Deliverables Submission Calendar

Software Projects, Spring 2011

Starting project work: 15/04/2011

No Phases Deliverables Description Submission Date


Describes the scope of
the project, functional
GATHERING &
& non-functional
1 ANALYZING SRS Document May 25/05/2011
requirements, use case
REQUIREMENT
diagram(s), usage
scenarios
Describes the
Method & Work methodology &
2 PLANNING PHASE schedule of the project Jun 6/06/2011
Plan

Activity Diagram,
Sequence diagrams,
Collaboration Diagram,
Design Document
Architecture Design Jul 1/07/2011
I
Diagram, DFD(s) and
ERD if the project
domain requires
ANALYSIS AND
3 Object model ,class
DESIGN PHASE
diagram, interface
design, database design
Design Document if the project domain
Aug 2/08/2011
II requires database, test
cases, Deployment
Diagram , Component
Diagram
Working code for half
DEVELOPMENT Iteration I of the features for the Oct 3/10/2011
& applications.
4
FINAL PROJECT Working code for rest
REPORT Iteration II of the features of the Dec 2/12/2011
applications.
Compilation &
Final Project submission of Final
Dec 16/12/2011
Report Project Report and
FINAL Presentation
5
REPORT/VIVA Final viva exam of the Schedule to be
project published after
Final Viva
final term exams
for Spring 2011