profile ledcor – napa

Project Details Overcoming Challenges are careful so that we can bring in only
Located on Main Street between Fifth Dewatering and staging of equipment material that is needed at any particular
and Third streets on the west bank of the and workers was also an issue on the time but so that the subcontractors can
Napa River, the Napa Riverfront is a Riverfront project, since the building is easily access it when needed.”
mixed-use project, consisting of 40,000 located on the river. With as many as 40 subcontractors on
square feet of commercial, 30,000 “We have to carefully stage each sub- the project at peak, Baptista says the
square feet of office space and 50 resi- contractor and deal with the parking of advantage of working with an experi-
dential condominium units. the personnel on-site to make sure all enced crew is that it can work on multi-
The project is being developed by merchants remain happy,” he says. ple projects within the tri-level building
Channel Properties and will include two Because the development is along the at one time.
mixed-use towers with space for offices, waterfront, the logistics of material As Napa continues to be a popular
condos, restaurants and other retail, delivery had to be well-timed. Its prox- destination, fueling additional invest-
and will be connected by a 40-foot-wide imity to the river also required that the ments, Ledcor’s Napa location will con-
deck along the Napa River. groundwater level on the project be tinue to grow. x
Ledcor is currently managing the lowered, and 24/7 water treatment was
installation of the mechanical/electri- required.
cal/plumbing systems and has complet- “We have to limit what we can keep on Clear Water provides comprehensive water treatment
services to the construction industry. The groundwater
ed the metal framing. site, so instead of getting lead times level on the Napa Riverfront project needed to be lowered
The building broke ground in May months ahead of time we get more small- and 24/7 water treatment was required. An automated sys-
tem performed this treatment and real-time status was
2007 and is expected to be completed by er, frequent drop-offs,” Baptista explains. transmitted to the Clear Water for management decisions
February 2009. “We really plan the staging area and and reporting.