEXURE B(ii)

COREWISE DETAILS OF 245kV LINE/BUS COUPLER CTs

(1200-800-400/1-1-1-1-1 A)

NUMBER OF CORES – 5
Core Application Current Output Accuracy Formula for minimum Maximum Instrument
No. Ratio (A) burden class knee point voltage At CT Exciting Security
(VA) as per Secondary resistance at Current factor
IEC 185 750C at 800Atap (Volt) (mA)
1 2 3 4 5 6 7 8
1. MAIN–I 1200-800- - PS 80(RCT+9) 80AT Vk -
DISTANCE 400/1
PROTECTION
2. MAIN–II 1200-800- - PS 80(RCT+9) 80AT Vk -
DISTANCE 400/1
PROTECTION
3. BUS 1200-800- - PS 100(RCT+4) 30AT Vk/2 -
DIFFERENTIAL 400/1
MAIN
4. BUS 1200-800- - PS 100(RCT+4) 30AT Vk/2 -
DIFFERENTIAL 400/1
CHECK
5. METERING 1200-800- 40 1.0 - - ISF<5
400/1

NOTE :
1. 5 cores of 245kV line CT have been kept in view of general design being followed in
HVPNL.

2. In case this CT is used exclusively for bus bar protection purpose on a transformer
circuit at sub station having high impedance bus bar protection scheme then core no 1,2
& 5 shall be short circuited at site.

3. In case this CT is used for feeder circuit on a sub station having low impedance bus bar
protection scheme then core no. 4 shall be short circuited at site and where there is no
bus bar protection scheme core no. 3 & 4 shall be short circuited at site .

25
ANNEXURE-C

PRINCIPAL PARAMETERS of PTs:-

Sr. Item Specification


No. 245kV
1. Type/Installation Single Phase, SF6 insulated
2. Highest system voltage (kV rms) 245
3. Suitable for system frequency 50Hz
4. Voltage ratio
a) Rated primary voltage (kV rms). 220/√3
b) Secondary voltage (volts). 110/√3
5. PT Core I,II

6. Method of earthing the system Solidly Earthed


7. 1.2/50 microsecond lightning 1050
impulse withstand voltage (kVp)
8. 1 Minute dry & wet power 460
frequency withstand voltage
primary (kV rms)
9. Rated voltage factor 1.2 continuous and 1.5 for 30 seconds
10. One minute power frequency
withstand voltage for secondary 3.0
winding (kV rms)
11. Max. temperature rise over As per IS:3156 or equivalent IEC
ambient of 50°C

26
ANNEXURE D(i)

COREWISE DETAILS OF 245kV POTENTIAL TRANSFORMER (PT)

Sl. Particulars Requirement


No.
1. Rated Primary voltage 220/√3kV
2. Type Single phase
3. No. of Secondaries 2
4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds
5. Rated voltage (volts) Secondary-I Secondary-II
110/√3 110/√3
6. Application Protection & Protection
Measurement
7. Accuracy 1/3P 3P
8. Output burden (VA) 150 50
9. Percentage voltage error & As per ISS/IEC
phase displacement
(minutes) for respective
specified accuracy classes.

Note:- Each winding shall fulfil its respective specified accuracy requirement within its
specified output range whilst at the same time the other winding has an output of any
value form zero to 100% of the output range specified for the other winding in line
with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC.

27
SECTION-3
CHAPTER-1
TECHNICAL SPECIFICATION FOR
100 MVA, 220/66 kV POWER TRANSFORMER
1.00 SCOPE:
a) This specification covers the design, manufacture, assembly testing at
manufacturer’s works before despatch, supply and delivery at site as per
schedule of Requirement of 100 MVA, 220/66 kV Power Transformer.
b) All drawings, schedules and annexures appended to this specification shall
form part of the specification and supplement the requirements specified. The
equipment/materials offered by the Bidder shall be complete in all respects
and, whether called for specifically or not, all accessories, hardware and
services required for normal satisfactory operation of the system shall be
deemed to be included in unit rates quoted. Design and manufacture shall
also be such that equipment/ accessories of the same type and rating would
be interchangeable.
Specific reference in this specification and documents to any material by
trade name, make or catalogue number shall be construed as establishing
standard of quality and performance and not as limiting competition. All
equipment/ accessories offered shall also be of proven design and
manufacture. The make of all accessories and hardware shall be subject to
HVPNL’s approval.
2.00 Codes & Standards:
All standards, specifications and codes of practice referred to herein shall be the
latest editions including all applicable official amendments and revisions as on date
of opening of bid.
IS:5 Colour for ready mix paints.
IS:325 Three phase induction motors.
IS:335 New insulating oils for transformer.
IS:375 Marking & arrangement of Switch-gear Bus-bars main
connections and auxiliary wiring.
IS:1866 Code of practice for maintenance of insulation oil
IS:2026 Specification for Power Transformers.
&IEC:76
IS:2099 Bushing for alternating voltages above 1000 volts
& 3347
IS:2147 Degree of protection provided by enclosures for low voltage
switchgear & control gear.
IS:2705 Current transformer
IS:3637 Gas operated relay.
IS:3639 Fittings and accessories for Power Transformers.
IS:6600 Guide for loading of oil immersed transformers.
&IEC-354
IS:8468 On load tap changer.
&IEC:214
IS:5561 Electricity power connectors.
IS:617 Aluminium Alloy grade.
IS:2629 Recommended practice for hot-dip Galvanising.
IS:8478 On load tap changer application guide.
IS:8603 : Dimensions for porcelain transformer bushings for use in heavily
polluted atmosphere (36 kV Class). Dimensions for oil filled porcelain
transformer bushings for use in medium polluted atmosphere.

-1-
IS:9434 Guide for sampling and analysis of free and dissolved gas in oil filled
equipment.
IS:10028 Code of practice for selection, installation and maintenance of
transformers.
IS:12676 Dimensions for OIP insulated condenser bushings.
CBIP Manual on transformer.
Equipment complying with other internationally accepted standards would also be
considered if these ensure performance and constructional features equivalent or
superior to standards listed above. In such a case the Bidder shall clearly indicate
the standards adopted, furnish a copy in English of the latest revision of standard
alongwith copies of all official amendments and revisions in force as on date of
opening of bid and clearly bring out the salient features for comparison.
3.00 CLIMATIC CONDITIONS:
3.1 Max. Temprature 50 C
3.2 Min. Temprature -2.5 C
3.3 Max. relative humidity 100%
3.4 Min. relative humidity 26%
3.5 Average number of rainy days per annum Nearly120 Days.
3.6 Average annual rain fall 900mm
3.7 Average number of dust strom days per annum 35
3.8 Isoceraunic level 45
3.9 Max Wind pressures. 195kg/sqmt.
3.10 Altitude above mean sea level. Less than 1000 mt.
4.00 TYPE AND RATING:
4.1 The transformer shall be of 3 phase oil immersed three legged core type with
ONAN/ONAF/OFAF cooling suitable for outdoor service as step down
transformer.
4.2 The ratings and other characteristics which are not covered elsewhere shall
be, as detailed in following clauses:
4.2.1 Max. Continuous capacity:
a) ONAN 50 MVA
b) ONAF 75 MVA
c) OFAF 100 MVA
4.2.2 Number of phases 3

4.2.3 Frequency 50 Hz(±5%)


4.2.4 Rated Voltage:
a) HV side 220 Kv
b) LV sid 66 kV

4.2.5 Max. System Voltage


a) HV Side 245kV
b) LV Side 72.5kV
4.2.6 Connections:
a) HV side Star with neutral solidly earthed
b) LV side ----------------do----------------
4.2.7 Vector group YYO

-2-
4.2.8 Tapping On load tappings at neutral end
of 220 kV side for variation +10
% to -10% in steps of 1.25%
each .

4.2.9 Rated short duration Power frequency withstand Voltage


a) HV Side 395kV rms
b) LV Side 140kV rms
c) Neutral 70kV rms

4.2.10 Rated lightning impulse withstand Voltage


a) HV Side 950kV Peak
b) LV Side 325kV Peak
c) Neutral 170 kV Peak
4.2.11 %age Impedance 12.5% at 100MVA base

4.2.12 B.I.L for Bushings


a) HV Side 1050kV Peak/460kV rms
b) LV Side 325kV Peak/140kV rms
c) Neutral 170 kV Peal/ 70 kV rms

4.2.13 Creepage:
a) Total 25mm per kV corresponding to
highest system voltage
b) Protected 50% of the total creepage distance

5.00 GENERAL DESIGN OF TRANSFORMER:


5.1 The transformer and accessories shall be so designed as to facilitate
inspection, cleaning and repairs. The requirement of Indian Electricity Rules
shall be kept in view.
5.2 The design shall ensure satisfactory operation under severe working
conditions due to fluctuating load of steel furnaces and voltage variations in
the system including those, due to short circuits. The transformer shall be
designed as to minimize the risk of accidental short circuits caused by
animals, birds or vermins.
The design shall incorporate every reasonable precaution and provision for
the safety of all those concerned in the operation and maintenance of the
equipment keeping in view the requirements of Indian Electricity Rules.
5.3 All material used shall be of the best quality and of class most suitable for
working under specified conditions and shall withstand the atmospheric
conditions and temperature variations without undue deterioration or
distortion or setting up of undue stress in any part thereof.
5.4 Cast iron shall not be used for any parts other than the radiator valve bodies.
5.5 Corresponding parts liable to replace shall be interchangeable.
5.6 All taper pins to be used in the mechanism shall be split types as per latest
edition of IS: 2393.

-3-
5.7 All mechanism should be rust and corrosion proof. Means shall be provided
for lubrication of moving parts not immersed in oil.
5.8 The construction shall be such as to avoid air or water pockets. Special care
shall be exercised to reduce noise and vibration to the minimum level.
5.9 Steel bolts of suitable finish will be used for diameters above 6mm. Brass
bolts or studs used for electrical connections shall not be of less than 6mm
diameter. On outdoor equipment, all bolts, nuts & washers in contact with
current carrying non-ferrous parts shall be phosphor bronze.
5.10 All nuts, bolts and pins shall be locked except those, which are external to the
transformer. If bolts and nuts are so placed as to be inaccessible by means of
ordinary spanners, the Bidder shall provide suitable special spanners.
5.11 Labels shall be provided for all apparatus like relays, switches, fuses, etc.
housed in any cubicle or marshalling kiosks. These shall be of incredible
material with matt/satin finish and permanent lettering. Labels mounted on
black surface shall have white letters and danger notices shall have red
lettering on a white background. The labels shall be secured by means of
brass screws or rust protected steel screws.
5.12 Surface in contact with oil shall not be galvanized or cadmium plated.
5.13 Before painting, all ungalvanised parts shall be cleaned, made free from rust,
scale and grease and external rough surfaces smoothened (filled with metal
deposition). The interior of the tank and other oil filled chambers shall be
cleaned by shot blasting or any other suitable method.
5.14 All external surfaces shall be given three coats of paints except for nuts, bolts
and washers which may be given one coat after assembling of transformer at
works. The final coat shall be a glossy oil and weather proof, non-fading paint
of shade 631 of IS: 5
5.15 The interior of mechanism chambers and kiosks shall be given 3 coats of
paint, the final coat being of a light coloured anti-condensation mixture.
5.16 The outer most radial spacers of the winding shall be locked in position by
means of vertical strips so that the same cannot fall off/get displaced.
5.17 The manufacturers must ensure proper & complete tightening of the nuts of
the coil clamping bolts. The nuts of all the coil clamping bolts will be tightened
to designed value & the job be carried out with torque spanners.
The devices used for locking the nuts of coil clamping bolts must be of such a
quality and such care should be taken first in tightening. The nuts and next in
locking them in position that the arrangement does not become loose due to
stresses caused by short circuits and fluctuating loads etc.
5.18 The noise level shall not be more than 80 db.
5.19 The transformers shall be designed to have short circuit rating of five
seconds as per IS: 2026. The thermal ability to withstand short circuit shall
be judged by calculation to be supplied above in the tender. The dynamic
ability to with stand short circuit shall be demon started by test in case facility
available in India other-wise calculations will be supplied day with contract
drawing.
5.20 Foundation bolts and nuts shall be supplied along with the transformer
(Preferably at the time of call for inspection) so that transformer plinth is ready
by the time transformer is received by the consignee.

-4-
6.00 INSULATING OIL:
Sufficient insulating oil conforming to IS-335/93 (latest edition) shall be supplied for
first filling of each transformer plus 10% extra oil of the total quantity of oil. Particular
attention shall be paid to deliver the oil at site free from moisture and of uniform
quality through out in non-returnable steel drums. The quantity of oil for first filling of
each transformer shall be stated in tender, alongwith trademark of the oil to be
supplied. Use of inhibitors in oil shall not be resorted to.
7.00 LIMIT OF TEMPERATURE RISE
7.1 With the above climatic conditions, given in clause-3 each transformer shall
be capable of operating continuously on any tap at their normal rating without
exceeding following temperature rises:
i) 50o C in oil by thermometer.
ii) 55o C in winding by resistance.
iii) Temperature of hot spot in winding not to exceed 98oC when calculated
over max. annual weighted average temperature of 32o C.
7.2 The limits of temperature rise mentioned above will have to be satisfied by the
manufacturer by carrying out the heat run test at the lowest negative tap.
This test shall be carried out by feeding 1.1 times the total losses at 75o C at
highest current tap.
7.3 OVERLOAD CAPACITY & CONTINUOUS RATING.
The safe over load capacity of the transformer and the duration of overload
under maximum temperature conditions without any damage to the winding or
harmful effects on the insulation shall be clearly stated in the tender which
must be as per IEC-354/IS: 6600, guide for loading of oil immersed
transformer.
8.00 IMPEDANCE:
The transformer shall have 12.5% impedance on 100 MVA base with tolerance as
per IS: 2026/Part-1 (1983). Impedance shall include positive and zero sequence and
shall be expressed in terms of the branches of the star connected equivalent
diagram, all on the same KVA base and range shall be given for each branch of the
equivalent circuit in turn. Percentage tolerance allowed at extreme tap should be as
applicable to normal tap.
9.00 FREQUENCY:
The transformer shall be suitable for continuous operation with a +/- 5% frequency
variation from a normal of 50 Hz without exceeding the temperature rise as specified
in Clause 7.1 above.
10.00 FLUX DENSITY:

10.1 The primary voltage variation, which may effect the flux density at every tap,
shall be kept in view while designing the transformer.
10.2 The transformer should be so designed that the working flux density should
not exceed 1.6 Tesla (16000 Lines per sq. cm) at normal voltage, frequency
& ratio. Tenders with higher flux density than specified shall not be
considered.

-5-
The Bidders should indicate the continuous allowable maximum flux density
as well as for time interval of one minute and five seconds. The limit of flux
density at which core material used by them saturates will also be stated in
the tender. The name of core material must be mentioned in the tender. The
successful Bidder shall be required to furnish magentisation curve of the core
material, design calculations and such other data/documents deemed fit by
the HVPNL for being satisfied that flux density is as desired.
NOTE: The above flux density has been specified to meet with the over fluxing of the
core due to temporary over voltage of the orders of 25% for one minute and
40% for five seconds that may appear in abnormal conditions such as the one
obtained following sudden loss of large loads.
11.00 CORE:
11.1 The core shall be constructed from the laminations of high grade cold rolled non-
aging, grain oriented silicon steel known as M4 High B Grade or superior grad CRGO
steels of maximum 0.27mm or less lamination thickness especially suitable for
transformer core.
11.2 The design shall be such as to avoid static discharge short circuit paths within itself
or to earthed clamping devices and production of flux component at right angle to the
plane of the lamination, which may cause local heating.
11.3 Adequate oil ducts shall be provided in the core for cooling. Tinned copper strip
bridging pieces shall be used for maintaining electrical continuity wherever the
magnetic circuit is provided into pockets by such ducts or insulating material thicker
than 0.25mm.
11.4 There should be no movement of the core assembly relative to the tank during
transport as well as in service due to sudden jerks caused by short circuits and
fluctuating loads.
11.5 Adequate lifting lugs shall be provided to enable core and winding to be lifted.
11.6 The insulation structure for the core to bolts and core to clamp plate shall be such as
to withstand a voltage of 2000V AC for one minute

12.00 SUPPRESSION OF HARMONICS:


The transformer shall be so designed as to suppress the harmonics voltage specially
the 3rd & 5th, to eliminate wave form distortion and interference with communication
circuits due to high frequency disturbances. Limiting percentage of harmonics at
normal voltage and at maximum system voltage shall be stated in the tender.
The transformer shall be so designed as to withstand thermal and electro-magnetic
stress under severe short-circuits where the fault level on 220 KV, 66 KV V bus are
of the order of 20,000, 5,000 MVA respectively.
13.00 WINDING:
13.1 The 220/66 kV windings shall have graded insulation whereas the neutral points shall
be insulated as amended in IS:2026.
13.2 The transformers shall be capable of operation without danger on any particular
tapping at the rated KVA when the voltage may vary by ± 10% of the voltage
corresponding to the tapping.
13.3 The windings and connections as well as the insulating material shall not soften ooz,
shrink or collapse during service.
13.4 No strip conductor wound on edge shall have a width exceeding six times its
thickness. The conductors shall be transposed at sufficient intervals to minimize eddy
currents and equalize the current and temperature distribution along the windings.

-6-
13.5 The windings and connections shall be properly brazed to withstand shocks during
transportation or transient conditions during service.
13.6 Adequate pre-shrinkage of the coil assembly using pre-compressed press board
material having low moisture content for the radial spacer blocks shall be ensured by
the manufacturers so that there is no displacement of the radial spacer blocks due to
frequent short circuits on the transformers.
13.7 All windings after being wound and all fibrous hygroscopic materials used in the
construction of the transformer shall be dried under vacuum and impregnated with
hot oil.
In addition to this the drying process be sufficiently extended for proper stabilization
of the coil assembly. More than one cycle of soaking in oil followed by retightening of
the coil assembly should be adopted.
13.8 The coil clamping rings wherever used shall preferably be of flat insulated steel
laminations. Axial laminated material except bakelised paper shall not be used.
13.9 The clamping arrangement shall exert equal pressure on all columns of spacers of
the transformer windings built of sections or disc-coils separated by spacers. In no
case, spiral winding will be used either for HV or LV windings.
13.10 The radial spacer blocks must be made of pre-compressed pressboard material,
which will not soften while in contact with oil or fray out into fibers or edges. The
slots should be so dimensioned that the blocks will not come out of the slots.
Uniform distribution of coil clamping force shall be designed by using an adequately
large number of coil clamping bolts and by transferring the clamping force from
clamping bolts to the clamping plates through intermediate members which can
spread the clamping force over a large area.
13.11 All joints shall be brazed/crimped considering the vibrations due to short circuits and
load fluctuations.
14.00 CURRENT DENSITY:
The HVPNL shall be at liberty to inspect built-up winding for its quality, weight of
copper, insulation and overall weight of coil assembly. The size of conductor used
for different windings shall also be checked during stage inspection to check the
current density . The transformer shall be so designed that the current density of all
the windings and the regulating winding at the lowest tap should not exceed 250
A/cm.Sq.
15.00 INTERNAL EARTHING ARRANGEMENTS:
15.1 All metal parts of the transformer except individual core laminations, core bolts and
individual clamping plates, shall be maintained at a fixed potential
15.2 The earthing connections shall have a minimum area of cross-section of 0.8 sq. cm.
except connections inserted between the laminations and in close terminal
connection with them which may have area of cross section of 0.2 sq. cm.
15.3 The top main core clamping structure shall be connected to the tank body by a
copper strip. One or more of the following methods shall earth the bottom clamping
structure.
(a) By connection through vertical tie-rods to the top structure.
(b) BY direct metal-to-metal contact with the tank base maintained by the weight
of the core and windings.
(c) By a connection to the top structure on the same side of the core as the main
earth connection to the tank.

-7-
15.4 The magnetic circuit shall be earthed to clamping structure by a link connection from
the top yoke near the bridging pieces referred to in Cl.11.3 in the side of main earth.
An inspection hatch shall be provided over the link in the tank cover.
15.5 For the individual insulated section of the magnetic circuit separate links shall be
provided. The bridged construction as per Cl.11.3 shall not be taken as being of
sectional construction.
16.1 TANK CONSTRUCTION
16.1.1 The tank shall be fabricated of a suitable grade steel and strong enough to allow
the lifting of complete transformer with oil by means of a crane or jacks and
transported to site without over-straining the joints etc.
16.1.2 The main tank body shall be capable of withstanding a vacuum of 100.64 kN/m2
(760mm of Hg.)
16.1.3 The base shall be so designed as to allow the transformer to be moved by skidding
without any injury.
16.1.4 All channeled constructions and stiffeners shall be designed to avoid retention of
water.
16.1.5 The transformer shall preferably be of bell type tank with the joint 500 mm above
the bottom of tank.
16.1.6 The tank construction shall be free of air pockets. Where such pockets cannot be
avoided, vent pipes of 15 mm internal diameter shall be provided to vent gases into
the main expansion pipes. In case of short branch pipes, however, minimum
diameter may be taken as 6mm.
16.1.7 All joints other than those, which may have to be broken, shall be welded. When
required they shall be double welded. All bolted joints to the tank shall be fitted with
suitable oil tight gaskets, which shall give satisfactory service under the operating
conditions and guaranteed temperature rise conditions. Special attention shall be
given to the methods of making hot oil tight joints between the tank and the cover
and also, between the cover and the bushings and all other out-lets to ensure that
the joints can be remade satisfactorily at site and with ease by semi-skilled labour.
16.1.8 Suitable lifting lugs for lifting the transformer filled with oil shall be provided on the
tank.
16.1.9 Four jacking lugs shall be provided to enable the transformer complete with oil to
be lifted or lowered by means of jacks. The lugs shall be fitted at a minimum height
(excluding under base if detachable) of 300mm for transformer upto 10 tons weight
and of 500mm for transformer above 10 tons weights.
16.1.10 The transformer shall be provided with detachable steel flanged wheels of 380mm
diameter and suitable for moving transformer complete with oil. These shall be
suitable for 2 rails of 1676 mm gauge alongwith longer axis and 2 rails of 3353 mm
along with shorter axis.
16.2 TANK COVER
16.2.1 The tank cover shall be of bolted type and of adequate strength so as not to distort,
when lifted. Suitable inspection cover shall be provided with lifting arrangements to
give access to bushings, winding connections or testing the earth connections. The
weight of each inspection cover shall not exceed 25 Kg.
16.2.2 Pockets shall be provided in the position of Max. oil temperature at CMR for fitting
a thermometer and for bolts of oil and winding temperature indicators. The
thermometer pockets shall be fitted with a captive screwed cap to prevent ingress
of water.
16.2.3 Suitable No. of jacking bolts shall be provided on tank cover, inspection
covers/windows including OLTC.

-8-
16.3 CONSERVATOR TANK, OIL GAUGE AND BREATHER
16.3.1 An adequate conservator tank complete with sump and drain valves shall be
provided in such a position as not to obstruct the electrical connections to the
transformer.
16.3.2 If the sump is formed by extending the feed pipe inside the conservator, this
extension shall be atleast 25mm.
16.3.3 One end of the conservator shall be bolted type to facilitate cleaning.
16.3.4 The conservator shall be provided with a magnetic oil level gauge.
16.3.5 The oil connections from the transformer tank to the conservator shall be at rising
angle of 3 to 9 degrees to the horizontal upto Buchholz relay. The inside diameter
of the pipe shall be 80mm. The Buchholz relay will have suitable valves on its both
side so as to facilitate its testing at site as well as cut off oil supply to the
transformer.
16.3.6 The conservator shall be provided with oil preservation system, which should be
suitable either to remove moisture continuously from air entering the air space with
which they are connected or may not allow direct contact of atmospheric air with oil
during operation, in addition to silicagel-breather.
16.4 VALVES:
16.4.1 The transformers shall be provided with 2 No. filter valve each of 50 mm size one
mounted close to the top of the main tank & the other close to bottom of the tank
oil circulation and one drain valve of 80mm size with plug. The conservator shall
have drain plug of 25mm size.
16.4.2 Two robust sampling valves with spouts suitable for taking samples of top, and
bottom oil. The top sampling valves shall be brought down by internal pipe
connections. Suitable name plates shall be affixed to the sampling valves. The
sampling device shall not be fitted on the filter valve.
16.4.3 Two air release plug of 15mm shall be provided.
16.4.4 Plugs shall be supplied for all valves opening to atmosphere.
16.4.5 All valves shall be of gun metal and comply with the latest edition of IS: 3639.

16.5 PRESSURE RELIEF DEVICES:


A suitable pressure relief device shall be provided for rapid release of any pressure
in transformer which may endanger the equipment. The device (s) shall operate at
static pressure less than hydraulic test pressure for transformer tank of OLTC
chamber. If the device is mounted on tank cover, it shall be fitted with a skirt
projecting 25mm inside the tank and of such construction as to avoid gas
accumulation.
In addition to pressure relief device(s) the provision of explosion vent should also
be made and the diaphragm shall be situated above max. oil level or second PRD
on the opposite side of first PRD be provided.
16.6 EARTHING TERMINALS:
16.6.1 Two earthing pads suitable for connecting 50x8mm mild steel flat shall be provided
at positions close to the two diagonally opposite bottom corners of tank. These
grounding terminals shall be suitable for bolted connection. Two earthing terminals
shall also be provided each on marshalling box and any other equipment mounted
separately. The earthing terminal should be capable of carrying full low voltage
short circuit current of transformer for four seconds.

-9-
16.7 JOINTS AND GASKETS: -
16.7.1 All gaskets used for making oil tight joints shall be of granulated cork bonded with
synthetic rubber. Metal tops shall be provided for preventing over compression
wherever compressible gaskets are provided.
16.8 RATING AND DIAGRAM PLATES:
16.8.1 Each transformer shall carry a diagram plate showing internal connections, voltage
vector relationship of different windings, plan view of the transformer showing
physical relationship of the terminals and no load voltage and corresponding current
for each tap.
16.8.2 Each transformer shall be provided with a rating plate data as specified in IS: 2026
or equivalent international standard.
16.8.3 The transformer shall carry a valve schedule plate shorting the location and
function of all values and air release cock on plugs. This plate shall warn operators
to refer to the maintenance instructions before applying the vacuum treatment for
drying.
16.8.4 I.R. values alongwith oil temperature at the time of testing at manufacturer's works
shall be indicated on rating plate or separate plate, to be provided on transformer.
16.9 THERMOSYPHON FILTER ARRANGEMENT

Thermosyphon filter arrangement shall be provided on the transformer for preserving


the quality of Transformer Oil. The filter assembly shall be mounted on the
Transformer as well as ground supported and connected with pipes and shut off
valves. Suitable instructions required to be followed for commissioning,
dismantlement & maintenance of the filter arrangement, re-generation and storage of
the adsorbent etc. must be included in the instruction manual. A detailed drawing
showing internal arrangement, shall also be required to be submitted. Suitable
capacity pump (along with motor) shall also be provided to boost circulation of oil.
The pump and motor should not be in main pipe line. It should be in bypass pipe line
having suitable valve to isolate from main pipe line. The main pipe line should have
two shut off valves at the bottom.

NOTE : - The pump and motor should be weather proof(Flow well Type).

The oil & absorbent capacity required in the Thermosyphon Filter is as under : -

(i) Quantity of oil 2.0% of total oil by weight.


(ii) Quantity of absorbent 1.25% of total oil by weight.
NITROGEN INJECTION FIRE PROTECTION CUM EXTINGUISHING SYSTEM
FOR 100 MVA TRANSFORMER
The Bidder shall provide the nitrogen injection fire protection cum extinguishing
system. The fire protection system using nitrogen as fire quenching medium is
required for the 100 MVA 220/132 kV T/F NIFPES shall act as fire preventer by
preventing transformer oil tank explosion and possible fire in case of internal faults. In
the event of fire by external causes such as busing fire, OLTC fires, fire from
surrounding equipment etc, it shall act as a fast and effective fire fighter. NIFPES
shall accomplish its role as fire preventer and extinguisher without employing water
and/or carbon dioxide. Fire shall be put out within max. 3 minutes of system
activation and within max. 30 seconds of commencement of nitrogen injection.
17.1 Activation of NIFPES
Mal-functioning of fire prevention/extinguishing systems is their major shortcoming
which leads to interruption in power supply. The Bidder shall ensure that the chances
of malfunctioning of NIFPES are practically nil. To achieve this objective, the Bidder
shall work out his scheme of activating signals which, while preventing mal-

- 10 -
operation, should not be too rigorous to make the operation of NIFPES impracticable
in case of actual need. Transformer isolation shall be the mandatory pre-requisite for
activation of the system in automatic mode or remote mode in the control room. In
addition, at least following electrical-signals shall be provided in series for activating
NIFPES.

17.1.1 Auto Mode


a) For prevention of fire: i) Differential relay operation
ii) Buchholz relay paralleled with
pressure relief valve
iii) Tripping of all connected breakers is
a pre-requisite for initiation of system
activation.
b) For extinguishing fire i) Fire detector
ii) Buchholz relay paralleled with
pressure relief valve
iii) Tripping of all connected breakers is
a pre-requisite for initiation of
system activation.
17.1.2 Manual Mode (Local/Remote) : Tripping of all connected breakers is
pre- requisite for initiation of system
activation.

17.1.3 Manual Mode (Mechanical) : Tripping of all connected breakers is a


pre- requisite for initiation of system
activation.
17.2 General description of NIFPES

17.2.1 Schematic of the system


NIFPES should be a stand alone dedicated system for oil filled transformer. It
should have a fire extinguishing (F.E.) cubicle placed on a plinth at a distance of 6-10
mtrs. from the transformer. The F.E. cubicle may be connected to the transformer oil
tank (near its top) and to the oil pit (of capacity approx. equal to 10% of transformer
oil tank) from its bottom through oil pipes with gate valves. The F.E. cubicle should
house a pressurised nitrogen cylinder connected to the transformer oil tank (near its
bottom). Cable connections are to be provided from signal box placed on the
transformer to the control box in the control room and from control box to F.E.
cubicle. Fire detectors placed at the top of transformer are to be connected in parallel
to the signal box. The signal box may be connected to a pre-stressed non-return
valve fitted between the conservator tank and Buchholz relay. Control box is also to
be connected to relay panel in control room for system activation signals.

17.2.2 Operation
On receipt of all activating signals, drain of pre-determined quantity of oil commences
thus removing high temp. top oil layer. Simultaneously nitrogen is injected under high
pressure at a pre-fixed rate, stirring the oil thus bringing the temperature of top oil
layer down. Nitrogen occupies the space created by oil drained out and acts as an
insulating layer between the tank oil and fire on top cover. Pre-stressed non-return
valve blocks oil flow from conservator tank, thus isolating it & preventing aggravation
of fire.

17.2.3 System components


Broadly, NIFPES shall consist of the following components. It is emphasized that all
components, irrespective of their exclusion in the details given below, necessary for
fast reliable and effective working of NIFPES shall be considered within the scope of
supply.

- 11 -
17.2.4 Fire Extinguishing cubicle

It shall be made of 3 mm thick steel sheet, painted dark red from inside and outside
with hinged split doors fitted with high quality tamper proof lock. It shall be complete
with the base frame and the following:-

• Nitrogen gas cylinder with regulator and falling pressure electrical contact
manometer.
• Oil drain pipe with mechanical quick drain valve.
• Electro mechanical control equipment for oil drain and pre-determined
regulated nitrogen release.
• Pressure monitoring switch for back-up protection for nitrogen release.
• Limit switches for monitoring of the system.
• Flanges on top panel for connecting oil drain and nitrogen injection pipes for
transformer.
• Panel lighting (CFL type)
• Oil drain pipe extension of suitable sizes for connecting pipes to oil pit.

17.2.5 Control box

Control box for monitoring system operation, automatic control and remote operation,
with following alarms indication, light switches, push buttons, audio signal, line fault
detection suitable for tripping and signaling on 110V DC/220V DC supply.

• System on*
• PNRV open*
• Oil drain valve closed*
• Gas inlet valve closed*
• PNRV closed^
• Fire detector trip^
• Buchholz relay trip^
• Oil drain valve open^
• Extinction in progress^
• Cylinder pressure low^
• Differential relay trip^
• PRV operated^
• Transformer trip^
• System out of service
• Line fault fire detector
• Line fault differential relay
• Line fault buchholz relay
• Line fault PRV
• Line fault transformer trip
• Line fault PNRV
• Auto / Manual/Off
• Extinction release on
• Extinction release off
• Lamp test
• Visual/Audio alarm
• Visual/Audio alarm
• Visual/audio alarm for DC supply fail

The signals marked (*) shall be in the top most row of control box panel. The
signals marked (^) shall follow next.

- 12 -
17.2.6 Pre-stressed non return valve (PNRV)

PNRV is to be fitted in the conservator pipe line between conservator and Buchholz
relay. It shall have the proximity switch for remote alarm, indication and with visual
position indicator. The PNRV should be of the best quality because malfunction of
PNRV shall be of serious consequence as its closing leads to stoppage of breathing
of transformer.

17.2.7 Fire detectors


The system shall be complete with adequate number of fire detectors fitted on the top
of oil tank, OLTC/OFF ckt. tap changer rated for 141 degree C for heat sensing each
fitted with two no. cable glands (water proof/weather proof).

17.2.8 Signal box


It shall be fitted on the transformer for terminating cable connections form PNRV and
fire detectors and for further connection to the control box.

17.2.9 Cables
Fire survival cables, able to withstand 750 degree C, 4 core x 1.5 mm sq. for
connection of fire detectors in parallel shall be used.

Fire retardant low smoke (FRLS) cable 12 core x 1.5 mm sq. for connection between
transformer signal box/marshalling box to control box and control box to fire
extinguishing cubicle shall be used.

Fire retardant low smoke cable 4 core x 1.5mm sq. for connection between control
box to DC supply source and fire extinguishing cubicle to AC supply source, signal
box/marshalling box to pre-stressed non return valve connection on transformer shall
be used.

17.2.10 Pipes
Pipes, complete with connections, flanges, bends tees etc. shall be supplied along
with the system.

17.3 Other items

a. oil drain and nitrogen injection openings with gate valves on transformer tank at
suitable locations.
b. Flanges with dummy piece in conservator pipe between Buchholz relay and
conservator tank for fixing PNRV.
c. Fire detector brackets on transformer top cover.
d. Spare potential free contacts for system activating signals i.e. differential relay
buchholz relay, pressure relief valve, transformer isolation (master trip relay).
e. Pipe connections between transformer to fire extinguishing cubicle and fire
extinguishing cubicle to oil pit.
f. Cabling on transformer top cover for fire detectors to be connected in parallel and
inter cabling between signal box to control box and control box to fire extinguishing
cubicle.
g. Mild steel oil tank with moisture proof coating and sheet thickness of minimum 5 mm,
with watertight cover, to be placed in the oil pit. This tank shall be provided with the
manhole, air vent pipe through silica gel breather, drain valve and a spare gate valve
at the top.
The capacity of tank shall be 10,000 ltrs. and shall be provided as each S/Stn. The
location of the tank shall be approved by the HVPNL. All the Transformers to be fitted
with NISPEF at that S/Stn. shall be connected through suitable piping arrangement to
this common tank.
h. DC-DC converter 220-110V DC (optional, incase 110V, supply is not available.)

- 13 -
i. Gate valves on oil drain pipe and nitrogen injection pipe should be able to withstand
full vacuum. A non-return valve shall also be fitted on nitrogen injection pipe between
transformer and gate valve.
j. The F.E. cubicle shall be painted with post office red colour (shade 538 of IS-5). All
the exposed parts i.e. pipes, supports, signal box etc shall be painted with enameled
paint.
k. Civil works of F.E. cubicle and oil pit are in the scope of bidder.

17.4 Interlocks

It shall be ensured that once the NIFPES gets activated manually or in auto mode, all
the connected breakers shall not close until the system is actually put in OFF mode.
Also PNRV shall get closed only if all the connected breakers are open.

17.5 Technical particulars

17.5.1 Fire extinction period

On commencement of nitrogen injection : Max. 30 secs.


From the moment of system activation to : Max. 3 mins.
Complete cooling.
Fire detectors heat sensing temperature : 1410C
Heat sensing area : 800mm radius
Pre-stressed non return valve setting for : minimum 60 ltr. Per operation.min.
Capacity of nitrogen cylinder : minimum 68 ltr. water cap.
and shall hold minimum 10 cubic mete
gas to 150 bar pressure.
Power Source :
Control Box : 110V DC/220V DC
Fire extinguishing cubicle for lighting : 230V AC

18.00 COOLING PLANT:


18.1 The cooling equipment shall consist of the following:
a. 2-50 percent tank
b. 2-100% pumps one of these being stand by
c. 2-stand by fans one in each 50% Bank
18.2 In case separate cooler banks are used, they shall be suitable for mounting on a
flat concrete base. These shall be provided with a valve (25 mm) at each point of
connection to the transformer tank, removable blanking plates to blank off main oil
connections to each cooler. Thermometer pockets with captive screwed cap at
inlet and outlet of each separate cooler, filter valve at top and bottom and air
release plug of 15mm.
18.3 The motor blowers shall be direct driven suitable for continuous out door operation
and complete with necessary air dusting. These shall be mounted independently
from the radiator and in the case, these are radiator mounting type, use shall be
made of some anti-vibration means. Care shall be taken that the blower unit is
capable of being removed without disturbing the radiator structure. The blades
shall be suitably painted and shall not be of hollow sections. Suitably painted wire
mesh guards with mesh not greater than 25mm shall be provided to prevent
accidental contact with the blades.

- 14 -
18.4 MOTORS:
18.4.1 The motor shall be squirrel cage totally enclosed weatherproof type suitable for
direct starting and for continuous running from 415/240 volts, three-phase/single
phase 50 HZ supply. The motors shall comply with IS as applicable for continuous
rated machine.
18.4.2 All motors shall be capable of continuous operation at frequency 50Hz with
variation of ±5% and 415/240 V AC ±10% variation of the normal voltage without
injurious over heating.
18.4.3 All motors shall have ball or roller bearing with hexagonal nipples for greasing. In
case of vertical spindle, motor shall have bearing capable of withstanding thrust,
due to weight of the moving parts.
18.4.4 Varnished cambric or glass insulator shall be used for connections from stator
winding to the terminal suitable for external wiring. The motor terminals shall be of
stud type and totally enclosed.
18.5 COOLER CONTROL:
18.5.1 Each motor or group of motors shall be provided with a 3 pole electrically operated
connector with control gear for motor operation by hand and automatically through
winding temperature indicator. Provision shall be made for over load protection but
no volt release shall not be provided.
18.5.2 All connection shall be so arranged as to allow either individual or collective
operation of the motors. Alarm indication (audio and visual) for failure of fans and to
indicate failure of power supply shall be provided.
18.5.3 The control equipment shall be installed in the marshaling box as specified in Cl.23
in a readily accessible position.
18.5.4 The alarm indication for failure of power supply and failure of individual fans be
provided through independent non trip alarm scheme to be wired on the remote tap
charger control cubicle conforming to the following. : -
i) The closing of an initiating contact shall actuate a buzzer and will be
accompanied by a flag indication on the concerned auxiliary relay.
ii) The closing of an initiating contact shall glow a lamp, which will not reset
until the fault has been cleared.
iii) It shall be possible to silence the buzzer by pressing 'Accept' push button.
If, after canceling the alarm but before resetting the visual signal, the same
fault persists the buzzer shall be suppressed.
iv) If after canceling the alarm but before resetting the visual signal, some other
fault takes place, the alarm accompanied by flag indication on appropriate
auxiliary relay shall take place.
v) If after canceling the alarm and after resetting the visual signal, the same
fault appears or some other fault takes place, the alarm, flag indication and
non-trip lamp indication shall reappear as usual.
vi) The non-trip alarm acceptance shall be by means of push button and
resetting of visual signal may also preferably be done through a push
button.
vii) Means shall be provided for test checking the lamp and alarm circuit at
frequent intervals.
viii) The equipment shall be suitable for 220 Volts DC operation.
Static facia aunnuciator conforming to the foregoing requirements of non-
trip alarm scheme too would be acceptable.

- 15 -
19.00 VOLTAGE CONTROL (ON LOAD TYPE):
19.1 The transformer shall by provided with OLTC which apart from being suitable for
local manual/electrical operation & remote electrical operation, shall be suitable for
operation by means of automatic voltage regulating relay. The AVR relay will be
fed by a single phase CVT (66000/110)/110/√3 volts installed on the secondary
side of transformer the variation in the transformation ratio is to be brought about
with out any phase displacement. 132 kV CVT is not included in the scope of
supply of the specification.
19.2 Equipment for 'local' and 'remote' electrical and 'local' manual operation shall be
provided and shall comply with the following conditions. Local/ remote switch may
be housed in remote control panel or in tap changer drive mechanism.
19.2.1 It shall not be possible to operate the electric drive when the manual operating gear
is in use.
19.2.2 It shall not be possible for any two electric controls to be in operation at the same
time.
19.2.3 The equipment suitable for supervisory control and indication on a multi way
switch, make-before break, having one fixed contact for each tap position, shall be
provided and wired to the tap changer drive gear. This switch shall be provided in
addition to any, which may be required for remote tap change position indication
purpose. Supervisory indication shall also be provided in the form of contacts to
close on. "Tap change incomplete" condition. All other components of the
supervisory gear if required be specified separately.
19.2.4 Operation from the local or remote control switch shall cause one tap movement
only. The control switch shall be returned to the 'neutral' position between
successive operations.
19.2.5 All Electrical control switch on the local operation gear shall be clearly labeled in a
suitable manner to indicate the direction of tap changing.
19.2.6 The local control switches shall be mounted, in the drive gear housing.
19.3 The equipment shall be so arranged as to ensure that when a tap change has
commenced, it shall be completed independent of the operation of the control
relays or switches. In case of failure of the auxiliary supply while tap change is in
progress or any other contingency such as stuck tap changer, adequate means
shall be provided to safe guard the transformers and its auxiliary equipment.
19.4 Suitable apparatus shall be provided for each transformer to give indications as
follows: -
19.4.1 To give indication, mechanically at the transformer and electrically at the remote
control cubicle of the position of tap in use.
19.4.2 To give an indication at the remote control cubicle that a tap change is in-progress,
by means of an illuminated lamp.
19.5 For remote control, the switches, tap position indicator, etc. shall be supplied duly
mounted on remote control cubicle.
19.6 All relays and operating devices shall be operated correctly at any voltage between
the limits specified in the relevant ISS.
19.7 The tap changing mechanism and mechanism shall be mounted in the oil tank or
compartment mounted in an accessible position on the transformer.
19.8 Any non oil filled enclosed compartment shall be adequately ventilated,
Thermostatically controlled heaters shall be provided in the driving mechanism
chamber and in the marshaling box. All contactor & auxiliary relay coils or other
parts shall be suitably protected against corrosion or deterioration due to
condensation, fungi etc.

- 16 -
19.9 The tap changer contacts which are not used for making or breaking current like
separate selector switch contacts can be located inside main transformer tank
where tap changer construction permits such an arrangement. The oil in case of on
load tap changer having separate compartment for selector contacts shall be
maintained under conservator head by means of pipe connection from the highest
point of the chamber to the conservator. Such connection shall be controlled by
suitable valve and shall be arranged so that any gas leaving the chamber will pass
into the gas and oil actuated relay. A separate buchholz relay may be provided for
this compartment.
19.10 It shall not be possible for the oil in these compartments of the tap change
equipment which contain contacts used for making or breaking current, to mix with
the oil in the compartments containing contacts and not used for making or
breaking current.
19.11 Any 'DROP DOWN' tanks associated with the tap changing apparatus shall be
fitted with guide rods to control the movement during lifting or lowering operations.
The guide rods shall be so designed as to take support of the associated tank
when in the fully lowered position with oil. Lifting gear fitted to 'Drop Down' tanks
shall include suitable device to prevent run-away during lifting and lowering
operations. They shall be provided with adequate breathing arrangement. The tap
changer shall be mounted in such a way that the cover of the transformer can be
lifted without removing connections between windings and tap changer.
19.12 Each compartment in which the oil is not maintained under conservator head shall
be provided with a suitable direct reading oil gauge.
19.13 The alternating supply for electrical operation of the control and indicating gear
shall be standard 415 Volts, three-phase, 3 wire, 50 Hz. along with 240 Volts single
phase, 2 wire 50 Hz, subject to a variation of ±5 percent so that the equipment
offered can withstand variation in AC
19.14 Limit switches shall be provided to prevent over-running of the mechanism and
except where modified in clause 18.15 shall be directly connected in the circuit of
the operating motor. In addition a mechanical stopper or other approved device
shall be provided to prevent over-running of the mechanism under any condition.
19.15 Limit switches may be connected in the control circuit of the operating motor
provided that a mechanical declutching mechanism is incorporated.
19.16 Thermal devices or other means like motor circuit breakers with shunt trip coil shall
be provided to protect the motor and control circuits. All relays, switches fuses, etc.
shall be mounted in the marshaling box or driving gear housing. These shall be
clearly marked for purpose of identification. They shall withstand the vibration
associated with tap changer gear operation.
19.17 The control circuits shall operate at 110V single phase to be supplied from a
transformer having a ratio of 415 or 240/55-0-55 V with the center point earthed
through a removable link mounted in tap changer drive.
19.18 The whole of the apparatus shall be of robust design and capable of giving
satisfactory service under conditions to be met in service including frequent
operation.
19.19 A five-digit counter shall be fitted to the tap changing mechanism to indicate the
number of operations completed by the equipment.
19.20 A permanently legible lubrication chart shall be fitted within the driving mechanism
chamber, where applicable.
19.21 The indigenous make OLTC having voltage rating as 132 kV & current rating 300
Amp. should be duly type tested from CPRI or other Govt. test house or reputed
lab from abroad to the extent the facilities of type test available with CPRI.

- 17 -
20.0 PARALLEL OPERATION:
20. 1 In addition to individual control of tap changer, provision shall be made to enable
parallel operation of the tap changer when one unit is running in parallel with
another similar unit of same rating.
20.2 Suitable selector switch and controls shall be provided so that any transformer of
the group can at a time be selected as master, follower or independent.
Arrangement shall be made that only one of the transformers can be selected as
master at a time.
20.3 An out of step device shall be provided for each transformer indicating out of step
condition by an indicating lamp and buzzer. It shall be arranged to prevent further
tap changing when transformers in a group operating in parallel control are one tap
out of step.
21.0 BUSHING INSULATORS AND TERMINALS:
21.1 Transformer shall be fitted with bushing insulators as follows: -
HV bushing: 245 kV class, condenser bushing of 800 Amp. rating without arcing
horns.
L.V. Bushing: 72.5/36 kV class condenser bushing of 1000/2000 Amp. rating
without arcing horns.
Neutral Bushing: 36 kV class oil communicating type porcelain bushing of
1000/2000 Amp. rating without arcing horns.
• The characteristics of the bushings shall be in accordance with IS: 2099 and IS:
3347.
• A continuous flexible pull through lead suitably sweated to the end of winding
copper shall be connected to the connector in the helmet of the 220/66 kV
Bushing. The bushings may be filled with oil, which may not be in
communication with the oil in transformer.
• All porcelain shall be free from defects and thoroughly vitrified with a smooth,
hard and uniform brown glaze. It should be capable of satisfactory use under
the climatic conditions as specified in clause-3.0.
• In case of paper insulation care shall be taken to prevent ingress of moisture
and a final coat of non-hygroscopic varnish shall be given to them.
• All clamps and fittings made of malleable iron or steel shall be galvanized as
per IS: 2629. The bushings flanges shall not be of re-entrant shape which may
trap air.
• Bi-metallic terminal connectors shall be supplied suitable for single/twin AAC
Tarantulla conductor for HV & LV side and neutral side. The take off for H.V. &
L.V. connectors will be Vertical and for Neutral it should be suitable for
horizontal take off.
• The connectors shall have six number bolts provided with check nuts &
washers. The connectors shall have rating corresponding to those of equipment
or higher and shall be designed most liberally with a higher factor of safety to
comply in all respects with temperatures rise, resistance, tensile strength
short-circuit withstand capability tests as specified in IS: 5561-1970 or
amendment thereof (Latest edition). Aluminum alloy used in the manufacture of
Bi-metallic connectors shall conform to designation Grade 4600 of IS:
617-1975. The steel bolts, nuts washers and check nuts shall be hot dip
galvanized marked with ISI certification mark or of GKW make.
22.00 TEMPERATURE INDICATING DEVICES:
22.1 All transformers shall be provided with a dial type thermometer for indicating oil
temperature. The indicator shall be fitted with a pointer to register maximum temp
recorded and adjustable set of mercury contact for alarm and trip.

- 18 -
22.2 In addition, all the transformers shall be provided with a dial type Hot Spot winding
temperature indicator in HV & LV winding. The indicator shall have a pointer to
register maximum temperature reached and four sets of adjustable mercury
contacts for alarm, trip, automatic control of fans & remote indication. The static
remote repeater (for winding temperature indicator) suitable for flush mounting shall
be installed on remote tap charge control cubicle.
22.3 The temperature indicators shall be housed in marshaling box.
22.4 The alarm (mercury) contact of WTI & OTI shall be adjustable between 50oC to
100oC where as their trip (mercury) contacts shall be adjustable between 60oC and
120oC. The temperature difference between opening & closing of these mercury
contacts shall not be more than 10oC.
22.5 The mercury contacts used for controlling cooling plant motors shall be adjustable
to close between 50oC and 100oC. The temperature differential between opening &
closing of this mercury contract shall be between 10oC to 15oC.
22.6 All contacts should be accessible on removal of the cover adjustable to scale. It
shall also be possible to move the pointers by hand for checking the operation of
contacts and associated equipment.
22.7 In addition each transformer shall be provided with a dial type thermometer for
indicating the ambient temperature.

23.00 GAS AND OIL ACTUATED RELAYS: -


23.1 The transformer shall be provided with a gas and oil actuated relay fitted with alarm
and trip contacts for main tank & oil surge relay for its OLTC as per IS:3637.
23.2 Each such relay shall be provided with a test cock to take a flexible connection for
checking relay operation
23.3 A machined surface shall be provided on top of relay for checking mounting angles
in the pipe cross level of relay and its setting.
23.4 The pipe work shall be such as to allow any gas formed in the tank to pass through
the relay. The oil circuit through the relay shall not form a parallel delivery path
with any circulating oil pipe, nor shall it be tied into or connected through the
pressure relief vent.
23.5 Adequate clearance between oil pipe work and live metal parts shall be provided.

24.00 MARSHALING BOX: -


24.1 A sheet steel (of 10 SWG size) vermin proof well ventilated and weather proof
marshaling box of suitable construction shall be provided for the transformer
auxiliary apparatus. The box shall have domed or sloping roofs. Ventilation
louvers, suitably padded with felt, shall also be provided. It shall be painted as per
Cl.5.14.
24.2 The marshaling box shall accommodate temperature indicators. Local electrical
control of tap changer (if same cannot be housed in motor drive housing.), Control
& protection equipment for cooling plant, terminal boards and gland plates for cable
etc. The equipment shall be mounted on panels and panels wiring shall be done at
the back for interconnections.
24.3 The temperature indicators shall be mounted at about 1600mm from ground level.
24.4 A metal clad heater with thermostat, controlled by a waterproof rotary switch on the
outside of the box, shall be provided.

- 19 -
24.5 The incoming cables shall enter from the bottom with gland plate not less than
450mm from the base of the box. Care shall be taken to avoid ingress of water
from the cable trench.
25.00 CONTROL CONNECTIONS, INSTRUMENTS WIRING, TERMINAL BOARD AND
FUSES: -
25.1 All cables and wiring shall be suitable for use under the conditions as specified in
Section -I. Any wiring liable to come in contact with oil shall be of oil resisting
insulation. The bare ends of stranded wire shall be sweated together to prevent oil
from creeping along the wire.
25.2 The instrument and panel wiring shall be run in PVC or non rusting metal cleats of
limited compression type.
25.3 The box wiring shall be as per relevant ISS. All wiring shall be of stranded copper
of 660V grade and size not less than 4 Sq. mm. for CT leads and not less than 2.5
Sq. mm for other connections. The panel wires and multi core cable shall bear
ferrules of white insulation material with indelible marking in black and as per
relevant ISS. Same ferrule number shall not be used on wires in different circuits.
Double ferrule may be provided where a change in number is required.
25.4 Stranded wires shall be terminated with tinned Ross Courtney terminals, washers
or crimped tubular lugs. Separate washers shall be used for each wire. Wire shall
not be jointed/tied between terminal points.
25.5 Where apparatus is mounted on panels all metal cases shall be separately earthed
by copper wire or strip not less than 2.5 sq. mm. The screens of screened pairs of
multi core cables shall be earthed at one end of the cable only.
25.6 All terminal boards shall be of stud-type & mounted obliquely towards the rear door
and these boards shall be spaced not less than 100mm apart. Suitable insulation
barriers shall be provided between adjacent connections. No live metal shall be
exposed at the back of terminal boards.
25.7 All fuses shall be of cartridge type and fuses and links shall be properly labeled.

26.00 Losses:-

The losses of each transformer shall be stated in the tender for OFAF rating (at full
load at 75 deg. C ) which shall be less than:-

Sr. No. Type of Losses 100 MVA 220/66 KV T/F


1 No load losses 54 KW (Max)
2 Load Losses 295 KW (Max)
3 Auxiliary Losses 8 KW (Max)

27.0 Noise level : Max. 80 dB

Transformer offers shall be rejected if audible sound level is higher than max. 80 dB.

- 20 -
28.00 TESTS:
28.1 ROUTINE TESTS:
All routine test shall be carried out on each transformer as per IS-2026 in the
presence of HVPNL's representative.
28.2 TYPE TESTS :
The following type tests shall be carried out on one transformer as per ISS:2026 in
the presence of HVPNL's representative.
i) Temperature rise test (along with DGA)
ii) Impulse voltage withstand test as per clause 13 of ISS-2026/1981 Part-III on
one limb.
There will not be any separate schedule for type test charges. The charges if any
may be included in bid price.
28.3 In addition, the following tests shall be carried out on the Transformer Tank:
28.3.1 OIL LEAKAGE TEST:
All tanks and oil filled compartments shall be tested for oil tightness by being
completely filled with oil of viscosity not greater than that of insulating oil to IS: 335
at ambient temperature and subjected to a pressure equal to normal pressure
plus 35KN/M2 (5 lbs sq. inch) measured at the base of the tank. This pressure
shall be maintained for a period not less than 12 hours, during which period no
leakage shall occur.
28.3.2 Following tests shall be carried out on each transformer as reference test:
i) Measurement of tan delta and capacitor of T/F Winding and bushings at 5
kV & 10 kV.
ii) Magnetic balance test.
iii) Magnetising current at low voltage
iv) Measurement of percentage impedance at all taps at low voltage.
v) Partial discharge test.
vi) Noise level test.
28.3.3 TRANSFORMER OIL:
The bidder shall indicate in detail facility available at his works for carrying out
various tests on transformer oil as per ISS: 335 (Latest) and oxidation stability test
as per ASTM:D-1934. It is contemplated that the oil test shall be carried out on the
transformer oil at the works of the transformer manufacturer before and after
pouring of oil. New transformer oil before pouring in tanks, should conform to
values Specified in ISS-335/93 and after pouring in the tank but before energisation
the transformer oil should conform ISS: 1866/83 Amendment No. I issued in
Dec.1987.

28.4 The HVPNL reserves the right to have any other, reasonable test carried out at his
expense either before shipment or at site to ensure that the transformer complies
with the requirement of this specification.

- 21 -
28.5 STAGE INSPECTION:
The HVPNL reserves the right for stage inspection of one or all the transformers at
following stages, to ensure that the internal details are in accordance with the
data/information supplied, for which the Bidder would give 30 days prior notice and
the Bidder would not go ahead with further production schedule without obtaining
concurrence from the HVPNL..
a. CORE:
Bidders will offer the core for inspection and approval by the HVPNL during
the manufacturing stage. Bidders call notice for the purpose should be
accompanied with the following documents.
a) Invoice of Bidder.
b) Mills test certificate.
c) Bill of landing.
d) Bill of entry certificate to customs.
Core material shall be directly procured either from the manufacturer or
through their accredited marketing organisation of repute only.
Following tests shall be carried out.
i. Measurement of flux density.
ii. No load loss measurement by providing dummy coils at 90%, 100%
and 110% rated voltage and frequency.
iii. Tests on CRGO sample taken from the core shall be carried out for
Carlit test (Resistance Measurement) watt loss test, lamination
thickness and aging tests.
iv. Physical inspection for quality of workmanship.
b. WINDINGS:
i. Measurement of cross-sectional area for current density.
ii. Measurement of weight of bare copper/ cover by resistance methods.
iii. Test may be carried out on sample of copper for assessing its quality.
c. TANK:
i) Vacuum Test:
One transformer tank out of the lot shall be subjected to vacuum pressure of
100.64 kN (760 mm of hg). The tanks to be designed for full vacuum shall be
tested at an internal pressure of 3.33 KN/M2 (25mm of Hg.) for one hour.
The permanent deflection of flat plates after the vacuum has been released
shall not exceed the values given below without affecting the performance of
the Transformer.
----------------------------------------------------------------------------------------------
Horizontal length of flat plate(mm). Permanent deflection(mm).
-------------------------------------------------------------------------------------------------
Upto & including 750 5.0
751-1250 6.5
1251-1750 8.0
1751-2000 9.5
2001-2250 11.0
2251-2500 12.5
2501-3000 16.0
above 3000 19.0
---------------------------------------------------------------------------------------------

- 22 -
ii) PRESSURE TEST:
One transformer tank out of the lot shall be subject to the pressure corresponding
to twice the normal head of oil or normal pressure plus 35KN/M2 (which ever is
lower) measured at the base of the tank and maintained for one hour. The
permanent deflection of flat plates after removal of excess pressure shall not
exceed the figures specified as above.
d. RADIATORS:
Radiator shall be routine and type tested at sub Bidders' work as per relevant
standard. Test reports are required to be supplied at the time of final inspection.
NOTE:
a. The insulation resistance values of the transformer windings will be
recorded at the time of carrying out routine tests, for 20 seconds, one
minute, two minutes with the help of 5000V motorized meggar. (Preferably
EVERSHED/ AVO & VIGNOLE MAKE). The polarisation index values (ratio
of 120/20 sec. value) will be accordingly calculated and recorded in the test
certificates and it should not be less than 1.5.
b. Dissolved gas analysis test shall be got carried-out before and after heat
run test at CPRI.
c. Capacitance and Tan Delta values for each transformer and condenser
bushings will be taken and recorded in the test certificates at 5 kV & 10 kV.
Insulation resistance value of condenser bushings shall also be recorded.
d. Lightening impulse test with the chopped wave applications as per clause
13 of IS: 2026/ 1981 (Part-III) amended upto date. This test will be carried
out on one of the limbs of HV and LV winding with positive polarity.
e. The tender should clearly indicate the testing facilities available with them
and tests which are to be arranged outside.
Bidder shall submit in-house test certificate at least 15 days in advance for final
testing of transformer. For testing T/F, all measuring instruments shall be of
highest efficiency and best quality. These shall be got calibrated from NPL/ Govt.
Agency and be got sealed by calibrating agency. HVPN reserves the right to
calibrate the instruments in the manner it desires.
Losses shall be measured with 3-wattmeter method only. Resistance shall be
taken with Double-Kelvin Bridge. Losses can be measured directly from CTs and
PTs and not through the panel. Ratio of the measuring instrument shall be such
that the multiplying factor is the minimum.
All tests shall be carried out in the presence of the HVPNL before dispatching the
material. Test certificates in quadruplicate will be submitted to the HVPNL for
approval. No material shall be despatched without prior inspection and approval
of test certificates unless otherwise agreed to. Type and routine test certificates of
all bought out items from recognised testing agency shall be submitted for
approval before commencing supplies. OLTC scheme including the master
follower functioning shall also be checked. Only fully assembled transformer
including mounting of radiators shall be put-up for inspection.

29.00 DRAWINGS:
29.1 The following drawings shall be supplied as part of the tender.
29.1.1 Outline dimensional drawing of transformer and accessories.
29.1.2 Bushing and terminal connectors drawing.

- 23 -
29.2 The bidder shall submit four sets of final version of all the above drawings for
HVPNL's approval along with the tender in a separate seal cover. These
drawings will be opened in the event of order. The HVPNL shall communicate his
comments/approval on the drawings to the Bidder within four weeks of the issue
of LOI. The manufacturer shall, if necessary, modify the drawings and resubmit
the same for HVPNL's approval within two weeks of receipt of comments. Such
duly revised drawings will be approved by the HVPNL within two weeks of their
receipt.
After receipt of HVPNL's approval to drawings, the manufacturer will submit a set
of reproducible of all the approved drawings and will also supply five sets of all
approved drawings and five sets of manual of instructions per transformer to
Substation Design Directorate HVPNL Panchkula.
ONE SET OF ALL THE APPROVED DRAWINGS AND MANUAL OF INSTRUCTIONS WILL
BE SUPPLIED ALONGWITH EACH TRANSFORMER WITHOUT WHICH THE SUPPLY
WILL NOT BE CONSIDERED AS COMPLETE SUPPLY.
29.2.1 Outline general arrangement drawings showing plan, front elevation & side
elevation with all fittings and accessories etc. The following information must be
specifically included on the drawings.
a. Make of transformer oil.
b. Electrical clearances, minimum as well as actual.
c. No. of radiator headers, number of radiator element in each header.
d. Small sketch showing un-tanking details.
e. Thickness of transformer tank bottom, side & top plates.
f. Type, shade, shade No. and thickness of transformer paint.
g. Roller, rail gauge sketch.
h. Weight of oil, bare copper weight windings, core, un-tanking mass,
transportation mass and dimensions etc.
29.2.2 Detailed of bushings showing plan, elevation, terminal details, mounting details
make and type number incorporating electrical characteristics, description of
various parts, total creepage/ & protected creepage distance, weight of oil, total
weight of bushing , dimensions, short time current rating etc.
29.2.3 Drawing showing HV & LV windings with arrangement of insulation and terminal
connections.
29.2.4 Schematic control and wiring diagram for auxiliary equipment like OLTC control
gear, cooler control gear, Marshaling Kiosk. Detailed write-up for schematic shall
also be supplied
29.2.5 Combined Rating & Diagram Plate.
29.2.6 Valve schedule plate.
29.2.7 Core assembly drawing with flux density calculations.
29.2.8 Interconnection diagram between OLTC panel, Drive mechanism and
marshalling kiosk.
29.2.9 Detailed calculations showing short circuit with stand capability due to radial and
axial forces during short circuit. Also calculation for thermal withstand capability
during short circuit.
29.2.10 Cable arrangement on the transformers.
29.2.11 Drawing showing connection of HV, LV lead with the respective bushing and their
place of storage during transportation.
29.2.12 Detailed drawing of NIFPES system along with its detailed write up.

- 24 -
SECTION-4
CHAPTER-1

TECHNICAL SPECIFICATION FOR


SURGE ARRESTORS (LIGHTNING ARRESTORS)

1.0 SCOPE:

1.1 This specification provides for the design, engineering, manufacture, assembly, stage
testing, inspection and testing before despatch, packing, forwarding and delivery at
site of Metal Oxide (gapless) 198 kV & 60 kV Surge Arrestors complete with discharge
counter, insulating base and other accessories for all rating arrester.

1.2 It is not the intent to specify completely herein all the details of design and construction of
Surge Arrestors. However, Surge Arrestors shall conform in all respects to the high
Standard of design and workmanship and be capable of performing in continuous
commercial operation upto Bidder's guarantee in a manner acceptable to HVPNL. The
Arrestors offered shall be complete with all parts, necessary for their effective and
trouble free operation. Such components shall be deemed to be within the scope of
supply, irrespective of whether they are specifically brought out in the commercial
order or not.

2. STANDARDS:

2.0 The Surge Arrestors shall conform to the latest editions and amendments available at
the time of supply, of the standards listed hereunder.
______________________________________________________________
Sl. Standard Title
No. Ref. No.
______________________________________________________________
1. IEC:99-4 Specification Part-4 for Surge Arrestors without gap for AC
system.

2. IS:3070 Specification for Lightning Arrestors


(Part-III) for alternating current system

3. IS: 2629 Recommended practice for hot dip galvanizing of iron


and steel.

4. IS: 2633 Method for testing uniformity of coating on zinc coated


articles.

5. IS:5621 Specification for large hollow porcelain for use in electrical


installation.

6. IS:2147 Degree of protection provided by enclosures for low voltage


switchgear and control.

7. Indian Electricity Rules, 1956.

______________________________________________________________________________

-1-
Note:

i) For the purpose of this specification all technical terms used hereinafter shall have
the meaning as per IEC/ISS specification.

ii) For the parameters of the Arrestor which are not specified in IEC specification for
Surge Arrestors, the provisions of IS: 3070 (Part-I) shall be applicable.

2.1 Surge Arrestors meeting with the requirements of other authoritative standards, which
ensure equal or better quality than the standards mentioned above shall also be
acceptable. Where the equipment offered by the Bidder conforms to other standards,
salient points of difference between the standards adopted and the specified standards
shall be clearly brought out in the offer. Four (4) copies of the reference standards in
English language shall be furnished alongwith the offer.

3.0 SERVICE CONDITIONS:

As per section-1 Vol-II

3.1 AUXILIARY POWER SUPPLY:

The equipment offered under this specification shall be suitable for the following auxiliary
power supplies.

a) Power Devices (like drive motors) 415V, 3 Phase, 4 wire 50 Hz,


neutral grounded AC supply

b) AC Control and protective 240V, single space, 2 wire 50


devices, lighting fixtures, space Hz, neutral grounded AC
heaters supply

c) DC alarm,control and protective 220V, DC 2-Wire


devices

Each of the foregoing supplies shall be made available by the HVPNL at the terminal
point for each equipment for operation of accessories and auxiliary equipment. Bidder’s
scope shall include supply of interconnecting cables, terminal boxes, etc., The above
supply voltages may vary as below and all devices shall be suitable for continuous
operation over entire range of voltages.

i) AC Supply-voltage+10%&-15% frequency + 5%

ii) DC Supply-15% to +10%

4.0 SYSTEM PARAMETERS:

The Surge Arrestors offered under this specification shall conform to the parameters
given below:

-2-
___________________________________________________________________
Sl. Particulars System Voltage (KV rms)
No. 220 66
___________________________________________________________________
1. Nominal system voltage 220 66
(kV rms)

2. Highest system voltage 245 72.5


(kV rms)

3. 1.2/50 microsecond
impulse voltage withstand
level

a. Transformers and 900 325


Reactors (kVp)
b. Other equipment 1050 325
and lines (kVp)

4. Minimum prospective 40 31.5


symmetrical fault current
for 1 second at Arrestor
location (kA rms)
5. Anticipated levels of
temporary overvoltage
and its duration

a) Voltage (p.u.) 1.5/1.2 1.5/1.2

b) Duration (Seconds) 1/10 1/10

6. System frequency(Hz) --------------------- 50 ± 2.5 C/S ----------------------

7. Neutral Grounding E.E* E.E*

8. Number of Phases ----------------------- Three --------------------


*E/E = Effectively earth
__________________________________________________________________

5.0 GENERAL TECHNICAL REQUIREMENTS:


5.1 The Surge Arrestors shall conform to the technical requirements as per Annexure-II

5.2 The energy handling capability of each rating of Arrestor offered, supported by
calculations, shall be furnished in the offer.

5.3 The Surge Arrestors shall be fitted with pressure relief devices and arc diverting ports and
shall be tested as per the requirements of IEC specification for minimum prospective
symmetrical fault current as specified in Clause 4.0 (4).

5.4 The grading ring on each complete Arrestor for proper stress distribution shall be provided if
required for attaining all the relevant technical parameters.

-3-
5.5 PROTECTIVE LEVELS:
The basic insulation levels and switching impulse withstand levels of the lines and
equipment to be protected, have been specified in clause 4.0, "Principal Parameters".
The protective characteristics of the Arrestors offered shall be clearly specified in the
schedule of guaranteed technical particulars.

5.6 GENERAL REQUIREMENTS:

5.6.1 The materials and components not specifically stated in this specification but which are
necessary for satisfactory operation of the equipment are deemed to be included in the
scope of supply unless specifically excluded.

5.6.2 Unless otherwise brought out separately by the Bidder in the schedule of deviations the
Surge Arrestors offered shall conform to the specification scrupulously. All deviations
from the specification shall be brought out in the schedule of deviations. The
discrepancies between the specification and the catalogues or literature submitted as
part of the offer shall not be considered as valid deviations unless specifically brought
out in the schedule of deviations.

5.6.3 Any deviation which has not been specifically brought out in the schedule of deviations
of the Bid Proposal Sheets, shall not be given effect to. The deviations brought out in
the schedule shall be supported by authentic documents, standards and other
references.

5.6.4 Each individual unit of Surge Arrestor shall be hermetically sealed and fully protected
against ingress of moisture. The hermetic seal shall be effective for the entire life time of
the Arrestor and under the service conditions as specified. The Bidder shall furnish
sectional view of the Arrestor, showing details of sealing employed.

5.6.5 The Bidder shall furnish in the offer, a sectional view of pressure relief device employed
in the Surge Arrestors offered.

5.6.6 The Surge Arrestors shall be suitable for hot line washing.

5.7 CONSTRUCTION:

5.7.1 All the units of Arrestors of same rating shall be inter changeable without adversely
affecting the performance.

5.7.2 The Surge Arrestors shall be suitable for pedestal type mounting.

5.7.3 All the necessary flanges, bolts, nuts, clamps etc., required for assembly of complete
Arrestor with accessories and mounting on support structure to be supplied by the
HVPNL, shall be included in Bidder's scope of supply.

5.7.4 The drilling details for mounting the Arrestor on HVPNL's support shall be supplied by the
Bidder.

5.7.5 The minimum permissible separation between the Surge Arrestor and any earthed object
shall be indicated by the Bidder in his offer.

5.8 PORCELAIN HOUSING:

-4-
5.8.1 All porcelain housings shall be free from lamination cavities or other flaws affecting the
maximum level of mechanical and electrical strengths.

5.8.2 The porcelain shall be well vitrified and nonporous.

5.8.3 The Creepage distance of the Arrestor housing shall be as per Annexure-I.

5.8.4 The porcelain petticoat shall be preferably of self-cleaning type (Aerofoil design). The
details of the porcelain housing such as height, angle of inclination, shape of petticoats,
gap between the petticoats, diameter (ID and OD) etc., shall be indicated by the Bidder
in his offer in the form of a detailed drawing.

5.8.5 The Arrestor housing shall conform to the requirements of IEC/ISS specification.

5.9 GALVANISATION, NICKEL PLATING ETC.:

5.9.1 All ferrous parts exposed to atmosphere shall be hot dip galvanised as per IS:2629 as
amended from time to time., Tinned copper/brass lugs shall be used for internal wiring
of discharge counter. Screws used for electrical connections shall be either made of
brass or nickel plated.

5.9.2 Ground terminal pads and name plate brackets shall be hot dip galvanised.

5.9.3 The material shall be galvanised only after completing all shop operations.

5.10 ACCESSORIES AND FITTINGS:

5.10.1 Discharge counters shall be provided for the Arrestors. The discharge counter shall be
provided with milli-ammeter for measuring the leakage current and shall not require any
DC or AC Aux. supply. It shall be suitable for outdoor use. The installation of discharge
counter shall not adversely affect the Arrestor performance.

5.10.2 The discharge counter shall register operation whenever lightning or any other
type of surge strikes the Surge Arrestor.

5.10.3 All necessary accessories and Earthing connection leads between the bottom of
the Arrestor and the discharge counter shall be in the Bidder's scope of supply. The
connecting lead between discharge counter and Surge Arrestor shall be of copper
flexible tape of size 25x4 mm and minimum of 1.5 meter length. The discharge counter
shall be so designed that the readings of discharges recorded by the counter and
the readings of milli-ammeter shall be clearly visible through an inspection window to a
person standing on ground. The minimum height of HVPNL's support shall be 2.5 Mts.
Terminal connector conforming to IS:5561 shall be supplied alongwith the arrester.

5.11 Each Surge Counter shall have terminals of robust construction for connection to
Earthing lead and these shall be suitably arranged so as to enable the incoming and
outgoing connections to be made with minimum bends.

5.11.1 Suitable grounding terminal shall be provided for earthing of surge arrestors up to water
level. Proper functioning of the Surge counter with Surge Arrestor shall be ensured by the
Bidder.

-5-
5.12 NAME PLATE:

The arrestor shall be provided with non-corrosive legible name plate indelibly marked with
the following information:

1. Haryana Vidyut Prasaran Nigam Ltd.

2. Order No.

3. Manufacturer's name or trade mark and identification no. of the Arrestor being
supplied.

4. Rated voltage.

5. Maximum continuous operating voltage.

6. Type.

7. Rated Frequency.

8. Nominal discharge current.

9. Long duration discharge class.

10. Pressure relief current in kA rms.

11. Year of manufacture.


6.0 TESTS:

6.1 TYPE TESTS:

The equipment should be offered type test. Test reports should not more then seven years
old reckoned from date of bid opening in respect of all the tests carried out in accredited
laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or
another electric power utility and be submitted by the successful bidder to HVPNL for
approval as schedule given in Bar Chart.
i) Insulation withstand test
ii) Residual voltage test
iii) Long duration current impulse withstand test
iv) Operating duty test
v) Pressure relief test
vi) Test of arrestor dis-connector
vii) Artificial pollution test on porcelain housed arrestors
viii) Temperature cycle test on porcelain housed arrestors)
ix) Porosity test on porcelain house arrestors
x) Galvanising test on exposed ferrous metal parts

-6-
6.2 ROUTINE TESTS:
As per quality assurance program (QAP).
6.3 ACCEPTANCE TESTS:
The following acceptance tests as stipulated in the relevant IS:3070 (PART-III) 1993 shall
be carried out by the Supplier in presence of HVPNL representative, unless dispensed
with in writing by the HVPNL.
i) Measurement of power frequency reference voltage
ii) Lightening impulse residual voltage test
ii) Partial discharge test

6.4 SURGE MONITOR

The following routine test shall be performed in the presence of HVPNL’s representative:

i) Tests for satisfactory operation of surge counter while discharging surges.


ii) Test for correctness of leakage current meter before and after the passage of
surges.
iii) Visual examination tests.

7.0 DOCUMENTATION:

7.1 The successful bidder shall submit four sets of following drawings for HVPNL approval.

List of drawings:-

i) General outline drawings of the complete Arrestors with technical parameters.

ii) Drawing showing clearance from grounded and other live objects and between
adjacent poles of Surge Arrestors, required at various heights of Surge Arrestors.

iii) Drawings showing details of pressure relief devices.

iv) Detailed drawing of discharge counters along with the wiring and schematic
drawing of discharge counter and meter.

v) Outline drawing of insulating base.

vi) Details of grading rings, if used.

vii) Mounting details of Surge Arrestors.

viii) Details of line terminal and ground terminals.

ix) Volt-time characteristics of Surge Arrestors.

x) Details of galvanising being provided on different ferrous parts.

-7-
xi) The detailed dimensional drawing of porcelain housing such as ID, OD, thickness
and insulator details such height, profile of petticoats, angle of inclination and gap
between successive petticoats, total Creepage distance etc.,

NOTE: All above drawings should bear a minimum space (14x10cm) for stamping the
approval of drawings by HVPNL.

-8-
ANNEXURE - I
(Surge Arrestors)
SHEET 1 OF 3

TECHNICAL REQUIREMENTS FOR METAL OXIDE


(GAPLESS) SURGE ARRESTORS

______________________________________________________________________
Sl. Particulars System voltage wise requirement of parameters
No. 220 kV 66 kV
______________________________________________________________________
1. Rated Arrestor 198 60
Voltage

2. M.C.O.V. (kV rms) 168 49

3. Installation ----------------------- Outdoor -----------------------

4. Class --------- ------------------ Station Class ---------------------

5. Type of cons- ------------------ ---------- Single Column, Single Phase----------


truction for
10 kA rated Arrestor.

6. Nominal discharge 10KA 10KA


current corres-
ponding to 8/20
microsec wave
shape (kA rms)

7. Min. discharge 5 KJ/kV (Referred to rated arrester voltage


capability. corresponding to Min. discharge characteristics)

8. Type of mounting ------------------------------------------ Pedestal -------------------------

9. Connection
(Between phase P/E P/E
to earth P/E)
(Between phase
to phase P/P)

-9-
ANNEXURE - I
(Surge Arrestors)
SHEET 2 OF 3

TECHNICAL REQUIREMENTS FOR METAL OXIDE


(GAPLESS) SURGE ARRESTORS

______________________________________________________________________
Sl. Particulars System voltagewise requirement of parameters
No. 220 kV 66 kV
______________________________________________________________________

10. Long duration 3 3


discharge class

11. Max. Switching Surge 455 140


kV(P) Protective level
voltage at 1000 Amp.

12. Max. residual voltage 550 170


kV(P) for nominal
discharge current
10 KA with 8/20
micro second wave

13. Max.residual voltage 600 186


kV(P) steep fronted
current impulse of
10 KA.

14. Minimum pros- 40 31.5


symmetrical fault
current for pressure
relief test (kA rms)

15. a) Terminal Connector -------------------Single Zebra------------------------


suitable for ACSR
conductor size
b) Take off Vertical vertical

16. Voltage (kV rms) Rated voltage of the Arrestor


(corona extinction)

- 10 -
ANNEXURE - I
(Surge Arrestors)
SHEET 3 OF 3

TECHNICAL REQUIREMENTS FOR METAL OXIDE


(GAPLESS) SURGE ARRESTORS

_____________________________________________________________________
Sl. Particulars System voltagewise requirement of parameters
No. 220kV 66 kV

17. Maximum radio -------------------------- 500 ----------------------------


interference
voltage (Microvolt)
when energised
at MCOV
18. Whether insulating Yes Yes
base and discharge
counter with
milli-ammeter are
required.
19. Minimum creepage 6125 1813
distance of Arrestor
housing (mm)
______________________________________________________________________

- 11 -
SECTION-4
CHAPTER-2
TECHNICAL SPECIFICATION FOR 72.5 kV ISOLATORS & LINE - CUM - EARTH SWITCHES

1.0 SCOPE:

This specification provides for design, engineering, manufacture, stage testing, inspection
and testing before dispatch, packing, forwarding and delivery at site of 72.5 kV class
Isolators and line-cum-earth switch complete with all fittings, accessories and associated
auxiliary equipment mandatory spares which are required for efficient and trouble free
operation as specified hereunder.

It is not the intent to specify completely herein all details of the design and construction of
equipments. However, the equipment shall conform in all respects to high standards of
engineering, design and workmanship and shall be capable of performing in continuous
commercial operation up to the Bidder's guarantee acceptable to the HVPNL. The
equipment offered shall be complete with all components necessary for its effective and
trouble free operation along with associated equipment, interlocks, protection schemes etc.,
Such components shall be deemed to be within the scope of supply, irrespective of whether
those are specially brought out in this specification and/or commercially ordered or not. All
similar parts particularly movable ones shall be interchangeable.

2.0 STANDARDS:
Unless otherwise specified elsewhere in this specification, the rating as well as
performance and testing of the isolators shall conform to the latest revisions and
amendments of the following standards available at the time of placement of order.
------------------------------------------------------------------------------------------------------------
Sl. No. Standard No. Title
------------------------------------------------------------------------------------------------------------
1. IS:9921 Alternating current isolators(dis-connectors) and earthing
switches.

2. IEC:129 -do-

3. IS:2544 Insulators.

4. IS:2147 Degree of protection provided by enclosure.

5. IS:4691 -do-

6. IS:325 Three phase induction motors.

7. IS:4722 Rotating electrical machines.

8. IS:2629 Recommended practice for hot dip galvanising of


iron & steel.

9. IS:4759 Hot dip galvanisation coating on structural steel.

10 . IS:2633 Method of testing weight, thickness and uniformity

11. IS:1573 Electroplated coating of zinc on iron and steel.

-1-
12. IS:6735 Spring washers.

13. IS:2016 Plain washers.

14. __ Indian Electricity Rules, 1956


--------------------------------------------------------------------------------------------------------------------
Equipment meeting with the requirements of other authoritative National or International Standards,
which ensure equal or better performance than the standards mentioned above, shall also be
considered. When the equipment offered by the bidder conforms to other standards salient points of
difference between standards adopted and the standards specified in this specification shall be
clearly brought out in the relevant schedule. Four copies of such standards with authentic
translation in English shall be furnished along with the offer.

3.0 SERVICE CONDITIONS:

As per section -1 Vol -lI

3.1 AUXILIARY POWER SUPPLY:

The equipment offered under this specification shall be suitable for the following auxiliary
power supplies.

a) Power Devices 415 V, 3 phase, 4 wire


(like drive motors) 50 Hz, neutral grounded
AC supply.

b) AC control and protective 240 V, single phase, 2 wire


devices, lighting 50 HZ, neutral grounded
fixtures, space heaters. AC supply.

c) DC alarm, control and 220 V, DC 2-wire


protective devices

Each of the foregoing supplies shall be made available by the HVPNL at the terminal point for each
equipment for operation of accessories and auxiliary equipment. Bidder's scope shall include
supply of interconnecting cables, terminal boxes, etc., The above supply voltages may vary as
below and all devices shall be suitable for continuous operation over entire range of voltages.

i) AC supply - voltage + 10%& -15% frequency ± 5%

ii) DC supply - 15% to + 10%

-2-
4.0 PRINCIPAL PARAMETERS:

The equipment covered in this specification shall meet the technical requirements listed below:
-----------------------------------------------------------------------------------------------------------------
Sl.No Technical Parameter 72.5 kV
----------------------------------------------------------------------------------------------------------------

1. Rated Frequency (Hz) ------------ 50 ------------

2. System Neutral Earthing ------ Effectively Earthed --------

3. No. of Phases (Poles) -------------- 3 -----------------

4. Temperature Rise ------- As per relevant IS/IEC ---

5. Safe Duration of overload

a) 150% of rated current ---------- 5 minutes --------------

b) 120% of rated current ---------- 30 minutes --------------

6. Rated voltage /Highest 66/72.5


system voltage (kV rms)

7. Type of disconnect (AB) DB

8. Rated normal current


(Amp rms) 1600

9. Rated short time withstand 31.5


current (kA rms) of MS
& EB for 1 sec duration

10. Rated dynamic withstand 78.75


current (kA)

11. Rated short circuit making 78.75


current of EB (kA peak)

12. Basic insulation level:


i) 1.2/50 micro-sec lightning
impulse withstand voltage
(+ ve or - ve polarity)
a) To earth (kVp) 325

b) Across isolating 375


distance One terminal subjected
to lightning impulse (kVp)
and opposite terminal
subjected to power
frequency (kV rms) voltage
(as per IS)

-3-
ii) Rated 1 minute power
frequency withstand voltage ( kV rms )

a) Across isolating distance 160

b) To earth and between 140


poles

13. Min. creepage distance of 1813


support and rotating
insulator (mm)

14. Phase to Phase spacing for 1830


installation (mm)

15. Minimum clearances:


a) Phase to earth 630

b) Phase to Phase 1300


(Across the same pole) ( Bidders offering lesser clearance must substantiate the
same with adequate information on impulse withstand capability of the equipment, However
the height of Post Insulator should not be less than 770 mm in case of 72.5 KV Isolator )

16. Height of center line of 3000


terminal pad above ground
level (mm)
17. Rating of auxiliary 10 A at 220V DC with breaking capacity
contacts of 2 A DC with time constant not less
than 20 ms.

18. Seismic acceleration .................... 0.3 g horizontal ................

19. Operating time ---------------- 12 sec or less ---------------

20. Rated mechanical As per relevant standards


terminal load
21. Rated magnetizing/ 0.7
capacitive current
make/break (Amps/rms)

22. RIV at 1 MHz & 1.1


X rated phase to earth -
voltage (micro volts)
----------------------------------------------------------------------------------------------------------------------

5.0 GENERAL TECHNICAL REQUIREMENTS:

5.1 The 72.5 kV Isolator with & without earth blade shall be triple pole, single throw, double
break , three post per phase, central pole rotating type.
5.2 The blade shall open and close in a horizontal plane.

5.3 Complete isolators with all the necessary items for successful operation shall be supplied
including but not limited to the following:

-4-
5.3.1 Isolators assembled with isolator blades (main and earth), complete base frame, linkages,
operating mechanism complete etc.

5.3.2 The three poles of the 72.5 kV Isolators covered by this specification will be gang operated
with one central cabinet for the required electrical devices mounted therein.

5.4 Material of earthing blades and contacts shall be same as those of main blades and
contacts. Cross sectional area of Earthing blades and contacts shall not be less than 50%
of cross sectional area of main blades and contacts. The Earthing blades shall have
the same short time current rating (thermal and dynamic) as that of main blades.

5.5 Support insulators for all types of isolators shall be of solid core type.

5.5.1 The insulator shall be made of homogeneous and vitreous porcelain of high mechanical
and di-electric strength. It shall have sufficient mechanical strength to sustain electrical and
mechanical loading on account of wind load, short circuit forces etc., Glazing of the
porcelain shall be of uniform brown or dark brown colour with a smooth surface arranged
to shed away rain water. The porcelain shall be free from lamination and other
flaws or imperfections that might affect the mechanical or dielectric quality. It shall be
thoroughly vitrified, tough and impervious to moisture. The porcelain and metal parts shall
be assembled in such a manner and with such material that any thermal differential
expansion between the metal and porcelain parts throughout the range of temperature
specified in this specification shall not loosen the parts or create undue internal stresses
which may affect the mechanical or electrical strength or rigidity. The assembly shall not
have excessive concentration of electrical stresses in any section or across leakage
surfaces. The cement used shall not give rise to chemical reaction with metal fittings. The
insulator shall be suitable for water washing by rain or artificial means in service
condition. Profile of the insulator shall also conform to IEC-815. Insulator shall have a
minimum cantilever strength of 6 KN.

5.5.2 Cap to be provided on top of the insulator shall be of high grade cast iron or malleable steel
casting. It shall be machine faced and hot dip galvanized. The cap shall have four numbers
of tapped holes spaced on a pitch circle diameter of 127 mm for 72.5 kV Isolators & Line-
cum-Earth Switches.The holes shall be suitable for bolts with threads having anti corrosive
protection. The effective depth of threads shall not be less than the nominal diameter of the
bolt. The cap shall be so designed that it shall be free from visible corona.

5.5.3 The casting shall be free from blow holes, cracks and such other defects.

5.5.4 All the ferrous metal parts shall be hot dip galvanised smoothly as per IS: 3638 (as amended
upto date), IS: 2633 or any other equivalent authoritative standard. The material shall be
galvanised only after shop operations have been completed upon it. The metal parts before
galvanising should be thoroughly cleaned of any paint, grease, rust, scales or alkali or any
foreign deposit which are likely to come in the way of galvanising process. The coating on
the metal parts shall withstand minimum four one minute dips in copper sulphate solution as
per IEC-168.

5.5.5 The insulator unit shall be assembled in a suitable jig to ensure correct positioning of the top
and bottom metal fittings relative to one another. The faces of the metal fittings shall be
parallel and at right angles to the axis of the insulator and the corresponding holes in the
top and the bottom metal fittings shall be in a vertical plane containing the axis of the
insulator.

-5-
5.5.6 It shall be the sole responsibility of the Bidder to carry out thorough inspection and quality
checks on the insulators at the insulator Bidder's works, before offering the insulators for
HVPNL's inspection.

5.6 OPERATING MECHANISM:

a) Each 72.5 kV isolators shall be remote controlled from the control room. Provision shall be
made for local motor control also. Operating mechanism shall also be equipped with local
manual operating device intended for emergency operation when motor operating
mechanism becomes inoperative. Additional electromagnetic type interlock shall be provided
so as to prevent the operation of isolator manually or electrically when the corresponding
circuit breaker is ON.

b) Manual operating mechanism through crank and reduction gear shall be provided for the
earth switch which too will be gang operated. The operation of earth switch which too will be
gang operated. The operation of earth switch shall also be electrically inter-locked by
providing a 63.5V rated Bidder and 220 kV DC rated electro magnet. The Bidder will be fed
from single phase (132 kV/√3/110 kV/√3) CVT/ PT provided at the entry of a transmission
line in the sub-station. The normally closed contact of said contactor will form part of series
chain with other contacts of line isolator/ earth switch to prevent closing of earth switch when
the contactor is in picked up position (which means that when the concerned transmission
line is live).

5.6.2 The operating mechanism shall provide quick, simple and effective operation. The motor
operated type operating mechanism shall be suitable for remote operation of all three poles
simultaneously as well as local manual operation through crank and reduction gear. The
design of manual operation shall be such that one man shall be able to operate the isolator
without undue effort with about 20 (twenty) revolutions of the crank. The operating
mechanism shall be suitable to hold the dis-connector in CLOSE OR OPEN position and
prevent operation by gravity, wind, short circuit forces, seismic forces, vibration, shock,
accidental touching etc.,
5.6.3 Limit switches for control shall be fitted on the isolator shaft within the cabinet to sense the
open and close positions of the isolators and earth switches.
5.6.4 It shall not be possible, after final adjustment has been made, for any part of the mechanism
to be displaced at any point in the travel sufficient enough to cause improper functioning
of the isolator when the isolator is opened or closed at any speed. All holes in cranks,
linkage etc., having moving pins, shall be drilled to fit accurately so as to maintain the
minimum amount of slack and lost-motion in the entire mechanism.
5.6.5 A "local/remote" selector switch and a set of open/close push buttons shall be provided on
the control cabinet of the isolator to permit its operation through local or remote push
buttons. The remote push buttons shall be arranged by the HVPNL.

5.6.6 Provision shall be made in the control cabinet to disconnect power supply to prevent
local/remote power operation.

5.6.7 Each motor operated mechanism shall be subjected to blocked rotor test.

-6-
5.7 CONTROL CABINET:
The control cabinet of the operating mechanism shall be made out of 12 SWG (2.64 mm
thick) sheet steel duly hot dip galvanised or 10 mm thick aluminium plate or casting. Hinged
door shall be provided with pad locking arrangement. Sloping rain hood shall be provided to
cover all sides. 15 mm thick neoprene or better type of gaskets shall be provided to ensure
degree of protection of at least IP:55 as per IS:2147. The cabinet shall be suitable for
mounting on support structure with adjustment for vertical alignment. Details of these
arrangements shall be furnished along with the tender.

5.8 MOTOR:

The motor shall be suitable for three phase, 415 V, A.C. with variations as specified in this
specification. It shall be totally enclosed type if mounted outside the control cabinet. The
motor shall withstand without damage stalled torque for at least three times the duration of
tripping device. The motor shall, in all other respects, conform to the requirement of IS-325.

5.9 GEAR:

The disconnector may be required to operate occasionally, with considerably long idle
intervals. Special care shall be taken for selection of material for gear and lubrication of
gears to meet this requirement. The gears shall be made out of aluminium bronze or any
other better material and lubricated for life with graphite or better quality non draining and
non hardening type grease. Wherever necessary automatic relieving mechanism shall be
provided. Complete details of components, material, grade, self lubricating arrangement,
grade of lubricants, details of jig, fixtures and devices used for quality check, shall be
furnished by the Bidder in his offer.

5.10 GLAND PLATE AND GLANDS:


A removable gland plate with double compression type brass cable glands shall be
provided with each operating mechanism for terminating all cables. Exact quantity of glands
to be provided, shall be intimated to the Bidder.

5.11 CONTROL CIRCUITS:

Control device shall store OPEN and CLOSE command even if the corresponding switch is
momentarily pressed until the command is fully executed and the components get de-
energised after execution. Failure of auxiliary power supply or loose contact shall not cause
faulty operation.

5.12 SUPPORTING STRUCTURE :

The Isolators and isolator - cum - earth switches shall be mounted rigidly in an upright
position on their own supporting structure and not on the line or bus bar structure. The
supporting structures will be arranged by the HVPNL. The isolator and isolator-cum-earth
switch will be suitable for mounting on HVPNL's standard supporting structure HTD/ST-87R
for 72.5 kV. One print of detailed structure drawing is enclosed with the specification which
may be perused & its suitability for the offered equipment be confirmed by the bidders. Any
additional member of structure required for mounting the M O M box of isolators as well as
line-cum-earth switch will be in scope of bidder's supply.

-7-
5.13 LIMIT SWITCH:

Limit switches shall be of reputed make. Auxiliary switch shall not be used as limit switch.
Details of make, rating and type of limit switch shall be furnished in the offer.

5.14 OVERLOAD AND SINGLE PHASING PREVENTER:

Suitable relay/device shall be provided to prevent overloading of the motor. Single phase
preventer shall be provided to operate on open circuiting of any phase and shall trip off the
motor. Complete details of the devices shall be furnished in the offer.

5.15 CONTACTOR:
The Bidder shall be suitable for making and breaking stalled motor current. The Bidder coil
shall be suitable for 220 V D.C. Two nos. of Bidders shall be provided for each motor for
OPEN and CLOSE operation respectively. Make, type, rating and details of the Bidder shall
be furnished in the offer.

5.16 AUXILIARY SWITCH:

5.16.1 Each operating mechanism box shall be equipped with ten nos. of NC and ten nos. of NO
auxiliary switches exclusively for HVPNL's use. In addition, two pairs of make-before-break
NO/NC contacts shall be provided in the operating mechanism box. 3 pairs of NC and 3
pairs of NO contacts shall be provided in the auxiliary switch box for earth mechanism.

5.16.2 The auxiliary switches and auxiliary circuits shall be capable of carrying the current of atleast
10 Amps continuously
5.16.3 Auxiliary switches shall be capable of breaking atleast 2A in a 220 V D.C. circuit with a time
constant of not less than 20 milli seconds.

5.16.4 Quick Make and Break (QMB) type auxiliary switch shall have snap action built-in within the
switch.
5.16.5 The auxiliary switches shall be actuated by a cam or similar arrangement directly mounted
on the isolator and shall be without any intermediate levels, linkages etc., to ensure fool
proof operation.

5.17 SPACE HEATERS:


Space heater, thermostatically controlled, suitable for single phase 240 V AC supply shall
be provided for motor operated operating mechanism to prevent condensation. A switch
and fuse/link shall be provided in the operating mechanism.
5.18 TERMINAL BLOCK AND WIRING:
Each operating mechanism shall be provided with 1100 V grade stud type terminal block
having washers, nuts & check nuts. All auxiliary switches, interlocks and other terminals
shall be wired upto terminal block. The terminal block shall have at least 20% extra
terminals. All wiring shall be carried out with 1100 V grade insulated 2.5 mm2 copper
wires.

5.19 DUTY REQUIREMENTS:


5.19.1 Isolators and earth switches shall be capable of withstanding the dynamic and thermal
effects of the maximum possible short circuit current of the systems in their closed position.
They shall be constructed such that they do not open under influence of short circuit
current.

