REMOVALOFREDUNDANTPIPELINE/
EQUIPMENT
Activity ID

Activity Name

Original Start
Duration

Finish
2011
Oct

REMOVAL Of REDUNDANT PIPELINES/EQUIPMENTS


PRELIMINARIES

87 20-Oct-11

18-Feb-12

17 20-Oct-11

12-Nov-11

Dec

Jan

Feb

AWARD OF CONTRACT

0 20-Oct-11

A1010

KICK OF MEETING

0 25-Oct-11*

A1020

ISSUANCE OF LOA FROM TAKREER

0 26-Oct-11*

A1030

SUBMISSION OF MS & TRA TO TAKREER

0 29-Oct-11*

A1040

ESTABLISHMENT OF TSF

6 29-Oct-11

03-Nov-11

A1050

SITE MOBILIZATION

8 03-Nov-11

12-Nov-11

KICK OF MEETING
ISSUANCE OF LOA FR OM TAKREER
SUBMISSION OF MS & TRA TO TAKREER

A1060

SAFETY INDUCTION

6 05-Nov-11

10-Nov-11

A1070

PTW TRAINING

6 06-Nov-11

12-Nov-11

42 13-Nov-11

10-Jan-12

1 13-Nov-11

13-Nov-11

03-Nov-11
12-Nov-11
10-Nov-11
12-Nov-11

13-Nov-11

A1080

PERMIT TO WORK FROM TAKREER

A1090

SITE SURVEY

25 13-Nov-11

11-Dec-11

A1100

MARKING OF LINES

45 20-Nov-11

10-Jan-12

10-Jan-12

A1110

TAKREER INSPECTION/CONFIRMATION FOR LINES

45 20-Nov-11

10-Jan-12

10-Jan-12

A1120

SHIFTING OF SCAFFOLDING AT SITE

14 13-Nov-11

28-Nov-11

A1130

ERECTION OF SCAFFOLDING

49 15-Nov-11

10-Jan-12

10-Jan-12

A1140

TAGGING OF LINES

49 15-Nov-11

10-Jan-12

10-Jan-12

59 15-Nov-11

04-Feb-12

20 08-Jan-12

04-Feb-12

SHUTDOWN PHASE
REMOVAL OF LINES AND EQUIPMENTS IN HYDRCRACKE R SECTION

11-Dec-11

28-Nov-11

8 18-Jan-12

29-Jan-12

A2070

ISOLATION/BLINDING

3 18-Jan-12

21-Jan-12

A2080

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

6 22-Jan-12

28-Jan-12

28-Jan-12

A2090

INSTALLATION OF PIPE SUPPORTS (IF REQ)

6 22-Jan-12

28-Jan-12

28-Jan-12

A2100

CUTTING/DEMOLISHING OF LINES

6 23-Jan-12

29-Jan-12

A2110

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

2 26-Jan-12

28-Jan-12

28-Jan-12

A2120

REMOVAL OF SCAFFOLDING

1 28-Jan-12

28-Jan-12

28-Jan-12

A2130

SITE CLEARANCE OF FO LINE

1 28-Jan-12

28-Jan-12

28-Jan-12

FUEL OIL LINE & ATOMIZED STEAM UNIT 101 AT B-01

( New Bar )
Milestone

Mar

AWARD OF CONTRACT

A1000

PRE-SHUTDOWN PHASE

2012

Nov

REVISED SCHEDULE

21-Jan-12

29-Jan-12

Date
05-Oct-11

Revision
1

Checked
FS

Approved
SZA

05-Oct-11 22:15

REMOVALOFREDUNDANTPIPELINE/
EQUIPMENT
Activity ID

Activity Name

Original Start
Duration

Finish
2011
Oct

FUEL OIL LINE ATMOIZING UNIT 103 AT B-04

3 29-Jan-12

01-Feb-12

2012

Nov

Dec

Jan

Feb

29-Jan-12

A2140

ISOLATION/BLINDING

1 29-Jan-12

29-Jan-12

A2150

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

2 30-Jan-12

31-Jan-12

31-Jan-12

A2160

INSTALLATION OF PIPE SUPPORTS (IF REQ)

2 30-Jan-12

31-Jan-12

31-Jan-12

A2170

CUTTING/DEMOLISHING OF LINES

2 31-Jan-12

01-Feb-12

01-Feb-12

A2180

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

1 01-Feb-12

01-Feb-12

01-Feb-12

A2190

REMOVAL OF SCAFFOLDING

1 01-Feb-12

01-Feb-12

01-Feb-12

A2200

SITE CLEARANCE OF FO LINE

1 01-Feb-12

01-Feb-12

01-Feb-12

SOUR WATER GAS LINE UNIT 104 AT 106 D-02

5 29-Jan-12

04-Feb-12

A1510

ISOLATION/BLINDING

2 29-Jan-12

30-Jan-12

A1520

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

4 31-Jan-12

04-Feb-12

A1530

INSTALLATION OF PIPE SUPPORTS (IF REQ)

