1.2 DEFINITIONS
AS2/08 F/ BILL 1 1
PRELIMINARIES & GENERAL CONDITIONS
1.3 PARTIES
1.4 ABBREVIATIONS
AS2/08 F/ BILL 1 2
PRELIMINARIES & GENERAL CONDITIONS
To
Collection :
a) Preliminaries
b) Building Works
c) Mechanical and Electrical Works
d) External Works
e) Equipment Installation Works
f) Provisional Sum
AS2/08 F/ BILL 1 3
PRELIMINARIES & GENERAL CONDITIONS
To
Collection:
The Contractor shall at his own cost, provide, form, fix and
maintain as and when directed by the S.O. such pumps, chutes,
walls, drains, bunds, silt traps and other temporary work such as
temporary round culverts necessary for the proper drainage of the
site so that no flooding or other damage or disturbance is caused
to areas surrounding the works or to the works throughout the
duration of the contract.
The Contractor shall construct wash trough at all exits from site.
All vehicles leaving the site shall be thoroughly cleaned by high-
pressure water jets. The Contract sum shall be deemed to include
for compliance with this sub-section.
To Collection :
2.5 DIMENSION
2.6 DRAWINGS
AS2/08 F/ BILL 1 5
PRELIMINARIES & GENERAL CONDITIONS
To
Collection:
Clauses Description
1. Definitions and Interpretation
2. Duties of S.O. and S.O.’s Representatives.
3. S.O.’s Right to Take Action.
4. Scope of Contract
5. S.O.’s Instructions.
5.i The Contractor’s attention is here drawn to the
requirements of this clause for S.O.’s instruction to be in
writing and/or subsequent confirmation in writing of oral
instruction issued.
6. Notices
7. Contract Documents
8. Sufficiency of Contract Documents
AS2/08 F/ BILL 1 6
PRELIMINARIES & GENERAL CONDITIONS
To Collection:
To
Collection:
Period of Insurance:
Amount of Guarantee
AS2/08 F/ BILL 1 8
PRELIMINARIES & GENERAL CONDITIONS
To Collection :
AS2/08 F/ BILL 1 9
PRELIMINARIES & GENERAL CONDITIONS
To
Collection:
AS2/08 F/ BILL 1 10
PRELIMINARIES & GENERAL CONDITIONS
iii. Establish bench marks approved by the S.O. and must be tied
up to an existing Government bench mark.
vi. Allow for providing theodolites, level and such like instruments
and attendance for the S.O. in checking of levels and setting
out of the Works throughout the contract period.
vii. Any assistance given by the S.O. in setting out will not relieve
the Contractor of his responsibility to set out the Works
accurately
To Collection :
I. All persons authorised by the S.O. shall have access to the site
at all times.
AS2/08 F/ BILL 1 11
PRELIMINARIES & GENERAL CONDITIONS
Provide all necessary exact and legible documents to all firms where it
is proposed to sub-let any portion of the work. Submit for approval a
list of firms he proposes to employ as Sub-Contractors for trade of
Specialist items
To Collection :
AS2/08 F/ BILL 1 12
PRELIMINARIES & GENERAL CONDITIONS
To Collection:
AS2/08 F/ BILL 1 13
PRELIMINARIES & GENERAL CONDITIONS
To
Collection :
AS2/08 F/ BILL 1 14
PRELIMINARIES & GENERAL CONDITIONS
AS2/08 F/ BILL 1 15
PRELIMINARIES & GENERAL CONDITIONS
To Collection:
AS2/08 F/ BILL 1 16
PRELIMINARIES & GENERAL CONDITIONS
To Collection:
J. NOTES TO CLAUSE 36
Insurance of works
AS2/08 F/ BILL 1 17
PRELIMINARIES & GENERAL CONDITIONS
To
Collection:
To
Collection:
AS2/08 F/ BILL 1 19
PRELIMINARIES & GENERAL CONDITIONS
The Contractor shall bear all overtime supervision cost that may be
incurred by the Employer due to such working outside normal
working hours.
Protect, uphold and maintain all pipes, ducts, sewers, cables and
other services that are found within the site during the execution
of the Works unless they are earmarked for demolition or diversion
in the Contract Bills.
To Collection:
AS2/08 F/ BILL 1 20
PRELIMINARIES & GENERAL CONDITIONS
3.4 ADVERTISING
To Collection:
AS2/08 F/ BILL 1 21
PRELIMINARIES & GENERAL CONDITIONS
Before commencement of the work, ten (10) views of the site are
to be taken and submitted to the S.O. for distribution as required.
The Contractor shall also provide the necessary albums for safe
keeping of the progress photographs and to produce receipts of
payment for reimbursement.
To
Collection :
Provide for all and off site management and supervision including
Site Engineers and all necessary clerical and supporting personnel.
AS2/08 F/ BILL 1 22
PRELIMINARIES & GENERAL CONDITIONS
Provide all necessary plant for the proper execution of the works
such as:
Provide the S.O. from time to time with up-to-date lists of all the
mechanical plant on site.
The Contractor shall maintain the plant during the currency of the
Contract and remove at the completion of the works. All plant and
machinery shall not be removed from the site without the consent
in writing of the S.O. which shall not be unreasonably withheld.