-8-
5.19.2 The earth switches, wherever provided, shall be constructionally interlocked so that the
earth switch can be operated only when the isolator is open and not vice-versa. The
constructional interlocks shall be built-in construction of isolator and shall be in addition to
the electrical and mechanical interlocks provided in the operating mechanism.
5.19.3 In addition to the constructional interlock, isolator and earth switches shall have provision
to prevent their electrical and manual operation unless the associated and other
interlocking conditions are met. All these interlocks shall be of fail safe type. Suitable
individual interlocking coil arrangements shall be provided. The interlocking coil shall be
suitable for continuous operation from DC supply and within a variation range stipulated in
this volume.

5.19.4 The isolator shall be capable of making/breaking normal currents when no voltage occurs
across the terminals of each pole of isolator on account of make/break operation.

5.19.5 The isolator shall be capable of making/ breaking magnetising current of 0.7 A at 0.15
power factor and capacitive current of 0.7 A at 0.15 power factor.

5.19.6 Isolator and earth switches shall be able to bear on the terminals the total forces including
wind loading and electrodynamic forces on the attached conductor without impairing
reliability or current carrying capacity.

5.20 INTERIOR ILLUMINATION:

A switch, HRC fuse and holder suitable for a 240 V lamp shall be provided in one of the
motor operated mechanism box of isolator and manually operated mechanism box of earth
switch.
5.21 POWER SOCKET:

A single phase 240 V 15A power socket and switch shall be provided in the motor operated
operating mechanisms of the Isolators poles.

5.22 CONTROL AND AUXILIARY SUPPLY:

A three phase switch with HRC fuses for phases and link for neutral shall be provided for
power supply and a 2 way switch with HRC fuses shall be provided for control supply in the
motor operated mechanisms of the Isolators.

5.23 ACCESSORIES:

The accessories to be provided on the isolator shall include but not limited to the following:

5.23.1 POSITION INDICATOR:

A position indicator to show whether the isolator is in ON or OFF position.

5.23.2 COUNTER BALANCE SPRINGS:


Counter balance springs, cushions etc., shall be provided to prevent impact at the end of
travel both on opening and closing of the isolator. The springs shall be made of durable and
non-rusting type alloy.

5.24 NAME PLATES:

Isolator and Earthing switches and their operating devices shall be provided with a name

-9-
plate. The name plate shall be weather proof and corrosion proof. It shall be mounted in
such a position that it shall be visible in the position of normal service and installation. It
shall carry the following information duly engraved or punched on it.

5.24.1 Isolator Base:


Name of utility (i.e. HVPNL) :
Name of Manufacturer :
P.O. No. :
Type Designation :
Manufacturer's serial number :
Rated voltage :
Rated normal current :
Rated short time current (rms) :
and duration :
Rated short time peak current (kAp):
Weight :

5.24.2 Earthing Switch:


Name of utility (i.e. HVPNL) :
Name of Manufacturer :
P.O. No. :
Type Designation :
Manufacturer's serial number :
Rated voltage :
Rated short time current (rms) :
and duration :
Rated short time peak current (kAp) :
Weight :

5.24.3 Operating Device:


Name of utility (i.e. HVPNL) :
Name of Manufacturer :
P.O. No. :
Type Designation :
Reduction gear ratio :
AC Motor :
i) Rated auxiliary voltage :
ii) Starting current :
iii) Designation of AC motor as per
per IS:4722 :
iv) Starting torque at 80%
of supply voltage :
v) Over travel in degrees after
cutting off supply :
Total operating time in seconds :
i) CLOSE operation - electrical :
ii) OPEN Operation - electrical :
-do- - manual :
Space Heater :
Rated voltage and power Auxiliary contacts
i) Rated current (Amps) :
ii) Time constant (ms) :
iii) No. of contacts used (NC & NO) :
iv) No. of free contacts (NC & NO) :

- 10 -
Terminal blocks and wiring
i) Rated current :
ii) Voltage grade and type :

5.25 PADLOCKING DEVICE:

All Isolator and Earthing switches shall be provided with padlocking device to permit
locking of the isolator and Earthing switch in both fully open and fully closed
positions. Power driven isolator and Earthing switch shall be arranged to be
interlocked electrically also.

5.26 SIGNALLING:

5.26.1 Signalling of the close position shall not take place unless the movable contact has
set in a position in which the rated normal current, the peak withstand current and
the short time withstand current can be carried safely.

5.26.2 Signalling of the open position shall not take place unless the movable contact has
reached the position such that the clearance between the moveable and fixed
contacts is at least 80% of the isolating distance.

5.27 EARTHING:

5.27.1 Flexible copper connections shall be provided between rotating earth blades and the
frame which shall have a cross-section of atleast 50 mm2 and shall be tinned or
suitably treated against corrosion.

5.27.2 The frame of each disconnector and Earthing switch shall be provided with two
reliable Earthing terminals for connection to the HVPNL's Earthing conductor/flat and
also clamping screws suitable for carrying specified short time current. Flexible
ground connections shall be provided for connecting operating handle to the
Earthing flat. The diameter of clamping screw shall be atleast 12 mm. The
connecting point shall be marked with earth symbol.

5.28 DESIGN AND CONSTRUCTION:

5.28.1 Full particulars of design, manufacture, jig template and quality control devices
developed for manufacture of the equipment offered in respect of but not limited to
the following, shall be furnished with drawings and descriptions alongwith the
tender.

i) Contacts, material, current density etc.,


ii) Design of contact pressure.
iii) Contact support and fixing arrangement on isolators.
iv) Turn and twist mechanism, clamps, locks etc.,
v) Bearings, housing of bearings, bushes etc.,
vi) Balancing of heights,
vii) Coupling pipes, joints, connection adjustments.
viii) Base plates.
ix) Down pipe guides and joints.
x) Brass bushes and bearings at various joints.
xi) Operating mechanism, type of gear motor, limit switch, aux.
switch, timers, size and thickness of box, degree of

- 11 -
protection, gland plate, gland etc.,
xii) Nuts, bolts and fasteners.
xiii) Interlocking devices.

Offers without the above information or with incomplete information shall not be
considered.

5.28.2 FASTENERS:

Nuts, bolts and washers of 5/8" and higher size shall be hot dip galvanised. The
bolts used on tapped holes of insulator cap shall be galvanised by centrifuge
process to avoid excess deposition of zinc on threads. Nuts, bolts and washers of
less than 5/8" size shall be of stainless steel when used on live parts and nickel
plated brass in other parts.
5.28.3 CONTACTS:

Contacts shall be made out of hard drawn electrolytic grade copper. Arcing
contacts wherever provided shall close first and open last. The contacts surface
shall be silver plated. Fabrication of contact shall be made with suitable jig to
avoid deviations during production. Details of size and shape of contacts, springs,
back plate, fixing arrangements design of contact pressure, life of contacts, limit of
temperature rise etc., shall be furnished along with the tender. The moving
contacts of tubular section shall be so dimensioned as to carry the rated current.

5.28.4 MOUNTING OF CONTACTS:

The contacts shall rest on a brass block and with initial tension. Suitable device
shall be provided to prevent dashing. Fabrication, welding etc., shall be done in
suitable jig to avoid deviations during production.

5.28.5 TERMINAL PAD:

The terminal pad shall be suitable for connection to aluminium terminal connector
through bimetallic plate wherever necessary. It shall be made out of electrolytic
copper heavily silver plated. Dimensions of the terminal pad shall be furnished with
the tender.

5.28.6 MOVING BLADE:

Moving blade shall be made out of hard drawn Electrolytic grade copper. Contact
surface of moving blade shall be heavily silver plated. The surface shall be wiped
during closing and opening operations to remove any film, oxide coating etc., Wiping
action shall not cause scouring or abrasion of surfaces.

5.28.7 The rotating insulator shall be mounted on housing with bearing housing. The
housing shall be made of gravity di-cast aluminium with smooth surfaces suitably
machined for seating the bearings. Two nos. of bearings with adequate shaft
diameter and distance between the bearings shall be provided to avoid wobbling
during operations. The bearings shall be of atleast 50 mm shaft diameter. The
bearings shall be of reputed make eg. SKF, HMT, NBC, TATA, and lubricated for
life. All other friction locations shall be provided with bearings, bushes, joints,
springs etc., shall be so designed that no lubrication shall be required during
service. Complete details of bearings, bushes, housing, greasing etc., shall be

- 12 -
furnished with the tender. The Earthing switch shaft shall also be provided with
necessary bearings.

5.28.8 Tandem pipes shall be of adequately dimensioned for the given duty and shall be
class B. Base plate of insulators for connection of tandem pipe shall be made out of
one piece 10 mm thick MS plate. Bolt and shackle device shall be used to connect
tandem pipe to the base plate.

5.28.9 The operating pipe too shall be of class B and adequately dimensioned for the given
duty. The pipe shall be terminated into a suitable swivel or universal type joint
between the insulator bottom bearing and the operating mechanism to take care of
marginal angular misalignment at site.

5.28.10 Each phase of isolator shall be provided with a rigid base fabricated from steel
sections. The base shall be suitable for mounting on support structures.
Fabrication, welding etc., shall be done by suitable jig, power press and templates
to avoid deviations during production. Details of dimensions sections, jig templates
and device used for production of the base shall be furnished with the tender.
5.29 TERMINAL CONNECTORS:

5.29.1 All Isolators shall be provided with universal type terminal connectors suitable for
0.4 Sq. inch ACSR conductor. The unit rate for types of terminal connector shall be
quoted in the relevant schedule.

5.29.2 The terminal connectors shall meet the following requirements:


i) Terminal connectors shall be manufactured and tested as per IS:5561.
ii) All castings shall be free from blow holes, surface blisters, cracks and
cavities. All sharp edges and corners shall be blurred and rounded off.
iii) No part of a clamp shall be less than 10 mm thick.
iv) All ferrous parts shall be hot dip galvanised conforming to IS:2629.
v) For bimetallic connectors, copper alloy liner of minimum thickness of 2
mm shall be cast integral with aluminium body.
vi) Flexible connectors shall be made from tinned copper / aluminium
sheets.
vii) All current carrying parts shall be designed and manufactured to
have minimum contact resistance.
viii) Connectors shall be designed to be corona free in accordance with
the requirements stipulated in IS:5561.

5.29.3 Wherever necessary bimetallic strip of standard quality shall be used to avoid
galvanic corrosion.

5.30 ASSEMBLY:
The disconnector shall be fully assembled at the works of the Bidder and
operations shall be carried out on it to ascertain that all parts fit correctly and
function satisfactorily.

5.31 PAINTING, GALVANISING AND CLIMATE PROOFING:


All interiors and exteriors of enclosures, cabinets and other metal parts shall be
thoroughly cleaned to remove all rust, scales, corrosion, grease and other
adhering foreign matter and the surfaces treated by recognised phosphating (e.g.
seven tank phosphating sequence). After such preparation of surfaces, two coats

- 13 -
of zinc oxide primer shall be given by suitable staving and air drying before final
painting. Colour of the final paints shall be of shade no. 631 of IS:5 i.e. epoxy light
grey. The finally painted cubicle shall present aesthetically pleasing appearance
free from any dent or uneven surface.

5.31.1 Paint inside the metallic housing shall be of anti-condensation type and the paint on
outside surfaces shall be suitable for outdoor installation.

5.31.2 All components shall be given adequate treatment of climate proofing as per
IS:3202 so as to withstand corrosive and severe service conditions.

5.31.3 All metal parts not suitable for painting such as structural steel, pipes, rods, levers,
linkages, nuts and bolts used in other than current path etc., shall be hot dip
galvanised and shall be capable to prevent corrosion in view of the severe climatic
conditions.

5.31.4 Complete details of painting, galvanising and climate proofing of the equipment shall
be furnished in the tender.

6.0 TESTS:

6.1 TYPE TESTS:


The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or
witnessed by HVPN or another electric power utility and be submitted by the
successful bidder to HVPNL for approval as schedule given in Bar Chart.
i) Insulation level test
ii) Temperature rise test
iii) Rated peak withstand current and rated short time withstand current test
iv) Short circuit making capacity test of earthing switch
v) Operation and mechanical endurance test
6.2 ROUTINE TESTS:
As per quality assurance program (QAP).
63 ACCEPTANCE TESTS:
The following acceptance tests as stipulated in the relevant IS:9921 (PART-IV) 1985
shall be carried out by the Supplier in presence of HVPNL representative, unless
dispensed with in writing by the HVPNL.
i) Power Frequency withstand voltage dry test of main circuit
ii) Voltage test on control auxiliary circuits
iii) Measurement of resistance of main circuit
iv) Mechanical operating test

7.0 INSPECTION:

i) The HVPNL shall have access at all times to the works and all other places
of manufacture, where the dis-connectors, earth switches and associated
equipment are being manufactured and the Bidder shall provide all facilities

- 14 -
with out extra cost for unrestricted inspection of the works, raw materials
manufacture of all the accessories and for conducting necessary tests as
detailed herein.

ii) The Bidder shall keep the HVPNL informed in advance of the time of
starting and of the progress of manufacture of equipment in its various
stages so that arrangements could be made for inspection

iii) No material shall be despatched from its point of manufacture unless the
material has been satisfactorily inspected and tested.

iv) The acceptance of any quantity of the equipment shall in no way relieve the
Bidder of his responsibility for meeting all the requirements of this
specification and shall not prevent subsequent rejection if such equipment
are later found to be defective.

8.0 DOCUMENTATION:
The successful bidder shall submit four sets of following drawings for HVPNL
approval.

LIST OF DRAWINGS AND DOCUMENTS:

The Bidder shall furnish four sets of following drawings alongwith his offer:
a) General outline and assembly drawings of the dis-connector operating
mechanism, structure, insulator and terminal connector.

b) Sectional views and descriptive details of items such as moving blades,


contacts, arms contact pressure, contact support bearing housing of
bearings, balancing of heights, phase coupling pipes, base plate,
operating shaft, guides.

c) Name plate.

d) Schematic drawing along with detailed write-up.

e) Wiring diagram
NOTE: All above drawings should be a minimum space (14x10cm) for stamping
the approval of drawings by HVPNL.

8.5 Instruction Manuals:

Twenty copies of the erection, operation and maintenance manuals in English


be supplied for each type of dis-connector one month prior to despatch of the
equipment. The manual shall be bound volumes and shall contain all drawings and
information required for erection, operation and maintenance of the dis-connector
including but not limited to the following particulars:

a) Marked erection prints identifying the component parts of the dis-connector


as shipped with assembly drawings.
b) Detailed dimensions and description of all auxiliaries.
c) Detailed views of the insulator stacks, metallic, operating mechanism,
structure, interlocks, spare parts etc.,

- 15 -
ANNEXURE-I
(Isolators)

LIST OF SPECIAL TESTS TO BE CARRIED OUT

---------------------------------------------------------------------------------------------------------
Sl. Name of the Test Standard to which it
No. Conforms
----------------------------------------------------------------------------------------------------------

1. Tests on insulators IS:2544


IEC:168

2. Tests on terminal connectors IS:5561

3. Tests on galvanised components IS:2633

-------------------------------------------------------------------------------------------------------

- 16 -
SECTION - 4
CHAPTER - 3
TECHNICAL SPECIFICATION FOR 72.5 kV SF6 GAS CIRCUIT BREAKERS
1.0 SCOPE:
1.1 This specification provides for design, engineering, manufacture, stage testing, inspection and
testing before supply, packing, forwarding and delivery at site of 72.5 kV, 3 pole SF6 gas filled
outdoor circuit breakers along with terminal connectors, structures, all the accessories and
auxiliary equipment and mandatory spares and maintenance equipment for the satisfactory
operation in various substations of the state as specified here in.
1.2 It is not the intent to specify completely all the details of design and construction of the circuit
breakers. However, the breakers shall conform in all respects to the high standard of
engineering design and workmanship and shall be capable of performing in continuous
commercial operation up to the Bidder’s guarantee in a manner acceptable to the HVPNL.
The circuit breakers equipment shall conform in all respects to high standards of engineering
design and workmanship and shall be capable of performing in continuous commercial
operation up to the bidders guarantee acceptable to the HVPNL. The equipment offered shall
be complete in all respect necessary for its effective and trouble free operation. Such
components shall be deemed to be within the scope of supply irrespective of whether those
are specially brought out in this specification and or the commercial order or not. All similar
parts particularly movable ones shall be interchangeable.
2.0 STANDARDS:
2.1 The circuit breakers shall conform to the latest revisions with amendments available at the
time of testing of relevant standards, rules and codes, some of which are listed herein for
ready reference.
Sl. No. Standard No. Title
1. IEC-56 Specification for alternating current circuit breakers.
2. IEC-376 Specification and acceptance of new supply of sulphur
hexafluoride.
3. IS-5578& 11353 Making and arrangement for switchgear bus-bar, main
connections and auxiliary wiring.
4. IS-2147 Degree of protection provided for enclosures for low
voltage switchgear and control gear.
5 IS-325 Specification for three phase induction motors.
6. IS-13118 Specification for circuit breakers.
7. IS-2629 Recommended practice for hot dip galvanising
of iron and steel.
8. IEC-137 Bushings for AC Voltages.
9. IS-2099 High voltage porcelain bushings.
10. IS-4379 Identification of the contents of Industrial Gas Cylinders.
11. IS-7285 Seamless high carbon steel cylinders for permanent and
high pressure liquefiable gases
12. IS-802 Code of practice for use of structural steel in (PART-1)
overhead transmission line towers.

-1-
2.2 Equipment meeting with the requirement of other authoritative Standards, which ensure equal
or better performance than the standards mentioned above, shall also be considered. When
the equipment offered by the Bidder conforms to other standards salient points of difference
between standards adopted and the standards specified in this specification shall be clearly
brought out in the relevant schedule. Four copies of such standards with authentic translation
in English shall be furnished alongwith the offer.
3.0 SERVICE CONDITIONS:
3.1 As per section - I Vol. – II

3.2 AUXILIARY POWER SUPPLY:


Auxiliary electrical equipment shall be suitable for operation on the following supply system.
a. Power Devices 415 V, 3 phase 4 wire 50 Hz,
(like drive motors) Neutral grounded AC supply.
b. D.C. Alarm, control Two independent sources of 220 V DC, ungrounded 2 wire
Protective Device Substation wise exact details shall be furnished to the
Successful bidder
c. Lighting 240 V, single phase, 50 Hz AC supply.
Each of the foregoing supplies shall be made available by the HVPNL at the terminal point for
each circuit breaker for operation of accessories and auxiliary equipment. Bidder's scope
include supply of interconnecting cables, terminal boxes etc., The above supply voltage may
vary as below and all devices shall be suitable for continuous operation over the entire
range of voltages.
i) AC supply : voltage + 10% & -15%, frequency ± 5%
ii) D.C. Supply : ±10%.

4.0 PRINCIPAL PARAMETERS:


The SF-6 gas Circuit Breakers covered in this specification shall meet the technical
requirements listed hereunder.
PRINCIPAL TECHNICAL PARAMETERS:
-------------------------------------------------------------------------------------------------------
Sl. Item Specification
No. 72.5 kV
-------------------------------------------------------------------------------------------------------
1. Rated voltage (kV rms), 72.5
frequency (Hz.) 50
2. Continuous current 1600
rating (A rms)
3. Type 3 pole outdoor SF6
4. Mounting Hot dip galvanised lattice steel support structure, bolted
type to be supplied by the Bidder.
5. Number of Poles 3

-2-
6. Type of Operation 3 pole gang
Operated

7. Phase to phase spacing 1400


in the switchyard i.e.
Interpole spacing for
breaker (mm)
8. Required ground 3000
clearance from the lowest
live terminal if both the
terminals are not in
the same horizontal plane. (mm)
9. Phase to earth 800
clearance (mm)
10. Height of concrete plinth 150
(to be provided by the
HVPNL) (mm)
11. Minimum height of the 2550
lowest part of the ( Bidders offering lesser clearances must
support insulator from substantiate the same with adequate
ground level (mm). Information on impulse test withstand
capability of equipment)
12. Operating mechanism Spring / Pneumatic Spring / Pneumatic
(with unit compressor) (with unit compressor)
13 Auto reclosing duty Three Single and
phase three phase
14. Rated operating duty 0-0.3 sec. -CO- 3 min -CO cycle
15. "First pole to clear" As per IS-13118
factor (Type of tripping) (Trip free)
16. Max. closing time (ms) ------------- 150 ------------
17. Max. total break time (ms) Less than 3 cycles or 60 ms

-3-
18. 1.2/50 microsecond 325
impulse withstand
voltage (kV peak)

19. 1 minute power 170


frequency withstand
voltage (kV rms)
20. Rated breaking current capacity:-
i) Line charging at 10
rated voltage at 90 deg.
leading power factor
(A) rms
ii) Small inductive ----------------- 0.5 to 10 -------------------
current (A) rms without exceeding switching o/v 2.0 p.u
iii) Cable charging 125
breaking current (A)
iv) Short circuit current
a) AC component (kA rms) 31.5
b) % DC component Corresponding to minimum opening time as per
IEC-56.
c) Duration of short circuit 1 sec

22. Rated short circuit 78.75


making current capacity (kA)
23. Permissible limit of As per clause 5.27
temperature rise
24. Max. acceptable difference in
the instants of closing/opening
of contacts
i. Within a pole (ms) 5
ii. Between poles (ms) 10
25. Min. creepage distance of 1813
support insulator (mm)
26. Short time current carrying 31.5
capability for one second (kA)

-4-
27. i) Rating of auxiliary
contacts ----- 10 A at 220 V D.C. -------
ii) No. of auxiliary 10 NO and 10 NC as spare with due
contacts provision to add more if required

28. Breaking capacity of 2 A DC with the circuit time


auxiliary contacts constant not less than 20 ms
29 . Noise level at base ------- 140 db (max.) -----------
and upto 50 meters
30 Seismic acceleration ------ 0.3g (horizontal) --------
31. Min. Corona extinction - - -
voltage kv (rms)
-------------------------------------------------------------------------------------------------------------
5.0 GENERAL TECHNICAL REQUIREMENTS:
5.1 Circuit breakers offered shall be sulphur hexaflouride (SF6) type only.
5.2 Any part of the breakers, especially the removable ones, shall be freely interchangeable
without the necessity of any modification at site.
5.3 Circuit breaker shall comprise of three identical single pole units. The 72.5 kV circuit breaker
is not meant for single pole re-closure. The units for these breakers shall be linked together
mechanically. Complete circuit breaker with all the items necessary for successful operation
shall be supplied, including but not limited to the following:
5.3.1 Breaker assemblies with bases, support structure for circuit breaker as well as for control
cabinet, central control cabinet and foundation bolts for main structure as well as control
cabinet and central control cabinet (except concrete foundations), terminals and operating
mechanisms are included in the scope of supply.
5.3.2 Compressed SF6 gas, pneumatic systems complete including compressors, tanks, piping,
fittings, valves and controls and necessary supports for interpole piping for pneumatic
systems.
5.3.3 Instruments, gauges and other devices for SF6 gas pressure, pneumatic pressure
supervision.
5.3.4 All necessary parts to provide a complete and operable circuit breaker installation such as
main equipment, terminal, control parts, connectors and other devices, whether specifically
called for herein or not.
5.4 The support structure of circuit breaker as well as that of control cabinet shall be hot dip
galvanised. All other parts can be grey colour painted as per shade 631 of IS-5.
5.5 Circuit breaker shall be suitable for hot line washing.
5.6 All breakers shall be supplied with universal type terminal connectors.
5.7 The current density adopted for the design of the terminal pads shall in no case exceed the
following values.
5.8 For copper pads - 1.6 A/sq.mm. and others - 1.0 A/sq.mm.

-5-
5.9 CONTACTS:
5.9.1 All making and breaking contacts shall be sealed free from atmospheric effects. Contacts
shall be designed to have adequate thermal and current carrying capacity for the duty
specified and to have a life expectancy so that frequent replacements due to excessive
burning will not be necessary. Provision shall be made for rapid dissipation of heat generated
by the arc on opening.
5.9.2 Main contacts shall be the first to open and the last to close so that there will be little contact
burning and wear.
5.9.3 If arcing contacts are used they shall be the first to close and the last to open. These shall be
easily accessible for inspection and replacement. If there are no separately mounted arcing
contacts the main contacts shall be easily accessible for inspection and replacements. Tips
of arcing contacts and main contacts shall be silver plated or have tungsten alloy tipping.
5.9.4 Any device provided for voltage grading to damp oscillations or to prevent restrike prior to
the complete interruption of the circuit or to limit over-voltages on closing shall have a life
expectancy comparable to that of the breaker as a whole.
5.9.5 Breakers shall be so designed that when operated within their specified rating, the
temperature of each part will be limited to values consistent with a long life of the material
used. The temperature shall not exceed that indicated in IEC-56 under specified ambient
conditions.
5.9.6 Contacts shall be kept permanently under pressure of SF6 gas. The poles shall be partially
filled with SF6 gas at the time of despatch and only topping upto required pressure shall be
permitted at site. The gap between the open contacts shall be such that it can withstand
atleast the rated phase to ground voltage continuously at zero gauge pressure of SF6 gas due
to its leakage.
5.10 PORCELAIN HOUSING:
5.10.1 The porcelain housing shall be of single piece construction without any joint or coupling. It
shall be made of homogeneous, vitreous porcelain of high mechanical and dielectric
strength. Glazing of porcelain shall be uniform brown or dark brown colour with a smooth
surface arranged to shed away rain water or condensed water particles (fog), free from
blisters, burns and similar other defects.
5.11 ADDITIONAL REQUIREMENTS:
a) The circuit breakers shall be single pressure type and single break, the design and
construction of the circuit breaker shall be such that there is minimum possibility of gas
leakage and entry of moisture. There should not be any condensation of SF6 gas on the
internal insulating surface of the circuit breaker.
b) All gasketed surfaces shall be smooth, straight and reinforced, if necessary to minimise
distortion and to make a tight seal. Where the operating rod of the operating mechanism
connected to the arc chamber (SF6 media) adequate suitable Oring seals shall be provided.
The test holes for leakage test of the internal seals shall also be provided.
c) In the interrupter assembly there shall be a absorbing product box to eliminate SF6
decomposition products and moisture. The material used in the construction of the circuit
breakers shall be fully compatible with SF6 gas.
d) Each pole shall form an enclosure filled with SF6 gas independent of the other two poles. The
SF6 gas density of each pole shall be monitored and regulated by individual pressure
switches
e) The SF6 gas density monitor shall be adequately temp. compensated. The density monitor
shall meet the following requirements:

-6-
i) It shall be possible to dismantle the density monitor for checking/ replacement without
draining the SF6 gas by using suitable interlocked non-return couplings.
ii) It shall damp the pressure pulsation while filling the gas in service so that the flickering
of the pressure switch contacts does not take place.
iii) A pressure indicator shall also be supplied.
iv) The alarm and trip setting shall be such that:
a) Advance warning can be given for the low pressure below an unacceptable level.
b) After alarm, the breaker shall open if the pressure falls below pre- determined value.
f) Means for pressure relief shall be provided in the gas chamber of circuit breaker to avoid
damages or distortion during occurrence of abnormal pressure increase or shock waves
generated by internal electric faults. The position of vents, diaphragms and pressure relief
devices shall be so arranged as to minimise danger to the operators in the event of gas or
vapour escaping under pressure.
g) Facility shall also be provided to reduce the gas pressure within the breaker to a value not
exceeding 6 millibar for 72.5 kV within 4 hours or less. Each circuit breaker shall be capable of
withstanding this degree of vacuum without distortion or failure of any part.
h) Sufficient SF6 gas shall be provided to fill all the circuit breakers installed. In addition to this
20% of the total gas requirement shall be supplied in separate cylinders as spare requirement.
The pressure loss in the breaker shall not be more than 1% per year under normal operating
conditions.
i) Provisions shall be made for attaching an operation analyzer after installation at site to record
contact travel, speed and making measurement of operation timings and synchronization of
contacts in one pole.
5.12 SULPHUR HEXAFLUORIDE GAS (SF6 GAS):
a) The SF6 gas shall comply with IEC-376, 376A and 376B and be suitable in all respects for
use in the switchgear under the worst operating conditions.
b) The high pressure cylinders in which the SF6 gas is shipped and stored at site shall comply
with requirements of the following standards and regulations:
IS:4379 Identification of the contents of industrial gas cylinders.
IS:7285 Seamless high carbon steel cylinders for permanent and high pressure
liquefiable gases.
The cylinders shall also meet Indian Boiler regulations.
c) Test: SF6 gas shall be tested for purity, dew point, breakdown voltage, water contents as per
IEC-376, 376A and 376B and test certificates shall be furnished to HVPNL indicating all the
tests as per IEC-376 for each lot of SF6 gas.
5.13 DUTY REQUIREMENTS:
5.13.1 The circuit breakers shall be totally re-strike free under all duty conditions and shall
be capable of performing specified duties without opening resistors.
5.13.2 The circuit breakers shall meet the duty requirements for any type of fault or fault
location, for line charging and roping when used on an effectively grounded
system and perform make and break operations as per stipulated duty cycles
satisfactorily.
5.13.3 The Circuit Breakers shall be capable of:

-7-
i) Clearing short line faults (Kilo metric faults) with source impedance behind
the bus equivalent to symmetrical fault current specified.
ii) Breaking inductive currents of 0.5 to 10A without switching over-voltage
exceeding 2.3 p.u.
iii) Breaking 25% of the rated fault current at twice rated voltage under phase
opposition condition.
5.13.4 The critical current which gives the longest arc duration at lockout pressure of
extinguishing medium and the arc duration shall be indicated.
5.13.5 The breakers shall satisfactorily withstand the high stresses imposed on them
during fault clearing, load rejection and re-energisation of lines with trapped charges.
The breakers shall also withstand the voltage specified in clause 4.0 "Principal
Parameters" of this specification.
5.14 TOTAL BREAK TIME:
5.14.1 The "Total Break Time" as specified in clause 4.0, "Principal Parameters" of this
section shall not be exceeded under any of the following duties:
i) Test duties 1,2,3,4,5 (with TRV as per IEC-56).
ii) Short line fault L90, L75 (with TRV as per IEC-56).
5.14.2 The Bidder may please note that there is only one specified break time of the breaker
which shall not be exceeded under any duty conditions specified such as with
the combined variation of the trip coil voltage, (85-110%) pneumatic pressure and
arc extinguishing medium pressure etc., While furnishing the proof for the total
break time of complete circuit breaker, the Bidder may specifically bring out the
effect of non-simultaneity between contacts within a pole or between poles and show
how it is covered in the guaranteed total break time.
5.14.3 The values guaranteed shall be supported with the type test reports.
5.15 OPERATING MECHANISM AND ASSOCIATED EQUIPMENTS:
5.15.1 The circuit breakers shall be designed for electrical local as well as remote control
5.15.2 (i) The mechanism shall be adequately designed for specified tripping and re-closing
duty. The entire operating mechanism control circuitry, individual breaker compressor
unit etc. as required shall be housed in an out-door type,CRCA steel enclosure. This
enclosure shall conform to degree of protection IP-55 of ISS-2147. The enclosure shall
be invariable mounted on a separate concrete plinth of 150 mm height.
5.15.2 (ii) The operating mechanism shall be spring closing and spring tripping through electric
motor for 72.5kV SF-6 Circuit Breaker. The mechanism shall be adequately designed
for specified tripping and re-closing duty. The entire operating mechanism control
circuitry as required shall be housed in an out-door type,CRCA steel enclosure. The
enclosure shall be invariable mounted on a separate concrete plinth of 150 mm height.
5.15.3 All working parts in the mechanism shall be of corrosion resistant material. All bearings
which require greasing, shall be equipped with pressure grease fittings.
5.15.4 The design of the operating mechanism shall be such that it shall be practically
maintenance free. The guaranteed years of maintenance- free operation, the number
of full load and full rated short circuit current breaking/operation without enquiring any
maintenance or overhauling, shall be clearly stated in the bid. As far as possible the
need for lubricating the operating mechanism shall be kept to the minimum and
eliminated altogether if possible.

-8-
5.15.5 The operating mechanism shall be non-pumping (and trip free) electrically
pneumatically under every method of closing. There shall be no rebounds in the
mechanism and it shall not require any critical adjustments at site. Operation of the
power operated closing device, when the circuit breaker is already closed, shall not
cause damage to the circuit breaker or endanger the operator. Provision shall be
made for attaching an operation analyser to facilitate testing of breaker at site.
5.15.6 A mechanical indicator shall be provided to show open and close position of the
breaker. It shall be located in a position where it will be visible to a man standing on
the ground level with the mechanism housing closed. An operation counter shall also
be provided in the central control cabinet.
5.15.7 The Bidder shall furnish detailed operation and maintenance manual of the mechanism
along with the operation manual for the circuit breakers.
5.16 CONTROL:
5.16.1 The close and trip circuits shall be designed to permit use of momentary contact
switches and push buttons.
5.16.2 Each breaker pole shall be provided with two (2) independent tripping circuits, valves
and coils each connected to a different set of protective relays.
5.16.3 The breaker shall normally be operated by remote electrical control. Electrical tripping
shall be performed by shunt trip coils. However, provisions shall be made for local
electrical control. For this purpose a local/remote selector switch and close and trip
push buttons shall be provided in the breaker central control cabinet. Remote located
push buttons and indicating lamps shall be provided by the HVPNL.
5.16.4 The trip coils shall be suitable for trip circuit supervision. The trip circuit supervision
relay would be provided by the HVPNL. Necessary terminals shall be provided in the
central control cabinet of the circuit breaker by the Bidder.
5.16.5 Closing coil shall operate correctly at all values of voltage between 85% and 110% of
the rated voltage. Shunt trip shall operate correctly under all operating conditions of
the circuit breaker upto the rated breaking capacity of the circuit breaker and at all
values of supply voltage between 85% and 110% of rated voltage. If additional
elements are introduced in the trip coil circuit their successful operation and reliability
for similar applications on outdoor circuit breakers shall be clearly brought out in
the additional information schedules. In the absence of adequate details the offer is
likely to be rejected.
5.16.6 Suitable relay for monitoring of DC supply voltage to the control cabinet shall be
provided. The pressure switches used for interlock purposes shall have adequate
contact ratings to be directly used in the closing and tripping circuits. In case the
contacts are not adequately rated and multiplying relays are used then the interlock
for closing/opening operation of breaker shall be with No logic of the relay i.e. if the
DC supply to the interlock circuit fails then it is essential that breaker trips in
order to protect the switchgear and connected equipment like transformers etc., for
any possible faults at that time. Provision for automatic tripping of the breaker shall
be made alongwith the flag indication for non-availability of DC supply. The
connection must be such that capacitor provided for this purpose gets charged from
the DC source provided by the Board only and the capacitor supply is released for the
tripping circuit as soon as DC supply fails. It must be possible to close the breaker
only after restoration of DC supply. The entire arrangement of CTD must be
accommodated in a separate box and it shall be mounted to control cubicle
5.16.7 For pneumatically and spring operated mechanisms a local manual closing device
which can be easily operated by one man standing on the ground shall also be

-9-
provided for maintenance purposes and direction of motion of handle shall be clearly
marked.
5.16.8 The auxiliary switch of the breaker shall be preferably positively driven by the breaker
operating rod and where due to construction features, same is not possible a plug-in
device shall be provided to simulate the opening and closing operations of circuit
breaker for the purpose of testing control circuits.
5.17 MOTOR COMPRESSED SPRING CHARGING MECHANISM:
Spring operated mechanism shall be complete with motor, opening spring, closing
spring and all other necessary accessories to make the mechanism a complete
unit. Breaker operation shall be independent of motor which shall be used solely for
the purpose of charging the closing spring. Motor rating shall be such that it requires
only 15 seconds for fully charging the closing spring. Closing operation shall
compress the opening spring and keep ready for tripping. The mechanism shall be
provided with means for charging the spring by hand. This operation shall be carried
out with the doors of the cubicle open. During this process no electrical or
mechanical operation of the mechanism shall endanger the operator or damage
the equipment. A mechanical indicating device shall be provided to indicate the state
of the charge spring and shall be visible with the door of the cubicle closed. An
alarm shall be provided for spring failing to be charged by a pre-set time after circuit
breaker closing. The spring mechanism shall be fitted with a local manual release,
preferably by a push button to avoid in advertent operation. Means shall be
provided for discharging the spring when the circuit breaker is in the open position
without circuit breaker attempting to close.
5.18 PNEUMATICALLY OPERATED MECHANISM:
a) Individual compressor units (ICU) shall be provided for pneumatically operated
circuit breakers.
b) The ICU shall be complete with air piping and accessories, all stop valves,
tees, pressure reducers etc., required for normal operation of the breaker.
c) The breaker local receivers shall comply with the requirements in clause 5.29
and shall have sufficient capacity for two CO operations of the breakers at the
lowest pressure for auto reclosing duty without refilling. The Bidder shall ensure
that rated pressure. is available at all the breaker locations.
d) Independently adjustable pressure switches with potential free, ungrounded
contacts to actuate a lockout device shall be provided. This lockout device with
provision of remote alarm indication shall be incorporated in each circuit
breaker to prevent operation whenever the pressure of the operating
mechanism is below that of parameter required for satisfactory operation of the
circuit breakers. The scheme should permit operation of all blocking and
alarm relays as soon as the pressure transient present during the rapid
pressure dip has been damped and a reliable pressure measurement can be
made. Such facilities shall be provided for following conditions:
i) Close lockout pressure.
ii) Auto reclose lockout pressure.
iii) Extreme low pressure.
e) The compressed air mechanism shall be capable of operating the circuit
breaker under all duty conditions with the air pressure immediately before
operation between 85% and 110% of the rated supply pressure. The

- 10 -
make/break time at this supply pressure shall not exceed the specified
make/break time within any value of trip coil supply voltage as specified.
f) The compressed air piping shall comply to requirements given in clause 5.28.8.
5.19 OPERATING MECHANISM HOUSING:
The operating mechanism housing/control cabinet shall conform to the requirement
specified in clause 5.30.
5.20 INTERLOCKS:
It is proposed to electrically interlock the circuit breaker with HVPNL's associated air
break isolating switches in accordance with switchyard safety interlocking scheme.
The details of the scheme will be furnished to the successful Bidder. All accessories
required on breaker side for satisfactory operation of the scheme shall be deemed to
be included in the scope of supply of this specification.
5.21 SUPPORTING STRUCTURE:
The Bidder shall indicate the price of support structure alongwith the foundation
bolts required separately in the bid proposal sheets and these shall be considered in
evaluation. However, in case the equipment offered have integral support structure or
the specialities of the breaker are such that support structures have to be provided by
the successful Bidder, the prices of these support structures shall be included in the
price of the equipment and same shall be indicated clearly in the bid proposal sheet.
The support structure shall meet the following requirements:
1) The minimum vertical clearance from any energised metal part to the bottom of
the circuit breaker (structure) base, where it rests on the foundation pad,
shall be 2.85meters for 72.5kV.
2) The minimum vertical distance from the bottom of the lowest porcelain part of
the bushings, porcelain enclosures or supporting insulators to the bottom of the
circuit breaker base, (from the ground level) shall be 2.55 meters for all
voltages.
3) The minimum clearance between the live parts and earth shall be 0.8 meters
for 72.5kV.
5.22 FITTINGS AND ACCESSORIES:
5.22.1 Following is a partial list of some of the major fittings and accessories to be furnished
by Bidder in the central control cabinet. Number and exact location of these parts shall
be indicated in the bid.
a) Central control cabinet in accordance with clause no. 5.30 complete with
i) Cable glands for control cables off sizes will be intimated to the successful
bidders .
ii) Local/remote changeover switch.
iii) Four digit operation counter.
iv) Pneumatic pressure gauges SF6 gas pressure gauge.
v) Control switches to cut off control power supply.
vi) Fuses and links as required.
vii) The number of terminals provided shall be adequate enough to wire out all
contacts and control circuits plus 24 terminals spare for HVPNL's use.
viii) Operation hour meter for motor.

- 11 -
ix) Three pin plug with socket.
x) Illuminating lamp with door switch.
xi) Lock and key for mechanism box.
xii) Capacitor tripping device.
xiii) Thermostatically controlled space tubular heater.
b) Anti-pumping relay.
c) Rating plate in accordance with IEC incorporating year of manufacture.
Note :- Such components, required for satisfactory operation of breaker, shall be deemed to
be within the scope of supply irrespective of whether these are specifically mentioned
or not above.
5.22.2 Additional fittings for pneumatically operated circuit breaker.
a) Unit compressed air system in accordance with clause No.5.28.
b) Breaker local air receivers.
c) Pressure gauge spring loaded safety valve, pressure switch with
adjustable contacts and explosion vents in case provision is not in-
built.
d) Pressure switch to initiate an alarm if the pressure in the aux.
reservoir remains below a preset level for longer than it is normally
necessary to refill the reservoir
e) Stop, non-return and other control valves, piping and all accessories
upto breaker mechanism housing.
5.23 SURFACE FINISH:
5.23.1 All interiors and exteriors of tanks and other metal parts shall be thoroughly cleaned
to remove all rust, scales, corrosion, greases or other adhering foreign matter. All
steel surfaces in contact with insulating oil, as far as accessible, shall be painted
with not less than two coats of heat resistant, oil insoluble, insulating paint.
5.23.2 All metal surfaces exposed to atmosphere shall be given two primer coats of zinc
chromate and two coats of epoxy paint with epoxy base thinner. All metal parts not
accessible for painting shall be made of corrosion resisting material. All machine
finished or bright surfaces shall be coated with a suitable preventive compound and
suitably wrapped or otherwise protected. All paints shall be carefully selected to
withstand tropical heat and extremes of weather within the limits specified. The
paint shall not scale off or wrinkle or be removed by abrasion due to normal handling.
All external paintings shall be as per shade no. 631 of IS:5.
5.23.3 All ferrous hardware, exposed to atmosphere, shall be hot dip galvanised.
5.24 GALVANISING:
All ferrous parts including all sizes of nuts, bolts, plain and spring washers, support
channels, structures, etc., shall be hot dip galvanised to conform to latest version of
IS:2629 or any other equivalent authoritative standard.
5.25 EARTHING:
The operating mechanism housing, control cabinets, dead tanks, support structure
etc., shall be provided with two separate Earthing terminals suitable for bolted
connection to 50x8mm MS flat to be provided by the HVPNL for connection to station
earth mat.

- 12 -
5.26 NAME AND RATING PLATES:
Circuit breaker and its operating device shall be provided with a rating plate or
plates marked with but not limited to following data:
a) Manufacturer's name or trade mark.
b) Serial number or type designation making it possible to get all the relevant
information from the manufacturer.
c) Year of manufacture.
d) Rated voltage.
e) Rated insulation level.
f) Rated frequency.
g) Rated normal current.
h) Rated short circuit breaking current.
i) First pole to clear factor.
j) Rated duration of short circuit.
k) Rated auxiliary DC supply voltage of closing and opening devices.
l) Rated pressure of compressed air gas for operation and interruption.
m) Rated out of phase breaking current
n) Rated supply voltage of auxiliary circuits.
o) Rated supply frequency of auxiliary circuits.
p) Purchase order number and customer's name.
The coils of operating devices shall have a reference mark permitting the data to be
obtained from the manufacturer.
The rating plate shall be visible in position of normal service and installation. The
rating plate shall be weather proof and corrosion proof.
5.27 LIMITS OF TEMPERATURE RISE:
The temperature rise on any part of equipment shall not exceed the maximum
temperature rise specified below under the conditions specified in test clauses. The
permissible temperature rise indicated is for a maximum ambient temperature of 50 C.
If the maximum ambient temperature rises, permissible values shall be reduced
accordingly.
-------------------------------------------------------------------------------------------------
Sl. Nature of the part or Maximum value of
No. of the liquid ---------------------------------------
Temp. at a Temp. rise ambient
max air temp not exceeding 50 C
--------------------------------------------------------------------------------------------------
1. Contacts in air. silver-faced 105 55
copper, copper alloy or alumi-
nium alloy {see notes (i) & (ii)}

- 13 -
Bare copper or tinned alumi- 75 25
nium alloy.
2. Contacts in oil:
i) Silver-faced copper, copper 90 40
alloy or aluminium alloy
(see note ii)
ii) Bare copper or tinned alumi- 80 30
nium alloy.
3. Terminals to be connected to 105 55
external conductors by screws
or bolts silver faced
(see note iii)
4. Metal parts acting as springs (See note iv) (See note iv)
5. Metal parts in contact with
insulation of the following
classes:
Class Y : (for non-impreg- 90 40
nated materials)
Class A : (for materials
immersed in oil 100 50
or impregnated)
Class E : in air 120 70
in oil 100 50

Class B : in air 130 80


in oil 100 50
Class F : in air 155 105
in oil 100 50

Enamel : oil base 100 50


synthetic : in air 120 70
synthetic : in oil 100 50
6. Any part of metal or of insul- 100 50
ating material in contact
with oil except contacts.
7. Oil 90 40
----------------------------------------------------------------------------------------------------------

- 14 -
Notes: i) When applying the temperature rise of 55 C, care should be taken to ensure
that no damage is caused to the surrounding insulating materials.
ii) The quality of the silver facing shall be such that a layer of silver remains at the
points of contact after the mechanical endurance tests. Otherwise, the contacts
shall be regarded as "bare".
iii) The values of temperature and temperature rise are valid whether or not the
conductor connected to the terminals is silver-faced.
iv) The temperature shall not reach a value where the elasticity of the material is
impaired. For pure copper, this implies a temperature limit of 75 C.
5.28 COMPRESSED AIR SYSTEM:
5.28.1 Each circuit breaker shall be supplied with individual compressor unit. Each ICU shall
be provided with compressor, piping, piping accessories, local air receivers, control
valves, filters, coolers of adequate capacity, reducing valves, isolating valves, drain
ports etc.,
5.28.2 The capacity of local air receivers shall be sufficient for two operations of the
circuit breaker, at the lowest pressure for auto reclosing duty without refilling.
5.28.3 Air Compressor:
a) The air compressor shall be oil-less and of air cooled type complete with
cylinder, lubrication, drive motor and slide rails. Each compressor shall be
rated for the following duty:
i) Total running time Not exceeding
of compressor per day 20 minutes.
ii) Normal running air charging Not exceeding
15 minutes.
iii) Air charging time after one Not exceeding
close-open operation of all breakers 60 minutes.
b) Compressor shall be driven by automatically controlled motors conforming to
this specification.
c) The compressor shall be provided with automatic adjustable unloading
device during starting.
d) Each compressor shall be equipped with a starting operation counter and a
running barometer.
5.28.4.1 Inter-cooler and After Cooler:
Inter-cooler between compressor stages and after-cooler at discharge of HP cylinder
shall be included in Bidder's scope. These shall be of air cooled type and shall be
designed as per ASME Code of IEMA Standards. The design pressure on the air side
of cooler shall be 25 times the working pressure. A corrosion allowance of 3 mm
shall be included for all steel parts.
5.28.5 Air Receivers:
a) Air receiver shall be designed in accordance with the latest edition of the
ASME Code for Pressure Vessel-Section VIII of BS:5197. A corrosion
allowance of 3.0 mm shall be provided for shell and dished ends in case the air
receiver are not hot dip galvanised . Receivers shall be coated on the inside
face with anti-rust medium.

- 15 -
b) Air receivers shall have a manhole with cover for inspection and cleaning.
Connections for air inlet and outlet, drain and relief valves shall be flanged
type. Pressure gauge and pressure switch connections shall be of screwed
type.
c) Accessories such as suitable sized safety valve to relieve full compressor
discharge at a set pressure equal to 1.1 times the maximum operating
pressure, blow off valve, auto drain tap with isolating and bypass valve, dial
type pressure gauge with isolating and drain valve and test connection shall be
provided.
d) The receiver shall be rated such that the compressor will not start within
less than hour hours for supplying the leakage of air from the compressed air
system. This condition shall be met with only one compressor in operation at a
time.
5.28.6 Quality of Air:
Compressed air used shall be dry and free of dust particles. Arrangement for
conditioning the compressed air shall be provided as an integral part of air compressor
system. Air shall not condensate at working pressure at a temperature of minus 10 C.
Measures of achieving this shall be brought out clearly in the bid. All instruments
required for checking the quality of air shall be furnished as special tools alongwith the
breakers.
5.28.7 Controls and Control Equipment:
a) The compressor control shall be of automatic start/stop type initiated by
pressure switches on the main receiver. Supplementary manual control shall
also be provided.
b) Duplicate incoming supply of 415 V, AC shall be provided by the HVPNL at
switchyard motor control center. The compressor MCC which is in Bidder's
scope shall be as per para of this section. Manual change over scheme from
the source to other shall be arranged. Facility to annunciate failure of power
supply to the compressor motor control center shall be provided.
c) All control equipment shall be housed in a totally enclosed sheet steel
cabinet conforming to relevant standards. Pressure gauges, other indicating
devices and control switches shall be mounted on the control cabinet.
5.28.8 Compressed Air Piping, Valves and Fittings:
a) The flow capacity of all valves shall be at least 20% greater than the total
compressor capacity.
b) The high pressure pipe and air system shall be such that after one O-0.3
sec -CO- operation the breaker shall be capable of performing one
CO-operation within 3 minutes.
c) All compressed air piping shall be bright annealed, seamless phosphorous
Deoxidized Non-Arsenical Copper alloy or stainless steel pipe (C-106 of
BS:2871-1957).
d) Compressor air piping in the switchyard trenches shall be laid with a slope of
1 in 1000. All necessary fittings required for this purpose including the drain
valves at all the low points shall be included in the proposal. The piping shall
be laid horizontally on steel supports in RCC trenches having a slope of 1 in
500.

- 16 -
e) All joints and connections in the piping system shall be brazed or flared as
necessary.
f) All compressed air piping shall be carried out in accordance with BS:162.
g) Compressed air piping system shall be complete with saddle clamps to
support the piping system at every one meter interval and expansion joint at
every 40 meters interval.
5.28.9 Motor Control Center:
The 415 Volt motor control centers conforming to requirements for control cabinets
stipulated in clause 5.3 of this specification shall be fixed type and fully
sectionalised and shall be equipped with load break switches. Motor feeders shall
be provided with isolating switch fuse unit and Bidder with thermal overload
relay and open phase protection. The motor Bidder shall have one normally open
auxiliary contact for alarm purposes. An ammeter shall be provided on the motor
feeders. The motor control circuit shall be independent from all other control circuits.

5.28.10 Fuses:
All fuses shall be of the HRC cartridge type, conforming to IS:2208 and suitable for
mounting on plug-in type of fuse bases. Fuses shall be provided with visible operation
indicators to show that they have operated. All accessible live connections shall be
adequately shrouded, and it shall be possible to change fuses with the circuit live,
without danger of contact with live conductor. Insulated fuses pulling handle shall be
supplied with each control cabinet.
5.29 TERMINAL CONNECTORS:
5.29.1 All the circuit breakers shall be provided with terminal connectors suitable for 0.4
Sq.inch ACSR Zebra Conductor.
The terminal connectors shall meet the following requirements:
a) Terminal connectors shall be manufactured and tested as per IS:5561.
b) All castings shall be free from blow holes, surface blisters, cracks and activities.
All sharp edges & corners shall be blurred and rounded off.
c) No part of a clamp shall be less than 10 mm thick.
d) All ferrous parts shall be hot dip galvanised conforming to IS:2633.
e) For bimetallic connectors, copper alloy liner of minimum thickness of 2 mm
shall be cast integral with aluminium body.
f) Flexible connectors shall be made from tinned copper/ aluminium sheets.
g) All current carrying parts shall be designed and manufactured to have minimum
contact resistance.
h) Connectors shall be designed to be corona free in accordance with the
requirements stipulated in IS:5561.
5.30 SPECIFICATION FOR CONTROL CABINETS:
1. Control cabinets shall be sheet steel enclosed and shall be dust, weather and
vermin proof. Sheet steel shall be at least 2.6mm thick (2 mm if CRCA) sheet
used. Control cabinets shall be provided with a hinged door and padlocking
arrangement. The door hinges shall be of union joint type to facilitate easy

- 17 -
removal. Door shall be properly braced to prevent wobbling. There shall be
provision in the bottom sheet for entrance of cables from below.
2. Equipment and devices shall be suitable for operation on a 415 V, 3 phase 3/4
wire 50 Hz AC system. The wiring shall be of stranded copper with minimum
cross section of 2.5 Sq.mm with 1100 V PVC insulation.
3. Bus bars shall be of tinned copper of adequate cross-section to carry the
normal current, without exceeding the permissible temperature rise over an
ambient temperature of 50 C outside the cubicle. The buses shall be braced
to withstand forces corresponding to short circuit current of 25 kA.
4. Motors rated 1 KW and above being controlled from the control cabinet shall
be suitable for operation on a 415 V, 3 phase 50 Hz system. Fractional KW
motors shall be suitable for operation on a 240 V, 1-phase, 50 Hz supply
system.
5. Isolating switches shall be group operated units 3-pole for use on 3-phase
supply systems and 2 pole for single phase supply systems) quick make
quick break type, capable of breaking safely and without deterioration, the
rated current of the associated circuit. Control cabinet door shall be
interlocked with the operating handle of the switch so as to prevent opening of
the door when the switch is closed. A device for bypassing the door interlock
shall also be provided. Switch handle shall have provision for locking in both
fully open and fully closed positions.
6. Fuses shall be HRC cartridge link type having prospective current rating of not
less than 46 kA (rms). They shall be provided with visible operation indicators
to show when they have operated. One fuse pulling handle shall be supplied
for every ten fuses or a part thereof.
7. Push button shall be rated for not less than 6 Amps, 415 V AC or 2 Amps,
220V DC and shall be flush mounted on the cabinet door and provided with
appropriate name plates. Red, Green and Amber indicating lamps shall be
flush mounted and provided with series resistors to eliminate the possibility of
short circuiting of control supply in the event of fusing of lamps.
8. For motors upto 5 KW, contactors shall be direct-on-line, air break, single throw
type and shall be suitable for making and breaking the starting current of
the associated motor which shall be assumed equal to 6.5 times the full load
current of the motor at 0.2 p.f. For motors above 5 KW, automatic star delta
type starters shall be provided. 3 pole contactors shall be furnished for 3 phase
motors and 2-pole contactors for single phase motors. Reversing contactors
shall be provided with electrical interlocks between forward and reverse
contactors. If possible, mechanical interlocks shall also be provided.
Contactors shall be suitable for uninterrupted duty and shall be of duty
category class AC4 as defined in IS:2959. The main contacts of the
contactors shall be silver plated and the insulation class for the coils shall be
class E or better. The dropout voltage of the contactors shall not exceed 70%
of the rated voltage.
9. Contactors shall be provided with a three element, positive acting, ambient
temperature compensated, time lagged, hand reset type thermal overload relay
with adjustable setting. Hand reset button shall be flush with the front door of
the cabinet and suitable for resetting with starter compartment door closed.
Relays shall be either direct connected or CT operated depending on the rated
motor current.

- 18 -
10. Single phasing preventer relay shall be provided for 3 phase motors to provide
positive protection against single phasing.
11. Mini starters shall be provided with no volt coils whenever required.
12. All necessary cable terminating accessories such as glands, crimp type
tinned copper lugs etc., for control cables shall be included in Bidder's scope of
supply. Suitable brass cable glands shall be provided for cable entry.
13. Wiring for all control circuits shall be carried out with 1100/650 volts grade PVC
insulated tinned copper stranded conductors of sizes not smaller than 2.5 sq.
mm atleast 10% spare terminal blocks for control wire terminations shall be
provided on each panel. The terminal blocks shall be ELMEK type or
equivalent. All terminals shall be provided with ferrules Visibly marked or
numbered and these identifications shall correspond to the designations on the
relevant wiring diagrams. The terminals shall be rated for adequate capacity
which shall not be less than 10 Amps.
14. Control cabinet shall be provided with 240 V, 1-phase 50 Hz, 20 W
fluorescent light fixture and 5 amps, 3 pin socket for handlamp.
15. Space heaters shall be provided inside each cabinet complete with thermostat
(preferably differential type) to prevent moisture condensation. Heaters shall
be controlled by suitably rated double-pole miniature Circuit Breakers.
16. Signal lamps provided shall be of neon screw type with series resistors,
enclosed in bakelite body. Each signal lamp shall be provided with a fuse
integrally mounted in the lamp body.
17. All AC control equipment shall be suitable for operation on 240 V, 1 phase
50 Hz system.
18. Items inside the cabinet made of organic material shall be coated with a fungus
resistant varnish.
19. All doors, panels, removable covers and breaker openings shall be gasketed all
around. All louvers shall have screens and filters. Cabinets shall be dust,
moisture and vermin proof.
5.31 MOTORS:
5.31.1 Motors shall be "Squirrel Cage" three phase induction motors of sufficient size
capable of satisfactory operation for the application and duty as required for the driven
equipment.
5.31.2 Stator:
a) Stator Frame:
The stator frame and all external parts of the motors shall be rigid fabricated
steel or of casting. They shall be suitably annealed to eliminate any residual
stresses introduced during the process of fabrication and machining.
b) Stator Core:
The stator lamination shall be made from suitable grade magnetic sheet steel
varnished on both sides. They shall be pressed and clamped adequately to
reduce the core and teeth vibrations to minimum.
c) Insulation and Winding:
i) All insulated winding conductor shall be of copper. The overall motor
winding insulation shall be conventional class B type. The winding

- 19 -
shall be suitable for successful operation in hot, humid and tropical
climate with the ambient temperature of 50 C. The insulation shall
be given fungicidal and tropical treatment as per IS:3202.
ii) Any joints in the motor insulation such as at coil connections or between
slot and winding section shall have strength equivalent to that of slot
section of the coil.
iii) For 415 Volt motors, after the coils are placed in slots and all
connections are made, entire motor assembly shall be impregnated by
completely submerging core and winding in suitable insulating
compound or varnish allowed by proper baking. At least two additional
submersions and bakes shall be applied either making a total of at least
three submersions and bake treatment.
5.31.3 Rotor:
a) Rotors shall be adequately designed to avoid overheating during the starting
and running conditions.
b) Rotors shall be properly balanced so as to keep the vibration under running
condition within the limits.
c) Rotors of induction motors shall be of rigid core construction with bars firmly
secured and solidly bonded to the end rings. The end rings assembly shall be
such that it is free to move with expansion of the bars without distortion. The
connection of the bars to the end ring shall be made by brazing or fusion
welding.
d) Rotors shall be so designed as to keep the combined critical speed with the
driven equipment away from the running speed by at least 20%.
e) Rotors shall also be designed to withstand 120% of the rated speed for 2
minutes in either direction of rotation.
f) All high speed rotors shall be constructed with provision of re-balancing the
rotor on its site position without major disassembly.
5.31.4 Bearings:
a) Depending upon the capacity and loading conditions Bidder shall design
suitable grease lubricated or oil lubricated bearings.
b) Greased ball and roller bearings when used shall be of reputed make subject to
HVPNL's approval. The minimum standard life of the bearings shall not be less
than 30,000 working hours taking all motor and driven loads into account.
These shall be pressure grease gun lubricated type fitted with grease nipple
and shall have grease relief devices.
c) Bearing shall be so constructed that the loss of grease and its creeping
alongwith shaft into motor housing is prevented. It shall also prevent dirt and
water from getting into the motor.
d) Unless otherwise approved, bearing lubrication system shall be such that no
external forced oil or water is necessary to maintain
the required oil supply or to keep bearing temperature within permissible
limits.
e) For oil lubricated bearings, drain plugs shall be provided for draining any
residual oil when required.

- 20 -
5.31.5 Enclosures:
a) Motors to be installed outdoor shall have hose proof enclosure equivalent to
IP-55 as per IS:4691. For motors to be installed indoor, the enclosure shall
be dust proof equivalent to IP-54 as per IS:4691.
b) Two independent Earthing points shall be provided on opposite sides of the
motor for bolted connection of Earthing conductor.
c) Motors shall have drain plugs so located that they will drain water resulting
from condensation or other causes from all pockets in the motor casing.
d) Motors weighing more than 25 kg shall be provided with eyebolts, lugs or other
means to facilitate lifting.
5.31.6 Cooling Method:
Motors shall be of self ventilated type having TEFC (totally enclosed fan cooled)
enclosure.
5.31.7 Rating Plate:
The rating plate shall conform to the requirements of IEC incorporating the year of
manufacture.
5.31.8 Operational Features:
a) Continuous motor rating (name plate rating) shall be at least ten (10) percent
above the maximum load demand of the driven equipment at design duty
point and the motor shall not be overloaded at any operating point of driven
equipment that will arise in service.
b) Motors shall be capable of giving rated output without reduction in expected life
span when operated continuously in the system having the particulars as given
in Annexure-II.
5.31.9 Starting Requirements:
a) All induction motors shall be suitable for full voltage direct-on -line starting.
These shall be capable of starting and accelerating to the rated speed
alongwith the driven equipment without exceeding the acceptable winding
temperature even when the supply voltage drops down to 85% of the rated
voltage.
b) Motors shall be capable of withstanding the electro dynamic stresses and
heating imposed if it is started at a voltage of 110% of the rated value.
c) The locked rotor current shall not exceed six (6) times the rated full load
current for all motors, subject to tolerance as given in IS:325.
d) Motors, when started with the driven equipment imposing full starting torque
under the supply voltage conditions specified under clause 5.32.9(a) above
shall be capable of withstanding at least two successive starts from cold
condition at room temperature and one start from hot condition without
injurious heating of winding. The motors shall also be suitable for three equally
spread starts per hour under the above referred supply condition.
e) The locked rotor withstand time under hot condition at 110% of rated voltage
shall be more than starting time with the driven equipment at minimum
permissible voltage by at least two seconds or 15% of the accelerating time
whichever is greater. In case it is not possible to meet the above requirement,
the Bidder shall offer centrifugal type speed switch mounted on the motor shaft

- 21 -
which shall remain closed for speeds lower than 20% and open for speeds
above 20% of the rated speed. The speed switch shall be capable of
withstanding 120% of the rated speed in either direction of rotation.
6.0 TESTS:
6.1 TYPE TESTS:
The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or
witnessed by HVPN or another electric power utility and be submitted by the
successful bidder to HVPNL for approval as schedule given in Bar Chart.
i) Impulse withstand voltage test
ii) Power frequency voltage withstand dry test on main circuit
iii) Short circuit withstand capability test
iv) Mechanical endurance test
v) Temperature rise test
vi) Radio interference voltage (RIV)
vii) Measurement of the resistance of main circuit
viii) Short time withstand current and peak withstand current test
ix) Out of phase making & breaking test
x) Shunt reactor current switching test
xi) Dielectric test
xii) IP-55 test on operating mechanism
xiii) Seismic test
6.2 ROUTINE TESTS:
As per quality assurance program (QAP).
63 ACCEPTANCE TESTS:
The following acceptance tests as stipulated in the relevant ISS-13118 shall be carried
out by the Supplier in presence of HVPNL representative, unless dispensed with in
writing by the HVPNL.
i) Power frequency voltage withstand dry test on main circuit
ii) Voltage withstand test on control and auxiliary circuits
iii) Measurement of resistance of the main circuit
iv) Mechanical operating test
v) Design and visual test
vi) Tightness Test
7.0 INSPECTION:
7.1 The HVPNL shall have access at all times to the works and all other all other places of
manufacture, where the circuit breaker are being manufactured and the Bidder shall
provide all facilities without extra charges, for unrestricted inspection of the Bidder's
works, raw materials, manufacture of the equipment., all the accessories and for
conducting necessary test as detailed herein.
7.2 The Bidder shall keep the HVPNL informed in advance, about the manufacturing
program so that arrangement can be made for inspection.
7.3 No material shall be despatched from its point of manufacture unless the material has
been satisfactorily inspected and tested.

- 22 -
7.4 The Bidder shall submit their internal inspection report containing manufacturer's test
certificates before offering the material for inspection.
7.5 The acceptance of any quantity of equipment shall in no way relieve the Bidder of his
responsibility for meeting all the requirements of this specification and shall not prevent
subsequent rejection if such equipment are later found to be defective.
8.0 DOCUMENTATION
8.1 The successful bidder shall submit four sets of following drawings for HVPNL approval.
List of Drawings and Documents:
The Bidder shall furnish four sets of relevant descriptive and illustrative published
literature pamphlets and the following drawings for preliminary study alongwith the
offer.
a) General outline drawings showing dimensions and shipping weights, quantity of
insulating media, air receiver capacity etc.,
b) Sectional views showing the general constructional features of the circuit
breakers including operating mechanism, arcing chambers, contacts etc., with
lifting dimensions for maintenance.
c) Schematic diagrams of breakers offered for control supervision and reclosing.
d) Structural drawing, design calculations and loading data for support structures.
e) Foundation drilling plan and loading data for foundation design.
f) Terminal Connector
NOTE: All above drawings should be a minimum space (14x10cm) for stamping
the approval of drawings by HVPNL.

8.2 TEST REPORTS:


i) Four copies of acceptance test reports shall be furnished to the HVPNL.
One copy will be returned, duly certified by the HVPNL and only there
afterwards shall the material be despatched.
ii) All records of routine test reports shall be maintained by the Bidder at his
works for periodic inspection by the HVPNL.
iii) All test reports of tests conducted during manufacture shall be maintained by
the Bidder. These shall be produced for verification as and when requested for
by the HVPNL.

- 23 -
SECTION-5

CHAPTER-1

TECHNICAL SPECIFICATION FOR

72.5kV CURRENT TRANSFORMERS


AND
245kV &72.5kV NEUTRAL CURRENT TRANSFORMERS

1
CONTENTS

CLAUSE NO. TITLE PAGE NO.

1.0 SCOPE 3
2.0 STANDARDS 3
3.0 PRINCIPAL PARAMETERS 4
4.0 GENERAL TECHNICAL REQUIREMENTS 5
5.0 TESTS 8
6.0 DOCUMENTATION 9

ANNEXURE
1. CORE-WISE DETAILS FOR
A-(i) 245kV NCTs (300-150/1A) 10
B-(i) 72.5kV TRANSFORMER INCOMER CTs 10
(1000-500/0.577-1-1-1A)
B-(ii) 72.5kV NCT (1000-500/1A) 10

2
1.0 SCOPE :
1.1 This specification provides for design, engineering, manufacture, stage testing
inspection and testing before despatch, packing, forwarding and delivery at site for
72.5kV CTs and 245kV & 72.5kV NCTs complete with all fittings.
1.2 It is not the intent to specify complete herein all details of the design and
construction of equipments. However the equipment shall conform in all respects to
high standards of engineering design and workmanship and shall be acceptable of
performing in continuous commercial operation up-to the bidders guarantee
acceptable to the purchaser. The equipment offered shall be complete with all
components necessary for its effective and trouble free operation. Such
components shall deemed to be within the scope of supply irrespective of whether
those are specially brought out in this specification and or the commercial order or
not. All similar parts shall be interchangeable.

2.0 STANDARDS
The equipment offered shall conform to latest relevant IS/IEC listed hereunder or
their equivalent IEC/IS.

2.1 INSTRUMENT TRANSFORMERS:


Sr. No. Standard No. Title
1. IS:2165 Insulation Co-ordination for equipment of 100kV and above.
2. IS:2705 Current Transformers.
(I to IV)
3. IS:2099 Bushings for alternating voltages above 1000Volts.
4. IS:3347 Dimensions of porcelain transformer bushings.
5. IS:2071 Method of High Voltage Testing.
6. IS:335 Insulating oil for transformers Switchgears.
7. IS:2147 Degree of protection provided by enclosures for low voltage
switchgear and control.
8. IS:2633 Method of testing hot dipped galvanized articles.
9. IS:4800 Enameled round winding wires.
10. IS:5561 Terminal connectors.
11. IS:11065 Drawings.
12. IEC 44-1 Current Transformers.
13. IEC-270 Partial Discharge Measurement
(or IS:11322)
14. IEC-44(4) Instrument Transformer measurement of PDs.
15. IEC-171 Insulation co-ordination.
16. IEC-60 High voltage testing techniques.
17. IEC-8263 Method for RIV test on high voltage insulators.
18. Indian Electricity Rules 1956.
19. IS:5621 Hollow porcelain insulators.

3
2.2 The bidder shall also note that list of standards presented in this specification is not
complete. Whenever necessary the list of standards shall be considered in
conjunction with specific IS/IEC. When the specific requirements stipulated in the
specifications exceed or differ than those required by the applicable standards, the
stipulation of the specification shall take precedence.

2.3 Equipment meeting with the requirements of other authoritative standards, which
ensure equal or better performance than the standards mentioned above, shall also
be considered. When the equipment offered by the supplier conforms to other
standards salient points of difference between standards adopted and the standards
specified in this specification shall be clearly brought out in the relevant schedule.
Four copies of such standards with authentic translation in English shall be
furnished alongwith the offer.

3.0 PRINCIPAL PARAMETERS:


The current transformers covered in this specification shall meet the technical
requirements listed hereunder.
PRINCIPAL TECHNICAL PARAMETERS :-

Sr.No. Item 245kV 72.5kV


1. Type of C.T./ installation. Single phase, oil filled, single phase, oil filled,
dead tank, hermetically hermetically sealed,
sealed, outdoor type outdoor type,
2. Type of mounting Steel structures
3. Suitable for system 50Hz
frequency
4. Highest system Voltage (kV 245 72.5
rms)
5. Minimum Neutral CT 33 15
Insulating Voltage
6. Current ratio A/A
a) Line - -
b) Transformer - -
c) Transformer Incomer - 1000-500/0.577-1-1-1
d) Bus Coupler CT - -
e) NCT 300-150/1 1000-500/1
7. Method of earthing the Solidly earthed
system
8. Rated Continuous Thermal 125% for all taps
current
9. Ratio taps The tapings shall be only on secondary winding
10. Acceptable limit of As per IS:2705 or equivalent IEC
temperature rise above the
specified ambient
temperature for continuous
operation at rated current.
11. Acceptance partial discharge As per IS:11322-1985 or equivalent IEC
level at 1.1 times the rated
voltage

4
Sr.No. Item 245kV 72.5kV
12. 1.2/50 microsecond lightning impulse withstand voltage (kVp)
a) CTs - 325
b) NCTs 170 95
13. 1 minute dry & wet power frequency withstand Voltage primary (kV rms)
a) CTs - 140
b) NCTs 70 38
14. Power frequency over 3.0
voltage withstand
requirement for secondary
winding (kV rms) (for 1
minute)
15. Min. creepage distance of porcelain housing (mm)
a) CTs - 1815
b) NCTs 900 440
16. Rated short time withstand 40 31.5
current (kArms) for 1 second
17. Rated dynamic withstand 100 78.75
current (kAp)
18. Maximum Creepage factor 4.0

4.0 GENERAL TECHNICAL REQUIREMENTS:


4.1 The insulation of the instrument transformer shall be so designed that the internal
insulation shall have higher electrical withstand capability than the external
insulation. The designed dielectric withstands values of external and internal
insulation's shall be clearly brought out in the guaranteed technical particulars. The
dielectric withstand values specified in this specification are meant for fully
assembled instrument transformers.
4.2 PORCELAIN HOUSING:
4.2.1. The details of location and type of joint, if provided on the porcelain, shall be
furnished by the Supplier alongwith the offer. The housing shall be made of
homogeneous, vitreous porcelain of high mechanical and dielectric strength, glazing
of porcelain shall be uniform brown or dark brown colour with a smooth surface
arranged to shed away rain water or condensed water particles (fog).
4.2.2 Details of attachment of metallic flanges to the porcelain shall be brought out in the
offer.
4.3 The metal tanks shall have bare minimum number of welded joints so as to minimize
possible locations of oil leakage. The metal tanks shall be made out of mild
steel/stainless steel/aluminum alloy, depending on the requirement. Welding in
horizontal plane is to be avoided as welding at this location may give way due to
vibrations during transport resulting in oil leakage. Supplier has to obtain specific
approval from purchaser for any horizontal welding used in the bottom tank.
4.4 SURFACE FINISH:
The ferrous parts exposed to atmosphere shall be hot dip galvanized or shall be

5
coated with atleast two coats of Zinc Rich Epoxy painting. All nuts, Bolts and
washers shall be of stainless steel.
4.5 INSULATING OIL:
Insulating oil required for first filling of the instrument transformer shall be covered in
Supplier's scope of supply. The oil shall meet the requirements of latest edition IS:
335 or equivalent IEC.
4.6 PREVENTION OF OIL LEAKAGE & ENTRY OF MOISTURE:
4.6.1 The supplier shall ensure that the sealing of instrument transformer is properly
achieved. In this connection the arrangement provided by the Supplier at various
locations including the following ones shall be described, supported by sectional
drawings.
i) Locations of emergence of primary and secondary terminals.
ii) Interface between porcelain housing and metal tank/s.
iii) Cover of the secondary terminal box.
4.6.2 Nuts and bolts or screws used for fixation of the interfacing porcelain bushings for
taking out terminals shall be provided on flanges cemented to the bushings and not
on the porcelain.
4.6.3 For gasketed joints, wherever used nitrile butyl rubber gaskets shall be used. The
gasket shall be fitted in properly machined groove with adequate space for
accommodating the gasket under compression.
4.7 OIL LEVEL INDICATORS:
Instrument transformers shall be provided with oil sight window (Prismatic Type) at
suitable location so that the oil level is clearly visible with naked eye to an observer
standing at ground level.

4.8 EARTHING:
Metal tank of instrument transformer shall be provided with two separate earthing
terminals for bolted connection to 50x8mm MS flat to be provided by the Purchaser
for connection to station earth mat.
4.9 Instrument transformer shall be provided with suitable lifting arrangement to lift the
entire unit. The lifting arrangement shall be clearly shown in the general
arrangement drawing. Lifting arrangement (lifting eye) shall be positioned in such a
way as to avoid any damage to the porcelain housing or the tanks during lifting for
installation/transport. Necessary string guides, if required shall be offered which
shall be removable type.

4.10 NAME PLATE:


The instrument transformer shall be provided with non-corrosive, legible name plate
with the information specified in relevant standards, duly engraved/punched on it. In
addition to these the following specific points shall also be marked on the name
plate.
i) P.O. No. with date and (item No, if any)
ii) Connection diagram.
iii) Rated continuous thermal current.
iv) General knee point voltage formula.
The size of nameplate and its location on the equipment should be such that it is

6
clearly readable with naked eyes while standing on ground.

4.11 Suitable terminal connectors for connecting conductor shall be supplied. Suitable
terminal earth connectors for earthing connections shall also be provided.
4.11.1. The terminal connectors shall meet the following requirements:
1) Terminal connectors shall be manufactured and tested as per IS: 5561 or equivalent
IEC.
2) All castings shall be free from blowholes, surface blisters, cracks and cavities. All
sharp edges and corners shall be blurred and rounded off.
3) No part of a clamp shall be less than 10mm thick.
4) All ferrous parts shall be hot dip galvanized conforming to IS: 2633 or equivalent
IEC.
5) For bimetallic connectors, copper alloy liner of minimum 2mm thickness shall be
cast integral with aluminium body.
6) Flexible connectors shall be made from tinned copper/ aluminium sheets.
7) All current carrying parts shall be designed and manufactured to have minimum
contact resistance.
8) Connectors shall be designed to be corona free in accordance with the requirements
stipulated in IS:5561 or equivalent IEC.
4.12 Enamel, if used for conductor insulation, shall be polyvinyl acetate type and shall
meet the requirements of IS: 4800 or equivalent IEC. Polyester enamel shall not be
used. Double cotton cover, if used, shall be suitably covered to ensure that it does
not come in contact with oil.
4.13 The temperature rise on any part of equipment shall not exceed maximum
temperature rise specified in IS: 2705 or equivalent IEC. However, the permissible
temperature rise is for a maximum ambient temperature of 50o C.
4.14 The CT/NCT shall be so constructed that it can be easily transported to site within
the allowable transport limitation and in horizontal position, if the transport limitations
so demand.
4.15 Suitable arrangement shall be made for compensation of variation in the oil volume
due to ambient variation and to take care of internal abnormal pressures. The
pressure variation shall be kept within limits, which do not impair the tightness of the
instrument transformer. A pressure relief device capable of releasing abnormal
internal pressure shall be provided.
4.16 The CT secondary terminals shall be brought out in a weather proof terminal box.
The terminal box shall be provided with removable gland plate.
The terminal box/boxes shall be dust and vermin proof. The dimensions of the
terminal box/boxes and its/their openings shall be adequate to enable easy access
and working space with use of normal tools.
4.17 Polarity shall be indelibly marked on each primary and secondary terminal. Facility
shall be provided for short-circuiting and grounding of the secondary terminals inside
the terminal box.
4.18 The instrument transformers shall be vacuum filled with oil after processing and
thereafter hermetically sealed to eliminate breathing and to prevent air and moisture
from entering the tanks. Sealing type oil filling and/or oil sampling cocks shall be
provided with facility to reseal the same. The method adopted for hermetic sealing

7
shall be described in the offer.
4.19 The castings of base, collar etc shall be diecast and tested before assembly to
detect cracks and voids if any.
4.20 The instrument security factor of metering core shall be low enough and less than 5.
This shall be demonstrated on all the ratios of the metering core, in accordance with
procedure specified in IS: 2705 or equivalent IEC. In case the instrument security
factor of less than 5 is not possible to be achieved on higher ratios, auxiliary CTs of
ratio 1/1 shall be deemed to be included in the supplier's scope of supply. This shall
also be specifically brought out by the supplier in his offer.
4.21 PRIMARY WINDING:
The design density for short circuit current as well as conductivity of the metal used
for primary winding shall meet the requirement of IS: 2705 or equivalent IEC. The
supplier shall in his offer furnish detailed calculations for selection of winding
cross-sections.
4.22 SECONDARY WINDING:
Suitably insulated wire of electrolytic grade shall be used for secondary windings.
Type of insulation used shall be described in the offer. For multi ratio design, suitable
tapping shall be provided on secondary winding only. Ratio tap selection through
primary side shall not be acceptable.
4.23 The exciting current of the CT shall be as low as possible. The supplier shall furnish
alongwith his offer the magnetization curve/s for all the core/s. The cores shall be of
high grade, non-ageing electrical silicon laminated steel of low hysterisis loss and
high permeability to ensure high accuracy at both normal and over current.

4.24 PRIMARY TERMINALS:


Each primary terminal shall be made out of rods of not less than 30mm dia copper or
equivalent as per IS/IEC.
4.25 Any deviation from the specification shall be clearly brought out separately. In the
absence of any specific mention, it shall be implied that the equipment offered is
entirely according to this specification.
4.26. The 72.5 kV and above voltage level instrument transformers shall be provided with
suitable test tap for measurement of tests such as partial discharges etc. in factory
as well as at site. Provision shall be made of a screw on cap for solid and secured
earthing of the test tap connection, when not in use. A suitable caution plate shall be
provided duly fixed on the cover of the secondary terminal box indicating the
purpose of the test tap and necessity of its solid earthing as per prescribed method
before energising the equipment.
5.0 TESTS :
5.1 TYPE TESTS
The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accredittic body or
witnessed by HVPN or another electric power utility and be submitted by the
successful bidder to HVPNL for approval as schedule given in Bar Chart.
Temperature-rise Test.
i) Short time current tests.

8
ii) Lighting impulse test.
iii) High voltage power frequency wet withstand voltage test.
iv) Determination of errors or other characteristic according to the requirement so of the
appropriate designation or accuracy class.
5.2 ROUTINE TESTS :
As per quality assurance program (QAP).
5.3 ACCEPTANCE TESTS:
The following acceptance tests as stipulated in the relevant ISS-2705 shall be
carried out by the Supplier in presence of HVPNL representative, unless dispensed
with in writing by the HVPNL.
i) Verification of terminal marking and polarity.
ii) High voltage power frequency dry withstand voltage test for primary winding.
iii) High voltage power frequency dry withstand voltage test for secondary winding.
iv) Over voltage inter-turn test.
v) Partial discharge tests
vi) Determination of errors or other characteristic according to the requirement so of the
appropriate designation or accuracy class.
6.0 DOCUMENTATION:
6.1 The successful bidder shall submit four sets of following drawings except 6.1(b)
below (actual of which shall be supplied at the time of inspection) for HVPNL
approval.
List of drawings:
a) General outline and assembly drawings of the equipment.
b) Graphs showing the performance of equipments in regard to magnetisation
characteristics; ratio & phase angle curves, ratio correction factor curves.
c) Sectional views showing:
i) General Constructional Features.
ii) Materials/Gaskets/Sealing used.
iii) The insulation & the winding arrangements, method of connection of the
primary / secondary winding to the primary / secondary terminals etc.
iv) Porcelain used and its dimensions.
d) Arrangement of terminals and details of connection studs provided.
e) Name plate.
f) Schematic drawing.
g) Detailed drawing of pressure release device with detailed literature
h) Terminal connector drawing.

NOTE:- All above drawings should bear a minimum space (14X10cm) for stamping the
approval of drawings by HVPNL.

9
ANNEXURE I-A(i)
COREWISE DETAILS OF 245 kV NEUTRAL CTs
(300-150/1A)
NUMBER OF CORE - 1
Application Current Accuracy Formula for minimum knee- Maximum Minimum
Ratio (A) class point voltage at CT Exciting Insulation
as per Secondary resistance Current Voltage
IEC 185 at 750C at (mA) (kV)
300Atap(Volt)
1 2 3 4 5 6
REF 300-150/1 PS 14(RCT+2) 30AT VK/2 33
PROTECTION

ANNEXURE-I-B(i)
COREWISE DETAILS OF 72.5kV TRANSFORMER INCOMER CT
(1000-500/.577-1-1-1A)
NUMBER OF CORES - 4
Core Application Current Output Accuracy Formula for minimum Maximum A.L.F./
No. Ratio (A) burden class knee-point voltage Exciting I.S.F.
(VA) as per At CT Secondary Current
IEC 185 resistance at 750C at (mA)
1000A tap (Volt)
1 2 3 4 5 6 7 8
1 DIFFERENTIAL 1000-500/0.577 - PS 40 (RCT+2) 30AT VK/4 -
PROTECTION
2 REF 1000-500/1 - PS 14 (RCT+2) 30AT VK/2
PROTECTION
3 OVER 1000-500/1 15 5P - - ALF 10
CURRENT &
EARTH FAULT
PROTECTION

4 METERING 1000-500/1 15 1.0 - - ISF <5

ANNEXURE-I-B(ii)
COREWISE DETAILS OF 72.5kV TRANSFORMER INCOMER NCT
(1000-500/1A)
No. OF CORES= 1
Core Application Current Output Accuracy Formula for minimum Maximum Minimum
No. Ratio (A) burden class knee point voltage Exciting Insulatio
(VA) as per At CT Secondary Current n Voltage
IEC 185 resistance at 750C at (mA) (kV)
1000A tap (Volt)
1 2 3 4 5 6 7 8
1 REF 1000-500/1 - PS 14 (RCT+2) 30AT VK/2 15
PROTECTION

10
11
SECTION -5

CHAPTER-2

TECHNICAL SPECIFICATION FOR

245 kV & 72.5 kV

CAPACITIVE VOLTAGE TRANSFORMERS (CVTs)

1
CONTENTS

CLAUSE NO. TITLE PAGE NO.


------------------------------------------------------------------------------------------------------------------
1.0 SCOPE 3

2.0 STANDARDS 3

3.0 PRINCIPAL PARAMETERS 4

4.0 GENERAL TECHNICAL REQUIREMENTS 6

5.0 TESTS 10

6.0 DOCUMENTATION 11

ANNEXURES
I. COREWISE DETAILS FOR

A-(i) 245 kV CVTs 12

B -(i) 72.5 kV CVTs 13

--------------------------------------------------------------------------------------------------------

2
1.0 SCOPE :

1.1 This specification provides for design, engineering, manufacture,


stage testing, inspection and testing before dispatch, packing,
forwarding and delivery at site of 245kV & 72.5kV CVTs complete with
all fittings.

1.2 It is not the intent to specify completely herein all details of the design
and construction of equipments. However the equipment shall
conform in all respects to high standards of engineering design and
workmanship and shall be capable of performing in continuous
commercial operation upto the bidders guarantee acceptable to the
purchaser. The equipment offered shall be complete in all
components necessary for its effective and trouble free operation.
Such components shall be deemed to be within the scope of supply
irrespective of whether those are specially brought out in this
specification and or the commercial order or not. All similar parts
particularly movable ones shall be interchangeable.

2.0 STANDARDS:

The equipment offered shall conform to latest relevant IS/IEC listed


hereunder or their equivalent IEC/IS.

Sr. No. Standard No. Title.


1. IS : 3156 Voltage transformer
(Part-I to Part-III)
2. IS : 3156 (Part-IV) Capacitor Voltage Transformer
3. IS : 2099 High Voltage porcelain bushing.
4. IS : 3347 Dimensions of porcelain transformer
bushings
5. IS : 2071 Method of High Voltage Testing
6. IS : 335 Insulating oil for transformers and
switchgears
7. IS : 2165 Insulation Co-ordination for
equipments of 100 kV and above.
8. IS : 2147 Degree of protection provided by
enclosures for low voltage switchgear
and control.
9. IEC- 186 Voltage Transformers
10. IEC - 186A First supplement to IEC publication
186
11. IEC - 270 Partial discharge Measurement

3
12. IS - 5561 Terminal Connectors
13. IS -4800 Enameled round winding wires
14. IEC- 44 (4) Instrument Transformer
measurement of PDs
15. IEC-171 Insulation Co-ordination
16. IEC - 358 Coupling capacitor divider.
17. IEC-60 High Voltage testing techniques.
18. IEC-8263 Method for RIV test on high voltage
insulators.
19. IS: 9348 Coupling capacitors and capacitor
dividers
20. IS: 2633 Methods of testing hot dipped
galvanized articles
21. IS: 11065 Drawings.
22. Indian Electricity Rules 1956
23. IS: 5621 Hollow porcelain insulators.

2.2 The bidder shall also note that list of standards presented in this
specification is not complete. Whenever necessary the list of standards
shall be considered in conjunction with specific IS/IEC. When the
specific requirements stipulated in these specifications exceed or differ
than those required by the applicable standards, the stipulation of the
specification shall take precedence.

2.3 Equipment meeting with the requirements of other authoritative


standards, which ensure equal or better performance than the
standards mentioned above, shall also be considered. When the
equipment offered by the supplier conforms to other standards salient
points of difference between standards adopted and the standards
specified in this specification shall be clearly brought out in the relevant
schedule. Four copies of such standards with authentic translation in
English shall be furnished alongwith the offer.

3.0 PRINCIPAL PARAMETERS :

The capacitor voltage transformers and potential transformers covered in this


specification shall meet the technical requirements listed hereunder.

4
3.1 PRINCIPAL PARAMETERS:-

Sr. Item Specification


No. 245kV 72.5kV
1. Type/Installation …….…..
Single Phase Oil filled Self cooled,
Hermetically sealed Outdoor type ………..
2. Type of mounting …………………… Steel structure ……………………
3. Highest system 245 72.5
voltage (kV rms)
4. Suitable for system ……………………………. 50Hz …………………….
frequency
5. Voltage ratio
a) Rated primary 220/√3 66/√3
voltage (kV rms).
b) Secondary voltage Core I,II Core I
(volts) 110/√3 110/√3

6. Method of earthing ………………… Solidly Earthed ………………………


the system
7. 1.2/50 microsecond 1050 325
lightning impulse
withstand voltage
(kVp)
8. 1 Minute dry & wet 460 140
power frequency
withstand voltage
primary (kV rms)
9. Min. creepage 6125 1815
distance of porcelain
housing (mm)
10. Creepage factor …………………. …. 4.0 ………………………….
(max.)
11. Rated voltage factor ……. 1.2 continuous and 1.5 for 30 seconds ……….
12. Equivalent ……………….. 8800+10% ……………………
capacitance at - 5%
power frequency for
carrier coupling for
CVT (PF)
13. Resultant high 8800 in carrier frequency range of 40 KHz N.A to 500
frequency KHz with variation in capacitance as contained in IEC-
capacitance for CVT 358 (i.e- 20% & +50%)
(PF)

5
14. One minute power
frequency withstand …………………… 3.0 …………………………
voltage for
secondary winding
(kV rms)
15. Max. temperature …… As per IS:3156 or equivalent IEC ………
rise over ambient of
50°C

4.0 GENERAL TECHNICAL REQUIREMENTS:


4.1 CAPACITOR VOLTAGE TRANSFORMER (CVT):
4.1.1 The insulation of the instrument transformers shall be so designed that the
internal insulation shall have higher electrical withstand capability than the
external insulation. The designed dielectric withstand values of external and
internal insulations shall be clearly withstand values specified in this
guaranteed technical particulars. The dielectric withstand values specified in
this specification are meant for fully assembled instrument transformers.

4.1.2 Porcelain Housing :


4.1.2.1 The details of location and type of joint, if provided on the porcelain, shall be
furnished by the supplier alongwith the offer. The housing shall be made of
homogeneous, vitreous porcelain of high mechanical and dielectric strength,
blazing of porcelain shall be of uniform brown or dark brown colour with a
smooth surface arranged to shed away rain water or condensed water
particles (fog).

4.1.2.2 Details of attachment of metallic flanges to the porcelain shall be brought out
in the offer.

4.1.3 The metal tanks shall have bare minimum number of welded joints so as to
minimize possible locations of oil leakage. The metal tanks shall be made
out of mild steel/Stainless steel/aluminium alloy, depending on the
requirement. Welding in horizontal plane is to be avoided as welding at this
location may give way due to vibrations during transport resulting in oil
leakage. Supplier has to obtain specific approval from purchaser for any
horizontal welding used in the bottom tank.
4.1.4 Surface Finish:
The ferrous parts exposed to atmosphere shall be hot dip galvanised or shall
be coated with atleast two coats of zinc rich epoxy painting. All nuts, bolts
and washers shall be made out of stainless steel.

4.1.5 Insulating Oil:


Insulating oil required for first filling of the instrument transformer shall be
covered in supplier's scope of supply. The oil shall meet the requirements of
latest edition IS:335 or equivalent IEC.
6
4.1.6 Prevention of Oil leakages and Entry of Moisture:

4.1.6.1 The supplier shall ensure that the sealing of instrument transformer is
properly achieved. In this connection the arrangement provided by the
supplier at various locations including the following ones shall be described,
supported by sectional drawings.
i) Locations of emergence of primary and secondary terminals.
ii) Interface between porcelain housing and metal tanks.
iii) Cover of the secondary terminal box.

4.1.6.2 Nuts and bolts or screws used for fixation of the interfacing porcelain
bushings for taking out terminals, shall be provided on flanges cemented to
the bushings and not on the porcelain.
4.1.6.3 For gasketed joints, wherever used nitrile butyl rubber gaskets shall be used.
The gasket shall be fitted in properly machined groove with adequate space
for accommodating the gasket under compression.
4.1.7 Oil level indicators:
Instrument transformers shall be provided with oil sight window at suitable
location so that the oil level is clearly visible with naked eye to an observer
standing at ground level.

4.1.8. Earthing:
Metal tank of the instrument transformer shall be provided with two separate
earthing terminal for bolted connection to 50X8mm MS flat to be provided by
the Purchaser for connection to station earth-mate.

4.1.9 Instrument transformer shall be provided with suitable lifting arrangement, to


lift the entire unit. The lifting arrangement shall be clearly shown in the
general arrangement drawings. Lifting arrangement (lifting eye) shall be
positioned in such a way so as to avoid any damage to the porcelain housing
or the tanks during lifting for installation/transport. If necessary, string guides
shall be offered which shall be of removable type.

4.1.10 NAME PLATE:

The instrument transformer shall be provided with non-corrosive, legible


name plate with the information specified in relevant standards, duly
engraved/punched on it. In addition to these P.O. with the date, Item No.
P.O. & Connection diagram shall also be marked in rating plate.

4.1.11 Suitable terminal connectors for connecting conductor shall be supplied.


Suitable terminal earth connectors for earthing connections shall also be
provided.
4.1.12 The terminal connectors shall meet the following requirements:
1) Terminal connectors shall be manufactured and tested as per IS:5561 or

7
equivalent IEC.
2) All castings shall be free from blow holes, surface blisters, cracks and
cavities. All sharp edges and corners shall be blurred and rounded off.
3) No part of a clamp shall be less than 10mm thick.
4) All ferrous parts shall be hot dip galvanized conforming to IS:2633 or
equivalent IEC.
5) For bimetallic connectors, copper alloy liner of minimum 2mm thickness shall
be cast integral with aluminium body.
6) Flexible connectors shall be made from tinned copper/ aluminium body.
7) All currents carrying parts shall be designed and manufactured to have
minimum contact resistance.
8) Connectors shall be designed to be corona free in accordance with the
requirements stipulated in IS: 5561 or equivalent IEC.
4.1.13 Enamel, if used for conductor insulation, shall be either polyvinyl acetate type
or amide emide type and shall meet the requirements of IS:4800 or
equivalent IEC. Polyester enamel shall not be used. Double cotton cover, if
used, shall be suitably covered to ensure that it does not come in contact
with oil.
4.1.14 The temperature rise on any part of equipment shall not exceed maximum
temperature rise specified in IS:3156 o or equivalent IEC. However, the
permissible temperature rise indicated is for a maximum ambient
temperature of 50°C.
4.1.15 The instrument transformers shall be so constructed that it can be easily
transported to site within the allowable transport limitation and in horizontal
position, if the transport limitations so demand.
4.1.16 The instrument transformers shall be vacuum filled with oil after processing
and thereafter hermetically sealed to eliminate breathing and to prevent air
and moisture from entering the tanks, sealing type oil filling and/or oil
sampling cocks shall be provided with facility to reseal the same. The method
adopted for hermetic sealing shall be described in the offer.
4.1.17 Suitable arrangement shall be made to accommodate the expansion and
contraction of oil due to temperature variation. The pressure variation shall
be kept within limits which do not impair the tightness of the instrument
transformer. A pressure relief device capable of releasing abnormal internal
pressure shall be provided.
4.2 CAPACITOR VOLTAGE TRANSFORMER (CVT):
4.2.1 The CVTs comprising of a capacitor divider unit and electromagnetic unit shall
be single phase, oil filled hermetically sealed, self cooled, outdoor type and
suitable for direct line connection without any fuse and isolating switches,
These CVTs are required to be used on interlinking substations in Haryana
power system for the purpose of protection, synchronising, interlocking, carrier
coupling and metering. CVTs shall be suitable for connecting the carrier
terminals to single circuit and double circuit transmission lines for phase to
phase coupling for power line carrier, voice communication, telemetering &
teleprinting services.
8
4.2.2 The secondary terminals of potential unit, high frequency coupling terminal and
the earthing terminals shall be brought out separately and housed in a water
proof cabinet outside the main steel chamber.
4.2.3 The capacitor voltage transformer shall be suitable for simultaneous use as
measuring unit, for feeding voltage supply to protective relays and as coupling
capacitor for carrier transmission i.e. for voice communication, carrier
protective relays, telemetering, teleprinting services over one or more carrier
channels in the frequency range of 40 to 500KHz.
4.2.4 The capacitors shall be designed for wide frequency band and low dielectric
loss. Their natural frequency shall be considerably higher than the carrier
frequency range of 40 KHz to 500 KHz.
4.2.5 The unit capacitors shall be so designed that no damage to internal elements
or change in electrostatic capacitance is resulted by the application of impulse
voltage.
4.2.6 Each CVT including its emvt unit shall be filled with insulating oil conforming to
IS:335 or equivalent IEC. And shall be hermetically sealed against moisture
and dust.
4.2.7 The electromagnetic voltage transformer unit of CVT intended for out-door
installation whose primary is to be fed by the inter-mediate tapping of capacitor
divider shall be of oil immersed, self cooled design and shall be suitable for
metering, relaying & synchronising services. The core of this transformer shall
be of high grade, nonageing, cold rolled, laminated electrical silicon steel of low
hysteresls loss & of high permeability so as to ensure high accuracy at normat
& high voltages. The primary winding shall be connected through a
compensating reactor to compensate the voltage increase at inter-mediate
tapping, whatever is the load within range of rated burden.