3 31-Jan-12

02-Feb-12

A1540

CUTTING/DEMOLISHING OF LINES

3 01-Feb-12

04-Feb-12

04-Feb-12

A1550

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

2 02-Feb-12

04-Feb-12

04-Feb-12

A1560

REMOVAL OF SCAFFOLDING

1 04-Feb-12

04-Feb-12

04-Feb-12

A1570

SITE CLEARANCE OF FO LINE

1 04-Feb-12

04-Feb-12

04-Feb-12

6 26-Jan-12

02-Feb-12

FUEL OIL LINE TRACING STEAM

30-Jan-12
04-Feb-12
02-Feb-12

28-Jan-12

A1580

ISOLATION/BLINDING

2 26-Jan-12

28-Jan-12

A1590

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

4 29-Jan-12

01-Feb-12

A1600

INSTALLATION OF PIPE SUPPORTS (IF REQ)

3 29-Jan-12

31-Jan-12

A1610

CUTTING/DEMOLISHING OF LINES

4 30-Jan-12

02-Feb-12

A1620

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

2 31-Jan-12

01-Feb-12

01-Feb-12

A1630

REMOVAL OF SCAFFOLDING

1 01-Feb-12

01-Feb-12

01-Feb-12

A1640

SITE CLEARANCE OF FO LINE

2 01-Feb-12

02-Feb-12

18 08-Jan-12

01-Feb-12

REMOVAL OF INSTRUMENTATIONS ON FO AND SWG AT U101 & U104


A1650

ISOLATION OF POWER AND SIGNAL CABLES FOR FIELD IN STRU MENTS

1 08-Jan-12

08-Jan-12

A1660

ISOLATION OF PNEUMATIC INSTRUMENTS

1 09-Jan-12

09-Jan-12

A1670

DISMANTLING OF REDUNDANT INSTRUMENTS

8 10-Jan-12

18-Jan-12

( New Bar )
Milestone

REVISED SCHEDULE

Mar

01-Feb-12
31-Jan-12
02-Feb-12

02-Feb-12

08-Jan-12
09-Jan-12
18-Jan-12

Date
05-Oct-11

Revision
1

Checked
FS

Approved
SZA

05-Oct-11 22:15

REMOVALOFREDUNDANTPIPELINE/
EQUIPMENT
Activity ID

Activity Name

Original Start
Duration

Finish
2011
Oct

2012

A1680

DISMANTLING/REMOVAL OF POWER CABLES FROM INSTRUMENTS

8 19-Jan-12

28-Jan-12

Feb
28-Jan-12

A1690

SHIFTING OF INSTRUMENTS IN SCRAYARD

4 29-Jan-12

01-Feb-12

01-Feb-12

10 22-Jan-12

04-Feb-12

10 22-Jan-12

04-Feb-12

3 22-Jan-12

24-Jan-12

REMOVAL OF LINES IN HYDROSKIMMER SECTION


FUEL OIL LINE UNIT 11,12,13,14 & 15

Nov

Dec

Jan

24-Jan-12

A1160

ISOLATION/BLINDING

A1170

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

10 22-Jan-12

01-Feb-12

A1180

INSTALLATION OF PIPE SUPPORTS (IF REQ)

9 22-Jan-12

31-Jan-12

A1190

CUTTING/DEMOLISHING OF LINES

9 23-Jan-12

01-Feb-12

01-Feb-12

A1200

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

8 24-Jan-12

01-Feb-12

01-Feb-12

A1210

REMOVAL OF SCAFFOLDING

2 01-Feb-12

02-Feb-12

A1220

SITE CLEARANCE OF FO LINE

1 04-Feb-12

04-Feb-12

ATMOIZED STEAM LINE UNIT 11,12,13,14 & 15

8 23-Jan-12

01-Feb-12

01-Feb-12
31-Jan-12

02-Feb-12
04-Feb-12

24-Jan-12

A1230

ISOLATION/BLINDING

2 23-Jan-12

24-Jan-12

A1240

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

8 23-Jan-12

31-Jan-12

31-Jan-12

A1250

INSTALLATION OF PIPE SUPPORTS (IF REQ)

