1. 69,000 MT FFB Expected to be process for Ladang Mamahat Palm Oil Mill year
2010 .
2. Estimate FFB Process are 69,000 MT at year 2010, Oil Production is 15,180 MT,
base on average extraction rate 22.00% and kernel production is 2,070 MT base on
average extraction kernel 3.00%.
4. Capital expenditure for year 2010 is RM 485,000.00, there are the following items:-