4.2.8 The design shall be free from corona effect to keep noise level of carrier
frequency link very low. Use may be made of grading rings or Electrostatic
screen for this purpose if required.
4.2.9 The design shall be suitable for rapid reclosing of the circuit and shall be
capable of accurate and proportionate transmission of sudden variation in the
primary voltage.

4.2.10 Each CVT shall be provided with a suitable damping device so that ferro
resonance oscillation due to saturation of iron core of transformer or any
inductance connected in parallel with it and initiated by either over voltages on
the net work side or by opening of the short circuited primary or secondaries,
shall be practically zero. Oscillations of the secondary voltages which may
arise as a result of breakdown of primary voltages due to short circuts shall not
affect the proper working of protective relays. This shall confirm to provisions of
clause:42 of IEC recommendations 186-A.
4.2.11 Design of the potential units of the CVT shall be based on the following
requirements in connection with protective relaying.

9
i) They must transmit accurately sudden drops of primary voltage.
ii) The CVTs must not enter into sub-harmonic resonance and transient
oscillations during energisation. They must be damped out with
sufficient rapidness.
iii) They must have sufficiently low short circuit impedance as seen from
secondary.
4.2.12 A device shall be incorporated in a capacitor voltage transformer for the
purpose of limiting over voltages which may appear across one or more of its
components and/or to prevent sustained ferro resonance.
The device may include a spark gap and may be located in several different
ways according to its nature. *(Clause 2.12 of IS:3156 (Part-IV)-1978 or IEC-
186A Clause 37.12)
4.2.13 Suitable terminal boxes with removable gland plate for facilitating the entry of
H.F. Cable & VT control cables shall be provided at an accessible position.

5.0 TESTS:
5.1 TYPE TEST
5.1.1 TYPE TESTS OF CAPACITIVE VOLTAGE TRANSFORMERS (CVT's):
The equipment should be offered type test. Test reports should not more
then seven years old reckoned from date of bid opening in respect of all the
tests carried out in accredited laboratories (based on ISO/IEC) by a reputed
accreditatic body or witnessed by HVPN or another electric power utility and
be submitted by the successful bidder to HVPNL for approval as schedule
given in Bar Chart.
i) Temperature Rise Test.
ii) Impulse test.
iii) Ferro-resonance test.
iv) Transient response test.
v) High voltage power frequency wet withstand voltage test.
vi) Determination of errors or other characteristics according to the
requirements of the appropriate designation or accuracy class.
vii) Capacitance measurement before voltage test.
viii) Voltage test between terminals.
ix) Measurement of capacitance and tangent of the loss angle after
voltage test.
x) Voltage test between the low-voltage terminal and the earth terminal.
xi) Oil leakage test.
xii) High frequency test.
xiii) Determination of temperature co-efficient.
5.2 ROUTINE TESTS :
As per quality assurance program (QAP).

5.3 ACCEPTANCE TESTS:

10
The following acceptance tests as stipulated in the relevant ISS-3156 shall be
carried out by the Supplier in presence of HVPNL representative, unless
dispensed with in writing by the HVPNL.
i) Verification of terminal marking and polarity.
ii) High voltage power frequency dry withstand voltage test for Primary winding.
iii) High voltage power frequency dry withstand voltage test for Secondary
winding.
iv) Partial discharge tests
v) Determination of errors or other characteristics according to the requirements
the appropriate designation or accuracy class.

6.0 DOCUMENTATION:
6.1 The successful bidder shall submit four sets of following drawings except
6.1(b) below (actual of which shall be supplied at the time of inspection) for
HVPNL approval.
List of drawings:
a) General outline and assembly drawings of the equipment.
b) Graphs showing the performance of equipments in regard to
magnetization characteristics; ratio & phase angle curves, ratio correction
factor curves.
c) Sectional views showing:
i) General Constructional Features.
ii) Materials/Gaskets/Sealing used.
iii) The insulation & the winding arrangements, method of connection of the
primary / secondary winding to the primary/secondary terminals etc.
iv) Porcelain used and its dimensions.
d) Arrangement of terminals and details of connection studs provided.
e) Name plate.
f) Schematic drawing.
g) Detailed drawing of pressure release device with detailed literature
h) Terminal connector drawing.
NOTE:- All above drawings should bear a minimum space (14X10cm) for stamping the
approval of drawings by HVPNL.

11
ANNEXURE- IA(i)

COREWISE DETAILS OF 245kV CAPACITOR VOLTAGE TRANSFORMER


(CVT)

Sl. Requirement Particulars


No.
1. Rated Primary voltage 220/√3kV
2. Type Single phase
3. No. of Secondaries 2
4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds
5. Capacitance (minimum) 8800 (+10%, -5%) pico farads
6. Rated voltage (volts) Secondary-I Secondary-II
110/√3 110/√3
7. Application Protection & Protection
Measurement
8. Accuracy 1/3P 3P
9. Output burden (VA) 100 50
10. Percentage voltage error & As per ISS/IEC
phase displacement
(minutes) for respective
specified accuracy classes.

Note:- Each winding shall fulfil its respective specified accuracy requirement
within its specified output range whilst at the same time the other
winding has an output of any value form zero to 100% of the output
range specified for the other winding in line with clause 6.2.1 of IS
3156 (Part-2 & Part-3) 1992 or its equivalent IEC.

12
ANNEXURE- IB(i)

COREWISE DETAILS OF 72.5kV CAPACITOR VOLTAGE


TRANSFORMER (CVT).

Sl. Requirement Particulars


No.
1. Rated Primary voltage 66/√3kV
2. Type Single phase
3. No. of Secondaries 1
4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds
5. Capacitance (minimum) 8800 (+10%, -5%) pico farads
6. Rated voltage (volts) 110/√3
7. Application Protection metering, carrier coupling &
interlocking of line cum earthswitch
8. Accuracy 1/3P
9. Output burden (VA) 50
10. Percentage voltage error & As per ISS/IEC
phase displacement
(minutes) for respective
specified accuracy classes.

13
SECTION-5

CHAPTER-3

TECHNICAL SPECIFICATION FOR

220 kV & 66kV

CONTROL AND RELAY PANELS

FOR SUBSTATIONS WITHOUT SUBSTATION AUTOMATION

SYSTEM

1
CONTENTS

CLAUSE NO. TITLE PAGE NO.


-------------------------------------
1.0 SCOPE 3

2.0 STANDARDS 3

3.0 SERVICE CONDITIONS 4

4.0 PRINCIPAL PARAMETERS 5

5.0 GENERAL TECHNICAL REQUIREMENTS 6

6.0 TESTS 33

7.0 DOCUMENTATION 34

ANNEXURES

A. TRANSMISSION LINE DATA 35

B. LINE PARAMETERS 36

C. DETAILS OF CARRIER EQUIPMENT 37

2
1.0 SCOPE:
1.1 This specification covers the design, engineering, manufacture, inspection &
testing at manufacturer’s work before despatch, packing, forwarding and delivery
at site of 220 kV & 66 kV control & relay panels for S/Stns. without substation
automation system.
1.2 Unless specifically excluded from the offer, all fittings and accessories, not
specifically stated in this specification but which are necessary for satisfactory
operation of the scheme or to complete the work in a good workman like manner
shall be deemed to have been included in the scope of supply of the Bidder.
1.3 CO-ORDINATION :
Circuit Breakers, CT's, PT's/CVT's & Isolating Switches etc. are being purchased
against separate specification. The Bidder of control & relay panels shall be
responsible for preparing complete wiring diagram of 66kV & 220 kV C&R panel
boards and shall also undertake to mount & wire any equipment received from
other supplier. The schematic of breakers & isolators are required to be
incorporated in the panel schematic.
1.4 EXPERIENCE:
The Bidder shall arrange C&R panels along with main relays from the same
manufacturer. However, one of the distance protection schemes on each 220 kV
feeder C&R panel and busbar protection on bus coupler cum bus bar protection
panel can be of other make also.
The manufacturer own make relays includes the relays manufactured by their
Principals /Associates.

2.0 STANDARDS :
2.1 The equipment offered shall conform to latest relevant Indian Standards listed
hereunder or equivalent IEC :-
Sr. Standard Title
No.
1. IS: 5 Colour for ready mix paints.
2. IS: 375 Marking & arrangements for switchgear, bus bars, main
connections & auxiliary wiring.
3. IS: 694 PVC insulated cable for working voltage upto and
including 1100 V.
4. IS: 722 AC Electricity meters.
5. IS: 1248 Direct acting indicating analogue electrical measuring
Part-I& IV instruments & their accessories.
6. IS: 2419 Dimensions for panel mounted indicating & recording
electrical instruments.
7. IS :3231 Electrical relays for power system protection.
8. IS :8686 Static protective relays.
9. IS :2147 Degree of protection provided by enclosures for low
voltage switchgear & control gear.

3
2.2 The works covered by the specification shall be designed, engineered,
manufactured, built, tested and commissioned in accordance with the Acts, Rules,
Laws and Regulations of India.
2.3 The equipment to be furnished under this specification shall conform to latest
issue with all amendments of standard specified above.
2.4 In addition to meeting the specific requirement called for in the Technical
Specification, the equipment shall also conform to the general requirement of the
relevant standards and shall form an integral part of Specification.
2.5 The Bidder shall note that standards mentioned in the specification are not
mutually exclusive or complete in themselves, but intended to compliment each
other.
2.6 The Bidder shall also note that list of standards presented in this specification is
not complete. Whenever necessary the list of standards shall be considered in
conjunction with specific IS/IEC.
2.7 When the specific requirements stipulated in the specification exceed or differ than
those required by the applicable standards, the stipulation of the specification shall
take precedence.
2.8 Other internationally accepted standards which ensure equivalent or better
performance than that specified in the standard referred shall also be accepted.
2.9 In case governing standards for the equipment is different from IS or IEC, the
salient points of difference shall be clearly brought out alongwith English language
version of standard or relevant extract of the same. The equipment conforming to
standards other than IS/IEC shall be subject to HVPNL's approval.
2.10 The bidder shall clearly indicate in his bid the specific standards in accordance
with which the works will be conformed.

3.0 SERVICE CONDITIONS:


3.1 Equipment to be supplied against this specification shall be suitable for
satisfactory continuous operation under the following tropical conditions:-
i) Location IN THE STATE OF HARYANA
ii) Max. ambient air temp (°C) 50
iii) Min. ambient air temp (°C) -2.5
iv) Maximum Relative humidity (%) 100
v) Minimum Relative humidity (%) 26
vi) Average annual rainfall (mm) 900
vii) Max. wind pressure (kg/sq. m.) 195
viii) Max. altitude above mean sea level (meters). 1000
ix) Isoceraunic level (days/Year) 50
x) Seismic level (horizontal acceleration) 0.3 g
xi) Average number of dust storm 35
(days per annum)
Note:-i) Moderately hot and humid tropical climate conducive to rust and fungus
growth. The climatic conditions are also prone to wide variations in
ambient conditions.
ii) Air conditioning or any special arrangement for making the control room
dust proof shall not be provided in any of the S/Stn.
3.2 All control wiring, equipment & accessories shall be protected against fungus
growth, condensation, vermin & other harmful effects due to tropical environments.

4
3.3 AUX. POWER SUPPLY :
i) A.C. Supply : 415/240 Volts, 3-phase, 4-wire, 50 Hz
Voltage variation : ± 10%
Frequency variation : ± 3%
ii) D C Supply : 220 Volts, 2 wire available from S/Stn.
battery(insulated)
Variation : ±10%.
3.4.1.1 220 kV & 66 kV voltages will be three phase having normal frequency of 50 Hz
subject to a variation of ± 3%. Neutrals of the Power Transformers at the S/Stn.
covered in this specification are solidly earthed.

4.0 PRINCIPAL PARAMETERS :

4.1 The panels shall have the principal dimensions as detailed below:-
i). Depth of panels = 610 mm
ii). a) Height of switchboard above base frame = 2210 mm
b) Height of base frame = 102 mm
iii). Width of corridor in case of duplex panels = 762 mm
iv). TYPE OF PANEL :
a) Simplex control & relay panels for all 66kV circuits.
b) Duplex control & Relay panels for all 220 kV circuits.
Note:- The offer of the bidder not conforming to above requirement shall be out
rightly rejected.

4.2.1 MIMIC DISPOSITION :


The mimic disposition on control panel should be matching to our standard
drawings; the details of which will be supplied to successful bidder.

4.2.2 MIMIC SCHEME :


Suitably painted mimic diagram will be reproduced on the panels/boards covered
by the specification. Automatic semaphores for indicating 'open' and 'close'
position of circuit breakers, isolators & earth switches shall be suitable
incorporated in the mimic diagram. The colour scheme for all the S/Stn. specified
herein shall, however, be as under;-
----------------------------------------------------------------------------------------------------------------------
Voltage Level Colour Shade No. (according to IS:5 or Equivalent IEC)
---------------------------------------------------------------------------------------------------------------------
220 kV Dark brown 412
66 kV Golden brown 414
---------------------------------------------------------------------------------------------------------------------

4.2 ARRANGEMENT OF PANELS:


The panels shall be fabricated so that even if the serial of panels is changed no
difficulty will be faced in the placement of panels and cabling etc. The sequence of
various panels in a panel board at a S/Stn. shall be supplied to successful bidder.

5
5.0 GENERAL TECHNICAL REQUIREMENTS:

5.1 MATERIAL & WORKMANSHIP :


All material used in the construction of the panels/relays shall be of the best
quality obtainable of their respective kind and whole of the work shall be of the
highest class, well finished and of approved design and make.
Castings shall be free from blow-holes, flaws, cracks or other defects and shall be
smooth grained and of true dimensions and forms.
The draw out mechanism in respect of draw out relays should be smooth and
convenient so as to give adequate service during their use.

5.2 DEPARTURE FROM THE SPECIFICATION:


Should the bidder wish to depart from the provisions of this specification either on
account of manufacturing practice or for any other reasons, he will draw specific
attention to the proposed points of departure on the prescribed Performa in his
tender and submit such full information, drawings and specifications as will enable
the merit of his proposal to be appreciated.
In the event of Bidder drawings, specification and tables etc. disagreeing with this
specification during the execution of the contract this specification shall be held
binding unless the departures have been fully recorded as required above.

5.3 PAINTING:
All unfinished surfaces of steel panels and frame works shall be sand blasted to
remove rust scale, foreign adhering matter & grease. A suitable rust resistance
primer shall be applied on the interior & exterior of steel which will be followed by
application of an under coat suitable to serve as base for finishing coat. The
finishing coat shall be as under :-
Exterior - Stove enameled light grey as per shade No.631 of IS:5.
Interior - stove enameled white.
Base frame - Stove enameled glossy black.

5.4. TESTING EQUIPMENT AND TESTING FACILITIES ON THE RELAYS :


The bidder shall recommend suitable testing equipment (alongwith quantity)
required for field testing of protective schemes and other relays offered against
this specification. The actual quantity to be ordered shall be determined by the
HVPNL.
Also adequate testing facilities should be provided on the relay so as to test them
without the necessity of their removal or making any extra connections. The
Bidder will clearly indicate the testing procedure to be followed in respect of relays
offered.
5.5 The transmission lines shall be either in form of overhead conductor or
combination of overhead conductor & underground cable. The tentative
transmission line data in respect of 220kV & 66kV lines covered in this
specification is given at Annexure-A.
The standard chart providing the details of per unit values of Z1, Z2 & Z0 on 100
MVA base per 100 km of overhead line for calculating these values for full lengths
of lines are enclosed at Annexure-B.
The tentative details of carrier equipment are enclosed at Annexure-C.
The suitability of distance scheme offered with reference to the above parameters
may be seen.

6
Guaranteed test sheets shall be submitted by the bidder. Relevant literature shall
be supplied along with the bid for proper appreciation of the offered equipment.

5.6 TRANINING OF PERSONNEL : as per clause 12 of section I General.

5.7 GENERAL DESCRIPTION :

5.7.1. DUPLEX C&R PANEL BOARDS :


The panel shall comprise of cubicles placed in juxtaposition to form continuous
board. At each Substation the relay boards shall be mounted back to back with
the control board and so arranged as to have a corridor carrier in between to
provide access to internal wiring. Hinged lockable access doors shall be fitted at
both ends of the corridor and switch boards interior shall be automatically lit by the
opening of these doors.
The C&R panels tendered for sr. no. 4.1. (iv)(b) above may match in the following
respects :-
i) Heightwise and depthwise matching including the matching in respect of
corridor width.
ii) Size & disposition of mimic diagram matching.
The offered C&R panels shall be complete with side covers for each circuit, end
access doors with concealed hinges having a swing of not less than 105 in fully
open position of the doors.
The control and relay cubicles shall be made of sheet steel of thickness not less
than 10 SWG for the base frame, door frame, front and rear portions of cubicle
and not less than 14 SWG for doors, side, top & bottom portions.
The bottom of the cubicle frame shall be suitable for erection on flush concrete
floor. The trench, carrying the control cables, shall run at the back of erected C&R
panel boards in the switch house building. Evenly spaced grout bolts projecting
through the base channel forming members of the frame shall be used for
securing cubicles to the floor.
The front panels of all cubicles shall be detachable and all inter-connections from
the control panel to the relay panel & vice -versa shall be through terminal
connectors. The inter-connections shall preferably run underneath the top cover.
The control & relay boards shall be completely dust & vermin proof. The enclosure
shall provide degree of protection not less than IP-31 in accordance with IS:2147
and shall be suitable for tropical use. All holes and extension windows in the
panels shall be blanked and access doors shall be lined with compressible liners
at the edges.
5.7.2 SIMPLEX C&R PANEL BOARDS :
The panel board for the substations mentioned at sr. no. 4.1. (iv)(a) above shall
be of `simplex' type & consisting of separate cubicles (for each circuit complete
with side covers) made of sheet steel of thickness not less than 10 SWG for the
base frame, door frame and front portions of the cubicles and not less than 14
SWG for door, side, top & bottom portion having provision for extension at both
ends with internal wiring, illumination with door operated off & on switch. The
cubicle shall be suitable for floor mounting with its bottom open. Each cubicle shall
be fitted with flush mounted steel hinged door & lock at the back & all the
equipments will be mounted in front. The supply shall include suitable grouting
bolts and nuts etc. All holes and extension windows shall be blanked and access
doors shall be provided with compressible liners at the edges.

7
These simplex panels offered may, therefore, match in following respects :-
i) Height-wise and depthwise matching.
ii) Size & disposition of mimic diagram matching.
The control & relay boards shall be completely dust & vermin proof. The enclosure
shall provide degree of protection not less than IP-31 in accordance with IS:2147
and shall be suitable for tropical use.

5.8 SUPERVISION SCHEME :

5.8.1 INDICATING LAMPS :


5.8.1.1. 220 kV control panel of all 220 kV circuits covered by this specification shall be
fitted with the following supervision lamps:-
Circuit breaker `Open' : Green.
Circuit breaker `Close' : Red.
Auto trip : White.
Spring charge lamp : Blue
5.8.1.2 66 kV control & relay panel boards of all respective concerned S/Stations covered
by this specification shall be provided with the following supervision lamps :-
Circuit breaker `close' : Red.
Circuit breaker `Open' : Green.
Auto trip : White.
Spring charge lamp : Blue
5.8.1.3 Auto trip lamp shall be wired on 220 V DC whereas circuit breaker `open', circuit
breaker `close' and spring charge lamps shall be wired so as to be on 220 V AC
under normal conditions with an automatic changeover relay to change them over
to 220V DC supply in the event of failure of AC supply.
5.8.1.4 Glass/Plastic lens of appropriate colour shall be screwed into the front of the lamp
body. The design of indication lamps shall be such as to facilitate replacement of
fused lamps.
5.8.1.5 An engraved label indicating the purpose of the lamp shall also be provided with
each lamp.

5.8.2. SEMAPHORE INDICATORS :


Automatic semaphore relays of the under-mentioned types shall be provided to
mimic the position of circuit breakers, isolators and earth switches in the mimic
diagram painted on the control and relay boards.
5.8.2.1. The control & relay panels of all the S/Stns. covered by this specification shall be
provided with supply failure type semaphores to show on/off position of the circuit
breakers/isolators/earth switches. When the supply failure to the semaphore
occurs the pointer shall take up an intermediate position to indicate the supply
failure. For distinction purposes, the disc diameter of the semaphore relays used
to mimic the circuit breaker position will be bigger than those for isolator/earth
switch.
5.8.2.2. The operating coil of the semaphore relays shall be continuously rated & shall be
suitable for use with 220 V DC. The semaphore relays shall work satisfactorily
between 80 % -120 % of rated DC voltage.

5.8.3 ANNUNCIATOR :
5.8.3.1. Each of the control and relay panels shall have independent annunciation
scheme. The scheme shall generally conform to the followings:-

8
i) The closing of an initiating contact shall sound an alarm and light an
annunciator indicating lamp. It shall be possible to silence the alarm by pressing
`accept' push button.
ii) By pressing the `reset' push button the individual indicating lamp shall be
extinguished provided that the troubled contact has opened. The resetting
shall be possible only after the alarm is accepted.
iii) Lighting of an annunciator lamp shall not interfere with or cause false
operation of any other annunciator lamp whether lighted simultaneously or in
sequence. Operation of `reset' push button shall not cause the alarm to
sound whether or not the trouble contact is closed.
iv) With the help of `lamp test' push button it shall be possible to test all the
lamps in the group.
v) The lamps for visual annunciation system shall have separate
compartments behind inscribed translucent windows. These shall be so
arranged that illumination from one compartment shall not light adjacent
windows.
vi) The equipment shall operate on 220 V DC and shall be complete with
`alarm accept', `alarm reset' and `lamp test' push buttons.
vii) Only static facia alarm scheme is acceptable .
5.8.3.2. The minimum annunciation ways for various 220 kV & 66 kV C&R panels shall be
provided as under:-
Description Annunciation Ways (Nos.)

Transformer Feeder Bus Transformer Capacitor


panel panel Coupler incomer panel
panel for panel
double
bus
24 24 24 - -
220 kV
66 kV 16 12 10 10 10
All the 66kV & 220 kV panels have trip as well as non trip annunciations, as such
the facia must have two buses; one for trip alarm and another for non trip alarm.
All trip facia shall have red colour and all non trip facia shall have white colour.

5.8.4 ALARMS :
5.8.4.1 Alarm scheme for trip alarms :
Trip commands due to operation of protective relays will trip the breaker and light
the relevant annunciation window. Auxiliary contact of circuit breaker and trip bus
of annunciator will actuate bell (common to a panel board at a S/Stn.) & will be
cancelled by the circuit breaker control handle & ‘Accept’ button of annunciator in
case of all the panels against this specification. Auto trip lamp will glow on the
concerned panel & there will be flag indication on the concerned protective
relays/auxiliary relay of the panel.
5.8.4.2 Alarm scheme for non-trip alarms :
Non-trip commands will light the relevant annunciation window. Non- trip bus of
annunciator will actuate hooter (common to a panel board at a S/Stn.) & will be

9
cancelled by the ‘Accept’ button of annunciator in case of all the panels against
this specification.

5.8.4.3 D.C. Fail alarm scheme;


A relay for monitoring the Trip Circuit D.C. wiring of the control and relay panels
shall be provided. The operation of the DC fail scheme shall be accompanied by
visual (indicating lamp of amber colour on the concerned panel) and audio (ringing
of common buzzer) annunciation. It shall be possible to silence the buzzer by
pressing the 'accept' push button while the lamp shall continue to glow fill the fault
has been attended to & D.C. supply restored. A 'DC fail test' push button will be
provided to test the lamp circuit of the scheme.

5.9 METERING SCHEME :


5.9.1. All indicating and integrating instruments shall be of switch-board type back
connected suitable for flush mounting and provided with dust and vermin proof
cases and finished in egg shell bright black colour and shall be calibrated to read
directly the primary quantities. All fixing screws, nuts and threaded parts shall be
designed to relevant Indian Standards. All the instruments (i.e. Voltmeters,
frequency meters & Wattmeters) shall be in square pattern case and shall conform
to the provisions of the latest edition of IS:1248 & IS:2419 or relevant B.S., I.E.C.
standards. The nominal sizes of these indicating instruments shall be 144 mm2.
Energy meters shall conform to provisions of IS:13779 amended upto date or
relevant I.E.C. standards.

5.9.2 AMMETERS :
Ammeter shall be suitably scaled (additional dials, if any, required to cover all the
taps of the CT's shall be included at the time of tendering ) and provided with a
selector switch facilitating the measurements of phase currents as well as the
unbalance current. The coil of the ammeter shall be rated for 1 Amp. for 66 kV &
220 kV levels . The instruments shall be of moving iron spring controlled type of
industrial grade `A' classification with accuracy class 1.

5.9.3 VOLTMETERS :
Voltmeter shall be suitably scaled and provided with selector switch (wherever
asked for ) to facilitate the measurement of phase-to-phase and phase- to-neutral
voltage of all the three phases one by one. The coil of the voltmeter shall be rated
for 110 volts ( phase-to-phase ) wherever asked with selector switch and 110/√3
volts if asked without selector switch. The instrument shall be of moving iron
spring controlled type of industrial grade `A' classification with accuracy class of 1
and shall conform to IS:1248 or relevant I.E.C. standard.

5.9.4 DIGITAL BUS VOLTAGE AND FREQUENCY METERS :


Digital bus voltage and frequency meters shall be of class 0.5 and shall have
digital display of four & a half(4½) and four (4) digits respectively, with display size
not less than 25 mm (height).

5.9.5 KILO WATT HOUR METERS :


All the 220 kV & 66 kV feeder C & R panels against this specification shall be
provided with Kilo Watt hour meter. The Kilo Watt hour meter shall be of 3

10
element type suitable for use on three phase four wire unbalanced system.
Calibration shall correspond to CT ratio 400/1 A for 220 kV feeder & 300/1A for all
the 66 kV feeder panels. For other C.T. ratios, multiplying factors shall be used
which may be inscribed on the dial plate. The current coil of the instrument shall
be suitable for 1 Amp. CT secondary and voltage coil shall be suitable for 110
Volts (phase to phase).The instrument shall be static type. The accuracy class
should be 1.0 .

5.9.6 MEGAWATT METERS & MEGAVAR METERS:


The 220 kV feeder C&R panels against this specification shall be provided with
export/import type megawatt-meter & mega VAR-meter.The instrument shall be of
two element type suitable for use on three phase & three wire unbalanced system
and shall be scaled with Zero center MW and zero center MVAR (i.e. suitable for
indicating flow of active & reactive power in both the directions) corresponding to
line CT particulars. The current coil of these instruments shall be suitable for 1
Amp. CT secondary & voltage coil shall be rated 110 volts (phase to phase). The
instruments shall be iron cored dynamometer type and calibrated corresponding to
a CT ratio, spare dials shall be provided for remaining ratios of CT's.

5.9.7 FREQUENCY METERS:


Frequency meter shall have a range of 45 to 55 Hz. The instrument shall be of
moving iron spring controlled type of Industrial grade 'A' classification conforming
to relevant IS.

5.10 CONTROL SCHEME:

5.10.1 CONTROL SWITCH FOR CIRCUIT BREAKER :


5.10.1.1 It shall be possible to close various circuit breakers from the control room. For
this purpose control switches having pistol grip type and of the spring return to
neutral position type non lockable handles with alarm cancellation contacts shall
be provided for `OP' of ckt. breakers. These shall be so designed that after
being operated to `close' a circuit breaker, the operation cannot be repeated
until the switch has been turned to a `trip' position making it impossible to
perform two `closing' operations consecutively.
5.10.1.2 The rating of the control switch contacts shall be suitable for the duty imposed
by the closing & opening mechanism of circuit breakers and shall conform to the
recommendations which may be made by the suppliers of circuit breakers. The
moving & fixed contacts shall be of such a form & material as will ensure good
contact and long service under severe operation duty. All contacts shall be
readily renewable.
5.10.1.3 The number of contacts in the control switches shall be decided by the
tenderer in view of various requirements of this specification. Two pairs of
contacts one normally open and one normally closed shall be kept spare. The
total number of contacts proposed to be provided shall be stated in the tender.
5.10.1.4 Safety against inadvertent operation due to light touch in the control switches
shall be ensured.
5.10.2 CONTROL SWITCH FOR ISOLATOR :
It shall be possible to close the 220 kV Isolators from the control room. For this
purpose control switches with pistol grip handles & having no provision for locks
shall be mounted on the 220 kV C&R panels specified herein. The size/colour of

11
the control switch handle meant for isolator will be different so as to be easily
distinguishable from those meant for circuit breaker controls.

5.10.3 MANUAL SYNCHRONIZING ARRANGEMENT :


5.10.3.1 Synchronizing switches shall be provided on each of the 220 kV feeder & bus
coupler panels to facilitate checking of various parameters with the instruments
mounted on the synchronising panel.
5.10.3.2 Suitable interlock shall be provided in the closing circuits of C.B. so that the C.B.
could be closed only after the synchronizing (of the supplies) has been checked.

5.11 COMMUNICATION COMPATIBILTY OF RELAYS

All relays shall conform to the requirements of IS:3231/IEC-60255/IEC 61000 or


other applicable standards. Relays shall be suitable for flush or semi-flush
mounting on the front with connections from the rear. All protective relays shall be
in draw out or plug-in type modular cases with proper testing facilities. Necessary
test plugs/test handles shall be supplied loose and shall be included in Bidder’s
scope of supply.
All main protective relays shall be numerical type and communication protocol
shall be as per IEC 61850. Further, the test levels of EMI as indicated in IEC
61850 shall be applicable to these.
For numerical relays, the scope shall include the following :
a) Necessary software and hardware to up/down load the data to/from the relay
from/to personal computer installed in the substation. However, the supply of PC
is not covered under this clause.
b) The relay shall have suitable communication facility for future connectivity to
SCADA. The relay shall be capable of supporting IEC 61850 protocol (with optical
port).

5.12 TRIP CIRCUIT SUPERVISION RELAY:


The relay shall be capable of monitoring the healthiness of each trip coil and
associated circuit of circuit breaker during "on & off" conditions. The relay shall
have time delay on drop-off of min. 200 milli seconds and shall be provided with
operation indicator.
220 kV circuit breakers being procured are generally equipped with 2 trip coils in
each phase/pole of the breaker. For monitoring of trip circuits, both in `open' &
`close' position of the circuit breaker, 6 Nos. automatic trip circuit supervision
relays (one for each pole and each trip coil) are proposed.
For monitoring of entire trip circuit (from control & relay panel terminal to the trip
coil of circuit breaker) both in `open' & `close' position of the circuit, 2 No.
automatic trip circuit supervision relays are proposed for 66 kV panels.
5.13 D.C. FAIL ALARM RELAY:
A suitable relay for monitoring the Trip Circuit D.C. wiring of the control and relay
panels shall be provided. The relay shall have time delay on drop-off of min. 100
milli seconds and shall be provided with operation indicator.
5.14 VOLTAGE SELECTION SCHEME:
The 220 kV & 66 kV bus PTs exist on all the phases of both the 220 kV & 66 kV
buses at substations having double bus arrangement. Proper voltage selection
scheme shall be provided on panels.

12
5.15 AUTO RECLOSING SCHEME:
5.15.1 The protective scheme shall incorporate the necessary equipment to impart
auto-reclosing impulse to the circuit breaker when it has tripped either due to the
operation of the line protection scheme in the first zone or the accelerated
operation of it with the help of carrier equipment. No auto-reclosing impulse shall
be transmitted in the event of a fault cleared by the IInd & IIIrd zone of line
protection scheme. Auto-reclosing will also be blocked in case the circuit breaker
is tripped manually.
5.15.2 The provision of single & three phase auto-reclosing is to be made on 220 kV
feeder C&R panels.
5.15.3 CHECK SYNCHRONIZING & DEAD LINE CHARGING SCHEME :
Check synchronizing relay and dead line charging equipment shall be provided for
220 kV feeder C&R panels. The check synchronizing relay shall compare the
phase angle & frequency of the `incoming' and `running' supplies and allow the
auto-reclose to take place only if the said parameters are within the permissible
limits. The dead line charging equipment shall ensure auto-reclosing a circuit
breaker on to a `dead' line leaving the checking of synchronism of two supplies to
the other end of it.
Synchronising check relay with necessary auxiliary equipments shall be provided
which shall permit breakers to close after checking the requirements of
synchronising of incoming and running supply. The phase angle setting shall not
exceed 35 degree and have voltage difference setting not exceeding 10%. This
relay shall have a response time of less than 200 milliseconds when the two
system conditions are met within preset limits and with the timer disconnected.
The relay shall have a continuously adjustable time setting range of 0.5-3 secs.
5.15.4 A four position stay-put non-locking type of auto-reclose selector-switch shall be
provided on each of the 220 kV feeder C&R panels and shall have the following
four positions:
a) `Single phase auto' :
In this position, the relay shall allow single shot single pole auto reclosing for
single line to ground fault. For any other fault, the scheme shall allow all the three
poles of the circuit breaker to trip & lock them out.
b) `Single & three phase auto' :
In this position the relay shall allow single shot single pole auto-reclosing for single
line to ground fault and three pole auto-reclosing for other faults such as line to
line, double line to ground and three phase faults.

c) `Three phase auto' :


In this position, the relay shall impart three pole, single shot-reclosing impulse
irrespective of the type of fault.
d) `Non - auto' :
By putting the switch in this position it shall be possible to make the reclosing
scheme totally inactive and all the three poles of the circuit breaker shall trip
irrespective of the nature of a fault.
5.15.5 The reclosing scheme shall automatically reset after any successful reclosure and
shall lock out in case the circuit breaker trips immediately after reclosure. Also the

13
(reclosing) scheme shall not initiate reclosing upon an unsuccessful attempt to
manually close circuit breaker.
5.15.6 There shall be clear target indications for successful & un-successful operation.
5.15.7 The autoreclosing scheme shall have continuously variable dead time setting
range of 0.1-2 secs for single phase reclosing as well as for three phase reclosing.
The scheme shall have continuously variable reclaim time setting range of 5-300
secs.
Note:- The auto reclosing scheme in built with numerical distance protection relays is
acceptable provided it is available in both Main -I and Main-II distance protection
schemes and meets the above specification.

5.16 PROTECTION SCHEME :

5.16.1 PROTECTION SCHEME FOR POWER TRANSFORMERS .

A) TRANSFORMER DIFFERENTIAL PROTECTION :


The relay shall
i) Be triple pole numerical type.
ii) Have 3 instantaneous high set over-current units.
iii) Have second harmonic restraint or other inrush proof feature and be stable
under normal over fluxing condition.
iv) Have fifth harmonic by pass filter or similar other arrangement to prevent
maloperation of the relay under operating conditions.
v) Be suitable for rated current of 1A and include necessary ICTs for ratio &
phase angle correction.
vi) Have operating current setting sufficiently low (15% or less) so as to cover
practically the whole of the transformer against all types of faults.
vii) Have adjustable bias setting range of 20- 50%.
viii) Have maximum operating time of 30 milli seconds at 5 times the rated
current.
ix) Be provided with necessary terminals & links to measure current in
restraining circuits & in the operating circuits of all the phases under load
without making any wiring changes.
x) Cover the lightning arrestors (proposed to be provided very close to the
transformer) in the zone of protection.
xi) The Scheme shall have in-built features of disturbance recorder and event
logger. The scope of the relay shall include necessary software and
hardware to down load the DR & EL data from relay to the PC installed in
S/Stn. However, the supply of PC is not covered under this clause.
For disturbance recorder and event logger features, it shall have 8 analog
and 16 digital channels (out of which at least 8 shall be external digital
inputs). It shall have its own time generator and the clock of the time
generator shall be such that the drift is limited to +0.5 seconds/day, if
allowed to run without synchronization. Further, it shall have facility to
synchronize its time generator from Time Synchronization Equipment
having output of following types.

• Voltage signal: (0-5V continuously settable, with 50m Sec. minimum pulse
duration)

14
• Potential free contact (Minimum pulse duration of 50 m Sec.)
• IRIG-B
• RS232C
The recorder shall give alarm in case of absence of synchronising pulse
within specified time.
a) The disturbance recorder shall meet the following requirements:
• The frequency response shall be 5 Hz on lower side and 250 Hz or better
on upper side.
• Scan rate shall be 1000 Hz/Channel or better.
• Pre–fault time shall not be less than 100 milliseconds and the post fault
time shall not be less than 2 seconds (adjustable). If another system
disturbance occurs during one post-fault run time, the recorder shall also
be able to record the same. However, the total memory of acquisition unit
shall not be less than 5.0 seconds.
b) The event logger shall meet the following requirements:
• The time resolution shall be 1 milli second.
• Cope with up to 40 changes in any one 10 milli seconds interval.
• The date and time should be printed to the nearest 1 milli second followed
by a message describing the point which has operated.
• Events occurring whilst a previous event is in process of being printed are
to be stored to await printing.

B) NON DIRECTIONAL THREE OVER CURRENT+ ONE EARTH FAULT


PROTECTION WITH HIGH SET:
The 3 O/C & 1 E/F elements shall be either independent or composite units. The
relay shall be single pole inverse definite minimum time lag having definite min.
time of 3 secs. at 10 times settings. Over current relay with a setting range of
50%-200% of 1 Amp. supplemented with high set units having a setting range of
500% to 2000% of 1 Amp. shall be provided. Earth fault relay with a setting range
of 20%-80% of 1 Amp. supplemented with high set units having a setting range of
200% to 800% of 1 Amp. shall be provided.
C) RESTRICTED EARTH FAULT PROTECTION :
It shall be single pole type for the clearance of earth faults in the protected zone.
The relay shall be of high impedance type with a suitable setting to cover at least
90% of the winding & shall have a setting range of 10% to 40% of 1 Amp. or
suitable voltage setting. The relay shall be complete with tuned 50 Hz circuit &
stabilizing resistance. The tuned circuit will help reject harmonics produced by CT
saturation and thus make the relay operative for fundamental frequency only. The
stabilizing resistance may appropriately be set to avoid mal-operation under
through fault conditions. The relay shall be numerical type.
D) 8 No. auxiliary relays for various transformer trip functions (Main Buch. Trip,
OLTC Oil Temp. Trip, Winding Temperature Trip, Oil Temp Trip, Pressure Relief
Trip, Surge Relay Trip and two no. spare) shall be provided.
E) OVER FLUXING PROTECTION:
An over fluxing detecting relay for the protection of the transformer against over-
fluxing conditions is proposed to be provided on each of the 220 kV transformer
C&R panels covered by this specification. The relay shall be numerical in design
with adjustable setting so as to avoid its operation on momentary system
disturbances. The relay shall be suitable for 110 Volts. The relay shall have

15
inverse time characteristics, matching with transformer overfluxing withstand
capability curve. The relay shall provide an alarm with v/f setting range of 100% to
130% of rated values and time delay continuously settable from 0.1 to 6 seconds
to draw the operator's attention about the existence of over-fluxing conditions. The
tripping time shall be governed by v/f versus time characteristics to cause tripping
of transformer controlling circuit breaker if the over-fluxing conditions continue to
exist.
Note:- The over fluxing relay in built with the numerical differential protection relay is
acceptable provided it meets the above specification.
F) OVER LOAD ALARM RELAY:
It is proposed to provide an over current (i.e. single phase) relay for initiating an
alarm during transformer overload condition on the T/F C&R panels. The relay
shall have CONTINUOUS VARIABLE setting range of 50-120% of 1Amp. and
shall be supplemented by a continuously variable timer of 1 to 10 seconds. The
relay shall be arranged to sound an alarm when the transformer exceeds the
setting for a given period of time to draw the operator's attention.
Note:- The over load alarm relay in built with the numerical differential protection relay is
acceptable provided it meets the above specification.

5.16.2 PROTECTION SCHEME FOR LINES:

A) MAIN- I NON-SWITCHED DISTANCE PROTECTION [FOR 220 kV LINES] :


The scheme shall :-
i) be numerical & modular in construction. Relay shall have continuous self
monitoring & diagnostic feature.
ii) have high speed non-switched distance relays for three phase systems to
clear all type of line faults within the set reach of the relay.
iii) It should cover at least line sections completely with 20% in hand margin.
iv) measure all type of faults without the need to switch the measuring
elements to the faulty phase or phases. Zone switching to extend the
reach of the measuring elements is not allowed. The reach of each zone
shall be independently & individually adjustable and shall have setting in
steps of 1%. Memory circuits with defined characteristics shall be provided
in all three phases to ensure correct operation during close-up 3 phase
faults and other adverse conditions.
v) have a max. operating time upto trip impulse to circuit breaker (complete
protn. time including applicable carrier & trip relay time) under source to line
impedance ratios (SIR) under all possible combinations of fault with PT
being used on the line (with all filters included) at 50% of zone-1 reach :
for SIR 0.01-4:as 40 ms at nearest end & 60 ms at other end of line.
for SIR 4-15 :as 45 ms at nearest end & 65 ms at other end of line.
(carrier transmission time is taken as 20 ms provided that any reduction in
carrier time shall be directly reflected as reduction in maximum operating
time).
vi) have stepped time-distance characteristics and shall have at least two
directional and one non-directional independently variable time graded
distance protection zones to cover two adjacent line sections.
vii) The relay shall have mho or quadrilateral or other suitably shaped
characteristics for zone-1,2,3. The relay shall have an adjustable

16
characteristics angle setting range of 30 - 85 degree or shall have
independent resistance(R) & reactance(X) setting..
viii) ensure that this long coverage is consistent with limitations imposed by
heavy loading and sound phase component of fault current. If the
characteristics of starting relays are such that it cannot pick-up because of
very low infeed, under-voltage relays may also be used as supplementary
relays.
ix) have two independent continuously variable time setting range of 0-3
seconds for zone-2 and 0-5 seconds for zone-3.
x) have a maximum resetting time of less than 35 milli-seconds.
xi) have facilities for offset features with adjustable 10-20% of Zone-3 setting.
xii) have residual compensation variable from 30-150%.
xiii) operate instantaneously when circuit breaker is closed to zero-volt 3 phase
fault.
xiv) be suitable for single & three phase tripping.
xv) have a continuous current rating of two times of rated current. The voltage
circuit shall be capable of operation at 1.2 times rated voltage. The relay
shall also be capable of carrying a high short time current of 80 times rated
current without damage for a period of 1 sec.
xvi) be selective between internal and external faults.
xvii) have adequate contacts to meet the complete scheme requirements & if
required incorporate three separate high speed self reset trip relays for
single phase faults and a fourth high speed trip relay for multi-phase faults.
xviii) have suitable number of potential free contacts. Multiplication relays, if
required, shall be provided for Carrier aided features, Auto reclosing, Event
Logger, Disturbance recorder & Data acquisition system.
xix) include power swing blocking protection which shall
a1) be of triple pole type
a2) have suitable setting range to encircle the distance protection described
above.
a3) have a continuously adjustable time delay on pick up of setting range 0-2
seconds.
a4) block tripping during power swing conditions.
a5) be of numerical type
xx) include fuse failure protection which shall
a1) monitor all the three fuses of PTs/CVTs and associated cable against
open circuit.
a2) inhibit trip circuits on operation and initiate annunciation.
a3) remain inoperative for system earth faults.
a4) be of numerical type.
xxi) be wired for carrier inter-tripping (PUR/POR) & carrier blocking features
selectable at site.
xxii) be suitable for 1 Amp. rated CT secondary, 110V (phase to phase ) VT
supply and 220 V DC supply. Mode of conversation of DC supply from 220
V DC to the voltage level required for their scheme may be mentioned in
detail. Requirement of CTs & VTs for the satisfactory working of the
scheme may also be indicated in the tender.
xxiii) The relay shall be suitable for series compensated line and must have a
current reversal guard feature.

17
xxiv) The Scheme shall have in-built features of broken conductor detection,
distance to fault locator, disturbance recorder and event logger. The scope
of the relay shall include necessary software and hardware to down load
the DR & EL data from relay to the PC installed in S/Stn. However, the
supply of PC is not covered under this clause.
For disturbance recorder and event logger features, it shall have 8 analog
and 32 digital channels (out of which at least 16 shall be external digital
inputs). It shall have its own time generator and the clock of the time
generator shall be such that the drift is limited to +0.5 seconds/day, if
allowed to run without synchronization. Further, it shall have facility to
synchronize its time generator from Time Synchronization Equipment
having output of following types.

• Voltage signal: (0-5V continuously settable, with 50m Sec. minimum pulse
duration)
• Potential free contact (Minimum pulse duration of 50 m Sec.)
• IRIG-B
• RS232C
The recorder shall give alarm in case of absence of synchronising pulse
within specified time.
a) The disturbance recorder shall meet the following requirements:
• The frequency response shall be 5 Hz on lower side and 250 Hz or better
on upper side.
• Scan rate shall be 1000 Hz/Channel or better.
• Pre–fault time shall not be less than 100 milliseconds and the post fault
time shall not be less than 2 seconds (adjustable). If another system
disturbance occurs during one post-fault run time, the recorder shall also
be able to record the same. However, the total memory of acquisition unit
shall not be less than 5.0 seconds.
b) The event logger shall meet the following requirements:
• The time resolution shall be 1 milli second.
• Cope with up to 40 changes in any one 10 milli seconds interval.
• The date and time should be printed to the nearest 1 milli second followed
by a message describing the point which has operated.
• Events occurring whilst a previous event is in process of being printed are
to be stored to await printing. Over 100 such events must be stored.
c) The distance to fault locator shall meet the following requirements:
• Be On-Line type and suitable for breaker operating time of 2 cycles.
• The display shall be directly in percent of line length or kilometers without
requiring any further calculations.
• Shall have an accuracy of 3% or better for the typical conditions defined for
operating timings measurement of distance relays. The above accuracy
should not be impaired by presence of remote end infeed, predominant
D.C. component in fault current, high fault arc resistance, severe CVT
transients.
• Shall have parallel line mutual zero sequence compensation feature.

18
B) MAIN -II NON-SWITCHED DISTANCE PROTECTION [FOR 220 kV LINES] :
For Main-II distance protection, scheme shall be numerical and shall have same
features as that of Main-I protection against sub para 5.14.2.(A) above but with
different measuring technique.

C) NON-SWITCHED DISTANCE PROTECTION SCHEME [FOR 66 kV LINES] :


The main protection scheme for these lines will be distance scheme working
on definite distance measuring principle both for phase & earth faults. The scheme
shall :-
i) be numerical & modular in construction. Relay shall have continuous self
monitoring & diagnostic feature.
ii) have high speed non-switched distance relays for three phase systems to
clear all type of line faults within the set reach of the relay.
iii) It should cover at least line sections completely with 20% in hand margin.
iv) measure all type of faults without the need to switch the measuring
elements to the faulty phase or phases. Zone switching to extend the
reach of the measuring elements is not allowed. The reach of each zone
shall be independently & individually adjustable and shall have setting in
steps of 1%. Memory circuits with defined characteristics shall be provided
in all three phases to ensure correct operation during close-up 3 phase
faults and other adverse conditions.
v) have a max. operating time upto trip impulse to circuit breaker (complete
protn. time including trip relay time) under source to line impedance ratios
(SIR) :0.01-4 as 50ms under all possible combinations of fault at 50% of
zone-1 reach.
vi) have stepped time-distance characteristics and shall have at least two
directional and one non-directional independently variable time graded
distance protection zones to cover two adjacent line sections.
vii) The relay shall have mho or quadrilateral or other suitably shaped
characteristics for zone-1,2,3. The relay shall have an adjustable
characteristics angle setting range of 30 - 85 degree or shall have
independent resistance(R) & reactance(X) setting..
viii) ensure that this long coverage is consistent with limitations imposed by
heavy loading and sound phase component of fault current. If the
characteristics of starting relays are such that it cannot pick-up because of
very low infeed, under-voltage relays may also be used as supplementary
relays.
ix) have two independent continuously variable time setting range of 0-3
seconds for zone-2 and 0-5 seconds for zone-3.
x) have a maximum resetting time of less than 55 milli-seconds (including the
resetting time of trip relays).
xi) have facilities for offset features with adjustable 10-20% of Zone-3 setting.
xii) For correct measurement of earth faults necessary equipment for residual
compensation shall be included. It shall have residual compensation
variable from 30-150%.
xiii) operate instantaneously when circuit breaker is closed to zero-volt 3 phase
fault.
xiv) be suitable for three phase tripping.
xv) have a continuous current rating of two times of rated current. The voltage
circuit shall be capable of operation at 1.2 times rated voltage. The relay

19
shall also be capable of carrying a high short time current of 80 times rated
current without damage for a period of 1 sec.
xvi) have adequate contacts to meet the complete scheme requirements & if
required incorporate separate high speed self reset trip relays.
xvii) have suitable number of potential free contacts. Multiplication relays, if
required, shall be provided for Event Logger, Disturbance recorder & Data
acquisition system.
xviii) include power swing blocking protection which shall
a1) be of triple pole type
a2) have suitable setting range to encircle the distance protection described
above.
a3) have a continuously adjustable time delay on pick up of setting range 0-2
seconds.
a4) block tripping during power swing conditions.
a5) be of numerical type
xix) include fuse failure protection which shall
a1) monitor all the three fuses of PTs/CVTs and associated cable against
open circuit.
a2) inhibit trip circuits on operation and initiate annunciation.
a3) remain inoperative for system earth faults.
a4) be of numerical type.
xx) be suitable for 1 Amp. rated CT secondary, 110V (phase to phase ) VT
supply and 220 V DC supply. Mode of conversation of DC supply from 220
V DC to the voltage level required for their scheme may be mentioned in
detail. Requirement of CTs & VTs for the satisfactory working of the
scheme may also be indicated in the tender.
xxi) The Scheme shall have in-built features of broken conductor detection,
distance to fault locator, disturbance recorder and event logger. The scope
of the relay shall include necessary software and hardware to down load
the DR & EL data from relay to the PC installed in S/Stn. However, the
supply of PC is not covered under this clause.
D) THREE OVER CURRENT+ ONE EARTH FAULT PROTECTION:
The 3 O/C & 1 E/F elements shall be either independent or composite units. It
shall include VT fuse failure relays for alarm purposes.
DIRECTIONAL OVER CURRENT RELAY :
The relay shall
i) have IDMTL characteristic with a definite minimum time of 3.0 seconds at
10 times setting.
ii) have a variable setting range of 50-200% of 1 Amp.
iii) have a characteristic angle of 45 degree lead.
iv) include operatio indicator.
v) be suitable for 110V VT secondary.
DIRECTIONAL EARTH FAULT RELAY:
The relay shall
i) have IDMTL characteristic with a definite minimum time of 3.0 seconds at
10 times setting.
ii) have a variable setting range of 20-80% of 1 Amp.
iii) have a characteristic angle of 45 degree lag.
iv) include operation indicator.

20
v) be suitable for connection across open delta formed by 110/√3 volt rated
secondary of VT.
E) FEEDER OVER LOAD ALARM RELAY :
It is proposed to provide a single pole over current relay for the purpose of
monitoring the load flow on feeders to sound an alarm whenever load flow in the
line exceeds the setting for a given period of time to draw the operator's attention.
The relay shall have CONTINUOUS VARIABLE setting range of 50-200% of 1
Amp. and shall be supplemented by a continuously variable timer of 1 to 10
seconds.
Note:- The Feeder over Load Alarm Relay in built with numerical distance
protection relay is acceptable provided it meets the above specification.

5.16.3 PROTECTION SCHEME FOR BUS COUPLER:


NON DIRECTIONAL THREE OVER CURRENT+ ONE EARTH FAULT
PROTECTION WITH HIGH SET:
The 3 O/C & 1 E/F elements shall be either independent or composite units. The
relay shall be single pole inverse definite minimum time lag having definite min.
time of 3 secs. at 10 times settings. Over current relay with a setting range of
50%-200% of 1 Amp. supplemented with high set units having a setting range of
500% to 2000% of 1 Amp. shall be provided. Earth fault relay with a setting
range of 20%-80% of 1 Amp. supplemented with high set units having a setting
range of 200% to 800% of 1 Amp. shall be provided.
5.16.4 BUSBAR PROTECTION SCHEME :
One bus bar protection scheme shall be provided for each main bus for 220kV
having double bus arrangement. Bus bar protection scheme shall :-
i. be of numerical, low impedance type and modular in construction. The
scheme shall be complete in all respects to cater the need of at-least 14
feeders/ bays.
ii. have maximum operating time upto trip impulse to trip relay for all types of
faults of 15 milli seconds at 5 times setting value.
iii. operate selectively for each bus bar.
iv. give hundred percent security upto 40 kA fault level.
v. incorporate check feature.
vi. incorporate continuous supervision for CT secondaries against any possible
open circuit and if it occurs, shall tender the relevant zone of protection
inoperative and initiate an alarm.
vii. not give false operation during normal load flow in bus bars.
viii. incorporate clear zone indication.
ix. be of phase segregated, triple pole type and provide independent zones of
protection for each bus.
x. include necessary auxiliary relays for each circuit as required for the
scheme.
xi. shall be biased differential type and shall have operate and restraint
characteristics.
xii. be transient free in operation.
xiii include continuous DC supply supervision for alarm and trip circuits
separately and provide separately non-trip alarm for B/B protection alarm
circuit DC fail & B/B protection trip circuit DC fail conditions.
xiv. shall include necessary multitap auxiliary CTs for each bay.

21
xv. include protection 'in/out' switch for each zone.
xvi. include necessary CT switching relays. Also provide indication to monitor
`Operate' status of the CT switching relays with a common push button and
shall have CT selection incomplete alarm with adequate time delay when
proper CT switching has not taken place.
xvii. bus bar protection scheme should cover the blind zone on account of single
CT on B/C circuit.
xviii. Include high speed tripping relays for each bay..
xix. The Scheme shall have in-built features of disturbance recorder and event
logger. The scope of the relay shall include necessary software and
hardware to down load the DR & EL data from relay to the PC installed in
S/Stn. However, the supply of PC is not covered under this clause..

5.16.5 LOCAL BREAKER BACK UP PROTECTION SCHEME:


The relay shall be provided to take care of stuck breaker conditions. The local
breaker back up protection scheme will under such conditions, immediately after
the operation of primary / back up protection, transmit the tripping impulse to all
the circuit breakers connected to that bus zone of which the circuit breaker forms
part. The scheme shall be supplemented with a timer suitable for station DC
supply and continuously adjustable setting of .05 to .5 sec. on pick up.
The relay shall :
i) be triple pole type with a setting range of 20% -80% of rated current.
ii) have operating time of not more than 15 m-sec.
iii) have a resetting time of not more than 15 m-sec.
iv) be of numerical type.
v) have a continuous thermal with stand of two times rated current
irrespective of setting.
Note:- The LBB protection scheme in built with numerical busbar protection
scheme is acceptable provided it meets the above specification.

5.16.6 PROTECTION SCHEME FOR CAPACITOR C&R PANELS:


A) NON DIRECTIONAL THREE OVER CURRENT+ ONE EARTH FAULT
PROTECTION WITH HIGH SET:
The 3 O/C & 1 E/F elements shall be either independent or composite units. The
relay shall be single pole inverse definite minimum time lag having definite min.
time of 3 secs. at 10 times settings. Over current relay with a setting range of
50%-200% of 1 Amp. supplemented with high set units having a setting range of
500% to 2000% of 1 Amp. shall be provided. Earth fault relay with a setting
range of 20%-80% of 1 Amp. supplemented with high set units having a setting
range of 200% to 800% of 1 Amp. shall be provided.
B) TIME DELAY RELAY:-
A time delay relay must be included with adjustable setting range of 0-5 minutes
to provide a time lag before which the bank shall not be again switched on (to
avoid closing of the circuit breaker on a trapped charge).
C) UNDER VOLTAGE PROTECTION :-
One inverse time under voltage relay having setting range of 50% to 90% of
110/√3 volt (Phase-to-neutral) shall be provided to disconnect the capacitor bank
under low voltage conditions.

22
D) OVER VOLTAGE PROTECTION :-
One inverse time over voltage relay suitable for operation with 110/√3 volt AC
supply (Phase to neutral) with setting range of 100% to 130% shall be provided.
E) UNBALANCE PROTECTION :-
The unbalance protection shall be provided through current unbalance relay
connected to the NCT in neutral of capacitor bank connected in double star. Two
such relays, one each for alarm & trip are required. The setting of the relay shall
be 10% to 40% of the CT secondary (i.e. 1A for 66 kV voltage levels) followed by
a time delay through a timer of 0.1 sec. for transient free operation of the
protection.
The relay should not operate for healthy state spill current in neutral. Number of
units of failure on which alarm shall come and tripping is initiated, be clearly
mentioned for proper setting of the relays.

5.16.7 TRIPPING RELAY:


High speed tripping relay shall
i) be instantaneous ( operating time not to exceed 10 milli-seconds.)
ii) reset within 20 milli-seconds.
iii) Be 220 Volt DC operated.
iv) Have adequate contacts to meet the scheme requirement
v) Be provided with operation indicators for each element/coil.

5.17 SYNCHRONISING PANEL:


5.17.1 The synchronising instruments shall be mounted on a swing type synchronising
panel and shall be hinged at one end of 220 kV Duplex board. The synchronising
panel shall have suitable dimensions to avoid congestion of wiring and
equipments mounted there. The panel shall be equipped with the following
equipments:
-1 No.selector switch for synchronising with check-off-without check.
-2 No. voltmeters.
-2 No. frequency meters
-1 No. synchroscopoe
-1 No. synchroscope cut off switch
-2 No. lamps for bright lamp synchronisation
-1 No. Green lamp for synchronising in limit indication
-1 No. reversing voltage transformer for bright lamp synchronisation
-1 No. lamp for synchronisation by pass.
5.17.2 Suitable auxiliary voltage transformers wherever necessary shall also be provided
for synchronising condition.
5.17.3 Synchronising check relay with necessary auxiliary equipments shall be provided
which shall permit breakers to close after checking the requirements of
synchronising of incoming and running supply. The phase angle setting shall not
exceed 35 degree and have voltage difference setting not exceeding 10%. This
relay shall have a response time of less than 200 milliseconds when the two
system conditions are met within preset limits and with the timer disconnected.
The relay shall have a continuously adjustable time setting range of 0.5-3 secs.
A guard relay shall be provided to prevent the closing attempt by means of
synchronising check relay when control switch is kept in closed position long
before the two systems are in synchronism

23
5.18. RELAY SETTINGS :
The successful bidder will be responsible for calculating the relay setting of the
protection schemes included in the bid and obtain HVPN's M&P wing clearance
before their adoption. Any data\ information in regard to the power system
required by the supplier for this purpose shall be supplied by HVPN.
5.19 TIME SYNCHRONISATION EQUIPMENT
i) The Time synchronisation equipment shall receive the co-ordinated
Universal Time (UTC) transmitted through Geo Positioning Satellite System
(GPS) and synchronise equipments to the Indian Standard Time in a substation.
ii) Time synchronisation equipment shall include antenna, all special cables and
processing equipment etc.
iii) It shall be compatible for synchronisation of Event Loggers, Disturbance
recorders and SCADA at a substation through individual port or through Ethernet
realised through optic fibre bus.
iv) The synchronisation equipment shall have 2 micro second accuracy. Equipment
shall give real time corresponding to IST (taking into consideration all factors like
voltage, & temperature variations, propagation & processing delays etc).
v) Equipment shall meet the requirement of IEC 60255 for storage & operation.
vi) The system shall be able to track the satellites to ensure no interruption of
synchronisation signal.
vii) The output signal from each port shall be programmable at site for either one
hour, half hour, minute or second pulse, as per requirement.
viii) The equipment offered shall have six (6) output ports. Various combinations of
output ports shall be selected by the customer, during detailed engineering, from
the following :
· Voltage signal : Normally 0-5V with 50 milli Seconds minimum pulse duration. In
case any other voltage signal required, it shall be decided during detailed
engineering.
· Potential free contact (Minimum pulse duration of 50 milli Seconds.)
· IRIG-B
· RS232C
ix) The equipment shall have a periodic time correction facility of one second
periodicity.
x) Time synchronisation equipment shall be suitable to operate from 220V DC DC
as available at Substation.
xi) Equipment shall have real time digital display in hour, minute, second (24 hour
mode) & have a separate time display unit to be mounted on the top of control
panels having display size of approx. 100 mm height.
5.20. SMALL WIRING :
a) All wiring shall be of switch board type consisting of stranded /single
annealed copper conductor insulated with polyvinyl chloride insulation
suitable for 650 volts service and in accordance with IS : 694.
b) The wiring of the following circuits shall not be less than the size specified
below:
CTs, PTs & CVTs circuits : 2.5 mm2
Control, alarm & supervision circuits etc. : 1.5 mm2

24
c) All wires will be continuous from one terminal to the other and also will have
no tee - junction enroute. The connections shall be securely made with the
help of connecting lugs to ensure non-oxidation of the bare copper
conductor. At the terminal connections, washers shall be interposed
between stud type terminals and holding nuts. All holding nuts shall be
secured by locking nuts. The connection studs shall project at least 6 mm
from the lock nut surface.
d) Bus wires shall be fully insulated and run separately. Fuses and links
shall be provided to enable all the circuits in a panel to be isolated from the
bus wire. Wherever practicable, all circuits in which the voltage exceeds
125 volts shall be kept physically separated from the remaining wiring. The
function of each circuit shall be marked on the associated terminal boards.
e) All wiring diagrams for the control and relay boards shall be drawn as
viewed from the back of the cubicle and shall be in accordance with IS:375
or equivalent IEC. Multi core cable tails shall be so bound to its cable that
each wire may be traced without difficulty.
f) All potential bus wiring, non-trip and trip alarm bus wiring, AC & DC control
supply, panel lighting bus wires and such other wiring which runs from
panel to panel within a C&R panel board shall be laid out in gutters and
shall be suitably screened. In case of `simplex' type C&R boards these
common wires will run through bus wire holes.

5.21. TERMINAL BOARDS, TEST BLOCKS & SPARE CONTACTS :


a) Terminal block connectors built from cells of moulded dielectric and brass
stud inserts shall be provided for terminating the outgoing ends of the
panel wiring and the corresponding tail ends of control cables. Insulating
barriers shall be provided between adjacent connections. The height of the
barriers and the spacing between terminals shall be such as to give
adequate protection while allowing easy access to terminals. Provision shall
be made on each pillar for holding 10% extra connectors.
b) The terminal blocks shall be suitable for 650 Volts service and for
connection with both copper and aluminum wires.
c) Terminal boards shall be mounted in such a manner as to afford easy
access to terminations and to enable ferrule numbers to be read without
difficulty. Wire ends shall be so connected at the terminals that no wire
terminal gets marked due to succeeding connections. Terminal board rows
shall be adequately spaced and shall not be less than 100 mm apart so as
to permit convenient access to wires and terminations. Labels in the form
of engraved plastic plates shall be provided on the fixed portion of terminal
boards. No live metal parts shall be exposed at the back of terminal boards.
d) Switch board type back connected test block with contacts shall be provided
with links or other devices for shorting terminals of CT leads before
interrupting the normal circuit for injection from an external source or for
inserting testing instruments in the circuit without causing open circuit of the
CT. The potential testing studs shall preferably be housed in narrow
recesses of the block, wherever required, shall be placed as close to the
equipments as possible. Test blocks shall be of flush mounting pattern and
the number of test blocks being provided on each control and relay panel
shall be stated in the tender.

25
e) The purpose of all the relays (including the auxiliary relays) switches, lamps
& push buttons etc. is required to be indicated just below the respective
equipment through engraving or painting.
f) Spare contacts of relays are required to be brought on T.B's and shall be
indicated on the drawings.

5.22. BUS WIRES :


The VT, DC, AC, trip alarm , non-trip alarm & DC fail etc. inter panel bus wire
terminals shall be brought on Bus T.B's as well as on T.B's so that any panel
specified herein can be used separately at the Substation specified in this
specification. The said bus wires for the panels specified in case of existing
substations shall be matched with the bus wires of the C&R panels already
available at site, the drawing for matching purposes for which shall be supplied to
the successful bidder. The bus wire terminals shall be indicated on the panel
schematic drawings as well. The bus wire diagram shall also be supplied
alongwith the schematic drawings for each panel.

5.23. FERRULES :
Wire No. shall be indicated on panel schematic and wiring diagrams and
accordingly engraved ferrules with the same numbers and letters as indicated in
the said diagrams shall be provided on the terminal ends of all wires for easy
identification of circuits for inspection and maintenance. Ferrules shall be of strong
& flexible insulating material with glossy finish to prevent adhesion. These shall be
engraved and marked clearly and shall not be effected by dampness. Ferrule
numbering shall be in accordance with IS:375. The same ferrule number shall not
be used on wires in different circuits on a panel. At those points of interconnection
between the wiring carried for equipments of different suppliers where a change of
number cannot be avoided double ferrules shall be provided on each wire with the
appropriate connection diagram of the equipment.

5.24. SPACE HEATERS :


Tubular space heaters suitable for connection to the single phase 220 Volts AC
supply complete with switches located at convenient positions shall be provided at
the bottom of each control and relay panel to prevent condensation of moisture.
The watt loss per unit surface of heater shall be low enough to keep surface
temperature well below visible heat.

5.25. ILLUMINATION :
The C&R panel shall be provided with 220/240 Volts AC interior lighting. The
lamp shall be free from hand shadows. A door operated button switch shall be
provided in each simplex panel. Each simplex panel shall be provided with one
no. illumination lamp with door switch.

5.26 POWER SOCKET :


Single phase 240 volt AC, 5/15A power socket with power on/off switch shall be
provided in each simplex panel.

5.27 SAFETY EARTHING :


Earthing of current free metallic parts or metallic bodies of the equipment mounted
on the switch boards shall be done with bare copper conductor. Copper bus of

26
size 25 mm x 6 mm extending through entire length of a control and relay board
shall be provided. The earthing conductor shall be connected by Rose Courtney
terminals and clamp junctions.
The neutral point of star connected secondary windings of instrument transformers
and one corner of the open delta connected LV side of potential transformer, if
used shall be similarly earthed with the main earth bar of the switch board earthing
system. Multiple earthing of any instrument transformer shall be avoided.
An electrostatic discharge point shall be provided in each panel connected to
earth bus via 1 Mega Ohm resistor.

5.28. NAME PLATE :


An easily accessible engraved or painted panel name plate shall be provided
inside each panel. It must include G.A. drawing No., purchase order No., Bidder's
reference No., name of s/stn. as per purchase order and name of circuit. In
addition to this, an engraved plate indicating the purchase order no. alongwith
name of s/stn. is required to be affixed on the panel at appropriate height so that it
is readable while standing in front of the panel. These are required to be indicated
on the G.A. drawings also.
An engraved label indicating the purpose of all the relays & switches shall also be
provided.

5.29 PANEL DETAILS:


The mountings on various 220 kV & 66kV C&R panels against various
Substations specified herein shall be as under. The bidders shall give the details
of the various panel mountings in the same serial as specified herein as under for
the convenience of checking of the same w.r.t. the provision in the specification.
Any trip relay, auxiliary relay, timers, contact multiplication relay, ICT, IVT & test
block etc. required for the completeness of the scheme shall be added by the
Bidder as per scheme requirements and no cost addition on these accounts shall
be considered at a later date.
The following is the general criteria for the selection of the equipments to be
provided in each type of panel.

5.29.1 MOUNTING DETAILS:

(A) 220 kV C&R PANEL BOARD COMPRISING OF THE FOLLOWING:

(i) 220 kV Transformer C&R Panels for 100 MVA, 220/66 kV Transformers.
Each of these panels will be equipped with the followings:-
Control panel:
1. Black PVC circuit label. 1
2. Mimic diagram section. 1
3. Indication lamps for CB open, close, spring charge and auto 4
trip indications.
4. Semaphore indicators for isolator & Earth Switch position indication. 5
5. Semaphore indicator for CB position indication. 1
6. Ammeter suitably scaled. 1
7. Ammeter selector switch. 1
8. Spring return to neutral CB control switch with sequence 1
device, lost motion device and 2 pairs of bell alarm contacts.

27
9. Spring return to neutral isolator & Earth Switch control switches. 4
10. 24 ways static facia annunciator complete with accept, 1
reset and lamps test push buttons.
11. Trip circuit supervision relays. 6
12. AC/DC changeover relay. 1
13. Set of Trip Ckt. DC supply supervision scheme including one No. 1
push button each for DC fail test and DC fail accept and one
No. indicating lamp (amber) for DC fail visual indication.
To be mounted inside :-
1. Set of illumination lamps with on/off switches. 1
2. Space heater with switch. 1
3. Power socket with on/off switch. 1
4. Set of corridor illumination lamps with door switches at both ends
of the corridor. 1

Relay Panel :-
1. Black PVC circuit label. 1
2. Transformer differential relay. 1
3. REF relay. 1
4. Single pole non-directional over current relay 3
with highset.
5. Transformer over load alarm relay. 1
6. Over fluxing relay. 1
7. High speed tripping relay. 1
8. Aux. relay for Transformer buch., OLTC oil temp., winding 8
temp., oil temp., pressure relief, surge relay trip
functions and 2 nos. spare.
9. Voltage selection relay 1
10. Set of relays for local breaker back up protection. 1
11. High speed tripping relay for bus bar protection. 1
To be mounted Inside :-
1. Set of illumination lamps with on/off switches. 1
2. Space heater with switch. 1
3. Power socket with on/off switch. 1

(ii) 220 kV Feeder C&R Panels for 220kV Lines

Each of these panels shall be equipped with the followings :

Control panel:
1. Black PVC circuit label 1
2. Mimic diagram section. 1
3. Indicating lamps for CB open, close, spring charge 4
and auto trip indications.
4. Indication lamp for carrier healthy indication. 2
5. Semaphore indicators for isolators position indication. 3
6. Semaphore indicator for earth switch position indication. 4
7. Semaphore indicator for CB position indication. 1
8. Ammeter suitably scaled. 1
9. Ammeter selector switch. 1

28
10. Voltmeter suitably scaled. 1
11. Voltmeter selector switch. 1
12. 3 phase, 3 wire, 2 element, dynamometer MW meter 1
suitably scaled.
13. 3 phase, 3 wire, 2 element, dynamometer MVAR meter 1
suitably scaled.
14. 3 phase, 4 wire, 3 element static kWh meter, one for import 2
and one for export energy measurement.
15. 3 phase, 4 wire test terminal block for the above. 1
16. Spring return to neutral CB control switch with sequence 1
device, lost motion device and 2 pairs of bell alarm contacts.
17. Spring return to neutral isolator & Earth Switch control switches. 6
18. Carrier in/out switches. 2
19. Synchronizing switch. 1
20. Push button for dead bus closing. 1
21. 24 way static facia annunciator complete with accept, 1
reset and lamps test push buttons.
22. Trip circuit supervision relays. 6
23. AC/DC changeover relay. 1
24. Set of Trip Ckt. DC supply supervision scheme including one No. 1
push button each for DC fail test and DC fail accept and one
No. indicating lamp (amber) for DC fail visual indication.
To be mounted inside :-
1. Set of cubicle illumination lamps with on/off switches. 1
2. Space heater with switch. 1
3. Power socket with on/off switch. 1
4. Set of corridor illumination lamps with door
switches at both ends of the corridor 1

Relay Panel:
1. Black PVC circuit label. 1
2. Numerical Distance scheme, non-switched with carrier 1
inter-tripping/carrier blocking (selectable at site),
out of step blocking, single & three phase tripping
as Main-I protection including SOTF, VT fuse failure
protection, test blocks, aux. relays & tripping relays.
3. Numerical Distance scheme, non-switched with carrier 1
inter-tripping, out of step blocking, single & 3 phase
tripping as Main-II protection including SOTF, VT fuse
failure protection, test blocks, aux. relays & tripping relays.
4. Single and three-phase auto reclosing scheme including 1
aux. relays & tripping relays.
5. Auto reclose selector switch. 1
6. Check synchronizing & dead line charging relay. 1
7. Set of voltage selection relay 1
8. Carrier receive aux. relays. 2
9. Carrier healthy aux. relays. 2
10. Aux. relay to pole discrepancy. 1
11. Over load alarm relay. 1
12. LBB protection scheme. 1

29
13. High speed trip relay for bus bar protection 1
14. Single pole directional over current relay. 2
15. Single pole directional earth fault relay. 1
To be mounted inside :-
1. Set of cubicle illumination lamps with on/off switches. 1
2. Space heater with switch. 1
3. Power socket with on/off switch. 1
NOTE:- The protection scheme and metering shall be fed from bus PTs.

iii) 220 KV BUS COUPLER CUM BUS-BAR PROTECTION C&R PANEL.


The panel shall be equipped with the following:
Control panel:

1. Black PVC circuit label. 1


2. Mimic diagram section 1
3. Indicating lamps for CB open , close, spring charge and auto trip 4
indications
4. Semaphore indicators for isolator & Earth Switch position 6
iindication and for Bus Earth Switch
5. Semaphore indicator for breaker position indication 1
6. Ammeter suitably scaled 1
7. Ammeter selector switch 1
8. Voltmeter suitably scaled 2
9. Voltmeter selector switch 2
10. Frequency meters 2
11. Spring return to neutral CB Control Switch with sequence device, 1
lost motion device and 2 pairs of bell alarm contacts
12. Spring return to neutral isolator & Earth Switch control switch 4
13. Synchronising selector switch along with push button for dead 1
Bus closing.
14. 24 ways static facia annunciator complete with accept, reset and 1
lamps test push buttons.
15. Trip circuit supervision relays 6
16. AC/ DC changeover relay 1
17. Set of Trip Ckt. DC supply supervision scheme including one No. 1
push button each for DC fail test and DC fail accept and one No.
indicating
lamp (amber) for DC fail visual indication

30
18. Digital frequency meter 1
19. Digital volt meter 1
20. Bus 1/2 voltage selector switch for above two items 1
To be mounted inside
1. Set of cubicle illumination lamps with on/off switches 1
2. Space heater with switch 1
3. Power socket with on/off switch 1
4. AC buzzer for DC fail alarm 1
5. DC bell for trip alarm 1
6. DC hooter for non trip alarm 1
7. Set of corridor illumination lamps with door switches at both 1
ends of the corridor.
Relay Panel:
1. Black PVC circuit label 1
2. Triple pole combined 2 O/C & 1 E/F relay 1
3. Set of high speed trip relay 1
4. LBB protection scheme 1
5. High speed trip relay for bus bar protection 1
6. Bus bar protection scheme as per the detail given at para 1
5.16.4

To be mounted inside:
1. Set of cubicle illumination lamps with on/ off switches 1
2. Space heater with switch 1
3. Power socket with on/ off switches 1

iv) SYNCHRONISING PANEL:

The swing door type synchronising panel shall be equipped as detailed at para
5.17 above.

31
(B) 66 kV C&R panel Board Comprising of the following:-

(i) 66 kV Transformer (incoming) C&R panels for 100 MVA, 220/66 kV


Transformers.
Each of these panels shall be equipped with the followings :-

On the front:
1. Black PVC circuit label. 1
2. Mimic diagram. 1
3. Indication lamps for CB open, close & auto trip indications. 3
4. Spring charge indication lamp. 1
5. Semaphore indicators for isolator position indication. 2
6. Semaphore indicator for CB position indication. 1
7. Voltmeter (to be fed from CVT for AVR) 1
8. Ammeter suitably scaled. 1
9. Ammeter selector switch. 1
10. Spring return to neutral CB control switch with sequence 1
device, lost motion device & two pairs of bell alarm contracts.
11. 10 Way static alarm facia complete including accept, reset & 1
lamp test push buttons.
12. Trip circuit supervision relays. 2
13. Triple pole non directional combined 2 over current and 1
1earth fault relay.
14. High speed trip relay. 1
15. AC/DC change over relay. 1
16. REF relay . 1
17. Set of Trip Ckt. DC supply supervision scheme including one No. 1
push button each for DC fail test and DC fail accept and one
No. indicating lamp (amber) for DC fail visual indication.

To be mounted inside :-
1. Illumination lamp with door switch. 1
2. Space heater with switch. 1
3. Power socket with on/off switch. 1

6.0 TESTS:
6.1 TYPE TESTS:
The equipment should be offered type test. Test reports should not more then
seven years old reckoned from date of bid opening in respect of all the tests
carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic
body or witnessed by HVPN or another electric power utility and be submitted by
the successful bidder to HVPNL for approval as schedule given in Bar Chart.
a) Insulation tests as per IEC 60255-5
b) High frequency disturbance test as per IEC 60255-4 (Appendix -E) -Class III
(not applicable for electromechanical relays)
c) Fast transient test as per IEC 1000-4, Level III(not applicable for
electromechanical relays)
d) Relay characteristics, performance and accuracy test as per IEC 60255.
e) Tests for thermal and mechanical requirements as per IEC 60255-6
f) Tests for rated burden as per IEC 60255-6

32
g) Contact performance test as per IEC 60255-0-20
h) Conformance tests as per IEC 61850

6.2 ROUTINE TESTS:


As per quality assurance program (QAP).

6.3 ACCEPTANCE TESTS:


Following tests shall be carried out at the manufacturer’s works after complete
assembly in presence of HVPNL representative, unless dispensed with in writing
by the HVPNL:-
i) Checking wiring of circuits and their continuity.
ii) One minute high voltage test.
iii) Insulation resistance of complete wiring, circuit by circuit with all equipment
mounted on panel.
iv) Checking the operation of protection schemes.

7.0 DOCUMENTATION:
7.1 The successful bidder shall submit four sets of G.A. and schematic drawings for
HVPNL’s approval incorporating following details also.
a) Schematic drawings of breakers are to be incorporated in the panel schematic
drawings.
b) Trip details of transformer are to be incorporated in the panel schematic drawings.
After receipt of HVPNL’s approval, the bidder shall submit final drawings for each
circuit of the following drawings:-
i) Boardwise arrangement drawing (applicable for the panel board at a
Substation having more than one panel).
ii) G.A.drawing alongwith G.A. legend and foundation details.
iii) Schematic drawings alongwith legend & internal wiring details of main
relays like transformer differential relay, REF relay, local breaker back up
schemes, distance protection scheme, bus-bar protection scheme, voltage
selection scheme etc.
iv) Equipment-wise & wire-wise wiring diagrams.
Each set of drawings shall be bound separately.
7.2 The bidder shall furnish specified no. of nicely printed and bound volumes of the
instruction manuals in English language of the equipment. The instruction manual
shall contain step by step instructions for all operational & maintenance
requirements for all the protective and aux. relays, switches, instruments etc.
mounted on the panel and shall include the following aspects.
i) Storage for prolonged duration.
ii) Unpacking.
iii) Erection.
iv) Handling at site.
v) Pre commissioning tests.
vi) Operating procedures.
vii) Maintenance procedure.
viii) Precautions to be taken during operation & maintenance work.
ix) Catalogue numbers of all the components liable to be replaced during the
life of the panels.
x) Internal wiring diagrams of all the relays.

33
Each set of instruction manuals shall be bound separately.
NOTE:- One master set for all the substations shall be supplied with in a week of
placement of order to the Design Directorate to facilitate the checking
and approval of drawings.

34
ANNEXURE-A

TRANSMISSION LINE DATA (TENTATIVE)

--------------------------------------------------------------------------------------------------------------------------
Sr. Name of Circuit O.H. Line U.G. Cable
No. Line Conductor size Cable Size in
length Sq. inch ACSR length Sq. mm
In km(approx) copper equivalent in km(approx.) (Al.)
--------------------------------------------------------------------------------------------------------------------------

--------------------------------------------------------------------------------------------------------------------------

35
ANNEXURE-B

LINE PARAMETERS (per UNIT)/100 MVA BASE/100 km

WITH CONDUCTOR SIZE & POWER CAPACITY

Voltag No. Conduct Resistan Reactan Susceptan Resistan Reactan Line


e of or size ce ce ce ce ce Capacit
(kV) Ckt (inch2) R X Y R0 X0 y
. Ω Ω Ω Ω Ω (MW)

220 D/ 0.40 0.0088 0.0443 0.2700 0.05109 0.21666 300


C

220 S/C 0.40 0.0176 0.0886 0.1350 0.05951 0.26180 150

66 D/ 0.15 0.2347 0.4637 0.0272 0.71210 2.70857 50


C

66 S/C 0.15 0.4695 0.9275 0.0136 0.93744 3.20761 25

Remarks:

1. Size of Earth wire for:-

220 kV = 7/3.15 mm

66 kV = 7/2..5 mm

2. Resistance of conductor at 200 C.

3. Resistivity of Earth Assumed= 100

36
ANNEXURE-C

DETAILS OF CARRIER EQUIPMENT

The carrier terminals available in carrier equipment for feeders are as under:-

CARRIER BOOST

CARRIER SEND
(MAIN-I) + VE

CARRIER SEND + VE
(MAIN-II)
- VE

DIRECT TRIP
(SEND) + VE
- VE

CARRIER HEALTHY
(MAIN-I)

CARRIER HEALTHY
(MAIN-II)

CARRIER SIGNAL
RECEIVE
(MAIN-I)

CARRIER SIGNAL
RECEIVE
(MAIN-II)

DIRECT TRIP
(RECEIVE)

37
SECTION-6
CHAPTER-1
PART-I

TECHNICAL SPECIFICATION FOR 220 KV (CROSS LINKED POLYETHYLENE INSULATED


POWER CABLE:

1.1 SCOPE

1.1.1 The scope under this section covers design, manufacuture, testing, packing, supply,
delivery and laying of 220 KV, XLPE, insulated power cable for use with effectively earthed
distribution systems.
1.2 STANDARDS:Unless otherwise specified, the cables shall conform, in all respects, to
IEC-502/1983/IEC-840/1988 and IS:7098 (Part-III)/1993 with latest amendment or latest
edition for cross linked polyethylene insulated PVC sheathed cable for working voltage of
220 KV.
1.3 CLIMATIC CONDITIONS: The climatic conditions under which the cable shall operate
satisfactorily are as follows:-
a) Location : IN THE STATE OF HARYANA
0
b) Maximum ambient temperature of air in shade C : 50
0
c) Minimum ambient temperature of air in shade C : -2.5
0
d) Maximum daily average ambient temperature C : 40
0
e) Maximum yearly average ambient temperature C : 30

f) Maximum relative humidity % : 100

g) Minimum relative humidity % : 26

h) Average number of thunder storm days per annum : 35

i) Average annual rain fall mm : 900

j) Max. wind pressure kg/m2 : 195

k) Altitudes not exceeding above MSL Meter : 1000


0
l) Max. soil temp. at cable depth C : 30

m) Isoceranic level days/year : 50

n) Seismic level (horizontal acceleration) : 0.3g

-1-
1.4 PRINCIPAL PARAMETERS:
1.4.1 220 KV (E) grade XLPE single core power cable of single length, with H.D. aluminium
conductor, shielded with extruded semi-conducting layer, insulated with dry gas cured
cross linked polyethylene (XLPE) insulation, insulation screened with extruded semi-
conducting layer, insulated core copper-wire, screened lapped with a combination of semi-
conducting water swell able and poly aluminium laminated followed by black extruded PE
(Poly-thylene) inner sheath. Single H.D. aluminium wire armoured and graphite coating
PVC outer sheathed overall cable, confirming to IEC-502 (1983) for construction and also
confirming to IS:7098 (Part-III)/1993 or any latest amendments thereof.

1.4.2 Outer sheathing should be designed to afford high degree of mechanical protection and
should also be heat, oil chemicals and weather resistant. Common acid. Alkalis and saline
solution should not have adverse effect on the PVC sheathing material used.

1.4.3 The cable should be suitable for laying in covered trenches and/or under ground for
outdoor.

1.4.4 CABLE PARAMETERS 220 KV


i) Voltage Grade (Uo/U) 127/220
ii) No. of cores Single
iii) Size (mm2) 400mm2,630mm2,800mm2,1000mm2
iv) Nominal system voltage KV 220
v) Highest system voltage KV 245
vi) System Frequency Hz 50
vii) Variation in Frequency + 3%
viii) Fault level individually for
i) Conductor 40KA for1sec
ii) Cu.Screen 31.5KA for 1sec
iii) Armour 31.5KA for 1sec
ix) Maximum allowable temperature
0
a) Design continuous operation at rated C 90
full load current, the max, temp. of
0
conductor shall not exceed. C 250
b) The conductor temperature after a
short circuit for 1.0 sec shall not
exceed.
x) Basic insulation level 1050 KVP
(1.2/50 Micro Second Wave)

xi) 1-min. power frequency withstand voltage (rms) 460 KV

xii) System earthing Effectively earthed

1.5 GENERAL TECHNICAL REQUIREMENTS:

1.5.1 CONDUCTOR: The cable conductor shall be made from stranded H.D.aluminium to form
compact circular shaped conductor having resistance within limits specified in
IS:8130/1984 and any amendment thereof. The conductor shall confirm to IEC:228 and
the shape shall be compacted circular shaped.

-2-
1.5.2 CONDUCOTR SHIELD: The conductor having a semi-conducting screen shall ensure
perfectly smooth profile and avoid stress concentration. The conductor screen shall be
extruded in the same operation as the insulation; the semi-conducting polymer shall be
croos-linked.

1.5.3 INSULATION: The XLPE insulation should be suitable for specified 220 kV system
voltage. The manufacturing process shall ensure that insulations shall be free from voids.
The insulation shall withstand mechanical and thermal stressed under steady state and
transient operating conditions. The extrusion method should give very smooth interface
between semi-conducting screen and insulation. The insulation of the cable shall be of
high standard quality, generally confirming to IEC-502 and I.S. 7098 Part-II/1988 (latest
edition).

1.5.4 INSULATION SHIELD: To confine electrical field to the insulation, non-magnetic semi-
conducting shield shall be put over the insulation. The insulation shield shall be extruded
in the same operation as the conductor shield and the insulation by suitable extrusion
process. The XLPE insulation shield should be bonded type. Metallic screening shall be
provided. The metallic screen shall be of copper wire having fault current capacity same
as the conductor (40 KV for 1-sec).

1.5.5 INNER SHEATH: The inner sheath shall comprises of a combination of semi-conducting
water swell able and ploy aluminium laminated tape. The sheath shall be suitable to
withstand the site conditions and the desired temperature. It should be of adequate
thickness, consistent quality and free from all defects. The sheath shall be extruded and of
black P.E. (Poly-ethylene).

1.5.6 ARMOUR: Single H.D. Aluminium wire armouring shall be provided. The dimension of
H.D.Aluminium wire armouring shall be as per latest IS:3975/19988. The armour shall be
having fault current same as capacity conductor (40 KV for 1 sec.)

1.5.7 OUTER SHEATH: Suitable semi conducting layer coated on extruded PVC outer sheath
confirming to IEC: 502/1983, shall be applied over armouring with suitable additives to
prevent attach by rodents and termites.

1.5.8 CONSTRUCTION:
1.5.8.1 All materials used in the manufacture of cable shall be new unused and of finest quality.
All materials should comply with the applicable provision of the tests of the specification.
IS, IEC, Indian Electricity Rules, Indian Electricity Act and any other applicable statutory
provisions rules and regulations.

1.5.9 CURRENT RATING: The cable will have current ratings and derating factors as per
relevant standard IEC.

1.5.9.1 The one-second short circuit rating values each for conductor, screen & armour shall be
furnished and shall be subject to the purchaser’s approval.

1.5.9.2 The current ratings shall be based on maximum conductor temperature of 90 deg. C with
ambient site condition specified for continuous operation at the rated current.

-3-
1.5.9.3 SIZE:
The different sizes of cable shall be 220 KV Single Core
a) 400mm2
b) 630mm2
c) 800mm2
d) 1000mm2

1.5.10 OPERATION:
1.5.10.1Cables shall be capable of satisfactory operation under a power supply system frequency
variation of plus minus 3% voltage variation of plus, minus 10% and combined frequency
voltage variation of 10% (absolute sum).

1.5.10.2 Cable shall be suitable for laying in ducts or buried under ground.

1.5.10.3 Cable shall have heat and moisture resistance properties. These shall be of type
and design with proven record on transmission network service.

1.5.11 LENGHTS: The cable shall be supplied in standard drum lengths as below:

Size of cable Standard Drum Length

a) 66 1c x 400mm2, 630mm2,800mm2, 500 meters + 5% tolerance and


1000mm2 + 2% overall tolerance in total quantity of cable.

1.5.11 INDENTIFICATION MARKING: Identification of cables shall be provided externally at


three meters’ intervals to identify as under:-

i) ‘Name of Manufacture’
ii) ‘Year of manufacture’
iii) ‘Voltage grade’ to be printed/embossed at the interval ofone meter-length. The
identification, by printing or embossing shall be done only on the outer sheath.
Name of purchaser shall also be embossed.
1.6.0 TESTS:
1.6.1 TYPE TESTS
The XLPE Cable offered should be type tested. Test reports should not be more
than seven years old reckoned from date of bid opening in respect of the following
tests carried out in accredited laboratories (based on ISO/IEC) by a reputed
accreditatic body or witnessed by HVPN or another electric power utility and be
submitted by the successful bidder to HVPNL for approval as per schedule given in
Bar Chart:-
i) Physical tests for insulation and outer sheath.
ii) Bending test.
iii) Di-electrical power factor test.
iv) Heating cycle test followed by di-electrical power factor as a function of voltage and
partial discharge test.
v) Impulse withstand test.

1.6.2 ROUTINE TESTS:


As per quality assurance program (QAP).

-4-
1.6.3 ACCEPTANCE TESTS:
All the acceptance tests as stipulated in the relevant standard shall be carried out
by the Supplier in presence of HVPNL representative, unless dispensed with in
writing by the HVPNL.

1.7 INSPECTION
The material shall be inspected and tested before dispatch by an authorised
representative of the Nigam in respect of quality.
The inspecting officer shall also satisfy himself about the correctness of length of cables
as provided in Instruction No. 208 of E.B. Manual of Instruction 1963 Edition amended
vide O/O No. G/BD-33(57) 75 dt. 18.04.75 now HVPNL. In case the supplier is not in a
position to get these tests carried out at his works, such tests may be got carried out by
him at any Govt. recognised test agency at his own expense.

1.8 TEST CERTIFICATES


The supplier shall supply test certificates from a Govt. agency in respect of quality as per
IS:7098(part-II) 1985 with latest amendments thereof for approval of the purchaser.

1.9 PACKING
The cable shall be supplied in non-returnable wooden drum as per IS:10418:1982 so
constructed, as to enable the cable to be transported on each drum. The cable wound on
such drum shall be one continuous length. The ends of cables shall be sealed by means
of non-hygroscopic sealing material.

1.10 MARKING
The marking on the drum shall have the following information: -

a) Reference to Indian Standard & cable code.


b) Name of the manufacturer & trade name.
c) Nominal cross section area of conductor for the cables.
d) Number of core.
e) Sequential No. at each meter.
f) Type of the cable & voltage for which it is suitable.
g) Length of cable on the drum.
h) Approximate gross weight.
i) Net weight of the cable.
j) Drum identification number.
k) P.O. No. and date.
l) Consignee’s name with designation.
m) Year of manufacture.

1.11 DRAWINGS & INSTRUCTION MANUAL


The tenderer shall supply the following drawings with the tender: -

i) Detailed drawing of the cable showing conductor, screening insulation, Armouring,


outer sheath etc.
ii) Detailed drawing showing jointing of cable and sealing of end boxes.

Copies of instruction manuals for testing, installation jointing operation and maintenance of
cables, shall also be submitted with the offer for reference of the purchaser.

1.12 TECHNICAL & GUARANTEED PARTICULARS: The tenderer shall furnish guaranteed
technical particulars as called for in appendix-I (Schedule-A) of this specification.

-5-
Particulars, which are subject to guarantee, shall be clearly marked. Offer not containing
this information will not be considered.

-6-
PART-II
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF 220 KV
XLPE UNDERGROUND POWER CABLE

SECTION-1
SPECIFICATION FOR LAYING OF CABLE

1.1 LAYING, JOINTING AND INSTALLATION (GENERAL):


1.1.1 It will be necessary for the successful tenderer to arrange technical supervision during
installation of cable laying and termination.

1.1.2 The successful tenderer shall arrange for the services of fully qualified and competent
supervising Engineer/Engineers and necessary minimum number of jointers, semi skilled
labourers, as he deems I absolutely necessary.

1.1.3 Provision of special tolls/appliances required for conductor joining and stripping/dressing
and applicable of XLPE insulation etc. shall be made by the successful tenderer.

1.1.4 The successful tenderer shall furnish all necessary information, including drawings,
manuals and instructions relating to both cable laying and jointing practice.

1.1.5 The associated civil works, which are necessary in laying/installation of power cable,
though not specifically mentioned, but shall be completely in the scope of successful
tenderer.

1.1.6 The route map showing the proposed installation of power cable will be issued to the
successful bidder. Cables are to be laid in single trench as per instruction of E.I.C.

1.1.7 Successful tenderer has to arrange at his own for first-aid, fire protection, electricity and
water requirement at site. He shall also arrange for signboard, caution board, safety and
security personnel etc. on cable route.

1.1.8 The successful tenderer has to bear with any temporary interruption that may occur during
actual erection work, when the matter with other agency is involved.

1.1.9 No idling charges or cost over run for the entire project shall be entertained.

1.1.10 Approval for installation of the underground cable route from Electrical Inspector shall be
arranged by Purchaser. However, permission for commencement of work and permission
for commissioning of cable after completion of laying has to be arranged by the successful
tenderer.

1.1.11 Successful tenderer shall arrange space for working office, workshop & store/yard for
storing requisite material like kits, cables etc.

1.1.12 The Arbitration in the dispute shall be strictly as per standard commercial terms &
conditions of the board.

-7-
1.2 LAYING OF POWER CABLE:
1.2.1 The 220 KV (E) XLPE cable shall be installed underground and normally buried directly in
the ground complying with all applicable standards and IS:1255 & their amendments.

1.2.2 The sealing of power cable ends during the storage; execution & completion of jointing
works shall be in the scope of successful tenderer. In no circumstances, the cable ends
shall be kept open. The amount due to damages done because of water/moisture ingress
OR penetration in the cable/conductors during execution shall be recovered from
successful tenderer. It shall be responsibility of successful tenderer to make them good
OR replace free of cost without affecting the completion schedules.

1.2.3 Three single core cables shall be laid in trefoil formation.

1.2.4 The power cable shall be laid generally at a depth of 2500mm and can vary, if obstacles
like power cable of other rating/telephone cable/water pipe line etc, come in the way of
installation. At least minimum Depth of 2000 mm shall be maintained from nearest road
level.