8 23-Jan-12

31-Jan-12

31-Jan-12

A1260

CUTTING/DEMOLISHING OF LINES

8 24-Jan-12

01-Feb-12

A1270

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

2 25-Jan-12

26-Jan-12

A1280

REMOVAL OF SCAFFOLDING

2 26-Jan-12

28-Jan-12

A1290

SITE CLEARANCE OF FO LINE

FUEL OIL LINE TRACING STEAM UNIT 11,12,13,14 & 15

1 26-Jan-12

26-Jan-12

6 25-Jan-12

01-Feb-12

01-Feb-12
26-Jan-12
28-Jan-12
26-Jan-12

25-Jan-12

A1300

ISOLATION/BLINDING

1 25-Jan-12

25-Jan-12

A1310

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

4 26-Jan-12

30-Jan-12

30-Jan-12

A1320

INSTALLATION OF PIPE SUPPORTS (IF REQ)

4 26-Jan-12

30-Jan-12

30-Jan-12

A1330

CUTTING/DEMOLISHING OF LINES

4 28-Jan-12

31-Jan-12

31-Jan-12

A1340

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

2 31-Jan-12

01-Feb-12

01-Feb-12

A1350

REMOVAL OF SCAFFOLDING

1 01-Feb-12

01-Feb-12

01-Feb-12

A1360

SITE CLEARANCE OF FO LINE

1 01-Feb-12

01-Feb-12

01-Feb-12

53 22-Nov-11

02-Feb-12

UTILITIES - DISMANTLING OF PIPELINES(10" 2.5 KM AND 4" 3.7 KM)

( New Bar )
Milestone

REVISED SCHEDULE

Mar

Date
05-Oct-11

Revision
1

Checked
FS

Approved
SZA

05-Oct-11 22:15

REMOVALOFREDUNDANTPIPELINE/
EQUIPMENT
Activity ID

Activity Name

Original Start
Duration

Finish
2011
Oct

2012

Nov

Dec
08-Dec-11

Jan

Feb

A1700

ISOLATION/BLINDING

15 22-Nov-11

08-Dec-11

A1710

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

30 10-Dec-11

12-Jan-12

12-Jan-12

A1720

INSTALLATION OF PIPE SUPPORTS (IF REQ)

30 10-Dec-11

12-Jan-12

12-Jan-12

A1730

CUTTING/DEMOLISHING OF LINES

30 11-Dec-11

14-Jan-12

14-Jan-12

A1740

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

29 12-Dec-11

14-Jan-12

14-Jan-12

A1750

REMOVAL OF SCAFFOLDING

18 14-Jan-12

02-Feb-12

A1760

SITE CLEARANCE OF FO LINE

3 14-Jan-12

16-Jan-12

34 18-Dec-11

02-Feb-12

UTILITIES - DISMANTLING OF PIPELINES(GENERAL)

02-Feb-12
16-Jan-12

25-Dec-11

A1770

ISOLATION/BLINDING

7 18-Dec-11

25-Dec-11

A1780

INSPECTION BY TAKREER BEFORE DEMOLISHING/CUTTING

9 26-Dec-11

04-Jan-12

04-Jan-12

A1790

INSTALLATION OF PIPE SUPPORTS (IF REQ)

