Академический Документы
Профессиональный Документы
Культура Документы
UGANDA.
Presented
By
Charlotte Kamugisha
Managing Director,
Bunyonyi Safaris Ltd
Kampala
Uganda
Address
P. O. Box 26905 Kampala Uganda East Africa
Tel: 256-41-347460
Fax: 256-41-345605
Kamugi@imul.com
TABLE OF CONTENTS
2
1.0 PROJECT BACKGROUND
In Uganda there are two cement plants, mainly operating below capacity. They produce for the
domestic and export market in the neighboring countries of Rwanda, Burundi and Eastern
Democratic republic of Congo, which lack cement plants. This has contributed to the high cost
of cement in the region. Much of the cement in Uganda is also imported from Kenya and
Tanzania. Cement is sold at ex-factory price of about USD 210 per ton.
3
4. Have had political problems that have led to low economic growth and hence less cement
consumption. This last problem is gradually being overcome and the countries and
populations are faced with a great challenge to develop infrastructure as well as decent
housing.
A summary of the cement consumption trends as analyzed by a UNIDO sponsored study in
1997 is as below:
Table 1: Cement Consumption Trends
Year Production (tons) Imports (tons) Total Growth in
Consumption Consumption
(tons) 1987-00
1987 15,908 71,275 87,183 100.00
1988 14,703 111,757 126,460 145.05
1989 17,378 130,685 148,033 169.80
1990 26,920 61,495 88,417 101.14
1991 27,130 102,659 129,797 148.87
1992 37,881 135,879 173,760 199.30
1993 52,011 116,124 168,135 192.85
1994 45,558 212,886 246,444 282.67
1995 45,558 201,490 269,342 308.94
Ref: UNIDO 1997
N.B. 15,680 tons (actual) were imported from Hima cement factory to D.R. Congo.
4
2.0 THE PROJECT
The company therefore seeks to acquire the technology and financing to:
• To produce the cement,
• To harness hydro electric power and also needs the
• To purchase vehicles and to distribute the cement.
5
2.5 Project Cost
The project cost is summarized as below:
Table 3: Capital expenditure details
PROJECT ITEM SHAREHOLDERS FINANCING TOTAL
EQUITY REQUIRED
A Land 0
40 acres in Busanza 200,000
Total 200,000 0 200,000
B Buildings & infrastructure 0
B1 Stores, warehouse, offices etc 500,000
B2 Vertical kiln 2.5m internal diameter 100,000
600,000 600,000
C Machinery, Equipment, facilities 0
C1 Cement plant 300tpd CIF Kisoro 6,000,000
C2 Hydro electric plant 5-15MW, CIF Kisoro 1,200,000
C3 6 Compressors and 18 jack hammers 300,000
C4 Solar electric system for lighting 10,000
C5 Water pump 10,000
0 7,520,000 7,520,000
D Office equipment
D1 Furniture, fixtures, fittings, computers 20,000 0
D2 Communication equipment 5,000 0
25,000 0 25,000
E Vehicles 0
E1 Four 50 ton trucks, 2 saloon car 1,200,000 1,200,000
F Pre operating costs
F1 Site preparation 25,000
F2 Mining lease & Environmental impact 20,000
assessment
F3 Design and engineering 30,000
6
3.0 FINANCIAL VIABILITY
The total initial investment in the project including working capital requirements is expected to
be approximately USD$ 10,855,900. In order to assess the project financial viability, 6-year
profit and loss cash projections have been developed. The 6-year projections not only enable
assessment of adequacy of cash flows to cover loan repayments but also allow for a going
concern assessment of the project.
7
3.2 Financial Projections
Table 5: Financial projections.
1st year 2nd year 3rd year 4th year 5th year 6th year
RECEIPTS
Loan 9,702,000 0
Shareholders 1,076,900 0
equity
Cash sales 0 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000
Profit/loss carried 0 1,175,100 629,000 655,100 555,200 645,300
fwd
Total Receipts 10,855,900 4,775,100 4,229,000 4,255,100 4,155,200 4,245,300
PAYMENTS
Pre-operational 9,406,900 1,200,000 0 0 0
expenses
Operational 249,000 249,000 249,000 249,000 249,000 249,000
expenses
Contingency 10% 24,900 24,900 24,900 24,900 24,900 24,900
Depreciation (5%) 0 0 0 376,000 436,000 436,000
Loan repayment 0 1,702,000 2,500,000 2,500,000 2,500,000 500,000
Bank interest 0 970,200 800,000 550,000 300,000 0
(10%)
Total payments 9,680,800 4,146,100 3,573,900 3,699,900 3,509,900 1,209,900
Total receipts 10,855,900 4,775,100 4,229,000 4,255,100 4,155,200 4,245,300
Profit/loss 1,175,100 629,000 655,100 555,200 645,300 3,035,400
To reduce the emission of sulfur dioxide into the atmosphere, a kiln with a pre-calciminer to
increase the rate of desulferisation will be used.
8
5.0 BENEFITS OF THE PROJECT.
The project will be of benefit to the country and the region by:
• Providing cement for construction at relatively cheaper prices and hence saving the country
foreign exchange.
• Paying taxes.
• Providing employment hence improving standards of living of the population
• Reducing the impact of population growth on land resources and hence decreasing
environmental degradation. (By providing alternative employment, the project will take
pressure off the land resource hence reducing environmental degradation).
It is for the above reasons that Kaku Cement works is committed to contribute 1% of all profits
earned after the loan is fully paid back to the promotion of modern and intensive agriculture and
forestry. A program has already been developed for this purpose. In brief it will set into motion
a cycle distribution of improved seeds, tree seedlings and domestic animals from farmer to
farmer. It will also provide agricultural and forestry advisory services. This will be done by
providing the above materials for free to a few selected farmers who will then be required to
pass on some units of their 1st harvest to another farmer for free. This will create a cycle and
once set in motion the program is expected to expand and grow hence benefiting many poor
households that would otherwise have not afforded the services. The program will also be
sustainable once set in motion.
9
APPENDIX 1: CHEMICAL RESULTS OF KAKU RIVER LIMESTONE
10
REFERENCES
UNIDO 1997: Preliminary Assessment for the Feasibility of Establishing a New Small/Medium
Cement Plant Based on the Evaluation of the Availability of Sufficient Reserves of Raw
Materials in the Eastern and/or Western Regions of Uganda. Uganda Investment Authority
Kampala.
11