1.2.5 The cables shall be completely surrounded by a layer of having a low thermal resistivity
(selected sand) sand about 250mm over & below of the cable surface throughout width of
the cable trench at no extra cost. (River sand shall be allowed for surrounding layer).

1.2.6 The extra protection of pre-cost flat RCC slab with proportion 1:2:4 having size 600(L)
X300(B) X 50(Thk) mm shall be provided about 250mm over the power cables for
complete route of the cable.

The RCC slab shall be with proportion not less than 1:2:4 (M-150) and also shall have
steel reinforced of 6/8 mm dia. Steel bar (4 nos. of 300mm side and 5 Nos. on 600 mm
side ) at adequate required distance. The slab shall be given curing time of minimum 15
days.

1.2.7 Normally, the back filling shall consist of the materials earlier excavated, however, bigger
stones or piece of rock should be removed OR if required new soil has to be provided and
used for back filling with no extra cost.

1.2.8 The cable drum must be handled correctly and with care during transport and laying of the
power cables, in order to avoid damage to the cables. Any damages done because of poor
handing of the cables to the properties of corporation, private OR to anybody shall be
responsibility of successful bidder & the board reserves the right to recover the amount
due to such damages.

1.2.9 The minimum bending radius of the cable shall be 30xD where D is diameter of the cable.

-8-
1.2.10
The contractor has to keep allotted 220 KV power cable, material supplied by him in safe
custody and transport to the respective sites and will be fully responsible for any damage
to or loss of any or all allotted equipments or materials supplied by him at any stage during
transportation or erection or taking over to the sub station by the HVPNL. The contractor
has to return empty cable drum as instructed by CE. The route map for cable will be
issued free of cost to the contractor before commencement of work.

The contractor has to open site store at sub station site or at place nearby the sub station
site and ensure for safe custody of all the stored materials at his own cost.

The contractor shall have total responsibility for the entire materials stores, loose, semi
assembled and/or erected by him at site in his custody. The Contractor shall make suitable
security arrangements at his own cost to ensure the protection of all materials, equipment
and works from theft, fire pilferage and any other damages and loss. It shall be the
responsibility of the contractor to arrange for security till the works are finally taken over by
the HVPNL.

1.3 CROSSINGS:

1.3.1 a) where road crossing comes in way of laying power cable, the power shall be laid
through NP-4 RCC Hume Pipes. The required length of Hume pipe shall be arranged by
the successful tenderer at no extra cost.

b) The RCC Hume pipe inner dia-meter shall not be less than 1000mm.

c) The RCC pipes to be laid shall have minimum depth in such a way that the back filling
on top surface of the pipe shall be at least 600mm in depth. The pipe joints shall be
smooth so that cables are not damaged during pulling & operation.

d) During the crossing of utilities like water line, drainage lines, telephone lines, gas lines
etc. sufficient care shall be taken & protection shall be made available so that other utilities
do not damage the cable mechanically and/or electrically or do not effect the performance
of the cable.

e) NALA CROSSINGS/CULVERT CROSSINGS: The Nala crossings are to be made with


separate fly-over bridges of adequate sizes to carry all the cables in required formation.
The brides are to be made at the sufficient distances from the edge of Nala considering
the further expansions of roads. The strength shall be such that it should not wash away
with the flow of water during heavy rain.

Detailed route and sectional view for laying cables is available and may be collected.

-9-
1.4 IDENTIFICATOIN, MARKING AND WARNING:

1.4.1 The identification marker shall be of adequate size fabricated from 3mm thick,
25mmx25mm aluminium strip. The marker shall be embossed with letter as stated below:

“HVPNL-220 KV S/S” and “Phase R or Y or B" as the case may be .

The marker shall be tightened with nylon thread along with each cable at interval of 3
meters in such a way that it does not damage/penetrate the outer sheath of cable because
of the dead weight of back filled materials OR soil.

1.4.2 A pre-warning PVC yellow tape with size 152 mm (width) x 100 microns thick
(HDDPE)/LLDPF shall also be laid as per following clause of the specification. The
warning tape shall also contain the “WARNING” printed in black letters as under (In
English as well as Hindi).

“CAUTION: 220000 VOLTS HVPNL CABLE”

1.4.3 A pre-warning tap as per above clause shall be laid below ground level in the earth about
400/500 mm deep along the route of cable and in jointing bays.

1.4.4 The cable route marker is to be made from R.C.C. blocks duly embossed on all the side as
under:-
“HVPNL 220KV CABLE LINE”

The minimum size shall be 600x400x50mm. It shall be at least embedded in ground upto
400mm depth. The exposed portions shall be painted with non-washable paints. The
interval should be minimum 30meters between two markers. It should be put at bends,
curves, road crossing etc. of cable route.

1.5 TEST AFTER INSTALLATION:

1.5.1 Pre-commissioning tests on site, to be undertaken by the successful tenderer shall include
the following:-
a) Insulation Resistance of each cable drum length after laying and before jointing.

b) Tests for detection of damage to outer sheath, if any.

c) Serving insulation resistance after laying each cable length shall withstand a
voltage of 10 KV DC for one minute between each reinforcement and external
conducting surface; In addition, the serving insulation resistance shall be measured
and checked with the values obtained during routine factory tests.

d) On completion of the cable laying and jointing work, the complete installation shall
be checked with a D.C. voltage of 3 Uo applied for 15 minutes between each
conductor and sheath.

e) Conductor resistance of each cable of each complete circuit.


f) Test for 5 min. with system voltage applied between the conductor and the screen.

g) Test for 24 hours with normal operating voltage of the system.

h) Continuity & phase confirmation.

- 10 -
Note: The pre-commissioning test at (f) or (g) at site to be undertaken as an alternative to
the test (d).

1.6 GENERAL:
1) The cable laying shall have to be done, as per actual site condition at the time of
execution, and as per the instruction of the engineer-in-charge.

2) The scope of work shall also include assistance in obtaining required


permission/approval from various statutory authorities i.e. Municipal Corporation, Gram
Panchayat (if any), PWD, Electrical Inspector, Telecom Department etc. Payment
demanded by any statutory authority as a compensation shall be reimbursed by
HVPNL on submission of documentary evidence i.e. receipt of such payment made.

3) The Un-priced schedule of the offered item shall also be submitted in technical bid.
4) The successful bidder has to complete the work within one quarters after
commencement period of one month.

5) The end of cut pieces of cables left out during executions shall be sealed to prevent
ingress of any moisture in the cable before handing over to consignee.

6) Detailed route and sectional view for laying cables is available and may be collected.

7) The rate of laying of 220 KV Cable covers the cost of fixing of 3 phase earth box and
laying of Co-axial cable.

8) Civil work for all other nala crossings, road crossing etc. for all the above lines shall be
considered in scope of bidder.

- 11 -
Section-6
Chapter-2
TECHNICAL SPECIFICATION FOR
220V (200AH) AND
48V (300AH) BATTERY BANKS

1.0 SCOPE:

The scope of this specification covers design, manufacture, assembly, supply,


testing at works, packing, forwarding, dispatch of VRLA batteries along with
necessary accessories, fittings etc. to the destination.
These equipments are to be complete in every respect, details to the functions
designated to the entire satisfaction of the purchaser. It is required that the
supplier accepting the contract agrees to furnish all apparatus, appliances and
material whether specifically mentioned or not but which may be found
necessary to complete, to perform and testing any of the herein specified
equipment (s) for compliance with the requirements implied without extra
charges. The erection/maintenance tools and specific tools if any will also form
part of supply.

2.0 General Technical Requirement

All the materials/components used in Battery Chargers and Valve Regulated


Lead Acid Battery (VRLA) shall be free from flaws and defects and shall
conform to relevant standards and good engineering practices:-
2.0.1 For 400 KV Sub-stations, DC System shall consist of two (2) battery sets for
each of 220V and 48V systems respectively. The standard scheme drawing is
enclosed with this specification.
2.0.2 For 220 KV sub-station, DC System shall consist of two (2) float-cum-boost
chargers and one (1) battery set for each of 220V system. For 48V system DC
scheme shall consist of one (1) battery. The standard scheme drawing is
enclosed with this specification.
2.0.3 Bidder shall select number of cells, float and Boost voltage to achieve following
requirement :

Minimum voltage available


Maximum Voltage
System when no charger working Minimum
during Float
Voltage and battery fully discharged Nos of Cell
Operation
up to 1.85 V per cell.
220 Volt 242 Volt 198 Volt 107
48 Volt 52.8 Volt 43.2 Volt 23

2.1 CLIMATIC CONDITIONS:

The equipment to be supplied against the specification shall be suitable for


satisfactory continuous operation under the following tropical conditions:

1
Max. ambient air temperature 500 C
Max. daily average ambient temperature 450 C
Max. yearly weighted ambient temperature 350 C

Min. air temperature (-) 50 C


Max. humidity 100%
Min. relative humidity 26 %
Average number of thunder storm days per annum 40
Average annual rain fall 15 cm to 100 cm.
Number of months during which tropical monsoon 4 months (June to
conditions prevail altitude above MSL Sept). Varies from 61
meters to 815.00 mtrs.
Average number of rainly days per annum. 120 days
Seismic level (Horizontal acceleration) 0.3g.
Degree of pollution Heavy
Intensity of solar radiation 1.0 KW/sq.m.
Max. Wind load 195 kg/sq.m.

3.0 Battery

3.1 Type
The DC Batteries shall be Normal Discharge type Valve Regulated Lead Acid
(VRLA) and shall conform to IS 15549: 2004/IEC 60896-21 & 22, 2004
standard. These shall be factory filled, charged & suitable for a long life under
continuous float operations and occasional discharges. The 220 V DC systems
should be unearthed and 48V DC system is Positive Earth system.
Battery sets shall be capable of operating at a peak ambient temperature of 50
Deg.C. The offered battery shall be compact and shall require no maintenance.
All safety equipment required for installation shall be provided by the
manufacturer.

3.2 Constructional Requirement

Plates:
Positive plates shall be made of flat pasted type using high corrosion resistant
alloy for durability, maintenance free, long life both in cyclic as well as in float
applications. The Grids are of Semi Radial Squarish grid to reduce internal
Resistance and travel current in shorter time.

Negative plates shall be heavy duty, durable flat plate using lead alloy pasted
Semi Radial Squarish Grid. Negative plates shall be designed to match the life
of positive plates and combination of positive and negative plates shall ensure
long life, durability and trouble free operation of battery.

Computer controlled/PLC operated in house equipment should be deployed for


preparation of lead oxide and paste to ensure consistency in paste quality &
properties. Conventional / manual type of paste preparation will not be allowed.

3.3 Containers & Lids

2
The container & lids shall be made of polypropylene Copolymer material and
shall have chemical and electro-chemical compatibility along with acid resistant
and shall conform to UL-94/ ASTM-D-2863 standard. The material shall meet all
the requirements of VRLA batteries and be consistent with the life of battery.
The porosity of the container shall be such as not to allow any gases to escape
except from the regulation valve.
The tensile strength of the material of the container shall be such as to handle
the internal cell pressure of the cells in the worst working condition.
The container shall be capable of withstanding the rigours of transport, storage
and handling. The containers shall be enclosed in a steel tray.
For identification each cell / module shall be marked in a permanent manner to
Indicate the Following information.
I. Cell Serial number.
II. Positive and Negative is embossed on the cover
III. Month and Year of manufacturing.

3.4 Cell Covers

The cell covers shall be made of suitable material compatible with the container
material and permanently fixed with container by Hermetic Heat Sealing
technique. It shall be capable to withstand internal pressure without bulging or
cracking. Fixing of pressure regulation Valve & terminals posts in the cover shall
be such that the seepage of electrolyte, gas escapes and entry of electrostatic
spark are prevented.

3.5. Separators

The separators used in manufacturing of battery cells shall be spun glass micro
porous Matrix having high acid absorption capability & resistant to battery grade
Sulphuric acid along with good insulating properties. Sufficient separator overlap
and PVC shield protection to bottom edges of the plates is to be provided to
prevent short circuit formation between the edges of adjacent plates.

3.6. Pressure Regulation Valve

Each cell shall be provided with a pressure regulation valve. The valve shall be
self re-sealable. The vent plug shall be made with suitable grade of fire retardant
plastic material. Each valve opening shall be covered with flame barrier capable in
preventing the ingress of flame into the cell interior when the valve opens and
hydrogen / oxygen gas mixture is released. The valve unit shall be such that it
cannot be opened without a proper tool.

3.7. Terminal Posts

Both the Positive and Negative terminals of the cells shall be capable of proper
termination and shall ensure its consistency with the life of battery. The terminals
shall have adequate solid copper core cross-section to avoid overheating at
maximum current load. The surface of the terminal post extending above the cell
cover including bolt hole shall be coated with an acid resistant and corrosion
retarding material. Terminal posts or any other metal part which is in contact with
the electrolyte shall be made of the same alloy as that of the plates or of a
proven material that does not have any harmful effect on cell performance. Both
Positive and negative terminal posts of VRLA Battery shall be colored Red and
Black to make it unambiguously identifiable.

3.8. Connectors, Nuts & Bolts, Heat Shrinkable Sleeves

The connectors shall be non corroding lead coated copper of suitable size to

3
enable connections of cells. Copper connections shall be suitably lead coated to
withstand corrosion due to Sulphuric acid/fumes.
Nuts and bolts for connecting the cells shall be made of stainless steel with good
acid resistant characteristics. All inter cell connectors shall be protected with heat
shrinkable silicon sleeves for reducing the environmental impact including a
corrosive environment.

3.9. Flame Arrestors

Each cell shall be equipped with a Flame Arrestor to defuse the Hydrogen gas
escaped during charge and discharge. Material of the flame arrestor shall not
affect the performance of the cell.

3.10. Battery Bank Stand

All batteries shall be mounted in a suitable metallic stand/frame. The frame shall
be powdered coated with acid resistant paint (2 coats) and should have
protection against fungus growth and other harmful effect due to tropical
environment. The suitable insulation shall be provided between stand/frame and
floor to avoid the grounding of the frame/stand. The joining of the frames should
not leave crevices and ensure proper and tight fit.

3.11. Capacity Requirements

When the battery is discharged at 10 hour rate, it shall deliver 80% of C (rated
capacity, corrected at 27º Celsius) before any of the cells in the battery
bank reaches 1.85V/cell.

The battery shall be capable of being recharged from the fully exhausted
condition (1.75V/cell) within 10 hrs up to 90% state of charge. All the cells in a
battery shall be designed for continuous float operation at the specified float
voltage throughout the life.

The capacity (corrected at 27ºCelcius) shall also not be less than C and not more
than 120% of C before any cell in the battery bank reaches 1.75V/cell. The
battery voltage shall not be less than the following values, when a fully charged
battery is put to discharge at C/10 rate:

(a) After Six minutes of discharge: 1.98V/cell


(b) After Six hours of discharge: 1.92V/cell
(c) After 8 hours of discharge: 1.85V/cell
(d) After 10 hours of discharge: 1.75V/cell

Loss in capacity during storage at an average ambient temperature of 35º Celsius


for a period of 6 months shall not be more than 60% and the cell/battery shall
achieve 85% of its rated capacity within 3 charge/discharge cycles and full rated
capacity within 5 cycles, after the storage period of 6 months. Voltage of each cell
in the battery set shall be within 0.05V of the average voltage throughout
the storage period. Ampere hour efficiency shall be better than 90% and watt
hour efficiency shall be better than 80%.

3.12. Expected Battery Life

The battery shall be capable of giving 1200 or more charge/discharge cycles at


80% Depth of discharge (DOD) at an average temperature of 27º C.
DOD (Depth of Discharge) is defined as the ratio of the quantity of
electricity (in Ampere-Hour) removed from a cell or battery on discharge to its
rated capacity.
The battery sets shall have a minimum expected life of 20 years at float

4
operation.
3.13. Accessories along with Battery System

Each battery shall be supplied with following accessories and devices:

a) Torque Wrench.
b) Cell Test Voltmeter (-3-0-+ 3) Volts with least count of 0.01 Volt

3.14. Type Test of Battery

The Bidder/Supplier shall supply type tested battery per IS 15549: 2004/IEC
60896-21 & 22 over the range of at least one capacity per design and should
have met requirement of Service Life test as per above stated IEC standards
within last seven years. The Bidder/Supplier shall submit necessary evidences
enclosed along with tender documents.

Sr.No Description
1 Gas Emission
2 High Current Tolerance
3 Short Circuit Current and DC internal resistance
4 Protection against internal ignition from external spark source
5 Protection against ground short propensity
6 Content & durability of required marking
7 Material Identification
8 Valve Operation
9 Flammability Rating of material
10 Intercell connector performance
11 Discharge Capacity
12 Charge Retention during storage
13 Float Service with daily discharge for reliable mains power
14 Recharge behavior
15 Service life at an operating temperature of 400 C for brief
duration exposure time
16 Impact of stress temperature of 60oC for brief duration
exposure time with 3 hours discharge test
17 Abusive Over discharge
18 Thermal runway sensitivity
19 Low temperature sensitivity
20 Dimensional sensitivity at elevated internal pressure &
temperature
21 Stability against mechanical abuse of units during installation

Test shall be conducted in accordance with IEC 60896-21 & 22,2004


3.14.1 Routine Test of Battery
1. Physical examination test
2. Visual Inspection
3. Dimensions, Mass & Layout
4. Marking & Packing

3.14.2 Acceptance Test of Battery


1. Polarity Marking
2. Verification of Dimensions
3. Test of AH Capacity.

5
3.15. List of Factory & Site Tests for Battery

Sr.No Test Factory Tests Site Tests

1 Physical Verification Yes


2 C/10 Capacity test on the cell Yes

3.16. Installation and Commissioning

Manufacturer of battery shall supervise the installation as recommended in O&M


manual/or relevant standards. All necessary instruments, materials, tools and
tackles required for installation, testing at site and commissioning are to
arranged by battery manufacturer/Bidders.

4.0 MARKING AND PACKING:

4.1 MARKING:

The following information shall be indeligibly and durably marked on the outside
of the cell.

a) Nominal Voltage
b) Manufacturer’s name, type and trade name.
c) AH capacity at 10 hour rate.
Voltage for float operation at 20 deg. C with tolerance of (+/-) 1%.
d) Month & year of manufacturer
e) Country of origin.
f) S.No. of cell/cell No.

4.1.1 The cells and batteries may also be marked with the ISI certification mark, if
any.

4.2 PACKING:
The cells shall be suitably packed so as to avoid any loss or damage during
transit.

5.0 INSTRUCTION MANUAL:


The manufacturer shall supply one copy of instructions manual for initial charging
(if required)/treatment, and routine maintenance during service, with each and
every battery set. The manufacturer shall supply 5 copies of instructions manual
to the purchaser.

The following information shall be provided on, the instruction cards.


a) Designation of cell or battery
b) Ampere hour capacity.
c) Nominal voltage
d) Manufacturer’s instructions for charging
e) Voltage for float operation at 20 deg.C with tolerance (+/-) 1%.
f) Maintenance instructions
g) Environmental & safety provisions required.

6.0 TESTS:

All the acceptance tests as per relevant standards mentioned shall be carried out
for batteries in presence of our inspecting officer free of cost. Type test
certificates (not older than 7 years from the date of opening of tender) are to be
submitted for approval of purchaser.

6
7.0 DRAWINGS:

The tenderer will submit the detailed dimensional drawings for battery sets
including stands.

8.0 TYPE TEST CERTIFICATES:

The tenderer will submit the complete type test certificates as per relevant
standards mentioned (not older than 7 years from the date of opening of tender)
for battery sets with their tenders, without which the offers are likely to be
ignored.

9.0 GUARANTEED TECHNICAL PARTICUALRS:

Guaranteed Technical Particualrs for battery sets as per Annexure-A attached


shall be furnished along with the tender.

10.0 ACCESSORIES:

Each battery set shall be supplied complete with all necessary accessories viz.
stand, inter connections, cell no. Plates with sticker, multi meter complete with
leads, spanners.

11.0 BILL OF MATERIAL:

The firm shall also have to furnish the bill of material used in battery set.

7
SECTION-6
Battery Charger
CHAPTER-3
1. Battery Charger

The DC system for 220V DC is unearthed. The Battery Chargers as well as their
automatic regulators shall be of static type and shall be compatible with VRLA
batteries. All battery chargers shall be capable of continuous operation at the
respective rated load in float charging mode, i.e. Float charging the associated Lead-
Acid Batteries at 2.13 to 2.27 Volts per cell while supplying the DC load. The chargers
shall also be capable of Boost charging the associated DC battery at 2.28 to 2.32
volts per cell at the desired rate.
Charger shall regulate the float/boost voltage in case of prescribed temperature rise
of battery as per manufacturer’s recommendation to avoid thermal runaway.
Necessary temperature sensors shall be provided in mid location of battery banks
and shall be wired up to the respective charger for feedback control. The
manufacturer shall demonstrate this feature during testing of each charger.
1.1 The battery chargers shall be provided with facility for both automatic and manual
control of output voltage and current. A selector switch shall be provided for selecting
the mode of output voltage/current control, whether automatic or manual. When on
automatic control mode during float charging the chargers output voltage shall remain
within + 1% of the set value, for AC input voltage variation of + 1% frequency
variation of + 5% a combined voltage and frequency variation of + 1% and a DC load
variation from zero to full load.
1.2 All battery chargers shall have a constant voltage characteristics throughout the
range (from zero to full load) at the floating value of the voltage so as to keep the
battery fully charged but without harmful overcharge.
1.3 All chargers shall have load limiters having drooping characteristics, which shall
cause, when the voltage control is in automatic mode, a gradual lowering of the
output voltage whet eh DC load current exceeds the Load limiter setting of the
Charger. The Load-limiter characteristics shall be such that any sustained overload or
short circuit in DC system shall not charge the Charger nor shall it cause blowing of
any of the Charger fuses. The Charger shall not trip on overload or external short
circuit.
1.4 Uniform and step less adjustments of voltage setting (in both manual and automatic
modes) shall be provided on the front of the Charger panel covering the entire float
charging output range specified. Step less adjustments of the Load-limiter setting
shall also be possible from 80% to 100% of the rated output current for Charging
mode.
1.5 During Boot Charging, the Battery Charger shall operate on constant current mode
(when automatic regulator is in service). It shall be possible to adjust the Boost
charging current continuously over a range of 50 to 100% of the rated output current
for Boost charging mode.

The Charger output voltage shall automatically go on rising, when it is operating on


Boost mode, as the Battery Chargers up. For limiting the output voltage of the
Charger, a potentiometer shall be provided on the front of the panel, whereby it shall
be possible to set the upper limit of this voltage any where in the output range
specified for Boost Charging mode

-0-
1.6 The Charger manufacturer may offer an arrangement in which the voltage setting
device for Float charging mode is also used as output voltage limit setting device for
Boost charging mode and the Load-limiter of Float charging mode is used as current
setting device in boost charging mode.

1.7 Suitable filter circuits shall be provided in all the chargers to limit the ripple content (
Peak to Peak) in the output voltage to 1% irrespective of the DC load level, when
they are not connected to a battery.

1.8 MCCB

All Battery Chargers shall have 2 Nos. MCCBs on the input side to receive cables
from two sources. Mechanical interlock should be provided such that only one shall
be closed at a time. It shall be of P2 duty and suitable for continuous duty MCCB’s
should have auxiliary contacts for annunciation.

1.9 Rectifier Transformer

The rectifier transformer shall be continuously rated, dry air cooled (A.N) an of class F
insulation type. The rating of the rectifier transformer shall have 10% overload
capacity.

1.10 Rectifier Assembly

The rectifier assembly shall be fully/half controlled bridge type and shall be designed
to meet the duty as required by the respective charger. The rectifier shall be provided
with heat sink having their own heat dissipation arrangements with natural air cooling.
Necessary surge protection devices and rectifier type test acting HRC fuses shall be
provided in each arm of the rectifier connections.

1.11 Instruments

One AC voltmeter and one AC ammeter along with selector switches shall be
provided for all chargers. One DC voltmeter and DC ammeter (with shunt) shall be
provided for all chargers. The instruments shall be flush type, dust proof and moisture
resistant. The instruments shall have easily accessible means for zero adjustment.
The instruments shall be of 15 accuracy class. In addition to the above a centre zero
voltmeter with selector switch shall also be provided for 220 V Chargers for testing
purpose.

1.12 Air Break Switches

One DC output switch shall be provided in all chargers. They shall be air break type
suitable for 500 Volts AC/ 250 DC. The contacts of the switches shall open and close
with a snap action. The operating handle of the switch shall be fully insulated from
circuit. ‘ON’ and ‘OFF’ position on the switch shall be clearly indicated. Rating of
switches shall be suitable for their continuous load. Alternatively, MCCB’s of suitable
ratings shall also acceptable in place of Air Break Switch.

-1-
1.13 Fuses

All fuses shall be HRC Link type. Fuses shall be mounted on fuse carriers which are
in turn mounted on fuse bases. Wherever it is not possible to mount fuses on carriers,
fuses shall be directly mounted on plug-in type base. In such case one insulated fuse
pulling handle shall be supplied for each charger. Fuse rating shall be chosen by the
Bidder depending on the circuit requirement. All fuses in the chargers shall be
monitored. Fuse failure annunciation shall be provided on the failure of any fuse.

1.14 Blocking Diode

Blocking diode shall be provided in the positive pole of the output circuit of each
charger to prevent current flow from the DC battery into the charger.

1.15 Annunciation System

Audio-visual indications through bright LEDs shall be provided in all Chargers for the
following abnormalities:-
a) AC Power failure.
b) Rectifier/chargers fuse blown.
c) Over voltage across the battery when boost charging.
d) Abnormal voltage (High/Low)
e) Any other annunciation if required

Potential free NO contacts of above abnormal conditions shall also be provided for
common remote indication “CHARGER TROUBLE” in Owner’s Control Board.
Indication for charger in float mode and boost mode through indication lamps shall be
provided for chargers. A Potential free contact for float/boost mode shall be provided
for external interlocks.

1.16 Name Plates and Marking

The name plates shall be white with black engraved letters. On top of each Charger,
on front as well as rear sides, larger and bold name plates shall be provided to
identify the Charger. Name plates with full and clear inscriptions shall also be
provided on and inside of the panels for identification of the various equipments and
ease of operation and maintenance.

1.17 Charger Construction

The Chargers shall be indoor, floor-mounted, self-supporting sheet metal enclosed


cubicle type. The Bidder shall supply all necessary base frames, anchor bolts and
hardware. The Chargers shall be fabricated from 2.0mm cold rolled sheet steel and
shall have folded type of construction. Removable gland plates for all cables and lugs
for power cables shall be supplied by the Bidder. The lugs for power cables shall be
made of electrolytic copper with tin coat. Power cable sizes shall be advised to the
Bidder at a later date for provision of suitable lugs and drilling of gland plates. The
Charger shall be tropicalised and vermin proof. Ventilation louvers, if provided shall
be backed with screens. All doors and covers shall be fitted with synthetic rubber
gaskets. The chargers shall have hinged double leaf doors provided on front and on

-2-
backside for adequate access to the Charger’s internals. All the charger cubicle doors
shall be properly earthed. The degree of protection of Charger enclosure shall be at
least IP-42 as per IS: 13947 Part -1.

1.17.1 All indicating instruments, control switches and indicating lamps shall be mounted on
the front side of the Charger.

1.17.2 Each Charger shall be furnished completely wired upto power cable lugs and terminal
blocks and ready for external connections. The control wiring shall be carried out with
PVC insulated, 1.5 sq.mm. stranded copper wired. Control terminals shall be suitable
for connecting two wires, with 2.5 sq.mm stranded copper conductors. All terminals
shall be numbered for ease of connections and identification. Each wire shall bare a
ferrule or tag on each end for identification. At least 20% spare terminals shall be
provided for control circuits.
1.17.3 The insulation of all circuits, except the low voltage electronic circuits shall withstand
test voltage of 2 KV AC for one minute. An air clearance of at least ten (10) mm shall
be maintained throughout for such circuits, right up to the terminal lugs. Whenever
this clearance is not available, the live parts shall be insulated or shrouded.

1.18 Painting
All sheet steel work shall be pre-treated in tanks, in accordance with IS:6005
Degreasing shall be done by alkaline cleaning. Rust and scale shall be removed by
pickling with acid. After pickling, the parts shall be washed in running water. Then
these shall be rinsed in slightly alkaline hot water and dried. The phosphate coating
shall be ‘Class-C’ as specified in IS:6005. Welding shall not be done after
phosphating. The phosphating surfaces shall be rinsed and passivated prior to
application of stoved lead oxide primer coating. After primer application, two coats of
finishing synthetic enamel paint of shade -692 (smoke grey) of IS-5 shall be applied,
unless required otherwise by the Owner. The inside of the chargers shall be glossy
white. Each coat of finishing synthetic enamel paint shall be properly staved. The
paint thickness shall not be less than fifty (50) microns.

1.19 TESTS

1.19.1 Battery Chargers shall conform to all type tests as per relevant Indian Standard
Performance test on the Chargers as per Specification shall also be carried out on
each charger as per specification. Rectifier transformer shall conform to all type tests
in IS:4540 and short circuit test as per IS:2026. Following type tests shall be carried
out for compliance of specification requirements:-

i) Voltage regulation test.


ii) Load limiter characteristics test
iii) Efficiency tests
iv) High voltage tests
v) Temperature rise test
vi) Short circuit test at no load and full load at rated voltage for sustained
short-circuit.
vii) Degree of protection test
viii) Measurement of ripple by oscilloscope.
ix) Temperature compensation feature demonstration

-3-
1.19.2 The Bidder may be required to demonstrate to the OWNER that the chargers
conform to the specification particularly regarding continuous rating, ripple free
output, voltage regulation and load limiting characteristic, before despatch as well
as after installation at site. At site the following tests shall be carried out:-

i) Insulation resistance test


ii) Checking of proper annunciation system operation
1.19.3 If a Charger fails to meet the specified requirements, the Bidder shall replace the
same with appropriate Charger without affecting the commissioning schedule of
the Sub-Station, and without any extra cost to the OWNER.

1.19.4 The Bidder shall present for inspection, the type and routine test certificates for
the following components whenever required by the OWNER.

(i) Switches
(ii) Relays/MCCBs
(iii) Instruments
(iv) DC fuses
(v) SCR
(vi) Diodes
(vii) Condensers
(viii) Potentiometers
(ix) Semiconductor
(x) Annunciator
(xi) Control wiring
(xii) Push buttons and contactors

Makes of above equipment shall be subject to Owner’s approval.

-4-
SECTION-6
CHAPTER-4

TECHNICAL SPECIFICATION OF D.C. DISTRIBUTION BOARD.

1. SCOPE:
This specification provides for design, Engineering, manufacture, stage testing,
inspection and testing before dispatch, packing, forwarding and delivery at site of D.C.
Distribution Board, complete with all fittings accessories and associated auxiliary
equipment mandatory which are required for efficient and trouble free operation as per
specified here under.

It is not the intent to specify completely all the details of design and construction of
equipment. However, the equipment shall conform in all respects to the high standard of
engineering, design and workmanship and shall be capable of performing in continuous
commercial operation up to the Bidder’s guarantee acceptable to the purchaser. The
equipment offered shall be complete in all component necessary for its effective and
trouble free operation along with associated equipment interlocks protection scheme etc.
Such components shall be deemed to be within the scope of supply irrespective of
whether those are specially brought out in this Specification and or the commercial order
or not. All similar parts particularly movable ones shall be interchangeable.

1.02 CLIMATIC CONDITIONS :


As per Section-I Vol-II.
1.03 STANDARD:
All material and equipment shall comply in every respect with the requirements of the
latest edition of the relevant Indian Standard IS:1651.
1.04 MANUFACTURE AND WORKMANSHIP:
All the material used in the construction of the equipment shall be of the best quality
obtainable of their respective kinds and whole of the work shall be of the highest class,
well finished and of approved design and make. Casting shall be free from blow holes,
flaws and of the true form and dimensions.
All machined surfaces shall be true and smooth and well finished.
1.05 DUTY AND GENERAL ARRANGEMENTS:
The storage batteries are required for providing an independent and reliable source of
220 Volts D.C. supply for control, protection, alarm and indicating circuits of the high
voltage switchgear in various attended type Sub Stations. The batteries shall be kept in
a state of floating trickle charge and provision be made for rapid charging the batteries
when so required.
The power for the charging apparatus shall be given through an independent 4-core
cable connection from an A.C. 50 cycles 3 phase 415 ± 10% volts switchboard fed from
a Station Transformer. D.C. Distribution shall be through fuse protected rotary switches
mounted on a separate distribution board.
1.06 TYPE OF EQUIPMENT:
All equipment shall be located indoors. D.C. Distribution panel are to be mounted on the
floor in the control room adjacent to the Battery room.

Necessary doors and screens shall be provided wherever required. All equipment shall
be vermin proof. The overall design of the entire equipment should be adequate for the
duty in view to ensure trouble free and dependable service.

-1-
The various cables whether for A.C. supply to the battery charging equipment or for D.C.
Distribution circuits, which are to be arranged by the Bidder shall have P.V.C. insulation.
The conductors may be of copper or aluminum. All panel wiring to be provided by the
supplier, shall consist of suitable colored/marked P.V.C. insulated cables.
1.07 BUS BARS AND SUPPORTS:
The bus bars shall be of aluminium having adequate cross-sections. The bus bars shall
be so designed and mounted that their expansion and contraction does not subject,
either the Bus Bars or their supports, to any stresses. All bus bars and connections shall
be duly marked and colored for identification.
1.08 INSTRUMENTS:
All instruments shall have 96 sq mm dials and flush mounted on the panels. Moving coil
spring controlled instruments shall be used except those for A.C. which may be of the
moving iron type. The error of indication shall not exceed 1% throughout the effective
range of the meter.
1.09 RESPONSIBILITY FOR DESIGNS:
The Bidder shall assume full responsibility for co-ordinate and adequate design and shall
conform to the best engineering practice for the operating conditions specified. In case
the equipment covered by this specification is to be co-ordinate with other equipment,
the Bidder shall furnish complete information and data as may be desired by the
purchaser.
1.10 CELL TERMINALS:
Terminal posts of each cell should be clearly stamped as positive and negative and they
should be made clearly distinguishable. Two pairs of Battery terminal should be
provided, so that a spare cell may be connected before the previous cell in series is
removed for over-haul.
1.11 GROUNDING:
All metal parts should be grounded according to Indian Electricity Rules. Main ground
Bus shall be provided by the purchaser. Special grounding lugs of adequate size shall
be provided by the supplier on the charging equipment.
1.12 INTER CHANGEABILITY:
Corresponding parts of plant and equipment shall be made to gauge or jig and shall be
interchangeable in every respect.
1.13 DOCUMENTATION

The successful bidder shall submit four sets of drawings for HVPNL approval.
The following drawing shall be supplied with the tender: -
i) Outline drawings of all apparatus showing sufficient details to enable the
purchaser to determine whether the design proposed can be installed
satisfactorily or not.
ii) Wiring diagram of battery charger.
NOTE: All above drawings should be a minimum space (14x10cm) for
stamping the approval of drawings by HVPNL.

-2-
1.14 FOUNDATIONS AND FIXINGS:
All plants and equipment shall be provided with a complete set of foundation holding
down bolts, washers, nuts plants and other fixture as may be required and these shall be
supplied by the Bidder. These fittings will be fixed by the purchaser in the foundations
unless otherwise specified. All foundation bolts, fixtures etc. shall be supplied as soon as
possible after the contract drawings have been approved.

1.15 INSTRUCTION AND MARKING PLATES:


All gauges, meters, instruments etc. shall have dials or scales calibrated in metric
system of units. All name plates, instruction plate, warning signs and any marking
what-so-ever on the equipment and its parts and accessories shall be in Hindi-English
Language, using idioms, words and meaning as in current use in India.
In order to facilitate sorting and erection at site every part of the plant and equipment
shall be suitably marked.

1.16 TROPICAL TREATMENT & PAINT:


All corrodible parts and surfaces shall be of such material and shall be provided with
such paint or other protective finish that no part of the installed equipment shall be
injuriously affected by the atmospheric moisture, heat and fumes. The panels shall be
finally painted with light grey paint having shade No.631 of IS:5 with stove enameled
finish.

1.17 PLACE OF MANUFACTURE AND INSPECTION:


The Bidder shall state in his tender the place(s) of manufacture, testing and inspection of
the various portions of the work included in the tender. The purchaser or his duly
authorised agent shall have access to the Bidder's or sub Bidder's work at any time
during working hours for the purpose of inspecting the manufacture and testing of
materials, equipment and completed plant and the Bidder shall provide the necessary
facilities for inspection.

1.18 TESTS:

1.18.1 Type Tests


The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed
by HVPN or another electric power utility and be submitted by the successful bidder to
HVPNL for approval as schedule given in Bar Chart.
i) Verification of constructional requirements
ii) Verification of marking
iii) Verification of dimensions

-3-
1.18.2 Routine Tests
As per quality assurance program (QAP).

1.18.3 Acceptance Tests


The following acceptance tests for DCDB shall be carried out by the Supplier in
presence of HVPNL representative, unless dispensed with in writing by the HVPNL.

i) Dimension test
ii) Visual check test
iii) quantative check
iv) Functional checks
v) wiring HV Test
vi) Insulation resistance test

1.18.4 SAMPLING SCHEME AND CRITERIA FOR ACCEPTANCE:


The sampling scheme and criteria for acceptance for cells up to and including 600 AH
capacity shall be in accordance with clause 5 1.4 of IS-8320-1976. The sampling
scheme for cells of higher capacities shall be subject to agreement between the user
and the manufacturer.

1.19 SPARE PARTS :-


The Bidder shall quote separately in his tender for spare parts as he world recommend
for the main maintenance operation of the equipment for the period of 5 years. Of
detailed list of such spares parts which item wise prices shall be given under schedule of
requirement and prices. The purchaser may order spares subsequently as may be finally
decided upon, at the rates given in the tender. All spares parts shall be interchangeable
and shall be of same make material and both workmanship as the corresponding parts
furnished with the main equipment.

1.20 DETAILS OF TECHNICAL PARTICULARS AND SPECIFICATION:


Details of the technical particulars and specification required have been given in
Appendix (b). Any other particulars considered necessary by the supplier may also be
given in addition to the above listed in Data requirement sheet.

1.21 COMPLETENESS OF EQUIPMENT:


Any fittings, accessories or apparatus which may not have been specifically mentioned
in the specification, but which are usually necessary in the equipment shall be deemed
to be included in the contract and shall be supplied by the Bidder without extra cost.

-4-
APPENDIX 'A'

SCHEDULE OF REQUIREMENT

D.C. DISTRIBUTION BOARD:


The D.C. Distribution Board shall be housed in a sheet steel cubicle with
adequate ventilation and it should be vermin proof as far as possible and should
be provided with louvers for ventilation backed by fine wire mesh, which applies
to both charging equipment and D.C. Distribution Board. The DCDB shall match
with the battery charging equipment and should be complete with bus bars of
suitable capacity, wiring, rating plates, glands and fixing bolts. The minimum size
of cubical should be 600X700X1600 mm. The following components shall be
provided on the D.C. distribution board:

FOR 200 AH BATTERIES


1. Double pole ON/OFF rotary switch
of 200 Amps. for 200 AH rating and
100 Amps. for 100 AH Battery with
2 Nos. HRC fuses of 100 Amps 1 set

2. Moving coil ammeter of 96mm sq. and


range 0-200 amps. for 200 AH battery
and 0-100 Amps. for 100 AH battery
for measuring the load on the bus. 1 No

3. Change over contactor :

a) 20 Amps. for 200 AH battery and 10 Amps.


for 100 AH battery change over Bidder
AC/DC for switching indication over
to DC. On failure of AC supply and 1 No
also for emergency pilot light in
the event of AC failure.

b) 10 Amps HRC fuses for pilot light 2 Nos.

4. Double pole D.C. Rotary switches with


HRC fuses for each of following feeders:

a) 220 kV closing supply of 50 Amps,


capacity 1 No

b) 66 kV -do- 1 No

-5-
e) 11 kV closing supply 100 Amps.
capacity 1 No

f & g) spare 100 Amp. capacity 2 Nos.


h & i) spare 50 Amp. capacity 2 Nos.

5. Double pole D.C. rotary switch of 10 Amps. rating with 10 Amp. HRC fuses for each of
the following feeders:

a) 11 kV Tripping supply 10 Amp capacity 1 No

b) 66 kV -do- 1 No

c 220 kV -do- 1 No

d) Carrier telephone 10 Amp. capacity 1 No

e) 66 kV Relay & Board panel 10 Amp. capacity 1 No

f) 220 kV Relay & Board panel 10 amp. capacity 1 No

g) Spare 10 Amp capacity 3 Nos.


All the instruments shall be of flush mounted type. The rotary switches shall also be
flush mounted except for the protection portion in the panels. All switches shall be
mounted on the front panel and all the HRC fuses together with their fuse fittings on
the front panel but within a chamber that can be opened by half doors, to occasion
accessibility to the fuses. The various components shall be of the best quality and
from reputed manufacturers. The layout of components, wiring workmanship
reliability etc. shall be of the best quality. Adequate room should be provided within
the charger/DC distribution board cubicles for easy accessibility of components and
also to facilitate ventilation.

-6-
SECTION-6
CHAPTER 5

TECHNICAL SPECIFICATION OF 415


VOLTS L.T. SWITCH BOARDS.

1. SCOPE :

This specification covers design, Engineering, manufacture, stage testing, inspection


and testing before despatch, packing, forwarding and delivery at site of 415 Volts AC LT
Switch Board complete with all fittings, accessories and associated auxiliary equipment
mandatory spares as per Volume II which are required for efficient and trouble free
operation as specified hereunder.

It is not the intent to specify herein all the details of design and construction of
equipments. However, the equipment shall conform in all respects to the high standards
of engineering, design and workmanship and shall be capable of performing in
continuous commercial operation up to the Bidder’s guarantee in a manner acceptable
to the Purchaser. The equipment offered shall be complete with all components
necessary for its effective and trouble free operation along with associated equipment,
interlocks protection schemes etc. irrespective of whether those are specially brought
out in this specification and commercially added or not. All similar parts particularly
movable ones shall be interchangeable.

1.02 CLIMATIC CONDITIONS :


The equipment is required to operate satisfactorily under the following site conditions:-

i. Max. Temperature 500C


ii. Min. Temperature -2.50C
iii. Relativehumidity
a) Max. 100%
b) Min. 26%
iii. Average number of rainy days per annum Nearly 120 days
iv. Average rain fall per year. 900 mm
v. Average number of dust storm days per annum 35
vi. Isoceraunic level 45
vii. Max. Wind pressures 195 kg/sqmt.
viii. Altitude above mean sea level Less than 1000 mt.

1.03 STANDARDS:
The metal clad (preferably sheet metal) air break switch to be supplied against this
Specification shall meet with the requirements laid down in IS-4064-1978 (part I & II)
(latest edition). The HRC fuses shall comply with the Is-2208-1962 (latest amended). All
other equipments shall also comply with the requirements of the latest edition of the
respective Indian Standards.

1.04 MATERIAL AND WORKMANSHIP:


All the materials used in the construction of the equipment shall be of the best quality
obtainable of their respective kinds and whole of the work shall be of the highest class,
well finished and of approved design and make of the true form and dimensions.

All machined surfaces shall be true and smooth and well finished.

-1-
1.05 INTER CHANGEABILITY:
Corresponding parts of plant and equipment shall be made to gauge or jig and shall be
interchangeable in every respect.

1.06 DOCUMENTATION
The successful bidder shall submit four sets of drawings for HVPNL approval.
NOTE: All above drawings should be a minimum space (14x10cm) for stamping the
approval of drawings by HVPNL.

1.07 FOUNDATIONS AND FIXINGS:


All plants and equipment shall be provided with a complete set of foundation holding
down bolts, washers, nuts plants and other fixtures as may be required and these shall
be supplied by the Bidder. These fittings will be fixed by the purchaser on the
foundations unless otherwise specified.
1.08 INSTRUCTION AND MARKING PLATES:
All gauge meters, instruments etc. shall have dials or scales calibrated in metric system
of units. All name plates, instruction plate, warning signs and any marking what-so-ever
on the equipment and its parts and accessories shall be in Hindi-English Language,
using idioms, words and meaning as in current use in India.

In order to facilitate sorting and erection at site every part of the plant and equipment
shall be suitably marked.

1.09 PAINTING
The whole of the plant except bright parts, valves and such portions as are finished shall
be painted with two painting coats of approved rust resisting paint in plain colours for
packing and the parts not so painted shall be protected from deterioration during transit.
All the ferrous parts shall be painted with battle ship grey paint by means of spray
painting. The painting should be as per relevant ISS. All the non ferrous parts including
the bus bars, thimbles, jumpers shall be tinned plated and sleeves of proper thickness
and size shall be provided on all the jumpers. After erection at site every painted part
shall be well cleaned filed and chopped and shall then receive two coats of best oil paint
of approved colour, to be supplied by the Bidder without any extra cost.

1.10 TESTS:
1.10.1 TYPE TEST
The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed
by HVPN or another electric power utility and be submitted by the successful bidder to
HVPNL for approval as schedule given in Bar Chart.

1.10.2 Routine Test


As per quality assurance program (QAP).

1.10.3 Acceptance Test


The following acceptance tests shall be carried out by the Supplier in presence of
HVPNL representative, unless dispensed with in writing by the HVPNL.

-2-
i) Dimensional test
ii) Continuity test
iii) Insulation resistance test
iv) High voltage test
v) Inter locking test

1.11 INSTRUCTION BOOKS:


Applicable parts, lists, catalogues and operating instructions in English Language
specially prepared to cover all the equipment furnished under this specification which
may be needed or prove useful in operation, maintenance, repair, dismantling or
assembling and for the repair and identification of parts for ordering replacements shall
be assembled under a common cover and submitted in duplicate for each unit to the
purchaser free of cost.

1.12 REPRODUCIBLE DRAWINGS:


The Bidder shall supply two sets of full size reproducible drawings (approved by the
purchaser) along with detailed drawings of various major components/accessories etc.
(showing sectional views, wherever necessary) on oil cloth to prove useful in the
erection, operation maintenance and repair of the equipment. He shall also supply
twenty sets of azo prints of the above mentioned drawings for use in field and design
offices.

1.13 PARTICULARS OF THE SYSTEM:


The equipment shall be suitable for 415 Volts 50 cycles, 3 Phase 4 wire system with
neutral solidly earthed.

1.14 RISE IN TEMPERATURE:


The equipment shall be operated at maximum ambient temperature of 500C and as such
the temperature rise of its parts should be proportionately below the figure provided in
respective standards.

1.15 EACH SWITCH SHALL COMPRISE OF:


Metal clad floor mounting combination fuse switch board consisting of a suitable bus bar
of 320 Amps rating for 15 Ckts. Triple pole and neutral bus bar chamber, mounted on a
high floor stand arranged and equipped for the circuits given in the schedule of
requirement and mounted above and below the bus bar chamber to form a suitable
arrangement. The bus bar chamber shall have provision for adding two more switch
units as given in the schedule at a later date. The switches shall be quick make and
break type.
The switch boards shall be installed indoors. The enclosing chambers shall be dust-tight
and vermin proof.
All equipments shall be suitable for reception of Alumiium cable rising from the ground.
The details of equipment required for each switch board has been given in the schedule
of requirement.

1.16 BUS BARS:


The bus shall be made of high conductivity copper or Aluminium and shall have
adequate cross section so as to be capable of carrying 300 Amps in phase and 150
Amps. in neutral.

-3-
The bus bar shall be so designed and mounted in the separate chamber such that their
expansion or contraction does not subject either the bus bars or their insulation supports
to any stresses.
The bus bar shall be properly spaced so as to provide easy access during maintenance
and inspection etc. There should be no joints in the bus bars.
The current density for copper and aluminium bus bars must not exceed 1 A/cm2 and 87
A/cm2 respectively.

1.17 CONNECTIONS:
All the connections for the tee’s from the bus bars shall be bolted type and suitable
spring washers shall be provided to ensure proper jointing and material of the bolts shall
be of suitable metal. All the connections shall be provided with thimbles of suitable
rating.

1.18 METERING EQUIPMENT


Metering equipment for the station transformer/Incomer shall be located between the
L.T. side of the transformer and L.T. Bus Bars. The metering equipment shall include
300/5 Amps C.T.s having burden 15 VA with accuracy class 1 and 3 phase 4wire
unbalanced load integrating electronic KWH meter. A 100 mm dial flush mounted MISC
(moving iron spring controlled) Voltmeter and a 100 mm dial flush mounted MISC
ammeter both with phase selector switch shall also be provided on each switchboard to
indicate the bus bar voltage and total load on the station transformer/Incomer feeder. All
the meters shall be enclosed in separate chamber to have a flush pattern type
appearance. The meters shall be dust tight.

1.19 EARTHING
Two separate earths shall be run and each and every metallic parts of the
stand/switches/bus bar chambers shall be earthed at two different places independently.
The size of the earthing conductor for the switches and individual parts shall not be less
than No. 8 SWG copper conductor and size of the main for earthing shall not be less
than No. 3 SWG copper conductor.

1.20 BUS BAR CHAMBER


The bus bar chamber shall be made out of angle iron of suitable size as specified below
along with other details: -
a) Thickness of sheet steel enclosures, doors, covers
i) Cold rolled 2mm minimum
ii) Hot rolled +2.5mm minimum

b) Degree of protection IP-54 as per BS-


2817/IEC-144
c) Colour finish shade
i) Interior Glossy white
ii) Exterior Light grey
Semi glossy shade

d) Earthing bus material size Copper 25x6 mm

e) Purchaser’s earthing conductor Galvanised steel


Material
Size 30x6 mm
f) Clearance in air of live parts

-4-
i) Phase to Phase 80 mm
ii) Phase to earth 80 mm
1.21 LABELS:

Each switch shall be provided with suitable labels paginated on hard plastic sheet and
duly held in boss framed of the size 75x50 mm for the incoming and outgoing feeders.
The hard plastic sheet shall be of white colour and will be painted in black for the
outgoing feeders whereas it shall be painted bright red for the incoming feeders.

1.22 INTERLOCKING
Interlocks must be provided to ensure that the switch cover cannot be opened when the
switch is in the closed position. It should however be possible for competent examiner to
over ride this interlock and operate the switch with enclosure open.

1.23 FIRE HAZARDS


The switch and its associated apparatus shall be arranged to minimize fire hazards.

1.24 CLEARANCES
The clearances between phases and between phases and earth shall be as per IS-
3072-1975 with latest amendments.

1.25 CONTACTS
All live contacts of the switch shall be adequately shrouded to prevent accidental contact
when the equipment is either in the isolated or normal closed position and shall be silver
plated of suitable thickness. The fixed contacts of the fuse switch unit shall be fully
shrouded with arc resistant material. Material needs to be specified in the tender.

1.26 CABLE AND BOXES:

a) The incoming switch and outgoing switches shall be provided with cable and boxes
of suitable size capacity and rating suitable for PVC cables. Suitable cleating
arrangement shall also be provided for the cables entering the switch fuse units in
the top tier.
The cabling arrangement shall be such that cables outgoing from Isolator unit can be
connected or disconnected easily and safely.

1.27 RUPTURING CAPACITY


The rupturing capacity of the bus bar switchgear/cartridges shall not be lower than 2
MVA at 415 volts.

1.28 The individual fuse switch unit shall be provided in such a way that they can be removed
from the front of the switch board for servicing and maintenance.

1.29 MARKING
All the switches shall be clearly marked with the following particulars: -
a) Reference to the standard.
b) Rated voltage.
c) Rated normal current.
d) Rated marking capacity.
e) Breaking capacity.
f) Type of fuse/links to be used.
g) Name plate.

-5-
1. Supplier name.
2. Purchaser
3. P.O. No.
4. Rating.
5. Serial no.
6. Year of manufacturing.

1.30 OTHER PARTICULARS


The Bidder should clearly furnish the following information in their offer: -
a) Material and plating of the contacts.
b) Current density assumed.
c) Temperature rise under continuous full load over the ambient temp. of 500C.
d) Temperature rise under short circuit condition.
e) Guaranteed Technical particulars as required in appendix-A.

1.31 List of references if similar L.T. Switch Board already in service/supplied with
complete details shall be furnished.

-6-
ANNEXURE ‘A’

SCHEDULE OF REQUIREMENTS

A. 220kV Sub-Stations

415 V 3 Phase 4 wire L.T. Switch Board comprising of 17 circuits TP & N switch fuse units
consisting of one incomer from Station transformer of 500 A and another incomer from alternate
emergency AC supply in case of failure of station transformer supply of 320 A with suitable CTs
and selector switch for incomer feeders and 15 Nos. switch fuse units with HRC fuses for
outgoing feeders having the following ratings for 220 KV S/Stns.

Sr. L.T.Feeders Switch Fuse rating No.


No. rating (Amps)
(Amps)
1. Incoming from Station transformer 500 400 1

2. Alternate Source 320 300 1

3. Oil filtration set feeder 200 160 1

4. Colony lighting feeder 200 160 1

5. Yard lighting feeder 160 100 1

6. Fan control of T/F, OLTC motor and oil 100 63 1


motor of 220/132 or 220/66 KV T/F

7. Fan control of 132/33, 132/11, 66/33, 63 50 1


66/11 KV T/F & OLTC motor

8. 220 KV Breaker operation (compressor 32 25 1


and space heaters etc.) OCB feeder

9. 132/33, 132/11, 66/33, 66/11 KV Breaker 32 25 1


and space heater etc. OCB feeder

10. Outdoor street lighting feeder 63 50 1

11. Water pump and sewerage pump. 63 50 1

12. Carrier room 32 25 1

13. Battery charger 32 25 1

14. Control panel indicator 32 25 1

15. Spare feeder 160 100 1

16. Provision for additional switch fuse unit

-7-
17. To be mounted at a later stage.

TOTAL 17 Nos.

NOTES:
1. Each circuit as indicated above shall have switch rating, HRC fuse rating and LT feeder
labeling as mentioned against each. It shall include bus bar connections, terminals,
cable glands and cable lugs etc.

2. Each Incomer shall be provided with the following equipments:

i) One No. 100mm dial flush mounting moving iron spring controlled (MISC)
ammeter of scale of 0-500A with phase selector switch.

ii) One No. 100 mm dial flush mounting MISC voltmeter of range 0-500V with phase
selector switch.

iii) 3 Nos. 500/5A CTs having burden 15 VA and accuracy class 1 and Instrument
Security factor.

iv) One No. 3 phase , 4 wire unbalanced load integrating watt hour meter
(operatable on 500/5A CTs).

v) TTB for LT CT meter.

3. Make of each component must be listed in bid.

4. The bus bar shall be designed for 500 A for phase and 250 A for neutral.

-8-
SECTION-6
CHAPTER 6

FIRE FIGHTING EQUIPMENT

1.0 SCOPE
Portable fire extinguishers of Carbon Dioxide type and Dry chemical Powder type
shall be provided in adequate numbers for protection the Control Room Building and
all other Buildings in the sub-stations. The protection shall cover all the rooms/areas
of the buildings. The quantity and location of the extinguishers shall be as per the
requirements of Fire protection Manual (Part-I) issued by Tariff Advisory Committee
of India (TAC) and IS:2190.

1.1 Trolley Mounted fire extinguishers of 22.5 kg Carbon Dioxide type and 22.5 kg Dry
Chemical Powder type shall be used for protection of all 220kV, 132/66kV
Transformers and reactors in the S/Stn. Two DCP type and two CO2 type
extinguishers shall be provided for each transformer/reactor.

2.0 PORTABLE TYPE FIRE EXTINGUISHERS:

2.1 This Specification lays down the requirement regarding fire extinguishers of following
types:
a) Carbon Dioxide type
b) Dry Chemical powder type
2.2 All the portable extinguishers shall be capable of discharging freely and completely
in upright position.
2.3 Each extinguisher shall have the instructions for operating the extinguishers on its
body itself.
2.4 All extinguishers shall be supplied with initial charge and accessories as required.
2.5 Portable type extinguishers shall be provided with suitable clamps for mounting on
walls or columns.
2.6 All extinguishers shall be painted with durable enamel paint of fire red colour
confirming to relevant Indian Standards.
2.7 Capacities of each type shall be as indicated in the schedule of quantities.
2.8 Carbon Dioxide (CO2 type) extinguishers shall conform to IS:2878.
2.9 Dry chemical powder type extinguisher shall conform to IS:2171.

2.10 TESTS AND INSPECTION

2.10.1 All tests required to ensure that the equipment conforms to the Specification
requirements and relevant standards and codes.
2.10.2 A performance demonstration test at site of five (5) percent or one (1) number
whichever is higher, of the extinguishers shall be carried out by the Bidder. All
consumable and replaceable items required for this test would be supplied by the
Bidder without any extra cost to the Purchaser.
2.10.3 Performance listing of extinguishers shall be in line of applicable Indian Standards.
In case, where no Indian Standard is applicable for a particular type of extinguishers,
the method of testing shall be mutually discussed and agreed to before placement of
order for the extinguishers.

-1-
2.11 PERFORMANCE GUARANTEE
The Bidder shall guarantee all equipment supplied by him against any defect due to
faulty design, materials and workmanship. The equipment shall be guaranteed to
operate satisfactorily at the rated conditions at site.

2.12 PAINTING
Each fire extinguisher shall be painted with durable enamel paint of fire red colour
conforming to relevant Indian Standards.

3.0 TROLLEY MOUNTED DRY CHEMICAL POWDER TYPE MOBILE FIRE


EXTINGUISHER
The Specification lays down the requirement regarding wheeled fire extinguisher of
dry chemical powder type.

Design, Manufacture, Material of construction and performance of mobile type fire


extinguisher shall comply with the requirements of latest Indian Standards & shall
have BIS approval (ISI marked).

3.1 PERFORMANCE REQUIREMENT


The capacity of the mobile dry chemical powder type fire extinguisher shall be 22.5
kg which means the total capacity of the container, when powder completely filled to
the specified level shall be 22.5 kg.
The fire extinguishers shall be used for Class ‘B’, ‘C’, and ‘E’ fires.

The extinguishers shall operate in the vertical position, mounted on solid rubber tyre
trolley wheels.

The effective throw during operation of the extinguishers shall not be less than 10
meter.

A carbon dioxide cartridge fitted with valved discharge head, shall provide sufficient
carbon dioxide to expel the dry chemical powder.

3.2 DESIGN AND CONSTRUCTION


The construction of wheeled fire extinguishers shall conform to IS standard and not
be limited to the requirements mentioned here.

The shape of the body of the fire extinguisher shall be cylindrical. It shall have
adequate supporting arrangement.

The balance of the fully equipped assembly shall be so arranged that it can be easily
towed speedily behind a jeep or a car and also wheeled by a single operator.

Two solid rubber tyred trolley wheels shall be fitted to the body of the mobile fire
extinguisher. The rubber tyres shall have an effective life, and less than three (3)
years.

The extinguisher shall be fitted with a discharge hose and nozzle connection. The
hose shall be of rubber or composite construction, having a length of 4.5-meter
minimum. The bursting pressure of the hose shall be minimum 42 kgf/cm (g).

-2-
The design of discharge nozzle shall be such that when the extinguisher is operated
in still air the powder will be thrown in the form of a jet having a range of 10m
(minimum) for a period of 50-60 seconds. The nozzle shall be fitted with a hand
control device.

Provision shall be therefore making a pressure test on the body.

To minimize corrosion, the various components shall be provided with suitable anti-
corrosive as per the requirement of applicable codes.

Each mobile extinguisher shall be complete with initial charge, discharge fittings and
accessories.

3.3 TESTS AND INSPECTION


Testing at manufacturer’s works.

The manufacturer shall conduct all tests required to ensure that the equipment
furnished will conform to this Specification requirements, relevant Indian Standards
and applicable codes. Everybody shall be capable of withstanding an internal
hydraulic pressure of 25 kgf/cm (g) without leakage or visible distortion, prior to
painting, for a minimum period of 5 minutes.

In destruction tests, if called for, ultimate failure shall occur at a test pressure not less
than 32 kgf/cm (g) and if it occurs below 35 kgf/cm (g) there shall not be damage in
any joint, seam casting of fittings.

A performance demonstration test at site on five (5) percent or one (1) number,
whichever is higher, shall be required to be carried out by the BIDDER. All
consumable and replaceable items required for the test shall be supplied by the
BIDDER without any extra cost to Purchaser.

After conduction tests as in 1.1 and 1.4 the body shall be properly washed and
drained off. After 24 hours, the interior shall be examined and it must be free from
any stain, rust etc.

3.4 PERFORMANCE GUARANTEE

The BIDDER shall guarantee all equipment supplied by him against any defect due
to faulty design, materials and workmanship. The equipment shall be guaranteed to
operate satisfactorily at the rated conditions at site.

3.5 PAINTING
Each mobile fire extinguisher shall be painted with durable enamel paint of red colour
conforming to relevant Indian Standard. The mobile foam type fire extinguisher shall
be of make approved by Tariff Advisory Committee/NFPA/FOC/UL. Appliances
conforming to the relevant BS/NFPA Standards are also acceptable provided the
construction generally conform to the IS Standards so that spares refills/cartridges of
Indian make conforming to IS Specification can be used after the operation of the
extinguisher.

Spare charge cartridges equivalent to requirements of 2 Nos. extinguishers shall also


be supplied.

-3-
4.0 TROLLEY MOUNTED CARBON-DIOXIDE TYPE MOBILE FIRE EXTINGUISHER

1.1 This Specification lays down the requirements regarding wheeled fire extinguisher of
carbon-dioxide.

1.2 Design, manufacture, material of construction and performance of extinguisher as


specified herein after shall comply with the requirements of latest applicable Indian
Standards IS-2878 or equivalents and shall have BIS approval (ISI marked).

1.3 PERFORMANCE REQUIREMENT


1.3.1 The capacity of the extinguisher shall be 22.5 kg of carbon-dioxide when filled in the
container to a filling ratio of about 0.66, 7.
1.3.2 The extinguisher shall be designed for use where larger high intensity fire hazards
are involved requiring versatility of action. These shall be used for Class ‘B’ fire, i.e.
fire in flammable liquid. Class ‘C’ fire i.e. fire in gaseous substances under pressure
and Class ‘E’ fire, i.e. fires in live electrical equipment.
1.3.3 The extinguisher shall be operated in upright position, by releasing a suitable valve.
1.3.4 The range of effective operation of the extinguishers shall be about 4 meters.

1.4 DESIGN AND CONSTRUCTION


The construction of wheeled fire extinguisher, carbon-dioxide type, shall in general
conform to IS:2828 subject to the requirements mentioned hereunder:
1.4.1 The carbon-dioxide gas shall conform to IS:307.
1.4.2 The shape of the body of the extinguisher shall be cylindrical. The body shall be of
steel cylinder. It shall have adequate supporting arrangement so that it can rest on
the wheeled body in upright position and the operator be free to direct the stream.
1.4.3 The balance of the full equipped trolley unit shall be so arranged, that despite its
considerable weight, it can be easily wheeled by one man. It should be capable of
being towed speedily behind a jeep or car.
1.4.4 The cylinder shall be mounted on a trolley fitted with two cushion tyred wheels and
fitted with suitable handle. The overall wheel diameter shall be about 280 mm.
The frame of the trolley shall be made of welded steel section.
1.4.5 The design shall permit easy maintenance and operation with one man service.
1.4.6 The extinguisher shall be fitted with a high pressure flexible hose of about 9 m length
and internal dia to hoses shall not be more than 12 mm.
1.4.7 A discharge horn made of fibre or any material non-conducting to electricity shall be
fitted with a handle made of thermal insulating material capable of protecting
operators hand from freezing effects.
1.4.8 Suitable provision for firmly securing the horn to the body, when it is not in use, shall
be provided. The fixing device shall not interfere with the operation or mobility of the
extinguisher.
1.4.9 The discharge valve or operating head shall be capable of being operated
satisfactorily. It shall be made of material as specified in IS:2878.
1.4.10 There shall be no leakage of CO2 from valve or fitting during the use of extinguisher.
Valve shall be provided with suitable safety device to prevent over pressure in
cylinder.
1.4.11 A seal or device shall be fitted to indicate that the extinguisher has not been used.
1.4.12 Each extinguisher shall be complete with initial charge, discharge fittings and other
accessories as required.

-4-
1.5 TEST AND INSPECTION

1.5.1 The extinguisher at ambient temperature shall expel at least 95% of its content as
continuous discharge with in a maximum of 90 seconds and minimum of 30 seconds.
1.5.2 The extinguisher without its attachment shall be shelved for 21 days after filling and
shall be check weighed at the end of the period. There shall be no loss of mass.
1.5.3 Carbon-dioxide cylinder shall be hydrostatically tested at a pressure of 236 kgf/cm
(g) to prove leak tightness for a period of one hour.
1.5.4 Hose assembly with its coupling shall be hydrostatically tested at a pressure of 315
kgf/cm (g) without failure.
4.5.5 All tests required to ensure that the equipment conforms to the Specification
requirements and relevant standards and codes shall be conducted by the
manufacturer. Adequate time ahead of these shop tests the Purchaser shall be
informed so that if he so desires, his representative may witness the tests.
1.5.5 A performance demonstration test at site on five (5) percent or one (1) number,
whichever is higher, shall be required to be carried out by the BIDDER. All
consumable and rechargeable items required for the test shall be supplied by the
BIDDER without any extra cost to Purchaser.

1.6 PERFORMANCE GUARANTEE


The BIDDER shall guarantee all equipment supplied by him against any defect due
to faulty design, materials and workmanship. The equipment shall be guaranteed to
operate satisfactorily at the rated conditions at site.

1.7 PAINTING & MARKING


Each extinguisher shall be painted in red and permanently marked in accordance
with the requirements laid down in IS-2878. besides permanently making on the front
of the extinguisher indicating its purpose, content and usage shall also be provided.

1.7.1 The mobile Carbon-dioxide type fire extinguisher shall be of make approved by Chief
Inspector of Explosives, Nagpur, India and Tariff Advisory
Committee/NFPA/FOC/UL.

2. VENTILATION SYSTEM
Mechanical ventilation systems using exhaust fans shall be provided for all the
rooms which are not considered for air conditioning. Capacity of the fan shall be
selected so as to have the minimum air changes in the various rooms as below:

Battery room, Pantry, toilets : 15 air


Changes/hr.
All other rooms : 12 air
Changes/hr.

For Battery room, the fan shall be bifurcated type spare proof construction.

-5-
SECTION – 6
CHAPTER – 7(I)

TECHNICAL SPECIFICATION FOR UNARMOURED


COPPER CONTROL CABLES

1.0 SCOPE
1.1 This specification provides for design, engineering, manufacture, stage testing,
inspection testing before dispatch, packing, forwarding and delivery at site of
unarmoured control cable.

1.2 It is not the intent to specify complete herein all details of the design and construction
of material. However, the material shall conform in all respects to high standards of
engineering, design and workmanship and shall be capable of performing in
continuous commercial operation up to the bidders guarantee acceptable to the
HVPNL. The material offered shall be complete in all components necessary for its
effective and trouble free operation. Such components shall be deemed to be within
the scope of supply irrespective of whether those are specially brought in this
Specification and or the commercial order or not. All similar parts particularly
movable ones shall be interchangeable.

2.0 STANDARDS
2.1 Copper control cable to be supplied shall be PVC insulated. PVC sheathed
unarmoured for indoor and outdoor applications in air, in ground, in water and in
concrete trenches. The control cable shall conform in all respects to the
requirements of IS-1554 (Part-I) 1988 and its subsequent amendments, if any at the
time of placement of order. All CT/PT circuits control cables are to be of size 4 mm2
copper cable. The incoming AC and DC supply cable to MKs/C&R Panels/CBs will
be of size 4 mm2 and 6mm2 copper and all other control cable will be of size 2.5 mm2
copper cable.
2.2 Control cables meeting with the requirement of other authoritative standard, which
ensure equal or better performance than the standards mentioned above, shall be
considered. When the equipment offered by the bidder adopted and the standards
specified in this Specification shall be clearly brought out in the relevant schedule.
Four copies of such standards with authentic translation in English shall be furnished
along with the offer.

2.3 PRINCIPAL PARAMETERS(TECHNICAL)


2.3.1 MATERIAL
All the material used in the manufacture of the cables shall be of the best available
quality with regard to strength, durability and shall also be manufactured according to
best engineering practices.

2.3.2 CONSTRUCTIONAL FEATURES


The insulated core shall be provided with inner sheath, unarmoured but provided
with an outer sheath as specified in IS-1554 (part-I) 1998 amended up to date. The
control cable offered shall be suitable for use in system up to 1100 volts. The
conductors shall be composed of plain annealed high conductivity copper which
before stranding shall be approximately circular in section, smooth, uniform in quality

-1-
and free from scale, in-equalities, spills, splits and other defects. The conductors
shall conform to appropriate dimensions and resistance as per IS-1554 (part-I) 1998.

3.0 GENERAL TECHNICAL PARTICULARS


3.1 INSULATION
The basic material employed as insulating compound shall consist of compounded
polyvinyl chloride (PVC) or suitable copolymers of which major constituent shall be
vinyl chloride or mixture of polyvinyl chloride and suitable copolymers which have
been suitably compounded and processed so as to comply with the requirements of
IS-1554 (part-I) 1988. The PVC compound going into the formation of insulation shall
also comply with the provisions of IS-5831-1970 “PVC insulation and sheath of
electric cable”. The insulation shall withstand the rigours of climate and site
conditions and shall not crack or retract in normal use. The colour code of the cores
of control cable shall be as per clause 10.1 of ISS-1554 (part-I) 1988. However, the
outer PVC sheath shall be black or grey. The colour coding as employed in the
formation of the cable for individual cores and sheath shall be indicated in the bid.
The PVC/Co-polymer compounds going into the formation of the outer sheathing
shall afford a high degree of mechanical protection besides being oil and weather
resistant.

3.2 MARKING
Every cable drum shall be clearly marked with inedible ink or with suitable weather
resistant paint and shall bear the following particulars: -
i) Manufacturer name and trade mark, if any.
ii) HVPNL Order No. and Date.
ii) Year of manufacture.
iii) Nominal sectional area of conductor of the cable.
iv) No. of cores.
v) Type of cable and voltage for which it is suitable.
vi) Length of cable on the drum.
vii) Weight of tare.
viii) Direction of rolling the drum.
ix) Gross weight of the drum.

4.0 TEST
4.1 TYPE TESTS

The copper control cables offered should be type tested. Type test report of similar
cables should not be more than seven years old, reckoned from the date of bid
opening in respect of the following tests, as per relevant ISS-1554/Part-I-1988 and
carried out in accordance with the procedure laid down in relevant
ISS/IEC/Internationally recognized equivalent standard from any accredited test
house/ Lab. For Indian manufacturers, the tests got conducted from Govt. test labs
shall also be acceptable. These type test reports shall be submitted by the
successful bidder to HVPNL for the approval as per schedule given in commercial
document.
i) Test on conductors
a) Annealing Test
b) Conductor Resistance Test
ii) Physical test for insulation and outer sheath.
a) Tensile strength and elongation at break.
b) Ageing in air oven.

-2-
c) Shrinkage test.
d) Hot deformation test.
e) Loss of mass in air oven.
f) Heat shock test.
g) Thermal stability.
iii) Test for Thickness of Insulation and Sheath.
iv) Insulation resistance test.
v) High voltage test (Water immersion test).
vi) High voltage test at room temperature.
vii) Flammability test.

4.2 ROUTINE TESTS :

As per quality assurance program (QAP).

4.3 ACCEPTANCE TESTS:


The following acceptance tests as stipulated in the relevant ISS-1554 (Part-I) shall
be carried out by the Bidder in presence of HVPNL representative, unless dispensed
with in writing by the HVPNL.
i) Annealing Test (for copper)
ii) Conductor Resistance test.
iii) Test for Thickness of Insulation and Sheath.
iv) Tensile strength and elongation at break of insulation and sheath.
v) Insulation resistance test.
vi) High Voltage test at room temperature.

-3-
SECTION – 6
CHAPTER – 8(II)

TECHNICAL SPECIFICATION FOR ARMORED


COPPER CONTROL CABLES

1.0 SCOPE

1.1 This specification provides for design, engineering, manufacture, stage testing,
inspection testing before dispatch, packing, forwarding and delivery F.O.R.
destination of armored control cable.

1.2 It is not the intent to specify complete herein all details of the design and construction
of material. However, the material shall conform in all respects to high standards of
engineering, design and workmanship and shall be capable of performing in
continuous commercial operation up to the bidders guarantee acceptable to the
HVPNL. The material offered shall be complete in all components necessary for its
effective and trouble free operation. Such components shall be deemed to be within
the scope of supply irrespective of whether those are specially brought in this
Specification and or the commercial order or not. All similar parts particularly
movable ones shall be interchangeable.

2.0 STANDARDS

2.1 Copper control cable to be supplied shall be PVC insulated. PVC sheathed
unarmoured for indoor and outdoor applications in air, in ground, in water and in
concrete trenches. The control cable shall conform in all respects to the
requirements of IS-1554 (Part-I) 1988 and its subsequent amendments, if any at the
time of placement of order. All CT/PT circuits control cables are to be of size 4 mm2
copper cable. The incoming AC and DC supply cable to MKs/C&R Panels/CBs will
be of size 4 mm2 and 6 mm2 copper and all other control cable will be of size 2.5
mm2 copper cable.

2.2 Control cables meeting with the requirement of other authoritative standard, which
ensure equal or better performance than the standards mentioned above, shall be
considered. When the equipment offered by the bidder adopted and the standards
specified in this Specification shall be clearly brought out in the relevant schedule.
Four copies of such standards with authentic translation in English shall be furnished
along with the offer.

3.0 PRINCIPAL PARAMETERS (TECHNICAL)

3.1 ARMOURING
The insulated core shall be provided with inner sheath, Armouring and outer sheath
as specified in IS-1554 (part-I) 1988 amended up to date. The control cable offered
shall be suitable for use in system up to 1100 volts.

The conductors shall be composed of plain annealed high conductivity copper which
before stranding shall be approximately circular in section, smooth, uniform in quality
and free from scale in-equalities, spills and other defects. The conductors shall
conform to appropriate dimensions and resistance as per IS-1554 (part-I) 1988. the

-4-
Armouring shall be arranged over the inner sheath and shall consist of galvanised
round steel wires, where the specified nominal diameter over the insulation of inner
sheath does not exceed 13mm. The armor of cable having a specified nominal dia
greater than 13mm shall consist of either galvanised round steel wires/strips shall
conform to IS-1554 (part-I) 1988. the steel wires and strips used for Armouring shall
conform to IS-3975-1967. The direction of lay of armor shall be opposite to that of
outer layer of cores.

3.2 MATERIAL
All the material used in the manufacture of the cables shall be of the best available
quality with regard to strength, durability and shall also be manufactured according to
best engineering practices.

4.0 GENERAL TECHNICAL PARTICULARS

4.1 INSULATION
The basic material employed as insulating compound shall consist of compounded
polyvinyl chloride (PVC) or suitable copolymers of which major constituent shall be
vinyl chloride or mixture of polyvinyl chloride and suitable copolymers which have
been suitably compounded and processed so as to comply with the requirements of
IS-1554 (part-I) 1988. The PVC compound going into the formation of insulation shall
also comply with the provisions of IS-5831-1970 “PVC insulation and sheath of
electric cable”. The insulation shall withstand the rigours of climate and site
conditions and shall not crack or retract in normal use. The colour code of the cores
of control cable shall be as per clause 10.1 of ISS-1554 (part-I) 1988. However, the
outer PVC sheath shall be black or grey. The colour coding as employed in the
formation of the cable for individual cores and sheath shall be indicated in the bid.
The PVC/Co-polymer compounds going into the formation of the outer sheathing
shall afford a high degree of mechanical protection besides being oil and weather
resistant.

4.2 MARKING
Every cable drum shall be clearly marked with indelible ink or with suitable weather
resistant paint and shall bear the following particulars: -
j) Manufacturer name and trade mark, if any.
ii) HVPNL Order No. and Date.
iii) Year of manufacture.
iv) Nominal sectional area of conductor of the cable.
v) No. of cores.
vi) Type of cable and voltage for which it is suitable.
vii) Length of cable on the drum.
viii) Weight of tare.
ix) Direction of rolling the drum.

5.0 TEST
5.1 TYPE TESTS
The copper control cables offered should be type tested. Type test report of similar
cables should not be more than seven years old, reckoned from the date of bid
opening in respect of the following tests, as per relevant ISS-1554/Part-I-1988 and
carried out in accordance with the procedure laid down in relevant
ISS/IEC/Internationally recognized equivalent standard from any accredited test

-5-
house/ Lab. For Indian manufacturers, the tests got conducted from Govt. test labs
shall also be acceptable. These type test reports shall be submitted by the
successful bidder to HVPNL for the approval as per schedule given in commercial
document.
i) Test on conductors
a. Annealing Test
b. Conductor Resistance Test
ii) Physical test for insulation and outer sheath.
a. Tensile strength and elongation at break.
b. Ageing in air oven.
c. Shrinkage test.
d. Hot deformation test.
e. Loss of mass in air oven.
f. Heat shock test.
g. Thermal stability.
iii) Test for Thickness of Insulation and Sheath.
iv) Insulation resistance test.
v) High voltage test (Water immersion test).
vi) High voltage test at room temperature.
vii) Flammability test.
viii) Test for armouring wires/strips

5.2 ROUTINE TESTS :

As per quality assurance program (QAP).

5.3 ACCEPTANCE TESTS:


The following acceptance tests as stipulated in the relevant ISS-1554 (Part-I) shall
be carried out by the Bidder in presence of HVPNL representative, unless dispensed
with in writing by the HVPNL.
i) Annealing Test (for copper)
ii) Conductor Resistance test.
iii) Test for Thickness of Insulation and Sheath.
iv) Tensile strength and elongation at break of insulation and sheath.
v) Insulation resistance test.
vi) High Voltage test at room temperature.

-6-
Section-6
Chapter-8
TECHNICAL SPECIFICATION FOR 11 kV CROSS LINKED ETHYLENE
INSULATED PVC SHEATHED SINGLE CORE AND THREE CORE POWER
CABLES

1. SCOPE
This specification covers the design, manufacture, testing, inspection at
manufacturer’s work, supply & delivery F.O.R. destination of 630mm2 Single
Core XLPE insulated PVC sheathed Cable and three core XLPE cable suitable
for solidly grounded system size as per clause(5) mentioned below.

2. PARTICULARS OF THE SYSTEM


The cable should be suitable for use on 50 Cycles, 3 Phases solidly earth
neutral system & working voltage of 11kV.

3. STANDARDS
The cable covered under this Specification shall conform in all respects with
the latest editions of IS-7098 (Part-2) 1985 & IS-8130-1984 & IEC:502 of the
latest version thereof.

4. TECHNICAL PARTICULARS
11kV, Single Core under ground XLPE insulated PVC sheathed cable suitable
for working potential of 11kV on earthed system manufactured in accordance
with IS-7098 (Part-2) 1985 with latest amendments. The Aluminium conductor
shall comply with requirements specified in IS:8130-1984. The insulation shall
be chemically cross-linked polyethylene confirming to the physical, electrical
and ageing property as required in latest edition of IS-7098 (Part-2) 1985.
Cable shall be provided with both conductor screening and insulation
screening. The conductor screening shall be non-metallic and shall be
consisting of either semi-conducting tape or a layer of semi-conducting
compound or combination of two. The insulation screening shall consist of non-
metallic semi conducting tape of extruded semi conducting compound layer in
combination with non-magnetic metallic shield. Armouring shall be arranged
over the core and it shall be of non-magnetic material. The material for the
Armouring shall be as per relevant ISS. Over the Armouring the cable shall be
provided with extruded PVC outer sheath. The composition of PVC compound
shall be type ST-2 of iS-5831-1984. The colour of outer sheath shall be black
or grey.

5. SIZE
The different size of the cable shall be: -
a) Single Core 630mm2 .
b) Three Core 300mm2.
c) Three Core 185mm2.
d) Three Core 50mm2.

6. TESTS
6.1 Type Tests
The equipment should be offered type test. Test reports should not more then
seven years old reckoned from date of bid opening in respect of all the tests
carried out in accredited laboratories (based on ISO/IEC) by a reputed
accreditatic body or witnessed by HVPN or another electric power utility and be
-1-
submitted by the successful bidder to HVPNL for approval as schedule given in
Bar Chart.
i) Physical tests for insulation and outer sheath.
ii) Bending test.
iii) Di-electrical power factor test.
iv) Heating cycle test followed by di-electrical power factor as a function of
voltage and partial discharge test.
v) Impulse withstand test.

The remaining type test report as per clause 3 of ISS-7098/IEC-871 shall be


submitted by the successful bidder within three months from the date of
placement of order. These type test reports shall be from Govt./Govt. approved
test house OR from reputed Lab Abroad and shall not be more than seven
years old, reckoned from the date of placement of order. The failure to do so
will be considered as a breach of contract.

6.2 ROUTINE TESTS AND ACCEPTANCE TESTS


All routine and acceptance tests shall be carried as per relevant ISS in the
presence of Nigam’s representative.

7. INSPECTION
The material shall be inspected and tested before dispatch by an authorised
representative of the Nigam in respect of quality.
The inspecting officer shall also satisfy himself about the correctness of length
of cables as provided in Instruction No. 208 of E.B. Manual of Instruction 1963
Edition amended vide O/O No. G/BD-33(57) 75 dt. 18.04.75 now HVPNL. In
case the Bidder is not in a position to get these tests carried out at his works,
such tests may be got carried out by him at any Govt. recognized test agency
OR from reputed Lab Abroad at his own expense.

8. TEST CERTIFICATES
The Bidder shall supply test certificates from a Govt. agency OR from reputed
Lab Abroad in respect of quality as per IS:7098(part-II) 1985 with latest
amendments thereof for approval of the HVPNL.

9. PACKING
The cable shall be supplied in non-returnable wooden drum as per
IS:10418:1982 so constructed, as to enable the cable to be transported on
each drum. The cable wound on such drum shall be one continuous length.
The ends of cables shall be sealed by means of non-hygroscopic sealing
material.

10. MARKING
The marking on the drum shall have the following information: -

a) Reference to Indian Standard & cable code.


b) Name of the manufacturer & trade name.
c) Nominal cross section area of conductor for the cables.
d) Number of core.
e) Sequential No. at each meter.
f) Type of the cable & voltage for which it is suitable.
g) Length of cable on the drum.
h) Approximate gross weight.
i) Net weight of the cable.
j) Drum identification number.
-2-
k) P.O. No. and date.
l) Consignee’s name with designation.
m) Year of manufacture.

Note: Cable should be marked with ISI Certification mark.

11. DRAWINGS & INSTRUCTION MANUAL


The tenderer shall supply the following drawings with the tender: -

i) Detailed drawing of the cable showing conductor, screening insulation,


Armouring, outer sheath etc.
ii) Detailed drawing showing jointing of cable and sealing of end boxes.

Copies of instruction manuals for testing, installation jointing operation and


maintenance of cables, shall also be submitted with the offer for reference of
the HVPNL.

-3-
SECTION-6
CHAPTER-9

TECHNICAL SPECIFICATIONS FOR OUTDOOR NON SEALED TYPE THREE PHASE 11 KV/433V
DISTRIBUTION TRANSFORMERS OF 200 KVA CAPACITIES

1.0 SCOPE:

This specification covers the design, engineering, manufacture, shop testing, supply & delivery
of oil immersed, naturally cooled, three-phase, 50 Hz, double-would, outdoor type Distribution
transformers of 200KVA, capacity for use on systems with nominal voltages of 11 KV. Any
other parts not specifically mentioned in this specification, but otherwise required for proper
functioning of the equipment should be included by the tenderer in his offer.

Transformers will be plinth mounted

2.0 STANDARDS:
The transformers shall conform in all respect to IS: 1180-1981 & IS: 2026-1977 except where
specified otherwise. Equipment meeting any other authoritative Standards which ensures an
equal or better quality than the standards mentioned above will also be acceptable. In such
cases the copy of standards (English Version) adopted should be enclosed with the tender.

3.0 CLIMATIC CONDITIONS:


As per Vol-II Section-1.

4.0 PRINCIPAL PARAMETERS OF THE TRANSFORMER

The transformer shall be suitable for outdoor service as step down transformer. The electrical
parameters of the transformer shall be as follows:-

1) Rated HV voltage 11 KV

2) Rated LV voltage 433 volts

3) Connection (HV) Delta

4) Connection (LV) Star neutral brought out

5) Vector Group Dyn11

6) Material of winding For 200 KVA Aluminium,


double wound type

7) Type of cooling ONAN

8) Max. current density in


HV & LV Winding

a) For aluminium wound 200 KVA T/F 1.5A/mm2

9) Method of system earthing Neutral solidly earthed system

5.0 NO-LOAD VOLTAGE RATIO


The no-load voltage ratio shall be 11000/433V.

6.0 TEMPERATURE RISE


-1-
The transformer shall be capable of operating continuously at its normal rating without
exceeding the temperature rise limit. The temperature rise shall not exceed the limits of 500C
(measured by resistance) for transformer windings and 400C (measured by thermometer) in
top oil above the ambient temperature when tested in accordance with IS. The transformer
with higher temperature rise shall not be acceptable. Hot spot temperature shall not exceed
950C when calculated on an annual weighted average temperature of 350C as per IS:2026.
6.1 The limits of temperature rise mentioned above will have to be satisfied by the manufacturer by
carrying the Heat run test at the lowest negative tap by feeding losses corresponding to the
rated current of the tap.
7.0 LOSSES

The no load and load losses for 11/0.433 KV shall not exceed the values given in the following
table.
KVA Rating No load losses in Watts (Max.) Full load losses in Watts
(Max) At 75Deg.C.
200 400 3135

These losses are maximum allowable and there would not be any positive tolerance However,
the manufacturer can offer losses less than above.

The Bidder shall quote No-Load loss in KW at the rated voltage and frequency. The load loss
in KW at rated voltage, frequency & out put, for the temperature 75 degree centigrade shall
also be quoted. The Bidder shall guarantee these loss figures.

7.1 Noise level : 80 dB

Transformer offers shall be rejected if audible sound level is higher than the values
required by the owner.

8.0 IMPEDANCE:
The recommended percentage impedance at 750C is 4.5% for 200KVA T/F with a tolerance
as per IS:2026.

9.0 WINDING
9.1 The primary (HV) windings shall be connected in Delta and the secondary (LV) winding in Star
(Vector system DYn11) so as to produce a positive displacement of 30 degree from the
primary to secondary vectors of the same phase. The neutral of secondary windings shall be
brought out to a separate insulated neutral terminal. The neutral is to be solidly earthed in a
separate earth pit and the transformer body is to be connected to station grounding system.

HV windings shall consist of single coil design. The copper wires for coil formation shall be of
sufficient cross-sectional area to impart desired mechanical strength. All delta leads from HT
coils as well as HT line leads should be taken out through DPC. The current density in these
leads should not exceed 0.8A/sq.mm.

9.2 The winding shall be so designed as to produce minimum out of balance forces in the
transformers. Transformers of 200 KVA shall be aluminium wound and sizes above 200 KVA
shall be copper wound. The current density for aluminium wound transformer shall be limited
to 1.5A/mm sq. and for copper wound transformer shall be limited to 2.6A/mm.sq.

9.3 The winding design shall ensure that all the coil assemblies are of identical voltage ratio and
shall be interchangeable and repairing of the winding could be made easily without special
equipment.

-2-
9.4 The conductor used in the coil shall be best suitable to the equipment and all the permanent
current carrying joints in the winding and leads shall be properly sleeved and crimped/brazed
instead of jointing with solder or welding. All LV coils ends shall be provided with
brazed/crimped lugs and HV coil ends by brazing/crimping.

9.5 Double paper covering shall be used for winding insulation both for HV & LV windings.
Electrical grade epoxy coated insulated paper shall be used for inter-layer insulation of the HV
& LV coils, corrugated cylinder made of pre-compressed board shall be provided between HV
& LV winding. Angle shaped and rings made from pre-compressed board shall be used
between end coil and the core.

OR

For 200 KVA transformers DPC insulation shall be used, Electrical Grade Insulation Kraft
paper in layers of total thickness not less than 4 mm shall be used for interlayer insulation,
DPC and Kraft paper used shall be of uniform density and free from any foreign particles and
shall conform to IS:698/56 and latest amendments thereof. The end turn of each layer shall be
properly and fully covered to avoid interlayer flashover. Corrugated Cylinder made from pre-
compressed insulation board should preferably be used between LV and HV windings. The
insulation of coils shall be vacuum impregnated in oil to develop full electrical strength in the
windings. All material used in the insulation and assembly of the winding shall be insoluble non
catalytic and chemically inactive in the hot transformer oil and shall not soften or otherwise be
adversely effected under operating conditions.

The core and coil assembly shall be fully dried out in ‘Air Drying Oven’ till the coils are
shrunken to the designed level and are completely dried. Only then they will be impregnated in
the transformer oil.

9.6 Minimum gap of 25 mm shall be maintained between the end coils and core.

9.7 The overloading capacity of transformer shall be as per IS-6600.

9.8 The value of unbalance current shall not be more than 2% of the full load current.

10.0 CORE CONSTRUCTION

10.1 The core shall be constructed from high grade, non-aging Cold Rolled Grain Oriented (CRGO)
silicon steel laminations conforming to grade M4 or better. The maximum flux density in any
part of the cores and yoke at normal voltage and frequency shall be such that the flux density
with + 12.5% voltage variation from rated voltage or frequency variation of -5% shall not
exceed 1.6 Tesla. The bidder shall provide saturation curve of the core material proposed to
be used.

10.2 The design of magnetic circuit shall be such as to avoid static discharge development of short
circuit within itself or in the earthed clamping structure.

10.3 Each lamination shall be insulated such that it will not deteriorate due to mechanical pressure
and the action of hot transformer oil.

10.4 a) Core material shall be directly procured either from the manufacturer or through their
accredited marketing organization of repute and not through any agent.

10.4 b) All parts of the core shall be of robust design, capable of withstanding any shock to
which they may be subjected during handling, lifting, transportation, installation and
service including short circuit condition. Clamping of core and winding assembly with
tank should be done by angle iron pieces, bolted to tank wall.

-3-
10.4 c) Adequate arrangement shall be provided to enable the core and winding be lifted by
lifting lugs.

Use of seconds CRGO steel for core construction is strictly prohibited.

Bidder can –offer transformer made of other superior (Low, Loss) for material and they
should furnish design details in their bid. Successful bidders should submit require type
test certificates after issue of P.O. but before material offered for inspection.

“The core material should be imported directly from the reputed manufacturer. Core
material shall be processed by slitting only. Core cutting/slitting be done in front of
inspecting officers deputed by HVPN.”

11.0 TANK CONSTRUCTION

11.1 The tank shall be of robust construction in accordance with the best engineering
practice. The main tank of the transformer shall be fabricated from tested quality of
mild steel of adequate thickness i.e. minimum 4.00 mm. (for side walls) and 6.00mm
(for top & bottom plates). The tank shall be valid (V shape welding fillet) inside of tank
two outside welding of tank to bear more pressure to avoid bursting.

11.2 To provide rigidity and to meet the pressure inside the tank, due to short circuit current,
the tank shall be suitably stiffened. The stiffeners wherever applicable are provided on
all the four side walls of the tank, designed not to retain water.

11.3 The tank cover shall be slightly sloping towards HV bushing and shall provide facilities
for draining of water.

11.4 The transformer tank shall be complete with al accessories, lifting lugs and shall be
designed as to allow the complete transformer tank, filled with oil to be lifted by crane
or other means without risk of any damage and transported by Rail/Road without
straining any joint and without causing leakage of oil.

11.5 Bolted inspection covers shall be provide on tank and top cover to inspect core,
winding and have access to the bottom of bushing.

11.6 The tank shall be capable of with standing the pressure of +/- 1 kg/cm2 without
deformation.

The permanent deflection of plate after pressure has been released shall not exceed
the values given below:

LENGTH OF PLATE DEFLECTION

750 mm 5 mm

751-1250 mm 6 mm

12.0 FINISH

The exterior of the transformer tank and other ferrous fittings shall be thoroughly
cleaned, scraped and given a priming coat and two finishing coats of durable oil and
weather resisting paints or enamel. The colour of the finishing coats shall be dark
admiralty grey conforming to No. 632 of IS:5-1961 “Colours for Ready Mixed Paints
(second revision)”.

-4-
13.0 CLEARANCES

The external electrical clearance between phase to phase and phase to earth shall be
in accordance with Clause 7.1 of IS: 2099 shall not be less than the values given
below:-
Voltage Medium Clearance Phase to Clearance Phase to
Phase (mm) earth (mm)
11 KV Air 255 205

433V Air 75 55

The aforesaid clearances are minimum and no negative tolerance on these clearances
shall be allowed.

14.0 BUSHINGS

14.1 Terminal arrangement: The transformer shall be fitted with three high voltages and
four low voltage outdoor types porcelain bushing of appropriate voltage and current
rating. Each terminal including the neutral shall be distinctly marked and coloured for
phase voltage on both HV and LV sides. The system of marking shall be in accordance
with the latest amendment of relevant IS.
14.2 The electrical characteristics of high voltage bushing shall conform to latest version of
IS: 2099 and IS: 3347. The low voltage bushing shall conform to latest version of IS:
7421. All porcelain bushing shall be homogeneous, free from flaws effecting its
mechanical strength or dielectric quality. They should be well vitrified, uniformly glazed,
tough and impervious to moisture. The creepage distance of all the bushing shall be
25mm per KV of highest system voltage suitable for heavily polluted atmosphere and
the protected creepage distance not less than 50% of total.

14.3 Bushing terminals: To avoid bimetallic action at the point of connection to the copper
windings and to the external aluminium cables/conductors, both- HV & LV bushing
stems shall be made of aluminium alloy/copper confirming to the requirement of
IS:3347.
14.4 The terminal connectors shall receive ACSR on HT side. The terminals shall be directly
screwed on to the stem to secure effective sealing the bushing. The transformers shall
be provided with bimetallic connectors bushings both on HV & LV Side.

15.0 FITTINGS AND ACCESSORIES

15.1 The transformer shall be fitted with the following fittings & accessories.

(a) Two earthing terminals

(b) Oil level indicator

(c) Lifting lugs and platform lugs

(d) Rating, diagram and terminal marking plate(s)

(e) Silica gel breather of approved design containing min. 0.25kg dehydrated silica get

(f) Drain-cum-Sampling valve (steel) welded to the tank.

(g) Thermometer pocket with dial type thermometer on tank cover.

(h) Air Release Plug

(i) Pressure relief device in the form of explosion release vent.


-5-
(j) Filling hole having P1-1/4 thread (with cover) on the conservator.

(k) Filter valve-2 nos. on top and bottom ends of tank at opposite sides.

(l) Conservator with filling hole and drain plug.