9 26-Dec-11

04-Jan-12

04-Jan-12

A1800

CUTTING/DEMOLISHING OF LINES

28 27-Dec-11

28-Jan-12

A1810

SHIFTING OF REDUNDANT PIPES TO SCRAPYARD

28 28-Dec-11

29-Jan-12

A1820

REMOVAL OF SCAFFOLDING

5 29-Jan-12

02-Feb-12

A1830

SITE CLEARANCE OF FO LINE

2 29-Jan-12

30-Jan-12

59 15-Nov-11

04-Feb-12

24 15-Nov-11

17-Dec-11

UTILITIES - TANKS DISMANTLING


Tank 23 FO2

28-Jan-12
29-Jan-12
02-Feb-12
30-Jan-12

15-Nov-11

A2210

BLINDING/ISOLATION

1 15-Nov-11

15-Nov-11

A2220

NITROGEN PURGING OF LINES

1 16-Nov-11

16-Nov-11

A2230

CUTTING OF THE TANKS SHELL AND ROOF

14 17-Nov-11

03-Dec-11

A2240

CUTTING/REMOVAL OF FOUNDATIONS OF TANKS

14 01-Dec-11

17-Dec-11

A2250

SHIFTING OF MATERIAL TO SCRAPYARD

15 20-Nov-11

06-Dec-11

A2260

REMOVAL OF EXTERNAL SCAFFOLDING

2 20-Nov-11

21-Nov-11

21-Nov-11

A2270

SITE CLEARANCE

1 22-Nov-11

22-Nov-11

22-Nov-11

23 23-Nov-11

25-Dec-11

Tank 123 FO2


A2280

BLINDING/ISOLATION

1 23-Nov-11

23-Nov-11

A2290

NITROGEN PURGING OF LINES

1 24-Nov-11

24-Nov-11

A2300

CUTTING OF THE TANKS SHELL AND ROOF

14 26-Nov-11

11-Dec-11

( New Bar )
Milestone

REVISED SCHEDULE

Mar

16-Nov-11
03-Dec-11
17-Dec-11
06-Dec-11

23-Nov-11
24-Nov-11
11-Dec-11

Date
05-Oct-11

Revision
1

Checked
FS

Approved
SZA

05-Oct-11 22:15

REMOVALOFREDUNDANTPIPELINE/
EQUIPMENT
Activity ID

Activity Name

Original Start
Duration

Finish
2011
Oct

A2310

CUTTING/REMOVAL OF FOUNDATIONS OF TANKS

14 10-Dec-11

25-Dec-11

A2320

SHIFTING OF MATERIAL TO SCRAPYARD

15 28-Nov-11

14-Dec-11

A2330

REMOVAL OF EXTERNAL SCAFFOLDING

2 28-Nov-11

29-Nov-11

A2340

SITE CLEARANCE

1 30-Nov-11

30-Nov-11

23 01-Dec-11

02-Jan-12

Tank 30 F01
A2350

BLINDING/ISOLATION

1 01-Dec-11

01-Dec-11

A2360

NITROGEN PURGING OF LINES

1 03-Dec-11

03-Dec-11

A2370

CUTTING OF THE TANKS SHELL AND ROOF

14 04-Dec-11

19-Dec-11

A2380

CUTTING/REMOVAL OF FOUNDATIONS OF TANKS

14 18-Dec-11

02-Jan-12

A2390

SHIFTING OF MATERIAL TO SCRAPYARD

15 06-Dec-11

22-Dec-11

A2400

REMOVAL OF EXTERNAL SCAFFOLDING

2 06-Dec-11

07-Dec-11

A2410

SITE CLEARANCE

1 08-Dec-11

08-Dec-11

22 10-Dec-11

10-Jan-12

Tank 30 F02

2012

Nov

Dec

Jan

29-Nov-11
30-Nov-11

01-Dec-11
03-Dec-11
19-Dec-11
02-Jan-12
22-Dec-11
07-Dec-11
08-Dec-11

BLINDING/ISOLATION

1 10-Dec-11

10-Dec-11

10-Dec-11

A2430

NITROGEN PURGING OF LINES

1 11-Dec-11

11-Dec-11

11-Dec-11

A2440

CUTTING OF THE TANKS SHELL AND ROOF

14 12-Dec-11

27-Dec-11

A2450

CUTTING/REMOVAL OF FOUNDATIONS OF TANKS

14 26-Dec-11

10-Jan-12

A2460

SHIFTING OF MATERIAL TO SCRAPYARD

15 14-Dec-11

31-Dec-11

REMOVAL OF EXTERNAL SCAFFOLDING

2 14-Dec-11

15-Dec-11

A2480

SITE CLEARANCE

1 17-Dec-11

17-Dec-11

27-Dec-11
10-Jan-12
31-Dec-11
15-Dec-11
17-Dec-11

23 18-Dec-11

18-Jan-12

A2490

BLINDING/ISOLATION

1 18-Dec-11

18-Dec-11

A2500

NITROGEN PURGING OF LINES

1 19-Dec-11

19-Dec-11

A2510

CUTTING OF THE TANKS SHELL AND ROOF

14 20-Dec-11

04-Jan-12

A2520

CUTTING/REMOVAL OF FOUNDATIONS OF TANKS

14 03-Jan-12

18-Jan-12

A2530

