Вы находитесь на странице: 1из 4

SITE TEST REPORT Client:

DUBA POWER PLANT


(UNITS- 7 TO 9)
Najm AL Jazira CONTRACT NO: 20721047/00

System : O/C, E/F & CBF Protection Relay “MiCOM P127” Consultant:
Location : 33kV GIS(H06 –Interconnection Feeder to Existing 33kV S/s)

KKS No : C0AH Date : 30/10/2010 Page 1 of 4

FINAL SETTING TESTING REPORT OF O/C, E/F & CBF PROTECTION RELAY “MiCOM P127”

RELAY DATA:

Relay Tag F301 Relay Function 51,51N and 50BF


Relay Make AREVA Nominal Current 1A
Type/Style P127BA0F312BC0 Aux. Supply Voltage 48-250 V DC

Serial. No 31034914

VISUAL AND MECHANICAL CHECKS:

Item Description Checked


1 Inspect for physical damage and defects. O.K
2 Check Name Plate information for correctness. O.K
3 Verify tightness of external wiring. O.K
4 Check for proper installation and mounting. O.K

ELECTRICAL CHECKS:

Item Description Checked


1 All connections checked according to the wiring diagram. O.K
2 Auxiliary power supply checked for rating and polarity. O.K
3 Case earthing checked. O.K
4 CT shorting facility checked. O.K

COMPANY SIEMENS ISCOSA NAJM AJEC SEC


NAME Ali M Khater Mohammed Eltohamy Santhaseelan
SIGNATURE
DATE
SITE TEST REPORT Client:
DUBA POWER PLANT
(UNITS- 7 TO 9)
Najm AL Jazira CONTRACT NO: 20721047/00

System : O/C, E/F & CBF Protection Relay “MiCOM P127” Consultant:
Location : 33kV GIS(H06 –Interconnection Feeder to Existing 33kV S/s)

KKS No : C0AH Date : 30/10/2010 Page 2 of 4

FINAL SETTING TESTING REPORT OF O/C, E/F & CBF PROTECTION RELAY “MiCOM P127”
1. PROTECTION FUNCTION TESTING:
1.1 Over Current Protection Function (I>):
I> Setting:

I > Testing:

Relay Setting Operating Time at 2 Is (Sec)


Phase Pick Up (A) Drop Off (A)
I> TMS Calculated Measured
R 0.65 0.25 0.714 0.679 2.51 2.54
Y 0.65 0.25 0.715 0.679 2.51 2.54
B 0.65 0.25 0.715 0.679 2.51 2.54

Pass Criteria
- Pick-up should occur at 1.1 Is ±2%. - Reset should occur at 1.05 Is ±2%.
- IDMT operating time: ±5%+30… 50 ms.

1.2 Earth Fault Protection Function (Ie>):

Ie> Setting:

Ie> Testing:

Relay Setting Operating Time at 2 Ies (Sec)


Phase Pick Up (A) Drop Off (A)
Ie> TMS Calculated Measured
N 0.1 0.4 0.110 0.105 4.012 4.08

Pass Criteria
- Pick-up should occur at 1.1 Ies ±2%. - Reset should occur at 1.05 Ies ±2%.
- IDMT operating time: ±5%+30… 50 ms.
COMPANY SIEMENS ISCOSA NAJM AJEC SEC
NAME Ali M Khater Mohammed Eltohamy Santhaseelan
SIGNATURE
DATE
SITE TEST REPORT Client:
DUBA POWER PLANT
(UNITS- 7 TO 9)
Najm AL Jazira CONTRACT NO: 20721047/00

System : O/C, E/F & CBF Protection Relay “MiCOM P127” Consultant:
Location : 33kV GIS(H06 –Interconnection Feeder to Existing 33kV S/s)

KKS No : C0AH Date : 30/10/2010 Page 3 of 4

FINAL SETTING TESTING REPORT OF O/C, E/F & CBF PROTECTION RELAY “MiCOM P127”

1.3 Circuit Breaker Failure Function:

1.3.1 External Initiation:

I< BF Trip Time


I< BF Trip Time
Phase Measured
Setting Pick Up (A) Reset (A) Setting (mSec)
(mSec)
R 0.10 0.101 0.098 200 213
Y 0.10 0.101 0.098 200 212
B 0.10 0.101 0.098 200 215

1.3.2 Internal Initiation:

Trip Time
Phase Injected Current (A)
Expected (Sec) Measured (Sec)
RYB 1.3 2.71 2.75

Pass Criteria
- CB Fail Timer (tBF) ±2% +10… 30 ms.

2. CHECK ALL FRONT PANEL LEDS OPERATION:

LEDs Function Test Results


LED 1 TRIP OK
LED 2 ALARM OK
LED 3 WARNING OK
LED 4 HEALTHY OK
LED 5 I>, Ie> Start OK
LED 6 I> Trip OK
LED 7 Ie> Trip OK
LED 8 CBF Trip OK

COMPANY SIEMENS ISCOSA NAJM AJEC SEC


NAME Ali M Khater Mohammed Eltohamy Santhaseelan
SIGNATURE
DATE
SITE TEST REPORT Client:
DUBA POWER PLANT
(UNITS- 7 TO 9)
Najm AL Jazira CONTRACT NO: 20721047/00

System : O/C, E/F & CBF Protection Relay “MiCOM P127” Consultant:
Location : 33kV GIS(H06 –Interconnection Feeder to Existing 33kV S/s)

KKS No : C0AH Date : 30/10/2010 Page 4 of 4

FINAL SETTING TESTING REPORT OF O/C, E/F & CBF PROTECTION RELAY “MiCOM P127”
3. OUTPUT RELAYS CHECKS:

Output Relay Relay Function Terminal No. Results


K0 Relay faulty signal to annunciator 36,35(NC) OK
K1 Trip Coil 1 2-6 OK
K2 Trip Coil 2 8-12 OK
K3 Trip signal to annunciator 14-16 OK
K4 Upstream CB-Trip Coil 1 18-20 OK
K5 Upstream CB-Trip Coil 2 1-3 OK
K8 CBF Trip 13-15 OK

4. BINARY INPUT:

Binary Input Relay Function Terminal No. Results


U1 CBF initiation 22-24 OK

TEST EQUIPMENTS USED:

Test Device: Secondary Injection Kit


Serial Number: 9500554
Make & Model: Programma , Freja 300 R05C
Calibration Due Date: 10 August 2011

COMPANY SIEMENS ISCOSA NAJM AJEC SEC


NAME Ali M Khater Mohammed Eltohamy Santhaseelan
SIGNATURE
DATE

Вам также может понравиться