(m) Porcelain bushings with arcing horns and terminal connectors on HV side.

(n) Porcelain bushings on LV side and HV side conforming to IS-3347, part-1 and III of the
latest version thereof with brass studs fitted with single gap arcing horns.

(o) Off load tap changer (for above 200 KVA transformers with tapping range of +3% to -
6% in steps of 3% each with a locking device.

(p) Bimetallic terminal connector for HV/LV Bushings connecting to ACSR.

(q) PSR Radiators duly tested for leakage and pressure.

(r) Plain rollers ( 4 nos. bi-directional) suitable for use on 1000 mm gauge track with
clamping device or base mounting arrangement as required.

Note: (i) The fittings listed above are indicative and any other fittings which are
generally required for satisfactory operation of the transformer are
deemed to be included in the quoted price of the transformer.

16.0 CONSERVATOR

16.1 A conservator shall be provided with each transformer.


The oil level gauge and the plain silica gel breathing device shall be fixed to the
conservator which shall also be provided with a drain plug and a filling hole with a
cover .In addition, the cover of the main tank shall be provided with an air release plug
to enable trapped air to be released unless the conservator is so located as to
eliminate the possibility of air being trapped in the main tank.

16.2 The inside diameter of the pipe connecting the conservator to the main tank shall be
within 20 to 50 mm and it should project into the conservator in such a way that its end
is approximately 20 mm above the bottom of the conservator, so as to create a sump
for collection of impurities. The minimum oil level (corresponding to -50C) should be
above the sump level. Breather pipe should be connected at top of the conservator
tank with two bends at right angles.

17.0 SEALING GASKETS


All sealing washers and gaskets shall be made of oil and heat resistant
Nitrile/Neoprene rubber/synthetic rubber bonded cork type RC-70C Gaskets.
The oil level in the transformer shall be made up to the required level while the
transformer filled with oil is maintained at a temperature of 450C.
All steel screws, nuts and fasteners exposed to atmosphere shall be either galvanized
or cadmium plated.

18.0 TRANSFORMER OIL


The transformer shall be supplied complete with first filling of oil. The insulating oil shall
comply with the requirements of IS:335/1983 with latest version thereof. Oil shall be
filled under vacuum with a vacuum type filtering machine.

19.0 BASE MOUNTING ARRANGEMENT


The under base of all transformers shall be provided to make them suitable for fixing
mounting on plinth.
-6-
20.0 RATING AND TERMINAL MARKING PLATES(S)
Each transformer shall be provided with non-detachable rating diagram and terminal
marking plate(s) of weather proof material, fitted in a visible position and showing the
complete information as given under clause 16 of IS:1980 (Part-I)-1981or any
authoritative standards for transformers including the following details:-
i) HVPNL order no. & Date
ii) Date of inspection
iii) Property of HVPN.
21.0 RADIATORS

These shall be made of ERW tubes with minimum side thickness of 18 SWG. These
tubes should be used in vertic formation without any bending and properly welded on
both ends to common headers. These radiators should be individually test for leakage
and pressure tests etc. before welding with the main tank.

22.0 TESTS AND INSPECTION


All the tests shall be carried out in accordance with clause 16 of IS (Part-I) 1977

22.1 ROUTINE TESTS:


All transformers shall be subjected to the following routine tests at the manufacturer’s
works in accordance with IS 2026 and 1180 (Part-I): -

a) Measurement of winding resistance.


b) Ratio, Polarity and phase relationship.
c) Measurement of Impedance voltage/short circuit impedance.
d) Load losses.
e) No load losses and no load current.
f) Insulation resistance.
g) Induced over voltage withstand.
h) Separate source voltage withstand.
i) Oil leakage test.
j) Magnetic balance test and magnetizing current and low voltage.

22.2 TYPE TESTS


The following type tests shall be made on the transformers in addition to the
routine tests from (a) to (f) as indicated in 22.1 above: -

i) Temperature rise test shall be carried out on one unit from each lot as
offered for inspection.

ii) Air pressure tests: The tank shall be fixed with a dummy cover with all
fittings including bushings in position and shall be subjected to the following pressure
created inside the tank:

a) 0.8 kg/cm2 above the atmospheric pressure for 10 minutes.

b) A vacuum corresponding to (-) 0.7 kg/cm2 for 10 minutes. Permanent deflection of flat
plate after pressure has been released, shall not exceed the value given below: -

LENGTH OF PLATE DEFLECTION

Upto 750 mm 5 mm

751-1250 mm 6 mm

i) Impulse voltage withstand test on all the three limbs of HT side as per clause 13 of ISS
2026/1991/Part-II conducted at some recognized/Govt. Test house not more than 7
-7-
years old from the date of bid opening shall required to be submitted. The dispatches
shall only be allowed after successful conductance of this test.
ii) SHORT CIRCUIT TEST: This test shall be made in accordance with the details
specified in IS 2026/1977 conducted at some recognized/Govt. Test house OR from
reputed Lab Abroad not more than 7 years old from the date of bid opening shall
required to be submitted. The dispatches shall only be allowed after successful
conductance of this test. If short circuit tests on unit of similar design of transformer
with capacity as per schedule had been conducted earlier than certificate shall be
produced along with tender and the test need not be conducted.
iii) Unbalance Current Test: The value of unbalanced current indicated by the ammeter
shall not be more than 2% of the full load current.

No supplies will be allowed to be despatched without inspection by the HVPNL/its


representative and without carrying out the impulse and short circuit tests satisfactorily.

22.3 FLUX DENSITY TEST:


The Bidder shall arrange to conduct the flux density test on one of the cores of the
transformers in each lot so as to ensure that the flux density does not exceed the
maximum specified limit of 1.6 Tesla at normal voltage & frequency.

22.4 OIL TEST


At least two samples of oil shall be drawn out of any two sizeable lots from total
ordered quantity to ensure that the oil used complies with the requirements of the
Specification as per ISS-335. However, inspecting officer can draw oil samples from
any number of lots if considered necessary so as to ensure that transformer oil
conforming to ISS is being used. The despatches for such lots shall be allowed only
after receipt of satisfactory oil test results.

22.5 OIL LEAKAGE TEST:


The air pressure tests provided as a routine test shall be carried out on 10% of the
transformers in each lot. The firm shall ensure to get this test carried out strictly as per
relevant ISS.

22.6 PHYSICAL CHECK ON VARIOUS DIMENSIONS (INTERNAL & EXTERNAL


WEIGHT CLEARANCE ETC.)
One No. transformer from each lot shall be opened for checking of core weight, size
and weight of HT & LT conductor, quantity of oil and various clearances etc.

22.7 INSPECTION
The inspection shall be carried out by an outside inspection agency to be nominated by
the Nigam’s representative. All tests & inspection shall be made at the place of
manufacturer unless otherwise specifically agrees upon between the manufacturer and
the HVPNL at the time of placing the order. The manufacturer shall afford the inspector
representing the HVPNL all reasonable facilities, without charge, to satisfy himself that
the material is being furnished in accordance with this Specification.

22.8 The HVPNL has the right to have the tests carried out at its own cost by an
independent agency whenever there is any dispute regarding the quality of supply. If
the transformer fails in the tests, the cost shall be borne by the Bidder and if it passes,
the cost shall be borne by the Nigam.

23.0 INSULATION RESISTANCE OF WINDINGS:


The minimum insulation resistance values in Mega ohms between winding and earth
when the transformer is filled with oil should be as below: -

-8-
INSULATED RESISTANCE VALUES IN MEGA OHMS BETWEEN WINDING AND EARTH

200C 300C 400C 500C 600C


11000 Volt(HV) 800 400 200 100 50
433 Voltage(LV) 400 200 100 50 25

The insulation resistance values will be measured with a 2500V, preferably motorized meggar
and of some good standard manufacturer such as M/s Evershed & Vignole make.

24.0 TEST VOLTAGE


Transformers shall be capable of withstanding the power frequency and impulse test
voltages prescribed as below: -

NOMINAL SYSTEM HIGHEST SYSTEM IMPULSE POWER


VOLTAGE VOLTAGE TEST FREQUENCY
VOLTAGE TEST VOLTAGE
11KV (rms) 12KV (rms) 75KV (peak) 28KV (rms)

25.0 TOLERANCE OF ELECTRICAL PERFORMANCE


Tolerance shall be according to clause 11 of IS:2026 (part-I/General:1977).

26.0 DRAWING AND LITERATURE


The successful bidder shall submit the equipment drawing(s) in quadruplicate, to the
CE/P&D, HVPNL, Panchkula for his approval. Such drawing(s) will be
commented/approved by HVPNL within four weeks of their receipt. The successful
bidder will re-submit such drawing(s) duly reflecting the HVPNL’s comments within 2
weeks of their receipt, which will be approved by the HVPNL within 2 weeks. The
successful bidder shall supply 6 copies each of approved drg. and descriptive
literature containing handling, erection & maintenance instructions to the CE/P&D,
HVPNL, Panchkula for distribution amongst field organisation. Reproducible(s) of the
approved drawing(s) will also be supply by the successful bidder. Also, a copy of each
of the drawing(s) & descriptive literature will accompany the equipment for use by the
stores/field offices drawing it for application on Nigam’s power system.

27.0 PACKING
Transformers shall be delivered suitably packed. Although the method of packing is left
to the discretion of the manufacturer, it should be robust enough for rough handling,
that is occasioned during transportation by rail/road.

28.0 GUARANTEED DATA


Guaranteed Technical particulars and other Technical data in respect of
equipment/material offered shall be furnished duly signed along with the tender in the
Performa attached as Vol-III. Any other particulars considered necessary may also be
given in addition to those listed in the schedule.

-9-
SECTION-6
CHAPTER – 10

TECHNICAL SPECIFICATION FOR LT TWO CORE, 3½ CORE AND FOUR CORE


PVC INSULATED UNARMOURED CABLE OFF SIZES FOR WORKING VOLTAGE
UPTO & INCLUDING 1100 V, FOR SERVICE CONNECTIONS.

1. SCOPE:- This specification provides for design, manufacture, inspection at


manufacturer’s works, testing before dispatch, supply and delivery of unarmoured 2
core, 3½ core and 4 core PVC sheathed Aluminium conductor cables for voltage upto
1.1 kV.

2. STANDARD:- LT distribution unarmoured cables shall be suitable for service voltage of


1100 volts (640 volts to earth) and made from high conductivity Aluminium conductor
insulated with PVC compound and having inner and outer sheathing of PVC compound.
The cables shall be strictly in conformity with ISS-1554/Part-I/1988 with latest
amendments/ edition if any and shall be ISI/ IEC marked. The inner and outer sheathing
shall be carried out as per relevant ISS. However, material manufactured as per any
other International Standard which offers equivalent or materials better in quality and
workmanship as compared to mentioned standards shall also be acceptable. Aluminium
conductor complying with IS:8130-1984 shall be used.

3. CLIMATIC CONDITIONS:- The cable shall work satisfactorily under the following
climatic conditions:-

i) Maximum ambient temperature 50oC


ii) Minimum ambient temperature -2.5oC
iii) Maximum relative humidity 100%
iv) Minimum relative humidity 26%
v) Altitude Below 1000 meters above mean
sea level.
vi) Average no. of Rainy days per annum. 120
vii) Average annual Rain fall. 900 mm
viii) Maximum wind pressure 195 Kg/ meter2

4 TECHNICAL PARTICULARS:- The cable shall be suitable for use on 50 Hz three phase
AC solidly earthed Neutral power system working voltage of 3 x 240/ 415 Volt.

4.1 Sheathing:-
a) 4 Core Cables:- The Bidder has the option to provide inner and outer sheathing
of PVC compound by single or separate pressure extrusion process as per
relevant ISS.
b) 3 ½ Core Cables.
c) 2 core cable.

-1-
i) Inner and outer sheathing shall be provided by separate operation process only.
ii) Where inner and outer sheathing are to be provided with PVC compound (by
separate operation) the sheathing are to be provided by pressure extrusion
process.
iii) Where inner sheathing is to be provided with thermo plastic material or proofed
tape which shall not be harder than PVC used for insulating and outer sheathing
shall be provided with pressure extrusion process.

Note:- Cable with sheathing by sleeves extrusion shall not be accepted.

5. SIZES:- The normal sizes of the cables shall be as per schedule of requirements as per
requirement.

6. TESTS:-

6.1 TYPE TESTS:-


The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed
by HVPN or another electric power utility and be submitted by the successful bidder to
HVPNL for approval as schedule given in Bar Chart.
i) Tensile Test
ii) Wrapping Test
iv) Annealing Test
v) Resistance Test

6.2 ROUTINE TEST


As per quality assurance program (QAP)

6.3 ACCEPTANCE TEST:- The following acceptance tests as stipulated in the relevant IS-
8130:1984 shall be carried out by the Supplier in presence of HVPNL representative,
unless dispensed with in writing by the HVPNL.

a) Tensile test.
b) Wrapping test.
c) Resistance test.
d) Annealing test.

7. MANUFACTURER IDENTIFICATION:- HVPNL alongwith brand name, manufacturer


name, voltage rating, size and year of manufacture in English shall be embossed on the
outer sheath of the cable at regular intervals of approximately 1 to 1.5 metre.

8. INSPECTION AND TEST:- An authorised representative of the HVPNL shall inspect,


examine and test the equipment/ material in respect of quality, size and ratings as per
ISS/ IEC mentioned above at the manufacturer’s works during or after the manufacture
of goods prior to dispatch on receipt of a clear notice of minimum two weeks in advance
to be reckoned from the date of receipt of the same by the HVPNL. No material will be
allowed to be dispatched without prior inspection and approval. The inspecting officer of
the HVPNL may also inspect the material during the course of manufacture. In case,
inspection of any consignment is waived off by the HVPNL, the Bidder will be required to

-2-
furnish the requisite test certificates (for acceptance as well as routine tests) for
approval. It will be the responsibility of the Bidder to make adequate arrangements for
testing of material at their works without any additional charge to the HVPNL. All testing
instruments and appliances will be made available and material destroyed/ consumed
during testing will be to the account of the Bidder.

8.1 SAMPLING OF CABLES:-


a) Scale of sampling:- Samples shall be taken and tested from each lot for
ascertaining the conformity of the lot to the required specifications.

b) The number of samples to be selected as per table given below at random (the
randomness of selection, random number tables shall be used as per IS:4905-
1968. No. of drums to be taken permissible number of as sample (a).

S.No. of drums/ No. of coils/ No. of drums to be taken Permissible number of


reels in lot. as sample. refectives.
(n) (n) (n)
Upto 50 3 0
51 to 100 5 0
101 to 300 13 0
301 to 500 20 1
501 to above 31 2

The inspector shall have the option to take the sample (s) from any point in the
length of any drums selected at random for carrying out various tests and total
length of that particular drum(s) of such two pieces because of this sampling in
such a particular case will be considered as one length.

9. PACKING:- The cable shall be packed and supplied in non-returnable wooden drums
provided with cast iron bushings to resist any damage during transit. Material offered for
inspection should be duly packed provided with blank lead seals for the purpose of
sealing by the Inspecting Officer. The Bidder will put their own seals also on the two
ends of the cables.

10. DRUM LENGTH:- The cable shall be supplied in standard lengths as under:-
Cable upto 185 sq.mm. = 500 Metres + 5%
Cable above 185 sq.mm. = 250 Metres + 5%

Non standards lengths not less than 100 metres each shall be acceptable upto 5% of the
ordered quantity. A tolerance of + 5% is permissible allotted to each consignee with
overall + 2% tolerance on the ordered quantity for completion of order.

11. MARKING:- The marking on the drums shall have the following informations:-
a) Trade mark, if any.
b) Name of the manufacturer.
c) Nominal cross sectional area of conductor of the cable.
d) Year of manufacture.
e) Type of cable and voltage for which it is suitable.
f) Length of cable on the drum/ reel.
g) Approximate gross weight.

-3-
h) Number of cores and colour of cores.
i) Net weight of the cable.
j) Drum/ reel identification no.
k) Purchase Order No. and Date.
l) Consignee’s name with designation.
m) ISI mark/ IEC mark.
n) Direction of rotation of drum/ reel (by means of an arrow).
o) Reference IS:1554/Part-I/1988.

-4-
SECTION – 6
CHAPTER - 11

TECHNICAL SPECIFICATION FOR


OUTDOOR
MARSHALLING KIOSKS

LIST OF CONTENTS

CLAUSE NO DESCRIPTION PAGE NO.


1.0 SCOPE 2
2.0 WORKMANSHIP AND MATERIAL 2
3.0 PRINCIPAL PARAMETERS 2
4.0 TESTS 7
5.0 INSPECTION 7
6.0 DOCUMENTATION 8
7.0 PACKING AND FORWARDING 9

-1-
1.0 SCOPE :
1.1 This specification covers the manufacture and supply of 200 Terminals Marshalling
Kiosks complete with all fittings for out door installations in Haryana State as per
schedule of requirement and generally conforming to the Specifications laid down in the
following pages.

1.2 It is not the intent to specify herein complete / all details of the design and construction of
equipment. However, the equipment shall conform in all respects to high standards of
engineering, design and workmanship and shall be capable of performing in continuous
commercial operation up to the Bidders guarantee acceptable to the HVPNL. The
equipment offered shall be complete in all aspects necessary for its effective and trouble
free operation. All similar parts particularly movable ones shall be interchangeable.

2.0 WORKMANSHIP AND MATERIAL :


All materials used in the construction of marshalling kiosks, terminal connector blocks &
other accessories/fitments shall be of the best quality obtainable of their respective kind
and the whole work shall be of highest class and well finished.

3.0 PRINCIPAL PARAMETERS :


The Marshalling Kiosks covered in this Specification shall meet the Technical
requirements listed hereunder: -

3.1 DESCRIPTION OF MARSHALLING KIOSK :


The marshalling kiosk to be suitable for pedestal mounting shall be made of sheet steel.
The side panels and rear panels constituting three sides for the kiosk and its internal
equipment mounting panel shall be fabricated with atleast 12SWG sheet steel whereas
the doors and the roof in the form of a detachable canopy 1250 * 675 mm shall be made
of 12 SWG sheet steel. The canopy shall be suitably fixed with the main cubicle with nut
& bolts packed with gasket so as to provide no opening to inside and shall be sufficiently
projected in all sides to prevent splash of rainwater to the inside of the marshalling kiosk.
The Marshalling Kiosk excluding canopy will be 1400mm (height) * 1200mm (width) *
550mm (depth) complete with double door in front provided with pad-locking facility in the
door handle. The doors of the Marshalling Kiosk will be hinged by means of die-cast
hinges, each of which is split into two identical members, one fixed to the doorframe and
the other to the door. A minimum of two sets of hinges will be provided on each side of
the door. The hinge assembly shall be smoothly finished without any sharp corner and

-2-
should be small and compact yet with sufficient rigidity to withstand the weight of the door
and to withstand the shocks due to swings of the door. The hinges should comprise of a
locating pin on one die-cast body and a free hole on the other die-cast member. The
inside edge of the doors shall be provided with 10mm thick synthetic rubber gasket.
Further stiffener should be provided suitably in order to provide sufficient structural rigidity
to the doors. One of the doors shall carry danger plate and other shall carry the label
indicating the number of terminals provided, make and HVPNL PO reference for easy
identification of equipment in our stores/field. The Marshalling Kiosk shall be bolted on
the 550 mm high angle-iron frame work made of 40x40x5 mm MS angle braced (length-
wise) by 40x5 mm MS flat (depth-wise). The bottom of the kiosk will be fitted with
1000mm*225mm removable blank cable glands supporting plate to be drilled at site for
fixing cable gland. The inside edges of Gland Plate shall be provided with 10 mm thick
one side adhesive Synthetic Rubber Gasket with Nuts & Bolts. Overall tolerance in
Dimensions shall be + 5%.
The Marshalling Kiosk should be equipped with 1No. tubular space heater of atleast
60Watt 240VAC with toggle ON/OFF switch, 1No. 15A 3-pin socket with ON/OFF switch,
1No.Illuminating lamp with Lamp Holder and ON/OFF Switch complete with respective
rewireable fuses and links. The said accessories shall be of reputed make. The switches,
fuses and links will be located on the equipment mounting panel. The tubular space
heater will be located at centre at the bottom of Marshalling Kiosk and shall have watt
loss per unit surface of heater low enough to keep surface temperature well below visible
heat. The Marshalling Kiosk shall be equipped with 3 No. earth test links made of tinned
copper for CT circuits.

The kiosk shall be provided with 2 studs on the main frame (one on each side) to
effectively earth the body of the kiosk.

THE MARSHALLING SHALL BE DUST, WATER AND VERMIN PROOF. THESE


ASPECTS MAY BE CAREFULLY CONSIDERED BY THE BIDDERS AND
NECESSARY CONSTRUCTIONAL DETAILS TO ACHIEVE THEM MAY BE
HIGHLIGHTED IN THE BID.

3.2 METAL TREATMENT AND PAINTING :


The raw material used in the construction of Marshalling Kiosk and its
fitments/accessories will be best of its kind, free from rust, cracks and flaws. The sheet
steel employed for fabrication of Marshalling Kiosk shall be properly degreased and
treated (chemically) to remove rust, scale and foreign adhering matter. A suitable high

-3-
luster rust resisting primer shall be applied on the sheet steel which will be followed by
application of an undercoat suitable to serve as base for finishing coat. The finishing coat
on the exterior will be light Grey to shade 631 of IS:5 and interior will be glossy white and
duly baked to give good adherence and finish.

THE BIDDER MAY DETAIL OUT THEIR TECHNIQUE/METHOD OF METAL


TREATMENT AND PAINTING IN THEIR BIDS.

3.3 TERMINAL BLOCK CONNECTORS :


Terminal block connectors built from cells of moulded dielectric virtually unbreakable
(Malemine) having 5mm dia brass studs with two (terminals) studs per way are to be
provided. The block moulding will shield the terminals requiring no end barrier or adjacent
block to complete the insulation. The terminal block will be suitable for mounting on the
standard rail in the normal right angles to the rail position. The terminal connector will
conform to the following details: -

i) Current and voltage rating 30 Amps, 660 VAC/900 VDC


ii) Capacity Up to three ring-tongue crimped copper
wires of 6mm2 cross-sectional area.
iii) Material for:
a) Body Cells of moulded dielectric virtually
unbreakable (Malemine).
b) The channel on which terminal MS dully hot dip galvanised.
blocks are to be fixed.
c) Terminal studs and nuts Tin coated Brass.
d) Connecting Link Tin plated copper to IS-1897.
e) Washer Brass plain nickel plated washer
(1 No. per stud).
f) Spring Washer Spring steel (1 No. per stud) –
Electroplated.
g) Star washer/teeth washer MS plated (1 No. per stud)
iv)a) Terminal connectors should be Type Tested. Terminal Connectors for CT, PT &
CVT shall have provision of splitting facilities and shorting links for
measurement of CT currents without opening the CT and isolation of PT & CVT
circuits. Terminal connectors used for CT, PT, CVT and AC Supply shall be
suitable for Copper Control Cables having cross sectional area 4Sq.mm. For

-4-
DC Supply, the terminal connectors shall be suitable for Copper Control Cables
having cross sectional area 6Sq.mm. For control and interlocking circuits, the
terminal connectors shall be suitable for Copper Control Cables having cross
sectional area 2.5Sq.mm. Further, fuses & links of suitable rating shall be
provided for 3 Phase 4 Wire AC Supply & 220 V DC Supply at TB-2.
Out of total nos. of given terminals of the Marshalling Kiosks, terminal blocks for
the 1st row TB-1 and 10th row TB-10 as per sketch shown at page 6 & 7 under
clause 3.4 will be of splitting type 1st row TB-1 for measuring the CT current
(without opening the CT secondary) and 10th row TB-10 PT/CVT circuits for
providing isolation. 2nd row TB-2 to 9th row TB-9 will be of stud type. In 2nd row
TB-2, Stud Type Terminal Connectors suitable for Copper Control Cables of
4Sq.mm & 6Sq.mm are to be provided as shown at page 6 & 7 under Cl. 3.4. In
3rd row TB-3 to 9th row TB-9 Terminal Connectors suitable for Copper Control
Cables of 2.5Sq.mm cross sectional area.
b) Terminal identification carrier The terminal block is to be complete
with terminal identification carrier
(see clause-3.4 for identification
numbers).
v) Covers A clear nylon cover should be
provided which can be clipped to the
sides of the Terminal Block.

3.4 DISTRIBUTION OF TERMINALS AND THEIR IDENTIFICATION NUMBERS:


The total number of terminal in the Marshalling Kiosk will be distributed in ten rows.
Terminal block connector row’s shall be adequately spaced and in no case less than 100
mm apart center to center of the terminal block so as to permit convenient access to
terminations. Labels in the form of plastic/steel plates carrying numerals for terminal
identification shall be so mounted as to cause no interference with regard to access to
terminal nuts. The numerals marked from top to bottom in ascending order starting from
left-hand side as viewed from the front of Marshalling Kiosk and a progressively
increasing from left-hand-side to right-hand-side in 200 terminals Marshalling Kiosks
respectively.

-5-
a) 200 Terminals Marshalling Kiosk (For 66kV):
TB-1 TB-2 TB-9 TB-10
1 21 161 181

2 22 162 182

3 23 163 183

14Nos. TB’s of

4Sq.mm

34

35

18 178 198
19 6Nos. TB’s of 179 199
6Sq.mm

20 40 180 200

4.0 TEST
4.1 Following tests shall be carried out at the manufacturers works after complete assembly
of marshalling kiosks and the test reports of such tests supplied in quadruplicate for
approval of the CE/MM, HVPNL, Panchkula before effecting despatch of the equipment:-
i) Checking and verification of the dimensions, gauge of the sheet steel, angle-iron frame
work, terminal block connector and its components etc. viz-a-viz the respective approved
drawings(s).
ii) Checking wiring of circuits and their continuity.
iii) One minute applied voltage tests for illumination/heater wiring in the marshalling kiosks.
iv) Insulation resistance of complete wiring, circuit by circuit, with the lamp/heater mounted
in the marshalling kiosks.

5.0 INSPECTION :
i) The HVPNL shall have access at all times to the works and all other places of
manufacture, where the marshalling kiosks are being manufactured and the Bidder shall
provide HVPNL representative all facilities for unrestricted inspection of the works, raw
materials, manufacture of all the accessories and for conducting necessary tests as
detailed therein.

-6-
ii) The successful Bidder shall keep the HVPNL informed in advance of the time starting and
of the progress of manufacture of equipment in its various stages and shall give prior
notice of at least 15 days for inspection of material, so that arrangements could be made
for inspection.
iii) No. material shall be despatched from its point of manufacture unless the material has
been satisfactorily inspected and tested.
iv) The acceptance of any quality of the equipment shall in no way relieve the successful
Bidder of his responsibility for meeting all the requirements of this Specification and shall
not prevent subsequent rejection if such material is later found to be defective.

6.0 DOCUMENTATION :
6.1 All drawings shall conform to international standards organisation (ISO) `A' series of
drawing sheet/Indian Standards Specification IS:11065. All drawings shall be in ink and
suitable for microfilming / digitization / scanning, etc for archive purposes. If drawings are
computerized than all drawings shall be nicely printed. All dimensions and data shall be in
S.I.Units.

6.2 LIST OF DRAWINGS AND DOCUMENTS :


In addition to any other drawings which the bidder may like to enclose to explain the
merits of his proposal. The following drawing shall be enclosed with the bid: -
i) Dimensional drawing of the kiosk highlighting constructional features of the hinges and
the junction of canopy with the cubical.
ii) Dimensional drawing of the terminal connector block highlighting the material of various
components forming it the label carrier and details of its arrangement in 10 rows.
iii) Dimensional drawing showing the disposition of terminals in 10 rows as viewed from the
front of the Marshalling Kiosk with its doors open and terminal identification numerals
assigned to them.
iv) Dimensional drawing showing top view with gland plate & side view of cubical.
v) Bill of material for all accessories mounted in MK.
a) Description of Item, Make, Type & QTY. of material provided.
b) Voltage & current rating
v) Catalogue of terminal connectors installed in Marshalling Kiosks for reference.

NOTE:-All above drawings should bear a minimum space (14X10cm) for stamping the
approval of drawings by the HVPNL.

-7-
6.3 The successful bidder/Bidder shall submit four sets of final versions of complete and
correct equipment drawings for HVPNL’s approval alongwith bid in a sealed envelope.
The HVPNL shall communicate his comments/approval on the drawings to the
bidder/Bidder within 21 days from the date of issue of LOI. The submission of complete
and correct readable drawings for approval is the responsibility of the bidder/Bidder. The
Bidder shall, if so required by the HVPNL, modify the drawings and resubmit four copies
of the modified drawings for HVPNL’s approval within two weeks from the date of
HVPNL’s comments. Then, the HVPNL shall approve the revised drawings within two
weeks from the date of its receipt.

6.4 The manufacturing of the equipment shall be strictly in accordance with the approved
drawings and no deviation shall be permitted without the written approval of the HVPNL.
All manufacturing and fabrication work in connection with the equipment prior to the
approval of the drawing shall be at the bidder/Bidder's risk.

6.5 The successful bidder/Bidder shall also supply one set of nicely bound documents
comprising all the approved drawings & instruction manual containing handling,
installation, testing and commissioning of equipment at the time of despatch of material to
the consignee with each equipment for our field staff without which the supply will not
be considered as complete supply. In addition, 1 sets of such bound manuals and final
approved drawings shall be supplied for reference & record in design office alongwith one
good quality soft copy on a suitable media of approved drawings and instruction manuals,
if computerized.

6.6 Approval of drawings / work by HVPNL shall not relieve the bidder/Bidder of his
responsibility and liability for ensuring correctness and correct interpretation of the latest
revision of applicable standards, rules and codes of practices. The equipment shall
conform in all respects to high standards of engineering, design, workmanship and latest
revisions of relevant standards at the time of ordering and HVPNL shall have the power to
reject any work or material which in his judgement is not in full accordance therewith.

7.0 PACKING AND FORWARDING :


7.1 The marshalling kiosks shall be securely packed to avoid scratches on the sheet steel &
transit damage to various components constituting the marshalling kiosks. The
bidder/Bidder shall be responsible for any damage to the equipment during transit due to
improper & inadequate packing. The easily damageable material shall be carefully
packed & marked with the appropriate symbols.

-8-
SECTION – 6
CHAPTER – 12

SECTION: DIESEL GE NERATOR SET


Table of Contents

Clause No. Description Page No.


1.1 SCOPE OF SUPPLY
1.2 SCOPE OF SERVICE
1.3 TECHNICAL REQUIREMENT
1.4 PLANT DESIGN
1.4.1 Diesel Engine
1.4.2 Air Suction & Filtration
1.4.3 Fuel & Lubricating System
1.4.4 Engine Starting System
1.4.5 Fuel Injection and Regulator
1.4.6 Alternator
1.4.7 Coupling
1.4.8 Mounting Arrangement
1.4.9 Peripherals
1.5 CONTROL AND INSTRUCMENTATION
1.6 D.G. SET Enclosure
1.7 INSTALLATION ARRANGEMNT
1.8 DOCUMENTS
1.9 TESTS
1.10 COMMISSIONING CHECKS

-1-
SECTIONAL : DIESEL GENERATOR SET
1.1 SCOPE OF SUPPLY
1.1.1 The scope covers supply of Diesel Generator Set of Stationary Type
having a net electrics output of 100kVA capacity at specified site
conditions of 500C ambient temperature and 100% relative humidity on
FOR site basis. DG set shall be equipped with:-
(i) Diesel engine complete with all accessories.
(ii) An alternator directly coupled to the engine through coupling, complete
with at accessories.
(iii) Automatic voltage regulator.
(iv) Complete starting arrangement, including two nos. batteries & chargers.
(v) Base frame, foundation bolts etc.
(vi) Day tank of 500 Litre capacity.
(vii) Engine Cooling and lubrication system.
(viii) Engine air filtering system.
(ix) Exhaust silencer package.
(x) Set of GI pipes, valves, strainers, unloading hose pipes as required for
fuel transfer system from storage area to fuel tank including electrically
driven fuel pump.
(xi) All lubricants, consumable, touch up paints etc. for first filing, testing &
commissioning at site. The fuel oil for first commissioning will also be
provided by the Bidder.
(xii) AMF panel for control, metering and alarm.
(xiii) Enclosure for silent type D.G. Set.

1.2 SCOPE OF SERVICE


1.2.1 The Bidder shall provide following services :-
a) Design manufacture, shop testing including assembly test.
b) Despatch, transportation to site.
c) Erection, testing & commissioning with all equipments/materials required
for the purpose.
d) Drawings, data, design calculations and printed erection, operation &
maintenance manual.
e) Certification and compliance for meeting noise level & emission
parameters and other requirements in accordance with latest Notification
of MOEF.
1.3 TECHNICAL REQUIREMENTS
1.3.1 The rating of DG sets are as follows
1.3.1.1 DG set net out put after considering deration for engine and alternator
separately due to temperature rise in side the enclosure and on account
of power reduction due to auxiliaries shall be 100kVA, 1500 RPM,
0.8RPM, 0.8Pf, 415V, 3 phase, 50Hz. The above ratings are the minimum
requirements.

1.3.1.2 DG Set shall also be rated for 110% of full load for 1 hour in every twelve
hrs of continaous running.

-2-
1.3.2 The output voltage, frequency and limits of variation from open circuit to
full load shall be as follows:-
a) Voltage variation +5% of the set value provision shall exist to
adjust the set value between 90% to 110%
of nominal Generator voltage of 415V.

b) Frequency 50Hz +2%

1.3.3 The Diesel Generator and other auxiliary motor shall be of H class with
temperature rise limited to Class-F for temperature rise consideration.

13.4 NOISE LEVEL & EMISSION PARAMETERES: These shall be as per


latest Notification of MOEF.

1.4 PLANT DESIGN

1.4.1 DIESEL ENGINE

1.4.1.1 The engine shall comply with the IS 10002/BS 5514/ISO 3046; latest
edition.
1.4.1.2 Diesel engine shall be turbo changed multicylinder V-type in line type with
mechanical fuel injection system.
1.4.1.3. The engine with all accessories shall be enclosed in a enclosure to make
it work Silently (Within permissible noise level without any degradation in
its performance.
1.4.1.4 The Diesel Engines shall be directly water cooled. Cooling of water
through radiator and fan as cavisaged.
1.4.1.5 The fuel used shall be High Speed Diesel Oil (HSD) or Light Diesel Oil
(LDO) as per IS:1460.

1.4.2 AIR SUCTION & FILTRATION

1.4.2.1 Suction of air shall be from vanulation and exhaust flue gasses will be let
out to outside atmosphere. Condeasate traps shall be provided on the
exhaust pipe.
1.4.2.2 Filter shall be dry type as filter with replaceable elements.

1.4.3 FUEL AND LUBRICATING OIL SYSTEM

1.4.3.1 The engine shall have closed loop lubricating system. No moving parts
shall require lubrication by hand prior to the start of engine or while it is in
operation.

1.4.4 ENGINE STARTING SYSTEM

1.4.4.1 Automatic electric starting by DC starter motor shall be provided.

1.4.5 FUEL INJECTION AND REGULATOR

-3-
1.4.5.1 The engine shall be fitted with electronic governor suitable for class A-1
as per IS 10000.
1.4.5.2 The engine shall be fitted with a heavy, dynamically balanced fly wheel
suitable for constant speed governor duty.

1.4.6 ALTERNATOR

1.4.6.1 The alternator shall comply with BS 2613/IS 4722/IEC 34: latest edition.
1.4.6.2 The alternator shall be of continuously rated duty, suitable for 415V, 3
Phase, 50 Hz Power development having brush-less, synchronous, self-
excited, self-regulating system.
1.4.6.3 The alternator shall be drip-proof, screen protected as per IP-23 degree
of Protection.
1.4.6.4 The rotor shall be dynamically balanced to minimize vibration.
1.4.6.5 It shall have the winding of class H but limited to Class-F for temperature
rise consideration.
1.4.6.6 It shall have the winding of class H but limited to Class-F for temperature
rise consideration.
1.4.6.7 The Alternator regulator shall be directly coupled to the engine and shall
be complete with the excitation system, automatic voltage regulation of
+/- 1% voltage adjusting potentiometer and under over speed protection.

1.4.6.8 TERMINAL BOX

1.4.6.8.1 Six (6) output terminals shall be provided in alternator terminal box.
Terminals shall be suitable for 31/2 Core 300 mm2 XLPE cable for
100kVA DG set. The neutral shall be formed a AMF panel. The generator
terminal box shall be suitable to house necessary cables an should be
made of non-magnetic material.
1.4.6.8.2 The alternator with all accessories shall be enclosed in a enclosure to
make it work Silently (within permissible noise level)

1.4.7 COUPLING

1.4.7.1 The engine and alternator shall be directly coupled by means of self-
aligning flexible flange coupling to avoid misalignment.
1.4.7.2 The coupling shall be provided with a protecting guard to avoid accidental
contract.

1.4.8 MOUNTING ARRANGEMENT

1.4.8.1 The engine and alternator shall be mounted on a common heavy duty,
rigid fabricated steel base frame constructed from ISMC of suitable
sections.
1.4.8.2 Adequate number of anti-vibration mounting pads shall be fixed on the
common base frame on which the engine and the alternator shall be
mounted to isolate the vibration from passing on to the common base
frame or the foundation of the D.G. Set.

1.4.9 PERIPHERALS

-4-
1.4.9.1 FUEL TANK

1.4.9.1.1 The Fuel tank of 500 Litre capacity shall be provided on a suitably
fabricated steel platform. The tank shall be complete with level indicator
marked in litres, filling inlet with removable screen, an outlet, a drain plug,
an air vent, an air breather and necessary piping. The tank shall be
painted with oil resistant paint and shall be erected I accordance with
Indian explosive act of 1932. Fuel tank shall be kept outside of enclosure.
The fuel piping shall be carried out to connect the D.G. set kept inside.

1.4.9.1.2 For transferring fuel to Fuel tank transfer pump is envisaged. The
capacity of transfer pump shall be adequate to fill the day tank in about 30
minutes. Fuel pump shall be electrically driven.

1.4.9.2 BATTERY and BATTERY CHARGER

1.4.9.2.1 Two nos. 24V batteries complete with all leads, terminals and stand shall
be provided Each battery shall have sufficient capacity to give 10 nos.
successive starting impulse to the diesel engine.
1.4.9.2.2 The battery charger shall be complete with transformer, suitable rating
(415V, 3 Ph., 50Hz./230V, 1Ph., 50Hz) rectifier circuit, charge rate
selector switch for “tricle”/’boost’ charge, D.C. ammeter & volunteer,
annunciation panel for battery charge indication/loading/failures.
1.4.9.2.3 The charger shall float and Boost Charge the battery as per
recommendation manufacturer of battery. The charger shall be able to
charge a fully discharged batter I state of full charge in 8 Hrs. with 25%
spare capacity.
1.4.9.2.4 Manual control for coarse and find voltage variation shall be provided.
Float charger sl. have built-in load limiting features.
1.4.9.2.5 Ripple shall not be more than 1% (r.m.s.) to get smooth DC voltage shall
be provided.
1.4.9.2.6 Charger shall be provided with Out-put Voltmeter & Ammeter.
1.4.9.2.7 Changeover scheme for selecting battery and battery charger by
changeover switch show be provided.

1.5 CONTROL AND INSTRUMENTATION

1.5.1 Each D.G. Set shall be provided with suitable instruments, interlock and
protection arrangement, suitable annunciation and indications etc. for
proper start up, monitoring and safe operation of the unit. One local AMF
control panel alongwith D.G. set shall be provided by the Bidder to
accommodate these instruments, protect relays, indication lamps etc. The
AMF Panel shall have IP-52 degree of Protection as IS:12063.
1.5.2 The D.G. sets shall be provided with automatic start facility to make it
possible to take load within 30 seconds of Power Supply failure.
1.5.3 Testing facility for automatic operation of D.G. Set shall be provided in
AMF panel.
1.5.4 A three attempt starting facility using two impulse timers and summating
timer for shall be proved and if the voltage fails to develop within 40 sec.

-5-
from receiving the final impulse, the set shall block and alarm to this effect
shall be provided in the AMF panel.
1.5.5 Following instruments shall be provided with Diesel Engine.
a) Lub Oil Pressure Gauge.
b) Water Temperature Thermometers.
c) Engine Tachometer/HR
d) Any other instruments necessary for DG Set operation shall be
provided.
1.5.6. DG Set shall be capable of being started stopped manually from remote
as well as laid (Remote START/STOP push button shall be provided in
415V ACDB). However interlock shall be provided to prevent shutting
down operation as long as DG care breaker is closed.
1.5.7. The diesel generator shall commence a shutdown sequence whenever
any of the following conditions appear in the systems :-
a) Overspeed
b) Overload
c) High temperature of Engine and Cooling Waters
d) High temperature inside enclosure
e) Low lube oil pressure
f) Generator differential protection
g) Short Circuit Protection
h) Under Voltage
i) Under Voltage
j) Further interlocking of breaker shall be provided to prevent parallel
operation of DG set with normal station supply.
1.5.8 Following indication lamps for purposes mentioned as under shall be
provided in AMF Panel
1.5.8.1 Pilot indicating lamp for the following:-
a) Mains ON
b) Alternator ON
c) Charger ON/OFF
d) Breaker ON/OFF
e) Main LT Supply ON/OFF.

1.5.8.2 Visual Annunciation shall be provided for set shut down due to :
a) Engine overheating
b) Low Oil Pressure
c) Lack of Fuel
d) Set failed to start in 30 secs after receiving the first start impulse
e) High Cooling Water Temperature
f) Low level in daily service fuel tank
g) Overspeed trip
h) Audio & Visual Annunciation for alternator fault.

1.5.9 Thermostatically controlled space heaters and cubicle illumination


operated by Door Switch shall be provided in AMF Panel. Necessary
isolating switches and fuses shall also be provided.
1.5.10 AMF Panel shall have facility for adjustment of speed and voltage
including the adjustments in remote as well as in local mode.

Following shall also be provided in AMF Panel.

-6-
a) Frequency meter.
b) 3 Nos. Single Phase CTs for metering.
c) 3 Nos. (Provided by LT swgr. Manufacturer) Single Phase CTs with KPV
300V & RCT 0.25 ohm for differential protection of DG Set on neutral side
only for 100kVA.
d) One (1) DC Ammeter (0-40A)
e) One (1) DC Voltmeter (0-30V)
f) One (1) Voltmeter Selector Switch
g) One (1) AC Ammeter
h) One (1) AC Voltmeter
i) Three (3) Timers (24V DC)
j) Two (2) Auto/Manual Selector Switch
k) Two (2) Auto/Test/Manual Selector Switch
l) Eleven (11) Aux. Contactors suitable for 24V DC.
m) One (1) Motorised potentiometer for voltage adjustment
n) Two (2) Set Battery charger as specified in Technical Specification
o) One (1) Set Phase & Neutral busbars.
p) Any other item required for completion of Control Scheme shall be
deemed to be included.

1.6 D.G. SET ENCLOSURE

1.6.1 GENERAL REQUIREMENTS

1.6.1.1 Diesel engine, alternator, AMF panel, Batteries and Chargers shall be
installed outdoor in a suitable weather-proof enclosure which shall be
provided for protection from rain, sun, dust etc. Further, in addition to the
weather proofing, acoustic enclosures shall also be provided such that
the noise level of acoustic enclosure DG set shall meet the requirement of
MOEF. The diesel generator sets should also conform to Environment
(Protection) Rules, 1986 as amended. An exhaust fan with louvers shall
be installed in the enclosure for temperature control inside the enclosure.
The enclosure shall allow sufficient ventilation to the enclosed D.G. Set
so that the body temperature is limit to 500C. The air flow of the exhaust
fan shall be from inside to the outside the shelter. The exhaust fan shall
be powered from the DG set supply output so that it starts with the
starting of the DG set and stops with the stopping of the DG set. The
enclosure shall have suitable viewing glass to view the local parameters
on the engine.
1.6.1.2 Fresh air intake for the Engine shall be available abundantly; without
making the engine to gasp for air intake. A chicken mess shall be
provided for air inlet at suitable location in enclosure which shall be
finalized during detailed engineering.
1.6.1.3 The Enclosure shall be designed and the layout of the equipment inside it
shall be such that there is easy access to all the serviceable parts.
1.6.1.4 Engine and Alternator used inside the Enclosure shall carry their
manufacturer’s Warranty for their respective Models and this shallnot
degrade their performance.

-7-
1.6.1.5 Exhaust from the Engine shall be let off through Silence arrangement to
keep the noise level within desired limits. Interconnection between silence
and engine should be through stainless steel flexible hose/pipe.
1.6.2 All the Controls for Operation of D.G. Set shall be easily assessable.
There should be provision for emergency shut down from outside the
enclosure.
1.6.3 Arrangement shall be made for housing the Battery Set in a tray inside
the Enclosure.

1.6.4 CONSTRUCTION FEATURES

1.6.4.1 The enclosure shall be fabricated from at least 14 Gauge CRCA sheet
steel and of Modular construction for easy assembling and dismantling.
The sheet metal components shall be pre-treated by Seven Tank Process
and Poweder coated (PURO Polyester based) both-in side and out side –
for long life. The hard-ware and accessories shall be high tensile grade.
Enclosure shall be given a lasting anti-rust treatment and finished with
pleasant environment friendly paint. All the hardware and fixtures shall be
rust proof and able to withstand the weather conditions.
1.6.4.2 Doors shall be large sized for easy access and provided with long lasting
gasket to make the enclosure sound proof. All the door handles shall be
lockable type.
1.6.4.3 The Enclosure shall be provided with anti-vibration pads (suitable for the
loads and vibration they are required to carry) with minimum vibration
transmitted to the surface the set is resting on.
1.6.4.4 High quality rock wool of required density and thickness shall be used
with fire retardant thermo – setting resin to make the Enclosure sound
proof.
1.6.4.5 Provision for Neutral/Body Earthing.
1.6.5.1 Points shall be available at two side of the enclosure with the help of
flexible copper wires from alternator neutral, and electrical panel body
respectively. The earthing point shall be isolated through insulator
mounted on enclosure.

1.7 INSTALLATION ARRANGEMENT

1.7.1 DG set enclosed in enclosure shall be installed on Concrete Pedestal


300mm above FGL.

1.8 DOCUMENTS

1.8.1 Following drawings and data sheet shall be submitted for approval:
(i) Data sheet for Engine, Alternator, Batter, AMF Panel and Enclosure.
(ii) G.A. drawing of DG set.
(iii) Layout of DG set in the enclosure along with sections.
(iv) GA and schematic of AMF panel.
(v) Arrangement of inclined roof and pedestal.

1.8.2 The DG Set shall be supplied with


(i) DG Set test certificate.

-8-
(ii) Engine Operation & maintenance Manual.
(iii) Engine Parts Catalogue.
(iv) Alternator Operation, maintenance & Spare Parts Manual.
(v) Alternator Test Certificate.

1.9 TESTS

a) The Diesel generator sets shall be tested for routine and acceptance tests
as per the relevant IS/IEC standards.
b) The Type Test Report for diesel engine and alternation are not required to
be submitted or the makes indicated at Annexure-E of Section:
GTR/HVPNL approved list of subvendors. For the new makes (other than
those indicated at Annexure-E/HVPNL approved list of subvendors) Type
Test Reports as per relevant standard shall be submitted for HVPNL’s
approval.

1.10. COMMISSIONING CHECKS

In addition to the checks and test recommended by the manufacturer, the


Bidder shall carryout the following commissioning test to be carried out at
site.
1. LOAD TEST
The engine shall be given test run for a period of atleast 6 hours. The set
shall be subjected to the maximum achievable load as decided by HVPNL
without exceeding the specified DG Set rating:
During the load test, half hourly records of the following shall be taken :
a) Ambient temperature.
b) Exhaust temperature if exhaust thermometer is fitted.
c) Cooling water temperature at a convenient point adjacent to the
water output from the engine jacket.
d) Lubricating oil temperature where oil cooler fitted.
e) Lubricating oil pressure.
f) Colour of exhaust gas.
g) Speed.
h) Voltage, wattage and current output.
i) Oil tank level.
The necessary load to carryout the test shall be provided by the HVPNL.

2. INSULATION RESISTANCE TEST FOR ALTERNATOR


Insulation resistance in mega-ohms between the coils and the frame of
the alternator when tested with a 500V megger shall not be less than
1R=2x (rated voltage in KV)+1

3. CHECK OF FUEL CONSUMPTION


A check of the fuel consumption shall be made during the load run test.
This test shall be conducted for the purpose of proper tuning of the
engine.

-9-
4. INSULTAITON RESISTANCE OF WIRING
Insulation resistance of control panel wiring shall be checked by 500V
Megger. The IR shall not be less than one mega ohm.

5. FUNCTIONAL TESTS

a) Functional tests on control panel.


b) Functional test on starting provision on the engine.
c) Functional tests on all Field devices.
d) Functional tests on AVR and speed governor.

6. MEASUREMENT OF VIBRATION
The vibration shall be measured at load as close to maximum achievable
load and shall not exceed 100 microns.

7. Noise Level Check As Per Relevant Standard.

8. The tests shall be carried out with the DG set operating at rated speed
and at maximum achievable load. Necessary correction for Test
environment condition & background noise will be applied as per
IS:12065.

- 10 -
SECTION-6
Chapter-13
TECHNICAL SPECIFICATION FOR
AAC TARANTULLA CONDUCTOR

CONTENTS

CLAUSE NO. TITLE PAGE NO.


1.0 SCOPE 1
2.0 STANDARDS 1
3.0 CLIMATIC CONDITIONS 2
4.0 PRINCIPAL PARAMETERS 2
5.0 GENERAL TECHNICAL REQUIREMENT 3
6.0 TESTS 7
7.0 INSPECTION 10
8.0 DOCUMENTATION 11
9.0 PACKING AND FORWARDING 11
10.0 QUANTITY AND DELIVERY 13
REQUIREMENT
11. GUARANTEED TECHNICAL 13
PARTICULARS
ANNEXURES
I QUANTITY AND DELIVERY 14
REQUIREMENTS
II SYSTEM PARTICULARS 15
III GUARANTEED TECHNICAL 16
PARTICULARS OF AAC TARANATULLA
CONDUCTOR

-1-
TECHNICAL SPECIFICATION FOR AAC TARANTULLA CONDUCOTR FOR
TRANSMISSION LINES

1.0 SCOPE

1.1 This specification provides for design, manufacture, engineering, inspection,


stage testing and testing before despatch, packing and delivery at site of All
Aluminium conductor specified herein for its satisfactory operation on various
Transmission lines and substations of the State.
1.2 AAC Tarantula conductor is to be used as power conductor on single circuit
and double circuit transmission lines and sub-stations of the HVPNL.

2.0 STANDARDS

2.1 The power conductor shall conform to the following Indian Standards, which
shall mean latest revision, amendments/changes adopted and published,
unless otherwise specified herein before.

SL.No. Indian Standards Title

1. IS: 398 Part I to V (As Specification for Aluminium


relevant) conductors for overhead
Transmission purpose.

2. IS : 1778 Reels and Drums for Bare


conductors

3. IS : 1841 EC grade Aluminium rod produced


by rolling

4. IS : 5484 EC grace Aluminium rod produced


by continuous casting and rolling

-2-
3.0 CLIMATIC CONDITIONS

I. Location In the state of Haryana


II. Maximum Ambient Air Temperature deg. 50
C
III. Minimum daily ambient Air Temperature (-) 2.5
deg. C
IV. Average daily ambient Air Temperature 32
deg. C
V. Maximum relative humidity (%) 100
VI. Average rainfall per annum (mm) 900
VII. Maximum altitude above mean sea level 1000
(metres)
VIII. Isoceraunic level (Days/annum) 45
IX. Maximum wind pressure (kg/Sq. metre) 195
X. Seismic level (Horizontal acceleration) 0.3 G

4.0 PRINCIPAL PARAMETERS

4.1 The detail of conductor are tabulated below

a) Stranding and wire diameter 37/5.23 mm Al.

Code name AAC TARANTULLA


b) Number of strands per layer of aluminium Wire
Central 1

1st Aluminium layer 6


2nd Aluminium layer 12
3rd Aluminium layer 18
c) Total Sectional area of aluminium (Sq. mm) 795.6 mm2
d) Overall diameter (mm) 36.61mm
e) Approximate weight (kg/km) 2198 kg/km
f) Calculated max. d.c.resistance at 20 Deg.C 0.03656
(ohm/km)
g) Minimum UTS (kN) of conductor 11,600 kg.
h) Modulus of Elasticity 0.5976x106 kg/cm2
i) Coefficient of linear expansion (per Deg.C) 23X10-6

-3-
4.2 The details of aluminium strand are as follows:

a) Minimum breaking load of strand before stranding


(kN)
b) Minimum breaking load of strand after stranding (kN) 3.08
c) Maximum D.C resistance of strand of 20 Deg. C 1.350
(ohm/km)
d) Diameter mm (Standard/Max/Min) 5.23/5.28/5.18
e) Mass (Kg/Km) 59.40

5.0 GENERAL TECHNICAL REQUIREMENT

5.1 The ACC Tarantulla conductor shall be suitable for being installed directly in
air supported on suspension insulator strings or anchored through tension
insulator strings at the power cross arms of single circuit and double circuit
transmission line towers.
5.2 The conductor shall therefore be suitable for satisfactory operation under the
tropical climatic conditions listed under the clause 3.0.

5.3 Physical constants of materials

5.3.1. Physical constants for Hard-drawn Aluminium.

5.3.2. Resistivity

The resistivity of aluminium depends upon its purity and its physical
condition. For the purpose of this specification the maximum value permitted
is 0.028264 ohm. Sq.mm/mt at 20 Deg. C and this value has been used for
calculation of the maximum permissible value of resistance.

Note: It is not intended to check the resistivity from the measured values of
resistance.

-4-
5.3.3 Density

At a temperature of 20 Deg. C the density of hard drawn aluminium has been


taken as 2.703 g/cub cm.

5.3.4 Constant-Mass Temperature Co-efficient of Resistance

At a temperature of 20 Deg.C the constant –mass temperture co-efficient of


resistance of hard drawn aluminium measured between two potential points
rigidly fixed to the wire, the metal being allowed to expand freely, has been
taken as 0.004 per degree Celsius.

5.3.5 Co-efficient of Linear Expansion

The co-efficient of linear expansion of hard-drawn aluminium at 0 Deg.C has


been taken as 23.0x10-6per deg.C. This value holds good for all practical
purposes over the range of temperatures from 0 Deg.C to highest safe
operating temperature.

5.4 Materials

5.4.1 The conductor shall be manufactured from EC grade aluminium rods suitably
hard-drawn on wire drawing machines. The aluminium rods used shall
comply with IS:1841-1978 and IS:5484. The mechanical and electrical
properties of aluminium wire shall comply with the requirements given in
relevant standard. The aluminium wire shall be manufactured from not less
than 99.5% pure electrolytic aluminium rods of E.C. Grade.

5.5 Freedom from Defects

5.5.1 The wires shall be smooth and free from all imperfections such as spills,
spilts, slag inclusion, die marks, scratches, fittings, blow-holes, projections,
looseness, overlapping of strands, chipping of aluminium layers etc. and all
such other defects which may hamper the mechanical and electrical
properties of the conductor. Special care should be taken to keep away dirt,
grit etc. during stranding.

5.6 Wire Sizes

5.6.1 Nominal Size

The aluminium for the stranded conductor covered by this standard shall
have diameters specified in clauses 4.1.

5.6.2 Tolerances on normal size

-5-
5.6.2.1 Aluminium Wires
A tolerance of + 1% is permitted on the nominal diameter of AAC conductor.

Note: In order to maintain the circularity of the wires the tolerance allowed in
5.6.2.1 shall apply to both the measurement at right angles taken at
the same cross-section as per clause 2.2 of IS:398 (Part-II) (Second
Revision with latest Amendments).

5.7 Joints in wires

5.7.1 Aluminium wires

No joints shall be permitted in the aluminium wires in the outermost layer of


the ACSR conductor. Joints in the inner layers are permitted, in addition to
those made in the base rod or wire before final drawing, but no two such
joints shall be less than 15 metres apart in the complete stranded conductor.
Such joints shall be made by cold pressure butt-welding.

Note: Joints are not permitted in the outermost layer of the conductor in
order to ensure a smooth conductor finish and reduce radio interference
levels and corona losses on the extra high voltage lines.

5.8 Stranding

5.8.1 The wires used in the construction of all aluminium conductor shall, before
stranding, satisfy all the relevant requirements of this specification.

5.8.2 The lay ratio of the different layers shall be within the limits given in the table
below

LAY RATIO OF ALL ALUMINIUM CONDUCTOR


No. of Lay Ratios for Aluminium Wires
wires
Al. Outside Layer Immediately Innermost Layer of
Layer beneath out side conductor with three
layer Aluminium Wire Layers
Min. Min. Max. Min. Max.
Max.
37 11.25 14 14 21 18 21

Note: For the purpose of calculation, the mean lay ration shall be taken as
the arithmetic mean of the relevant minimum and maximum values given in
this table.

-6-
5.8.3. In all constructions, the successive layers shall have opposite directions of
lay, the outermost layer being right-handed. The wires in each layer shall be
evenly and closely stranded.

5.8.4. The lay ratio of any aluminium layer shall not be greater than the lay ratio of
the aluminium layer immediately beneath it.

5.9 Standard Length

5.9.1 The standard length of the conductor shall be 500 meters. A tolerance of
+5% on the standard length shall be permitted. All lengths outside this limit of
tolerance shall be treated as random lengths.
5.9.2 Random lengths will be accepted provided no length is less than 70% of the
standard length specified and the total quantity of such random lengths shall
not be more than 5% of the total quantity ordered.
5.9.3 Supplier shall also indicate the maximum single length above the standard
length, he can manufacture, in the guaranteed technical particulars.

6.0 Tests

6.1 The type, acceptance and routine tests and tests during manufacture, shall
be carried out on the conductor. For the purpose of this clause:

6.1.1 Type tests shall mean those tests, which are to be carried out to prove the
process of manufacture and general conformity of the material to this
specification. These tests shall be carried out on samples prior to
commencement of commercial production against the order. The supplier
shall indicate his schedule for carrying out these tests in the activity
schedule.

6.1.2 Acceptance tests shall mean those tests, which are to be carried out on
samples taken from each lot offered for pre-despatch inspection, for the
purposes of acceptance of that lot.

6.1.3 Routine tests shall mean those tests which are to be carried out on each
strand/spool/length of the conductor to check requirements which are likely to
vary during production.

-7-
6.1.4 Tests during manufacture shall mean those tests, which are to be carried out
during the process of manufacture and end inspection by the Supplier to
ensure the desired quality of the end product to be supplied by him.

6.1.5 Samples for individual wires for tests shall be taken before stranding from not
less than ten percent of the spools in the case of aluminimum wires. If
samples are taken after stranding, they shall be obtained by cutting 1.2
metres from the outer end of the finished conductor from not more than ten
percent of the finished reels.

6.1.6 The standards and norms to which these tests will be carried out are listed
against them.

6.1.7 For type and acceptance tests, the acceptance values shall be the values
guaranteed by the Supplier in the proforma for “Guaranteed Technical
Particulars”, furnished in the Annexure-II or the acceptance value specified in
this specification, whichever is more stringent for that particular test.

6.2 Acceptance Tests

a) Visual and dimensional check


b) Visual check for joints, scratches etc. and lengths of conductor.
c) Dimensional check on aluminium strands
d) Check for lay ratios of various layers
e) Breaking load test on aluminium strands
f) Wrap test on aluminium strands
g) DC resistance test on aluminium strands

Note: All the above tests shall be carried out on aluminium strands after
stranding only.

6.3 Routine Tests

a) Check to ensure that the joints are as per specification


b) Check that there are no cuts, etc. on the strands.
c) Check that drums are as per specifications.
d) All acceptance tests are mentioned in Clause 6.2 above shall be
carried out on each coil.

-8-
6.4 Testing Expenses

6.4.1 The testing charges for the type tests specified shall be indicated separately
in the prescribed schedule.
6.4.2 The supplier shall indicate the type test charges for each type test
separately.
6.4.3 In case of failure in any type, the supplier is either required to modify the
design of the material or repeat the particular type test three times
successfully at his own expenses. The decision of the Purchaser in this
regard shall be final binding.
6.4.4 Suppliers shall indicate the laboratories in which they propose to conduct the
type tests. They shall ensure that the tests can be completed in these
laboratories within the time schedule guaranteed by them in the appropriate
schedule.
6.4.5 The entire cost of testing for the acceptance and routine tests and tests
during manufacture specified herein shall be treated as included in the
quoted unit price of conductor, except for the expenses of the
inspector/Purchaser’s representative.

6.5 Additional Tests

The Purchaser reserves the right of having at his own expenses any other
test(s) of reasonable nature carried out at Supplier’s premises, at site, or in
any other place in addition to the aforesaid type, acceptance and routine test,
to satisfy himself that the material comply with the specifications.

6.6 Sample Batch for testing

6.6.1 Samples shall be obtained by cutting 2mtrs. length from the outer end of the
finished conductor from minimum 10% of the finished drums offered for
inspection.
6.6.2 The Supplier is required to carry out all the acceptance tests successfully in
the presence of Purchaser’s representative before despatch.

6.7 Test Reports

6.7.1 Copies of type test reports shall be furnished in at least six(6) copies
alongwith one original. One copy shall be returned duly certified by the
Purchaser only after which the material will be dispatched.
6.7.2 Record of routine test reports shall be maintained by the supplier at his works
for periodic inspection by the Purchaser’s representative.
6.7.3 Test Certificates of tests conducted during manufacture shall be maintained
by the supplier. These shall be produced for verification as and when desired
by the Purchaser.

-9-
6.8 Test Facilities

6.8.1 The following additional test facilities shall be available at Supplier’s works

a) Calibration of various testing and measuring equipment including


tensile testing machine, resistance measurement facilities, burette,
thermometer, barometer etc.
b) Standard resistance for calibration of resistance bridges.
c) Finished conductor shall be checked for length verification and surface
finish on separate rewinding machine at reduced speed (variable from
8 to 16 meters per minute). The rewinding facilities shall have
appropriate clutch system and shall be free from vibrations, jerks etc.
with transverse layering facilities.

7.0 INSPECTION

7.1 The Purchaser’s representative shall, at all times, be entitled to have access
to the works and all places of manufacture where conductor shall be
manufactured and the representative shall have full facilities for unrestricted
inspection of the Supplier’s works, raw materials and process of manufacture
and conducting necessary tests as detailed herein.

7.2 The Supplier shall keep the Purchaser informed in advance of the time of
starting and of the progress of manufacture of conductor in its various stages
so that arrangements can be made for inspection.

7.3 No material shall be dispatched from its point of manufacture before it has
been satisfactorily inspected and tests, unless the inspection is waived off by
the Purchaser in writing. In the later case also, the conductor shall be
dispatched only after satisfactory testing for all tests specified herein has
been completed and approved by the Purchaser.

7.4 The acceptance of any quantity of material shall in no way relieve the
Supplier of any of his responsibilities for meeting all requirements of the
specification, and shall not prevent subsequent rejection if such material is
later found to be defective.

7.5 At least 10% of the total number of drums subject to minimum of two in any
lot put up for inspection shall be selected at random to ascertain the length of
conductor by the following method.

“At the works of the manufacture of the conductor, the conductor shall be
transferred from one drum to another at the same time measuring its length
with the help of a graduated pulley & Cyclometer. The difference in the
average length thus obtained and as declared by the Supplier in the packing

- 10 -
list shall be applied to all the drums if the conductor is found short during
checking.”

8.0 DOCUMENTATION

8.1 Six sets of type test reports, duly approved by the Purchaser shall be
submitted by the Supplier for distribution, before commencement of supply.
Adequate copies of acceptance and routine test certificates, duly approved
by the Purchaser shall accompany the dispatched consignment.
8.2 Approval of drawing/work by Purchaser shall not relieve the Supplier of his
responsibility and liability for ensuring correctness and correct interpretation
of the latest revision of applicable standards, rules and codes of practices.
The material shall conform in all respects to high standards of engineering,
design, workmanship and latest revisions of relevant standards at the time of
ordering and Purchaser shall have the power to reject any work or material
which in his judgement is not in full accordance therewith.

9.0 PACKING & FORWARDING

9.1 The conductor shall be supplied in non-returnable, strong wooden drums


provided with lagging of adequate strength capable of withstanding
displacement during transit, storage and subsequent handling and stringing
operation in the field. The drums shall generally conform to IS: 1778-1980
except otherwise specified hereinafter.
9.2 The drums shall be suitable for wheel mounting and for jetting off the
conductor under a minimum controlled tension of the order of 5 kN.
9.3 The Supplier shall submit the proposed drum drawings alongwith the bid.
However, the same shall be in line with the requirements as stated herein.
After placement of the Letter of Award, the Supplier shall submit four copies
of fully dimensioned drawing of the drum he wishes to supply , for
Purchaser’s approval before taking up manufacturing of Conductor. After
getting approval from the Purchaser, the Supplier shall submit 30 more
copies of the approved drawing to Purchaser for further distribution and field
use at Purchaser’s end.
9.4 All wooden components shall be manufactured out of seasoned soft wood
free from defects that may materially weaken the component parts of the
drums. Preservative treatment for ani-termite/antifungus (Aldrime/Aldruse)
shall be applied to the entire drum with preservatives of a quality which is not
harmful to the conductor.
9.5 The flanges shall be of two/three ply construction with each ply at right
angles to the other and nailed together. The nails shall be driven from the
inside face flange, punched and then clenched on the other face. The
tolerance in thickness of each ply shall be +3 mm only. There shall be atleast
3 nails per plank of ply with maximum nail spacing of 75mm. Where a slot is
cut in the flange to receive the inner end of the conductor, the entrance shall
be in line with the periphery of the barrel.

- 11 -
9.6 The wooden battens used for making the barrel of the conductor shall be of
segmental type. These shall be nailed to the barrel supports with at least two
nails. The battens shall be closely butted and shall provide a round barrel
with smooth external surface. The edges of the battens shall be rounded or
chamfered to avoid damage to the conductor.
9.7 Barrel studs shall be used for construction of drums. The flanges shall be
holed and the barrel supports slotted to receive them. The barrel studs shall
be threaded over a length on either end, sufficient to accommodate washers,
spindle plates and nuts for fixing flanges at the required spacing. The Barrel
studs should be tack-welded with the nuts after tightening.
9.8 Normally, the nuts on the studs shall stand proud of the flanges. All the nails
used on the inner surface of the flanges and the drum barrel shall be
countersunk. The ends of barrel shall generally be flushed with top of the
nuts.
9.9 The inner check of the flanges and drum barrel surface shall be painted with
a bitumen based paint.
9.10 Before reeling, card board of double corrugated or thick bituminized
waterproof bamboo paper shall be secured to the drum barrel and inside of
flanges or the drum by means of a suitable commercial adhesive material.
The paper should be dried before use. Medium grade Kraft paper shall be
used in between the layers of the conductor. After reeling the conductor, the
exposed surface of the outer layer of conductor shall be wrapped with think
polythene sheet across the flanges to preserve the conductor from dirt, grit
and damage during transportation and handling and also to prevent ingress
of rain water during storage/transport.
9.11 A minimum space of 125mm shall be provided between the inner surface of
the external protective layer and outer layer of the conductor.
9.12 Each batten shall be securely nailed across grains as far as possible to the
flange edges with at least 2 nails per end. The length of the nails shall not be
less than twice the thickness of the battens. The nail shall not protrude above
the general surface and shall not have exposed sharp edges or allow the
battens to be released due to corrosion.
9.13 Outside the protective layer, there shall be a minimum of two binders
consisting of hoop iron/galvanized steel wire. Each protective layer shall
have two recess to accommodate the binders.
9.14 The conductor ends shall be properly sealed and secured with the help of U-
nails on one side of the flanges. The conductor shall be hinged by use of
galvanized steel wire/aluminium wire at three locations atleast 75mm apart or
more covered with PVC adhesive tape so as to avoid loosening of conductor
layers in transit and handling.

- 12 -
9.15 Only one length of conductor shall be wound on each drum.

9.16 Marking

Each drum shall have the following information stenciled on it in indelible ink
alongwith other essential data:
a) Purchase order number
b) Name and address of consignee
c) Manufacture’s name and address
d) Drum Number
e) Size of conductor
f) Length of conductor in meters
g) Gross weight of drum with conductor
h) Weight of empty drum with lagging
i) Arrow marking for unwinding

10.0 QUANTITY AND DELIVERY REQUIREMENT

Quantity and delivery requirement is set out in Annexure-I of this specification

11.0 GUARANTEED TECHNICAL PARTICUALRS

The guaranteed technical particulars duly signed are required to be furnished


by the bidder along with the tender as per Annexure-II.

- 13 -
ANNEXURE-I

QUANTITY AND DELIVERY REQUIREMENTS

Sr.No. Name of the material Qty.(Kms) Destination Delivery in


months
1 37/5.23 mm AAC

- 14 -
SECTION-7

TECHNICAL SPECIFICATION FOR SWITCHYARD ERECTION

1.0 GENERAL
This section covers the Technical requirements of various ancillary items and general
switchyard erection practices. All ancillary items under the Bidder’s scope of supply shall
conform to the type tests and routine tests as per the relevant standards.

1.1 STRING INSULATORS & HARDWARE


1.1.1 GENERAL
The insulators for suspension and tension strings shall conform to IS:731 and long
rod insulator shall conform to IEC-433(1980). Insulator Hardware shall conform to
IS:2486.

1.2 CONSTRUCTIONAL FEATURES

1.2.1 Suspension and tension insulator shall be wet process porcelain with ball
and socket connections. Insulator shall be interchangeable and shall be
suitable for forming either suspension or strings. Each insulator shall have
rated strength marking on porcelain printed and applied before firing.
1.2.2 Porcelain used in insulator manufacture shall be homogeneous, free from
Laminations, cavities and other flaws or imperfections that might affect the
mechanical or dielectric quality and shall be thoroughly vitrified, tough and
impervious to moisture.
1.2.3 Glazing of the porcelain shall be uniform brown colour, free from blisters,
burrs and other similar defects.
1.2.4 When operating at normal rated voltage there shall be no electric
discharge between conductor and insulator which would cause corrosion
or injury to conductor or insulator by the formation of substances due to
chemical action. No radio interferences shall be caused when operating at
normal rated voltage.
1.2.5 The design of the insulator shall be such that stresses due to expansion
and contraction in any part of the insulator shall not lead to deterioration.
All ferrous parts shall be hot dip galvanised in accordance with the latest
edition of IS:2629. the zinc used for galvanising shall be of grade Zn-99.5
as per IS-209. the zinc coating shall be uniform, adherent, smooth,
reasonably bright, continuous and free from imperfections such as flux,
ash, rust stains, bulky white deposits and blisters.

1.2.6 Bidder shall make available data on all the essential features of design
including the method of assembly of discs and metal parts, number of
discs per insulators, the manner in which mechanical stresses are
transmitted through discs to adjacent parts, provision for meeting
expansion stresses, results of corona and thermal shock tests,
recommended working strength and any special design or arrangement
employed to increase life under service conditions
1.2.7 Insulator Hardware shall conform to the requirements stipulated for clamps
and connectors. All Hardware shall be designed for tensile load with a
factor of safety 2.
1.2.8 Insulator Hardware shall be of forged steel. Malleable cast iron shall not
be accepted except for insulator disc cap. The surface of Hardware must
be clean, smooth, without cuts, abrasion or projections. No part shall be
subjected to excessive localized pressure. The metal parts

shall not produce any noise-generating corona under operating conditions.

-1-
1.2.9 The tension insulator string shall be designed for the required tensile load
Earth wire tension clamp shall be designed for the required tensile load
with a factor of safety two (2).
1.2.10 The tension insulator string assembly shall be supplied along with suitable
turnbuckle at the rate of one turnbuckle per string.
1.2.11 All Hardware shall be bolted type.

1.3 TESTS

In accordance with the requirements stipulated in section1 and section2, the


suspension and tension strings, insulator discs and Hardware shall be conform to
type tests as per relevant IS/IEC and shall be subjected to the following
acceptance tests and routine tests.

1.3.1 ACCEPTANCE TESTS FOR DISC INSULATOR


a) Visual Examination (IS 2486-1971) Part 1.
b) Verification of Dimensions : Cl no. 10.5 IS:731-1971
c) Temperature cycle test: Cl no. 10.6 IS:731-1971
d) Puncture Test: Cl no. 10.10 IS:731-1971
e) Galvanising Test: CI no. 10.12 IS:731-1971
f) Mechanical performance test : IEC:575-1977 Cl.4
g) Test on locking device for ball and socket coupling IEC:372(2)-1976.
h) Porosity test Cl no. 10.11 IS:7311-971.

1.3.2 ACCEPTANCE TEST ON HARDWARE FITTING

a) Visual Examination: CI. 5. 10 IS:2486 (Part-1).

b) Verification of Dimensions :CI. 5.8 IS:2486 (part-I)-1971.

c) Galvanizing/Electroplating tests : CI. 5.9 IS:2486 (Part-I)-1971.

d) Slip strength test :CI 5.4 of IS:2486 (Part-I).

e) Shore hardness test for the Elasto-meters (if applicable as per the value
guaranteed by the Bidder).

f) Mechanical strength test for each component.

g) The load shall be so supplied that the component is stressed in the same way as
it would be in actual service and the procedure as given in 13.1 (g) above should
be followed.

h) Test on locking devices for ball and socket coupling : IEC:372(2) – 1976.

1.3.3 ROUTINE TEST ON DISC INSULATOR/ LONG ROAD INSULATOR

a) Visual inspection :Cl. No. 10.13 IS:731-1971.

b) Mechanical Routine Test : Cl. No. 10.14 IS:731-1971.

c) Electrical Routine Test: Cl. No. 10.15 IS:731-1971.

-2-
1.3.4 ROUTINE TEST OF HARWARE FITTINGS
a) Visual examination :Cl. 5.10 of IS-2486(I).
b) Mechanical strength test: Cl. 5.10 of IS-2486 (I).
Samples taken from the zinc ingot shall be chemically analyzed as per IS:209 - 1966. The
purity of zinc shall not be less than 99.5%.

c) Chemical Analysis, mechanical hardness tests and magnetic – particle


inspection for malleable casting:
The chemical analysis, hardness tests and magnetic particle inspection for
malleable castings will be as per the internationally recongnised procedures for
these tests. The sampling will be based on heat number and heat treatment
batch. The details regarding tests will be as discussed and mutually agreed to by
the Bidder and HVPNL in Quality Assurance Program.

d) CHEMICAL ANALYSIS, HARDNESS TESTS AND MAGNETIC PARTICLE FOR


FORGINGS
The chemical analysis, hardness tests and magnetic particle inspection for
forgings will be as per the internationally recognized procedures for these tests.
The sampling will be based on heat number and heat treatment batch.

e) CHEMICAL ANALYSIS, HARDNESS TESTS AND MAGNETIC PARTICLE


INSPECTION FOR FABRICATED HARDWARE:
The chemical analysis, hardness tests and magnetic particle inspection for
fabricated hardware will be as per the internationally recognised procedures for
these tests. The sampling will be based on heat number and heat treatment
batch.

1.4 PARAMETERS

1.4.1 DISC INSULATORS

a) Type of insulators : Fog type

b) Size of insulator units (mm) : 280 x 145 for 12000 kg.


255 x 145 for 9000/4500 kg.

c) Electro mechanical strength : 12000/ 9000/ 4500 kg for Twin/


single conductor.

d) Creepage distance of individual : Markings on porcelain shall be


insulator units (minimum and as printed and applied before firing.
required to meet total creepage
distance).e) Markings.

1.4.2 INSULATOR STRING

220 kV 66 kV 11 kV

f) Power frequency
withstand voltage 460 kV 140 kV 28 kV
of the complete (rms) (rms) (rms)
string with arcing
horns (dry & wet)

-3-
g) Lightning impulse 1050 kV 325 kV 75 kV
withstand voltage
of the complete
string with corona
control rings (+ and
– peaks)
i) Power frequency 1.3 times actual wet flashover voltage of
puncture withstand the unit.
voltage for a string
insulator unit.
j) RIV level of the complete 1000 micro volts
string with CC rings at
1.1 U/-3 (max)
k) Total creepage distance
of the complete insulator ---------------- 25 mm/kV ------------------
string (mm)
l) Total no. of discs per 15 S/T 6 S/T 2 S/T
strings. 14 S/S 5 S/S 2 S/S
1.4.3 C-WEDGE AMPACT CONNECTOR
The Fired ‘C’ wedge connector will consist of a sprint ‘C’ and a wedge made from a
special Aluminium alloy of high ductility and electrical conductivity. These Fired wedge
connectors will use a power-activated cartridge for installation with the proper conductor
combinations. When connected, these taps will provide a tenable electrical and
mechanical connection for solid, stranded or compressed conductor combinations
including AAC, AAAC & ACSR. Fired wedge connectors will consist of groups coded by
different colors according to their cartridge power. The dimensions for the wedge shall be
manufactured to close tolerance to ensure repeatability and reliability of the connection.
All sharp edges and burrs shall be removed. The wedges shall be burnished to achieve
optimum surface roughness for electrical contact.
The Fired Aluminimum wedge connector shall meet the current cycle test requirements
as per ANSI C119.4-1998 Class AA.
The Fired Aluminium Wedge connector shall meet the mechanical requirements as per
ANSI C119.4-1998 Class-3, minimum tension. When tested as specified, taps shall not
break or separate from cable (wire) until attaining minimum tensile load specified or 5% of
the rated cable strength of the weaker conductor.

2) ACSR MOOSE/ ZEBRA CONDUCTOR


2.1 DETAILS OF CONDUCTOR
2.1.1 The conductor shall conform to IS:398(Part V)-1982 except where otherwise specified
herein.
2.1.2 The details of the conductor are tabulated below:
Moose Zebra
a) Stranding and wire diameter 54/3.53mm 54/3.18mm
AL+7/3.53mm steel AL+7/3.18mm steel
b) Number of strands
core 1 1
1st Layer 6 6
2nd Layer 12 12
rd
3 Layer 18 18
th
4 Layer 24 24

c) Sectional area of Aluminium 528.5 mm2 428.9 mm2

-4-
d) Total sectional area 597 mm2 484.50 mm2
e) Overall diameter 31.77mm 28.62 mm
f) Approximate weight 1998 kg/km 1621 kg/km
g) Calculated DC resistance at 0.05595 ohm/km 0.06868 ohm/km
20 degree C
h) Minimum UTS 159.60 KN 130.32 KN
2.1.3 The details of aluminium strand are as follow:
i) Minimum breaking load of strand 1.57 kN 1.29 kN
before stranding
ii) Minimum breaking load of strand 1.49 kN 1.23 kN
after stranding
iii) Maximum D.C resistance of 2.954 ohms/KM 3.651 ohms/KM
strand at 200C
2.1.4 The details of steel strand are as follows:
i) Minimum breaking load of strand 12.86 kN 10.43 kN
before stranding
ii) Minimum breaking load of strand 12.22 kN 9.95 kN
after stranding
iii) Minimum no. of twist to be with 18-before stranding 18-before stranding
stood in torsion test when tested 16-after stranding 16-after stranding
on a gauge length of 100 times
diameter of wire
2.2) WORKMANSHIP
2.2.1 The finished conductor shall be smooth, compact, uniform and free from all imperfections
including spills and splits, die marks, scratches, abrasions, scuff marks, kinks (protrusion
of wires), dents, press marks cut marks, wire cross over riding, looseness(wire being
dislocated by finger/hand pressure and/or unusual bangle noise on tapping) material
inclusion, white rust, powder formation or black spots(on account of reaction with trapped
rain water etc., dirt, grit etc.
2.2.2 All the Aluminium and steel strands shall be smooth, uniform and free from imperfections,
such as spill, diemarks, scratches, abrasions and kinks after drawing.
2.2.3 The steel strands shall be hot dip galvanised and shall have a minimum zinc coating of
250 gm/sq.m after stranding of the uncoated wire surface. The zinc coating shall be
smooth, continuous and of uniform thickness, free from imperfections and shall withstand
minimum two and half dips after stranding in standard preece test. The steel wire rods
shall be of such quality and purity that when drawn to the size of the strands specified
and coated with zinc, the finished strands and the individual wires shall be of uniform
quality and have the same properties and characteristics as prescribed in IEC 888-1987.
2.2.4 The steel strands shall be preformed and post formed in order to prevent spreading of
strands in the event of cutting of composite core wire. Care shall be taken to avoid
damage to galvanisation during pre-forming and post-forming operation.

2.3) JOINTS IN WIRES

2.3.1 ALUMINIUM WIRES

No joints shall, be permitted in the individual wires in the outermost layer of the finished
conductor. However, joints in the 12 wire and 18 wire inner layers of the conductor shall
-5-
be allowed but these joints shall be made by cold pressure butt welding and shall be such
that no such joints are within 15 meters of each other in the complete stranded conductor.

2.3.2 STEEL WIRES

There shall be no joints of any kind in the finished wire entering into the manufacture of
the strand. There shall also be no strand splices in any length of the completed stranded
steel core of the conductor.

2.4) TOLERANCES
The manufacturing tolerances to the extent of the following limits only shall be permitted in
the diameter of individual Aluminium and steel strands and lay-ratio of the individual
Aluminium and steel strands and lay-ratio of the conductor:

a) Diameter of Aluminium and steel strands:


Nominal Maximum Minimum
Aluminium
Moose
3.53 mm 3.57mm 3.49mm
Zebra
3.18 mm 3.21 mm 3.15 mm
Steel
Moose
3.53mm 3.60mm 3.46mm
Zebra
3.18 mm 3.24 mm 3.12 mm

b) Lay ratio of Conductor:


MOOSE ZEBRA
Maximum Minimum Maximum Minimum
Steel 6 wire 28 13 28 13
layer
Aluminium 12 wire 17 10 17 10
layer
18 wire 16 10 16 10
layer
24 wire 14 10 14 10
layer

-6-
2.5) MATERIALS

2.5.1 ALUMINIUM
The Aluminium strands shall be hard drawn from electrolytic Aluminium rods having purity
not less than 99.5% and a copper content not exceeding 0.04%.

2.5.2 STEEL
The steel wire strands shall be drawn from high carbon steel wire rod and shall conform
to the following chemical composition:

Element %Composition
Carbon 0.50 to 0.85
Manganese 0.50 to 1.10
Phosphorous Not more than 0.035
Sulphur Not more than 0.045
Silicon 0.10 to 0.35

2.5.3 ZINC
The Zinc used for galvanising shall be electrolytic High Grade Zinc of 99.95% purity. It
shall conform to and satisfy all the requirements of IS:209-1992.

2.6 STANDARD LENGTH


2.6.1 The Conductor shall be supplied in standard length of 1500/1800 meters as required. No
joint shall be allowed within a single span of stringing.

2.7 TESTS:

In accordance with the requirements stipulated in Section 1 and Section 2, the conductor
shall conform to type tests as per relevant IS/IEC and shall be subjected to the following
acceptance tests and routine tests:
2.7.1 ACCEPTANCE TESTS
a) Visual check for joints, )
scratches etc. and ) IS:398 (Part – V) 1982
lengths of conductor. )

b) Dimensional check on )
steel and Aluminium )
strands. )

c) Check for lay ratios of )


various layers. )

d) Galvanising test on steel )


strands. )

e) Torsion and Elongation


test on steel strands

f) Breaking load test on ) IS:398 (Part – V) 1982


steel and Aluminium ) Clause 12.5.2, 12.7 & 12.8
strands. )

g) Wrap test on steel and )


Aluminium strands )
-7-
h) DC resistance test on )
Aluminium strands. )

i) UTS test on welded joint )


of Aluminium strands. )
)

NOTE:

All the above tests except test mentioned at (I) shall be carried out on Aluminium and
steel strands after stranding only.

2.7.2 ROUTINE TESTS

a) Check to ensure that the joints are as per specification.


b) Check that there are no cuts, fins etc. on the strands.
c) All acceptance test as mentioned above to be carried out on each coil.

2.7.3 TESTS DURING MANUFACTURING

a) Chemical analysis of zinc )


used for galvanising. )

b) Chemical analysis of )
Aluminium used for making )
Aluminium strands. )

c) Chemical analysis of steel )


used for making steel )
strands. )

3.0 GALVANISED STEEL EARTHWIRE

3.1 DETAILS OF EARTHWIRE

3.1.1 The galvanised steel earth wire shall generally conform to the Specification of ACSR core
wire as mentioned in IS:398 (Part-II)-1976 except where otherwise specified herein.
3.1.2 The details of the earthing are tabulated below:

a) Stranding and wire diameter : 7/3.66 mm steel


b) Number of strands
Steel core : 1
Outer steel layer : 6
c) Total sectional area : 73.65 mm2
d) Overall diameter : 10.98 mm
e) Approximate weight : 583 kg/km
f) Calculated d.c. resistance at 200C : 2.5 Ohms/km
g) Minimum ultimate tensile strength : 68.4 KN
h) Direction of lay of outer layer : Right hand

-8-
3.2 WORKMANSHIP

3.2.1 All steel strands shall be smooth, uniform and free of all imperfections, such as spills and
splits, die marks, scratches, abrasions and kinks after drawing and also after stranding.
3.2.2 The finished material shall have minimum brittleness, as it will be subjected to
appreciable vibration while in use.
3.2.3 The steel strands shall be hot dip galvanised and shall have a minimum zinc coating of
275 gms/sq. m.) after stranding of the uncoated wire surface.

The zinc coating shall be smooth, continuous, of uniform thickness, free from
imperfections and shall withstand three and a half dips after stranding in standard preece
test. The steel wire rod shall be of such quality and purity that, when drawn to the size of
the strands specified and coated with zinc, the finished strands shall be of uniform quality
and have the same properties and characteristics in ASTM designation B498-74.
3.2.4 The steel strands shall be performed and post formed in order to prevent spreading of
strands while cutting of composite earth wire. Care shall be taken to avoid damage to
galvanization during pre forming and post forming operation.
3.2.5 To avoid susceptibility towards wet storage stains (white rust), the finished material shall
be provided with a protective coating of boiled linseed oil.

3.3 JOINTS IN WIRES


There shall be no joint of any kind in the finished steel wire strand entering into the
manufacture of the earth wire. There shall be no strand joints or strand splices in any
length of the completed stranded earth wire.

3.4 TOLERANCES
The manufacturing tolerances to the extent of the following limits only shall be permitted
in the Diameter of the individual steel strands and lay length of the earth wire:

Standard Maximum Minimum

Diameter 3.66 mm 3.75 mm 3.57 mm

Lay length 181 mm 198 mm 165 mm

3.5 MATERIALS

3.5.1 STEEL
The steel wire strands shall be drawn from high carbon steel rod and shall conform to the
following requirements as to the chemical composition: -

Element
%Composition

Carbon Not more than 0.55


Manganese 0.4 to 0.9
Phosphorus Not more than 0.04
Sulphur Not more than 0.04
Silicon 0.15 to 0.35

-9-
3.5.2 ZINC
The zinc used for galvanising shall be electrolytic High Grade Zinc of 99.95% purity. It
shall conform to and satisfy all the requirements of IS:209-1979.

3.6 STANDARD LENGTH

3.6.1 The earth wire shall be supplied in standard drum length of manufacturer as per actual
requirement.

3.7 TESTS

In accordance with the requirements stipulated in Section1 and Section2, earth


wire shall conform to type tests as per relevant IS/IEC and shall be subjected to
the following acceptance tests and routine tests:

3.7.1 ACCEPTANCE TESTS


a) Visual check for joints, )
scratches etc. and length )
of Earth wire. )

b) Dimensional check )

c) Galvanising test )

d) Lay length check )

e) Torsion test )

f) Elongation test )

g) Wrap test )

h) DC resistance test ) IS:398 (Part – III) 1976

i) Breaking load test )

j) Chemical analysis of )
steel

3.7.2 ROUTINE TESTS

a) Check that there are no cuts, fins etc. on the strands.


b) Check for correctness of stranding.

3.7.3 TESTS DURING MANUFACTURING

a) Chemical analysis of zinc )


used for galvanising. )

b) Chemical analysis of steel )

- 10 -
4. MARSHALLING KIOSK

4.1 PRINCIPAL PARAMETERS


The Marshalling Kiosk shall be suitably fixed so as to provide no opening to inside
and shall be sufficiently projected to prevent splash of rainwater to the inside of
the Marshalling Kiosk.

The Marshalling Kiosk will be 1400 mm (height) 1200 mm (width) and 550 mm
(depth) complete with double door in front provided with pad-locking facility in the
door handle. The Marshalling Kiosk shall be bolted on the 550 mm high angle-iron
frame work made of 35x35x6 mm MS angle braced length-wise by 35x6 mm MS
Flat.

The Marshalling Kiosk shall be equipped with 3 No. earth test links made of tinned
copper for CT circuits.

4.2 TERMINAL BLOCK CONNECTORS


Terminal block shall conform to requirements given in Section 2(GTR).

The terminal connector will conform to the following details:

i) Current & Voltage Ratings 30 Amps, 660VAC/900 VDC


ii) Capacity up to three ring-tongue
crimped copper wires of 4
square mm, cross sectional area.
iii) a) disconnecting type terminal blocks for CTs and PTs Terminal connectors for
CT/PTs shall have provision of disconnecting and shortening links for
measurement of CT currents without opening the CTs and isolation of PT
circuits.

4.3 DISTRIBUTION OF TERMINALS AND THEIR IDENTIFICATION NUMBERS


The no. of terminals required shall be as follows:

220kV-300 & 66kV-200

The total number of terminals in the Marshalling Kiosk will be distributed in ten
rows. Terminal block connector row’s shall be adequately spaced and in no case
less than 100 mm apart center of the terminal block so as to permit convenient
access to terminations.

Labels in the form of plastic/steel plates carrying numerals for terminal


identification shall be so mounted as to cause no interference with regard to
access to terminal nuts. The numerals marked from top to bottom in ascending
order starting from left-hand side as viewed from the front of the Marshalling Kiosk
and a progressively increasing from left hand side to right hand side. The
numbering of Terminals and their arrangement in a 200 and 300 terminals
Marshalling Kiosks shall be as per sketch enclosed (Drg. No. C/ENG/HSEB/MB).

5. EARTHING CONDUCTORS

5.1 GENERAL
All conductors buried in earth and concrete shall be of mild steel. All conductors
above ground level and earthing leads shall be of galvanised steel.

5.2 CONSTRUCTIONAL FEATURES

5.2.1 GALVANISED STEEL


- 11 -
a) Steel conductors above ground level shall be galvanised according to IS:2629.
b) The minimum weight of the zinc coating shall be 610 gm/sq.m. and minimum
thickness shall be 85 microns.
c) The galvanised surfaces shall consist of a continuous and uniformly thick coating
of zinc, firmly adhering to the surfaces of steel. The finished surface shall be clean
and smooth and shall be free from defects like discolored patches, bare spots,
unevenness of coating, spelter which is loosely attached to the steel globules,
spiky deposits, blistered surfaces, flaking or peeling off etc. The presence of any
of these defects noticed on visual or microscopic inspection shall render the
material liable to rejection.

5.3 TESTS
Galvanised steel shall be subjected to four one minute dips in copper sulphate
solution as per IS:2633.

6. SPACERS

6.1 GENERAL
Spacers shall conform to IS-10162.

6.2 CONSTRUCTIONAL FEATURES

6.2.1 No magnetic material shall be used in fabrication of spacers except for GI Bolts
and nuts.
6.2.2 Spacer design shall be made to take care of fixing and removing during
installation and maintenance.
6.2.3 The design of the spacers shall be such that the conductor does not come in
contact with any sharp edge.

6.3 TESTS

6.3.1 In accordance with requirements stipulated in Section1 and Section2, each type of
spacer shall conform to type tests as per relevant IS/IEC and shall be subjected to
the following, acceptance tests and routine tests in addition to those specified in
IS/IEC: -

6.3.2 ACCEPTANCE TEST


The acceptance tests shall be as per IS:10162 (latest revision).

6.3.3 ROUTINE TEST

a) Visual Examination
b) Dimensional verification.

7. EARTHING
The earthing shall be in accordance with requirements given hereunder. The
earthmat design shall be done by the Bidder as per IEEE 80. The earthmat shall
be connected to the existing earthmat in case of substations where earthmat is
already laid.

7.1 GENERAL

7.1.1 Exact location of earthing connections shall be designed to suit the site
conditions.
7.1.2 Neutral points of system of different voltages, metallic enclosures and frame
works associated with all current carrying equipments and extraneous metal
works associated with electric system shall be connected to a single earthing
system unless stipulated otherwise.
- 12 -
a) Code of practice for Earthing IS:3043.
b) Code of practice for the protection of building and allied structures against
lightning IS:2309.
c) Indian Electricity Rules 1956 with latest amendments.
d) National Electricity Safety Code IEEE-80.

7.2 DETAILS OF EARTHING SYSTEM

ITEM SIZE MATERIAL


a) Main Earthing Conductor 40 mm dia Mild Steel
MS Rod

b) Conductor above ground & earthing 75x12 mm Galvanised Steel


leads (for equipment) GS Flat

c) Conductor above ground & earthing 75x12 mm Galvanised Steel


leads (for columns & aux. GS Flat
Structures)

d) Earthing of indoor LT panels, control 50x6 mm GS Galvanised Steel


panels marshalling Flat
boxes, MOM boxes, junction boxes
& lightning panels etc.

e) Rod electrode 40 mm dia, Mild Steel


3000 mm

f) Earthing for motors flat 25x3 mm Galvanised


steel

g) Earthing conductor along 50x6 mm GS Mild Steel


outdoor cable trenches primer Flat painted with Red
Oxide

7.3 EARTHING CONDUCTOR LAYOUT


7.3.1 Earthing conductors in outdoor areas shall be buried at least 600 mm below
finished grade level unless stated otherwise.
7.3.2 Wherever earthing conductors cross cable trenches, underground service ducts,
pipes, tunnels, railway tracks etc. It shall be laid minimum 300 mm below them
and shall be re-routed in case it fouls with equipment/structure foundations.
7.3.3 Tap-connections from the earthing grid to the equipment/structure to be earthed,
shall be terminated on the earthing terminals of equipment/structure.
7.3.4 Earthing conductors or leads along their run on cable trench, ladder columns,
beams, walls etc. shall be supported by suitable welding/cleating at intervals of
750 mm. Wherever it passage through walls, floors etc., galvanised iron sleeves
shall be provided for the passage of the conductor and both ends of

- 13 -
the sleeves shall be sealed to prevent the passage of water through the sleeves.
7.3.5 Earthing conductor around the building shall be buried in earth at a minimum
distance of 1500 mm from the outer boundary of the building. In case high
temperature is encountered at some location, the earthing conductor shall be laid
minimum 1500 mm away from such location.
7.3.6 Earthing conductor crossing the road shall be laid 300 mm below road or at a
greater depth to suit the site conditions.
7.3.7 Earthing conductor embedded in the concrete shall have approximately 50 mm
concrete cover.

