Вы находитесь на странице: 1из 1

Flinders - Xmas Creek

Activity ID Activity Name Original Start Duration 11 Grader Work along windrow (500m length) Weld DN450 pipeline Install air valves along BCI DN450 pipeline Tie in DN450 pipeline at haul rd burial Install 3 x off takes at Flinders Pit DN355 and DN250 work around Flinders T/N Install 11 burials Air valve installations Install sheet flow 1 10 4 3 5 5 11 2 10 18-Nov-11 18-Nov-11 18-Nov-11 22-Nov-11 Finish 28-Nov-11 18-Nov-11 27-Nov-11 25-Nov-11 0% 0% 0% 0% 0% 0% 0% 0% 0% Physical % Complete

Cape Crushing Schedule

"Safety is an investment ....not a cost


November 2011 December 2011 21 28 28-Nov-11, Flinders 05

18-Nov-11 11:25

14

12

Flinders
A1000 A1010 A1020 A1030 A1040 A1050 A1060 A1070 A1080

Grader Work along windrow (500m length) Weld DN450 pipeline Install air valves along BCI DN450 pipeline Tie in DN450 pipeline at haul rd burial Install 3 x off takes at Flinders Pit DN355 and DN250 work around Flinders T/N Install 11 burials Air valve installations Install sheet flow

22-Nov-11* 25-Nov-11 21-Nov-11* 26-Nov-11 22-Nov-11* 27-Nov-11 18-Nov-11 18-Nov-11 28-Nov-11 27-Nov-11 27-Nov-11* 28-Nov-11

Primary Baseline Actual Work

Remaining Work Critical Remaining Work

Milestone Summary

Page 1 of 1

Вам также может понравиться