Submission of Project Documentation

Complete Load Flow analysis including all system parameters like rated
currents, voltages, impedances, P.F, short circuit currents etc. at different
points in the system to be submitted

Site Installation, Testing, Commissioning and Customer Training

Preliminary Design of Protection and Control Scheme & Submission

Arrangement of Site Office and Site Office Equipment

Getting Approval from Client and go-ahead for Detailed design

Arrangement of Visas, Air Tickets and Boarding & Lodging at site

Selection of Hardware & Software Components & Preparation of BOQ-1


for all long lead items

Submission of Personal data of Site team members

Material Procurement as per the BOQ-1 and delivery to ABTC

Material procurement as per BOQ-2 and delivery at site

Detail Design & Engineering of Complete System

Preparation of BOQ-2 for any remaining and small items

Submission of FAT Date & FAT Procedure


Material transport from ABTC to site after FAT Condution

Arrangement for FAT including Air tickets, Visas, Boarding & Lodging Conduction of FAT