7.4 Earthing for GIS

To limit the undesirable effects caused by circulating currents, the following


requirements should be met:

All metallic enclosures should normally operate at ground,

When grounded at the designated points, the bus enclosure design


should ensure that no significant voltage differences exist between
individual enclosure sections and that neither the supporting
structures nor any part of the grounding systems is adversely
influenced by the flow of induced currents.

To avoid the circulation of enclosure currents beyond regular return


path within the GIS assembly, power cable sheath grounds should
be tied to the ground system via connections that are separated
from the GIS enclosures. To facilitated this isolation, the design of
cable terminations (potheads) should be such that an isolating air
gap or proper insulation elements are provided.

Enclosure return currents also cannot be permitted to flow through


any externally mounted current transformers.

Further, GIS manufacturer shall provide and be responsible for:

Providing the subassembly-to-subassembly bonding to assure safe


voltage gradients between all intentionally grounded parts of the
GIS assembly and between those parts and the main ground bus
of the GIS.

Furnishing readily accessible connectors of sufficient mechanical


strength to withstand electromagnetic forces and normal abuse,
and that are capable of carrying the anticipated maximum fault
current in that portion of the circuit without overheating.

Providing ground pads or connectors, or both, allowing, at least, for


two paths to ground from the main bus, or from each metallic
enclosure and auxiliary piece of GIS equipment designated for a
connection to the station ground if the main ground bus of the GIS
assembly does not actually exist. Proposing essential method for
connections between different type of metals, typically between a
copper cable or a similar ground conductor and aluminium
enclosure.

The following points should also be considered for GIS Grounding:

Precautions should be undertaken to prevent excessive currents


from being induced into adjacent frames, structures, or reinforcing
- 14 -
steel and to avoid establishment of current loops via other station
equipment, such as transformers or separate switchgear. If there is
the possibility of undesirable current loops via ground connections,
or if any sustained current path might partially close or pass
through grounded structures, the station grounding scheme and
the physical layout should be carefully reviewed.

Equal care is needed in the proximity of discontinuities in enclosure


grounding paths at the transformer connections to GIS and at the
interface points to conventional switchgear to prevent circulating
currents in the circuit breaker and transformer tank steel.

Where applicable, all isolating elements should be able to withstand to full


potential difference that may occur between the locally grounded system and that
external to GIS. The isolation of metal parts shall be made by means of ceramic
or plastic inserts. Adequate creepage distance shall be ensured.

7.5 EQUIPMENT AND STRUCTURE EARTHING

7.5.1 Earthing pads shall be provided by the Bidder of the apparatus/equipment at


accessible position. The connection between earthing pads and the earthing grid
shall be made by short and direct earthing leads free from kinks and splices. In
case earthing pads are not provided on the item to be earthed, same shall be
provided in consultation with engineer.

7.5.2 Whether specifically shown in drgs. or not, steel/structure columns, metallic stairs
etc. shall be connected to the nearby earthing grid conductor by two earthing
leads. Electrical continuity shall be ensured by bonding different sections of hand-
rails and metallic stairs.
7.5.3 Metallic pipes, conduits and cable tray sections for cable installation shall be
bonded to ensure electrical continuity and connected to earthing conductors at
regular. Apart from intermediate connections, beginning points shall also be
connected to earthing system.
7.5.4 Metallic conduits shall not be used as earth continuity conductor.
7.5.5 A separate earthing conductor shall be provided for earthing lighting fixtures,
receptables, switches, junction boxes, lighting conduits etc.
7.5.6 Wherever earthing conductor crosses or runs along metallic structures such as
gas, water, steam conduits etc. and steel reinforcement in concrete it shall be
bonded to the same.
7.5.7 Light poles, junction boxes on the poles, cable and cable boxes/glands, lockout
switches etc. shall be connected to the earthing conductor running along with the
supply cable which in turn shall be connected to earthing grid conductor at a
minimum two points whether specifically shown or not.
7.5.8 Railway tracks within switchyard area shall be earthed at a spacing of 30 mm and
also by both the ends.
7.5.9 Earthing conductor shall be buried 500 mm inside the switchyard fence. Every
alternate post of the fence and gates shall be connected to earthing loop by one
lead.
7.5.10 Flexible earthing connectors shall be provided for the moving parts.
7.5.11 All lighting panels, junction boxes, receptables fixtures, conduits etc. shall be
grounded in compliance with the provision of I.E. rules.
7.5.12 A continuous ground conductor of 16 SWG GI wire shall be run all along each
conduit run and bonded at every 600 mm by not less than two turns of the same
size of wires. The conductor shall be connected to each panel ground bus. All
junction boxes, receptables, lighting fixtures etc. shall be connected to this 16
SWG ground conductor.
7.5.13 50 mm x 6 mm MS flat shall run on the top tier and along the cable trenches and
the same shall be welded to each of the racks. Further this flat shall be earthed at
- 15 -
both the ends at an interval of 30 mtrs. The MS flat shall be finally painted with
two coats of Red Oxide primer and coats of post office and red enamel paint.

7.6 JOINTING

7.6.1 Earthing connections with equipment earthing pads shall be bolted type. Contact
surfaces shall be free from scale, paint, enamel, grease, rust or dirt. Two bolts
shall be provided for making each connection. Equipment bolted connections,
after being checked and tested, shall be painted with anti-corrosive
paint/compound.
7.6.2 Connection between equipment earthing lead and main earthing conductors and
between main earthing conductors shall be welded/brazed type. For rust
protections, the welds should be treated with red lead and afterwards thickly
coated with bitumen compound to prevent corrosion.
7.6.3 Steel to copper connections shall be brazed type and shall be treated to prevent
moisture ingression.
7.6.4 Resistance of the joint shall not be more than the resistance of the equivalent
length of the conductor.
7.6.5 All ground connections shall be made by electric arc welding. All welded joints
shall be allowed to cool down gradually to atmospheric before putting any load on
it. Artificial cooling shall not be allowed.
7.6.6 Bending of large rod/thick conductor shall be done preferably by gas heating.
7.6.7 All arc welding with large dia. Conductors shall be done with low hydrogen content
electrodes.

7.7 POWER CABLE EARTHING


Metallic sheaths and armour of all multi core power cables shall be earthed at
both equipment and switchgear end. Sheath and armour of single core power
cable shall be earthed at switchgear end only.

7.8 SPECIFIC REQUIREMENT FOR EARTHING SYSTEMS

7.8.1 Each earthing lead from surge arrestor and the neutral of the power transformer
shall be directly connected to two pipe electrodes in independent treated earth pit
up to water level which in turn, shall be buried in cement concrete pit with a cast
iron cover hinged to a cast iron frame to have an access to the joints. All
accessories associated with the power transformer shall be connected to the
earthing grid at a minimum two points.
7.8.2 Earthing terminal of each capacitor voltage transformer and down conductors of
tower with peak etc. shall be directly connected to rod electrode which in turn,
shall be connected to station earthing grid.
7.8.3 Auxiliary earthing mat comprising of closely spaced (300mm x 300mm)
conductors shall be provided at depth of 300 mm from ground level below the
operating handles of the MOM Boxes of Isolators. MOM Boxes shall be directly
connected to the auxiliary earthing mat.
7.8.4 Earthing of each Post Insulator base of Isolator and support Insulators of circuit
Breakers is required to be connected with earthing strip.
7.8.5 The earthing strips are required to be connected at the top of support structure on
both sides and not at bottom.
7.8.6 Insulating strings in the gantry beam are required to be connected at the base
with common strip.

7.9 SPECIFIC REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEM

7.9.1 Conductors of the lightning protection system shall not be connected with the
conductors of the safety earthing above ground level.
7.9.2 Down conductors shall be cleated on the structures at 2000 mm interval.
- 16 -
7.9.3 Connection between each down conductor and rod electrodes shall be made via
test joint located approximately 1500 mm above ground level. The bidders shall
include the cost of test links in the erection price component of respective
equipment/structure and no extra payment shall be made for the same.
7.9.4 Lightning conductors shall not pass through or run inside G.I. conduits.
7.9.5 All metallic structures within a vicinity of 2000 mm in air and 5000 mm below
ground shall be bounded to the conductors of lightning protection system.

8.1 LIGHTNING PROTECTION

8.1.1 Direct stroke lightning protection (DSLP) shall be provided in the switchyard by
shield wires. The layout drawings enclosed indicate arrangement. The final
arrangement shall be decided after approval of the DSLP calculations. Rezvik
method of lightning protection shall be followed. Any additional expenditure resulting
from change of layout if required shall be to the firm’s account.

8.1.2 The lightning protection system shall not be in direct contact with underground
metallic service ducts and cables.

8.2 PROTECTION OF SUBSTATION BUILDING AGAINST LIGHTNING

The protection system shall be supplied according to British Standards, BSI 6651:1985;

The protection system shall cover indoor and outdoor protection of structure against
lightning. The lightning protection system shall be composed of the following principal
components:

Air terminations,
Down conductors,
Joints & bolts,
Test joints,
Earth terminations,
Earth electrodes,

The protection system shall be avoided from corrosions.

The Contractor shall submit to the Employer the type and electrical characteristics of
protection system with technical documents for approval before installations. All lightning
protection system shall be visually inspected by a competent person of the Contractor
during installation,

After installation of protection system, the following measurements and checks shall be
performed by the Contractor under the witness of Employer's representatives according
to BS.6651:1985

Visually check in order to verify that they are in accordance with the
reference standards. The resistance to earth of the earth termination
network and of each earth electrode. The results of a visual check of all
conductors and joints or their measured electrical continuity.

9. MAIN BUS BARS

- 17 -
9.1 The brief description of the bus switching scheme, bus bar layout and equipment
connection already adopted are indicated in the SLDs enclosed with Section 1.
The bidder shall furnish supporting calculations for the bus bars/conductors to show
adequacy of design parameters for:

a) Cantilever strength of Post Insulators.


b) Short circuit forces and spacer location for each span of ACSR conductor
stringing.
c) Earthing design calculations.
d) Direct stroke lightning protection.
e) Ampacity calculations.

10. BAY EQUIPMENT #

The disposition of various bay equipment is shown in single line diagrams and
standard section drawing/layout drawing enclosed with Section 1.

11. TERMINAL POINTS

The terminal points for the scope of work of switchyard are given below: -

11.1 LINE FEEDERS


The transmission line shall terminate on line side gantry structure. The supply and
erection of tension insulator string for line termination and tension clamps for
earthwire are included in the scope of the bidder.
11.2 Lightning protection down conductor at this end, tap offs and jumper connections
from this dead end to all equipment in the switchyard are in Bidder’s scope.

12 EQUIPMENT ERECTION NOTES

12.1.1 All support insulators, circuit Breaker interrupters and other fragile equipment shall
preferably be handled with cranes having suitable booms and handling capacity.

12.1.2 The slings shall be of sufficient length to avoid any damage to insulator due to excessive
swing, scratching by sling ropes etc.

12.1.3 Handling equipment, sling ropes etc. should be tested periodically before erection for
strength.

12.1.4 Bending of compressed air piping should be done by a bending machine and through
cold bending only. Bending shall be such inner diameter of pipe is not reduced.

12.1.5 Cutting of the pipes wherever required shall be such as to avoid flaring of the ends.
Hence only a proper pipe cutting tool shall be used. Hacksaw shall not be used.

12.1.6 Muslin or leather cloth shall be used for cleaning the inside and outside of hollow
insulators.

12.1.7 All the equipment, instruments and auxiliaries required for testing and commissioning of
equipment shall be arranged at site by the Bidder.

12.2 STORAGE
The Bidder shall provide and construct adequate storage shed for proper storage of
equipments, where sensitive equipments shall be stored indoors. All equipments during
storage shall be protected against damage due to acts of nature or accidents. The
storage instructions of the equipment manufacturer/HVPNL shall be strictly adhered to.

13 CABLE TAGS AND MARKERS


- 18 -
13.1 Each cable and conduit run shall be tagged with numbers that appear in the cable and
conduit schedule.
13.2 The tag shall be of Aluminium with the number punched on it and securely attached to
the cable conduit by not less than two turns of 20 SWG GI wire conforming to IS:280.
Cable tags shall be of rectangular shape for power cables and circular shape for control
cables.
13.3 Location of cables laid directly underground shall be clearly indicated with cable marker
made of galvanised iron plate.
13.4 Location of underground cable joints shall be indicated with cable marker with an
additional inscription “Cable Joints”.
13.5 The marker shall project 150mm above ground and shall be spaced at an interval of 30
meters and at every change in direction. They shall be located on both sides of road and
drain crossings.
13.6 Cable tags shall be provided on all cables at each end (just before entering the
equipment enclosure), on both sides of a wall or floor crossing, on each duct/conduit
entry and at every twenty meters (20 m) in cable tray/trench runs. Cable tags shall be
provided inside the switchgear, motor control centers, control and relay panels etc.,
wherever required for cable identification, where a number of cables enter together
through a gland plate.
13.7 CABLE SUPPORTS AND CABLE TRAY MOUNTING ARRANGEMENTS
13.7.1 The Bidder shall provide embedded steel insert on concrete floors/walls to secure
supports for by welding to these inserts or available building steel structures, for the
purpose of casting in the control room.
13.7.2 The supports shall be fabricated from standard structural steel members.
13.7.3 Insert plates will be provided at an interval of 750 mm wherever cables are to be
supported without the use of cable trays, such as in trenches, while at all other places
these will be an interval of 1000 mm (as per drg. attached).

13.8 CABLE TERMINATION AND CONNECTIONS


13.8.1 The termination and connection of cables shall be done strictly in accordance with cable
and termination kit manufacturer’s instructions, drawing and/or as directed by the HVPNL.
13.8.2 The work shall include all clamping, fittings, fixing, plumbing, soldering, drilling, cutting,
taping, heat shrinking, (where applicable), connecting to cable terminal, shorting and
grounding as required to complete the job.
13.8.3 Supply of all consumable material shall be included in the scope of the Bidder.
13.8.4 The equipment will be generally provided with un-drilled gland plates for cables/conduit
entry. The Bidder shall be responsible for drilling of gland plates painting and touching up.
Holes shall not be made by gas cutting.
13.8.5 Control cable cores entering control panels /switchgear /MCC / miscellaneous panels
shall be neatly bunched, clamped and tied with nylon strap or PVC perforated strap to
keep them in position.
13.8.6 The Bidder shall tag/ferrule control cable cores at all terminations, as instructed by the
HVPNL. In panels where a large number of cables are to be terminated and cable
identification may be difficult, each core ferrule may include the complete cable no. as
well

- 19 -
13.8.7 Spare cores shall be similarly tagged with cable numbers and coiled up.
13.8.8 All cable entry points shall be sealed and made vermin and dust proof. Unused openings
shall be effectively closed.
13.8.9 Double compression type tinned/nickel plated brass cable glands shall be provided by the
Bidder for all power and control cables to provide dust and weather proof terminations.
13.8.10 The cable glands shall be tested as per BS:6121. They shall comprise of heavy duty
brass casting, machine finished and tinned to avoid corrosion and oxidation. Rubber
components used in cable glands shall be neoprene and of tested quality. The cable
glands shall be of approved make.
13.8.11 The cable gland shall also be tested for dust proof and weather proof termination. The
test procedure has to be discussed and agreed to between the HVPNL and cable glands
manufacturer.
13.8.12 If the cable and box or the terminal enclosure provided on the equipment is found
unsuitable and requires modification, the same shall be carried out by the Bidder, as
directed by the HVPNL.
13.8.13 Crimping tool shall be of approved design and make.
13.8.14 Cable lugs shall be tinned copper solderless crimping type conforming to IS:8309 and
8394. The cable lugs shall be of approved make.
13.8.15 Solderless crimping of terminals shall be done by using corrosion inhibitory compound.
The cable lugs shall suit the type of terminals provided.
14. DIRECTLY BURIED CABLES
14.1 The Bidder shall construct the cable trenches required for directly buried cables. The
scope of work shall include excavation, preparation of sand bedding, soil cover, supply
and installation of brick or concrete protective covers back filling and ramming supply and
installation of route markers and joint markers. The Bidder shall ascertain soil conditions
prevailing at site, before quoting the unit rates.
14.2 The power and control cable between LT station, Control room, shall be laid in the buried
cable trenches. Further, for lighting purposes also, buried cable trench can be used in the
outdoor area.
14.3 Cable route and joint markers and RCC warning covers shall be provided wherever
required. The voltage grade of cables shall be engraved on the marker.

15. INSTALLATION OF CABLES


15.1 Cabling shall be on cable racks, in built-up trenches, vertical shafts, excavated trenches
for direct burial, pulled through pipes, and conduits laid in concrete ducts, run bare and
clamped on wall/ceiling/steel structures etc. as shown in the drawings in detailed
engineering stage. Where specific cable layouts are not shown on drawings, Bidder
shall route these as directed by the HVPNL.
15.2 The Bidder shall fabricate and install mounting arrangements for the support and
installation of all the cables on angles at 1000 mm spacing in the trenches, as shown in
the drawing enclosed with Specification. These mounting structures/cable racks shall
be fabricated from structural steel members (channels, angles and flats) of the required
size. The fabrication, welding and erection of these structures shall conform to the
relevant clauses of Section STR, in addition to the Specifications given herein.
15.3 Cable racks and supports shall be painted after installation with two coats of metal
primer (comprising of red oxide zinc chromate in a synthetic medium) followed by two
finishing coats of Aluminium paint. The red oxide and zinc chromate shall conform to
IS:2074. All welding works inclusive of the consumables required for Specifications given
herein.
15.4 All inter pole cables (power & control) for all equipment shall be laid in cable trenches/Gl
conduit pipes of NB 50/100 mm diameter, class medium as per IS 4736 which shall be
buried in the ground at a depth of 250 mm. The interpole cabling piping of Breakers shall
be laid in cable trenches. The scope shall include all labour,

- 20 -
material, equipment for transporting, laying, burying etc. including required bends and
seals.
15.5 Cable shall be generally located adjoining the electrical equipment through the pipe
insert embedded in the floor. In the case of equipments located away from cable trench
either pipe inserts shall be embedded in the floor connecting the cable trench and the
equipment or in case the distance is small, notch/opening on the floor shall be provided.
In all these cases necessary bending radius as recommended by the cable Bidder shall
be maintained. Cabling in the control room shall be done on ladder type cable trays.
15.6 Cables from the equipment to trench shall run in GI conduits. Necessary conduits of
adequate sizes and length shall be supplied and installed by the Bidder. Flexible conduit
should be used between fixed conduit/cable trays (perforated type) and equipment
terminal boxes, where vibration is anticipated. The flexible conduit shall be as per the
relevant IS.
15.7 Power and control cables shall be laid in separate tiers. The order of laying of various
cables shall be as follows, for cables other than directly buried:
Power Cable on top tiers.
Control instrumentation and others service cables in bottom tiers.
15.8 Single core cables in trefoil formation shall be laid with a distance of three times the
diameter of cable between trefoil centerlines. All power cables shall be laid with a
minimum center-to-center distance equal to twice the diameter of the cable.
15.9 Trefoil clamps for single core cable shall be pressure die cast Aluminium (LM-6), Nylon or
fibre glass and shall include necessary fixing GI nuts, bolts, washers etc. These are
required at every 2 meter of cable runs. The cost of supply and erecting these clamps
shall be made on the unit rate basis.

15.10 Power and control cable shall be securely fixed to the trays/supports with self locking type
nylon ties with deinterlocking facility at every 5 meter interval for horizontal run Vertical
and inclined cable runs shall be secured with 25 mm wide and 2 mm thick Aluminium
strip clamps at 2 m.
15.11 Cables shall not be bent below the minimum permissible limit. The permissible limits are
as follows:

Table of cable and Minimum bending radius voltage grade


Power cable 12 D.
Control cable 10 D.
D is overall diameter of cable.

15.12 The cables are to be laid in single layers on racks and are to be routed through culvert
whenever there is road crossing.
15.13 In each cable run some extra length shall be kept at a suitable point to enable one (for LT
cables)/two (for HT cables) straight through joints to be made in case the cable develop
fault at later date.
15.14 Selection of cable drums for each run shall be so planned as to avoid using straight
through joints. Cable splices will not be permitted except where called for by the
drawings, unavoidable or where permitted by the HVPNL. If straight through joints are
unavoidable, the Bidder shall use the straight through joints kit of reputed make.
15.15 Control cable terminations inside equipment enclosures shall have sufficient lengths so
that changing of termination blocks can be done without requiring any splicing.
15.16 Metal screen and armour of the cable shall be bonded to the earthing system of the
station, wherever required by the HVPNL.
15.17 Rollers shall be used at intervals of about two meters while pulling cables.
15.18 All due care shall be taken during unreeling, laying and termination of cable to avoid
damage due to twist, kinks, sharp bends etc.
15.19 Cable ends shall be kept sealed to prevent damage.
15.20 Inspection on receipt, unloading and handling of cables shall generally be in accordance
with IS:1255 and other Indian Standard Codes of practices.

- 21 -
15.21 Wherever cable pass through wall openings or other partitions, wall sleeves with bushes
having a smooth curved internal surface so as not to damage the cable, shall be
supplied, installed and properly sealed by the Bidder at no extra charges.
15.22 Bidder shall remove the RCC/Steel trench covers taking up the work and shall replace all
the trench covers after the erection-work in that particular area is completed or when
further work is not likely to be taken up for sometime.
15.23 Bidder shall furnish three of the report on work carried out in a particular week, indicating
cable numbers, date on which laid, actual length and route, testing carried out,
terminations carried out, along with the marked up copy of the cable schedule and
interconnection drawing wherever any modifications are made.
15.24 Bidder shall paint the tray identification number on each run of trays at an interval of 10
m.
15.25 In case the outer sheath of a cable is damaged during handling/installation, the Bidder
shall repair it at his own cost to the satisfaction of the HVPNL. In case any other part of a
cable is damaged, the same shall be replaced by a healthy cable at no extra cost to the
HVPNL, i.e. the Bidder shall be paid for installation and removal of the damaged cable.
15.26 All cable terminations shall be appropriately tightened to ensure secure and reliable
connections. The Bidder shall cover the exposed part of all cable lugs whether supplied
by him or not with insulating tape, sleeve or paint.
15.26.a Separate racks/trays will be utilised for different voltage levels from
switchyard to control room.
15.26.b All the cable trenches will be constructed as per standard HVPNL design
as far as electrical portion is concerned.
15.26.c The GI pipe duly lugged at both ends and by providing bends/elbows or
trenches will be provided/constructed from equipment to trenches.
15.26.d Provision for accommodation of cables of future bays (All bays position
marked on the drawing whether shown dotted or not to be included for
future provision in main the trench size) are to be made in the main
trenches.
15.27 TESTS ON CABLE TRAYS
15.27.1 Test for galvanising (Acceptance test) to be done as per relevant standard.
15.27.2 DEFLECTION TEST (TYPE TEST)
A 2.5 meter straight section of all widths cable trays be simply supported at
two ends a uniform distributed load of 76 kg meter shall be applied along the
length of the tray. A maximum deflection at the mid span shall not exceed 7
mm.
15.28 CONDUITS, PIPES AND DUCT INSTALLATION
15.28.1 Bidder shall supply and install all rigid conduits, mild steel pipes, flexible
conduits, hume pipes etc. including all necessary sundry materials such as
tees, elbows, check nuts, bushing reducers, enlargers, coupling Cap, nipples,
gland sealing fittings, pull boxes etc. as specified and to be shown in detailed
engineering drawing. The size of the conduit/pipe shall be selected on the
basis of 40% fill criterion.
15.28.2 Bidder shall have his own facility for bending, cutting and threading the
conduits at site. Cold bending should be used. All cuts & threaded ends shall
be made smooth without leaving any edges. Anticorrosive paint shall be
applied at all field threaded portions.
15.28.3 All conduit/pipes shall be extended on both sides of wall/floor openings. The
fabrication and installation of supports and the clamping shall be included in
the scope of work by Bidder.

15.28.4 When two lengths of conduits are joined together through a coupling, running
threads equal to twice the length of coupling shall be provided on each conduit
to facilitate easy dismantling of two conduits.
18.28.5 Conduit installation shall be permanently connected to earth by means of a
special approved type of earthing clamps. GI pull of adequate size shall be
laid in all conduits before installation.

- 22 -
15.28.6 Each conduit run shall be painted with its designation as indicated on the
drawing such that it can be identified at each end.
15.28.7 Embedded conduits shall have a minimum concrete cover of 50 mm.
15.28.8 Conduit run sleeves shall be provided with the bushings at each end.
15.28.9 Metallic conduit runs at termination shall have two locknuts and a bushing for
connection. Flexible conduits shall also be suitably clamped at each end with
the help of bushings. Bushings shall have rounded edges so as not to damage
the cables.
15.28.10 When embedded conduits turn upwards from a slab or fill, the termination
dimensions shown on the drawings, if any, shall be taken to represent the
position of the straight extension of the conduit external to and immediately
following the bend. At least one half of the arc length of the bend shall be
embedded.
15.28.11 All conduits/pipes shall have their ends closed by caps until cable are pulled.
After cables are pulled, the ends of conduits/pipes shall be sealed in an
approved manner to prevent damage to threaded portions and entrance of
moisture and foreign material.
15.28.12 For underground runs, Bidder shall excavate and back fill as necessary.
15.28.13 Bidder shall supply, unload, store and install conduits required for the lighting
installation as specified. All accessories/fittings required for making the
installation complete, including but not limited to pull out boxes ordinary and
inspection tees and elbow, check nuts, male and female bushings (brass or
galvanised steel), caps, square headed male plugs, nipples, gland sealing
fittings, pull boxes, conduit terminal boxes, gaskets and box covers, saddle
terminal boxes, and all steel supporting work shall be supplied by the Bidder.
15.28.14 All unarmoured cable shall run within the conduits from lighting panels to
lighting fixtures, receptacles etc.
15.28.15 Size of conduit for lighting shall be selected as per the table given in the
attached drawings.
15.28.16 Exposed conduits shall be run in straight lines parallel to building columns,
beams and walls. Unnecessary bends and crossings shall be avoided to
present a neat appearance.
15.28.17 Conduit supports shall be provided at an interval of 750mm for horizontal runs
and 100 mm for vertical runs.
15.28.18 Conduit supports shall be clamped on the approved type spacer plates or
brackets by saddles or U-bolts. The spacer plates or brackets in turn, shall be
securely fixed to the building steel by welding and to concrete or brickwork by
grouting or by nylon rawl plugs. Wooden plug inserted in the masonry or
concrete for conduit support is not acceptable.
15.28.19 Embedded conduits shall be securely fixed in position to preclude any
movement. In fixing embedded conduit, if welding or brazing is used, extreme
care should be taken to avoid any injury to the inner surface of the conduit.
15.28.20 Spacing of embedded conduits shall be such as to permit flow of concrete
between them and in no case shall be less than 38 mm.
15.28.21 Where conduits are along with cable trays, they shall be clamped to
supporting steel at an interval of 600 mm.
15.28.22 For directly embedding in soil, the conduits shall be coated with an asphalt-
base compound. Concrete pier or anchor shall be provided wherever
necessary to support the conduit rigidly and to hold it in place.
15.28.23 Conduit shall be installed in such a way as to ensure against trouble from
trapped condensation.
15.28.24 Conduit shall be kept, wherever possible, at least 300 mm away from hot
pipes, heating devices etc. when it is evident that such proximity may reduce
the service life if cables.
15.28.25 Slip joints shall be provided when conduits cross structural expansion joints or
where long run of exposed conduits are installed, so that temperature change
will cause no distortion due to expansion or contraction of conduit run.

- 23 -
15.28.26 For long conduit run, pull boxes shall be provided at suitable intervals to
facilitate wiring.
15.28.27 Conduit shall be securely fastened to junction boxes or cabinets, each with a
lock nut inside and outside the box.
15.28.28 Conduits joints and connections shall be made thoroughly water-tight and rust
proof by application of a thread compound which insulates the joints. White
lead is suitable for application on embedded conduit and lead for exposed
conduit.
15.28.29 Field bends shall have a minimum radius of four (4) times the conduit
diameter. All bends shall be free of kinds, indentations of flattened surfaces.
Heat shall not be applied in making any conduit bend. Separate bends may be
used for this purpose.
15.28.30 The entire metallic conduit system, whether embedded or exposed, shall be
electrically continuous and thoroughly grounded. Where slip joints are used,
suitable bounding shall be provided around the joint to ensure a continuous
ground circuit.
15.28.31 After installation, the conduits shall be thoroughly cleaned by compressed air
before pulling in the wire.
15.28.32 Lighting fixtures shall not be suspended directly from the junction box in the
main conduit run.
16 ILLUMINATION SYSTEM
16.1.1 The scope of work comprises of design, engineering, testing, supply,
installation, testing and commissioning of various lighting fixtures complete
with lamps, supports and accessories, lighting panels, lighting complete with
distribution boxes, galvanised rigid steel conduits, lighting wires, G.I. Earthwire
receptacles, switchboards, switches, junction boxes, pull out boxes complete
with accessories, lighting transformer. The details of area to be illuminated are
given below: -
Control Room Building.
Switch Yard area.
Roads and streets.

16.1.2 The minimum lux levels to be maintained in the different areas shall be as per
following: -
S.No. Area Lux. Level
i) Switchyard 50 lux on power
transformer and 20 lux
on other equipment.
ii) Street/Road 20 lux.
Bidder shall submit detailed for reaching the above LUX levels.
16.1.3 Any material, wire, conduits, accessories etc. not specifically mentioned or
specified but required for installation of lighting fixtures are included in the
scope of Bidder.
All lighting fixtures & accessories shall be designed for continuous operation
under atmospheric conditions existing at site, without reduction in the life or
without any deterioration. The lighting fixtures shall be of Philips or Bajaj or
Crompton Greaves of make only.

16.2 TEMPERATURE RISE


All lighting fixtures and accessories shall be designed to have a low
temperature rise according to the relevant Indian Standards, the design
average ambient temperature shall be taken as 500C.

16.3 LIGHTING FIXTURES

16.3.1 All fixtures shall be designed for minimum glare.


16.3.2 All lighting fixtures shall be complete with lamps a specified and shall be
suitably wired up.
- 24 -
16.3.3 All lighting fixtures shall be complete with accessories. Outdoor type fixtures
shall be provided with outdoor type weather proof box.
16.3.4 Each lighting fixtures shall be provided with an earthing terminal and all metal
parts of the housing shall be constructed so as to ensure earthing continuity
throughout the fixture up to the earthing terminal.
16.3.5 The mounting facility and conduit knock-outs for the fixtures shall be suitable
for 20 mm conduit entry.
16.3.6 The wire shall be of 1100 V grade and PVC insulated with multi stranded
copper conductor.

16.4 TESTS
Manufacture’s type and routine test certificates shall be submitted for the fixtures
and accessories.

16.5 SYSTEM DESCRIPTION


The lighting system shall comprise of the following: -

16.5.1 AC NORMAL LIGHTING


All the lights connected to the AC lighting system in different area will be
connected to the AC distribution boards to be supplied.

16.5.2 DC EMERGENCY LIGHTING


DC emergency in Control room, relay and protection room, office, LT
switchgear room, D.C.D.B. room shall be provided to avoid complete darkness
in case of complete AC failure. The number of DC emergency lights to be
provided shall be calculated on the basis that atleast illumination level of
atleast 30 LUX is achieved when DC emergency lights get switched ON.
16.5.3 RECEPTACLES
Adequate number of 5A, 15 A, (single phase) and 32 A (3phase) receptacles
shall be provided at suitable locations to be mutually during the detailed
engineering.

16.6 ERECTION, TESTING AND COMMISSIONING OF LT PANELS &


BATTERY CHARGER
16.6.1 The Bidder shall unload, erect, install, test and put into commercial use all
electrical equipment included in this Specification.
16.6.2 Equipment shall be installed in a neat, workman so that it is level plumb,
square and properly aligned and oriented. Tolerance shall be as established in
Bidder’s drawings or as stipulated by HVPNL. No
equipment shall be permanently bolted down to foundations until the
alignment has been checked and found acceptable by the HVPNL.
16.6.3 Bidder shall furnish all supervision, labour tools equipment rigging materials,
bolts, wedges, anchors, concrete insert etc. in proper time required to
completely install, test and commission the equipment.
16.6.4 Manufacture’s and HVPNL’s instructions and recommendations of all
equipment.
16.6.5 Bidder shall move all equipment into the respective room through the regular
door or openings specifically provided for this purpose. No part of the structure
shall be utilised to lift or erect any equipment without prior permission of
HVPNL.
16.6.6 All switchboards shall be installed in accordance with Indian standards
IS:3072 and at HVPNL’s instructions. Switchboard panels shall be installed on
finished surfaces, concrete or steel stills. Bidder shall be required to install and
align any channel sills which from part of foundations. In joining shipping
sections of switchboards together adjacent housing of panel section or flanged
throat sections shall be bolted together after alignment has been completed.
Power bus, enclosures ground and control splices of conventional nature shall

- 25 -
be cleaned and bolted together being drawn up with torque spanner of proper
size or by other approved means.
16.6.7 All switchboards shall be made completely vermin proof.
16.6.8 Bidder shall take utmost care in holding instruments, relaying and other
delicate mechanism wherever the instruments and relays are supplied
separately they shall be mentioned only after the associated panels have been
erected and aligned. The blocking materials HVPNL for safe transit of
instrument and relays shall be removed after ensuring that panel been
completely installed and to further movement of the same should be
necessary. Any damage shall be immediately reported to HVPNL.
16.6.9 Equipment furnished with finished coats of paint shall be touched by up Bidder
if their surface is specified or marred while handling.
16.6.10 Foundation work for all switchboard panels will be carried out by Civil Bidder.
However, minor modifications shall be carried out by the Bidder at no extra
cost.
16.6.11 After installation of panels, power and control wiring and connections, Bidder
shall perform operational tests on all switchboards, to verify proper operation
of switchboards/panels and correctness of all equipment in each and every
respect.
16.6.12 COMMISSIONING CHECK TESTS
The Bidder shall carry out the following commissioning check wherever
applicable in addition to the other checks and tests recommended by the
manufacturers: -

16.6.12.1 GENERAL
i. Check nameplate details according to the Specification.
ii. Check for physical damage.
iii. Check tightness of all bolts, clamps, joints connecting terminals.
iv. Check earth connection,
v. Check cleanliness of insulators and bushings.
vi. Check all moving parts for proper lubrication.

16.6.12.2 CIRCUIT BREAKERS


i. Check alignment of Breaker truck for free movement.
ii. Check correct operation of shutters.
iii. Check control wiring for correctness of connections, continuity and IR
values.
iv. Manual operation of Breaker completely assembled.
v. Power closing/opening operation, manually and electrically.
vi. Breaker closing and tripping time.
vii. Trip free and anti-pumping operation.
viii. IR values, minimum pick up voltage and resistance of coils.
ix. Contact resistance.
x. Simultaneous closing of all the three phases.
xi. Check electrical and mechanical interlocks provided.
xii. Check on spring charging motor, correct operation of limit switches, and
timeof charging.
xiii. All functional checks.

16.2.12.3 CURRENT TRANSFORMERS


i) Megger between winding and winding terminals top body.
ii) Polarity test.
iii) Ratio identification checking of all ratios on all by primary injection of
current.
iv) Spare CT cores, if any, to be shorted and earthed.

16.2.12.4 VOLTAGE TRANSFORMER


i) Insulation resistance test.
- 26 -
ii) Ratio test on all cores.
iii) Polarity test.
iv) Line connections as per connection diagram.

16.2.12.5 CUBICLE WIRING


i) Check all switch development.
ii) Each wire shall be traced by continuity tests and it should be made sure that
the wiring is as per relevant drawing. All interconnection between panels/
equipment shall similarly checked.
iii) All the wire shall be meggered to earth.
iv) Functional check of all control circuit e.g. closing, tripping control, interlock,
supervision and alarm circuit.
16.2.12.6 RELAYS
i) Check connections and wiring.
ii) a) Megger all terminal to body.
b) Megger AC to DC terminals.
iii) Check operations characteristics by secondary injection.
iv) Check minimum pick up voltage of DC coils.
v) Check operation of electrical/mechanical targets.
vi) Relays settings.
vii) Check CT and VT connections with particular reference to their polarities
for directional relays, wherever required.

16.2.12.7 METERS
i) Check calibration by comparing it with a sub-standard.
ii) Megger all insulated portions.
iii) Check CT and VT connections with a particular reference to their polarities
for power type meters.

16.7 ERECTION, TESTING AND COMMISSIONING OF BATTERY BANK

16.7.1 The control shall unload, erect, install, test and put into commercial use already
electrical equipment included in this Specification.

16.7.2 Equipment shall be installed in a neat, workman like manner so that it is level,
plumb, square and properly aligned and oriented tolerance shall be established in
Bidder’s drawings or as stipulated by HVPNL. No equipment shall be permanently
bolted down to foundations until the alignment has been checked and found
acceptable by the HVPNL.
16.7.3 Bidder shall furnish all labour tools equipment rigging materials, bolts, wedges,
anchors, concrete inserts etc. in proper time required to completely install, test
and commission the equipment.

16.7.4 Manufacturer’s and HVPNL’s instructions and recommendations shall be correctly


followed in handling, testing and commissioning of Battery Bank.

- 27 -
SECTION – 8
STRUCTURES

1.0 GENERAL

1.1 The scope of specification covers fabrication, proto-assembly supply and


erection of galvanised steel structure for towers, latticed griders and equipment
support structure. Towers, girder & equipment support structures shall be as per
HVPN drawing conforming to IS 2062 (latest).

o The scope shall include all types of bolts, nuts, step bolts, inserts in
concrete, gusset plates, equipment mounting bolts, structure Earthing
bolts, foundation bolts, spring washers, fixing plates, angles and bolts for
structure mounted or ground mounted marshalling boxes (AC/ DC
Marshalling box & equipment control cabinet) and any other items as
required to complete the job.

The connection of all structures to their foundations shall be by base plates and
embedded anchor/ foundation bolts. All steel structures and anchor/ foundation
bolts shall be fully galvanized. The weight of the zinc coating shall be at least
0.610 kg/m2. One additional nut shall be provided below the base plate which
may be used for the purpose of leveling.

2.0 DESIGN REQUIREMENTS

2.1 Minimum distance from the hole centre to edge shall be 1.5x bolt diameter.
Minimum distance between center to center of holes shall be 2.5x bolt diameter.

2.2 The minimum bolt diameter shall be 16 mm.

2.3 In order to facilitate inspection and maintenance, the structures shall be provided
with climbing devices. Each tower shall be provided with step bolts not less than
16 mm diameter & 175 mm long spaced not more than 450 mm apart, staggered
on faces on one leg extending from about 0.5 meters above ground level to the
top of the tower. The step bolt shall conform to IS:10238. Ladders on towers with
lighting appliances shall be provided with safety guards.

2.4 If luminaries are proposed to be fixed on gantries/ towers, then the proper
loading for the same shall be considered while designing. Also holes for fixing the
brackets for luminaries should be provided wherever required.

2.5 Foundation bolts/ studs shall be designed for the loads for which the structures
are designed.

3.0 FABRICATION OF STEEL

-1-
3.1 The Bidder shall bear all the expenditure at all stages on account of loading/
unloading, transportation and other miscellaneous expenses and losses and
damages for all materials upto the fabrication yard/ shop and there after to the
erection site including all other expenses till the erection of work has been
completed and accepted. The unit rates shall be deemed to be inclusive of all
such incidental expenses and nothing extra shall be payable on any account in
this regard.

3.2 The fabrication and erection works shall be carried out generally in accordance
with IS:802. A reference however may be made to IS:800 in case of non-
stipulation of some particular provision in IS:802. All materials shall be
completely shop fabricated with proper connection material and erection marks
for ready assembly in field.

4.0 ASSEMBLY

i) The component parts shall be assembled in such a manner that they are
neither twisted nor otherwise damaged and shall be so prepared that the
specified camber, if any, is provided. In order to minimise distortion in
member the component parts shall be positioned by using the clamps,
clips, dogs, jigs and other suitable means and fasteners (bolts and welds)
shall be placed in a balanced patten. If the individual components are to
be bolted, paralled and tapered drifts shall bed used to align the part so
that the bolts can be accurately positioned.

ii) Sample towers, beams and equipment support structure shall be trial
assembled keeping in view the actual site conditions, before erection in
the fabrication shop and shall be inspected and approved by HVPNL
before mass fabrication. Necessary match marks shall be made on these
components in the shop before disassembly and despatching.

5.0 BOLTING

i) Every bolt shall be provided with a spring washer under the nut so that no
part of the threaded portion of the bolt is within the thickness of the parts
bolted together.

ii) All steel items, bolts, nuts and washers shall be galvanised.

iii) 2.0% extra nuts and bolts shall be supplied for erection.

-2-
6.0 WELDING

The work shall be done as per approved fabrication drawing which clearly
indicate various details of joints to be welded, type of weld, length and size of
weld, whether shop or site weld. Symbols for welding on erection and shop
drawings shall be according to IS:813. Efforts shall be made to reduce site
welding so as to avoid improper welding due to constructional difficulties.

7.0 FOUNDATION BOLTS

7.1 Foundation bolts for the towers and equipment supporting structures and
elsewhere shall be embedded in first stage concrete while the foundation is cast.
The Bidder shall ensure the proper alignment of these bolts to match the holes in
the base plate.

7.2 The Bidder shall be responsible for the correct alignment and leveling of all steel
work on site to ensure that the towers/ structures are plumb.

7.3 All foundation bolts for lattice structures are to be supplied by the Bidder.

7.4 All foundation bolts shall be fully galvanised so as to achieve 0.61 kg per Sq.m of
Zinc Coating as per specification.

8.0 STABILITY OF STRUCTURE

The Bidder shall be responsible for the stability of the structure art all stages of
its erection at site and shall take all necessary measures by the additions of
temporary bracing and guying to ensure adequate resistance to wind and also to
loads due to erection equipment and their operations.

9.0 GROUTING

The method of grouting the column bases shall be subject to approval of HVPNL
and shall be such as to ensure a complete uniformity of contact over the whole
area of the steel base. The Bidder will be fully responsible for the grouting
operations.

10.0 GALVANISING

10.1 All structure steel works and single pipe supports shall be galvanised after
fabrication.

10.2 Zinc required for galvanising shall have to be arranged by the manufacturer.
Purity of zinc to be used shall be 99.5% as per IS:209 (latest).

-3-
10.3 The Bidder shall be required to make arrangement for frequent inspection by the
HVPNL as well as continuous inspection by a resident representative of the
HVPNL, if so desired for fabrication work.

11.0 INSPECTION BEFORE DISPATCH

Each part of the fabricated steel work shall be inspected and certified by the
HVPNL of his authorised representative as satisfactory before it is dispatched to
the erection site. Such certificate shall not relieve the Bidder of his responsibility
regarding adequacy and completeness of fabrication.

12.0 TEST CERTIFICATE

Copies of all test certificate relating to material procured by the Bidder works
shall be forwarded to the HVPNL.

13.0 ERECTION

The Bidder should arrange his own erection plant and equipment, welding set,
tools and tackles, scaffolding, trestles equipment etc. and any other accessories
and ancillaries required for the work.

14.0 SAFETY PRECAUTIONS

The Bidder shall strictly follow at all stages of fabrication, transportation and
erection of steel structures, raw materials and other tools and tackles, the
stipulations contained in Indian Standard Code for erection for structural steel
work – IS:7205.

-4-
SECTION-9

CIVIL WORKS
1.0 GENERAL

The intent of specification covers the following:

Design, Engineering, Construction of all specified Civil Works of the


proposed substation covered under the scheme. All Civil Works shall
also satisfy the general technical requirements specified in other
sections of this specification and as detailed below. All the specified
designs shall be carried out to the required service conditions/loads as
specified elsewhere in the specifications or implied as per
National/International Standards and as specified by manufacturers.

All Civil Works shall be carried out as per applicable Indian Laws, latest
Standards and Codes. All material shall be of best quality conforming
to relevant Indian Standards and Codes. The successful bidder shall
furnish all design, (unless otherwise specified), drawings, labour, tools,
equipment, material, temporary works, construction plant and
machinery, supply fuel, transportation and all other incidental items not
shown or specified but are required for complete performance of the
works in accordance with approved drawings, specifications and
direction of HVPNL.

The work shall be carried out according to the design/drawings to be


developed by the successful bidder and submit the same for approval
of the HVPNL or shall be supplied to the bidder by the HVPNL as
detailed in the schedule of quantities. The GIS block Building and
alied structure(Common Portion) of switch house building shall
be developed by the successful Bidder and its design and
drawings shall be counter checked from any professional institute
like IIT, NIT, PEC Chandigarh etc. The design/drawing so approved
shall become the property of the Nigam and the Nigam shall be free to
use these designs/drawings at any of its upcoming/future station. For
all structures, buildings, foundations etc. necessary layout and details
shall be developed by the bidder keeping in view the functional
requirement of the sub-station facilities and providing enough space
and access for operation, use and maintenance based on the input
provided by the HVPNL. Certain minimum requirements are indicated
in this specification for guidance purposes only. However, the bidders
shall quote considering all the requirements essential for functional
purposes.

All the civil works covered under the said scheme shall be constructed
under the supervision of experienced degree holder civil engineers.

1
2.0 SOIL DATA

For the guidance of the bidders, the general soil data around proposed
sub-station is specified below.
Type of soil : Normal soil
Dry bulk density : 1600 kg/m2
Angle of internal friction : 28°
Cohesion : 00
Safe allowable B.C : 6t/m2 (F.O.S=2.5)
Depth of water table : Below 6M from N.S.L

2.1 GENERAL SITE DESCRIPTION

The proposed site is generally leveled and may require some


cutting/filling. As the formation level of sub-stations are generally kept
at higher level than its surroundings, the bidders are, advised to visit
the sites before quoting to access earth filling. The approx. quantity
of earth filing is provided in the schedule of quantity.

2.2 The soil data mentioned above shall be used for designing the
equipment structure foundations. Minimum depth of foundation in
natural ground shall not be less than 0.5 meter excluding lean concrete
except for trenches, the depth of which may vary as per site
requirements.

2.3 SITE PREPARATION

The site as available shall be handed over to the selected bidder.


Clearing of the site from bushes/trees including its roots shall be
carried out by the Bidder. The HVPNL, if required, shall arrange
necessary permission for cutting of trees from the concerned
authorities. The Bidder shall hand over the wood of trees to the
HVPNL.

The Bidder shall prepare the `CONTOURS` of land at suitable


intervals. The spot levels shall be taken at a distance not more the
5.0M intervals. The contours shall extend to sufficient distance (approx.
50M) around the land and main road in front of land and any other
important existing feature to give a fair idea about topography of the
area. On submission of contour plan by the successful bidder and
based on the surroundings, drainage condition etc., the HVPNL shall
fix the Formation Level which is generally fixed somewhat higher than
the surroundings. The Bidder, as per specifications shall carry out the
necessary earth cutting/filling (spreading) as per site requirements,
leveling, compaction and dressing to reach the desired formation level.

The Bidder at his own cost shall make the layout and levels of all
structures/buildings as per the general grid of the plot and the
Benchmark given by the HVPN.

The permanent Benchmark and all the change points shall be


established at the proposed site and the same shall be got
authenticated before taking any further levels. The Bidder shall provide

2
all help including instruments, materials and personnel to the HVPN or
his representative for checking the detailed layout and shall solely be
responsible for the correctness of the layouts and levels.

3.0 SCOPE

This clause covers the design, engineering, supply of labour, material


and execution of civil items including dismantling of the existing
foundations/structures wherever required, clearing the site, earth
cutting/filling wherever required, site preparation, supply and
compaction of fill material to achieve formation level, foundations,
excavation and compaction of backfill for foundation, roads, trenches
including trenches below floors in buildings etc., retaining wall,
(complete job).

3.1 WATER SAMPLE

Representative samples of ground water shall be taken when ground


water is first encountered before addition of water to aid drilling of
boreholes. The collected samples shall be of sufficient quantity and
shall be stored in air-tight containers so that chemical analysis of water
for use in concrete and curing could be carried out.

3.2 GENERAL

3.2.1 Material including excavated material unsuitable for founding of


foundations shall be removed and replaced by suitable fill material and
the same is required to be got approved from the HVPNL.

3.2.2 Fill/Backfill material around foundations or other works shall be free


from harmful salts viz. sulphates, chlorides and or any
organic/inorganic materials. The Fill/Backfill material should be
compacted as described under clause 3.4.

3.3 EXCAVATION AND BACKFILL

3.3.1 Excavation and backfill for foundations shall be in accordance with the
relevant IS code and as per approved design/drawings.

3.3.2 Whenever water table/seepage water is met during excavation, it shall


be dewatered and foundation pit shall be maintained dry i.e. free of
water during the excavation, concreting and back filling. No extra
payment on this count shall be admissible.

3.3.3 When embankments are to be constructed on slopes of 15% or


greater, benches or steps with horizontal and vertical faces shall be cut
in the original slope prior to placements of embankment material. The
vertical faces shall measure not more than 1.0 m in height.

3.3.4 Embankments adjacent to abutments, culverts, retaining walls and


similar structures shall be constructed by compacting the material not
exceeding 15cm in thickness of loose material before compaction in
successive uniform horizontal layers. Each layer shall be compacted as
required by means of mechanical tempers approved by the HVPNL.

3
Rocks larger than 10 cm shall not be placed in embankment adjacent
to structures.

3.3.5 Earth embankments of roadways and site areas adjacent to buildings


shall be placed in successive uniform horizontal layers not exceeding
20 cm in thickness in loose stage measurements and compacted to the
full width specified. The upper surface of the embankment shall be
shaped so as to provide complete drainage of surface water at all
times.

3.3.6 In case the switchyard area needs leveling & dressing only, to maintain
the final formation level as fixed by HVPNL, same shall be done with
utmost care and with proper compaction. If the top crest of earth (30
cm depth) is containing harmful salts and organic/inorganic materials or
excessive earth, it shall be scraped and disposed off at a place as
directed by HVPN.

3.3.7 To achieve formation level, the elevated earth, wherever required, shall
be cut and spread in layers and compacted, as prescribed in IS codes
and clause 3.4, in the low lying areas. Nothing shall be paid on this
account. Only the earth brought from outside after using sub-station’s
surplus earth, if any, for achieving formation levels of sub-station
including beneath roads within and outside the sub-station area, shall
only be paid.

3.4 COMPACTION

3.4.1 The method and equipment used to compact the fill material shall be
suitable to achieve the density that will give the allowable soil bearing
pressure required for the foundations, roads etc. in each layer of fill
material. Each layer of earth embankment when compacted shall be as
close to optimum moisture content as practicable. Embankment
material that does not contain sufficient moisture to obtain proper
compaction shall be wetted. If the material contains excess moisture,
then it shall be allowed to dry before rolling. The rolling shall begin at
the edges overlapping half the width of the roller each time and
progress to the center of the road or towards the building as applicable.
Rolling will also be required on rock fills. No compaction shall be
carried out in rainy season/during rains.

3.4.2 At all times, the unfinished construction shall have adequate drainage.
Upon completion of the road's surface course, adjacent shoulders shall
be given a final shaping, true alignment and grade.

3.4.3 The density to which fill materials shall be compacted shall be as per
relevant IS and as per direction of HVPNL. All compacted sand filling
shall be confined as far as practicable. Backfilled earth shall be
compacted to minimum 95% of the Standard Proctor's density at
Optimum Moisture Content (OMC). The sub-grade for the roads and
embankment filling shall be compacted to minimum 95% of the
Standard Proctor's density at OMC.

4
3.5 EARTH CUTTING

To maintain the formation level (FL), wherever required the Bidder will
cut the earth and use (spread) the same within the sub-station area
requiring filling as per directions of HVPN.

4.0 SITE SURFACING

4.1 SCOPE OF WORK

The Bidder shall furnish all labour, equipment and materials required
for complete performance of the work in accordance with the drawings,
Specification and direction of the HVPN.

Stone spreading along with cement concrete layer shall be done in


areas presently in the scope of the scheme. Stone spreading only
shall, however, be provided in the areas (bays) kept for future
expansion.

4.2 GENERAL REQUIREMENT

4.2.1 The material required for site surfacing/gravel filling should be free from
all types of organic materials and shall be of standard approved quality
as directed by the HVPN.

4.2.2 The material to be used for stone filing/site surfacing shall be


crushed/broken stone of 40mm nominal size (ungraded single size)
conforming to table 2 of IS: 383 – 1970. Hardness, flakiness shall be
as required for wearing courses are given below:-

a) Sieve Analysis Limits (Gradation) (IS: 383 – Table – 2)


Sieve Size % passing by weight
63mm 100
40mm 85-100
20mm 0-10 (upto 90% retained on sieve)

One Test shall be conducted for every 500 cum per source.

b) Hardness
Abrasion Value (IS: 2386 Part-IV) – not more than 40%
Impact value (IS: 2386 Part-IV) – not more than 30%

One test per 500 cum with a minimum of one test per source.

4.2.3 The Bidder, after all the structures and equipment have been erected
and accepted, shall furnish and install the site surfacing to the lines and
grades as shown in the drawing and in accordance with the
requirements and direction of the HVPN. The site shall be maintained
to the lines and grades indicated in the drawing by using 3 ton roller
with suitable water sprinklers to form a smooth and compact surface
condition which shall match with finished ground level of the switchyard
area.

5
4.2.4 100mm thick base layer of cement concrete in 1:4:8 (1 cement: 4 fine
aggregates conforming to zone-II as per IS:583: 8 coarse aggregate
nominal size 20MM) shall be provided in the areas excluding roads,
drains, cable trenches as per detailed engineering drawing. For easy
drainage of water, the slope of 1:1000 is to be provided from the ridge
to the nearest drain. The ridge shall be suitably located at the centre of
the area between the nearest drains. The above slope shall be
provided at the top of base layer of cement concrete in 1:4:8. A layer of
cement slurry of mix 1:4 (1 cement: 4 fine aggregates) shall be laid
uniformly over cement concrete layer. The cement consumption for
cement slurry shall not be less than 150kg per 100 sq.m. 20mm single
size coarse aggregate should be used for base concrete.

4.2.5 The sub grade shall be in moist condition at the time the cement
concrete is placed. If necessary, it should be saturated with water for
not less than 6 hours but not exceeding 20 hours before placing of
cement concrete. If it becomes dry prior to the actual placing of
cement concrete, it shall be sprinkled with water and it shall be ensured
that no pools of water or soft patches are formed on the surface.

4.2.6 Areas where the HVPNL is satisfied that proper filling of the base
course material by normal rolling equipment is not possible due to
closely laid foundations and structures, the filling of the base course
material shall be compacted by hand. Due care shall be exercised to
avoid any damage to the foundations, structures, equipments (Cable
trench or Cable) during rolling compaction or otherwise.

4.2.7 A final layer of 100mm thick uncrushed /crushed/broken stone of 40mm


nominal size (ungraded size) shall be spread uniformly over cement
concrete layer after curing is complete.

4.2.8 Generally site surfacing will be restricted upto 2.0m beyond the last
structure/equipment foundation. However, depending upon the site
requirement, the same shall be carried out as per instructions of HVPN.
To hold the stone (bajri) wherever required, a toe wall of 115mm thick,
300mm deep (1:4) shall be provided. Top of wall shall be 25mm above
top of bajri. All visible portion of toe wall shall be plastered and cement
painted.

5.0 SITE DRAINAGE

SCOPE

Adequate site drainage system shall be provided by the Bidder within


the switchyard fencing under the present scope including house
building & connection at one or more points to the outfall point located
outside the substation boundary wall is in the scope of Bidder. Invert
level of drainage system at outfall point shall be decided in such a way
that the water can easily be discharged outside the substation
boundary wall. Outfall point shall be got approved from HVPN before
commencement of construction. The Bidder shall obtain rainfall data
and design the storm water drainage system including culverts,
ditches, drains etc. to accommodate the most intense rainfall that is
likely to occur over the catchments area in one hour period on an

6
average of once per ten years. While designing the drainage system
following points shall taken care of:

5.1 The surface of the switchyard shall be sloped to prevent pounding of


water.

5.2 Longitudinal slope shall generally be not less than 1 in 1000. However,
keeping in view the discharge, the same can be increased to 1:2000.

5.3 RCC pipe drains shall be provided in area of switch yard where
movement of crane will be necessary in operating phase of the
substation.

5.4 For pipe drains, RCC concrete pipe of class NP3 shall be used.
However, for road crossings rail crossings etc., RCC pipes of class
NP4 shall be provided. For design of RCC pipes for drains and
culverts, IS; 456 and IS: 783 shall be followed.

5.5 Pipe drains shall be connected through manholes at an interval of max.


30m.

5.6 Sum pit of suitable size to hold water for 5 minutes discharge has to be
constructed within the substation boundary at suitable site as per
HVPNL’s drawing & directions of HVPN.

5.7 The drainage scheme and associated drawings shall be designed for
HVPNL approval before commencement of work.

5.8 Two non clog pumps (of reputed make) and of suitable capacity
(depending upon maximum discharge and capable of lifting particle
size 65mm) shall be provided by the Bidder without any extra cost at
sum pit.

6.0 RAINWATER HARVESTING.

6.1 In addition to drainage of rainwater in accordance with clause 5.0 of


section civil of Technical specification, the Bidder shall make
arrangement for rainwater harvesting also as per drawing supplied by
the HVPNL with the bid document.

6.2 Rainwater harvesting shall be done by providing one number recharge


structures with bore wells. The recharge structures shall be suitably
located within the sub-station. Branch drains from the main drain
carrying rainwater from entire switchyard, constructed in accordance
with clause 5.0, shall be connected to the recharge structures.

6.3 The internal diameter of recharge shafts shall be 3.0 meter as per
HVPNL drawing with 230mm thick lining of brick work upto a depth of
2.0 meter from ground level and 345mm thick brickwork below 2.0
meter depth. The brickwork shall be constructed with cement mortar
1:6 (1 cement: 6 coarse sand). The overall depth of shaft shall be 5.0
meter below invert level of drain. The shaft shall be covered with RCC
slab for a live load of 300kg per sq m. Two openings of size 0.7x0.7
meter shall be provided in the RCC cover slab as shown in the

7
drawing. An iron cover made of 5mm thick chequerred plate with
hinges shall be provided on the openings. Galvanized M.S. rungs of
20mm diameter at spacing of 300mm shall be provided in the wall of
shaft below the opening in the RCC slab to facilitate cleaning of shaft.

6.4 A 300 mm diameter bore well shall be drilled in the centre of the shaft.
The depth of bore well shall be 5.0 meter more than the depth of sub
soil water or as per directions of the HVPN.

6.5 A 150 mm dia. class 3 PVC pipe conforming to IS 4985-1981 with


latest revision shall be lowered in the bore well keeping bail plug
towards bottom of bore well. The pipe shall have 1.58 mm holes for
4.0 meter length starting from 1.0 meter from bottom of bore well.
Holes of 3.0 mm dia shall be provided for a length of 2.0 meter starting
from the bottom level of coarse sand and down wards. The overall
length of pipe shall be equal to total depth of bore well plus depth of
shaft.

6.6 Gravel of size 3mm to 6mm shall be filled around 150 dia PVC pipe in
the bore well. The shaft shall be filled with 500mm thick layers each
from the bottom of shaft with boulders of seize 50mm to 150mm, gravel
of size 5mm to 10mm coarse sand having particle size 1.5mm to 2.0
mm and boulders of size not less than 200mm respectively.

7.0 ROAD, CULVERTS AND PCC PAVEMENT/PARKING:

Latest specifications as adopted by HVPNL for construction of roads


and pavement shall be followed. Finished top (crest) of roads shall be
as per tender drawings & levels shall match with the levels fixed by the
HVPNL.

SCOPE:

7.1 This clause covers the supply of labour and material for executing the
work for the road & design, engineering, supply of labour and material
for providing culverts within the sub station fencing including approach
road from main Public/Village road to the sub-station main entry gate(s)
as contained in the General Electric layout (GELO)/Civil layout (CLO)
or as per requirement of the Sub-Station covered under the said
scheme.

7.2 The rates quoted shall be for constructions of roads as per attached
drawings, complete in all respect (except earth filling). Wherever earth
cutting is involved no extra payment shall be made for it. However,
layout of roads shall be as per General Electric layout (GELO)/Civil
layout plan of the Sub-Station.

7.3 Adequate turning space for vehicles shall be provided and bend radii
shall be set accordingly.

7.4 All substation roads shall be constructed to permit transportation of all


heavy equipment. The main road leading to control room/switch
yard/colony shall have a minimum 6m width with shoulder on either
side (Refer drawing HCD/SK-181). The roads within the sub-station

8
shall be as per General Electric layout (GELO)/Civil layout (CLO) and
as per above referred drawing. The shoulders/footpath/side-walk
should be provided with pre-cast kerbs on either side of the road. The
top edge of the kerbs shall be battered. The kerb stones with top 20cm
wide shall be laid with their length running parallel to the road edge,
true in line and gradient at a distance of 30cm from the road edge to
allow for the channel and shall project about 12.5cm above the latter.
The channel stones with top 30cm wide shall be laid in position in
camber with finished road surface and with sufficient slope towards the
road gully chamber. The joints of kerb and channel stones shall be
staggered and shall not be more than 10mm. Wherever specified all
joints shall be filled with mortar 1:6 (1 cement: 6 coarse sand) and
pointed with mortar 1:2 (1 cement:2 fine sand) which shall be cured for
7 days. The kerb should be painted as per directions of HVPN.

The necessary drainage openings of specified sizes shall be made


through the kerb as per drawings or as directed by the HVPN for
connecting to storm water drains.

Top of the shoulders/footpath/side-walk shall be provided with 20mm


thick precast chequred tiles made in ordinary grey cement without
chips laid on bed of 100mm coarse sand, PCC 1:8:16 (100mm thick)
and 20mm thick bed of cement coarse sand mortar 1:3 with neat
cement slurry between joints as per PWD specifications.

7.5 Adequate provision shall be made for road drainage.

7.6 The rate of camber on a cement concrete surfacing shall be 1 in 72


unless otherwise provided.

7.7 The base sub-grade is to be consolidated with power road roller of 8


Tons to 12 Tons (Roller shall pass a minimum of 5 runs on sub-
grade). The roller shall run over the sub-grade till the soil is evenly and
densely consolidated and behaves as elastic mass. All undulations in
the surface that develop due to rolling shall be made good with quarry
spoils and sub grade is re-rolled.

7.8 The coarse aggregate used shall be crushed or broken stone or any
naturally occurring aggregates such as kankar, laterites of suitable
quality shall conform to the physical requirements as given below:

Los Angeles Abrasion value (Max) 50% (IS: 2386 (Part-IV))


Aggregate Impact Value (Max) 40% (IS: 2386 (Part-IV) or IS: 5640)
Flakiness Index (Max) 10% (IS: 2386 (Part-I)

The crushed or broken stone shall be hard, durable and free from
excess flat, longated, soft and disintegrated particles, the 100mm thick
& 75mm thick. Soling aggregates shall conform to following grading
respectively.

9
GRADE SIEVE DESIGNATION PERCENT BY WT.
SIZE PASSING
95 to 45 125mm 100
90mm 90-100
63mm 25-60
45mm 0-15
22.4 mm 0-5
63 to 45 90mm 100
63mm 90-100
53mm 25-75
45mm 0-15
22.4mm 0-5
13.2 13.2 mm 100
11.2 mm 95-100
5.6mm 15-35
180 micron 0.10

7.9 The base shall be constructed, to have as nearly as practicable a


uniform bearing power throughout its entire width and to conform to the
line, grade and cross-section, shown in the drawing enclosed with the
document. Where existing road is to be widened every precaution shall
be taken to ensure that there would be no differential settlement
between the old surface and the newly added strip.

7.10 The base course shall be extended on either side to at least 15 cm (for
switch yard roads) beyond the edge of the concrete pavement. The
base course shall be prepared at least 2 days in advance of concreting.

7.11 The side forms shall be made of metal of approved section having a
thickness not less than 5 mm and shall have a depth equal to the
specified thickness of the slab. They shall be provided with an efficient
locking device to ensure continuity of line and level through joints and
with steel pins to hold them in position. Building up of forms shall not
be permitted. Flexible or curved forms of proper radius shall be used
for curves of 30 meters radius or less. Forms shall not deflect more
than 6mm. when tested as a simple beam with a span of 3 meters and
a load equal to that which is expected upon them during construction.
Forms shall be at least 7.5 cm wide at the base and shall be free from
wrap, bends or kinks. The top of the form shall not vary from a 3
meters straight edge by more than 3 mm at any point and the side of
the form by more than 6 mm.

7.12 The base under the form shall be compacted and cut to grade so that
the forms, when set, shall be uniformly supported for their entire length
and at the specified elevation. Surface found to be below established
grade at the form line shall be filled to grade in lifts of 12mm or less
and thoroughly re-levelled or tamped

7.13 Forms shall be set over length presenting 2 days work in advance of
the point where concrete is being proposed to be placed and shall be
cleaned and oiled prior to the placing of concrete. Forms shall remain
in place for at least 12 hours after placing the concrete. If the air
temperature is below 100C at any time during 12 hours period from the

10
time the concrete is placed, forms shall not be removed until 30 hours
after placing of the concrete. While using the device, care shall be
taken not to damage the edge of the concrete or of the form. Forms
shall be cleaned for reuse immediately after striking. They shall be
handled with care and in no circumstances shall be dropped or struck
with heavy hammers to remove adhering concrete.

7.14 After the base has been approved by the HVPN, it shall be sprinkled
with water and kept moist to prevent the absorption of water from the
concrete. If so required by the HVPN, it shall be saturated with water
previous night for not less than 6 hours previous to placing of the
concrete. The method of sprinkling of water shall not be such as to
form mud or pools of water. No concrete shall be placed around man-
holes for other structures until they have been brought to the required
grade and camber.

7.15 The concrete to be placed shall conform to M-20 grade design mix. For
small works, nominal mix of 1:1½:3 may be used for which specific
approval shall be obtained by the successful bidder. The concrete shall
be distributed to such depth that when consolidated and finished, the
slab thickness obtained is equal at all points and no surface is below
the specified level at any point. The un-compacted concrete will be
placed keeping the surface slightly higher than the top of the forms; the
amount of surcharge depending upon the consistency of the concrete.

7.16 The concrete shall be deposited on the prepared base for the required
width, in such a manner as to require as little re-handling as possible.
Concrete shall be placed at the working face as provided in the code.
Necessary hand-spreading shall be done with shovels and not with
rakes.

7.17 For large works, concrete shall be compacted by vibrators. However,


for small works hand-tamping shall be allowed at the discretion of the
HVPN.

7.18 The slab is laid continuously in strips/alternate between longitudinal


joints. Ends of slabs should be painted with bitumen before the
intermediate bays are filled in.

7.19 After belting and as soon as surplus water, if any, has risen to the
surface, the pavement shall be given a broom finish, with an approved
steel or fibre broom not less than 50cm wide. The broom shall be
pulled gently over the surface of the pavement from edge to edge.
Adjacent strokes shall be slightly overlapped. Brooming shall be
perpendicular to the centre line of the pavement and so executed that
the corrugations thus produced will be uniform in character and width,
and not more than 1.5mm deep. Brooming shall be completed before
the concrete reaches such as stage that the surface is likely to be torn
or unduly roughened by the operation. The broomed surface shall be
free from porous or rough spots, irregularities depression etc.

7.20 Immediately after the final set has taken place, the surface of the
finished concrete shall be kept covered with moist gunny bags for the
first 24 hours. The gunny bags shall then be removed and the grooves

11
in the transverse expansion and contraction joints shall be sealed
temporarily. The surface shall then be cured for at least 14 days by
pounding to a depth of about 7.5 cm or by covering with not less than
7.5cm layer of wet earth. The earth cover shall be kept wet
continuously during the whole curing period. At the expiry of the curing
period, the surface shall be cleaned of all earth etc.

7.21 Forms shall not be removed from freshly placed concrete until it has
set for at least 24 hours. They shall be so carefully removed and in
such a manner that no damage will be done to the edge of the
pavement. After the forms have been removed, the ends of all joints
shall be cleaned, after which the sides of the slab shall be covered with
earth to the level of the top of the slab.

7.22 The finished concrete road shall not be opened to traffic till after the
expiry of 4 weeks and till all the joints have been sealed, as specified
above.

7.23 The expansion joints shall not be more than 20mm. For filling the joints,
either pre-moulded or poured types of filers as described below may be
used.
(a) Sand 60%; asphalt 30%; saw-dust 7%; cement 3%.
(b) 80kg of hot bitumen; 1 kg cement; 0.25 cum of coarse sand.

7.24 Joints should not be sealed while the concrete is still green or when it
is damp. The sealing compound shall be heated until it is fluid enough
to pour easily into the joint. Rubberised compositions shall not be
heated above 1800. Preparation of base, lying of concrete/joints etc.
shall conform to the Indian Standard Specifications.

7.25 Cement concrete paving/parking shall be provided on front, rear &


sides, if any of Switch House Building as per drawing No. HCD/SK-
172. The concrete blocks shall be of size 4’×6’. The blocks shall be
casted in situ alternatively but after 48hrs. No gap is to be left between
the panels. Top surface be left rough but should be in level. Suitable
slope of earth for drainage of rainwater be provided.

7.26 RCC pipe culverts shall be provided at appropriate location(s) in the


roads as per site requirement. The culverts shall be of one or two pipes
(750mm i/d) as per situation. The exact location, number and diameter
of RCC pipe shall be decided by the HVPN. The design of culvert shall
be as per IRC standards for class ‘A’ loading. The design data,
contours and details required for design of culvert shall be submitted by
the successful bidder along with the design/drawing to HVPNL for
approval.

7.27 The finished surface shall be uniform and conform to the lines, grades
and typical X-section shown in the approved drawing.

12
8.0 TRANSFORMER FOUNDATION

8.1 TRANSFORMER FOUNDATION (2x100 MVA):

The transformer foundation plinth for placing the transformer shall be of


RCC having minimum Grade M-20 laid on base concrete (1:4:8) of
minimum thickness 100 mm. Foundation shall be designed for the
equipment load requirements of transformer including impact load
equivalent to 15% of total transformer load including oil etc. or total
Jacking Load whichever is more. The top of plinth i.e. top of rail level
shall match with height of tractor-trailer used for transporting the
transformer (minimum 750-mm from top of road). The plinth shall
extend upto edge of road for perfect movement from trailer to plinth
and vice-versa. Suitable arrangement for shifting the transformer from
trailer like jacking etc. wherever required shall be made in plinth and in
front of plinth on the road.

The space between the tract rails of the transformer plinth if any, shall
be suitably filled with compacted sand and 50-mm thick PCC of grade
1:2:4 laid on 75-mm thick base concrete (1:5:10) placed over
compacted earth filling. The top of PCC shall be minimum 300-mm
above the formation level of switchyard. Adequate drainage outlets
shall be provided and necessary slopes given to drain off rain water/oil.

The deep beam/wall having rails at top shall be of minimum thickness


as 300 mm and suitably restrained at ends by beam/ wall of same
thickness.

The rails shall be fresh, first quality 52-kg/meter medium manganese


steel as per Indian railway specification T-12-64 and its subsequent
revisions. Suitable arrangement shall be made to maintain the rail
gauge.

Suitable foundations shall be provided for all auxiliary equipment of the


transformer like radiators, fan supports etc. as required. The work of
Transformer foundation shall be taken in hand only after approval of
transfer equipment drawing and the transformer plinth foundation shall
match the equipment drawing.

8.2 PARTICULAR SPECIFICATION

The cable trench to transformer shall terminate outside transformer pit.


The cables leading to various components of transformer shall pass
through GI pipes supported suitably in transformer pit.

8.3 FIRE PROTECTION WALLS

8.3.1 GENERAL

Fire protection wall for 100MVA T/F shall be constructed as per


drawing no. HCD/TS-1106 supplied with the bid document.

8.4 PARTICULAR SPECIFICATION

13
The cable trench to transformer shall terminate outside transformer pit.
The cables leading to various components of transformer shall pass
through GI pipes supported suitably in transformer pit.

9.0 CABLE & PIPE TRENCHES

SCOPE

9.1 The cable trenches shall be provided in switchyard and inside the
switch house building and GIS block to carry the control cables etc.
wherever required. The layout and size of Cable trenches in switchyard
area shall be as approved by the HVPNL and detailed in floor plan/
GELO as applicable for indoor and outdoor cables. The construction of
trenches for various sizes shall be as per detailed drawing attached
with the tender. The size of cable trenches in GIS block building, if
required shall be developed by the successful bidder and approved by
HVPNL based on the requirements of panels to be provided. Since
there will be level difference in formation levels of S/Yard & plinth level
of S/House and GIS block buildings, the trenches have to be in proper
slope/stair.

9.2 Trenches shall be of reinforced cement concrete of M-20 grade. MS


angle 50x50x6mm welded with MS flat 50x6mm – 75mm long @1
meter c/c to hold the angle shall be provided on top of the trench walls
for protection of the edges.

9.3 RCC cable trenches and precast removable RCC covers enclosed by
suitable MS angles for edge protection in respect of switch yard
trenches (with lifting arrangement) shall be designed to withstand self
weight of top slab + concentrated load of 150kg at center of span on
each panel.

9.4 7mm thick chequred plates with lifting arrangement the bottom of which
shall be welded with MS Angle 65x65x6 mm for holding the plates shall
be provided over the indoor cable trenches.

9.5 Medium weight channels (ISMC) of 75x40mm shall be provided @


600mm across the indoor cable trenches to support the chequred
plates. The length of chequred plates shall be 600mm except at the
ends/bends.

9.6 The cables shall be placed on hard wood supported on steel racks of
MS Angles 50x50x6 (grouted in the RCC walls) spaced 1.0-m c/c. The
ends of the horizontal MS angles should be fixed with suitable angle
(by welding at 900) to hold the cables. All the racks (MS angles) shall
be painted with anti corrosive paint.

9.7 The top of trenches shall be kept at least 25mm above the gravel level.
The top of cable trench shall be such that the surface rain water do not
enter the trench.

14
9.8 All metal parts inside the trench shall be connected to the earthing
system.

9.9 Trench wall shall not foul with the foundations. Cable trenches shall be
blocked at the ends (if required for future extensions) with brick
masonry 1:6 in cement sand mortar and this brick masonry work shall
be plastered from both sides with cement sand mortar 1:4.

9.10 The trench bed shall have a slope of 1/500 along the run & 1/250
perpendicular to the run. In case straight length exceeds 30m, suitable
expansion joint shall be provided at appropriate space. The expansion
joint shall run through vertical wall and base of trench. All expansion
joints shall be provided with approved quality PVC water stops of
approx. 230x5 mm size.

9.11 Suitable box culvert (Single span or multi spans) shall be provided for
any road crossing. The box culvert shall extend 1.5 m on each side of
road and shall have 230-mm wide, 500mm high brick parapet wall at
ends. If required, the bed of trench on both sides of culvert shall have
to be lowered in slope, in 1.5 m length to meet the bed of culvert.

9.12 Necessary sumps shall be provided at suitable places as per direction


of HVPNL and each sump shall be provided with pumps of 1 HP
capacity with all accessories shall be supplied for pumping out water
collected in the cable trenches. Cable trenches shall not be used as
storm water drains. Man hole shall be provided at interval of not more
than 30 meters. This clause shall be applicable as per site requirement.

10.0 FOUNDATION FOR RCC CONSTRUCTION (GENERAL)

10.1 Work covered under this clause comprises the design, engineering,
supply and construction of foundations and other RCC constructions
for switchyard structures, equipment supports, trenches, drains, jacking
pad, crane hoisting, pulling block, control cables, bus supports,
transformers marshalling kiosks, auxiliary equipment system buildings
or for any other equipment or service and any other foundation
required to complete the work. This clause is as well applicable to other
RCC constructions.

10.2 In case of overlapping of foundations in switchyard area, deeper


foundation shall be constructed first. The foundations resting on filled
up soil, the fill material under foundation/trenches shall be such that the
maximum pressure from the footing transferred through fill material will
not exceed the allowable soil bearing pressure of original undistributed
soil.

10.3 In case earth filling is involved due to high fixation of formation level, all
foundation shall rest below virgin ground level and the minimum depth
excluding lean concrete of all foundations below virgin ground level
shall not be less than 500mm.

10.4 All the properties of concrete regarding its strength under compression,
tension, shear, punching and bond strength etc. as well as
workmanship will conform to IS: 456.

15
10.5 The concrete used as lean concrete or base concrete under the
structure/equipment/trench etc. foundations shall be minimum 100 mm
thick (1:4:8) irrespective of any thickness or grade of concrete
mentioned on drawings. The aggregate size shall be 20mm nominal for
100mm thickness and 40mm nominal for thickness more than 100mm.
Base concrete shall be well compacted. The top surface of base
concrete shall be leveled before placing the reinforcement. During
excavation if excavation exceeds than the required depth or if any
loose pocket of earth is met below the base then the loose earth shall
be removed or excavation depth be increased till normal hard soil is
met as per satisfaction of HVPN. This extra depth shall be filled with
lean concrete. No extra shall be payable an account of this extra
excavation and lean concrete.

10.6 If the site is sloppy, the foundation height will be adjusted to maintain
the exact level of the top of structures to compensate such slopes.

10.7 The Switch Yard foundations shall be 100mm above the finished
ground level or as per the manufacturers design. The plinth level of the
control room-cum-Administrative building shall be minimum 500mm
above the finished ground level. Keeping in view the surroundings,
plinth level of building shall be decided by the HVPNL.

10.8 The design and detailing of foundations shall be done based on the
approved soil data and sub-soil conditions as well as for all possible
critical loads and the combinations thereof. The spread or pile
foundation may be required based on soil/sub-soil conditions and
superimposed loads.

10.9 The cement concrete used for foundation shall be of grade M-20
(irrespective of any grade mentioned on the drawings). The mix-
design (conforming to IS-Standards) shall be done prior to start of
work, as per specifications, got approved from HVPNL and shall
be used for the construction, provided there is no change in the
source and the quality of materials. The source of material shall
be intimated to the HVPNL and shall be ensured that Mix design is
with the materials from intimated source only and it is not
changed during construction. In case source of material changes
or quality of material differs from the earlier approved parameters
the Mix design shall be done again.

10.10 The Coarse aggregate used shall be of 20 mm graded or two types of


single size aggregate mixed in some fixed ratio to have graded 20mm
aggregate. The Coarse aggregate shall conform to IS 383.

10.11 Grading of Fine aggregate shall conform to Zone-II of Table - 4 of IS:


383 and shall be free from deleterious materials.

10.12 The environmental exposure condition considered for mix design shall
be MILD.

10.13 For Mix-design, the degree of quality control shall be considered as


FAIR.

16
10.14 The Water cement ratio shall be minimum 0.50 and maximum 0.55.

10.15 The minimum slump shall be 25mm and maximum 75mm.

10.16 For Volumetric use of ingredients for concrete mix, the Bidder
shall intimate the size of measuring boxes along with the Mix-
design.

10.17 Ordinary Portland Cement (OPC) of Grade 43 conforming to IS: 8112


manufactured by major cement manufacturer shall be used.

10.18 The water used for preparing concrete and for curing purpose shall be
fresh, clean and free from oil, acids and alkalis, organic materials or
suspended or other deleterious substances. Saltish or brackish water
shall not be used. Water used for construction & curing etc. shall be
conforming to requirements of IS: 456 Clause 5.4. Bidder shall
arrange at his own cost sufficient quantity and good quality water
for construction and curing and other purposes.

10.19 No admixtures shall be used except water proofing cement additives


conforming to IS 2645 with the approval of the HVPNL.

10.20 Reinforcement steel (including TMT) Bars manufactured by main


producers or their authorized rerollers in India or abroad shall be used
and certificates in this regard shall be submitted by the Bidder to the
entire satisfaction of the HVPNL. The steel used shall conform to IS:
1786 for deformed and cold twisted bars. Required grade of steel shall
be Fe-415. All reinforcement shall be clean and free from loose mill
scale, dust, loose rust and coats of paint, oil or other coating, which
may destroy or reduce bond with concrete. Reinforcement bars should
be fresh. Bidder shall supply, fabricate and place reinforcement to
shapes and dimensions as indicated on the drawings or as required to
carry out the intent of drawings and specifications. Adequate nos. of
chairs, spacers of required size shall be provided to ensure the proper
placement of reinforcement. The reinforcement bars crossing one
another should be tied together at every intersection with two strands
of annealed steel wires 0.9 to 1.6 mm thick twisted and tied to make
the skeleton of the steel work rigid so that the reinforcement does not
get displaced during concrete placement.

All the reinforcement steel should be placed/ stacked at site store on


raised (at least 0.5 meter from near surroundings) pucca/brick platform
or reinforcement steel should be placed on MS/GI sheets. The
reinforcement steel after stacking should be covered with Tarpaulin to
avoid corrosion. Immediately before concreting (portion of
reinforcement to be embedded in concrete) shall be painted with
cement slurry after removing any rust/corrosion/any other foreign
material. Overlaps in more than 30% of bars will not be allowed at a
section. Fabricated Reinforcement bars shall be placed in position as
shown in the drawing or as directed by HVPN.

10.21 The bars crossing one another shall be tied together at every
intersection with two strands of annealed steel wires 0.9 to 1.6mm dia.

17
twisted and tied to make the skeleton of steel work rigid so that
reinforcement does not get displaced during placement of concrete.

10.22 Two types of steel shall not be used.

10.23 All the foundation bolts used for equipment foundations & for main
gantry tower foundations shall be galvanized.

10.24 The foundation bolts shall be embedded in concrete during concreting


and no grout holes shall be left for this purpose.

10.25 Excavation shall extend minimum 150 mm around foundation (from


RCC portion and not from lean concrete).

10.26 Proper shuttering & shoring shall be provided to support the excavated
earth face to avoid falling of earth. No extra charges shall be
admissible for the removal of fallen earth in the pit, once excavated.

11.0 MIXING, PLACING AND COMPACTION OF CONCRETE

11.1 The concrete shall be mixed in a mechanical mixer. The mixer shall
comply with IS: 1791 & 12119. The mixer shall be fitted with water
measuring devices.

11.2 Mixing shall be continued until there is uniform distribution of material


and the mix is uniform in colour and consistency. If there is segregation
after unloading from mixer, the concrete should be re-mixed, but in no
case the mixing shall be done close to the foundation, or place of work
but in case it is not possible the concrete may be mixed at the nearest
convenient place. From mixer, concrete shall be put on pucca platform
or steel troughs, which shall be leak proof to avoid any loss of
water/slurry. The concrete shall be transported from the place of mixing
to the place of final deposit as rapidly as practicable, which shall
prevent the segregation before any setting commences.

11.3 Proper shuttering shall be used for the construction of all type of
PCC/RCC works. Shuttering shall be rigidly tightened so that there are
no distortions in the shape. Shuttering shall be made sufficiently strong
to with stand all the loads and vibrations. Vibrators shall be used to
ensure thorough compaction.

11.4 After the shuttering has been removed, if the concrete surface is found
to be slightly damaged, same shall be repaired with rich cement sand
mortar to the satisfaction of the HVPNL's representative before the
foundation pits are back-filled.

12.0 CURING

The concrete after setting for 24 hours shall be cured by keeping the
concrete wet continuously for a period of 10 days (minimum) after
laying. The foundation be back filled with selected good earth free from
harmful salts, organic material, sprinkled with necessary amount of
water and well consolidated in layers not exceeding 200 mm of
consolidated thickness after a minimum period of 72 hours and

18
thereafter both backfilled earth and exposed top shall be kept wet for
the remainder of the prescribed curing time. The uncovered concrete
portion above the backfilled earth or vertical columns etc. shall be kept
wet by providing empty cement jute bags dipped in water fully wrapped
around the concrete for curing and ensuring that the bags are kept wet
by the frequent pouring of water on them. In case Portland Pozzolona
cement has been used, curing period shall be increased by HVPN.

13.0 DISMANTLING

The Bidder wherever required, shall carry out dismantling & disposal of
PCC/RCC upto a lead of 15 Km or as directed by the HVPN, to make
space for the proposed structures in the new proposed bays of the
Sub- Stations.

14.0 DESIGN

14.1 All the foundations except walls of switch house building, sum-pit etc.
shall be of Reinforced Cement Concrete. The design and construction
of RCC structures shall be carried out as per IS: 456 and minimum
grade of concrete shall be M-20 and the M-25 for water retaining
structures. Higher grade of concrete than specified above may be used
by the Bidder at the discretion of HVPNL without any additional cost to
the HVPNL.

14.2 Limit state method of design shall be adopted unless specified


otherwise in the specification/IS Codes.

14.3 For design and construction of steel-concrete composite beams IS:


11384 shall be followed.

14.4 For detailing of reinforcement, IS: 2502 and SP: 34 shall be followed.
Two layers of reinforcement (on inner and outer shall be provided for
wall & slab sections) having thickness of 150 mm and above. Clear
cover to reinforcement towards the earth face shall be minimum 50 mm
and for other components, same shall be as per IS: 456.

14.5 The procedure used for design of the foundations shall be the most
critical loading combination of steel structure and or equipment and/or
superstructure and other conditions, which produces the maximum
stresses in the foundation or the foundation component and as per the
relevant IS Codes of foundation design. The Bidder, for approval of
drawings shall submit detailed design calculations along with drawings.

14.6 Designer shall consider sub-soil water pressure that may be


encountered, following relevant standard strictly.

14.7 Necessary protection to the foundation work, if required shall be


provided to take care of any special requirements for aggressive
alkaline soil, black cotton soil or any other type of soil which is
detrimental/harmful to the concrete foundations without extra cost to
the HVPNL.

14.8 RCC column shall be provided with rigid connection at the base.

19
14.9 All sub-structures shall be checked for sliding and overturning stability
during both construction and operating conditions for various
combinations of loads. Factor of safety for these cases shall be taken
as mentioned in relevant IS Codes or as stipulated elsewhere in the
specifications. For checking against overturning weight of soil vertically
above footing shall be taken and inverted frustum of pyramid of earth
on the foundation should not be considered. In case of trench passing
above the footing base then for over turning only dead weight of trench
shall be considered.

14.10 Earth pressure for all underground structures shall be calculated using
coefficient of earth pressure at rest, co-efficient of active or passive
earth pressure (whichever is applicable). However, for the design of
sub-structures of any underground enclosures, earth pressure at rest
shall be considered.

14.11 In addition to earth pressure and ground water pressure etc. a


surcharge load of 2T/sq. m shall be considered for the design of all
underground structures including channels, sumps, tanks, trenches,
substructure of any underground hollow enclosure etc. for the vehicular
traffic in the vicinity of the structure or otherwise.

14.12 Following conditions shall be considered for the design of water tank in
pumps house, channels, sumps and trenches and other underground
structures.

a) Full water pressure from inside and no earth pressure and ground
water pressure & surcharge pressure from outside, (applicable only to
structures which are liable to be filled up with water or any other liquid).
b) Full earth pressure, surcharge pressure from outside and no water
pressure from inside.
c) For any water retaining structure or any member submerged in water
the minimum grade and concrete shall be M-25.
d) Design shall also be checked against buoyancy due to the ground
water during construction and maintenance stages. Minimum factor of
safety of 1.5 against buoyancy shall be ensured ignoring the super
imposed loadings.

14.13 Base slab of the any underground enclosure like water storage tank
shall also be designed for empty condition during construction and
maintenance stages with maximum ground water table (GWT) at 2.0
m. below ground level. Minimum factor of safety of 1.5 against
buoyancy shall be ensured ignoring the super-imposed loading.
Intermediate dividing piers of such enclosures shall be designed
considering water in one pump sump only & the other pumps sump
being empty for maintenance.

14.14 The foundations shall be proportioned so that the estimated total and
differential movements of the foundations are greater than the
movements that the structure or equipment is designed to
accommodate.

20
14.15 The foundations of transformer/reactor and circuit breaker shall be of
block type foundation. Minimum reinforcement shall be governed by IS:
2974 and IS:456.

14.16 The tower and equipment foundations shall be checked for a factor of
safety of 2.2 for normal condition and 1.65 for short circuit condition
against sliding, overturning and pullout. The same factors shall be
used as partial safety factor over loads in limit state design also.

14.17 MACHINE FOUNDATIONS:

a. All machine foundation shall be designed in accordance with the


provisions of the relevant parts of the latest revisions of Indian
standards IS: 2974, IS: 456 and IS: 2911. The provisions of DIN 4024
(latest) shall also be followed.
b. For the foundations of rotating machines, detailed static and dynamic
analysis shall be done. A fatique factor of 2.0 shall be considered for
dynamic forces. Minimum reinforcement shall be governed by IS: 2974
as well as IS: 456. RCC design shall be done by working stress
method.
c. All block foundations resting on soil or piles shall be designed using he
elastic half space theory.
The mass of the RCC block shall not be less than three times the mass
of the machine Dynamic analysis shall be carried out to calculate
natural frequencies in all the modes including coupled modes and to
calculate vibration amplitudes. Frequencies and amplitude criteria as
laid down by the relevant IS codes and/or machine manufacturers shall
be satisfied, minimum reinforcement shall be governed by IS: 2974 and
IS: 456.
d. For the foundations supporting minor equipments weighting less than
one ton or if the mass of the rotating parts is less than one-hundredth
of the mass of the foundation, non dynamic analysis is necessary.
However, is such minor equipment is to be supported on building
structures, floors etc. suitable vibration isolation shall be provided by
means of springs, neoprene pads etc. and such vibration isolation
system shall be designed suitably.

15.0 OTHER FOUNDATIONS

15.1 All foundations shall be designed in accordance with the provisions of


the relevant parts of latest revisions of Indian Standards IS: 456 and
other relevant Indian Standards.

15.2 Type of foundation system i.e. isolated footing or raft etc. shall be
decided based on the load intensity and soil strata.

16.0 BUILDINGS

16.1 GENERAL SCOPE

The Scope shall include construction of switch house building including


providing anti-termite treatment, plinth protection DPC of building,
sanitary, water supply, sintex/diplast polyvinyl tanks, electrification
including supply and providing of 2T split high wall mounted/window

21
ACs (as per electrical design requirement mentioned elsewhere) and
56” ceiling fans, 4ft. long CFL tubes with fittings modular switches,
boxes, electric wire etc. as per architectural drawings, flooring, finishing
items including acrylic emulsion and whether proof (exterior acrylic
paint), anodized aluminium doors/windows/ventilators frames provided
with 5.5mm thick glass, fire doors, indoor cable trenches with covers in
control room/battery room/ACDB/DCDB rooms etc. etc. complete in all
respect. Scope also covers any other item required for the completion
of building which has not been mentioned in the specification or in the
drawings.

HVPNL reserves the right to alter the finishing schedule and


specifications, therefore, such changes will have no additional financial
implication whatsoever to the HVPNL.

16.1.1 STORM WATER DRAINAGE FOR ALL BUILDINGS

The building drains shall be provided for the collection of storm water
from the roofs. This water shall be collected in junction boxes and
these boxes shall drain to the main drainage system of the station.

Cast iron rain water down comers conforming to IS: 1230 with water
tight lead joints shall be provided to drain off the rain water from the
roof. These shall be suitably concealed with masonry work of cement
concrete or cladding material. The number and size of down comers
shall be governed by IS: 1742 and IS: 2527.

All drains inside the buildings shall have minimum 40mm thick grafting
covers and in areas where heavy equipment loads would be coming,
pre-cast RCC covers shall be provided in place of steel grating.

For all buildings, suitable arrangement for draining out water collected
from equipment blow down, leakage, floor washings fire fighting etc.
shall be provided for each floor.

16.2 MATERIALS

The brief requirement regarding various materials to be used for


construction of building are detailed below or specified in respective
drawings. However, materials not specifically mentioned in the
specifications/drawings, the same shall also conform to the relevant IS
codes and got approved from the HVPNL before being used. The
Bidder shall remove from site any material not conforming of IS
Standards or rejected by the representative of HVPNL/HVPN.

16.3 BRICKS AND TILES

The bricks used shall be first Class bricks of nominal size


(22.86x11.11x6.83) cm so that every four courses shall measure 30.48
cm in height. A tolerance upto ± 6.5 mm in length ± 3.0 mm in width and
± 3.0 mm in thickness shall be permitted. The bricks shall be made from
good brick earth free from efflorescence/kankar, thoroughly burnt and
uniform deep red colour, regular in size and shape with parallel faces
and sharp edges, homogenous in colour, free from flaws etc, and shall

22
have all the qualities of a good brick. Bricks and tiles shall have ringing
sound when struck with each other.

Bricks shall have a minimum crushing strength of 105 kg/per sq. cm


and shall not absorb water more than 20% of its own dry weight after 24
hours immersion in cold water.

For tile terracing and tile facing, size of tile shall be (22.86x11.43x3.18)
cm having permissible tolerance of IS Standards for length ± 3 mm, ± 3
mm for width and 1.5 mm for thickness.

16.4 SAND (FOR MASONRY MORTAR & PLASTER)

Sand for masonry work and plaster shall preferably consist of natural
sand, However crushed stone sand or crushed gravel sand or a
combination of any of them be used. Sand shall be hard, durable, clear
and free from harmful impurities like iron pigments, mica salts, coal or
other organic impurities. Grading of sand for use in masonry mortar
shall be conforming to IS: 2116 and for use in plaster shall conform to
IS: 1542 tabulated as below:

IS Sieve Designation For mortar For Plaster


Percent passing by mass
10.0 mm - 100
4.75 mm 100 95 to 100
2.36 mm 90 to 100 95 to 100
1.18 mm 70 to 100 90 to 100
600 micron 40 to 100 80 to 100
300 micron 5 to 70 20 to 65
150 micron 0 to 15 0 to 50

The maximum quantities of clay, fine silt, fine dust and organic
impurities shall not exceed limits described in IS: 2386 (Part II). Clay,
fine dust and silt in natural sand or crushed gravel sand or crushed
stone sand not more then 5% by mass.

16.5 BRICK WORK

All brickwork shall strictly be according the specifications and notes


specified in the drawings. All bricks shall be soaked in stacks by
spraying clean water at regular intervals to keep them wet to the
satisfaction of HVPN. Each brick shall be set (with frog upwards) with
bed and vertical joints completely filled with mortar. Thickness of
mortar joint shall be 6.25 mm and shall not be more than 9.4 mm. For
exposed brickwork, bed joint will be 7.81 mm thick and vertical joint
6.28 mm.

All brickwork shall be true in plumb, straight edge, for exposed


brickwork or face work bricks shall be selected for purpose. The face
joints shall be duly racked to minimum depth of 13 mm when mortar is
green for providing key to plaster or pointing. The mortar used for brick
work/ plasterwork shall be machine mixed only.

23
All fixtures, doors/windows/CI pipes, outlet for water, hold fasts etc.
which are required to be built/laid in brickwork shall be embedded
simultaneously. Each day work done shall not be more than 1m in
height and no portion of the work shall be left more than 1m lower than
the other. The height of brick courses shall be kept uniform.