SHIFTING OF MATERIAL TO SCRAPYARD

15 22-Dec-11

08-Jan-12

A2540

REMOVAL OF EXTERNAL SCAFFOLDING

2 22-Dec-11

24-Dec-11

24-Dec-11

A2550

SITE CLEARANCE

1 25-Dec-11

25-Dec-11

25-Dec-11

Tank 80 FO2B

( New Bar )
Milestone

REVISED SCHEDULE

Mar

14-Dec-11

A2420

A2470

Feb

25-Dec-11

18-Dec-11
19-Dec-11
04-Jan-12
18-Jan-12
08-Jan-12

Date
05-Oct-11

Revision
1

Checked
FS

Approved
SZA

05-Oct-11 22:15

REMOVALOFREDUNDANTPIPELINE/
EQUIPMENT
Activity ID

Activity Name

Original Start
Duration

Finish
2011
Oct

Tank 90 F11A

24 26-Dec-11

26-Jan-12

2012

Nov

Dec

Jan

BLINDING/ISOLATION

1 26-Dec-11

26-Dec-11

A2570

NITROGEN PURGING OF LINES

1 27-Dec-11

27-Dec-11

A2580

CUTTING OF THE TANKS SHELL AND ROOF

14 28-Dec-11

12-Jan-12

A2590

CUTTING/REMOVAL OF FOUNDATIONS OF TANKS

14 11-Jan-12

26-Jan-12

A2600

SHIFTING OF MATERIAL TO SCRAPYARD

15 31-Dec-11

16-Jan-12

A2610

REMOVAL OF EXTERNAL SCAFFOLDING

2 31-Dec-11

01-Jan-12

01-Jan-12

A2620

SITE CLEARANCE

1 02-Jan-12

02-Jan-12

02-Jan-12

24 03-Jan-12

04-Feb-12

1 03-Jan-12

03-Jan-12

A2630

BLINDING/ISOLATION

A2640

NITROGEN PURGING OF LINES

1 04-Jan-12

04-Jan-12

A2650

CUTTING OF THE TANKS SHELL AND ROOF

14 05-Jan-12

21-Jan-12

A2660

CUTTING/REMOVAL OF FOUNDATIONS OF TANKS

14 19-Jan-12

04-Feb-12

27-Dec-11
12-Jan-12
26-Jan-12
16-Jan-12

03-Jan-12
04-Jan-12
21-Jan-12
04-Feb-12
24-Jan-12

A2670

SHIFTING OF MATERIAL TO SCRAPYARD

15 08-Jan-12

24-Jan-12

A2680

REMOVAL OF EXTERNAL SCAFFOLDING

2 08-Jan-12

09-Jan-12

09-Jan-12

A2690

SITE CLEARANCE

10-Jan-12

UTILITES - DISMANTLING OF EQUIPMENTS


A1920

DISMANTLING OF HEAT EXCHANGERS

1 10-Jan-12

10-Jan-12

49 27-Nov-11

02-Feb-12

20 27-Nov-11

19-Dec-11

A1930

DISMANTLING OF VESSELS

7 01-Dec-11

08-Dec-11

A1940

DISMANTLING OF VALVES

7 10-Dec-11

17-Dec-11

A1950

DISMANTLING OF PUMPS

13 18-Dec-11

01-Jan-12

A1960

DISMANTLING OF FILTERS

7 02-Jan-12

09-Jan-12

A1970

DISMANTLING OF TEMPERATURE CONTROLLERS

6 10-Jan-12

16-Jan-12

A1980

DISMANTLING OF STEAM TURBINES

10 17-Jan-12

28-Jan-12

A1990

DISMANTLING OF PANELS

4 19-Jan-12

23-Jan-12

A2000

DISMANTLING OF PUMP SKIDS

3 24-Jan-12

26-Jan-12

A2010

DISMANTLING OF BURNERS

3 28-Jan-12

30-Jan-12

A2030

CLEARANCE FROM SITE

3 31-Jan-12

02-Feb-12

( New Bar )
Milestone

REVISED SCHEDULE

Mar

26-Dec-11

A2560

Tank 90 F11B

Feb

19-Dec-11
08-Dec-11
17-Dec-11
01-Jan-12
09-Jan-12
16-Jan-12
28-Jan-12
23-Jan-12
26-Jan-12
30-Jan-12
02-Feb-12

Date
05-Oct-11

Revision
1

Checked
FS

Approved
SZA

05-Oct-11 22:15

REMOVALOFREDUNDANTPIPELINE/
EQUIPMENT
Activity ID

Activity Name

Original Start
Duration

Finish
2011
Oct

POST SHUTDOWN PHASE

10 05-Feb-12

18-Feb-12

A2040

SHIFTING/TRANSPORTATION OF MATERIAL AND EQUIPMENT

6 05-Feb-12

11-Feb-12

A2050

HOUSE KEEPING

2 05-Feb-12

06-Feb-12

A2060

DEMOBILIZATION OF MANPOWER

10 07-Feb-12

18-Feb-12

( New Bar )
Milestone

REVISED SCHEDULE

2012

Nov

Dec

Jan

Feb

Mar

11-Feb-12
06-Feb-12
18-Feb-12

Date
05-Oct-11

Revision
1

Checked
FS

Approved
SZA