Академический Документы
Профессиональный Документы
Культура Документы
2- 2- PCC 1:6:12 cement sand & stone ballast in all material labor
T&P etc in all complete material – cement 2.26 bag @ 241.00=544.66
F/Sand 0.50cum@373.00=186.50
40mm S/ballast 1.00cum@ 483.00=483.00
------------
1214.16/cum
Labour as per schedule 429.00/’’
1.5%W.A 18.21/’’
--------------
1661.37/’’
Say 1661.00/cum
4- P.C.C 1:2:4 with cement sand & stone ballast including all material labor
T&P etc in all complete material – cement 6.62 bag @ 241.00=1595.42
C/sand 0.45@428.00= 192.60
20 mm stone ballast 0.90@505.00= 454.50
2.5% wastage cement + Sand = 44.70
-----------------------
2771.22
Labour as per schedule 484.00
----------------
3255.22
1.5% W/A 48.82
10% C.P on labour 48.40
-----------------
3352.44/cum
Say 3352.00/cum
6- Same as item no. 5 but beam & column in super structure material-as item no. 5(A)
2796.09/cum
Labour as per schedule 1882.00
---------------------
4678.09
Add 1.5% W/A 70.17
10% C.P on laour 188.20
--------------------
4936.46/cum
Say 4936.00/cum
7- Same as item no. 5 but lintel bend & S/Shad - material as item no. 5(A)
2796.09/cum
Labour as per schedule 992.00
---------------------
3788.09
Add 1.5% W/A 56.82
10% C.P on laour 99.20
--------------------
3944.11/cum
Say 3944.00/cum
8- Same as item no. 5 but in slab work - material as item no. 5(A)
2796.09/cum
Labour as per schedule 1246.00
---------------------
4042.09
J.E RES A.E RES
B.F 4042.09
Add 1.5% W/A 60.63
10% C.P on laour 124.60
--------------------
4227.32/cum
Say 4227.00/cum
10- same as item no. 9 but in super structure material as item no. 9(A) 1674.43
Labour as per schedule 458.00
-----------------------
-
2132.43
1.5% W.A 31.68
10% C.P on labour 45.80
----------------
2210.21
Say 2210.00/cum
11- same as item no. 8 but ½ brick wall with 1:4 cement sand motar
material as item no. 9(A) 1674.43
labour as schedule 502.00
-----------------
2176.43
1.5% W.A 32.64
10% C.P on labour 50.20
Difference cement 1.85-1.26=0.59@241.00 142.15
----------------
2401.42
Say 2401.00/cum
J.E RES A.E RES
19- 2.5 cm thick 1:2:4 over 7.5cm thick 1:6:12 cement sand and s/b
in flooring and apron in all comp.
Material - cement 0.364@241.00 87.72
F/S 0.036@373.00 13.42
C/S 0.011@428.00 4.70
40 mm S/B 0.075 @ 483.00 36.22
20 mm S/B 0.023@505.00 16.61
labour as per schedule 63.00
-----------------------------
221.67
1.5% W.A 30.32
10% c.p on labour 6.30
-----------------
228.31
Say 228.00 /sqm