All the half brick thick walls shall be provided with 2 numbers - 6 mm
bars at every fourth layer.

In case of difference in the natural ground level and formation level, no


extra payment on account of extra brick work whether in building or
boundary wall shall be paid extra. The Bidder may, therefore, visit the
site before quoting rates for the brick work.

16.6 DAMP PROOF COURSE

On outer walls horizontal DPC shall be provided at level with plinth


protection and on inner face vertical DPC 20 mm thick, shall be
provided. On all inner walls horizontal DPC shall be provided at
floor/plinth level.

Horizontal DPC shall consist of cement concrete (1:1.5:3) 50 mm thick.


Edge of DPC shall be straight, even and vertical. It shall be cured for at
least 7 days, after which it shall be allowed to dry. Vertical DPC shall
consist of two layers of plaster (1:3) with total thickness of 20 mm. Hot
bitumen shall be applied over dried up surface in thin layer.

16.7 PAINTING, ACRYLIC EMULSION DISTEMPER/WHETHER PROOF


ACRYLIC PAINT

The switch house-cum-administrative building including walls & ceiling


shall be provided with Acrylic emulsion paint of reputed make over
prepared base. The outer face of building shall have peach colour
cement based whether proof exterior (acrylic paint) coating. Columns,
beams parapet and plastered area shall have mid cream colour
whether proof coating. All the steel work, wire mesh, doors & windows
etc., shall have first quality paints of approved make/shades. The
boundary wall shall be provided with water proof acrylic paint. All fire
fighting MS pipes shall have post office red colour

16.8 MATERIALS

The lime for white washing shall be unslaked lime of good quality,
which shall be slaked at spot, mixed with water at least for 24 hours,
than stained through coarse cloth, Indigo & some binding material like
gum be added in proper quantity before use. For colour washing
pigment of approved colour in proper quantity shall be used.

The Priming Paint shall conform to IS: 109 (Alkali resistant priming
paint).

24
The Acrylic emulsion distemper and whether exterior acrylic paint shall
be of superior quality manufactured by standard firms like ASIAN,
NEROLEC, BERGER, DULUX, SHALIMAR etc. The material should
be brought to site in sealed condition and stored properly.

All paints and allied materials shall be of superior quality manufactured


by standard firms like ASIAN, NEROLEC, BERGER, DULUX,
SHALIMAR etc. and meet the requirements of following Indian
Standards for wooden and metallic surfaces and shall be of approved
brands and manufacturer and of approved shade.

a) Primer for woodwork shall be conforming to IS: 3536, for Iron,


steal etc. shall be conforming to IS: 2074. The primer shall be
ready mixed primer.

b) Synthetic enamel paint shall be conforming to IS: 117, IS: 133


and IS: 137 of first quality.

16.9 APPLICATION

All the white wash/colour wash shall be done on well-prepared


surfaces to the satisfaction of HVPN. Minimum of 3 coats shall be
applied. The work shall be carried out as per IS: 6278.

a) DISTEMPERING: Two coats of acrylic emulsion distemper shall be


applied over a priming coat as detailed below:

i PREPARATION OF SURFACE: For new work the surface shall be


thoroughly cleaned of dust, old white or colour wash by washing and
scrubbing. The surface shall then be allowed to dry for at least 48
hours. It shall then be sand papered to give a smooth and even
surface. Any unevenness shall be made good by applying putty, made
of plaster of pairs mixed with water on the entire surface including filling
up the undulations and then sand papering the same after it is dry.

ii PRIMING COAT: The priming coat shall be with distemper primer or


cement primer.

iii A coat of alkali resistant priming paint conforming to IS:109 shall


be applied and allowed to dry for atleast 48 hours before
distempering is commenced.

iv ACRYLIC EMULSION/DISTEMPERING COAT: For new work, after


the primer coat has dried for at least 48 hours, the surface shall be
lightly sand papered to make it smooth for receiving the distemper,
taking care not to rub out the priming coat. All loose particles shall be
dusted off after rubbing. One coat of distemper properly diluted with
thinner (water or other liquid as stipulated by the manufacturer) shall be
applied with brushes in horizontal strokes followed immediately by
vertical ones, which together constitutes one coat.

v The subsequent coats shall be applied in the same way. Two or more
coats of distemper as are found necessary shall be applied over the
primer coat to obtain an even shade.

25
A time interval of at least 24 hours shall be allowed between
successive coats to permit proper drying of to preceding coat.

b) The wooden surface shall be cleaned of all unevenness, which shall be


removed by rubbing with a sand paper. The surface treated for
coatings, shall be dried before primer coat is applied.

c) PAINTING

i. All rust & scale be removed by scrapping or by brushing with


steel wire brush.
ii. The primer coat shall be allowed to dry before painting is
started.
iii. The putty around glass panes shall also be painted.
iv. The additional coats of paint etc. shall be provided if required for
the required finish as per HVPN.

16.10 FLOORING

The flooring of switch house building except battery room and toilet
shall be of precast terrazzo tiles. Anti-skid tile 300x300x7.7mm flooring
in toilets and pantry and acid-resistance tiles shall be provided above
40mm thick PCC (1:2:4) flooring in battery room.

Before flooring work is taken up, works such as laying of services


which otherwise would affect the laying of floors, plastering of all inside
& outside walls, ceilings, fixing of doors and window frames in place
and all heavy work in room may be completed.

The base layer for all floors shall be of 100-mm thick sand and 100 mm
thick cement concrete 1:5:10 laid on sand. The sand for base filling
shall be clean and dry, free from clay clods and other harmful
impurities such as iron pigments alkalis, coal and lignite, materials finer
than 75 microns. Sand shall be of particle size ranging from 1.18 mm to
150 micron. The fineness modulus shall vary from 0.8 to 1.0.
Generally sand fit for plastering is fit for sand filling under floor.

The pre cast terrazzo tiles of 300x300x25mm minimum thickness (the


finished thickness of the top upper layer shall be 10mm) in 50% white
& 50% ordinary grey cement with marble chip conforming to IS: 1237-
1980 and pre-polished granite stone (slab) flooring as approved by
HVPNL shall be laid on 20 mm thick bed of cement coarse sand mortar
1:3. The mortar shall be evenly spread over the base for two rows of
tiles and about three to five meters in length. The top of mortar shall be
kept rough so that cement slurry can be absorbed. Neat cement slurry
of honey like consistency shall be spread over the mortar bed @ 5 kg
per sq. meter. The joints shall be kept as thin as possible (not
exceeding 1.5 mm) and filled with neat cement slurry, treads of steps
and landing, if any. The floor shall be kept wet or flooded with water
and protected against damage due to traffic or any other cause, for at
least seven days after finishing the tiles.

26
After the tiles are cured and have dried up, these shall be ground
evenly with machine fitted with special rapid cutting grit blocks
(carborundum stone) of coarse grade (No. 60) till the marble chips are
evenly exposed and the floor is smooth. After the first grinding, the
surface shall be thoroughly washed to remove all grinding mud and
covered with a grout of cement and colouring matter in same mix and
proportion as the topping in order to fill any pin holes that appear. The
surface shall be allowed to cure for 5 to 7 days and then rubbed with
machine fitted with fine grit blocks (No.120). The surface is cleaned
and repaired as before and allowed to cure again for 3 to 5 days.
Finally the third grinding shall be done with machine fitted with fine
grade grit blocks (No. 320) to get even and smooth surface without
pinholes. The finished surface should show the marble chips evenly
exposed.

Where use of machine for polishing is not feasible or possible, rubbing


and polishing shall be done by hand, in the same manner as specified
for machine polishing except that carborundum stone of coarse grade
(No. 60) shall be used for the 1st rubbing, stone of medium grade (No.
80) for second rubbing and stone of fine grade (No. 120) for final
rubbing and polishing.

After the final polish either by machine or by hand, oxalic acid shall be
dusted over the surface @ 33 gm per square meter sprinkled with
water and rubbed hard with a nemdah block (Pad of Woolen rags). The
following day, the floor shall be wiped with a moist rag and dried with a
soft cloth and finished clean.

Anti skid floor tiles of reputed makes such as Somany, Kajaria, Nitco
etc. having minimum 300x300 mm nominal size and 7.7 mm thick
preferably in Beige colour shall be provided in the toilets. The tiles shall
conform to relevant EN/IS codes. The tiles shall conform to relevant
EN/IS codes. The tiles & the colour scheme shall be got approved from
the HVPNL.

Entire area around the Switch house building shall be provided with
PCC paving upto 1 meter from the outer edge of the building.

16.11 SKIRTING

Matching pre-cast terrazzo tiles 300x150x25mm made in 50% white &


50% grey cement conforming to IS: 1237-1980 shall be used in areas
provided with pre-cast terrazzo tile flooring. The minimum finished
thickness of tiles shall be 12.5 mm. Tile skirting and dado shall be fixed
only after laying the tiles in the floor. The portion of the wall to be
covered with skirting and dado shall be left unplastered. The wall
surface shall be evenly and uniformly covered with about 10 mm thick
backing of cement coarse sand mortar 1:3. However, in the case of
skirting, the tiles may be directly fixed without application of back as a
separate course. Before the backing mortar has hardened, the back of
each tile to be fixed shall be covered with a thin layer of neat cement
paste and the tile gently tapped against the wall with a wooden mallet.
The fixing shall be done from the bottom of the wall upwards. All the tile
faces shall be set in conformity with one another and shall be truly

27
vertical. The sides of the tiles shall be coated with grey or white
cement slurry with or without pigment to match the shade of tiles and
butt jointed. The joints shall be as thin as possible.

Tiles shall be ground and polished as for flooring by hand.

In toilets, the skirting/dado shall be of tiles of 6.7mm thick 200x200 mm


size of reputed makes such as Somany, Kajaria, Nitco etc. and should
go upto 6'-9" high from floor level. The tiles shall conform to relevant
EN/IS codes. The tiles & the colour scheme shall be got approved from
the HVPNL. Skirting/daddo colour and style should match with the
flooring.

16.12 DOORS /WINDOWS

The Bidder shall provide & fix Aluminium chowkhats/doors/windows/


ventilators (single & double leaf) consisting frame work including
vertical styles, top rails, lock (middle) rails and bottom rails with metal
fastener & screws fitted with nuts & bolts or using rawl plugs & screws
as per HVPNL drawings. The Aluminum section to be used shall be of
10 gauge (3mm) anodized (15 micron) of reputed makes such as
HINDALCO/JINDAL conforming to IS: 1968-1983. The doors &
windows shall be fitted with 5.5mm thick glass of reputed make like
TATA FLOAT/SAINT GOBBAIN, high-class rubber gasket & aluminium
beading complete so to make the glass airtight. The toilet doors shall,
however, be fitted with pre-laminated board (NOVAPAN/KIT/DECCO)
panels of appropriate size with aluminium beading to make it airtight.
The door/floor springs, locks (six lever of Godrej or equivalent),
handles, tower bolts, stoppers with rubber cushion, screws etc. shall be
of 1st quality ISI make as approved by HVPN.

16.13 TOILET & PANTRY FIXTURES

All the water closets, wash basins, squatting panes etc. shall be of
vitreous China clay in white colour, (first quality) conforms to IS: 2556.
The water closet in officer’s toilet shall be European type with single
syphonic low-level cistern. In general toilets high-level cistern shall be
provided with Indian type water closet. Providing and fixing in position
best Indian make 20mm dia., 600mm long towel rails fixed in raw slugs
embedded in walls with CP brass screws. All fixtures/fittings shall be
chromium plated of best quality and shall be approved by the HVPN.

Providing & fixing best Indian make white vitreous chinaware sink of
size 600x450x250mm with complete fittings including 40mm CP brass
waste and PVC pipe chromium plated brass tap. Granite slab 20-25mm
thickness as approved by HVPN is to be provided in the kitchen as
shown in drawing.

All water supply pipes shall be GI Pipes (medium quality) conforming


IS:1239 along with specials ISI marking.

All drainage pipes shall be HCI pipes along with special and ISI
marked, embedded in walls, having concrete 1:2:4 around the

28
horizontal pipes up to first inspection chamber/gully trap shall also be
HCI pipes.

From Inspection chamber onwards to soakage pit or to existing


sewerage system as the case may be SW Pipes shall be used.

Construction of soakage pit near switch house building or laying of SW


pipes up to sewerage system within sub-station is in scope of this bid.

16.14 ROOF

SCOPE:

This section covers the furnishing of all labour, materials, and


equipments and performing of all operations necessary to complete all
works for insitu water proofing of roofs using glass fibre based felt type-
2. Grade-I or fibre glass Tissue Reinforced Bitumen conforming to IS:
7193 (latest) and workmanship conforming to IS:3067 (latest) and IS:
9918 (latest).

16.14.1MATERIALS:

a. The glass fibre base felt shall be thin, flexible, uniformly bonded felt
composed of reinforced glass fibre coated on both sides with bitumen
modified with thermoplastics polymers. The bonding material shall
consist of modified grade bitumen (140/35).

The fibre glass tissue shall be thin, flexible, uniformly bonded mat
composed of chemically resistant borosilicate staple fibre glasses
distributed in a random porous structure, bonded together with a
thermosetting resin (phenotic type). The minimum weight of the tissue
shall not be less than 40gms per square meter and nominal thickness
shall be 0.50 + 0.1mm. The properties of fibre glass tissue shall
conform to IS: 7193 (latest).

b. BITUMEN PRIMER: A liquid bitumen of low viscosity which penetrates


into a prepared surface upon application. Primer shall conform to the
requirements laid down in IS: 3384 (latest).

c. BONDING MATERIAL: It shall consist of blown type bitumen


conforming to IS:702 (latest) or residual grade bitumen conforming to
IS:73 (latest). This shall be prepared by heating bitumen between 175
degree C to 205 degree C. The penetration of bitumen shall not be
more than 40 when tested in accordance with IS: 1203 (lates).

d. The materials required for plastering and surface finish like cement,
sand, 1st class brick/brick tiles shall be as per respe3ctive IS codes.

16.14.2 PREPARATION SURFACE:

a. The surface to be waterproofed shall be cleaned with wire brush and


then plastered with 12mm thick cement mortar 1:4 (1cement :2medium
coarse sand).

29
b. Suitable slope (1:5:100) shall be provided with cement concrete 1:2:4
(1 cement : 2 coarse sand : 4 stone aggregate 10mm nominal sized)
over roof slab. Heat insulation over the roof shall be provided on the
top of cement concrete 1:2:4. The heat insulating surface shall be
plastered with 12mm thick cement mortar plaster 1:4. In case heat
insulation is not provided, 12mm thick cement mortar plaster shall be
provided over cement concrete (1:2:4) laver.

16.14.3 APPLICATION:

Brief details of various treatments shall be as under:

a. Clean and prime the dry plastered surface with bitumen primer at the
rate of 0.4kg per sqm. This should properly embed the surface and
should be left till the time it is touch dry.

b. Apply the first coat of bitumen at the rate of 1.6 kg per sqm (min.) ato
the extent of width of felt/tissue roll.

c. Embed first layer of felt/tissue. The overlap shall be 100mm between


layers in either direction. The process shall be continued till the whole
proposed area is covered.

d. Apply second coat of hot bitumen at the rate of 1.6 kg per sqm (min.)

e. Apply second layer of felt/tissue. This layer of felt/tissue shall be


embedded perpendicular to earlier layer.

f. Apply third coat of hot bitumen at the rate of 1.6 kg per sqm (min.).

g. Apply third layer of felt/tissue. This later of felt/tissue shall be


embedded perpendicular to the earlier layer.

h. Apply fourth coat of hot bitumen at the rate of 1.6 kg per sqm. (min.).

i. Provide 12mm nominal size gravel over fourth coat of hot bitumen.

j. 1st class brick tiles 40mm thick conforming to IS code shall be laid in
cement mortar 1:3 (1 cement : 3 medium coarse sand) over water
proofing treatment and joints grouted with cement mortar 1:3 (1
cement: 3 fine sand). Proper care shall be taken to see that no joints
are left unfilled or inadequately filled. The joints shall be finished flush
with the tile surface.

k. The gutter and drain mouths shall be treated for water proofing as per
IS: 1346 (latest).

16.14.3 JUNCTION OF PARAPET WALL AND ROOF;

Fibre glass based felt/tissue treatment shall be applied wherever


junctions vertical and horizontal structures occur with minimum overlap
of 1d00mm. The water proofing treatment shall be applied as per
IS:9918 (latest).

30
16.14.4 EXPANSION JOINTS:

In case of expansion joints, two layers of fibre glass based felt type-2,
grade-1 as per IS:7193 (latest) shall be laid loose overlapping one
another with the end of felt to the stuck with bitumen alternatively and
finally covered with a layer of reinforced fibre glass tissue impregnated
with hot bitumen. The entire treatment shall be laid as per IS: 1346
(latest) with fibre glass based felt type-2, grade-1. The water proofing
in situ treatment of expansion joints with fibre glass based felt/tissue on
RCC roof slab shall be carried out as per IS: 9918 (latest).

16.14.5 GUARANEE:

A written guarantee of the water tightness shall be given for a minimum


period of 10 years.

16.14.6 GENERAL

The work shall be carried out by specialists in the trade. Workers shall
be provided with gum boots and hand gloves. Minimum overlaps of
100mm shall be given at the ends and sides of the strips of the
felts/tissue and properly bonded with bitumen. Joints in the successive
layers of the fibre glass based felt/tissue shall be staggered. There
shall be no air pockets. Corners shall be treated flush without any air
pockets or voids.

a. The materials and the sub-Bidders executing the work shall be duly
approved by the Engineer-in-charge/owner’s consultant.

b. Adequate covering shall be provided during work to avoid splashing or


staining of adjacent works and surfaces. Any surface or work splashed
or stained shall be thoroughly cleaned to the full satisfaction of the
Engineer-in-charge.

16.14.7 All roofs shall be provided with access (1 Meter wide) through a
staircase/cage ladder.

16.14.8 RCC parapet walls of minimum 900mm height will be provided on roof.

16.15 RAIN WATER PIPES

All rain water pipes shall be 4" dia. HCI pipes along with fixtures. Rain
water pipes shall be embedded in wall during construction as shown in
drawings. At top of roof proper grating shall be provided.

16.16 ELECTRICAL ITEMS

The general requirement of electrical fittings shall be as per drawing


attached with tender. The bidder shall prepare the actual design and
detail of circuits to be provided and layout of pipes.

The wiring shall be recessed conduit wiring. Heavy duty PVC conduits
of 20/25/30mm size and wires 2.5/4/6 sq. mm copper for circuit wiring
& 1.5 sq. mm copper for earth including wiring for sub-mains, modular

31
switch boards, junction boxes, switches/sockets 5 Amp, 5/16 Amp and
16 Amp, 240V indoor and outdoor receptacle including 2T split/window
AC’s, electronic step regulator mounted on the switch boards, provision
for telephone wires including telephone junction boxes/tap blocks,
sockets.

Depth of inspection/junction boxes shall be 80 mm in ceiling and 28


mm on wall surface which may vary as per requirement of modular
switches/regulator.

All the split/window ACs, ceiling fans, 28W (T-5) CFL tubes etc. shall
be of reputed company like LG/Samsung/Hitachi/Videocon,
Crompton/Philips/Osram etc. All switches, fittings, sockets, fans shall
be of latest modular design and of reputed make like Crompton,
Havel’s, Philips etc. All the material shall conform to latest IS
specification/and ISI marked. All the electrical fitting including ACs,
fans shall be as per electrical drawing to be provided by the HVPNL or
developed by the successful bidder. The items not provided herein but
are required to be provided as per drawing requirement or site
requirement shall be provided by the successful bidder without and
extra cost to the HVPNL.

16.17 SWITCH – YARD FENCING AND GATE

Fencing & Gates shall be provided for Switchyard area as per General
Electrical Layout Plan and any other specified area along the lines
shown. The design shall be as per drawings attached with the tender.

Chain link fence fabric shall of size 75mm; coated wire shall be of
3.15mm dia having zinc coating after weaving. The chain link fabric
shall be fixed to the intermediate parts and at top & bottom of fence by
welding/fixing 50x6mm M.S. flat all through its length.

All structural steel manufactured by TISCO, SAIL, IISCO and


RASHTRIYA ISPAT (primary manufacturers) shall conform to IS:
20621786 shall only be used and shall be painted with a coat of
approved steel primer and two coats of synthetic enamel paint. The
bidders shall, however, be allowed to use Amba steel, Rathi steel,
Kamdhenu steel, Barnala steel, P.R.S steel, Shidbali steel
(manufactured by secondary manufacturers) only after obtaining non-
availability certificate from the primary manufacturers. Before using
secondary steel, the selected bidder would require to conduct all
physical & chemical tests (lot wise & dia. wise) to establish its
conformity to IS Standards conforming to IS 2062.

The barbed wire shall consist of two splices per reel. The barbed wire
shall be formed by twisting two line wires, one containing barbs. The
barbed wire shall be of 12 SWG galvanized steel with its weight 155-
186 gm/m length of wire. Distance between two barbs shall be 75mm.
The barbs shall carry four points and shall be formed by twisting two
point wires, each two turn tightly round one line wire making altogether
4 complete turn. The barbs shall be finished in such a way that four
points are set and locked at right angles to each other. The barbs shall

32
have a length of not less than 13mm and not more than 18mm. The
points shall be sharp and well pointed.

Fasteners – Single strand aluminum or galvanized steel, wire


conforming to requirements for fence fabric 4mm diameter.

Tension wires - Single strand, high tensile, galvanized steel wire


4mm diameter.

Fittings and Hardware – Cast aluminum alloy or galvanized steel


malleable or ductile steel. Cast iron D-Clamp to be drop forged with
bolt, Check nut, Thimble and other material required for stretching the
Barbed wire complete in all respect.

Generally the drawing attached with the tender shall be applicable.


However, if due to difference of levels between formation level and
Switchyard and outside, normal foundations have to be changed in
some portion and retaining wall have to be provided below due to site
requirements. Successful bidder for approval before execution will
submit the suitable design. Nothing extra shall be payable on this
account.

17.0 GIS BLOCK

17.1 GENERAL SCOPE

A GIS block is required to house the switchgear and associated


equipment, the mechanical and electrical equipment and any other
facilities required for building services.

17.2 DIMENSIONS

The GIS block shall be approximately 14m x 10m to suit the installation
of the equipment. The building design shall take into consideration the
layout of the equipment and to allow enough area for the future
extension also. An open space of 2 meter shall be provided on the peri-
pheri of the equipment in order to allow easy operator movement and
access as well as maintenance.

17.3 BUILDING ENVIRONMENT

The GIS Block shall be slightly pressurized to prevent the ingress of


unfiltered air in addition the building shall be properly sealed to
minimize the flow of outside air into it and vice versa. Openings for
equipment and services shall be weatherproof. Explosion vents shall
be provided. If required.

The building wall and roofs shall be suitably insulated to reduce heat
absorption, Windows shall be shaded or shall be fitted with insulating
or heat reflecting glass, consistent with the design requirements for
ventilation.

33
17.4 BUILDING ARRANGEMENT

The GIS Block arrangement shall satisfy and be fit for the GIS and
associated equipment.

The main floor shall be at a common level through out the building to
facilitate movement.

The main floor shall be above grade and shall be designed and
constructed to ensure that flooding will not occur. No floor below grade
will be accepted.

Convenient routing of cables from the GIS building to control,


protection and other auxiliary building shall be considered.

17.5 CRANES, HOISTS AND SERVICE TRUCKS

Cranes and hoists shall be provided as required for servicing and


maintenance of the equipment components. Hoists shall be installed
permanently in rooms where heavy equipments are located to be used
for later maintenance.

17.6 FLOORING

II) Entire area around the GIS building shall be provided with RCC paving
starting from the building up to 2m clear distance for the full length of
the building and minimum 10m wide strip as approach to the GIS
building from both side shall be paved with RCC.

The above specified RCC paving shall be minimum 100mm thick M20
grade concrete over suitable underbed arrangement as specified for
switch house building.

ii) Cable vaults shall have 50mm thick smooth floor finish with cement
concrete i.e.1:1½:3.

iii) Heavy duty ironite concrete floor hardener shall be provided in GIS
Block as below:-

The topping shall, if possible, be placed on the base slab before the
latter has taken its final set. When this is not possible, the base slab
shall be thoroughly brushed with stiff brooms, wetted for twelve hours
and allowed to dry before the cement concrete floor topping is laid.
Surplus water shall be mopped up and a cement grout brushed well
into the surface immediately before laying the screeded bed to a level
12mm below the finishing level.

The cement floor minimum 50mm shall consist of a mix of one part
cement, one part sand and two parts crushed aggregate 10mm. This
shall be mixed, placed, thoroughly tamped with a grill hammer and
floated and screeded to receive the 12mm thick hard topping. Hard
topping shall be applied while the screeded bed is still wet. This shall
consist of one part of a cement ironate mixture or two parts by bulk of
well graded approved crushed granite of maximum 6/12 mm size. The

34
cement ironite shall consist of well mixed dry mixture containing one
part ironite to four parts cement by weight. Water shall be added after
mixing the aggregate, placing, tamping, floating and trowelling being
done in accordance with manufacturer’s recommendations. Care shall
be taken not to over trowel until the initial set has taken place.

17.7 ROLLING SHUTTERS

Rolling shutters with suitable operating arrangement


(manual/mechanical gear operator or electrical according to size shall
be provided in buildings to facilitate handling and transportation of
equipment. The rolling steel shutter shall be of an approved design and
make and Wicket gates shall be provided where required. The
specification of the rolling shutter is given as below:-

The curtains shall be made of interlocking scrolls made of hot rolled


double-tipped galvanized steel lathe sections of 18 SWG tested mild
steel strips at 75mm rolling centers, locked with galvanized malleable
iron clips. The bottom lathe shall be coupled to a lock plate fabricated
from 3mm thick galvanized steel plate and securely riveted with
stiffening angles. The guides shall be hot rolled mild steel galvanized
channel sections. These shall be embedded securely into concrete or
masonry face of anchored to steel stanchions with necessary lugs in an
approved manner. Latches shall be provided at both ends of the
bottom bolt plate of the curtain and provisions shall be made for locking
from both sides. Where required, wicket doors shall be provided with a
safety lock, tower bolt and handle. The hood covers shall be double
dipped hot galvanized 20 gauge steel adequately reinforced to prevent
sag. All steel parts of the door shall be double dipped hot galvanized.
The shutters shall be given (1) coat of zinc based primer paint before
installation.

18.0 STATUTORY RULES

Vender shall comply with all the applicable statutory rules pertaining to
factory acts, safety rules of Tariff Advisory Committee and Chief
Electrical Inspector.

19.0 DESIGN

a) The buildings shall be designed:

i) to the requirements of the National Building Code of India, and the


standards quoted therein,

ii) for the specified climatic & loading conditions,

iii) to adequately suit the requirements of the equipment and apparatus


contained in the buildings and in all respect to be compatible with the
intended use and occupancy.

iv) with a functional and economical space arrangement.

35
v) for a life expectancy of structure, systems and components not less
than that of the equipment which is contained in the buildings, provided
regular maintenance is carried out.

vi) to be aesthetically pleasing. Different buildings shall show a uniformity


and consistency in architectural design with the surrounding structures.

vii) to allow for easy access to equipment and maintenance of the


equipment.

viii) with, wherever required, fire retarding materials for walls, ceilings and
doors, which would prevent supporting or spreading of fire.

ix) with material preventing dust accumulation.

x) All structural steel inside the GIS hall shall be provided with the suitable
epoxy PO coatings, so as to avoid any maintenance during its life
period.

b) Suitable expansion joints shall be provided in the longitudinal direction


wherever necessary with provision of twin columns.

c) Individual members of the buildings frame shall be designed for the


worst combination of forces such as bending moment, axial force,
shear force, torsion etc.

d) Permissible stresses for different load combinations shall be taken as


per relevant IS Codes.

e) The building lighting shall be designed in accordance with the


requirements of relevant standards for both indoor and outdoors.

f) The building auxiliary services like ventilation system, fire protection


and detection systems and all other miscellaneous services shall be
designed in accordance with the requirements specified elsewhere in
the Specifications.

19.1 Design Loads

Building structures shall be designed for the most critical combinations


of dead loads, superimposed loads, equipment loads, crane loads,
wind loads, seismic loads, short circuit loads and temperature loads. In
addition, loads and forces developed due to differential settlement shall
also be considered.

Dead loads shall include the weight of structures complete with


finishes, fixtures and partitions and should be taken as per IS: 1991

Super-imposed loads in different areas shall include live loads, minor


equipment loads, cable trays, small pipe racks/hangers and erection,
operation and maintenance loads. Equipment loads shall constitute, if
applicable, all load of equipments to be supported on the building
frame.

36
For crane loads an impact factor of 30% and lateral crane survey of
10% of (lifted weight + trolley weight) shall be considered in the
analysis of frame according to provisions of IS: 875. The horizontal
surge shall be 5% of the static wheel load.

The wind loads and seismic forces shall be computed as specified in


Section 2 of this specification. Response spectrum method shall be
used for the seismic analysis using at least first five modes of vibration.

For temperature loading, the total temperature variation shall be


considered as 2/3 of the average maximum annual variation in
temperature. The average maximum annual variation in temperature
for the purpose shall be taken as the difference between the mean of
the daily minimum temperature during the coldest month of the year
and mean of daily maximum temperature during the hottest month of
the year. The structure shall be designed to withstand stressed due to
50% of the total temperature variation.

Wind and Seismic force shall not be considered to act simultaneously.

Floors/slabs shall be designed to carry loads imposed by equipment,


cables, piping, travel of maintenance trucks and equipment and other
loads associated with the building. In general, floors shall be designed
for live loads as per relevant IS and cable and piping loads of no less
than 5kN/sq.m hanging from the underside.

For consideration of loads on structures, IS: 875, “Code of practice for


structural safety of buildings” shall be followed. The following minimum
superimposed lie loads shall, however, be considered for the design.

a. Roof 150kg/m2 for accessible roofs 75kg/m2 for non-accessible roofs.

b. RCC floors 500 kg/m1 for offices and minimum 1000 kg/m2 for
equipment floors or actual requirement, if higher than 1000 kg/m2
based on equipment component weight and layout plans.

c. Stairs & balconies 500kg/ m2

d. Toilet Rooms 200kg/m2

e. Walkways 300kg/ m2

19.2 Submissions

The following information shall be submitted for review and approval of


HVPNL:-

i) Design criteria for structural steel and reinforced concrete design. The
criteria shall compose the codes and standards used, applicable
climatic data including wind loads, earthquake factors and maximum
and minimum temperatures applicable to the building locations,
assumptions of dead and live loads, including equipment loads impact
factors, safety factors and other relevant information.

37
ii) Structural design calculation and drawing (including
construction/fabrication) for all reinforced concrete and structural steel
structures.

iii) Architectural drawing showing floor plans, cross sections, longitudinal


sections and elevation of each building. The architectural drawings
shall be developed in ambience with adjacent buildings as per the
requirement.

iv) A detailed schedule of building finishes including color schemes.

v) A door and window schedule showing door types and locations, door
lock sets and lath sets and other door hardware.

The architectural drawings/building plans shall be got approved


from the owner before starting the work.

19.3 List of IS Codes and Standards

A brief list of applicable standards and codes to be used in the design


are indicated below the latest addition of the codes along with
amendments will only be referred to. The list is not exhaustive and any
other relevant code/standards may also be used in the design as per
the requirement.

IS: 456 (2000) Code of practice for plain and reinforcement


concrete.
IS: 783 Code of practice for laying of concrete pipes.
IS: 800 Code of practice or general construct ion of steel.
IS: 816 Code of practice for use of metal arc welding for
general construction in mild steel.
IS: 1893 Code of practice for criteria for earthquake
resistant design of structures.
IS: 2212 Code of practice for design and construction of
shallow foundations on soil.
IS: 2911 Code of practice for design and construction of pile
foundations (Relevant Part).
IS: 2950 Code of practice for design and construction of raft
foundation.
IS: 4326 Code of practice for earthquake resistant design
and construction of buildings.
IS: 5525 Recommendations for detailing of reinforcement in
reinforced concrete work.
IS: 6403 Code of practice for determination of bearing
capacity of shallow foundations.
IS: 10262 Recommended guidelines for concrete mix design.
IS: 13920 Ductile detailing of RCC structures subjected to
seismic forces.
SP:16 Design aid to the code for reinforced concrete to
IS: 456 – 1978.
SP: 23 Handbook of concrete mixes.
SP: 34 Handbook on concrete reinforcement and
detailing.

38
It is suggested that the Bidder may include all above information in his
bid itself so that Owner may comment if any change is warranted as
per their practice or otherwise.

20 RE-CARPETING OF BITUMINOUS ROAD

20.1 The existing bituminous road shall be repaired and re-carpeted after
filling the pot holes as per the HVPNL drawing

20.2 Finished top (crest) of roads shall be as per tender drawings & levels
shall match with the existing switchyard road.

20.3 Road construction shall be as per IRC standards. The Bitumen shall
conform to Grade 80/100.

20.4 Adequate provision shall be made for road drainage

21.0 FIELD QUALITY CONTROL PLAN

The Bidder shall submit the field quality control plan for effective control
on quality of civil works for approval from HVPNL before the start of
work. All cost of testing as per approved field Quality control plan or as
directed by HVPNL shall be borne by the Bidder.

22.0 After completion of civil works, a completion plan giving all details of
foundations, trenches, culverts, fencing budding etc. as built shall be
submitted with original tracing.

23.0 Any material or activity not covered under the specifications or drawings
shall be, as governed by relevant IS specification/National Building
Code of India.

24.0 GENERAL

The work shall be carried out by specialists in the trade. Workers shall
be provided with gum boots and hand gloves. Minimum overlaps of
100mm shall be given at the ends and sides of the strips of the
felts/tissue and properly bonded with bitumen. Joints in the successive
layers of the fibre glass based felt/tissue shall be staggered. There
shall be no air pockets. Corners shall be treated flush without any air
pockets or voids.

a. The materials and the sub-Bidders executing the work shall be duly
approved by the HVPN.

b. Adequate covering shall be provided during work to avoid splashing or


staining of adjacent works and surfaces. Any surface or work splashed
or stained shall be thoroughly cleaned to the full satisfaction of the
HVPN.

25.0 SPECIAL NOTE

Fully galvanized angles, flat, nut & bolts etc. shall be used in all the
items covered under this scheme. Galvanizing of the steel section shall

39
confirm to IS 2629-1985 and IS 4759-1968. All galvanizing members
shall withstand test as per IS 2633-1986. The galvanizing shall be done
after all fabrication work is completed, except that the nuts may be
tapped or re-run after galvanizing. Threads of the bolts and nuts shall
have a neat fit and shall be such that they can be turned with finger
throughout the length of the threads of bolts and they shall be capable
of developing full strength of the bolts.

40
SECTION-10
CHAPTER-1

TECHNICAL SPECIFICATIONS FOR PLCC EQUIPMENTS

1. GENERAL:
The manufacturer whose PLCC panels are offered should have designed,
manufactured, tested, supplied and commissioned PLCC panels for the specified
voltage and fault level.

2. STANDARD:

2.1 All the PLCC equipment covered under the package shall conform to the requirements
of the latest addition of the relevant IEC/IS Specification or equivalent National
Standards, except to the extent mentioned by this specification.
2.2 The works covered by the specification shall be designed, engineered, manufactured,
built tested and commissioned in accordance with the Acts, Rules, Laws and
Regulations of India.
2.3 The equipment to be furnished under this specification shall conform to latest issue with
all amendments of standard specified above.
2.4 In addition to meeting this specific requirement called for in the Technical Specification,
the equipment shall also conform to the general requirement of the relevant standards
and shall form an integral part of specification.
2.5 The Bidder shall nor that standards mentioned in the specification are not mutually
exclusive or complete in themselves but intended to compliment each other.
2.6 The Bidder shall note that list of standards presented in this specification is not
complete. Whenever necessary the list of standards shall be considered in conjunction
with specific IS/IEC.
2.7 When the specific requirements stipulated in the specification exceed or differ than
required by applicable standards, the stipulation of the specification shall take
precedence.
2.8 Other internationally accepted standards which ensure equivalent or better performance
than that specified in the standard referred shall also be accepted.
2.9 In case governing standards for the equipment is different from IS or IEC, the salient
points of difference shall be clearly brought out alongwith English language version of
standard or relevant extract of the same. The equipment conforming to standards other
than IS/IEC shall be subject to HVPNL’s approval.
2.10 The bidder shall clearly indicates in his bid the specific standards in accordance with
which the works will be conformed.

3. TRAINING:
As per clause 12 of section I General.

3.1 LOCATION OF EQUIPMENT:


The PLCC equipments as specified shall be installed at the respective ends of the
transmission lines.

4. FREQUENCY PLANNING:

4.1 For planning frequency and output power of carrier terminals, bidders may plan for a
minimum receive signal to noise ratio of 25dB for the speech channels without
compander and 15dB for protection signalling & 29dB for data transmission. The details
of line, tower, conductor shall be furnished to the Bidder to carry out the assessment of
signal attenuation. IEC/CIGRE specifications/guidelines shall be adhered to.
4.2 Frequency and output power of PLC terminals for protection shall be planned such that
the protection signal is received with full reliability even when one of the phase is

-1-
earthed or is on open circuit on the line side causing an additional minimum loss of
6dB.
4.3 Successful Bidder shall be fully responsible for the co-ordination required with
concerned State Electricity Board for finalising the frequency plan.
4.4 The frequency plan will be referred to wireless Advisor/DOT Department for clearance
and in case any change in the Bidder’s recommended carrier frequency and power
output is proposed by these authorities, the Bidder shall have to modify his proposal
accordingly. Change of power output shall however not involve repeater station.

5. PROPOSED ARRANGEMENT:

5.1 The power line carrier communication equipment required by the HVPNL is to provide
primarily efficient, secure and reliable information link for carrier aided distance
protection and direct tripping of remote and breaker and also for speech communication
between sub-station. It shall include separate carrier terminals of multipurpose type for
speech and protection purposes. Provision for super-imposing telex and data signals
shall be made on speech terminals. All carrier terminals including those for protection
shall be suitable for point to point speech communication also. Carrier aided protection
is not being provided on 132kV and below transmission lines in HVPNL.
5.2 For security reasons each transmission line shall be protected by Main-I and Main-ii
protections or Main & Backup protections. The features of Direct Trip Send and Direct
Trip Receive shall also be provided in the protection coupler.
5.3 The requirement of carrier information on each link covered under this specification is
for speech communication and protection signaling.
5.4 The equipment for protection signals shall have high degree of reliability and speed. It
shall be guaranteed to function reliably in the presence of noise impulse caused by
isolator or breaker operation. It shall also be possible to effect direct tripping of breaker
at one end when the other end breaker opens out either manually or by relays such as
Bus fault relay etc.
5.5 The time intervals between receipt of a trip command on the transmit side, its
transmission over the carrier link, reception at the far end and giving command to the
trip relays at the distant end shall not exceed 20 m.sec. for permissive inter-tripping and
30m.sec. for direct inter-tripping even for the longest line section. The above timings are
Inclusive of operating time for auxiliary relays and interposing relays, if any, included in
the PLCC equipment.
5.6 The requirement of protection signaling channel is such that security against incorrect
signals being received shall be atleast two to three orders higher than reliability against
a signal not being received.
5.7 The planning of frequencies for the PLCC terminals shall be done confederating the
existing PLCC network as well as full communication channel requirement detailed
above so that there is no problem of frequency allocation at a later date when the
subsequent section communication requirements come up.
5.8 For reasons of security and reliability, phase to phase coupling for S/C lines and inter-
circuit coupling for D/Clines shall be employed.
5.9 The parameters of the equipment quoted shall be such that the mode of wave
propagation on transmission line shall not impose any limitation on the efficient and
reliable performance of information link from protection or communication point of view.
5.10 The Bidder shall submit curves illustrating ‘incorrect tripping’ and ‘Failure to trip’
probability plotted against corona noise level in the presence of impulse noise due to
switching of isolator and circuit breaker etc. Detail of Field tests and laboratory tests for
successful operation of his equipment, under such adverse conditions shall be
furnished by the bidder. These are to be related to end-to-end signaling and shall take
into account the type of communication link.

-2-
6. POWER LINE CARRIER TERMINAL:

6.1 The offered PLCC equipment should be suitable for carrier transmission in high
frequency of Speech, Facsimile, Telegraphy, RTU data, Teleprotection signals in
frequency range of 40KHz to 500KHz over high voltage overhead power transmission
lines.
The system should have one/two speech channels each of which can be set for
full bandwidth speech cum fax conversations or shared speech cum superimposed date
channels or suitable for high sped 4 wire RTU data channel of 1200/2400 bits per
second. The superimposed data channel can support upto 600 baud (2760-3720 Hz,
960 Hz BW or 2280-3360 Hz, 1080 Hz BW) channel as a backup for RTU/SCADA.

The system should be fully field programmable and flexible easy to use and
compact leading to simplified network design, installation and maintenance work.
The system can provide up to 12/6Nos. of 50 baud, 8/4 Nos. of 100 baud or 1
Nos. of 600 baud voice band data for superimposed channels and speech up to 2
KHz/2.4KHz in VF circuits simply by changing plugin filters provided in channels
modem. Optionally system can be provided to give speech and data only channels
(upto 28/13/9 Nos. of 50/100/200 baud or 1 Nos. of 1200/2400 bps ) or Interface for
protection coupler signal.
As already indicated the information link shall be provided for speech,
protection, telex and data services. PLC terminals shall be fully co-ordinated to match
with the specific requirements. Because of strict requirement of high speed of operation,
security, reliability and efficient operation of protection channel along with the carrier
terminals, Bidder shall ensure the complete and fool-proof co-ordination of the PLC and
protection equipments. It shall therefore be necessity to have these combinations as
one unit without any mismatch or necessary of any intermediate co-ordination unit.
6.2 PLC terminal shall use Amplitude Modulation and shall have single side band
transmission mode. These shall be equipped for fixed frequency duplex working and
shall be fully transistorised, however, this fixed frequency shall be programmable at
site.
Characteristic input and output parameters of the SSB PLC terminals shall be as per
IEC-495, unless otherwise specified.
6.3 The features of carrier terminal are detailed out below:
a) Mode of transmission single side band with Amplitude Modulation
suppressed carrier or reduced carrier.

b) Carrier frequency range 40 to 500KHz

c) Nominal carrier frequency band in either direction of 4.0KHz


transmission

d) Power output (PEP) of HF terminals 20 watt

e) Frequency difference between a pair of PLC Frequency difference between


terminals VF signal at the transmitting and
receiving ends will not exceed 2
Hz with suppressed carrier. With
reduced carrier frequency
difference shall be zero. This
shall include permissible ambient
temperature variation and supply
frequency and voltage variation
of (+) 15 % and (-)10%

-3-
f) Automatic gain control For 40dB change in carrier
frequency signal level within the
regulation range, change in VF
receive levels of both speech and
other signals shall be less than
1dB.

g) Supply voltage 48V DC+15%-10% (Positive pole


earthed).
h) Nominal impedance
-Carrier freq. Sides 150ohm balanced
-VF sides 600ohm
i) Return loss within nominal freq. Band: -Not less than 10dB on Carrier
freq. Transmit side.
-Not less than 14dB on VF side.

j) Spurious emission at edge of nominal carrier freq. -10dBm(Max)


Band.
k) Speech level across 600ohms.
-Four wire transmit 0dBr to –17dBr
-Four wire receive 8 dBr to -3.5 dBr
-2 wire transmit 0dBr
-2 wire receive -7dBr
l) Permissible limits for variation of overall loss As per IEC 495/IS 9482
(attenuation) of the speech channel in relation to
800Hz for back to back operation of a pair of
terminals without compander.
m) Voltage withstand requirement D/C Power terminal.
When isolated from earth
Capable of with standing 500V
DC for 1 minute between both
terminals connected together and
earth.

When not isolated form earth. An impulse voltage of 1000v


1.2/50 applied between.

VF signaling and alarm circuit when free from earth. 500V DC applied for 1 minute
between both terminals of circuit
connected together and earth.

6.4 Following facilities to be provided in the PLC terminals:


1) Loop test facility for local transmitted and receiver.
2) Changeover provision of termination of PLC terminals on dummy load.
3) Position of each module may be marked at the back side of chassis also.
4) Terminal blocks for power supply, telephone cable and two HF cable sockets.
5) Channel testing from terminal to terminal.
6.5 All the PLC terminals shall be of multipurpose type. The bidder shall confirm that the
total transmission time for tele protection shall not exceed 20ms for permissive and
30ms for direct tripping signals.
6.6 In the input circuit of PLC terminal protective devices shall be provided in the form of
zener diodes or surge suppressors in order to eliminate an surge transfer through the
coupling device or the surge induced in the connecting path of HF cable.

-4-
6.7 To improve voice transmission characteristics for the system, companders and
expanders shall be provided. The companders shall have atleast 2:1 compression ratio
with a corresponding expansion ratio of 1:2. The operating range of compander shall be
compel with the audio power levels specified for 4 wire operation. The improvement
gained by companders shall however, not be taken into account for power allocation
and shall be in-hand reserve.
6.8 Sudden changes in input level to the receiver shall not cause false tripping. The bidder
shall clearly indication in his offer the methods adopted to ensure above phenomenon.
The receiver design shall also provide protection against false tripping from random
noise.
6.9 Fail-safe devices shall be provided, so that a malfunction in one unit or sub-assembly
cannot cause damage elsewhere in the system. All plug-in equipment shall be fitted
with features to prevent improper insertion. The electrical cables shall not be routed
across sharp edges or near sources of high temperature. The adjustments, which are
susceptible to misadjustment for accidental contact/vibration, shall be equipped with
suitable locking devices.
6.10 The PLC set shall be designed to give guaranteed performance from 0 deg. C to 50deg.
C ambient temperature. The thermal capability of the equipment shall be so designed
that the equipment remains operational successful upto 60deg. C ambient temperature.
Any ventilation fans provided for circulation of air inside the cabinets shall conform to
relevant Indian Standards.
6.11 The terminals shall be provided with built-in indicating Instrument to facilitate checking
of important voltages and current values and signal levels in different parts of the PLC
terminals. Protection fuses shall be provided in all important circuits and fuses shall be
so mounted as allow their easy inspection and replacement. All test points shall be
easily accessible.
The carrier set shall be provided with suitable supervision and alarm facilities Individual
parts of the carrier set should be accessible from front, making it possible to place the
carrier cabinets side-by-side. All components and parts of the carrier sets shall be
suitably tropicalised.
6.12 PLC terminals shall be housed in floor mounting sheet metal cabinets, suitable for
mounting on concrete plinth as well as channel frame by means of nuts and bolts or
welding. The cabinets shall be properly cleaned and spray painted with two coats or
synthetic enamel paint. Exterior of the cabinets shall be painted with smoke-glossy
finish. Interior of the cabinets shall be painted with white enamel paint with glossy finish.
All the panels shall be provided with suitable point for earthling with the earth of the
Grid/S/Stn.. Detailed drawings for earthing connections shall be submitted.
6.13 All cabinets having PLC terminals shall be provided with lamps of sufficient wattage for
interior illumination with switch.
6.14 A name plate shall be provided on the front door of each cabinet indicating channel
function, transmitter frequency and direction etc.
6.15 Bidder shall submit type test & routine test certificate from internationally reputed test
authorities for the quoted PLC terminals in respect of characteristic input and output
parameters of the PLC terminals in accordance with IEC-495 alongwith the Bid.

6.15.1 TYPE TESTS:


The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed
by HVPN or another electric power utility and be submitted by the successful bidder to
HVPNL for approval as schedule given in Bar Chart.

-5-
I Carrier frequency side
Nominal impedance, return loss and tapping loss
Balance of ground
Spurious omissions
carrier frequency levels
frequency accuracy
Voice Frequency Side
Automatic gain control
Transmit/receive frequency difference
Noise generated, within the termianls
Harmonic distortion
Selectivity
Nominal impedance and return loss
Balance of ground
Telephone signalling channel
Voltage withstand requirements
Electromagnetic compatibility
II Standard Equipment
Attenuation distortion
Group delay distortion
Signals above 3400 Hz
III Speech Plus Equipment
Attenuation distortion
Group delay distortion
IV Multichannel Terminals
Carrier frequency output power
Nominal impedance, return loss
Spurious omissions
Inter channel cross talk attenuation
V Common Requirements
AC Power Supply
DC Power Supply
Temperature and humidity
VI Storage Conditions
Subject to agreement between the manufacturer and the user

Routine Test:
As per quality assurance program (QAP).

ACCEPTANCE TESTS:
The following acceptance tests shall be carried out by the Supplier in presence of
HVPNL representative, unless dispensed with in writing by the HVPNL.

i) Carrier frequency levels


ii) Frequency accuracy

-6-
ii) Automatic gain control
iv) Transmit/receive frequency difference
v) Voltage withstand requirements
vi) Attenuation distortion
vii) Attenuation distortion
viii) Carrier frequency output power

7. SPEECH COMMUNICATION:

PLC equipments offered shall provide telephone communication between the


stations where the transmission line equipment shall be suitable for providing
the following:

a) It shall be possible for subscriber at any of the stations to contact the


subscriber at all other stations connected in the system by dialing his call
number. To achieve this a 24 lines EPAX with 4 wire interface & remote
subscriber units shall be provide/available at different stations.

b) The equipment shall contain all normal facilities like ring back tone, dial tone,
engage tone & priority tone and suitable pluses to established and disconnect
communication between subscribers.

c) The equipment shall be provided with necessary alarm circuits and fuses etc.

d) The equipment shall be of 4 kHz bandwidth on either direction for providing


super imposed data and be suitable for teleprinter facilities at a later date
without major modifications and high cost. The Bidder shall clearly indicate in
his bid the provision made in his proposal for future development and the
extent to which such additional facilities can be asked at a later date.

e) Arrangement for over-riding facilities shall be provided by means of priority


keys wherever specified. The over-riding facility shall enable cutting in ongoing
calls with the priority key and ask the concerned parties to finish their
conversation. The wanted number should then get automatically connected
without having to redial the number.

f) All the carrier telephone conversations shall be secret and it should not be
possible for anybody to over hear the conversation going on between any two
parties except those provided with over-riding facilities.

g) All the relays etc, used in the equipment shall be of roubust design to cope with
the duty imposed on them. Electronic components used in the equipment shall
be of long life type and as far as possible a few types only shall be used.

h) The cabinets housing the equipment for EPAX, four wire E/M interface &
remote subscriber units (four wire) shall have mounting arrangement similar to
that for PLC terminals and these cabinets shall also be painted with the same
paint similar to that of PLC terminals.

i) All the terminals for speech shall be supplied fully wired for addition of VFTs in
future. However, the terminal supplied shall be equipped with programmable
transit band pass filters.

-7-
j) Equipment for speech communication must be fully compatible with HVPNL’s
existing equipment. Any Interfaces required for proper matching and
connection with the HVPNL’s existing equipment shall be provided by the
Bidder.

k) Terminals for protection shall be suitable between two ends of each


transmission line or on tandem operation basis with back to back connection at
the intermediates stations.

l) Each PLC terminal for speech as well as protection purposes shall be provided
with a plug-in type service telephone and buzzer. Further, 4 wire remote
telephone instruments (parallel to service telephone) shall also be provided on
one PLC terminals for protection for each link. These instruments shall be
located in respective switchyard control room to enable the operator to make
emergency calls on point-to-point basis. Each such instrument shall be
equipped, with a buzzer and ‘press-to-call’ key and shall not require any
additional power supply units.

8. NETWORK PROTECTION EQUIPMENT (PROTECTION COUPLER) :

8.1 The bidder shall offer voice frequency transmission equipment which shall work
on frequency shift or coded signal principle for transmission/reception of
protection signals as single purpose channel. The equipment shall be suitable
for connection to the power line carrier terminal mentioned above.

8.2 The voice frequency transmission equipment shall not only be insensitive to corona
noise but shall also remain unaffected by impulse type noise which are generated by
electrical discharge and by the opening and closing of circuit breakers, isolators,
earthing switches etc. The equipment shall be made immune to a field strength of
10V/m expected to be caused by portable radio transmitters in the range of 20-1000
MHz . In his offer, the bidder shall clearly explain as to what measures have been
taken to make the equipment insensitive to corona noise, white noise and to impulse
noise of an amplitude larger than the wanted signal and submit full field test and
laboratory test reports. The guarantee on design data shall not be acceptable.

8.3 The equipment shall be unaffected by spurious tripping signals. The bidder shall
submit proof as to how this is achieved satisfactorily.

8.4 The equipment shall be suitable for transmission of direct and permissive trip signal as
well as blocking signals for protective gear of power system. The equipment shall be
operated in the audio frequency range in speech band or above speech band as
superimposed channel in 4KHz band of SSR carrier. The equipment shall operate with
full duplex frequency shift mode of operation. The protection signaling equipment shall
be solid state design, modular in construction and have a proven operating record in
similar application ever EHV systems. Details regarding application of the equipment
over 220kV systems shall be submitted along with the bid Each protection signaling
equipment shall provide:

i) Transmission facilities for minimum tow protection signals.

ii) Reception facilities for minimum two protection signals.

iii) Direct trip Send and Direct Trip Receive facility in addition to above two protection
signals.

8.5 The equipment shall be designed for remote tripping/blocking on permissive basis and
direct tripping for reactor fault and others. The overall time of PLC.VFT and

-8-
transmission path for permissive trip/blocking shall be 20m. sec. or less and for direct
tripping 30m.sec. or less even for the longest line section.

Operating time lower than specified above may be preferred provided they fulfil the
requirements of security and reliability as mentioned below:
False-trip probability >10-5
(Noise burst of nay amplitude)

Fall to trip probability >10-5


For S/N dB In 3.1 KHz Band
(while Noise Measurement)

8.6 It may be emphasised that specified time, as mentioned above is composed of the
following:

a) Back-to-Back signal delay in frequency shift or coded signals protection equipment.

b) Back-to-Back delay in PLC terminal.

c) Delay in transmission line.

d) Operation time of interposting relay, if any in frequency shift or coding equipment.

Reference is invited in this regard to the guide lines expressed in CIGRE Publication
“Teleprotection” report by Committee 34-35.

8.7 The following transfer criteria shall be provided by the equipments:

a) Transmit side:

One number potential free No (normally open) contact of protective relays (to be
supplied by the HVPNL) of under noted rating of each of the following functions:

i) Permissive trip command

ii) Direct trip command

Contact rating.

Maximum voltage :360volts.

Maximum current rating :5amps.

Maximum power rating :1200 w/va.

b) Receive side:

Voice frequency transmission equipment for network protection shall be provided with
one potential free No (normally open) contact of the under noted rating of each of the
following functions:

i) Permissive trip command

ii) Direct trip command

Contact rating.

-9-
Rated voltage :250volts DC

Rated current :0.1ADC.

Other Parameters :as per IEC-255-0-20

c) Alarm:

In addition, the voice frequency protection terminal shall provide at least one number
potential free change over contact of the following rating for alarm purposes.

Rated voltage :250volts DC

Rated current :0.1ADC.

Other Parameters :as per IEC-255-0-20

8.8 Frequency shift of coded signal protection equipment shall have atleast two channels.
In order to ensure full availability of PLC protections channel, arrangement of parallel
circuiting of these tow channels as main and stand by channels shall be made. This
arrangement is generally shown in relevant specification drawing. Each arrangement
shall be developed by the successful Bidder in co-ordination with protective relay
Bidder. The parallel wiring should however retain the concept of two protection
channels of each type of protection with each backing up the other 100% during
normal operation and also permit testing without affecting the other. The Bidder shall
submit drawings showing Inter-connection between PLCC and protection panels for
approval by the HVPNL.

8.9 It has to be ensured that under no circumstances protection channel should share the
power. Each protection channel shall be able to transmit power for which system is
designed. For example, a 20 W PLC terminal shall transmit 20 Watt (Max.) for
protection channel alone in the event of fault. Speech and superimposed data
channels, in the same protection terminal must get disconnected momentarily during
the operation of protection channels.

8.10 The equipment shall be constructed such that in permissive line protection system,
operational reliability of the protection channel may be checked over the carrier link by
means of a loop test. It shall be possible to carry out the above test from either end of
the carrier link. During healthy condition of the transmission line, the loop test shall not
initiate a tripping command. In the event of a system fault, while loop test is in
progress, protection signal shall over-ride the test signal.

8.11 The equipment shall be complete with built in counters for counting the number of trip
commands sent and number of trip commands received.

8.12 Bidder shall develop drawings showing inter-connection between protection panels
and PLCC panels and submit the drawings for HVPNL’s approval.

8.13 The voice frequency transmission equipment shall be suitable for 48V (+) 15% and
(-)10% DC power supply.
9. DOCUMENTATION

The successful bidder shall submit four sets of following drawings for HVPNL
approval:-

- 10 -
1. Outline general arrangement

2. Name and rating plate

3. Face plan

4. Wiring Diagram

5. Terminal connectors

6. Block Diagram

7. Terminal plan

8. Any other drawing required to complete the equipment like bird barrier etc.

NOTE: All above drawings should be a minimum space (14x10cm) for stamping the
approval of drawings by HVPNL.

10. ELECTRONIC PRIVATE AUTOMATIC EXCHANGE (EPAX)

10.1 The Electronic private Automatic Exchange (EPAX) wherever specified shall be
provided with 24 subscriber lines and 8 trunk lines. The trunk lines shall be connected
to PLCC channel (speech panels as existing in HVPNL i.e. WSI, BPL, ABB make). The
exchange will have its own ringing current and tone generator etc. The exchange shall
be suitable for working on 48 VDC Power supply (Positive pole state & of modular
construction and shall have multiple switching lines (minimum 4 routes). It shall be
programmable, either to debar or provide over-riding facility to certain subscribers.

10.2 EPAX shall also be provided with two(2) additional interface units and operate
exclusively with HVPNL’s leased subscriber lines of Department of
Telecommunication (DOT) and compatible with 2 wires full duplex, voice grade mode
of operation. The DOT leased lines shall be coordinated by the HVPNL with the
leasing authority (DOT).

10.3 The technology of the equipment supplied by the Bidder must conform to C-DOT
version.

11. TELEPHONE SET:

The instrument should be sturdy & compact in form. It should have Tone/Pulse facility,
flash and pause facility, last number redialing, visual ringing indication, ring volume
control and fast dialing facility. It should be compatible with different types of switching
units used in conjunction with PLCC system in HVPNL and also with the DOT line. It
should be able to be feed from exchange with F 48 V, 2x200 ohm feed bridge or 56 V
2x400 ohms feed bridge.

- 11 -
SECTION-10
CHAPTER-2

TECHNICAL SPECIFICATIONS FOR LINE TRAPS

1. LINE TRAP:

1.1 General:

The manufacturer whose line trap are offered should have designed, manufactured and
tested as per IS/IEC or equivalent standard and supplied the line traps for the specified
voltage and fault level.
All the equipment covered under the package shall conform to the requirements of the
latest edition of the relevant IEC/IS specifications or equivalent National Standards,
except to the extent modified by this specification and shall also be in accordance with
requirements under section I & II.

1.2 Location of equipment:

The line traps as specified shall be installed at the respective ends of the transmission
lines.

1.3 Line trap requirements:

Line traps shall be inserted into Extra-high voltage transmission line to prevent undue
loss of carrier signal for all power system conditions. Its impedance shall be negligible at
power frequency (50Hz) so as not to disturb power transmission but shall be relatively
high over the frequency band appropriate to carrier transmission.

Line trap shall consist of a main coil designed to carry continuously the rated current
without exceeding the limit of temperature rise. It shall be supplemented with a protective
device and tuning device.

Line trap shall be broad band tuned for its entire carrier frequency range form 50 to
500KHz. Resistive component of impedance of the line trap within its carrier frequency
blocking range shall not be less than 570 ohms.

Line trap shall be provided with a protective device in the form of surge arrestors which
shall be designed and arranged such that neither significant alteration in its protective
function nor physical damage shall result from either temperature rise or the magnetic
field of the main coil at continuous rated current or rated short time current. The
protective device shall neither enter into operation nor remain in operation, following
transient actuation by the power frequency voltage developed across the line trap by the
rated short time current. The protective device shall be shunt connected to the main coil
and tuning device.

The lightning arrestor shall be station class current limiting active gap type. Its rated
discharge current shall be 10KA.

The lightning arrestor provided with the line trap of each rating shall fully comply with the
requirements of IEC-99-4. It shall conform to type tests as applicable and type test
certificate for the same shall the submitted by the bidder.

The lightning arrestor provided with the line trap shall be subject to the routine and
acceptance tests as per IEC-99-4.

-1-
Line trap shall be equipped with the bird barriers.

Line trap shall conform to IEC-353 (latest) fulfilling the all technical requirements as
follows:

Technical Parameter 220kV 66kV


line line

Rated power frequency 50 Hz 50 Hz

Rated system voltage 220kV 66kV

Highest system voltage 245kV 72.5kV

Rated continuous, current at 50 degree 1250A 400A


C ambient.

Rated short time current for 1 second 31.5KA 10KA


Type of tuning ---------- Broad band ---------
Rated blocking band-width to be indicated by bidder

Minimum resistive component of impedance --------- 570 Ohms ---------


within the rated blocking band-width

Rated inductance of main coil (mH) 1.0 1.0

Radio interference voltage Not more than 500 micro volt at 187 kV (rms)

The Bidder shall indicate continuous current rating of the line trap at 65 deg. C ambient.

The line trap shall conform in type tests and shall be subjected to routine tests as per
IEC-353, as per following details:

TYPE TEST:
The equipment should be offered type test. Test reports should not more then seven
years old reckoned from date of bid opening in respect of all the tests carried out in
accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed
by HVPN or another electric power utility and be submitted by the successful bidder to
HVPNL for approval as schedule given in Bar Chart.
i) Short time current test.
ii) Power frequency voltage test on tuning device.
iii) Impulse voltage test.
iv) Temperature rise test
v) Measurement of radio influence voltage
vi) Measurement of the rated inductance of the main coil
vii) Measurement of power frequency inductance of the mail coil
viii) Measurement of blocking resistance and blocking impedance
ix) Measurement of tapping loss and tapping loss based on the blocking resistance
x) Measurement of loss at power frequency.

-2-
Routine Test:
As per quality assurance program (QAP).

ACCEPTANCE TESTS:
The following acceptance tests as stipulated in the relevant IS-8793: 1995 shall be carried
out by the Supplier in presence of HVPNL representative, unless dispensed with in writing
by the HVPNL.

i) Power frequency voltage test on tuning device.


ii) Measurement of the rated inductance of the main coil
iii) Measurement of blocking resistance and blocking impedance
iv) Measurement of tapping loss and tapping loss based on the blocking resistance

1.4 LINE TRAP MOUNTING:

The line trap shall be suitable for outdoor suspension mounting and shall be
mechanically strong enough to withstand the stresses due to maximum wind pressure of
260kg/Square meter.

Bidder shall be required to co-ordinate the mounting arrangement with the existing
arrangement at different sub-stations. Non-magnetic suspension hook/link of adequate
length and tensile strength to provide necessary magnetic clearance between the line
trap and suspension hardware shall be supplied by the Bidder.

The line trap shall be supplied compete with disc insulators and hardware fittings. The
disc insulators to be supplied with the line trap shall conform to IS: 731/1971 with latest
amendments. All hardware fittings associated with these insulators shall conform to IS:
2486 (Part-I)/1971 (1st Revision), IS: 2486 (Part-II)/1971 (1st Revision), IS:2486 (Part-
III)/1974 and IS:2486 (Part-IV)/1981 with latest amendments & revision. Copies of test
certificates of type tests and routine tests as stipulated in the above quoted ISS shall be
furnished with tender.

1.5 LINE TRAP TERMINAL CONNECTORS:

The line traps shall be suitable for connecting to ACSR single/twin bundle Zebra
conductor as per layout requirements. Necessary connector shall be supplied by the
Bidder.

Terminal connectors shall conform to IS: 5561 and shall also comply with requirements
indicated in Section GTR.

Terminal connectors shall be suitable for either horizontal or vertical take off the
conductor.

Clamps/connectors shall be designed for the same current ratings as line trap and
temperature rise shall not exceed 0.5 deg.C over 50 deg C ambient.
1.6 DOCUMENTATION

The successful bidder shall submit four sets of following drawings for HVPNL approval:-

1. Outline general arrangement

2. Name and rating plate

-3-
3. line trap mounting arrangement

4. terminal connectors

5. Any other drawing required to complete the equipment like bird barrier etc.

NOTE: All above drawings should be a minimum space (14x10cm) for


stamping the approval of drawings by HVPNL.

-4-
SECTION-10
CHAPTER-3

TECHNICAL SPECIFICATION FOR COUPLING DEVICE

1. COUPLING DEVICE:

1.1 The coupling devices shall be interposed between the capacitor voltage
transformer/coupling capacitor and coaxial line to the PLC transmitter/receiver and in
conjunction with the capacitor voltage transformer/coupling capacitor shall ensure:

a) Efficient transmission of carrier frequency signals between the carrier frequency connection
and the power line.
b) Safety of personnel and protection of the low voltage parts and installation, against the
effects of power frequency voltage and transient over voltage.

The coupling device, in conjunction with the CVT/CC shall form and electric filter of band
pass type.

a) It shall match characteristic impedance of HT line to impedance of the carrier frequency


connection. Impedance matching between power line and the carrier frequency connection
may be done by a transformer or an auto-transformer.
b) Galvanic isolation between primary and secondary terminals of the coupling device shall be
performed by the above mentioned transformer.
c) Power frequency currents derived by the CVT may be drained to the earth by a separate
inductance termed drain coil of suitable rating or through primary of the above transformer.
d) Voltage surges coming from the power line at the terminals of the coupling device shall be
limited by a non-linear surge arrester of suitable rating in the primary side. Requirement of
a gas type voltage arrester in secondary side of the coupling device shall have to be fully
justified.

The surges Arrester shall have power frequency spark over voltage co-ordinated with the
equipment ahead of it.

e) For direct and efficient earthing of its primary terminals, the coupling device shall be
equipped with an earthing switch. The coupling device shall be designed such that it shall
not be possible to remove the cover before the earthing switch is operated to the ‘earthed’
position. Further the Earth Switch shall be available for earthing of CVT-HT terminals,
when the coupling filter units are removed from circuit for maintenance/replacement. The
design shall take due regard of requirements for safety in accordance with the Indian
Electricity Rules.

1.2 Two numbers ‘phase to earth’ type coupling filters shall be used to achieve in secure
‘phase to phase’ / ‘Inter-circuit coupling’. Connection between secondaries of the two
phases to earth type coupling device shall be through a balancing transformer/hybrid such
that reliable communication shall be ensured even when one of the coupled phase to
earthed or open circuited on the line side.

Coupling device shall conform to IEC-481/IS-8997 and IS-8998 shall have the following
carrier frequency characteristics as applicable to a phase to earth type coupling device.
a) Nominal line side 400 ohms for 220kV line Ph-E &
impedance 600 ohms for Ph-Ph

-1-
b) Nominal line 150 ohms (balanced)
side impedance

c) Composite loss Not more than 2 dB

d) Return loss Not less than 12 dB

e) Band width shall suit the frequency plan between 40


and 500 KHz

f) Nominal peak envelope Not less than 650 Watt.


Power (for inter-modulation product 80 dB down)

The coupling device shall be suitable for outdoor mounting. Temperature of metallic
equipment mounted out door is expected to rise upto 65o C during the maximum ambient
temperature of 50o C specified. The equipment offered by the Bidder shall operate
satisfactorily under these conditions.

The elements of coupling device shall be fitted on a base plate and enclosed in a metal
box.

The HT Terminal of coupling device shall be connected to HF terminal of the CVT by


means of 6mm Sq. copper wire with suitable lugs & taped with 11kV insulation by the
Bidder.

Coupling device shall have at least two terminals for carrier equipment connection. Bidder
shall confirm that such a parallel connection to coupling device directly will not result in any
additional attenuation.

The coupling device including the drainage coil, surge arrestor and earthing switch shall
conform to type tests and shall be subjected to routine tests as per IEC-481/IS:8998.

1.3 TESTS:

1.3.1 Type Tests


The equipment should be offered type test. Test reports should not more then seven years
old reckoned from date of bid opening in respect of all the tests carried out in accredited
laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or
another electric power utility and be submitted by the successful bidder to HVPNL for
approval as schedule given in Bar Chart.
1.3.2 Routine Tests
As per quality assurance program (QAP).

1.3.3 Acceptance Tests


All acceptance tests as stipulated in the relevant IS:8998 shall be carried out by the Supplier
in presence of HVPNL representative, unless dispensed with in writing by the HVPNL.

-2-
SECTION-10
CHAPTER-4
TECHNICAL SPECIFICATION OF 48 VOLTS 120 AH SMPS BASED BATTERY
CHARGER SUITABLE FOR VRLA MAINTENANCE FREE BATTERY BANK

1. SCOPE:
This specification provides for design, Engineering, manufacture, stage testing,
inspection and testing before dispatch, packing, forwarding and delivery at site FOR
destination of 48 Volts 120 AH SMPS based battery charger suitable for indoor
installation, complete with all fittings accessories and associated auxiliary equipment
mandatory which are required for efficient and trouble free operation as per specified
here under.

It is not the intent to specify completely all the details of design and construction of
equipment. However, the equipment shall conform in all respects to the high standard of
engineering, design and workmanship and shall be capable of performing in continuous
commercial operation up to the Bidder’s guarantee acceptable to the purchaser. The
equipment offered shall be complete in all component necessary for its effective and
trouble free operation along with associated equipment interlocks protection scheme etc.
Such components shall be deemed to be within the scope of supply irrespective of
whether those are specially brought out in this Specification and or the commercial order
or not. All similar parts particularly movable ones shall be interchangeable.

1.02 CLIMATIC CONDITIONS :


The equipment to be supplied against the specification shall be suitable for satisfactory
continuous operation under the following tropical conditions:

Max. ambient air temperature 500 C


Max. daily average ambient temperature 450 C
Max. yearly weighted ambient temperature 350 C

Min. air temperature (-) 50 C


Max. humidity 100%
Min. relative humidity 26 %
Average number of thunder storm days per annum 40
Average annual rain fall 15 cm to 100 cm.
Number of months during which tropical monsoon 4 months (June to
conditions prevail altitude above MSL Sept). Varies from 61 meters to
815.00 mtrs.
Average number of rainly days per annum. 120 days
Seismic level (Horizontal acceleration) 0.3g.
Degree of pollution Heavy
Intensity of solar radiation 1.0 KW/sq.m.
Max. Wind load 195 kg/sq.m.

1.03 STANDARD:
All material and equipment shall comply in all respect with requirement of the latest
addition of the relevant IS/IEC/TEC/RDSO. A set of standards adopted, translated in
English, if it is in language other than English, shall also be enclosed with the tender, to
enable due comparison, wherever a standard is specially mentioned in these

-0-
specification. It is understood that the corresponding standard amongst the sources
mentioned above shall also apply.

1.04 MANUFACTURE AND WORKMANSHIP:


All the material used in the construction of the equipment shall be of the best quality
obtainable of their respective kinds and whole of the work shall be of the highest class,
well finished and of approved design and make. Casting shall be free from blow holes,
flaws and of the true form and dimensions.

All machined surfaces shall be true and smooth and well finished.

1.05 DUTY AND GENERAL ARRANGEMENTS:


The power for the charging apparatus shall be given through an independents
4-core cable connection from an A.C. 50 cycles 3 phase 415 ± 10% volts
switchboard fed from a Station Transformer.

1.06 GENERAL TECHNICAL REQUIREMENT:


 
The battery chargers of 48V/25Amp. in N+1 configuration with ultimate capacity
50Amp/75 Amp/100Amp shall be of SMPS type with type earth. The system shall consist
of a Distribution/Switching/Alarms arrangement (DSA) and Float Rectifier-cum-Chargers
(FR/FCs) in a rack. It shall employ modular configuration for flexible provision of DC
Power. It shall employ menu driven Micro Processor Controlled Techniques for DSA as
well as module for control, monitoring and alarm to achieve better reliability of the
system. The SMPS battery chargers shall be capable of continuous operation with float
voltage 2.23 to 2.25 Volts per cell (at 27 Deg. C) and 2.3 Volt per cell (at 27 Deg C) for
charge voltage while supplying the constant DC load

1.06.1 The SMPS battery chargers shall have constant voltage characteristics throughout the
range (from zero to full load) at the floating value of the voltage so as to keep the
maintenance free type VRLA batteries fully charged but without harmful overcharge.

The system shall employ a modular configuration to provide flexibility in view the future
load requirements of DC power. The modules shall be accommodated in a rack.
Distribution/Switching/Alarm (DSA) shall be provided in first rack or in a separate rack as
per manufacturer’s design for the ultimate system capacity. All factory wiring for the rack
shall be for the ultimate capacity so that only plugging of FR/FC module shall enhance
the DC power plant output.
1.06.2 Principal Parameters: -
Input Nominal Voltage i) 230 Volt +/-10% AC single phase for module of
25Amp.For ultimate capacity of 50Amp
ii) System rack having ultimate capacity of 75 Amp and
125Amp will be provided AC Three phase input power
supply and each module shall operate on individual
phase of three-phase AC input power supply.
Input Voltage Range 165V to 260 V AC
Frequency 48Hz to 52Hz
Power factor >0.98 at 50% and above load
Efficiency >0.90 at 50% and above load
Soft Start time 10 sec Min output current ramp up
Output Voltage adj. 48V to 56V DC

-1-
Current limit adjustable
For 25Amps SMPS 5 to 25A
For 50Amps SMPS 5 to 50A
For 100Amps SMPS 5 to 100A
Regulation:
1) Output voltage +/-5% of DC output voltage for any load of 25% to 100%
over shoot/under shoot
when charger is switched
on +/-5% of DC output voltage for any load of 25% to 100%
2) DC output voltage
over shoot for a step
change in AC voltage
165V to 260V single +/-5% of DC output voltage for any load of 25% to 100%
phase
3) DC output voltage
for a step load change of
25% to 100%
Ripple <200mV RMS
Load Sharing Better than +/-5% active current sharing at full load
Cooling Convection
1.07. Main Features of SMPS Charger

1.07.1 CONSTRUCTIONAL FEATURES:

The rack structure shall be made up of rigid frame work of steel profiles and rear door
may be of hinged or removable type. The rear door shall be provided with ventilation
arrangement. Alternate design of aluminum and other rigid structure meeting the requirements
are also permitted.
The rack shall be free of sharp edges or sharp corners. The rack shall be designed for
easy maintenance & installation. The rack mounting arrangement shall be such as to provide
easy access from rear and top for installation and maintenance.
The individual FR/FC module shall be easily mounted to/removed from the front side of
the rack. The FR/FC module shall be designed to slide in to the rack on a suitable mechanical
arrangement. The associated AC input, DC output connections, control/systems & interface
cable connecting the modules shall be connected /disconnected easily without causing any
interruption in the supply and damage to load or other working module.
Proper thermal engineering of hardware design shall be done by the manufacturer so as
to ensure the uninterrupted use of the equipment. The rack complete with all panels fitted shall
be designed to allow cooling by natural convection.
With the doors in position, all the common visual alarms and meters shall be clearly
visible. However the fixtures on the door shall not restrict the movement of door in any way.
The FR/FC modules shall be cooled by natural convection. AC input to FR/FC shall be
through locking type arrangement. DC output shall be through hot plug in connector on the
FR/FC side and through lugged termination on the bus bar/termination end. Control alarm and
mentoring connection shall be through connectors. The FR/FC module shall be removable from
the rack only. All AC input, DC output & alarm/control/monitoring cables interconnecting the
modules and rack shall be easily disconnected by plugs or connectors.

AC Terminations
The input terminal should be single phase or three phases as the case may be cleared
marked as R Y B and N and for AC three phase, L and N for AC single phase.

-2-
AC input termination shall be suitably protected against the accidental touch/contact with
the working staff for their protection and shall also have clear and prominent be “Danger”
marking. Screening shall be provided between AC and DC components to prevent accidents.
The AC input connection to the rectifier module shall be by means of locking type plug
and socket arrangement. All the connection between distribution and FR/FC shall be through
proper rated cables only. Fuses and circuit breakers for each FR/FC shall be easily accessible
and properly rated. Proper termination for the AC input of the circuit breakers and its output to
the FR/FC.
The system racks having ultimate capacity of 100 Amp. will be provided AC three phase
input power supply and each module shall operate on individual phase of three phase AC input
power supply.

DC Terminations
The output of each rectifier in the negative load shall be taken through full rated ISI marked
MCBs. All the AC, DC control & alarm cabling shall be supplied with the rack.
All DC +ve and - ve leads shall be clearly marked.

Wiring
All insulated conductors except those within the confines of a printed circuit board
assembly shall be of the rating enough to withstand the maximum current and voltage during
fault and overload. All the wires and cables used shall be fire retardant as per IS 1554 with
amendment I (June 94).
All wiring shall be neatly secured in position and accurately supported. Where wires
pass through any part of metal or cover the holes through which they pass shall be suitably
bushed.

Earthing: -
Two power earth terminals shall be provided in the frame of the system.

Mounting off component & layout:


Components mounting and fixing methods shall be secured. Suitable mechanical
structure/ arrangement for holding modules in position shall be provided so that the module is
held firmly by sliding through it.
The FR/FC modules shall be cooled convection. AC input to FR/FC shall be through
locking type arrangement. DC out put shall be through hot plug in connector on the FR/FC side
and through lugged termination on the bus-bar termination end. Control, alarm and monitoring
connections shall be through connectors.
The FR/FC module shall be removable from the front of the rack only. All
AC input, DC output and alarm/control/monitoring cables interconnecting the modules and racks
shall be easily disconnected by plugs or connectors.

1.07.02Distribution, Switching, Control, alarm & Monitoring (DSA)


The Distribution Switching sub - system of DSA shall preferably be in the modular from
whereas control, alarm &, monitoring sub-system shall only be modular. The Controller must be
Microprocessor based. The distribution switching sub-system 'may be accommodated in a rack
with other FR/FCs or in separate rack. These sub systems shall be rack mountable. DSA shall
preferably be housed in the upper portion of the rack above the FR/FC modules. The unit shall
be equipped to meet the ultimate system capacity.

-3-
1.07.03. Battery Temperature Compensation.
The charger shall be provided with the appropriate circuitry to interface with the
temperature probe assembly. With the probe, the charger shall automatically compensate
gassing and constant voltage setting inversely proportional to the probe’s temp/ battery ambient
temp., so that over charging at high temperature and under charging at low temperature can be
prevented.

1.07.04 Current Limiting (Voltage Drop)


Current Limiting (Voltage" Drop) shall be provided for float/ charge operation. The
float/charge limiting shall be continuously adjustable between 50% to 100% of rated out put
current for out put voltages range of 44.4 to 56 volt. For test purposes upper limit of 100% +5%
and lower limit of 50% - 5% shall be acceptable. The float and charge current limit adjustment
shall be provided on the front panel of the rectifier module. The FR/FC modules shall be fully
protected against short circuit. It shall be ensured that short circuit does not lead to any fire
hazard.

1.07.5 Fuses
All fuses shall be HRC Link type. Fuses shall be mounted on fuse carriers which are in
turn mounted on fuse bases. Wherever it is not possible to mount fuses on carriers, fuses shall
be directly mounted on plug-in type base. In such case one insulated fuse pulling handle shall
be supplied for each charger. Fuse rating shall be chosen by the Bidder depending on the circuit
requirement. All fuses in the chargers shall be monitored. Fuse failure annunciation shall be
provided on the failure of any fuse.

1.07.6 Blocking Arrangements


Blocking arrangement shall be provided in the positive pole of the out put circuit of the
charger to prevent current flow fr9m the DC battery into the charger.

1.07.7 Monitoring, Alarm and Indicating Lamps.

The visual indications/ display such as LEDs, LCDs or a combination of both shall be
provided on each FR/FC module to indicate:

(A) Functional indications:


The following functional indications shall be provided on FR/FC and DSA:
a) Mains available.
b) FR/FC on Auto Float.
c) FR/FC on Auto charge.

Note: The functional indication (a) shall be provided on both DSA & FR/FC module. While
b and c may be provided either on DSA or both FR/FC & DSA.

(B) Alarm indications


(i) On FR/FC
(a) FR/FC over voltage, under voltage or output fail.
(b) FR/FC over load (voltage drop)
Functional indications shall be extended as status and alarm. FR/FC fail to distribution /
switching / control & alarm unit.

-4-
(ii) On DSA
a) Load voltage high (above 56v /low (below 45.6 v)
b) FR/FC fail
c) Mains out of range
d) System Over Load
e) Mains ON/Battery Discharge
f) Temp. Compensation fail
g) Battery Fail or No Battery
h) Battery Isolated from the load

All alarm circuits shall be provided with suitable delay to ensure that they do not operate
to transient. All the protection /alarm shall be within tolerance of O.25v in case of DC voltage
and 10/0 in case of current. For AC voltage it shall be +/- 5V.
Every alarm, condition shall be accompanied with an audio alarm with audio cut off
facility.
Potential free contacts two (one for alarm and one redundant) shall be provided for extension of
alarms to centralized display. - .

1.07.8 Radio Interference


The equipment shall be efficiently screened against interference to radio and also other
communication equipment, which may be installed in the same building. All sources of noise
shall be filtered if necessary with suppressors generally in accordant with relevant standards.

1.07.9 Name plates and marking


The name plates shall be while with Black engraved letters. On top of each charger, on front as
well as rear sides, larger and bold name plates shall be provided to identify the charger.
Name plates with full and clear inscriptions shall also be provided on and inside of the panels for
identification of the various equipments and ease of operation and maintenance.

An etched, engraved or anodizer name plate shall be fitted on each $MPS battery charger unit
having following details inscribed.

Manufacture's name.
P.O . No. & date.
S.No. of SMPS unit
Rating of SMPS charger
Input voltage of SMPS charger
Output voltage of SMPS charger
Year of Manufacture
8.0 RESPONSIBILITY FOR DESIGNS:

The Bidder shall assume full responsibility for co-ordinate and adequate design and shall
conform to the best engineering practice for the operating conditions specified. In case
the equipment covered by this specification is to be co-ordinate with other equipment,
the Bidder shall furnish complete information and data as may be desired by the
purchaser.

9.0 TESTS & INSPECTION:

-5-
The tenderer must furnish test reports carried out on one of the SMPS battery charge
unit which shall pass all the prescribed type tests for conformity of relevant standards. These
type test reports must be issued by a Govt. approved / Govt. recognized/ a Govt. accredited
laboratory and must not be older than 7 years from the date of opening of tender.
Routine/ acceptance tests shall also be carried out on each SMPS Battery Charger as
per specification. Following type tests shall be carried out for compliance of specification
requirements:

TYPE TESTS:
(I) Visual Inspection
(II) Insulation Resistance Test
(III) Applied high Voltage test.
(IV) Performance test.
(V) Test for protection device.
(VI) Burn in test.
(VII) Climatic test.
(VIII) Vibration test.

9.1 ROUTINE & ACCEPTANCE TESTS:

On each of the SMPS battery chargers following routine and acceptance tests shall be carried
out at manufacturer's works before dispatch.
(I) Visual Inspection
(II) Insulation Resistance Test
(III) Applied high Voltage test.
(IV) Performance test.
(V) Test for protection device & other tests shall be carried out as per requirement of GTP in
the presence of inspecting officer.

9.2 INSPECTION:

The inspection of the equipments shall be carried out by the purchaser's representatives
in accordance to the relevant standards.

a) The purchaser shall have access at all times to the works and all other places of
manufacture, where the equipments are being manufactured and; the supplier shall
provide all facilities for unrestricted inspection of the Supplier's works, raw materials,
manufacture of the material and for conducting necessary tests at any stage.
b) The supplier shall keep the purchaser informed in advance about the manufacturing
program so, that arrangements could be made for inspection.
c) No equipments shall be dispatched from its point of manufacture unless the material has
been satisfactorily inspected, tested and cleared.
d) Inspection and acceptance of any quantity of equipment shall in no way relieve the
Supplier from his responsibility for meeting all the requirements of this specification and
shall not prevent subsequent rejection if such equipment is later found to be defective.

9.3 TESTS AT SITE: -

-6-
The purchaser reserves the right to conduct all the tests on the equipment after arrival at
site and the supplier shall guarantee test certificate figures under actual service conditions.

10. DRAWINGS, LITERATURE AND MANUALS:

In addition to any other drawings which the tenderer may like to submit lo show the arrangement
and merits of the offered equipments. The following drawings shall be supplied with the tender.
i. General installation layout of SMPS equipments showing position of all associated
equipments.
ii. Detailed dimensional drawings and descriptive literatures of all the associated
equipments separately.
iii. Circuit wiring diagram and schematic diagram.
iv. Literature/ pamphlets / manuals of SMPS and its associated equipments.

The successful tenderer shall within four weeks of placement of order, submit four sets
of final version of all the drawings of the SMPS Battery Charger for purchaser’s
approval. The purchaser shall communicate his comments/approval on drawings to the
supplier within a period of four weeks. The supplier shall if necessary modify the
drawings and resubmit three copies of modified drawings for purchaser’s approval within
two weeks from the purchaser’s comment, which will be approved within 15 days. After
receipt of purchaser’s approval the supplier shall submit four sets of drawings and
literature containing erection, operating and maintenance instructions per equipment. A
set of reproducibles of the approved drawing too will be supplied for the purchaser use.

11. PACKING & MARKING

i. All SMPS equipments shall be packed in strong seasoned wooden crates to avoid
handling problem.
ii. The packing shall be of sufficient strength to withstand rough handling during transit,
strong at site and subsequent handling in the field.
iii. Suitable cushioning, protective padding, or dunnage or spacers shall be provided to
prevent damage or deformation during transit and handling.
iv. All packing cases shall be marked legibly with the appropriate caution symbol and
correctly so as to ensure safe arrival at their destination and avoid dispatched on
account of faulty packing and faulty or illegible markings stenciled on it-in indelible ink.
Whenever necessary, proper arrangement for lifting, such as lifting hooks etc. shall be
provided. Any material found short inside the packing cases shall be supplied by supplier
without any extra cost.
v. Each consignment shall be accompanied by a detailed packing list containing the
following information:
a) Name of the consignee.
b) Details of consignment.
c) Destination.
d) Total weight of consignment.
e) Sign showing upper/lower side of the crate.
f) Handling and unpacking instruction.

All gauges, meters, instruments etc. shall have dials or scales calibrated in metric
system of units. All name plates, instruction plate, warning signs and any marking

-7-
what-so-ever on the equipment and its parts and accessories shall be in Hindi-English
Language, using idioms, words and meaning as in current use in India.
In order to facilitate sorting and erection at site every part of the plant and equipment
shall be suitably marked.

12. PLACE OF MANUFACTURE AND INSPECTION:


The tenderer shall state in his tender the place(s) of manufacture, testing and inspection
of the various portions of the work included in the tender. The purchaser or his duly
authorised agent shall have access to the Bidder's or sub Bidder's work at any time
during working hours for the purpose of inspecting the manufacture and testing of
materials, equipment and completed plant and the Bidder shall provide the necessary
facilities for inspection.

13. DEPARTURE FROM SPECIFICATION:


Should the tendered wish to depart from provision of this specification either on account
of a manufacturing practice or for any other reasons, he will draw special attention to the
proposed points of departure in his tender and submit such full information, drawings &
specifications as will enable the merit of his proposal to be appreciated.

-8-
APPENDIX ‘A’ 
SCHEDULE OF REQUIREMENT 
Battery Charger: 
The Battery Charging equipment shall be housed in a sheet steel cabin finished in stove 
enameled light grey color conforming to shade of 631 of IS‐5 specification. The charger 
cabin  shall  have  thickness  of  18  gauge  or  better  with  adequate  ventilation.  The 
minimum  size  of  cubical  should  be  585mm  Width,  500mm  depth  and  560mm  Height. 
The  rack  shall  be  free  of  sharp  edges  or  sharp  corners.  The  rack  shall  be  designed  for 
easy  maintenance  &  installation.  The  rack  mounting  arrangement  shall  be  such  as  to 
provide  easy  access  from  rear  and  top  for  installation  and  maintenance.  Two  power 
earth  terminals  shall  be  provided  in  the  frame  of  the  system  to  provide  effective 
earthing to the system. 
The  individual  Rectifier  module  shall  be  easily  mounted  to/removed  from  the 
front side of the rack. The Rectifier module shall be designed to slide in to the rack on a 
suitable  mechanical  arrangement.  The  associated  AC  input,  DC  output  connections, 
control/systems  &  interface  cable  connecting  the  modules  shall  be  connected 
/disconnected  easily  without  causing  any  interruption  in  the  supply  and  damage  to 
load or other working module. There should be auto/manual change over between float 
and boost charger.   
Charger Section: 
The charger should be suitable for operation from single (230 ± 30% volts, 50Hz) 
or 3 phase (415 ± 30% volts, 50Hz) AC supply as per the system ultimate capacity and 
suitable  for  charging  24  cell  at  2.16  to  2.40  per  cell  while  simultaneously  supplying  a 
continuous load as per requirement at an ambient temp. of 45⁰C. The output of charger 
should  be  stabilized  within  1%  of  the  charging  voltage.  There  should  be  individual 
MCB for each module and complete system. The charger section shall comprise of the 
following items: 
 
S No.  Item Description               Qty 
1.   Cabinet                1 
2.   Hot Swap Rectifiers Modules 25A/48V  N+1      ( N = Load Current +  
Battery Charging Current) 
 
 

-9-
The  rectifier  Modules  shall  be  hot  swappable  with  Individual  Alarm  Indications  for 
Over Voltage/ Under Voltage or Output Fail. 
 
3  Dropping Diode 
 
During  the  Boost  charging  the  full  battery  voltage  should  not  be  reflected  on  the  bus 
bars, that is, it should be ensured that the constant voltage is available on DC bus bars 
irrespective  of  the  fact  whether  the  battery  is  on  float  or  on  boost  charge  and  at  same 
time  all  battery  cell  should  be  equally  charged.  There  should  be  auto/manual  change 
over between float and boost charger.     
 
4  Voltage monitoring Card            1  
5  AC Contactor              1 
6  DC Contactor              1 
7  Low Voltage Detection Card          1 
8  MCB 6A                4 
9  MCB 32A                2 
10  Lightening Protection Device Class C        1 
11  Battery temperature Compensation Probe       2m  
12        Microprocessor based Controller                                        1 No 
The controller should be mounted so that it is front accessible , front monitored 
and Front Controlled. It shall be installed in such a manner that the LCD panel is visible 
without opening and Lock / Door of the unit. The controller should have the following 
facilities: 
 
A. Metering : 
a) Load Voltage. 
b) Load Current. 
c) Battery Voltage. 
d) Battery Current. 
e) Battery Temp. 
f) Voltage and current of Individual module. 
B.  Alarms and Indications : 
a) Load voltage high. 
b) Single Rectifier alarm 
c) Multiple Rectifier alarm 
d) Mains out of range 
e) System Over Load 
f) Mains ON/Battery Discharge 

- 10 -
g) Temp. Compensation fail 
h) Battery Fail or No Battery 
i) Battery Isolated from the load 
 
All alarm circuits shall be provided with suitable delay to ensure that they do not 
operate to transient. All the protection /alarm shall be within tolerance of O.25v in case 
of DC voltage and 10/0 in case of current. For AC voltage it shall be +/‐ 5V. 
 
Every alarm, condition shall be accompanied with an audio alarm with audio cut 
off facility. 
 
C. Functional Indications:  
a) Mains available. 
b) Rectifier on Auto Float.  
c) Rectifier on Auto Charge. 
d) Alarm to indicate general alarm condition 
 
13.  Potential free contacts: 
Potential free contacts should be provided for extension of alarms to centralized 
display. 
a) Mains out of range. 
b) Single Rectifier alarm 
c) Multiple Rectifier alarm 
d) Communication Error. 
e) System Over Load. 
f) System voltage high. 
g) System voltage low. 
 
All the components should be of best quality and from reputed manufacturers. The
layout of components, wiring workmanship reliability etc. shall be of best quality.
Adequate space should be provided within the charger section and Distribution,
Switching, Control, alarm & Monitoring section for easy accessibility of MCB, Fuses,
Alarms, protection devices etc. The charging equipment should be complete with the
various component listed above but necessarily limited to the same. The charger shall
also be complete with wiring, glands and fixing bolts.

- 11 -
SECTION-10
CHAPTER-5

TECHNICAL SPECIFICATION OF H.F.CABLE (150 OHMS BALANCED) FOR


CONNECTING POWER LINE CARRIER COMMUNICATION TERMINAL
WITH THE ASSOCIATED EQUIPMENT FOR HVPN CARRIER NETWORK

1. GENERAL:

High frequency cable shall connect the coupling device installed in the
switchyard to the PLC terminal installed indoor. The high frequency cable to be
offered by the bidder shall be suitable for being laid directly in trenches or in
ducts.
The cable shall be tinned copper braided and steel armoured and its outer
covering shall be protected against attack by termites. Bidder shall offer his
comments on method employed by him for earthing of screen and submit full
justification for the same with due regard to safety requirements.

1.1 SCOPE:-
1.1.1 This specification covers details of H.F. Cable (150 Ohms BALANCED)
required for connecting Power Line carrier Communication terminals with the
associated equipment for HVPN carrier Network.

1.1.2 The scope of supply shall Include design, manufacture, testing at


manufacturer’s works before despatch and delivery of the H.F. Cable for use on
Power Line carrier Communication equipment in HVPN.

1.2 CLIMATIC CONDITIONS:-


1.2.1 The EHV grid substations (66kV and above) where the HF Cable is required to
be installed are located in the level plains of Haryana. The climatic conditions
are of extreme nature varying from extreme cold to dry and tropical humidity to
hot.

1.2.2 The HF Cable is required to serve satisfactorily under the following climatic
conditions prevailing at site:-
i) Maximum ambient temperature : 50oC
ii) Minimum temperature : -2.5oC
iii) Relative humidity :
a) Maximum : 100%
b) Minimum : 26%
iv) Average Nos. of thunder
Storms days per annum : 45.
v) Average Nos. of rainy days per annum : 120 days
vi) Average rain fall per annum. : 900mm
vii) Average number of dust storms
days per annum : 35
viii) Attitude above mean sea level : less than1000
ix) Maximum temperature in the : 45oC.
shade.
x) Maximum wind pressure : 195 Kg/M2

-1-
1.2.3 The atmosphere is to be considered as laden with industrial and town gas and
dust in suspension during dry-months. Fog smoke and mild acid are also
present. Heavy lighting is also present during the months from June to October.
The H.F.Cable is exposed to sunshine, rain, Fog, Hail, Snow etc.

1.3 MATERIALS AND WORKMANSHIP:-

1.3.1 All materials used in the construction/manufacture of the H.F.Cable shall be


brand new and of the best quality obtainable of their respective kind and shall
confirm to their respective Indian Standards or other equivalent International
recognized standards whenever applicable. The successful bidder shall
assume full reasonability for coordinated and adequate design.

