PROJECT SPECIFICATIONS

Location: Power Plant Configuration: Pressure Ratio: Mass Flow: Turbine Speed: Exhaust Temperature: Net Capacity: Port Qasim, Karachi, Pakistan. 3 x MS9001FA GE Gas turbines with 2 x Steam Turbines and 3 x HRSGs. 17.0:1 1,413 lb/sec (641 kg/sec) 3000 rpm 1,116F (602C) Block - 1: 390.80 MW Block - 2: 786.90 MW Total: 1,177.70 MW Liquefied Natural Gas (LNG) converted to Gas Suitable for carrier of capacity - 100,000 CUM ~ 150,000 CUM 3 Million CUM (Approximately 2 Ships of 125,000 CUM of LNG per month.) 1177.7 MW 360 Days 10175328000 KWh 3412 BTU/KWh 34,718,219,136,000 1 mm BTU 1.055 GJ 36,627,721 100% Efficiency 73,255,442 55 % Efficiency MT 54.7 GJ/MT 1,339,222 Tons/annum Requirement 2,906,112 CUM

Fuel: Fuel Jetty: Annual Consumption: GAS REQUIREMENT CCGT Capacity Annual operation Annual Generation BTU BTU required GJ required

Requirement