ID Task Name Duration Cost Start Finish Predecessors 29 Nov '09 06 Dec '09 13 Dec '09 20 Dec '09

ish Predecessors 29 Nov '09 06 Dec '09 13 Dec '09 20 Dec '09 27 Dec '09 03 Jan '10 10 Jan '10 17 Jan '10 24 Jan '10 31 Jan '10 07 Feb '10 14 Feb '10 21 Feb '10 28 Feb '10 07 Mar '10 14 Mar '10 21 Mar '10 28 Mar '10
S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M T W T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F
1 Club Oceanic Project 120 days $150,010,263.20 Tue 01/12/09 Wed 31/03/10
2 SPA 110 days $10,690,567.20 Tue 01/12/09 Sun 21/03/10
3 Sub Structure 20 days $2,534,413.00 Tue 01/12/09 Mon 21/12/09
4 Super Structure 20 days $1,603,989.00 Wed 16/12/09 Tue 05/01/10 3SS+15 days
5 Masonary 15 days $1,001,318.20 Tue 05/01/10 Wed 20/01/10 4
6 Roof 15 days $1,630,593.00 Wed 20/01/10 Thu 04/02/10 5
7 Finishers 45 days $3,920,254.00 Thu 04/02/10 Sun 21/03/10 6
8
9 WATER RETAINING STRUCTURES, POOLS, SUMPS 118 days $12,934,113.00 Tue 01/12/09 Mon 29/03/10
10 Main Pool 85 days $10,853,972.00 Tue 01/12/09 Wed 24/02/10
11 Prepare earthworks 25 days $1,000,000.00 Tue 01/12/09 Sat 26/12/09
12 Concrete works 30 days $5,000,000.00 Sat 26/12/09 Mon 25/01/10 11
13 Need Tiles 0 days $0.00 Fri 15/01/10 Fri 15/01/10 15/01
14 Finishes 30 days $4,853,972.00 Mon 25/01/10 Wed 24/02/10 12
15 Kids Pool 30 days $928,092.00 Mon 25/01/10 Wed 24/02/10 12
16 Reflecting pool 30 days $0.00 Mon 25/01/10 Wed 24/02/10 15SS
17 Sewerage Plant 70 days $1,152,049.00 Mon 18/01/10 Mon 29/03/10 12FS-7 days
18
19 REFURBISHMENT OF POOL TOILET AND RETAINING WALL
50 days $2,190,622.00 Mon 25/01/10 Tue 16/03/10
20 Refurbishment of Toilets 20 days $1,728,833.00 Wed 24/02/10 Tue 16/03/10 15
21 Retaining Wall 30 days $461,789.00 Mon 25/01/10 Wed 24/02/10 12
22
23 TWO BLOCKS OF 8 ROOM 2 STOREY CHALETS 120 days $18,442,330.00 Tue 01/12/09 Wed 31/03/10
24 Sub Structure 20 days $1,222,606.00 Tue 01/12/09 Mon 21/12/09
25 Super Structure 20 days $4,009,702.00 Wed 16/12/09 Tue 05/01/10 24SS+15 days
26 Masonary 20 days $1,587,172.00 Wed 16/12/09 Tue 05/01/10 3SS+15 days
27 Roof 25 days $2,557,071.00 Tue 05/01/10 Sat 30/01/10 26
28 Need tiles 0 days $0.00 Mon 01/02/10 Mon 01/02/10 01/02
29 Need Toilet Accessories 0 days $0.00 Thu 07/01/10 Thu 07/01/10 07/01
30 Need toilet Fittings 0 days $0.00 Mon 01/02/10 Mon 01/02/10 01/02
31 Finishers 60 days $9,065,779.00 Sat 30/01/10 Wed 31/03/10 27
32
33 ONE BLOCK OF 4 ROOM TWO STOREY CHALET 87 days $10,341,888.00 Mon 21/12/09 Thu 18/03/10
34 Sub Structure 15 days $1,374,099.00 Mon 21/12/09 Tue 05/01/10 24
35 Super Structure 20 days $2,075,742.00 Tue 05/01/10 Mon 25/01/10 34
36 Masonary 20 days $855,681.00 Sun 17/01/10 Sat 06/02/10 35SS+12 days
37 Roof 20 days $1,391,744.00 Sat 06/02/10 Fri 26/02/10 36
38