1.3.2 The workmanship for HF Cable shall be of the highest grade and the entire
construction in accordance with the best modern engineering practice. The HF
Cable shall be designed to ensure satisfactory operation under the atmospheric
conditions prevailing at site.

1.4 STANDARDS:

1.4.1 The HF Cable and all its materials covered by this specification shall unless
otherwise stated complete in all respects with the requirements of the latest
edition of IS-5026 and IS-11967 Part-II/Sec-3.

1.5 DEPARTURE FROM SPECIFICATION:-


Should the bidder wish to depart from the provisions of this specifications either
on account of manufacturing practice for any other reasons he shall draw
special attention to the proposed points of departure a separate sheet(s) in his
tender as per Annexure-III of this specification and shall submit such full
information, drawings and specification so that the merits of his proposal may
be fully understood. This specification shall be held binding unless the
departures have been fully recorded as required above.

1.6 DOCUMENTATION:-
1.6.1 The successful bidder shall submit four sets of drawings for HVPNL approval.

1. Drawing showing the inside/inner of the HF Cable and dimensions of its


various components and structures including its weight.
2. Any other drawing to explain details and merits shall also be submitted.

NOTE: All above drawings should be a minimum space (14x10cm) for


stamping the approval of drawings by HVPNL.

1.7 TROPICAL TREATMENT:-

1.7.1 The H.F.Cable can be subjected during the service to extremely severe climatic
conditions detailed under Sr. No. 1.2 of this specification. All corrodible parts
and surfaces shall be provided with such protective finishes so that no part of
the installed H.F.Cable shall be injuriously affected by the atmospheric
conditions. The H.F.Cable, if required, may be given special treatments for
tropical conditions.
-2-
1.7.2 All part of the H.F.Cable that are likely to develop corrosion under normal
working conditions shall be effectively protected against corrosion by standard
methods to achieve durable results.

1.8 BIDDER’S EXPERIENCE:-

1.8.1 The bidder (s) shall clearly state in their experience and capability to undertake
design, manufacture, testing and supply of the items similar to that covered in
this specification giving complete information about their establishment i.e.
design office, working personnel, plant and machinery and testing facilities
available at the manufacturer’s works. Details of collaboration, if any, with other
renowned experienced manufacturers shall be stated in the tender.

1.8.2 The bidder shall supply list of purchase orders of similar item executed by them
during the past, giving the name of the purchase, year of supply and place of
installation of the item.

1.8.3 Information regarding satisfactory services/operation of the equipment supplied


in the past be also furnished with the tender.

1.9 RESPONSIBILITY OF DESIGN:-

The successful bidder shall assume full responsibility for adequate design for
the duty in view to ensure trouble free long service and tropical conditions and
shall use such arrangement and material as to confirm to the best engineering
practice for the operating conditions specified.
Impedance of the cable shall be such as to match the impedance of the PLC
terminal on one side and to that of the coupling device on the other side over
the entire carrier frequency range of 40-500 kHz. The H.F.Cable (150 ohms
balanced) shall meet the following parameters:-

1. Overall diameter of H.F.Cable shall be between 20-25 mm.


2. The mutual capacitance at 1 kHz of the H.F.Cable be 34 pf
(Nominal)/meter.
3. Conductor resistance of cable shall not exceed 12.8 ohm per km at
20oC & dia to be 1.4mm.
4. The H.F.Cable shall have bending radius of 20 times the overall
diameter of the cable.
5. Loop resistance of H.F.Cable will not exceed 30 ohms per km at 20oC.
6. Withstand test Voltage between conductor and outer sheath for one
minute to be 4kV.
7. The attenuation per km of the cable at various frequencies in the range
of 10 to 500 kHz shall remain in the range of 1 to 5.1 dB/km.
8. H.F.Cable will be with semi spaced dielectric, polythene string and tube
and annealed tinned braided copper wire with 90% coverage, polythene
inner sheath, GI wire braided armoring and overall PVC sheathed,
preferably grey. The protective armoring provided in the HF cable shall
consist of 0.3 mm (approx) dia of standard GI wire braiding with 70%
coverage.

-3-
1.10 TESTS:-
Type Tests:

The equipment should be offered type test. Test reports should not more then
seven years old reckoned from date of bid opening in respect of all the tests
carried out in accredited laboratories (based on ISO/IEC) by a reputed
accreditatic body or witnessed by HVPN or another electric power utility and be
submitted by the successful bidder to HVPNL for approval as schedule given in
Bar Chart.

i) Corona extinction voltage


ii) Characteristic impedance Attenuation (insertion loss)
iii) Structural return loss
iv) Capacitance
v) Capacitance Stability
vi) Capacitance unbalance
vii) Transmission unbalance
viii) Mechanically induced noise Voltage
ix) Time delay
x) Ageing stability
xi) Stress-crack resistance
xii) Outer conductor integrity
xiii) Screening efficiency
xiv) Cold bend
xv) Flow
xvi) Dimensional stability
xvii) Contamination
xviii) Bendability
xix) Flammability
xx) Resistance to fluids
xxi) Solderability Weight

ROUTINE TESTS:

As per quality assurance program (QAP).

ACCEPTANCE TESTS:
The following acceptance tests as stipulated in the relevant ISS:11967 (Part-
2/Sec-3), shall be carried out by the Supplier in presence of HVPNL
representative, unless dispensed with in writing by the HVPNL.
i) Visual and mechanical inspection
ii) Physical dimensions
Iii Marking
iv) Workmanship
v) Characteristic impedance Attenuation (insertion loss)

-4-
vi) Structural return loss
vii) Corona extinction voltage
viii) Capacitance
ix) Capacitance unbalance
x) Transmission unbalance
xi) Mechanically induced noise voltage
xii) Time delay
xiii) Cold dend
xiv) Contamination
xv) Resistance of fluids
xvi) Solderability Weight

1.11 INSPECTION:-

H.F.Cable shall be inspected by the authorised representative of the HVPNL at


manufacturer’s premises and acceptance test shall be carried out in
accordance with this specification. Inspection report alongwith the routine test
certificates shall be forwarded to the HVPNL for approval before despatch

1.12 PACKING AND DESPATCH :-

1.12.1 After approval of the Inspection/Test Certificates, the H.F.Cable will be


despatched as per the despatch instructions issued by the HVPNL.

1.12.2 The H.F.Cable shall be suitably packed in drum lengths of 500 meters with +
5% tolerance in drum lengths and total ordered quantity for transportation direct
to the consignee and the Bidder shall be responsible for all damages and
losses due to improper packing.

1.13 GUARANTEED TECHNICAL PARTICULARS:-

1.13.1 The bidders shall furnish with his offer Guaranteed Technical Particulars of the
HF Cable offered as per Annexure-I of this specification alongwith his
comments where his specification do not meet or exceed the requirements laid
down in this specification. These guaranteed technical particulars should be
supported by the published literature of the bidder.
1.13.2 Any other additional technical particulars may be supplied by the bidder which
he may like to give to prove the merits of the HF Cable offered by him. Tenders
without Guaranteed Technical Particulars may not be considered.

-5-
G-8/Package-A ANNEXURE

220KV GIS SUB- STATION AT A-4, FARIDABAD

LIST OF SWITCHYARD FOUNDATION DRAWINGS

A. TOWER DRAWINGS

SR. DRAWING NO.


NO. STRUCTURE TYPE

1. AT-1, AT-3 HVPN-003


2. CT-4, CT-5 HVPN-004

B. EQUIPMENT DRAWINGS

Sr. EQUIPMENT Drawing No.


No. DESCRIPTION 220kV 66kV
1. T/F 10/12.5MVA 66/11kV -- HCD/TS-1140
2. LA 0013 0022
3. Isolator - 0023
4. CVT 0012 0024
5. CT - 0025
6. NCT 0014 0014

C. OTHER DRAWINGS

S.N DRAWING NO. SUBJECT


1. HCD/SK-181 CROSS SECTION OF CONCRETE ROAD
2. HVPNl-001 CROSS SECTION OF BITUMENOUS ROAD
3. HCD/SK-172 CROSS SECTION OF PCC PAVEMENT/PARKING
4. HCD/TS-1224 (COM) RAIN HARVESTING SYSTEM
5. HCD/TS-1019 OUT DOOR CABLE TRENCHES
6. HCD/TS-1020 INDOOR CABLE TRENCHES & TRENCH X-ROAD
7. HCD/TZ-389 SUM-PIT CUM PUMP CHAMBER
8. HCD/TS-1024 SWITCH YARD FENCING
9. HCD/TS-1025 SWITCH YARD GATE
10. HCD/TS-182 (T) STANDARD DRAWING FOR SOAKAGE PIT
11. HCD/TS-1175 MAIN ENTRANCE GATE
GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

1 Manufacturers Name

2 Rating (MVA) 50/75/100

3 Voltage Ratio (KV) 220/66

4 Winding Connection Star with neutral


solidly earthed

5 Vector Group YY0

6 Number of Phase 3

7 Frequency (Hz) 50+5%

8 Type of cooling ONAN/ONAF/OFAF

9 Rating available at different cooling % 50%/75%/100%

10 Impedance data

a Guaranteed positive sequence impedance between HV-


LV at 75 deg.C with 100% rating at
i. Principal Tap 12.5%
ii. Maximum Tap
Iii. Minimum Tap

b Zero sequence impedance at principal tap

11 Guaranteed losses at 100% rated voltage (excluding


cooler loss) at 75 deg.C between HV and LV

a Iron loss (KW) (max) 54

b Copper loss (KW) (max) 295

12 Guaranteed cooler losses at

a 100% load (max) (KW) 8

13 Cooling equipment details

a Number of coolers and rating as per % of transformer 2x50%


cooling equipment
GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

b Mounting

c Fan motor data

i Number per cooler and rating as % of cooler


requirement (also indicate no.of spare fans)

ii Type

iii Rating (KW)

iv Locked rotor current (Amps)

v Temp. range over which cooler control is adjustable 50 0C to 1200C


(deg.c to deg.C)

d Oil pump motor data

i Number per cooler and rating as % of cooler


i t ( l i di t f )
ii Type

iii Rating (KW)

iv Locked rotor current (Amps)

v Temp. range over which cooler control is adjustable 50 0C to 1200C


(deg.c to deg.C)

e Type of oil pump and motor (whether oil submerged

f Radiator details

i Overall dimensions lxbxh (mm)

ii Total weight with oil (Kg)

iii Total weight without oil (Kg)

iv Thickness of Radiator tube (mm)

v Type of mounting

14 Thermal Data
GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

a Temperature rise in top oil over an ambient of 50 deg.C 50 0C

b Temp rise in winding by resistance measurement 55 0C

c Thermal time constant (Hours)

15 Withstand time for three phases short circuit at terminals 5 sec.


(secs)

16 Over excitation withstand time (sec)

i 1.25

ii 1.4

iii 1.5

17 Bushings

a High voltage

i) Manufacturer

ii) Type condenser

iii) Total creepage distance (mm) 6125

iv) Protected creepage distance (mm) 3062

v) Mounting tank cover

vi) Rated current (Amps) 800

b Low voltage

i) Manufacturer

ii) Type condenser

iii) Mounting tank cover

iv) Total creepage distance (mm) 3625

v Protected creepage distance (mm) 1812

vi) Rated current (Amps) 1000


GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

C Neutral Bushing

i) Manufacturer

ii) Type oil communicating

iii) Mounting tank cover

iv) Total creepage distance (mm) 900

v) Protected creepage distance (mm) 450

vi) Rated current (Amps) 1000

18 Is Vacuum filling required, if so state absolute pressure

19 Total quantity of oil (ltrs)

20 Tap changing equipment

a) Voltage class and current 132 kV & 300A

b) Number of steps 16

c) Range -10% to +10%

d) Step voltage 1.25%

e) Type High speed transition


type

f) Rated voltage of drive motor (volts)

g) No.of revolutions to complete one step

h) Time to complete one step on manual / auto operation


( )
i) Power required (kw)
GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

21 Insulation level

a) HV windings

i) Lightning impulse withstand voltage 950

ii) Power frequency withstand voltage (kv rms) 395

b) LV Winding

i) Lightning impulse withstand voltage 325

ii) Power frequency withstand voltage (kv rms) 140

c) HV Bushing

i) Lightning impulse withstand voltage 1050

ii) Power frequency withstand voltage (kv rms) 460

d) LV Bushing

i) Lightning impulse withstand voltage 325

ii) Power frequency withstand voltage (kv rms) 140

e) Neutral Bushing

i) Lightning impulse withstand voltage 170

ii) Power frequency withstand voltage (kv rms) 70

22 Approximate dimensions

a) Tank (lxbxh) mm

b) Overall dimensions with (mm) coolers lxbxh

c) Shipping dimensions (mm) (lxbxh)

d) Height for untanking (mm)

e) Dimensions of largest (mm) package (lxbxh)


GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

23 Weights of transformer components

a) Core (Kg)

b Windings (Kg)

c) Insulation (Kg)

d) Tank and fittings (Kg)

e) Oil (Kg)

f) Untanking weight (heaviest piece) (Kg)

g) Total weight Kg

h) Weight of heaviest package KG

i) Total shipping weight (Kg)

j) Parts detached for transport

24 Permissible overload (% of rating & time in minutes) As per IS:6600 &


IEC:354

25 Clearances

a) Minimum clearance between phases

i) In oil (mm)

ii) In air (mm) 2000/700 (CBIP)

b) Minimum clearance of HV winding to tank in oil (mm)

c) Minimum clearance of HV winding of earth in oil (mm)

d) Clearance between core (mm) and coil

e) Clearance between coil (mm)

f) Clearance between neutral to ground in air (mm)


GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

26 Conservator

a) Total volume (ltrs)

b) Volume between highest and lowest levels (ltrs)

27 Capacitance values

a) HV to earth (pf)

b) LV to earth (pf)

28a) Type of oil preservation

b) Material of air cell

c) Continuous temp. withstand capability of the air cell

29 a) No.of pressure relief device provided 2 or 1 No. PRD & 1


No. Explosion Vent

b) Operation pressure of pressure relief device

30 Oil

a) Quality of oil

i) Moisture content (ppm)

ii) Max tan delta value (at 90 deg.C)

iii) Resistivity (ohm – cm)

iv) Breakdown strength (kv)

v) Interfacial tension at 27 deg.C (min)

b) Quantity including 10% extra (Ltrs)

c) Standards applicable
GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

31 Core

a) Type of construction Core Type

b) Net core area (mm.sq)

c) Core material and grade used M4 HiB or Superior

d) Type of joint between core and yoke

e) Thickness of stamping (mm) 0.27mm (max)

f) Percentage silicon content (%)

g) Maximum flux density in core at rated frequency at

i) 90% voltage (wb/sq.m)

ii) 100% voltage (wb/sq.m) 1.6

iii) 110% voltage (wb/sq.m)

32 Winding

a) Type of winding Built of section/disc


coil. Spiral winding
not accepted

b) Current density at rated load

i) HV (A/Sq.cm) 250

ii) LV (A/Sq.cm) 250

iii) Regulating winding (A/Sq.cm) 250

c) Conductor area

i) HV (sq.mm)

ii) LV (sq.mm)
GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

Iii) Regulating winding

d) Maximum current density under short circuit

i) i) HV (sq.mm)

ii) LV (sq.mm)

e) Magnetising inrush current (Amps)

f) No load current (Amps) at rated frequency and at

i) 90% voltage (wb/sq.m)

ii) 100% voltage (wb/sq.m)

iii) 110% voltage (wb/sq.m)

g) Magnetising current at rated frequency and at rated


voltage

33 Tank

a) Type Preferably Bell

b) Material Low carbon steel

c) Approx Thickness of

i) Sides (mm)

ii) Bottom (mm)

iii) Cover (mm)

34 Radiator

a) Make

b) Material

c) Thickness

35 Vacuum withstand capability of


GTP OF 100 MVA 220 66 KV T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

a) Main tank (torr)

b) Radiators accessories (torr)

36 Pressure withstanding capability of

a) Main Tank

b) Radiator and accessories

37 Temperature indicators

a) OTI

i) Manufacturer

ii) Range 500 C to 1200C

iii) Accuracy

b) WTI

i) Manufacturer

ii) Range 500 C to 1200C

iii) Accuracy

c) RWTI

i) Manufacturer

ii) Range 500 C to 1200C

iii) Accuracy

iv) Auxiliary supply used 220 V DC

38 Terminal connectors

a) Make

b) Whether type tested

c) Governing standard
GTP of 66 KV SF6 CIRCUIT BREAKER
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 General
a) Name of the Manufacturer
b) Type of Circuit Breaker 3 pole outdoor SF-6
c) Manufacturer’s type designation

d) Standard Applicable IEC:56, IS:13118

e) Rated Voltage (KV rms) 72.5


f) Rated Current
i. Under normal condition (A) 1600
ii. Under site Conditions (A) 1600
g) Rated frequency (Hz) 50
h) Number of poles 3
I) Whether 3 pole or single pole 3 pole gang operated
unit
j) Whether All The 3 poles ganged
electrically or mechanically.

2 Guaranteed Technical
Particulars
a) Rated short circuit breaking
current
i. Symmetrical component at 31.5
highest system voltage (kA)
ii. DC Component (%) As per IEC:56
iii. Asymmetrical breaking current
at highest system voltage (kA)
b) Rated Making Capacity
i. At higher rated voltage (kAp) 78.75
ii. At lower rated voltage (kAp) 78.75
c1) Maximum Total break time less than 3 cycles or
under any duty condition for any 60msec.
current upto rated breaking
current with limiting conditions of
voltage and pressure (ms)
c2) Rated break time as per IEC
d) Closing time (ms) max.150msec.
e) Minimum opening time under
any condition with limiting
voltage and pressure (ms)
GTP of 66 KV SF6 CIRCUIT BREAKER
S. NO. DESCRIPTION PARTICULARS
Required Offered
f) Maximum opening time under
any condition with limiting
voltage and pressure (ms)
g) Maximum close open time under
any condition with limiting
voltage and pressure (ms)

h) First pole to clear factor as per IEC/IS


i) Short time current rating (kA) for 31.5
1sec
j) Rated operating duty O-0.3 sec-CO-3 min-CO

k) Maximum over voltage (p.u) on


switching capacitor banks of
rating upto 20 MVAR
l) Maximum pole discrepancy (ms)

m) Maximum arc duration and


corresponding current under
lockout pressure
n) Maximum temperature rise for
main contacts over design
ambient temperature of 50 deg
C.
o) Rated voltage & pick up range 220V DC & 85%-110%
for trip coil (V)
p) Rated voltage & pick up range 220V DC & 85%-110%
for closing coil (V)
q) Rated pressure and limits of
pressure of operating
mechanism
r) Rated pressure and limits of
pressure of extinguishing
medium
3 Dielectric Withstand of
Complete Breaker
GTP of 66 KV SF6 CIRCUIT BREAKER
S. NO. DESCRIPTION PARTICULARS
Required Offered
a) One minute dry & wet power
frequency withstand voltage
i. Between live terminal and 170
ground (KV rms)
ii. Between terminals with breaker 170
contacts open (KV rms)

b) 1.2/50 micro second impulse


withstand test voltage
i. Between live terminals and 325
ground (KVp)
ii. Between terminals with breaker 325
contacts open (KVp)
c) Maximum radio interference
voltage (micro V) at 1.1 Ur/ root
3

d) Total creepage distance


i. To ground (mm) 1813mm (min)
ii. Between terminals (mm) 1813mm (min)
4 Operating Mechanism
a) Type of operating mechanism
for
i Closing
Spring
ii Opening
b) Manufacturer’s type designation

c) Normal power consumption (W)


at rated voltage of 220-V DC

i. Trip coil
ii. Closing coil
4.1 Pneumatic operating Not applicable
mechanism
a) Rated operating pressure
(kg/sq.cm)
b) Range of pressure for
(kg/sq.cm)
i. Closing
ii. Opening
GTP of 66 KV SF6 CIRCUIT BREAKER
S. NO. DESCRIPTION PARTICULARS
Required Offered
c) Air Consumption at rated
pressure for
i. Closing (m3)
ii. Opening (m3)
iii. Close-Open (m3)
d) Number and Capacity (m3) of
breaker local air storage
receivers
e) No. of close operations for
which sufficient air is available in
local receiver

f) Capacity of compressor (m3/hr)


and working pressure (kg/cm2)

g) Maximum time for which


compressor can operate
continuously (min)
h) Time to fill
i) Air receiver after one CO
operation (min)
ii) For making up of losses
occurring in 4 hours (min)
i) Pressure at which compressor

i) Starts (kg/cm2)
ii) Stops (kg/cm2)
j) Safety valve
i) Low pressure stage blow off at
(kg/cm2)
ii) High pressure stage blow off at
(kg/cm2)
k) Safety valve opens at (kg/cm2)

l) No. of stored Co operation in


breaker air receiver
m) Alarm switch closes on air
receiver at (kg/cm2)
n) Lockout pressure (kg/cm2)
i) Closing
GTP of 66 KV SF6 CIRCUIT BREAKER
S. NO. DESCRIPTION PARTICULARS
Required Offered
ii) Opening
4.2 Spring charged mechanism
a) Number of close open
operations possible after failure
of AC supply to motor
b) Time required for motor to
charge the closing spring (min)

c) Whether indication of spring


charged condition provided in
central control cabinet
5 Type of Breaker
5.1 SF6 Circuit Breakers
a) Quantity of SF6 per pole (CuM)
at rated pressure
b) Guaranteed maximum leakage 1%
rate per year
c) Rated pressure of SF6 in
operating chamber (kg/cm2)
d) Limits of pressure at which
breaker operates correctly
(kg/cm2)
e) Standard to which SF6 gas As per IEC:376
complies
f) Capacity & filling ratio of
containers in which SF6 gas
would be shipped (CuM) and the
corresponding pressure (kg/Sq
cm)
g) Whether breakers are
dispatched filled with SF-6 or
required to be filled at site.
h) Density/Pressure gauge setting

i) Lockout
ii) Alarm
iii) Minimum time interval between
make/break operation
5.2 General
GTP of 66 KV SF6 CIRCUIT BREAKER
S. NO. DESCRIPTION PARTICULARS
Required Offered
a) Weight of complete 3 phase
breaker for foundation design
(kg)
b) Weight of heaviest part of
Breaker (Kg) part of breaker (kg)

c) Impact loading for foundation


design
d) Seismic level for which breaker 0.3g (horizontal)
is designed
e) Minimum safety clearance from
earther objects
f) Minimum clearance in air
i. between live parts (mm) 1400
ii. live parts to earth (mm) 800
iii. Live parts to ground level (mm) 3000
6 Constructional Details
a) Whether arcing contacts Yes
provided
b) Type and material of main
contacts and arcing contacts
c) Contact pressure on main
contacts (kg/Sq cm)
d) Contact separation in arcing
position (mm)
e) Contact separation in open
position (mm)
f) Rate of contact travel
i. Opening (m/sec)
ii. Closing (m/sec)
g) Whether the making & breaking Yes
contacts are hermetically sealed

h) Number of auxiliary contacts per 10 NO+10NC


pole provided for Owner's use

I) Rated voltage of auxiliary 220V DC


contacts (V)
j) Current rating of auxiliary
contacts
i. Continuous (A) 10
ii. DC breaking with 20 ms time 2
constant (A)
GTP OF 198 KV SURGE ARRESTERS
S. NO. DESCRIPTION Particulars
Required Offered
198kV 198kV
1 GENERAL

a) Manufacturer’s Name

b) Country of origin

c) Manufacturer’s type designation Station Class Heavy


Duty

d) Applicable standards IEC 99-4 IS : 3070

2 ELECTRICAL CHARACTERISTICS

a) Arrester class and type Gapless type, Station


Class

b) Rated arrester voltage (kV) 198kV rms.

c) Maximum continuous operating voltage (COV) 168kV rms.


at design ambient temperature

d) Nominal discharge current (8/20 micro sec.wave)(kA) 10KA

e) i) Minimum discharge 5 kJ/KV


capability (kJ/kV) referred
to rated voltage at minimum
of discharge characteristics

ii) Line Discharge class, as per IEC 3

f) Maximum equivalent front of wave protection level


(discharge voltage with 0.5x1.5 micro sec, 10 kA
impulse current)

g) Maximum switching surge residual voltage, at 455


1 kA (kVp)

h) Maximum residual voltage for 8/20 micro sec current


wave

i. at 50 % nominal discharge current (kVp)

ii. at 100 % nominal discharge current (kVp) 550

iii. at 200 % nominal discharge current (kVp)

i) One minute power frequency (dry) withstand voltage


of arrester (kV rms)(Min.)
j) Impulse withstand test voltage of arrester housing
with 1.2/50 micro sec wave, (KVp)
k) impulse currentwithstand
a) Transformers and Reactors (kVp) 900
b) Other equipment and lines (kVp) 1050

i. High current short duration (4/10 micro sec. wave) 100


(kAp)

l) Maximum internal ionisation at 50 Hz voltage equal


to

i. 1.05 COV

ii. 1.0 COV

m) Reference voltage and corresponding reference current >198kV


n) Pressure relief class A

o) Energy absorption capability in kJ per operation


of the arrester, during a switching surge discharge

p) Internal pressure required to operate pressure relief


device as a percentage of burst pressure of porcelain

q) Minimum prospective symmetrical fault current 40


(kA rms)

r) Rated voltage of ZnO disc (kV)

i) No. of ZnO discs in a unit

ii) No. of units/arrester

iii) Height/Thickness of ZnO discs (mm)

iv) Diameter of ZnO disc (mm)

3 EXTERNAL INSULATION
a) Applicable standard

b) Impulse voltage withstand test voltage of housing


with 1.2/50 micro sec wave (kVp)

c) One minute power frequency withstand voltage of


arrester housing dry & wet (kV rms)

d) Total creepage distance of of arrester housing (mm) 6125

4 Overall dimensions

a. Height(mm)
b. Diameter(mm)
5 Net weight(Kg.)
6 Cantilever strength (Kg. M)
GTP OF 60 KV SURGE ARRESTERS
S. NO. DESCRIPTION PARTICULARS
Required Offered
60kV 60kV
1 GENERAL

a) Manufacturer’s Name

b) Country of origin

c) Manufacturer’s type designation Station Class Heavy


Duty

d) Applicable standards IEC 99-4 IS : 3070

2 ELECTRICAL CHARACTERISTICS

a) Arrester class and type Gapless type, Station


Class

b) Rated arrester voltage (kV) 60kV rms.

c) Maximum continuous operating voltage (COV) 49kV rms.


at design ambient temperature

d) Nominal discharge current (8/20 micro sec.wave)(kA) 10KA

e) i) Minimum discharge 5 kJ/KV


capability (kJ/kV) referred
to rated voltage at minimum
of discharge characteristics

ii) Line Discharge class, as per IEC 3

f) Maximum equivalent front of wave protection level


(discharge voltage with 0.5x1.5 micro sec, 10 kA
impulse current)

g) Maximum switching surge residual voltage, at 140


1 kA (kVp)

h) Maximum residual voltage for 8/20 micro sec current


wave

i. at 50 % nominal discharge current (kVp)

ii. at 100 % nominal discharge current (kVp) 170

iii. at 200 % nominal discharge current (kVp)

i) One minute power frequency (dry) withstand voltage


of arrester (kV rms)(Min.)
j) Impulse withstand test voltage of arrester housing
with 1.2/50 micro sec wave, (KVp)
k) impulse currentwithstand
a) Transformers and Reactors (kVp) 325
b) Other equipment and lines (kVp) 325

i. High current short duration (4/10 micro sec. wave) 100


(kAp)

l) Maximum internal ionisation at 50 Hz voltage equal


to

i. 1.05 COV

ii. 1.0 COV

m) Reference voltage and corresponding reference current >60kV

n) Pressure relief class A

o) Energy absorption capability in kJ per operation


of the arrester, during a switching surge discharge

p) Internal pressure required to operate pressure relief


device as a percentage of burst pressure of porcelain

q) Minimum prospective symmetrical fault current 40


(kA rms)

r) Rated voltage of ZnO disc (kV)

i) No. of ZnO discs in a unit

ii) No. of units/arrester

iii) Height/Thickness of ZnO discs (mm)

iv) Diameter of ZnO disc (mm)

3 EXTERNAL INSULATION
a) Applicable standard

b) Impulse voltage withstand test voltage of housing


with 1.2/50 micro sec wave (kVp)

c) One minute power frequency withstand voltage of


arrester housing dry & wet (kV rms)

d) Total creepage distance of of arrester housing (mm) 1813

4 Overall dimensions

a. Height(mm)
b. Diameter(mm)
5 Net weight(Kg.)
6 Cantilever strength (Kg. M)
GTP OF 66 KV ISOLATORS (DISCONNECTING SWITCHES)
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 GENERAL

a) Name of the Manufacturer

b) Manufacturer's type designation Double Break - DB

c) Standard applicable for IS: 9921 (Part I to V)


isolators and earthing switches

d) Max. design voltage as which 66 KV


the insulator can operate

e) Rated voltage 72.5KV

f) Rated current 1600 Amps

g) Max. current that can be safely


interupter by the isolator

i) Inductive

ii) Capacitive (under site


conditions at 50 deg.C ambient

h) Rated frequency 50 Hz

I) Pole to pole spacing 1830 mm

2 GUARANTEED RATINGS:

a) Rated short time current of 31.5 KA


isolator for 1 sec. (KA) and 78.75 KA (peak)
dynamic current

b) Temperature rise over 50 deg.


C ambient temperature
corresponding to a maximum
continuous current

3 Dielectric withstand capacity


GTP OF 66 KV ISOLATORS (DISCONNECTING SWITCHES)
S. NO. DESCRIPTION PARTICULARS
Required Offered
of completely assembled
isolator and earth switch

a) One minute dry power


frequency withstand test
voltage (KV rms)
i) Against ground (KV rms) 140 KV rms

ii) Across isolating distance 160 KV rms


(KV rms)

b) 1.2/50 micro second impulse


withstand test voltage

i) Against ground (KV peak) 325KV (peak)

ii) Across isolating distance 375 KV (peak)

c) Total creepage distance to 1813 mm


ground

4 Operating Mechanism for


Main Blades & Earth switch

a) Type of operating drive


mechanism

b) Manufacturer's type designation

5 Interlocks

a) Whether mechanical/ Yes


constructional interlock
between isolator and earth
switch provided

b) Details of electrical interlock


enclosed for
I) Isolator
ii) Earth Switch
GTP OF 66 KV ISOLATORS (DISCONNECTING SWITCHES)
S. NO. DESCRIPTION PARTICULARS
Required Offered
c) Arrangement provided to Yes
prevent operation unless
interlock conditions are
satisfied

6 Constructional features

a) Minimum clearance in air


i) Between phases
ii) Between live parts to earth

iii) Between line parts when switch


is open
-on the same pole
-between adjacent poles

b) Whether position of earth switch can be Yes., Earth switches

interchanged at site to either side of pole are interchangeable

c) Minimum clearance between


live part and earth switch blade
throughout the entire
operational arc of earth switch

d) Terminal pad details


i) Diameter & length

ii) Material of pad HDE copper flat

e) Insulator data

i) Height
ii) Type Solidcore
iii) No. of insulators/stack One
iv) Mechanical & Electrical
parameters of insulator
v) Top and bottom fitting PCD
GTP OF 66 KV ISOLATORS (DISCONNECTING SWITCHES)
S. NO. DESCRIPTION PARTICULARS
Required Offered
vi) Weight of insulators
vii) Minimum creepage distance 25 mm/KV
viii) B.I.L 325 KV (peak)

f) Main contacts

i) Type of contacts
ii) Contact area

iii) Material of contacts HDE Copper

iv) Contact pressure Medium pressure

v) Maximum current density under


normal current carrying
capacity

vi) Thickness of silver plating

g) Number of auxiliary contacts 8 NO + 8 NC + 2 MBB


on isolator switch/pole for
Employer's use

h) Number of auxiliary contacts 3 NO + 3 NC


on earth switch/pole for
Employer's use

I) Auxiliary contacts

j) No. of insulator per pole Three

k) No. of break per pole Two

l) Type of closing/opening Horizontal

m) Mechanism Motor

i) Bearing material and size of


housing

ii) No. of bearings, location and


size

n) Tandem pipe:
GTP OF 66 KV ISOLATORS (DISCONNECTING SWITCHES)
S. NO. DESCRIPTION PARTICULARS
Required Offered
i) Size class and No. of pipes

ii) Auxiliary contacts

i) Rated voltage 220 V DC

ii) Rated continuous current 10 Amps

iii) Rated DC breaking current with 20 ms 2 Amps


time constant
GUARANTEED TECHNICAL PARTICULARS of 220 KV 800mm2 XLPE Cable

SR. NO DESCRIPTION PARTICULARS

Required Offered

1 Make
2 Type
3 Applicable Standard IS: 7098 (Part-III)/1993
Construction
Testing
4 Voltage Grade KV 127/220
5 Suitable for system with
a) Service Voltage KV 220
b) Neutral Earthing
6 Maximum Condutor Temperature
a) a) Continuous 0 90
C
b) b) Short time (Short Circuit) 0 250
C
7 Conductor
a) Material & conforming standard HD Aluminium, IS: 8130
b) Grade
c) Size, Nominal Area mm2 800
d) No. & Nom. Diameter of wire in each No/mm
conductor, Before stranding
8 Shielding on conductor
a) Material Semi -Conducting
Polymer
b) Grade
c) Type/Applicable Standard
d) Thickness (mm) mm2
e) Tolerance of thickness
9 Insulation
a) Material High standard quality
b) Type/Applicable Standard IS: 7098 (Part-II)
c) Thickness, Nominal mm
d) Negative tolerance of thickness mm
e) Approx. dia. Of core over insulation mm

10 Shielding on Insulation
a) Material Non-Magnetic semi-
conducting shield
b) Type/Applicable Standard
c) Thickness, extruded layer mm
d) Approx. dia. Of cable over shielding mm
SR. NO DESCRIPTION PARTICULARS

Required Offered

10A Copper Tape Screen


a) Material & Type
b) Nominal thickness of copper tape mm
10B Water barrier over copper screen
a) Material & type
b) Approx. thicknes of tape mm
10C Redial Water barrier
a) Material & type
b) Approx. thicknes of tape mm
11 Inner Sheath
a) Material Extruded and of black
polyethylene
b) Type/Applicable Standard
c) Thickness mm
d) Extruded? Yes/No. Yes
e) Approx. outside dial. over sheath mm
12 Armouring
a) Material Single HD Aluminium
wire
b) Type/Applicable Standard IS:3957
c) Fictitious calculated dial overinner mm
sheath (under armour)
d) Size(Approx. No x Nom. Wire Dia), Noxmm
Nominal Area
e) D.C.Resistance of armour at 200C ohm/km

f) Short circuit current carrying capacity KA

13 Overall sheath
a) Material Suitable Semi-
conducting layer coated
on extruded PVC outer
sheath
b) Type/Applicable Standard IEC:502
c) Calculated dial under sheath (over mm
armour) (As per annexure A to IEC
60502-2)
d) Thickness, Nominal mm
e) Colour
f) Tolerance of thickness
13A Conducting layer over outer sheath

14 Approx. overall diameter mm


SR. NO DESCRIPTION PARTICULARS

Required Offered

15 Standard drum length with tolerance meters 500 mtrs. +/- 5%


tolerance & +/- 2%
overall tolerance in total
quantity of cable
16 Net weight of cable, approx. kg/km
17 Approx. weight of empty drum kg
18 Continuous current rating for
standard IS condition laid direct
a) In ground, ground temp 300C Amps
b) 0 Amps
In duct, ground temp 30 C
c) 0 Amps
In air, ambient temp 30 C
19 FOR XLPE CABLE
The cable guaranteed to safel y
withstand continuous current for
temperature of 900C and also
0
withstand temperature of 130 C for a
duration of 500hours per year
20 Short circuit current for 3 second As per specification
a) Conductor kA
b) Aluminium wire armour kA
21 Electrical parameters at maximum
operating temperature
a) i) DC Resistance at 200C, conductor ohm/km

ii) AC Resistance at 900C, conductor ohm/km

b) Reactance at 50C/s, approx ohm/km


c) Impedance, Approx ohm/km
d) Capacitance per phase, Max. Micro F /mm
e) Vol. Resistivity at rated operating ohm/km
temperature 900C
f) Loss tangent
g) Partial discharge value
h) Charging current at normal operating mA/km
voltage
22 Recommended minimum bending
radius
23 The cables shall be tested as
specified under
a) Conductor resistance test
b) Partial discharge test
SR. NO DESCRIPTION PARTICULARS

Required Offered

c) High voltage test (specify test


voltage for 5 minutes)
CONTROL AND RELAY PANELS
Sr. Description PARTICULARS
No. Required Offered
I. PANELS.
1. Dimension of the C&R panels.
i) Depth
ii) Overall height 610 mm
iii) Width 2312 mm

2. Width of corridor (applicable in case 762 mm


of `Duplex' type panels).

3. Dimension of supporting channel. 102 mm


4. Thickness of the sheet steel proposed Min. 10 SWG for
for fabrication of panels. base frame, door
frame, front & rear
portions of cubicle
and not less than
14 SWG for doors,
sides, top & bottom
portion
II. SWITCH BOARD WIRING.
1. Insulation of wiring. 650V PVC
2. Material of wiring conductor. Copper
3. Size of wiring conductor for:
i) C.T. Circuits. 2.5 mm2
ii) C.V.T./P.T. Circuits. 2.5 mm2
iii) D.C. supply circuits. 1.5 mm2
iv) A.C. Supply Circuit. 1.5 mm2
v) Other circuits. 1.5 mm2
4. Size of earthing bar for safety 25mm X 6mm Copper
earthing.
5. Type of terminals used in wiring the stud
panel.

III. INDICATING AND INTEGRATING


INSTRUMENTS(AMMETER,
VOLTMETER, MW METER, MVAR
METER AND KWH METER TO BE
FILLED IN SEPARATELY
FOR EACH ITEM).
1. Make
2. Type
3. Size. 144 Sq. mm
4. VA burden
a) Current coil.
CONTROL AND RELAY PANELS
b) Potential coil.
5. Power consumption.
a) Current coil.
b) Potential coil.
6. I.S. Standard grade of accuracy. Class 1
7. Range of dial.
9. Limits of error in effective
8. range.
9. Calibration for :
a) CT Ratio.
b) P.T. Ratio.
10. Finish. Black
11. Short time overload capacity.
12. Descriptive leaflet reference Nos.

submitted.
13. Type & make of selector switch for:
a) Ammeter.
b) Voltmeter.
IV. CONTROL SWITCHES FOR CIRCUIT
BREAKER & ISOLATORS.
1. Make.
2. Type.
3. Type of handle provided. Pistol Grip
4. Number of position . 3
5. Whether no. of Normally closed &
Normally open contacts sufficient
for seheme requirements?
(Yes / No).
6. Whether spring return to neutral or Spring Return to
stay-put type. Neutral
7. Type of lock provided. Non lockable
8. Making capacity/breaking capacity at
220 Volt DC for both inductive &

non-inductive current.
9. Descriptive leaflet number submitted.
V. SEMAPHORE INDICATORS (FOR
CIRCUIT BREAKER, ISOLATOR
& EARTH SWITCH).
1. Make.
2. Type.
3. Diameter of the disk.
4. Operating voltage. 220V DC
5. Burden.
6. Whether latch-in type or supply Supply failure type
failure type.
7. Descriptive leaflet number submitted.
CONTROL AND RELAY PANELS
VI. INDICATING LAMPS.
1. Make.
2. Type.
3. Operating voltage. 220V DC/230V AC
4. Size of lens.
5. Wattage of the lamp.
6. Descriptive leaflet number submitted.

VII. OVER CURRENT & EARTH FAULT RELAY.


1. Make.
2. Type of relay.

3. Current coil rating. 1A/5A


4. Potential coil rating (applicable 110V/63.5V
only in case of directional relays).

5. Tap range. 50-200% o/c


20-80% e/f

6. Range of high set elements (wherever 500-2000% o/c


applicable). 200-800% e/f
7. VA burden.
a) Highest tap.
b) Lowest tap.
8. Time V/S current characteristics. IDMT
9. Trip contact rating.
10. Descriptive leaflet No. submitted.

VIII AUXILIARY RELAYS.


1. Make.
2. Type.
3. Capacity of contacts:
i) Continuously.
ii) for 3 seconds.
4. Operating coil VA burden.
5. Voltage operated or current operated.
6. No. of Normally closed & Normally Yes
open
contacts sufficient for seheme
requirements (Yes / No).
7. Contacts hand or self reset type.
8. Descriptive leaflet number submitted.

IX. FACIA ANNUNCIATOR .


1. Make .
2. Type.
3. Size.
CONTROL AND RELAY PANELS
4. No. of windows of the standard facia.
5. No. of additional windows that can be
added to the standard facia, as at
Sr.No. 3 above.
6. Provision of `Accept', `Reset', and Provided Separately
`Lamp test', push buttons in the
facia.
7. Mode of inscription on the facia

window.
8. Operating voltage. 220V DC
9. Description of leaflet submitted.
X. TRANSFORMER DIFFERENTIAL RELAY.
1. Make.
2. Type.
3. Minimum differential current at which 15% Max.
relay operations.
4. Range & steps of bias setting. 20-50%
5. Operating time at twice the relay 30m sec. max. at 5
setting. times rated current
6. VA burden of the relay.
7. Descriptive leaflet No. submitted.
8. No. of Normally closed & normally Yes
open contacts sufficient for scheme
requirement
XI. TRIP CIRCUIT SUPERVISION RELAY.
1. Make.
2. Type
3. Rating 220V DC
4. Minimum voltage for satisfactory
operation (% of rated voltage).
5. Monitoring of breaker trip coil in Yes
both
close & open position provided.
6. Safety resistors provided to limit Yes
the current if the relay coil is
short-circuited.
7. No. of Normally closed & Normally Yes
open
contacts sufficient for seheme
requirements (Yes / No).
XII. RESTRICTED EARTH FAULT RELAY .
1. Make.
2. Type.
3. Tap range. 10-40%
4. Timer setting range.
5. V A Burden.
6. Time/Current characteristics
CONTROL AND RELAY PANELS
7. Short time rating of relay.
8. Descriptive leaflet No. submitted.
XIII T/F OVER FLUXING RELAY.
1. Make
2. Type.
3. Rated Voltage (V,AC) 110 V
4. Rated DC Voltage. 220 V
5. Operating principle. V/F
6. No. of Normally closed & Normally Yes
open contacts sufficient for seheme
requirements (Yes / No).
7. Contacts self/hand reset.
8. Burden.
9. Setting range.
i) V/F 100-130%
ii) Time for alarm. 0.1-6 Sec.
iii) Time for tripping.
10. Whether inverse time operating Yes
characteristics provided.
11. Whether different time multiplier

settings provided.
12. Max. operating time of the relay at
i) 1.4 times the rated value of V/F.
ii) 1.25 times the rated value of
V/F.
13. Reset time.
XIV. LOCAL BREAKER BACK UP RELAYS .
1. Make.
2. Type.
3. Setting range (% of rating)
a) Phase faults. 20-80%
b) Ground faults. 20-80%
4. Operating time (m sec.) 15m Sec. Max.
5. Reset time (m sec). 15m Sec. Max.
6. Burden.
7. Timer range. 0.05-0.5 sec.
8. Whether no. of Normally closed & Yes
Normally open contacts sufficient
for scheme requirements? (Yes / No).
XV. OVER LOAD ALARM RELAY.
1. Make.
2. Type.
3. Rated Voltage.
4. Setting Ranges. 50-120%, 50-200%
For T/F, For Line
5. Operating time.
6. Setting range continuously variable. Yes
CONTROL AND RELAY PANELS
XVI. SELECTOR SWITCHES (AUTO-
RECLOSING IN/OUT, CARRIER
PROTECTION IN/OUT SWITCH,
TRIP TRANSFER SWITCH).
1. Make.
2. Type.
3. Type of handle.
4. No. of positions. As per scheme
requirement
5. No. of Normally closed & Normally Yes
open contacts sufficient for seheme
requirements (Yes / No).
6. Making & breaking capacity of
contacts.
7. Descriptive leaflet number submitted.
XVII. DISTANCE RELAYS.
1. Make.
2. Type of relay.
3. Type of distance measuring elements.
4. Details of starting units and their

Switching sequence, if applicable.


5. Range of settings (in secondary
ohms).
for Zone-I, Zone-2 & Zone-3.
6. Operating times:
i) First zone timing. Max. 40m sec. upto
breaker at 50% of
zone-I reach for
SIR 0.01-4
ii) Second zone time setting
adjustable between---secs to --- 0-3 Sec.
secs.
iii) Third zone time setting
adjustable between -------- secs 0-5 Sec.
to ------- secs.
7, Contacts rating:
i) First Zone.
ii) Second Zone.
iii) Third Zone.
8. VA burden :
i) Current circuit of the scheme.
ii) Potential circuit of the scheme.
9 Is the VA burden at Sr.No.8 above is
continuous ? (yes/No)
10. Operating time versus ZS/ZL curves
of the distance scheme.
11. Descriptive leaflet no. submitted.
CONTROL AND RELAY PANELS
XVIII. CHECK SYNCHRONIZING RELAY:
1. Make.
2. Type.
3. Rating ( V, ac ) 63.5 V
4. Aux. Voltage ( V, dc ) 220 V
5. Permissible voltage difference (%) 10% max.
6. Permissible phase angle difference 350 max.
(degree)
7. Response time of relay (without <200m sec.
timer)( m Sec )
XIX. AUTO RECLOSING :
1. Make.
2. Type.
3. Multi shot or single shot. Single shot
4. Rating (V, dc) 220 V
5. Suitable for 1 & 3 phase. Yes
6. Dead time setting range (Sec.) 0.1-2 sec.
7. Reclaim time setting range (sec.) 5-300 sec.
8. Four position selector switch Yes
provided.
9. Alarm contacts provided for
`Auto-reclosed',
`Reclosure unsuccessful'.
XX. SYNCHRONISING SWITCH :
1. Make.
2. Type.
3. Contact rating.
4. No. of position. 3
5. No. of contacts. As per scheme
requirement
6. Removable handle type ? Yes/No Yes
XXI. BUS-BAR PROTECTION
1. Make.
2. Type.
3. Applicable standard.
4. Rated Voltage/Frequency. 110VAC, 50Hz, 220V
DC
5. Operating time (maximum). 15m sec. at 5 times
setting
6. Resetting time (maximum).
7. Does the offer meet the Yes/No
requirements of technical
specification?
CURRENT TRANSFORMERS
Sr. Description 245KV
No. Required Offered
1. Manufacturer's Name

2. Type/Installation.
3. Conforming to standard. IS:2705
4. Rated voltage. 220kV
5. Rated frequency. 50 Hz
6. Detail of cores. As per annexures attached
with Tech. Specification
*Core No. I II III IV V
6.1 Purpose of cores.
6.2 Rated Secondary Current.
6.3 Class of accuracy.
6.4 Accuracy limit factor.
6.5 Formula governing minimum
knee point voltage at CT
Secondary resistance corrected
to 75 C.
6.6 Instrument security factor.
6.7 Secondary limiting voltage.
6.8 Maximum Secondary resistance
corrected to 75 C.
6.9 Rated burden.
6.10 Exciting current
for Distance protection
core at Vk, for Bus
Bar protection core & REF Core at
Vk/2. and for differential protection
Core at Vk/4
* No. of cores as per applicability for
a particular type of current
7. Rated primary current. As per annexures attached
with Tech. Specification
8. Rated short time withstand 40
current (kA rms) for
1 second duration.
9. Rated dynamic withstand 100
current (kA peak).
10. Rated continuous thermal current (pu). 1.25
11. One minute power
frequency withstand
voltage (kV rms)
a) Dry 460
70 for 220kV NCT
b) Wet 460
70 for 220kV NCT
CURRENT TRANSFORMERS
12. 1.2/50 micro-second 1050
impulse withstand voltage (kV peak) 170 for 220kV NCT
13. One minute power 3
frequency withstand
voltage of secondary
winding (kV rms)
14. Minimum creepage
distance (mm) 900 for 220V NCT
15. Maximum creepage factor. 4 for 220kV NCT
16. Winding
a) No. of primary turns
b) Primary amp. turns
(Dynamic condition)
c) Current density
d) Area of Cross-section & material
i) Primary turns
ii) Secondary turns

17. I.S. to which the oil conforms. IS 335


18. Weight of oil (kg).
19. Quantity of oil (Ltrs)
20. Total weight (kg).
21. Maximum shipping weight (kg)
22. Overall dimension.
23. Mounting details.
24. Maximum permissible
temperature rise of
winding when referred
to maximum ambient
temperature of 50 C
in terms of clause 7.2
(Table 2 of IS:2705
Part-1-1992 ) or
Equivalent IEC
CURRENT TRANSFORMERS
Sr. Description 72.5KV
No. Required Offered
1. Manufacturer's Name

2. Type/Installation.
3. Conforming to standard. IS:2705
4. Rated voltage. 66kV
5. Rated frequency. 50 Hz
6. Detail of cores. As per annexures attached
with Tech. Specification
*Core No. I II III IV V
6.1 Purpose of cores.
6.2 Rated Secondary Current.
6.3 Class of accuracy.
6.4 Accuracy limit factor.
6.5 Formula governing minimum
knee point voltage at CT
Secondary resistance corrected
to 75 C.
6.6 Instrument security factor.
6.7 Secondary limiting voltage.
6.8 Maximum Secondary resistance
corrected to 75 C.
6.9 Rated burden.
6.10 Exciting current
for Distance protection
core at Vk, for Bus
Bar protection core & REF Core at
Vk/2. and for differential protection
Core at Vk/4
* No. of cores as per applicability for
a particular type of current
7. Rated primary current. As per annexures attached
with Tech. Specification
8. Rated short time withstand 31.5
current (kA rms) for
1 second duration.
9. Rated dynamic withstand 78.75
current (kA peak).
10. Rated continuous thermal current (pu). 1.25
11. One minute power
frequency withstand
voltage (kV rms)
a) Dry 140
38 for 72.5kV NCT
b) Wet 140
38 for 72.5kV NCT
CURRENT TRANSFORMERS
12. 1.2/50 micro-second 325
impulse withstand voltage (kV peak) 95 for 72.5kV NCT
13. One minute power 3
frequency withstand
voltage of secondary
winding (kV rms)
14. Minimum creepage
distance (mm) 1815 for 72.5kV CT & 440
for 72.5kV NCT
15. Maximum creepage factor. 4
16. Winding
a) No. of primary turns
b) Primary amp. turns
(Dynamic condition)
c) Current density
d) Area of Cross-section & material
i) Primary turns
ii) Secondary turns

17. I.S. to which the oil conforms. IS 335


18. Weight of oil (kg).
19. Quantity of oil (Ltrs)
20. Total weight (kg).
21. Maximum shipping weight (kg)
22. Overall dimension.
23. Mounting details.
24. Maximum permissible
temperature rise of
winding when referred
to maximum ambient
temperature of 50 C
in terms of clause 7.2
(Table 2 of IS:2705
Part-1-1992 ) or
Equivalent IEC
CAPACITIVE VOLTAGE TRANSFORMER
Sr. No. Description 245KV
Required Offered
1. Name of manufacturer

2. Type and model

3. Rated voltage (kV) 220

4. Capacitance :
a) Primary capacitance C1 (pf)
b) Secondary capacitance C2 (pf)
c) Equivalent capacitance C (pf) 8800+10%-5%

5. Number of secondary windings 2

6. Rated secondary windings :


a) Winding-I (volts) 110/√3
b) Winding -II (volts) 110/√3
c) Winding-III (Volts) -
7. Rated secondary burden:
a) Winding - I (VA) 100
b) Winding - II (VA) 50
c) Winding - III (VA) -
8. Accuracy class of each secondary :
a) Winding -I (VA) 1/3P
b) Winding - II (VA) 3P
c) Winding - III (VA) -
9. Rated voltage factor with rated burden. 1.2 continuous & 1.5 for
30 seconds

10. One minute power frequency withstand: 460


Test (Dry) voltage (kV rms)

11. One minute power frequency withstand test 460


(wet) voltage (kV rms)

12. 1.2/50 micro second impulse wave withstand 1050


test voltage (kV p)

13. One minute power frequency withstand voltage 3


on secondaries (kV rms)
CAPACITIVE VOLTAGE TRANSFORMER
14 Total creepage distance (mm) 6125 min.
14. Creepage factor (mm) 4 max.
15. Is CVT suitable for carrier Yes
frequency in the range of 40 to 500 KHz?
(Yes/No)
16. Natural frequency of coupling capacitors >500k Hz
17. Rated Primary
burden of potential devices (VA)
18. Temperature rise at 1.2 times rated voltage with
rated burden (°C)

19. Guaranteed value of temp. coefficient.


(percent per °Ce
20. Guaranteed value of radio interference voltage
in micro-volts at different voltages.

21. Guaranteed sealing test. The pressure at


which sealing test is to be carried out.
22. Guaranteed value of the H.F capacitances and 8800+50%-20%
equivalent series resistance at different.
23. Value of stray capacitance and stray conductance
in the carrier frequency range of 40 to 500 KHz.

24. Weight of oil and the standard to which it conforms IS 335


i) In capacitor unit (Kg/IS)
ii) In measuring unit. (Kg/IS)
25. Total weight (Kg)
26. Over -all dimensions (mm)
27. Mounting flange dimensional details
28. Whether CVT are suitable for Yes
Carrier communication,
carrier protection,
carrier telemetering and
carrier teleprinting services,
metering, relaying protection,
synchronising and interlocking purposes.
29. Do the CVTs contain built in Yes
(Yes/No) compensating reactors and damping
device in P.T. portion?
CAPACITIVE VOLTAGE TRANSFORMER
Sr. No. Description 72.5KV
Required Offered
13. Name of manufacturer

14. Type and model

15. Rated voltage (kV) 66

16. Capacitance :
a) Primary capacitance C1 (pf)
b) Secondary capacitance C2 (pf)
c) Equivalent capacitance C (pf) 8800+10%-5%

17. Number of secondary windings 1

18. Rated secondary windings :


a) Winding-I (volts) 110/√3
b) Winding -II (volts) -
c) Winding-III (Volts) -
19. Rated secondary burden:
a) Winding - I (VA) 50
b) Winding - II (VA) -
c) Winding - III (VA) -
20. Accuracy class of each secondary :
a) Winding -I (VA) 1/3P
b) Winding - II (VA) -
c) Winding - III (VA) -
21. Rated voltage factor with rated burden. 1.2 continuous & 1.5 for
30 seconds

22. One minute power frequency withstand: 140


Test (Dry) voltage (kV rms)

23. One minute power frequency withstand test 140


(wet) voltage (kV rms)

24. 1.2/50 micro second impulse wave withstand 325


test voltage (kV p)

13. One minute power frequency withstand voltage 3


on secondaries (kV rms)
CAPACITIVE VOLTAGE TRANSFORMER
14 Total creepage distance (mm) 1815 min.
30. Creepage factor (mm) 4 max.
31. Is CVT suitable for carrier Yes
frequency in the range of 40 to 500 KHz?
(Yes/No)
32. Natural frequency of coupling capacitors >500k Hz
33. Rated Primary
burden of potential devices (VA)
34. Temperature rise at 1.2 times rated voltage with
rated burden (°C)

35. Guaranteed value of temp. coefficient.


(percent per °Ce
36. Guaranteed value of radio interference voltage
in micro-volts at different voltages.

37. Guaranteed sealing test. The pressure at


which sealing test is to be carried out.
38. Guaranteed value of the H.F capacitances and 8800+50%-20%
equivalent series resistance at different.
39. Value of stray capacitance and stray conductance
in the carrier frequency range of 40 to 500 KHz.

40. Weight of oil and the standard to which it conforms IS 335


iii) In capacitor unit (Kg/IS)
iv) In measuring unit. (Kg/IS)
41. Total weight (Kg)
42. Over -all dimensions (mm)
43. Mounting flange dimensional details
44. Whether CVT are suitable for Yes
Carrier communication,
carrier protection,
carrier telemetering and
carrier teleprinting services,
metering, relaying protection,
synchronising and interlocking purposes.
45. Do the CVTs contain built in Yes
(Yes/No) compensating reactors and damping
device in P.T. portion?
POTENTIAL TRANSFORMER
Sr. Description 245KV
No. Required Offered
1. Manufacturer's type and designation.

2. Type

3. Rated Frequency 50 Hz

4. Rated primary voltage 220 kV

5. Number of secondary windings 2

6. Rated secondary windings :


a) Winding-I 110/√3V
b) Winding -II 110√3V
c) Winding -III -

7. Class of Accuracy.
a) Winding - I 1/3P
b) Winding - II 3P
c) Winding -III -

8. Limits of errors.
a) Winding -I
i) Percentage voltage ratio error
ii) Phase displacement. (Minutes)
b) Winding - II
i) Percentage voltage ratio error
ii) Phase displacement (minutes)
c) Winding - III
i) Percentage voltage ratio error
iii) Phase displacement (minutes)

9. Rated burden.
a) Winding - I 150 VA
b) Winding -II 50 VA
c) Winding-III -

10. Rated voltage factor and time 1.2 Continuous & 1.5 for 30
Sec.
POTENTIAL TRANSFORMER
11. Temperature rise at 1.2 times rated
voltage when applied continuously with
rated burden (°C)

12. Insulation class of


a) Primary windings
b) Secondary windings

13. One minute power frequency: 460


(Dry) withstand Test voltage (kV)

14. One minute power frequency (wet) 460


withstand test voltage (kV)

15. 1.2/50 micro second impulse withstand 1050


test voltage (kV peak)

16. One minute power frequency withstand 3


voltage on secondaries (KV rms)

17. a) Creepage distance. -


a) Creepage factor -
18. Standard to which the equipment conforms

19. Standard to which the oil conforms IS335

20. Total weight of the P.T.

21. Overall dimensions

22. Mounting details

23. Weight of the oil

24. Total shipping weight.


GTP OF 200 KVA 11/0.4 KV LT T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 Manufacturer's Name & Address

2 Service Outdoor

3 Rated Voltage :

(a) HV Winding 11 kV

(b) LV Winding 0.433 kV

4 Rated frequency 50Hz

5 Number of phase 3

6 Connections :

(a) HV Winding Delta

(b) LV Winding Star neutral broughtout

7 Connection symbol Dyn-11

8 Type of cooling ONAN

9 Rating available at different cooling 200 kVA


(if any) in %

10 Tap changing equipment

(a) Manufacturer

(b) Type Off circuit tap changer

(c) No. of steps (+)3% to (-)3%


11 Guaranteed positive sequence
impedance at 75°C with 100%
rating at
(a) Principal tap 4.5%

(b) Maximum tap


GTP OF 200 KVA 11/0.4 KV LT T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

(c) Minimum tap

12 Temperature rise over an ambient


of 50°C

(a) Top oil (if applicable) °C 0


40 C

(b) Windings (by resistance 0


50 C
measurement method) °C

13 Guaranteed losses at rated voltage


on principal tap at rated freequency

(a) No load loss or iron loss 0.4 KW

(b) Copper loss at full load at 75°C 3.135 KW

14 Withstand time for three phase


short circuit at terminals (secs.)

15 No load current at rated Voltage 2% of full load current


and rated frequency (max)

16 Insulation level

(a) Separate source power frequency


voltage withstand

(i) HV Winding 28kV

(ii) LV Winding 3kV

(b) Induced over voltage withstanding

(i) HV Winding

(ii) LV Winding
GTP OF 200 KVA 11/0.4 KV LT T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

(c) Full wave lightning impulse


withstanding

(i) HV Winding 75 kV

(ii) LV Winding -

17 Regulation at full load at 75°C

(a) At unity power factor

(b) At 0.8 power factor

18 Terminal arrangement

(a) High voltage

(b) Low voltage

(c) LV Neutral

19 Bushings

(a) High Voltage

(i) Manufacturer

(ii) Type Porcelain

(iii) Minimum Creepage distance 300mm

(b) Low Voltage

(i) Manufacturer

(ii) Type Porcelain

(iii) Minimum Creepage distance 25mm

(c) LV Neutral

(i) Manufacturer

(ii) Type Porcelain

(iii) Minimum creepage distance 25mm


GTP OF 200 KVA 11/0.4 KV LT T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

20 Total quantity of oil (litres) required


for
first filling (wherever applicable)

21 Is vacuum filling required if so,


stated
absolute pressure

22 Efficiency at 75°C at unit power


factor.

(a) At full load

(b) At 3/4 full load

(c) At 1/2 full load

23 Approximate dimensions

(a) Tank enclosure LxBxH

(b) Overall LxBxH

24 Untanking height

25 Approximate Weight

(a) Core and winding

(b) Tank fittings

(c) Oil (if applicable)

(d) Total Weight

26 Despatch details

(a) Approximate mass of heaviest


package

(b) Approximate dimensions of largest


package
GTP OF 200 KVA 11/0.4 KV LT T/F
S. NO. DESCRIPTION PARTICULARS
Required Offered

(i) Length

(ii) Breadth

(iii) Height

27 Reference Standards IS:2026


GUARANTEED TECHNICAL PARTICULARS FOR 11 kV, 3Cx50 mm sq XLPE CABLE.
Sr. No. Descritption Particulars
Required Offered
1 Name of manufacturer Nigam requirement
2 Type of cable A2XFY
3 Voltage rating 11kV Earth system
4 Applicable standard IS: 7098 (pt-II) 1985, IS: 8130/84 with
up to date amendment
5 Conductor
a. Material EC Grade Aluminium of H2/H4 Grade
Aluminium as per IS: 8130/84

b. No & Nom Cross 3Cx50 mm2


sectional area
c. Minimum no. of wires in 6
each Core
d. Dia. Of each wire in Core In IS: 8130/84 latest only Min. No of
wire are specified and hence not
applicable.
e. Shape Stranded Compacted circular
6 Conductor screen
a. Material Semi conducting material
b. Thickness (mm) Min 0.3
7 Insulation
a. Material Cross linked polyethylene IS-7098 (2)
1985
b. Nom. Thickness 3.6 ( shall not be less than 3.6- 0.1
(mm)Nom mm +0.1*3.6)
8 Insulation screen
a. Non metallic part
i. Material Semi conducting compound
ii. Thickness (mm) min 0.3
b. Metallic part
I Material Copper tape
Ii Thickness (mm) min 0.045
9 Core Identification By coloured strips as per CI: 13.of
7098/85
10 Inner Sheath
a. Material PVC compound
b. Minimum thickness mm 0.5
11 Armour
a. Material GI strip as per IS: 3975/84
b. Nom. Thickness of strip 4.0mm +/-10% x 0.8mm +/-10%
12 Outer Sheath
a. Material PVC compound
i) Thickness (mm) Min 1.88
13 Approx. overall dia. of 48+/-2mm
cable mm
14 Standard packing length 500+/-5% Metre
15 Approx. weight of cable --
kg./ KM.
Sr. No. Descritption Particulars
Required Offered
16 Min Bending Radius 15 times the overall dia of the cable
17 Maximum D.C. resistance
of conductor ohm/Km

18 Approx. reactance at 50
Hz ohm/KM
19 Approx. A.C. resistance of
conductor at Maximum
operating temp. ohm/Km

20 Approx. capacitance per


phase mf/Km
21 Continuous current
carrying capacity under
standard conditions
a. In air at 400 C
b. In ground sat 300 C
c. In duct at 300 C
22 Maximum permissible
conductor temperature
a. At rated current
b. At short circuit condition
23 Short circuit rating of
conductor
GTP OF 220 V CHARGER
S. NO. DESCRIPTION PARTICULARS
Required Offered
220V BATTERY CHARGER
1 Manufacturer’s Name & country of
manufacture

2 Whether requirements of Charger Yes


manufacturer's
furnished

3 Charger dimensions

I. Height (mm)

II. Depth (mm)

III. Width (mm)

IV. Sheet thickness (mm) 2mm

4 Charger weight (Kg)

5 Charger rated output Current

a. Float charging mode

b. Boost charging mode 50 to 100%

6 Load limiter current setting range (Trickle


mode)

7 Automatic voltage regulator (Float Mode):

I. Type

II. Percentage stabilisation of the output DC 0 to full load DC Load


Voltage variation

III. Voltage setting range

IV. Response time of automatic voltage


Regulator

8 Manual voltage regulator (Float mode):

I. Type

II. Voltage setting range

9 Boost charging current setting range

10 Boost charging limit setting range


GTP OF 220 V CHARGER
S. NO. DESCRIPTION PARTICULARS
Required Offered
220V BATTERY CHARGER
11 Rectifier assembly:

I. Type of semiconductor material

II. Rated direct current percell

III. Rated direct voltage

IV. Rated input voltage

V. Type of connections of rectifier elements Fully/half controlled


bridge type

VI. Standard applicable IS:4540

12 Rectifier transformer:

I. Type Dry- Aircooled of class


F Insulation type

II. Rated KVA & % impedance As required

III. Input line winding connection in vector


representation

IV. Cell winding connection in vector


representation

V. One minute power frequency withstand


voltage (KV)

VI. Standard applicable IS 2026/IS 4540

13 Instruments:

I. Type Flush Type dust proof


and moisture resistant

II. DC Voltmeter range

III. DC Ammeter range


GTP OF 220 V CHARGER
S. NO. DESCRIPTION PARTICULARS
Required Offered
220V BATTERY CHARGER
IV. Dial size

V. Accuracy class as per IS 15

14 Contactor:

I. Type

II. Rated voltage

III. Rated current

IV. No.of power contacts

V. No., type and rating of aux. contacts

VI. Operating coil voltage

VII. Drop out voltage

15 Thermal Overload relay:

I. Tripping current range

II. Whether single phasing protection


provided

III. Standard applicable

16 Air Break Switches

I. Type Air Break Type

II. Rated voltage 500 V AC/250 V DC

III. Rated current

IV. Type and material of contacts

V. Standard applicable

17 Fuses:

I. Type HRC-Link Type

II. Rupturing capaity

III. Standard applicable


GTP OF 200V 48V BATTERY
SR.NO. DESCRIPTION PARTICULARS
Required Offered
220 V, 200AH 48V, 300 AH 220 V, 200AH 48V, 300 AH
1 Manufacturer's name and
country of manufacturer
2 Whether requirements of Battery
manufacturer's furnished

3 Guaranteed AH. Capacity at ten 200 AH 300 AH


hours discharge rate to 1.75
volts per cell at 27°C
4 AH Capacity at one hour >90% >90%
discharge rate to1.75 volts per
cell at 27°C
5 Cell designation in accordance Yes Yes
with Indian Standards
6 Applicable Indian Standards IS: 15549 IS: 15549
7 Average life in years (min) 20 Years 20 Years
8 Recommended range of float
charging voltage/
Boost Charging voltage
9 Boost charging current
10 Open circuit voltage of cell when
completely discharged at 27Deg
C
a.) At ten hours discharge rate 1.75V/cell 1.75V/cell
b.) At one hour discharge rate
11 Type of construction of positive Flat pasted Flat pasted
pates
12 Type of construction of negative heavy heavy
plates duty,durable flat duty,durable
plate using lead flat plate
alloy pasted using lead
semi radial alloy pasted
squarish grid. semi radial
squarish grid.

13 Containers
a. Type Sealed Sealed
b. Material
14 Sediment space (mm)
15 Cell dimensions (mm)
16 Recommended cell centres
distance (mm)
17 Amount and specificgravity of
electrolyte per cell require for
first filling at 27°C
18 Specific gravity of electrolyte
when fully charged at 27°C
GTP OF 200V 48V BATTERY
SR.NO. DESCRIPTION PARTICULARS
Required Offered
220 V, 200AH 48V, 300 AH 220 V, 200AH 48V, 300 AH
19 Maximum electrolyte
temperature that cell can
withstand continuously without
injurious effects.
20 Battery Racks
a. Type of material Metalic Stand Metalic Stand
with two coats with two
of acid resistant coats of acid
paint resistant paint

b. Outline dimensions (mm)


c. Whether anti-acid coating Yes Yes
provided
d. Net weight (kg)
21 Insulators material (for racks Polypropylene Polypropylen
and cells) e
22 Weight per cell
a. Net dry weight (Kg)
b. With electrolyte (Kg)
23 Total shipping weight of acid for
one battery unit(Kg)
24 Total shipping weight of one
battery unit (without electrolyte)
25 Short circuit current at Battery
terminals
26 Time for which the battery can
withstand short circuit at
terminals
27 Internal resistance of each cell
I. Full charged condition
II. Fully discharged condition
28 Recommended air charges per
hour
BATTERY CHARGER FOR 48 V BATTERY CHARGER
S. NO. DESCRIPTION PARTICULARS

Required Offered

A Battery Charging equipment


I Rectifier Assemblies and Equipment

1 Manufacturer's name & trade mark of


bridge rectifier
for battery
a) Float charger
b) Boost charger

2 Rated voltage (D.C)


a) Float charger
b) Boost charger

3 Rated direct current


a) Float charger
b) Boost charger

4 Rated input voltage


a) Float charger 165V to 260V AC
b) Boost charger

5 Rated input current per phase


a) Float charger
b) Boost charger

6 Boost charger A.C component of D.C


side
i.e repple contents
a) Float charger
b) Boost charger

7 Max power draw KVA & KW


a) Float charger
b) Boost charger

8 Efficiency
a) Float charger
b) Boost charger
9 A.C.input current power factor
a) Float charger
b) Boost charger

10 Voltage variation (DC voltage)/current


characteristic
to be attached with the tender
a) Float charger
b) Boost charger

11 Type of protection (over current


protection/over
voltage protection)
a) Float charger
b) Boost charger

12 Euipment resistance
a) Float charger
b) Boost charger

II Rectifier Transformer & chokes etc.

1 Type, make & capacity/rating


a) Float charger

b) Boost charger

2 Rated voltage line winding


a) Float charger
b) Boost charger

3 Rated voltage cell winding


a) Float charger
b) Boost charger

4 Rated current on line side


a) Float charger
b) Boost charger
5 Rated current on cell side
a) Float charger
b) Boost charger

6 Resistive D.C voltage


a) Float charger
b) Boost charger

7 Inductive D.C voltage drop


a) Float charger
b) Boost charger

8 Temperature rise
a) Float charger
b) Boost charger

III Rectifier cell/Stack

1 Average/forward current of device


a) Float charger
b) Boost charger

2 Forward over load current


a) Float charger
b) Boost charger

3 Reverse voltage
a) Float charger
b) Boost charger

4 Cell temperature
a) Float charger
b) Boost charger

5 Temperature rise
a) Float charger
b) Boost charger

6 Forward voltage drop


a) Float charger
b) Boost charger

IV Charger cabinet/cubicle

1 Size of steel sheet for charger cabinet


2 Colour shade of the charger cubicle

3 Dimensions (L*B*H)

4 Height of the lowest mounted equpment


of the panel
from ground level

V Other Data

1 Size of cable required for connection of


the charger
to the A.C incomming mains

2 Number & size of cable glands & cable


lugs

3 A.C mains input single phase to three


phase

4 Permissible plus & minus A.C mains


voltage &
freequency varriation.

5 Max. Temperature at which the 50 deg C


performance of the
equipment remains un-affected

6 Whether arrangement for automatic Yes


swicth ON and
switch OFF of float charger in the event
of failure or
restoration of mains supply, is provided
(this will be
in addition to manual operation)

7 List of major accessories provided Yes

8 Full details of arrangement made for Yes


alarm scheme for indicating any type of
mal-functioning in working of the
equipment
GTP of 415 V ACDB
Sr.No. Description Particulars
Required Offered
1. Standard: The specific standard to
which the switches are designed

2. Rating of switches
a) Number of phases 3
b) Service voltage 415V
c) Normal current
d) Frequency 50 HZ
e) Type of contacts Quick make and break type
f) Material of contacts of Cu with silver plating
switches and their plating
g) Clearance between
phases
h) Between live parts and
earth
3. Particulars of bus bar
a) Material
i) Phases High conductivity Cu or aluminum

ii) Neutral
b) Normal current rating
c) Area
i) Phases
ii) Neutral
d) Shape Rectangular
4. Bus bar chamber
a) Whether vermin proof. Yes
b) Thickness of sheet
c) M. S. angle size
5. Rupturing capacity of bus bar 2 MVA, 20KA at 415V
switchgear/cartridges
6. Temperature rise, under
continuous load in oC
7 Thickness of the sheet for
a) Main board
b) Metering chamber
GTP of 415 V ACDB
Sr.No. Description Particulars
Required Offered
8 Current density assumed for
current conducting components
9 Rated short circuit making capacity
of switches at 415 V in KA

10 Current transformer for metering


i) VA burden 15VA
ii) Accuracy class 1
iii) Instrument security factor

11 Make of
i) Switch boards
ii) Switches
iii) Selector switch
iv) HRC fuses
v) CTs
vi) KWH meter
vii) Voltmeter
viii) Ammeter
12 Details of type test supplied
13 Details of drawings supplied
14 List of references to which similar
switch fuse units have been in
service
GTP OF AAC TARANTULA CONDUCTOR
Sr No Description Particulars
Required Offered
1 Code Word AAC Tarantula Conductor
2 Maker’s name address and
country
a) Aluminum wire --
b) Complete Conductor ---
3 Stranding and wire Std Max Min Std Max Min
diameter.
Standard/Maximum/Minimu
m (mm)
a) Aluminum 37/5.23m 37/5.28m 37/5.18
m m mm
4 Standard nominal copper 484 sq mm.
area in sq mm.
5 Calculated equivalent 795.6 sq mm
aluminum area in sq mm.
6 Actual aluminum area in sq
mm.
7 Standard area of cross-
section in sq mm.
a) Aluminium strand
b) Conductor 795.6 sq mm

8 Diameter of complete 36.61 mm


conductor (in mm)
9 Minimum ultimate tensile
stress of Aluminum strand
in kg/ sq mm
10 Guaranteed breaking 11,600 Kg
tensile strength of
conductor in kg.
11 Minimum breaking load in 3.08 KN (314 KG)
Kg. for Aluminum strand
12 Purity of Aluminium rods in 99.50%
%
13 Maximum working tension

14 Weight in kg. Per km Approx.2198 Kg/Km

15 Max. Resistance in ohms


per km at 20o C
a) Aluminium strand 1.35
b) Conductor 0.03656
16 a) Continuous Max. Current As per ISS.
rating of conductor in still
air at 45o C ambient
temperature (Amps.)
b) Temperature rise for the As per ISS.
above current (o C)
GTP OF AAC TARANTULA CONDUCTOR
Sr No Description Particulars
Required Offered
17 Lay Ratio: Max. Min Max.
Aluminium 6 Wire layer 21 18
Aluminium 12 Wire layer 21 14
Aluminium 18 Wire layer 14 11.25
18 Whether the drum on which Yes
the conductor is wound
conforms to the
specification and whether
the detailed dimensioned
drawing submitted with the
tender.
19 Modulus of elasticity of 0.5976 x 106Kg/sq. cm
Aluminum strand

20 Co-efficient of linear 23x10-6


expansion of Aluminum
strand per degree
centigrade of
21 Standard length of each 0.500 Km
piece (km)
22 Maximum single length of Declared by Manufacturer for
conductor which can be reference
manufactured (km)

23 Tolerance, if any, on ± 5%
standard lengths
24 No. of standards length in One
one reel
25 Dimensions of the reel (in ------
cm)
26 Weight of the conductor in 1154 Kg (2198/2*+/- 5%)
one reel (in kg)

27 Weight of the reel (in kg) Declared by Manufacturer

28 Gross weight of the reel Sum of column 26 & 27


including weight of the
conductor (kg)
29 Standard according to ISS 398 Part I to V
which the conductor will be
manufactured and tested

30 Other particulars, if any If any to be furnished by


manufacturer
GTP OF CLAMPS AND CONNECTORS
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 Manufacturer’s Name and address

2 Applicable standards IS-5561-1970

3 Application Outdoor

4 Type Bolted type

5 For connection to

a) Conductor size and arrangement

b) Equipment terminal and arrangement

6 Material (state percentage composition of


constituents and impurities present)

a) Clamp body Al. alloy CR(A6) 4600, IS-617, 1975

b) Bolts and Nuts M.S. Hot dip Galv. IS-1367, 1979

c) Spring washers Spring steel - Electro Galv.

d) Liners, if any Cu./Al./2mm thick

7 Rated Current (A)

8 Maximum temperature rise over


temperature specified in project
current (°C)

9 Rated terminal load (kg) 110

10 Minimum thickness of any part(mm) 10mm

11 Weight of Clamp complete with hardware


GTP OF DC DISTRIBUTION BOARD
S. NO. DESCRIPTION PARTICULARS

Required Offered
a) Size of cable required for
connection of the battery
charger to the DC Distribution
Board.

b) Size of sheet steel(SWG)of the DC


distribution Board Cabinet
c) Make and type of instruments may be indicated as per details below
Make of DCDB

Sr. No. Description of Instruments Make Type Range / Capacity

1 Incoming Rotary Switch Rotary 200A

2 Voltmeter Moving Coil for DC 0-200 A


0-400 V

3 Ammeter As Above

4 Ammeter/Voltmeter for detecting Moving Coil 20-0-20 mA


earth leakage

5 Change over contactor Electro-mechanical 20 A

6 Outgoing feeder switches of rating Rotary 100 A,


50 A,10 A

7 H.R.C. fuses with fittings

Aluminium

b) Size of Main Bus Bar 25 X 6 mm

c) Size of Negative Bus Bar 25 X 6 mm


DISC INSULATOR/LONG ROD INSULATOR
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 Name of Manufacturer

2 Address of Manufacturer

3 Weight of single disc(kg)

4 Size and Designation of pin ball shank(mm)

5 Diameter of disc (mm)

6 Tolerence on Diameter (mm)

7 Ball to ball spacing


between disc (mm)

8 Tolerance on spacing (mm)

9 Minimum nominal creepage distance of single 25mm/KV


disc (mm)

10 Tolerance on creepage distance (mm)

11 Electromechanical Strength of disc (kN) 45-90-120

12 Material of Shell (Porcelain/Toughened glass) Porcelain (Fog type)

13 Power frequency flashover voltage of single disc

(a) Dry (kV rms) 28

(b) Wet (kV rms) 28

14 Power frequency withstand voltage of single disc

(a) Dry (kV rms) 28

(b) Wet (kV rms) 28

15 Power frequency puncture voltage of single disc 28


(kV rms)

16 Impulse flashover voltage of single disc (dry)

(a) Positive (kV peak) 75

(b) Negative kV peak 75


DISC INSULATOR/LONG ROD INSULATOR
S. NO. DESCRIPTION PARTICULARS
Required Offered

17 Impulse withstand voltage of single disc (dry)

(a) Positive (kV peak) 75

(b) Negative (kV peak) 75

18 Steepness of impulse voltage which the disc


insulators can withstand in steep wave front
test (kV/micro sec)

19 Visible discharge test of single disc (dry) (kV rms) 9

20 Maximum RIV at 1 MHz and 10 kV AC (rms) 50


voltage of single disc (micro V)

21 Purity of zinc used for galvanising (%) 99.95

22 No. of dips in standard preece test

(a) Socket 6

(b) Ball Pin 6

23 Axial and Radial run out (According to IEC)

(a) As per pointer A (mm)

(b) As per pointer B (mm)

24 Drawings enclosed
GTP OF EARTH WIRE
S. NO. DESCRIPTION PARTICULARS
Required Offered
7/3.66 mm EARTHWIRE

1 Name and Address of Manufacturer

2 PARTICULARS OF RAW MATERIALS

2.1 Steel Wires/Rods

(a) Carbon % Max. 0.55%

(b) Manganese % 0.40% to 0.90%

(c ) Phosphorous % Max.0.04%

(d) Sulphur % Max.0.04%

(e) Silicon % 0.15% to 0.35%

2.2 Zinc

(a) Minimum purity of zinc % 0.9995

3 STEEL STRANDS AFTER STRANDING

3.1 Diameter

(a) Nominal mm

(b) Maximum mm

(c ) Minimum mm

3.2 Minimum Breaking load of strand kN

3.3 Galvanising

(a) Minimum weight of zinc coating per Sq. gm


mtr of uncoated wire surface

(b) Minimum number of one minute dips Nos. 1minute=3 dips


that the galvanised strand can 1/2minute=1 dip
withstand in the standard preece test
GTP OF EARTH WIRE
S. NO. DESCRIPTION PARTICULARS
Required Offered
(c ) Min. Number of twists in a guage length Nos. 18
equal to 100 times dia of wire which the
strand can withstand in the torsion test

4 STRANDED EARTHWIRE

4.1 UTS of earthwire kN 68.4

4.2 Lay length of outer steel layer mm Std. 181mm


Max. 198mm
Min. 165mm

4.3 DC resistance of earyhwire at 20 deg.C ohm/km 2.5 Ohms/Km(Max.)

4.4 Standard length of earthwire m

4.5 Tolerance on Standard length m

4.6 Direction of lay of outer layer right hand

4.7 Linear mass of earthwire

(a) Nominal kg/km 583

(b) Maximum kg/km 595

(c ) Minimum kg/km 578

5 Drum is as per specification Yes


GTP OF INSULATOR HARDWARE
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 Manufacturer

2 Applicable Standards IS-2486 & IS-2633

3 Materials

a) Ferrous Parts Forged steel

b) Nuts & C14Bolts MS Hot Dip Galvanised

c) Cotter Pins Stainless steel/Brass

d) Split Pins Stainless steel/Brass

e) Strain and suspension clamps Aluminium Alloy-LM-6

4 Ultimate Strengths

a) Complete assembly (kg)

b) Suspension clamps (kg)

c) Strain clamp (kg)

d) D-Shackle (kg)

e) Ball eye (Kg)

f) Ball clevis (kg)

g) Clevis eye (Kg)

h) Socket eye (kg)

i) Socket clevis (Kg)

j) Yoke Plate (Kg)


GTP OF INSULATOR STRINGS
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 Manufacturer

b) Hardware

2 Type of String

a) Single/Double Single/Double

b) Suspension/Tension Suspension/Tension

3 Applicable Standards IS:2486

4 Type of Insulators

a) Ball & Socket/ other Ball & Socket

b) Normal / antifog Fog Type

5 Insulating Material Porcelain

6 No. of Units per String

7 Size of each unit

a) Diameter of disc (mm)

b) Spacing between Units (mm)

8 Weight

a) Each Disc (Kg)

b) Complete string (Kg)

9 Creepage Distance

a) Each Disc (mm) 25mm/KV

b) Complete String (mm)

10 Power Frequency Withstand Voltage

a) Each Disc

i) Dry (KV) 28KV rms


GTP OF INSULATOR STRINGS
S. NO. DESCRIPTION PARTICULARS
Required Offered

ii) Wet (KV) 28KV rms

b) Complete string

i) Dry (KV)

ii) Wet (KV)

11 Impulse Withstand Voltage

a) Each disc

I) Positive (kVp) 75

ii) Negative (kVp) 75

b) Complete Strings

I) Positive (kVp)

ii) Negative (kVp)

12 Power Frequency Puncture


Withstand Voltage of
each Disc (KV rms)

13 Electro Mechanical Strength of each


Disc (Kg)
GTP OF 1250A LINE TRAPS
S. NO. DESCRIPTION PARTICULARS
Required Offered

1 Name of manufacturer and country


2 Type, model and catalogue No.
3 Inductance of main coil in milli henry (mH) 1.0
4 Blocking capability in different ranges (resonant 50-500KHz
frequency range)
5 Minimum guaranteed resistive component over 570 Ohms
blocking range
6 Different tuning range offered
7 Variation in resonant frequency per degree centigrade Negligible
change in ambient temperature .
8 Variation in 50Hz impedance per degree centigrade Negligible
over varied in ambient temperature.

9 Detail of protection of capacitors and coil against Gapless/Gap type L.A.


voltage surges
10 Impedance at tuned frequency 570 Ohms
11 Change in impedance per degree centigrade variation Negligible
in ambient temperature
12 Material of main coil Aluminium
13 Attenuation in the tuned frequency band
14 Maximum tapping loss (insert a loss with a line 2.6dB
impedance of 400 ohms and 600 ohms).
15 System voltage rating in K.V 220
16 Continuous current rating in amp. at ambient 1250A
temperature 50 degree centigrade
17 Continuous current rating in amp. at ambient
temperature 65.5 degree centigrade
18 Maximum symmetrical short circuit current ratings for 31.5
one second duration in K.V.
19 Asymmetrical peak value of first half wave of rated 80.325 KAP
short time current.
20 Dynamic limiting current 80.325 KAP
21 Rated current and corresponding voltage 1250A/220 KV

22 Type of incoming and outgoing terminals Suitable for either


horizontal or vertical
take off
23 Type of mounting Suspension
GTP OF 1250A LINE TRAPS
S. NO. DESCRIPTION PARTICULARS
Required Offered

24 Maximum working stress if suspension mounted (2xMass of LT in Kg)


9.81+5000N
25 Ultimate tensile strength, if suspension mounted > CI 24

26 Class of insulation of line trap as per table-1 of IEC-353 F

27 Whether corona rings are provided

28 Whether bird barriers are provided Yes

29 Dimensions of the equipment.

i) Height

ii) Diameter

30 Net weight (APPROXIMATELY)

31 Gross weight (APPROXIMATELY)

32 Make and type of lightning arrestor Gapless/Gap type L.A.

33 Rated voltage of arrestor(protective device kV (rms) 11

34 Nominal discharge current for 8/20 μs wave impulse 10 KA

35 Discharge voltage at 10 kA 40 KVP

36 Minimum power frequency spark over voltage (peak) 18 KV for Gap type LA
kV
37 Maximum 1/50 as impulse spark over voltage (peak) 40 KV for Gap type LA
kV
38 Impulse withstand voltage of main coil and tuning unit. 60 KVP

39 Nominal discharge current of protective device 10 KA

40 Extinction potential of arrestor

41 Maximum residual discharge voltage for 8/20 ms


impulse.
a) at 5000 Amps 27 KVP

b) at 10000 Amps 30 KVP

42 Impulse current withstand value of L.A

a) Long duration As per IEC-99

b) High current. As per IEC-99

43 Residual voltage at 10 kA peak 30 KVP


GTP of COUPLING DEVICE
S. NO. DESCRIPTION Required Offered
1 Name of Manufacturer and address

2 Pass band range 35-500 KHz

3 Nominal peak envelope Power 650 Watt (min)

4 Primary impedance 600 Ohms

5 Secondary impedance 150 Ohms (Balanced)

6 Insulating level of isolating Transformer

a) Power Freq. withstand Voltage for 1 min. 5 kv (rms)

b) 1.2/50 micro sec impulse wave withstand Voltage 10 kv (Peak)

7 Arrester type and rating

i) Type Non-Linear

ii) Rated Voltage 1 KV

iii) Discharge Current 5 KA

8 Drainage Coil

Current carrying capacity at Power frequency:

a) Short time current for 0.2 sec. 50 A

b) Continuous Current 1A
GTP for HF CABLE
Sr. No. Description Particulars
Required Offered
1. Name of manufacturer
2. Type, designation and catalogue
No.
3. Characteristic impedance 150 Ohms +10%
4. Nominal capacitance / KM 34 pF

5. Attention per KM of H.F cable at 1.0 dB to 5.1 dB /km


various carrier Frequencies in
the range of 40 to 500 KHz
6. Conductor size and its material 1.40+0.03 mm Solid plan hard
drawn copper
7. Details of shielding and other Single braid, 0.2 mm tinned
coverings copper wire min. coverage 90%
8. Details of protective armouring GS Wiring braiding
provided Wire Dia- 0.3 mm
Min. Coverage-70%
9. One minute P.F. withstand 4 KV rms
voltage between conductor and
sheaths and between cores of
the Cable
10. Loop resistance per KM at 20 Max. 30 Ohms
deg C
11. Make up of H.F. cable
12. Overall diameter of the cable 20-25 mm
13. Minimum bending radius for 20xoverall dia. of cable
installation
14. Net weight /KM of cable 350 kg/km (approx)
15. Cable length / drum with 500 m + 5%
variation, if any
GTP OF POWER LINE CARRIER COMMUNICATION EQUIPEMENT

S. NO. DESCRIPTION PARTICULARS


Required Offered
1 A) Name of
Manufacturer & country
B) Place of Manufacturer

2 Type, designation, model


and catalogue No.
3 Type of Modulation Amplitude Modulation
4 Mode of transmission Single side band (SSB)
5 Carrier frequency range 40 KHz-500 KHz
6 Nominal carrier frequency 4 KHz
band
7 Carrier frequency accuracy Not more than + 10 Hz
from its nominal value.

8 Frequency difference Not more than 2 Hz


between a voice frequency
input (applied to transmit
end) of a pair of PLCC
terminals connected back to
back.
9 Max. H.F. amplifier output 40W
with single/multi tone keying
(peak envelope power).

10 Nominal carrier freq. Power 20W


(PEP) at the output of the
terminals at highest carrier
freq.
11 Loss in the line filters/H.F.
Hybrid at the highest carrier
frequency
12 Mean Carrier freq. Power
13 Ratio between peak Between 8.5 dB to 10 dB
envelope power and mean
power
14 Nominal impedance at the 600 Ohms
input (V. F. side) of carrier
terminals.
15 Nominal H.F. impedance at 150 Ohms balanced
the output of carrier
terminals
GTP OF POWER LINE CARRIER COMMUNICATION EQUIPEMENT

S. NO. DESCRIPTION PARTICULARS


Required Offered
16 Return loss within nominal Not more than 10 dB
carrier frequency band.
17 Effectively transmitted V. F. 300-3400 Hz
Band.
18 Return loss within VF Band. Not less than 14 dB

19 H.F. Oscillator details i.e.


type and its freq. Stability.
20 I.F. Oscillator details i.e.
type and its freq. Stability.
21 Automatic gain control For 40 dB change in carrier
(AGC) details frequency signal level within the
regulation range, change in VF
receive levels of both speech
and other signals shall be less
than 1dB
a) Range
b) Regulation
22 Level of spurious emission
at the
a) Edge of nominal - 10 dBm (max)
carrier band.
b) One band away from - 24 dBm (max)
nominal carrier freq. Band.

c) Twice band away from - 34 dBm (max)


nominal carrier freq. Band.

23 Relative level at V.F, 4-wire


terminal points.
a) Send leg 0 dBr to - 17dBr (-3.5 dBr)
b) Receive leg 8 dBr to - 3.5dBr (-3.5 dBr)
24 Relative level at V. F. 2-wire

a) Send leg 0 dBr


b) Receive leg -7dBr
GTP OF POWER LINE CARRIER COMMUNICATION EQUIPEMENT

S. NO. DESCRIPTION PARTICULARS


Required Offered
25 Permissible limits for As pe fig. 11 of IS: 9482:1996
variation of overall loss
(relative to 600 Hz) in
speech channel transmitted
over a pair of PLCC
terminals connected back to
back for 300-2400 kHz.
Effectively transmitted
speech frequency band.

26 Group delay distortion As pe fig. 12 of IS: 9482:1997


measured between 4-wire
transmit and 4-wire received-
point of a pair of
transmitting/receiving PLC
terminals.
27 H.F. sensitivity
28 Whether PLC terminal Yes
alongwith HF line filters are
tunable at site.
29 HF/IF send/receive filter
sensitivity.
30 Details of provision of Equalizers be provided
equalizers.
31 Whether HF hybrid is used
for speed band operation
also.
32 Whether HF receive/send
line filters have been
provided at the input of
receive leg and output of
send leg.
33 List of important jack test
points brought out on the
front of the panel.
34 Details of automatic
telephone switching unit,
provided in the PLC
terminal.
35 Details of modules in a set
of spares.
36 Noise performance
GTP OF POWER LINE CARRIER COMMUNICATION EQUIPEMENT

S. NO. DESCRIPTION PARTICULARS


Required Offered
a) Noise generated within the Shall not exceed -55 dBm
PLC terminal weighted
telephone noise level
measured at speech output
of a pair of PLC terminals.

b) Near end far end cross talk Shall not exceed -50 dBm
due to signal channel either
individually or collectively in
a pair of PLC terminals
without Compander.

c) Signal to noise ratio for Min. 25 dB


voice communication
referred to 1 Mw at relative
level of zero.
d) Minimum acceptable SNR 15 dB
for protection signaling at
the input or receiver.
e) Psophometric noise
contribution of a pair of PLC
terminals connected back to
back
f) Cross talk attenuation Not more than -50 dBm
between individual channels

37 Type of modulation and


frequency band for
telephone signaling
channels
38 Pulse distortion of telephone Shall not exceed 10%
signaling channels when
operated at a signaling
speed of 10 pulses per sec.
with mark to space ratio of
40/60 or 33-1/3/66-2/3 in a
pair of PLC terminals.
GTP OF POWER LINE CARRIER COMMUNICATION EQUIPEMENT

S. NO. DESCRIPTION PARTICULARS


Required Offered
39 The level between which the Limiter action starts between-
limiter action starts for any 3dB and 0dB for any sinusodial
frequency 300 Hz to 2400 signal of a frequency between
Hz. 300 Hz an the upper frequency
of the channel. The level of the
frequency signal shall not
exceed +3dB for an increase in
athe voice frequency input
signal to a level of +15 dB.

40 Distortion factor per 50% Less than -40 dBm


signal at 400 Hz with and
without compandor.
41 Whether Yes
compandor/Expander
provided.
42 The linearity as a function of
voice frequency input level
measuring set.
43 Details of meters provided
on test panel their range and
purpose.
44 Whether type test reports Yes
submitted with the bid.
45 D.C. supply requirement:
a) Voltage & permissible 48V DC+15%, -10%(Positive
variations pole earthed)
b) Maximum current
46 Voltage withstand Yes
capabilities
47 I} Dimension and weight of
cabinet
II) Whether steel cabinets
are suitable to
accommodate switching
units and protection
equipment’s also.
GTP OF PLCC-PROTECTION EQUIPMENT
S. NO. DESCRIPTION PARTICULARS
Required Offered
1 a) Name of manufacturer and country
b) Place of manufacture
2 Type, Designation, model & catalogues No.
3 Whether equipment works on frequency shift keying
4 Total no of protection commands which can be 4
5 Details of frequencies of codes used for various tripping
6 If guard frequency continuously transmitted/received and
7 a) Whether equipment is immune against tripping by
b) Arrangement employed in equipment for 7 (a)
8 a) Whether in the presence of spurious signal as well
b) Arrangement employed for 8(a) above.
9 a) Signal delay time with the V.F. protection signaling <20 msec for
b) Max. Guaranteed transmission time interval permissive
10 Unwanted action and missing action probabilities figures
11 Whether above probabilities adjustable at site.
12 Transmitter input requirements (contact rating)
a) Voltage 360V (Max)
b) Current 5A (Max)
c) Power 1200W/VA (Max)
13 Receiver output requirements
a) Voltage 250V
b) Current 0.1A
c) Power
d) Number of NO and NC contacts
e) Whether contacts position interchangeable from NO
14 Supervisory and alarm facilities
a) General alarm
b) Transmitter alarm
c) Receive alarm
d) Whether spare contacts available for providing
15 Battery supply input requirements
a) Voltage 48VDC
b) Current
c) Power

Вам также может понравиться