S.No.

Project Milestones Unit # 1 Date


1 Appointment of Engg Consultant 15-Nov-06*
2 Zero Date 01-Jul-07*
3 NTP 01-Jul-07*
4 Commence Test Piling 01-Aug-07*
5 Commence Working Piling 30-Aug-07*
6 Boiler Structure Erection Start 01-Feb-08*
7 Turbine Hall Structure Erection Start 15-Feb-08*
8 Pressure Parts Erection 30-Jun-08*
9 Boiler Drum Lifting 01-Aug-08*
10 Switchyard Ready for SUP 30-Oct-08*
11 Condenser Erection Start 15-Oct-08*
12 EOT Crane ready for Turbine/Condenser Erection 10-Oct-08*
13 HT Switchgear Commissioning (Prio-1) 30-Nov-08*
14 LT Switchgear Commissioning (Prio-1) 31-Dec-08*
15 Turbine Erection Start 01-Nov-08*
16 Raw Water Reservoir ready to receive water 30-Nov-08*
17 PT Plant commissioning 31-Jan-09*
18 Compressed Air System Ready (Prio-1) 15-Jan-09*
19 DM Plant commissioning 31-Jan-09*
20 Boiler Hydro Test 28-Feb-09*
21 Effluent Treatment Plant 1-Aug-09*
22 Fuel Oil System Commissioning 31-May-09*
23 Cooling Tower Ready 31-May-09*
24 Boiler Light up 15-Jun-09*
25 Turbine Box UP 31-May-09*
26 Ash Disposal System 16-Aug-09*
27 Ash Handling Plant Ready 16-Aug-09*
28 Coal Handling Plant Ready 31-Jul-09*
29 Steam Blow, SVF & Restoration 16-Aug-09*
30 TG Oil Flushing & Restoration 16-Aug-09*
31 TG on Barring Gear 01-Jul-09*
32 TG Rolling 17-Aug-09*
33 Synchronization Unit 1 31-Aug-09*
34 COD Unit 1 01-Oct-09*
* Unit #2 is scheduled three months behind Unit #1