39 Finishers 20 days $4,644,622.00 Fri 26/02/10 Thu 18/03/10 37
40
41 RIGHT WING GROUND FLOOR, 85 days $9,996,263.00 Tue 01/12/09 Wed 24/02/10
42 Demolition 25 days $1,005,874.00 Tue 01/12/09 Sat 26/12/09
43 Need tiles 0 days $0.00 Mon 21/12/09 Mon 21/12/09 21/12
44 Need Toilet Accessories 0 days $0.00 Mon 21/12/09 Mon 21/12/09 21/12
45 Need toilet Fittings 0 days $0.00 Mon 01/02/10 Mon 01/02/10 01/02
46 Repair work 60 days $8,990,389.00 Sat 26/12/09 Wed 24/02/10 42
47
48 RIGHT WING FIRST FLOOR, 85 days $12,545,543.00 Tue 08/12/09 Wed 03/03/10
49 Demolition 25 days $1,263,429.00 Tue 08/12/09 Sat 02/01/10 42SS+7 days
50 Repair work 60 days $11,282,114.00 Sat 02/01/10 Wed 03/03/10 49
51
52 REFURBISHMENT OF 4 NO. EXISTING 4 ROOM TWO STOREY
105 days
CHALETS $15,109,448.00 Tue 15/12/09 Tue 30/03/10
53 one block 40 days $3,777,362.00 Tue 15/12/09 Sun 24/01/10 42SS+14 days
54 one block 40 days $3,777,362.00 Sun 17/01/10 Fri 26/02/10 53FS-7 days
55 one block 40 days $3,777,362.00 Sat 16/01/10 Thu 25/02/10 49FS+14 days
56 one block 40 days $3,777,362.00 Thu 18/02/10 Tue 30/03/10 55FS-7 days
57
58 REMOVAL OF EXISTING CONCRETE COLUMNS & CONCRETE
52 days
REPAIR $4,223,958.00 Tue 01/12/09 Fri 22/01/10
59 Reception 7 days $951,154.00 Tue 01/12/09 Tue 08/12/09
60 Conference Hall 45 days $1,530,004.00 Tue 08/12/09 Fri 22/01/10 49SS
61 Concrete Repair 45 days $1,634,800.00 Tue 01/12/09 Fri 15/01/10
62 Demolition 20 days $108,000.00 Tue 01/12/09 Mon 21/12/09
63
64 WATER PROOFING, REPLACING ROOFING SHEETS, EXTERNAL
120 days
PAINTING
$7,267,999.00 Tue 01/12/09 Wed 31/03/10
65 Water proofing 60 days $1,275,325.00 Tue 01/12/09 Sat 30/01/10
66 Replace of Roof 30 days $4,807,674.00 Tue 01/12/09 Thu 31/12/09
67 Painting 58 days $1,185,000.00 Mon 01/02/10 Wed 31/03/10 65
68
69 EXTERNAL WORKS 58 days $16,605,407.00 Mon 01/02/10 Wed 31/03/10
70 Timber decking 58 days $4,896,678.00 Mon 01/02/10 Wed 31/03/10
71 Concrete decking 58 days $3,395,328.00 Mon 01/02/10 Wed 31/03/10
72 Boundry Wall 58 days $1,866,651.00 Mon 01/02/10 Wed 31/03/10
73 Car Park 58 days $6,446,750.00 Mon 01/02/10 Wed 31/03/10
74
75 REFURBISHMENT OF RESTAURANT 107 days $6,903,197.00 Tue 01/12/09 Thu 18/03/10
76 Demolition 12 days $506,140.00 Tue 01/12/09 Sun 13/12/09
77 Masonry 15 days $162,750.00 Sun 13/12/09 Mon 28/12/09 76
78 Roof 20 days $3,085,826.00 Mon 28/12/09 Sun 17/01/10 77
79 Finishes 45 days $2,545,780.00 Sun 17/01/10 Wed 03/03/10 78
80 Paint 15 days $602,701.00 Wed 03/03/10 Thu 18/03/10 79
81
82 ELECTRICAL INSTALLATION 85 days $10,270,262.00 Tue 05/01/10 Wed 31/03/10 4
83 PLUMBING INSTALLATION 85 days $12,488,666.00 Tue 05/01/10 Wed 31/03/10

Project: Club Oceanic Trinco- New Pro Task Split Progress Milestone Summary Project Summary External Tasks External MileTask Split
Date: Thu 28/01/10