4.5 LABOUR-ON-COSTS
To Collection:
Provide first aid kits at suitable locations on the Site and instruct
an adequate number of persons in their use.
The Bills of Quantities are not to be used as the basis for ordering
any material.
If the Contractor fails for any reason to supply any material which
he had contracted to supply or if he fails to supply any such
material in sufficient time to enable the contract to be completed
by the agreed date for completion then in either event the
Employer may supply any portion, or all of such material. If the
Employer supplies such material the cost in respect thereof to be
borne by the Contractor shall be:
Either
the current market rates
Or
the actual cost to the Employer at the date of supply, including
overhead and any other charges,
To Collection:
AS2/08 F/ BILL 1 24
PRELIMINARIES & GENERAL CONDITIONS
5.0 SAMPLES
Submit samples of materials and goods to the S.O. and obtain his
written approval before ordering in bulk.
The approved samples shall be kept by the S.O. who shall reject all
such materials and goods and condemn such workmanship that
does not correspond with the approved samples.
Provide all necessary water for use in Works by tapping from the
JBA water main. It shall be clean, fresh and fit for drinking.
Provide all temporary connections, pipes, fittings, storage tanks,
meters, etc., including liaising with the Local Authorities and clear
away and make good on completion and pay all costs and charges
in connection therewith.
Waste and debris arising from the Works are to be sprinkled with
water to prevent dust arising and all proper screens, dustsheets
etc. shall be provided.
AS2/08 F/ BILL 1 25
PRELIMINARIES & GENERAL CONDITIONS
AS2/08 F/ BILL 1 26
PRELIMINARIES & GENERAL CONDITIONS
To Collection:
Alter, shift and adapt all temporary structures from time to time as
necessary and remove on completion. Make good all areas
disturbed including reinstatement to original condition after
removal of temporary buildings and facilities.
AS2/08 F/ BILL 1 27
PRELIMINARIES & GENERAL CONDITIONS
To
Collection:
ii) Remove all paint spots from floors, walls, hardware, glass, etc.;
iii) Clean and polish all glass, glazed tiles and stainless steel
surfaces;
viii) Wash, clean, dry and polish all floor finishes (additional to
previous polishing);
ix) Hand over keys of all doors to the Superintending Officer. Keys
shall have identifying tags attached;
x) Leave the building and the surroundings clean, tidy and ready
for immediate occupation.
AS2/08 F/ BILL 1 28
PRELIMINARIES & GENERAL CONDITIONS
To Collection :
Provide and maintain ten (10) Nos. protective and safety helmets,
ten (10) Pairs Wellington boots, five (5) Nos. measuring tapes, all
necessary safety shoes and equipment for all the workmen,
Contractor’s site management personnel, clerk-of-works,
Consultants and their representatives and all authorised visitors to
site.
Generally any trees, shrubs, bushes and all vegetation, etc. within
the site are to be cleared away. However, where there are trees
(located within or close to the site) which are to be preserved, the
Contractor is to take all precautions to protect them from being
injured.
6.7 METRICATION
AS2/08 F/ BILL 1 29
PRELIMINARIES & GENERAL CONDITIONS
To Collection:
AS2/08 F/ BILL 1 30
PRELIMINARIES & GENERAL CONDITIONS
The sum allowed is to include all fees for conservancy, water and
electricity charges, deposits etc.
To Collection:
The Contractor shall pay all royalties and expenses and be liable
for all claims in respect of the used of patent right whether in
Malaysia or elsewhere for or in connection with any article supplied
under this Contract and shall indemnify the Employer against any
claims arising there from.
In the event of any claim being made or action brought against the
Employer, the Employer shall be immediately notified thereof and
the Contractor shall, at his sole expense conduct all negotiations
for the settlement of the same or any litigation that may arise
therefrom.
7.1 SIGNBOARD
AS2/08 F/ BILL 1 31
PRELIMINARIES & GENERAL CONDITIONS
The Contractor, his workmen or agents will not make any public or
press statements of any form or description which are exasperate
and detrimental to the interests of the BOUSTEAD HEAVY
INDUSTRIES CORPORATION BHD., supervisory staff or any
Consultants connected with this contract nor will divulge any
information to the public concerning this contract before or after
the completion of the works.
To Collection:
A) Site Vehicles
AS2/08 F/ BILL 1 32
PRELIMINARIES & GENERAL CONDITIONS
To Collection:
The contractor shall liase with the S.O regarding placement of the
equipment. Each set of computer system shall comprise of and be
supplied completed with requirement as listed below:-
To Collection:
............................................................................................................
From Page No. PRELIM/
............................................................................................................
From Page No. PRELIM/
1
............................................................................................................
From
2 Page No. PRELIM/
............................................................................................................
From
3 Page No. PRELIM/
............................................................................................................
From
4 Page No. PRELIM/
............................................................................................................
From
5 Page No. PRELIM/
............................................................................................................
From
6 Page No. PRELIM/
............................................................................................................
From Page No. PRELIM/
7
............................................................................................................
From
8 Page No. PRELIM/
............................................................................................................
From
9 Page No. PRELIM/
............................................................................................................
From
10 Page No. PRELIM/
............................................................................................................
From
11 Page No. PRELIM/
12
AS2/08 F/ BILL 1 34
PRELIMINARIES & GENERAL CONDITIONS
31
AS2/08 F/ BILL 1 35